Insert Name of Project – Post-Implementation Review
Questionnaire
Purpose of the Review
The Post Implementation Review (PIR) is a key component of the Project’s Finalisation
stage. This should take place within 4 to 6 weeks of the project’s end. However, it can be
held for the end of a Project Stage, or during a Project as a health-check.
Feedback on delivery of the project should be used to help future projects. Valuable
learning points should be recorded and shared within the organisation.

Group Principle/Rule - "Opportunities to learn by others' experience and best practice
should be sought"

About this Questionnaire
This questionnaire is designed to provoke thought regarding the delivery of the project. It
should be sent to key players involved in or affected by the project.
Please complete the questionnaire with your views on the project and return it to:
(Programme Office contact and address to be added)


Who are you?
Name
Project Role
Period of Involvement in
Project

Your views

What were the main causes of variance to cost and timescale performance?



How well did we achieve our critical success factors?



Which products were developed most smoothly?



Which products had the most issues during development?
Insert Company Logo


What were the top three things which went well and why?



What were the top three learning points you can take from the project?



What were the key points in the projects which seriously damaged or enhanced
the outcome?



What ideas for improvement do you have?




How do you feel about these statements?
Key: 5 strongly agree; 4 agree; 3 neutral; 2 disagree; 1 strongly disagree

Overall Project Performance                                     5      4     3   2   1
1   Everything delivered as intended / works as expected
2   It has solved the business pr
								