PowerPoint Presentation - University of California_ Berkeley by dandanhuanghuang

VIEWS: 13 PAGES: 39

									John F. Kennedy Space Center
                                                        LAUNCH SERVICES PROGRAM



                                    THEMIS
                  Mission Integration Working Group (MIWG) #7
                  Ground Operations Working Group (GOWG) #5
                    Delta - Ground Operations Review (GOR)




                                November 29, 2006
                                 KARS Park, KSC, Florida
              Hosts: Garrett Skrobot, NASA Mission Manager (MM)
              William Van Dyke, NASA Launch Site Integration Manager (LSIM)
                                               Agenda
                                           November 29, 2006
                          Meet-Me-Number: 1-877-991-5876 Passcode: 698067#
John F. Kennedy Space Center
                                                                     LAUNCH SERVICES PROGRAM

    MISSION INTEGRATION WORKING GROUP (MIWG) #7
    •     THEMIS Project Status                                                 P. Harvey/UCB
           –    Payload Schedule Update (Astrotech and Launch Site Schedules)
    •     Delta Program Status                                                  L. Loucks/Boeing
           –    LV Hardware Status
           –    Program Issues
    •     Mission Integration Status                                            L. Loucks/Boeing
           –    Integration Schedule
           –    Requirements Verification Matrix                                D. Tran/Boeing
           –    SCN Review
           –    Release of ICD Rev A
           –    Action Item Review
    •     Launch Site Integration Status
           –    Side by Side Testing/Ladder Mods/SSS Installation               V. Segall/Boeing
           –    Fueling & Procedure Status                                      C. Davis/NASA
           –    Range Status on Required Deliverables & Procedures              J. Wethern/45SW
                                           Agenda
                                       November 29, 2006
                          Meet-Me-Number: 1-877-991-5876 Passcode: 698067#
John F. Kennedy Space Center
                                                                   LAUNCH SERVICES PROGRAM


    MISSION INTEGRATION WORKING GROUP (MIWG) #7 - Continued
    •     Analysis Results                                                       L. Loucks/Boeing
          DTO Update
           –    Thermal
           –    RF Link Analysis
           –    Controls/ACS Gas Budget Update
    •     Mobile Telemetry Coverage                                              L. Loucks/Boeing
    •     Launch Management Update                                               KSC
    •     Mission Success Overview                                               KSC
    •     Review Spacecraft Mandatory / Required Launch Criteria                 KSC
                                                   Agenda
                                               November 29, 2006
                          Meet-Me-Number: 1-877-991-5876 Passcode: 698067#
John F. Kennedy Space Center
                                                                   LAUNCH SERVICES PROGRAM

 GROUND OPERATIONS WORKING GROUP (GOWG) #5/ Delta GOR
 •    Astrotech Readiness/Issues                                      G. Gleeson/ASO FL
 •    THEMIS Badging & Training Plan                                  K. Kerr/Analex KSC
 •    Launch Site Safety Status/Readiness                             C. Loftin/NASA Safety
 •    Telemetry and Communications Status/Readiness                   M. Lougheed/NASA KSC
 •    Spacecraft Procedure Status/Review                              R. Sterling/UCB
 •    Launch Site Readiness Poll (Go/No Go)
        –   THEMIS Project                                            P. Harvey
        –   NASA KSC Public Affairs                                   G. Diller
        –   Boeing Delta Mission Integration                          V. Segall
        –   Astrotech Mission Management                              G. Gleeson
        –   NASA LS Telemetry & Communicaitons                        M. Lougheed
        –   NASA KSC Safety                                           C. Loftin
        –   NASA MM                                                   G. Skrobot
        –   NASA LS Launch Site Integration                           W. Van Dyke
        –   NASA LS Launch Site Integration Branch                    F. Stone
John F. Kennedy Space Center
                                                               LAUNCH SERVICES PROGRAM




                                THEMIS PAYLOAD STATUS




                                        Peter R. Harvey
                                        Project Manager
                               University of California - Berkeley
                                   Payload Status
John F. Kennedy Space Center
                                                    LAUNCH SERVICES PROGRAM

      •    PCA Assembly and Test
                                   Payload Status
John F. Kennedy Space Center
                                                      LAUNCH SERVICES PROGRAM




                                          Acoustics
                    Vibration             & Shock            Spin Balance




                        Thermal Vacuum
                                              Storage
                                     FM2/FM3 Thermal Vacuum
                                                    ASO/PAD Schedule 1
John F. Kennedy Space Center
                                                                                                          LAUNCH SERVICES PROGRAM


                                ASO             ASO            ASO            ASO            ASO             ASO
                   DATE                                                                                                 PAD
                                (F1)            (F2)           (F3)           (F4)           (F5)        (PC and PCA)

                          Unpack Probe Unpack Probe Unpack Probe
                                                                 Unpack Probe Unpack Probe                PC Unpack
                            and EGSE     and EGSE     and EGSE
                                                                    (ASO1)       (ASO1)                    (ASO2)
                   11-Dec    (ASO1)       (ASO1)       (ASO1)

                            EGSE1 Setup, EGSE2 Setup, EGSE3 Setup,
                                                                           Install Bolt   Install Bolt
                             Install Bolt  Thermal      Thermal
                                                                             Cutters        Cutters
                               Cutters     Closeouts    Closeouts
                   12-Dec



                              Thermal        Install Bolt   Install Bolt    Thermal       Thermal
                             Closeouts         Cutters        Cutters       Closeouts     Closeouts


                   13-Dec



                                                                           RCS MEOP &
                            LPT, S/A Test
                                                                              LEAK

                   14-Dec



                            RCS MEOP &
                                       LPT, S/A Test                                                     PC-VCO TEST
                               LEAK

                   15-Dec

                                            RCS MEOP &
                                                       LPT, S/A Test
                                               LEAK
                   16-Dec
                                                    ASO/PAD Schedule 2
John F. Kennedy Space Center
                                                                                                          LAUNCH SERVICES PROGRAM




                               ASO           ASO            ASO             ASO             ASO             ASO
                  DATE                                                                                                 PAD
                               (F1)          (F2)           (F3)            (F4)            (F5)        (PC and PCA)



                                                         RCS MEOP &                                     INSTALL SEP
                                                                                        LPT, S/A Test
                                                            LEAK                                          HARNESS
                  18-Dec

                                                                                        RCS MEOP & INSTALL SMD
                                                                        LPT, S/A Test
                                                                                           LEAK       LINES
                  19-Dec

                              Probe          Probe          Probe          Probe           Probe
                           Transport to   Transport to   Transport to   Transport to    Transport to
                              ASO2           ASO2           ASO2           ASO2            ASO2
                  20-Dec
                           Weigh, Move Weigh, Move Weigh, Move Weigh, Move Weigh, Move
                            to Stands   to Stands   to Stands   to Stands   to Stands
                  21-Dec


                  22-Dec




                 Note: RCS MEOP & Leak are performed after hours
                                                ASO/PAD Schedule 3
John F. Kennedy Space Center
                                                                                                             LAUNCH SERVICES PROGRAM




                                 ASO             ASO             ASO             ASO             ASO             ASO
                   DATE                                                                                                     PAD
                                 (F1)            (F2)            (F3)            (F4)            (F5)        (PC and PCA)


                                                                                                               SLACK
                     1-Jan

                                                                                                               SLACK
                     2-Jan
                                Probe           Probe           Probe           Probe           Probe
                               Fueling         Fueling         Fueling         Fueling         Fueling
                     3-Jan
                                Probe           Probe           Probe           Probe           Probe
                               Fueling         Fueling         Fueling         Fueling         Fueling
                     4-Jan
                                Probe           Probe           Probe           Probe           Probe
                               Fueling         Fueling         Fueling         Fueling         Fueling
                     5-Jan
                     6-Jan
                     7-Jan

                              Probe RCS       Probe RCS       Probe RCS       Probe RCS       Probe RCS
                               Electrical      Electrical      Electrical      Electrical      Electrical
                             Verifications   Verifications   Verifications   Verifications   Verifications
                     8-Jan


                             Wet Weigh,      Wet Weigh,      Wet Weigh,      Wet Weigh,      Wet Weigh,
                             Probe to PC,    Probe to PC,    Probe to PC,    Probe to PC,    Probe to PC,     Bag PCA
                             Attach Pyro     Attach Pyro     Attach Pyro     Attach Pyro     Attach Pyro
                     9-Jan

                    10-Jan                                                                                    PCA FNL

                    11-Jan                                                                                    PCA FNL

                    12-Jan                                                                                     SLACK
                                       ASO/PAD Schedule 4
John F. Kennedy Space Center
                                                                   LAUNCH SERVICES PROGRAM




                               ASO    ASO    ASO    ASO    ASO        ASO
                   DATE                                                             PAD
                               (F1)   (F2)   (F3)   (F4)   (F5)   (PC and PCA)


                                                                  Spin Balance
                                                                   and Weigh
                   15-Jan

                                                                   PCA FNL
                   16-Jan

                                                                    SLACK
                   17-Jan
                                                                    SLACK
                   18-Jan
                                                                    SLACK
                   19-Jan
                   20-Jan                                           SLACK
                   21-Jan                                           SLACK

                                                                    SLACK
                   22-Jan

                                                                                 PCA EGSE TO
                                                                    SLACK
                                                                                   BLKHSE
                   23-Jan
                                                                                 PCA COMM
                                                                    SLACK
                   24-Jan                                                          CHECK
                                                                                 PCA COMM
                   25-Jan                                           SLACK
                                                                                   CHECK
                                                                  Mate to 3rd
                   26-Jan                                           Stage
                                      ASO/PAD Schedule 5
John F. Kennedy Space Center
                                                                  LAUNCH SERVICES PROGRAM




                               ASO    ASO    ASO    ASO    ASO        ASO
                    DATE                                                              PAD
                               (F1)   (F2)   (F3)   (F4)   (F5)   (PC and PCA)

                                                                       S/C
                    29-Jan                                         Clampband
                                                                  3rd Stage and
                    30-Jan                                         S/C Can Up
                                                                  Encapsulation
                    31-Jan
                                                                  Transport to
                     1-Feb                                            Pad
                                                                                    T-10 S/C
                                                                                  Functional &
                     2-Feb                                                          RF Test
                     3-Feb
                     4-Feb
                                                                                    T-9 S/C
                                                                                    Launch
                     5-Feb                                                         Rehearsal

                                                                                  T-8 Power On
                                                                                  Stray Voltage
                     6-Feb

                                                                                  T-7 Power Off
                                                                                  Stray Voltage
                     7-Feb
                                                                                  T-6 Remove
                                                                                  Bag, Fairing
                     8-Feb                                                        Installation

                                                                                   T-5 Fairing
                                                                                    Finaling
                     9-Feb
                                       ASO/PAD Schedule 6
John F. Kennedy Space Center
                                                                   LAUNCH SERVICES PROGRAM




                               ASO    ASO    ASO    ASO    ASO        ASO
                   DATE                                                              PAD
                               (F1)   (F2)   (F3)   (F4)   (F5)   (PC and PCA)


                                                                                 T-4 FRR, Prop
                                                                                   Load Prep
                   12-Feb
                                                                                  T-3 Second
                                                                                     Stage
                                                                                    Fueling,
                   13-Feb                                                          Ordnance
                                                                                  T-2 Launch
                                                                                  Readiness
                   14-Feb                                                           Review


                                                                                  T-1 Launch
                                                                                  Countdown
                                                                                     Start
                                                                                  **Launch **
                   15-Feb


                                                                                   Pack-UP

                   16-Feb
                   17-Feb
                   18-Feb
                   19-Feb                                                            SHIP
                                                       ASO/PAD Manpower
John F. Kennedy Space Center
                                                                                                        LAUNCH SERVICES PROGRAM


        Manpower
         27 Max while at ASO
         31 Max while at PAD

                 35

                 30

                 25

                 20

                 15

                 10

                  5

                  0
                                                        1/1/07


                                                                 1/8/07




                                                                                                          2/5/07
                                                                          1/15/07


                                                                                    1/22/07


                                                                                              1/29/07




                                                                                                                   2/12/07


                                                                                                                             2/19/07
                      12/11/06


                                 12/18/06


                                            12/25/06
                               Summary
John F. Kennedy Space Center
                                                 LAUNCH SERVICES PROGRAM



          Summary Status
           Probes and Probe Carrier are Flight Ready
           Plans and Procedures for ASO/PAD in Good Shape
           Shipment Contracted Two Trucks w/ Lead Car Ready


          Issues Potentially Impeding Launch Processing
           None
John F. Kennedy Space Center
                                                              LAUNCH SERVICES PROGRAM




                               Side by Side Testing / Ladder Mods /
                                          SSS Installations

                                     V. Segall / Boeing KSC
                                           Cape Status
John F. Kennedy Space Center
                                                                      LAUNCH SERVICES PROGRAM



  •    Access Ladder
         – Ladder modified, proof loaded, available for use
  •    Side-by-Side Testing
         – Procedure written and reviewed; ready for use
         – Date (15 Dec) coordinated
         – Logistics of delivery (14 Dec) discussed
                » Fork lift identified and available
                » Mission Integration will facilitate access for non-badged people
                » Actual delivery schedule discussion planned for post Astrotech THEMIS delivery
                                                   Cape Status
John F. Kennedy Space Center
                                                                                    LAUNCH SERVICES PROGRAM



  •    SSS Installation
         – Installation will be at Astrotech
                » Task is a payload support function; not a liability issue
                » Procedure (DCI) is written and in the review process
                » Date is under review: THEMIS requests the week of 18 Dec, but Boeing may not be
                  ready until after the 3rd of Jan. See schedule
                       •   Later date needs real time coordination in parallel with THEMIS fueling activities in the HPF
                       •   The SSS installation is planned for a separate bay so that mechanical operations will be de-
                           conflicted
                                                              THEMIS Upperstage Processing                                             Date 22 November 2006
             THE DELTA PROGRAM                                                   Le v e l 6 Sche dule                                  Rev: 27 now
                                                                 2006                                                                   2007
 John F. NOVEMBER
         Kennedy Space Center                                                    DECEMBER                                             JANUARY
20              27                         4                          11                18                  25             1
                                                                                                                   LAUNCH SERVICES PROGRAM8                            15
         LPD Pulls G200, G201, G202, G203
      Motor Dome Clean Check - (FACD) - (DCI: TBD)
         Equipment Transfer & Data Station Preps & Quals - (G200 T1)
         PAF Receiving & Mech Preps in Airlock - (G200 T1)
                        PAF Elec Equipment Installation - (G200 T2)
                            PAF Telemetry Preps - (G200 T3)
                                   Motor Offload & Leak Check/Transfer - (G202 T1)
                                   PAF Telemetry Test - (G200 T3)
                                                  Spintable Mechanical and Electrical Preps - (G201 T1)
                                                          Motor Bracket & Standoff Installation - (G203 T1)
                                                          PAF NCS Checks - (G200 T4)
                                                             PAF NCS N2H4 Load Preps - (G200 T5)
                                                             PAF NCS Test Securing - (G200 T4)
                                                                       Spacecraft Probe Carrier - Available
                                                                           PAF NCS N2H4 Load - (G200 T5)
                                                                             PAF/Spacecraft SBS Test Preps - (G200 T3) - (DCI: 1)
                                                                             NCS Vehicle N2H4 Load Securing - (G200 T5)
                                                                               PAF Mate Preps - (G203 T1)
                                                                                    Receive and Inspect SSS Ordnance
                                                                                  PAF Mate to Motor - (G203 T1)
                                                                                    PAF/Spacecraft SBS Test - (G200 T3) - (DCI: 1)
                                                                                             PAF/Spacecraft SBS Test Securing - (G200 T3) - (DCI: 1)
                                                                                                  Wire Harness Routing & Inst'l - (G203 T1)
                                                                                                    PAF/Motor Rec'v & Ord Inst'l - (G203 T2)
                                                                                           Spintable Ordnance Inst'l - (G207 T1)
                                                                                                        SSS Ordnance Installation
                                                                                                        TM Antenna Build - (G203 T1)
                                                                                                            Yo Weight Inst'l - (G203 T1)

 22-NOV-06   15:35    [Delta Schedules - Publish]/CII_THEMIS_US_now                                                                                    Page 1 of   2
                                                                 THEMIS Upperstage Processing                                        Date 22 November 2006
            THE DELTA PROGRAM                                                  Le v e l 6 Sche dule                                  Rev: 27 now
                                                2007
John F. Kennedy Space Center    JANUARY                                           FEBRUARY
                                                                    LAUNCH 3 4        6 7
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 SERVICES5PROGRAM 8                                                         9   10 11
  TM Antenna Inst'l - (G203 T2)
        NCS & ETA Blanket Inst'l - (G203 T2)
        Motor Buildup Securing - (G203 T1)
              Motor Weigh - (G203 T3)
              Spin Balance Preps/Adapter Balance - (G204 T1)
                    Transfer Motor to DPF & Align SBM - (G204 T2)
                                         Balance PAM - (G204 T2)
                                         Preps for Motor Mate - (G205 T1)
                                              Clampband Inst'l - (G205 T2)
                                              Motor Transfer to NPF/ Mate to Spintable - (G205 T1)
                                                    Clampband Finaling - (G205 T2)
                                                          Composite Electrical Preps - (G206 T1)
                                                          Third Stage Ignition S&A/Delivery/Installation - (G205 T2)
                                                                Composite Electrical Testing - (G206 T1)
                                                                             Composite Electrical Test Securing - (G206 T1)
                                                                                 Spintable Ordnance Finaling - (G207 T1)
                                                                                          Transport Canister Preps - (G209 T3)
                                                                                     Third Stage/Spacecraft Mate Preps - (G208 T2)
                                                                                          Spacecraft Weigh Preps (Astrotech) - (G208 T1)
                                                                                          Third Stage Close-out - (G207 T1)
                                                                                            Transfer Third Stage to Astrotech - (G208 T3)
                                                                                                  Spacecraft Weigh - (G208 T1)
                                    Spacecraft Mate/Clampband Inst'l/Tensioning - (G208 T2)
                                                               Spacecraft Clampband Finaling - (G208 T2)
                                                                    Spacecraft Finaling - (Spacecraft Ops)
                                                                           Engineering Walkdow n - (G209 T1)
                                            Third Stage & Spacecraft Can-up & Transport Preps - (G209 T1)
                                                              Third Stage & Spacecraft Transport to Pad - (G209 T1)

22-NOV-06   15:35        [Delta Schedules - Publish]/CII_THEMIS_US_now                                                                               Page 2 of   2
John F. Kennedy Space Center
                                                           LAUNCH SERVICES PROGRAM




                        KSC Fueling Team Status for THEMIS


                               Presented to: THEMIS Pre-Ship GOR

                                        By: Chuck Davis
                                   Fueling Team Lead, TA-E3

                                      November 29, 2006
                                           KSC
                               KSC Fueling Team Status
John F. Kennedy Space Center
                                                       LAUNCH SERVICES PROGRAM



  • Procedures:
         – THEMIS-specific deviations to OMI’s E5534 & E5502 are complete &
           under final review prior to obtaining signatures
         – OMI E5535 off-load procedure & pre-planned THEMIS-specific
           deviations will be available if required
  •    ICD “Appx. C” is complete
  •    MSPSP - Fueling GSE portion is complete
  •    All GSE will be in-calibration at the time of use
  •    Schedule:
         – Mobilize to Astrotech and set up GSE week of Dec 11
         – Connect to spacecraft ~ Jan 3
         – Prop load Jan 4
  • Prop Loading Team is GO for THEMIS shipment
John F. Kennedy Space Center
                                                       LAUNCH SERVICES PROGRAM




                               Range Status on Required
                                Deliverables & Procedures

                                   J. Wethern/45SW
                               Range & Deliverables Status
John F. Kennedy Space Center
                                                       LAUNCH SERVICES PROGRAM



  • MSPSP RELEASED & APPROVED
  • All required deliverables are up to date
  • PC handling procedure & Side by Side test are in review
         – All hazardous procedures in the NPF require Range Safety approval
John F. Kennedy Space Center
                                                       LAUNCH SERVICES PROGRAM




                               Astrotech Readiness / Issues

                                Gerard Gleeson / ASO FL
                                    Mission Specific Items
John F. Kennedy Space Center
                                                                                LAUNCH SERVICES PROGRAM




  • Item 1005 Phone installation in Control Room – to be performed after arrival, units available
  • Item 1030 Training and Badging - to be performed after arrival
  • Item 1101 SCAPE Suits – to be delivered as required prior to loading operations
  • Item 1180 Training for Cranes and Forklifts - to be performed after arrival
  • Item 4000 LAN configuration – to be completed on arrival – infrastructure is ready
  • Item 4110 IONet configuration – to be completed on arrival – infrastructure is ready
  • Item 4500 Voice Stations - to be installed after arrival, units available

  • Documentation
  • UCB Procedures received and reviewed, Comments sent to UCB
  • No major issues associated with Themis processing at Astrotech

  • Deliverables
  • All deliverables on site and ready for use, certificates presented in Data package as required


                               Astrotech is ready to receive THEMIS
                                                                                                             ASO Occupancy
John F. Kennedy Space Center
                                                                                                                                                                                                                             LAUNCH SERVICES PROGRAM


                                                                                                                        2006 Projected Occupancy Plan

      Revision date: 11-20-06                                  ASO                                        Atlas                                Delta                                                                                                                                                                            ASO

                    Month                      January             February          M arch                 April                   M ay               June                     July                 August           Sept ember             Oct ober            November          December        January                February
           Start of Week Monday        2   9     16    23 30   6    13   20 27   6     13   20   27   3     10    17   24   1   8    15    22 29   5   12     19 26   3    10   17     24   31   7   14   21 28   4     11   18    25   2   9   16   23 30   6    13   20 27   4    11   18   25   1   8    15   22   5    12   19

                 Main Conf. Room
                                                                                                                                                                                                                                            ST P - AV5 4 BC/DL
                        A High Bay
                                                                                                                                                                                                                                              CONT INGENCY
                   A Control Room
                                                                                 Astra-AV4
                            A Office
                        B High Bay                                                                                                                                                                                                          ST P - AV5 4 BC/DL
                   B Control Room
                            B Office
                        C High Bay
                   C Control Room                                                                                                                                                                                                                                                  T hemis - D2 GG/RF
      P                    C Office
      P
      F                                                                                                                                                                     Stereo
                        D High Bay
                                                      ASO Laminar Flow

                   D Control Room                                             GOES- N

                           D Office
          D Conf Room Downstairs                         GOES- N                                                                                                            Stereo - D2
                                                                                                                                                                            GG/DL - VS
                   E Control Room

                            E Office                                     GOES- N (Opt 1)

            E Conf Room Upstairs                         ASO Mod
                    F Office Quad 1                                      Astra-AV4
                    F Office Quad 2
                                                                                                                                                                                 Stereo
                    F Office Quad 3
                    F Office Quad 4


                       S Encap Bay

                        S High Bay                                                                                 D2 & Stereo
      H
      P                   Spin Bay                                                                           D2                            S                                                                                                                                             D2-T          Th
      F
                        N High Bay                                                                                                                                                                                                                                                            T hemis & D2
                                                                                                                                                                          D2 & Stereo
                      N Encap Bay
John F. Kennedy Space Center
                                                     LAUNCH SERVICES PROGRAM




                               THEMIS Badging & Training

                                Kathy Kerr / Analex KSC
                                KSC Badging & Training Status
John F. Kennedy Space Center
                                                                      LAUNCH SERVICES PROGRAM

        •    SLC-17 Badging & Training
               – 41 THEMIS personnel identified for unescorted access to SLC-17
                      » 36 have good NAC/PRP; 5 are In Process
               – 5 THEMIS personnel identified for SCAPE operations.
                      » 4 have completed SCAPE training; 1 person remaining

        •    Open items:
               – Required training: ELSA, CCAFS Safety and SLC-17 walk downs to be
                 scheduled post spacecraft arrival.
               – Schedule SCAPE training for one remaining person
               – AF Form 2856s have been completed and submitted to me. They will be
                 submitted to Pass & ID about 1 month prior to required pad access.
               – Air Force Badging once prerequisites have been completed.


        • Launch Site Planning Readiness Statement:
               – Plans are in place to complete remaining open items.
               – KSC Badging & Training is ready for THEMIS flight hardware arrival.
John F. Kennedy Space Center
                                       LAUNCH SERVICES PROGRAM




           NASA / KSC Safety Readiness for THEMIS




                                                       Chuck Loftin
                                            System Safety Engineer
                                    KSC Safety & Mission Assurance
                                          Launch Services Division
                                                 29 November 2006
                               Safety Documentation Status
John F. Kennedy Space Center
                                                    LAUNCH SERVICES PROGRAM




       • MSPSP
         - Final MSPSP approved 2 Nov 06

       • S/C Processing
         - Ground Processing Approval letter provided prior to
         THEMIS Delta GOR

       • Procedures
         - Integrated and Contingency Procedures under
         review
                               Readiness Statement
John F. Kennedy Space Center
                                                       LAUNCH SERVICES PROGRAM




          • NASA/KSC Safety and Mission Assurance,
            Launch Services Division has assessed the
            readiness of the THEMIS spacecraft for NASA at
            Astrotech, and has no constraints to the arrival of
            the Spacecraft.

                 - Any open items or issues are being tracked via the
                   Verification Tracking Log (VTL).
John F. Kennedy Space Center
                                                    LAUNCH SERVICES PROGRAM




         Telemetry and Communications Status / Readiness

                               Marty Lougheed / NASA KSC
                                    TELEMETRY &
                               COMMUNICATIONS READINESS
John F. Kennedy Space Center
                                                 LAUNCH SERVICES PROGRAM




             NASA Communications has had no change in our
             position since the THEMIS GOR ……………

             we are "GO" for the THEMIS 11 Dec arrival.
John F. Kennedy Space Center
                                                   LAUNCH SERVICES PROGRAM




            Status of Launch Site Procedures
                                   Rick Sterling
                               Themis I & T Manager
                                                                            Launch Site Procedures
John F. Kennedy Space Center
                                                                                            LAUNCH SERVICES PROGRAM



           Following charts show status, where used and whether hazardous.
                                  THEMIS I&T: LAUNCH SITE PLANS AND PROCEDURES
             PLANS                                                                       Status       ASO   PAD   HAZ
             thm-sys-002         THEMIS   Magnetics Contamination Control Plan           Complete     YES   YES
             thm-sys-046         THEMIS   Probe Shipping Plan                            Complete     YES   YES
             thm-sys-047         THEMIS   Launch Site Test Plan                          Complete     YES   YES
             thm-sys-052         THEMIS   Launch Site Contamination Control Plan         Complete     YES   YES
             PROCEDURES
             thm-mint-proc-010   THEMIS Probe Power On/Off Procedure                      Complete    YES   YES
             thm-mint-proc-011   THEMIS Probe Umbilical Safe-to-Mate                      Complete    YES   YES
             thm-mint-proc-013   THEMIS Probe LPT Procedure                               Complete    YES   YES   HAZ
             thm-mint-proc-014   THEMIS Probe AT Procedure                                Complete    YES   YES
             thm-mint-proc-015   THEMIS Probe Handling Procedure                          Complete    YES         HAZ
             thm-mint-proc-019   THEMIS Probe Solar Array Illumination Procedure          Complete    YES         HAZ
             thm-mint-proc-032   THEMIS Instrument LPT Procedure                          Complete    YES
             thm-mint-proc-034   THEMIS Instrument AT Procedure                           Complete    YES
             thm-mint-proc-051   \THEMIS Probe Fueling Procedure (KSC Proc)               Complete    YES
             thm-mint-proc-053   THEMIS Probe Pre-Launch Closeout Procedure               Complete    YES
             thm-mint-proc-054   THEMIS Probe Battery Ops Procedure                       Complete    YES   YES
             thm-mint-proc-055   THEMIS Probe RCS Pressure Test and Leak Check            Complete    YES         HAZ
             thm-mint-proc-062   THEMIS PCA LV Mate Procedure                             Complete    YES         HAZ
             thm-mint-proc-063   THEMIS PCA Electrical Test Procedure                     Complete    YES
             thm-mint-proc-065                                                            Complete
                                 THEMIS PCA Launch Tower Electrical Test Procedure (at Block House)   YES   YES
                                                                                   Launch Site Procedures
John F. Kennedy Space Center
                                                                                                      LAUNCH SERVICES PROGRAM

    To download procedures or see more detailed listing including author, revision number, etc:
    ftp://apollo.ssl.berkeley.edu/pub/THEMIS/2 Space Segment/2.2 Spacecraft/2.2.7 Launch Site Processing/2.2.7.1 Launch Vehicle Integration



              thm-mint-proc-066     THEMIS   PCA Pre Launch Closeout Proc                     Complete     YES     YES
              thm-mint-proc-067     THEMIS   PCA Spin Balance Procedure                       Complete     YES           HAZ
              thm-mint-proc-068     THEMIS   PCA Lifting and Handling Procedure               Complete     YES           HAZ
              thm-mint-proc-069     THEMIS   PCA Assembly Procedure                           Complete     YES           HAZ
              thm-mint-proc-070     THEMIS   PCA Separation System Test Procedure             Complete     YES           HAZ
              thm-mint-proc-071     THEMIS   PCA Purge Bag Installation and Removal           Complete     YES     YES
              thm-mint-proc-073     THEMIS   PCA EGSE Safe-to-Mate                            Complete     YES
              thm-mint-proc-077     THEMIS                                                    In Progress
                                             Probe Simulator to Blockhouse EGSE Verification Check-Out Procedure   YES
              thm-mint-proc-076     THEMIS   PCA to USPP Safe-to-Mate                         In Progress YES
              thm-mint-proc-077     THEMIS   PCA Launch Countdown                             Complete     YES     YES
              thm-mint-proc-086     THEMIS   RF Chirp Test                                    In Progress YES      YES   HAZ
              thm-mint-proc-105     THEMIS   Simulated Pyro Test Procedure                    Complete     YES
              thm-mint-proc-106     THEMIS   Battery Trending Test Procedure                  Complete     YES
              thm-mint-proc-107     THEMIS   PPMU Safe-to-Mate Procedure                      Complete     YES
              thm-mint-proc-120     THEMIS   Facility and MGSE Magnetic Test Procedures       Complete     YES     YES
              thm-mint-proc-122     THEMIS   ESA/SST Purge Hookup Procedure                   Complete     YES           HAZ
              thm-mint-proc-125     THEMIS   Probe ESC Closeout Procedure                     Complete     YES
              thm-mint-proc-126     THEMIS   Magnetic Screening and Degaussing Procedure      Complete     YES     YES
              thm-mint-proc-128     THEMIS   Handling of Pyrotechnic Devices                  Complete     YES           HAZ
              thm-mint-proc-132     THEMIS   EGSE RACKS Moving Procedure                      Complete     YES     YES   HAZ
              thm-mint-proc-141     THEMIS   Separation System Stow Procedure                 Complete     YES           HAZ
              thm-sai-proc1668      THEMIS   Side by Side Test                                Complete     YES
John F. Kennedy Space Center
                                                       LAUNCH SERVICES PROGRAM




                                Launch Site Readiness Poll


                               William Van Dyke / NASA KSC
John F. Kennedy Space Center
                                                        LAUNCH SERVICES PROGRAM




      • Launch Site Readiness Poll (Go/No Go)
             – THEMIS Project                           Peter Harvey
             – NASA KSC Public Affairs                  George Diller
             – Boeing Delta Mission Integration         Vic Segall
             – Astrotech Mission Management             Gerard Gleeson
             – NASA LS Telemetry & Communicaitons       Marty Lougheed
             – NASA KSC Safety                          Chuck Loftin
             – NASA MM                                  Garrett Skrobot
             – NASA LS Launch Site Integration          William Van Dyke
             – NASA LS Launch Site Integration Branch   Frank Stone

								