SANTA MARIA RIVER LEVEE by yaohongm

VIEWS: 4 PAGES: 46

									            GAP FIRE

EMERGENCY ACTION PLAN




        Jointly developed by

        Santa Barbara County

                 and

the Cities of Santa Barbara and Goleta


            August 2008




                  1
                                  Table of Contents

Background                                                                 3
1. Interagency Communication                                               5
2. Advanced Measures                                                       5
3. Monitoring and Maintenance                                              6
4. Public Information                                                      7
5. Emergency Response                                                      8
6. Signatures                                                              9
Appendix A: Established Emergency Contract Information                    10
Appendix B: Watershed Planning and Response Group Monthly                 13
Meeting Minutes
Appendix C: Agency Contact List – Restricted Use            Separate document




                                          2
                                          Background

Santa Barbara County, the City of Santa Barbara, and the City of Goleta have prepared this
Emergency Action Plan (EAP) in preparation for a possible flood emergency following the 2008
Gap fire. The purpose of the EAP is to safeguard lives and minimize property damage in the
event of flooding or debris flows generated by post-fire runoff from winter storms.

In July 2008, the Gap wildfire broke out on the south coast of Santa Barbara County and burned
a total of 9,544 acres before it was contained on July 28, 2008. The fire began on July 1, 2008,
in the Los Padres National Forest in the vicinity of Lizard’s Mouth on West Camino Cielo Road,
approximately 4 miles west of Highway 154 and 3.5 miles north of the city of Goleta. The
burned area encompasses portions of the San Jose Creek, Las Vegas/San Pedro Creek, Carneros
Creek, Tecolotito Creek, Ellwood/Winchester Creek, Tecolote Creek, and Eagle Canyon Creek
watersheds. This area was last burned in the 1955 Refugio fire. Table 1 provides a summary of
the affected South Coast watersheds.

The burned terrain is steep and mountainous with thin soils. The predominant vegetation type is
mature chaparral.

Post-wildfire changes in basin hydrology typically include a shift toward greater runoff volumes
and higher magnitude peak runoff rates during subsequent rainstorms. One cause is the removal
of vegetation that normally provides interception, attenuation, and evapotranspiration. Another
cause is the formation of soil hydrophobicity. Hydrophobic layers form in soil during intense
fires that vaporize a waxy substance found in plant material. The vapors penetrate the soil and
cool, causing the waxy substance to solidify and cling to soil particles forming a water repellent
layer. Increased soil erosion and the occurrence of mass movements including debris flows are
also concerns in watersheds where fire has destroyed vegetation.

The EAP addresses flood and sedimentation concerns in urbanized South Coast watersheds.
Primary concerns are flooding at the Santa Barbara Airport and in Goleta north of Calle Real
along Las Vegas and San Pedro Creeks, sedimentation in channels downstream of the burn area,
and plugging of culverts and bridges with debris.




                                                3
              Table 1. Summary of Affected Urbanized South Coast Watersheds
Watershed     Area      % Burned       Development              Hazard Notes
             (acres)                       Status
 San Jose     1,080        20       Urban downstream       Potential for debris and
                                    of Cathedral Oaks     sediment accumulation in
                                            Road         channel and sediment basin
San Pedro/    1,787        39       Urban downstream       Potential for debris and
Las Vegas                           of Cathedral Oaks     sediment accumulation in
                                            Road        channel and sediment basin;
                                                        high potential for plugging at
                                                           Calle Real and flooding
                                                                   upstream
 Carneros     1,508        59       Rural in upstream      Potential for debris and
                                        areas; urban      sediment accumulation in
                                      downstream of     channel and sediment basin;
                                         Calle Real     high potential for plugging at
                                                         Caltrans culvert under Hwy
                                                                      101
Tecolotito    1,892        49       Rural in upstream      Potential for debris and
                                     areas; developed     sediment accumulation in
                                      downstream of        channel sediment basin;
                                         Hwy 101        potential for plugging at City
                                                       of Goleta bridges and Caltrans
                                                            culvert under Hwy 101
Ellwood/      2,103        54          Subdivision at         Potential for debris
Winchester                             confluence of       accumulation in channel
                                     Ellwood Canyon
                                      and Winchester
                                      Canyon Creeks
 Tecolote      984         27             Large lot           Potential for debris
                                        subdivision        accumulation in channel
                                     upstream of Hwy
                                            101




                                              4
                                        Agency Responsibilities


1. Intra- and Interagency Communication

Santa Barbara County will:

      Facilitate communication with the agencies involved in planning and carrying out emergency
       response for the affected area (see Table 2). Contact for each agency is listed in Appendix C.
      Hold weekly coordination meetings beginning on August 11, 2008. The minutes from these meetings
       will be attached within Appendix B of this document as they become available.
      Participate in planning efforts by the USFS and NRCS and request technical assistance as necessary.
      Meet and communicate with the NWS and the USGS concerning debris flow forecasts and
       instrumentation for recording rainfall and streamflow during the 2008-09 winter season.

                    Table 2. Agencies Involved in South Coast Emergency Response
                                              Agency Name
         Santa Barbara County - Disaster Recovery (Public Works Department)
         Santa Barbara County - Office of Emergency Services (Executive Office)
         Santa Barbara County - Executive Office
         Santa Barbara County - Flood Control (Public Works Department)
         Santa Barbara County - Transportation Division (Public Works Department)
         City of Goleta
         City of Santa Barbara
         California Department of Transportation (Caltrans)
         Union Pacific Railroad (UPRR)
         National Weather Service (NWS)
         Natural Resources Conservation Service (NRCS)
         U.S.D.A. Forest Service (USFS)

The City of Santa Barbara will:

      Attend weekly coordination meetings.

The City of Goleta will:

      Attend weekly coordination meetings.


2. Advanced Measures

Planned pre-winter preparations are described in the Gap Fire Emergency Watershed Response Plan drafted
by the Santa Barbara County Public Works Department in August 2008.

Santa Barbara County will:

      Work to secure funding from federal (NRCS) and state (OES) sources for implementing flood
       protection measures and serve as the local sponsor for such funding.



                                                    5
      Enter into an agreement with the two Cities once federal and/or state funding is awarded to provide
       the County’s one-third of the cost of the local share of aerial hydromulching as described in the Gap
       Fire Emergency Watershed Response Plan.
      Secure emergency environmental permits for implementing flood protection measures as needed.
      Implement advanced flood protection measures within County jurisdiction and at County facilities.
       Examples of measures include treatments at County bridges, debris racks, channel clearing and
       desilting of existing sediment basins.
      Assist private landowners as described in the Gap Fire Emergency Watershed Response Plan.
      Provide 50% of the sand bags at the joint City of Goleta/County emergency sand bag station at Fire
       Station 14. Bags will be replenished as necessary throughout the winter.
      Provide sand to the joint City of Goleta/County emergency sand bag station at Fire Station 14. Sand
       will be provided throughout the winter.
      Provide emergency temporary treatment of the Goleta Beach Bridge to allow truck loading for beach
       disposal of excavated sediment.

The City of Santa Barbara will:

      Enter into an agreement with the County once federal and/or state funding is awarded to reimburse
       the County for one-third of the cost of the local share of aerial hydromulching as described in the Gap
       Fire Emergency Watershed Response Plan.
      Implement advanced flood protection measures within City limits and at City facilities (airport, City
       streets, City bridges) as deemed necessary by the City.
      Assist County forces and contractors with access and security for excavation on defined sediment
       basins on airport property.

The City of Goleta will:

      Enter into an agreement with the County once federal and/or state funding is awarded to reimburse
       the County for one-third of the cost of the local share of aerial hydromulching as described in the Gap
       Fire Emergency Watershed Response Plan.
      Implement advanced flood protection measures within City limits and at City facilities (City streets,
       City bridges) as deemed necessary by the City.
      Provide 50% of the sand bags at the joint City of Goleta/County emergency sand bag station at Fire
       Station 14. Bags will be replenished as necessary throughout the winter.


3. Monitoring and Maintenance

Santa Barbara County will:

      Monitor gauged rainfall using its ALERT system, a network of real-time meteorological monitoring
       equipment. Parameters measured and reported by the network include rainfall, stream flow, wind
       speed and direction, temperature, barometric pressure, and humidity. The data from these sensors are
       sent via radio telemetry through a series of repeaters to the Division’s downtown office and the NWS
       in Oxnard. The nearest NWS rainfall forecast location is San Marcos Pass.
      Consider installing one or two temporary rain gauges or other instrumentation in the burn area or
       downstream. The NWS and the USGS have suggested that they may install instrumentation to
       monitor post-fire runoff and debris flow activity. In this case, the County may choose to utilize the
       NWS/USGS gauges.

                                                      6
      Conduct evaluations and participate in efforts by other agencies to evaluate short- and long-term
       impacts in and downstream of burned watersheds. Potential impacts may include flooding, soil
       erosion including debris flows and landslides, impacts to infrastructure and flood control facilities,
       changes to vegetation structure, delivery of organic debris to downstream areas, and changes to USFS
       planned maintenance activities.
      Monitor and maintain County facilities throughout the winter as described in the Gap Fire Emergency
       Watershed Response Plan including defined sediment basins on Tecolotito (airport), Carneros
       (airport), San Pedro, and San Jose Creeks.
      Make available 24-hour staff for coordination and communication.

The City of Santa Barbara will:

      Monitor and maintain City facilities throughout the winter as described in the Gap Fire Emergency
       Watershed Response Plan, including maintenance of all City bridges and removal of accumulated
       debris to maintain flow capacity.
      Maintain all drainage features on airport property, including creek systems downstream of the
       designated sediment basins.
      Provide any necessary support (security, oversight, etc.) for County to access sediment basins on
       airport property for emergency excavation and trucking of excavated sediment, including 24-hour
       support if necessary.
      Maintain all City bridges including removal of accumulated debris to maintain flow capacity.
      Make available 24-hour staff for coordination and communication.

The City of Goleta will:

      Monitor and maintain City facilities throughout the winter as described in the Gap Fire Emergency
       Watershed Response Plan, including maintenance of all City bridges and removal of accumulated
       debris to maintain flow capacity.
      Make available 24-hour staff for coordination and communication.


4. Public Information

Santa Barbara County will:

      Assist the City of Goleta in disseminating public information as described in the Gap Fire Emergency
       Watershed Response Plan.
      Make staff available to communicate the increased risk that exists below the fire area.

The City of Goleta will:

      Establish a public information program to communicate the increased risk that exists below the fire
       area.
      Include in the public information program the discussion of other important issues such as flood
       insurance. A list of issues can be found in the Gap Fire Emergency Watershed Response Plan.




                                                     7
5. Emergency Response

Santa Barbara County will:

      Conduct emergency debris clearing, desilting and other measures as necessary and as described in the
       Gap Fire Emergency Watershed Response Plan.
      Alert the County Office of Emergency Services (OES) and the Cities of Goleta and Santa Barbara to
       adverse flooding and sedimentation conditions. Decisions concerning emergency evacuations will be
       the responsibility of the County OES and the Cities.
      Assist the County in declaring the winter of 2008-09 an emergency if deemed appropriate by the
       County Executive Office. Efforts will also be coordinated through the Public Works Disaster
       Recovery Manager and County OES.
      Make available 24-hour staff for coordination and communication.

The City of Santa Barbara will:

      Plan and initiate emergency response for the Santa Barbara Airport.
      Coordinate emergency evacuations with County OES.
      Make available 24-hour staff for coordination and communication.

The City of Goleta will:

      Conduct emergency debris clearing and other measures within the City limits as necessary.
      Plan and initiate emergency response for areas within the City of Goleta, particularly the residential
       areas upstream of Calle Real along Las Vegas and San Pedro Creeks.
      Coordinate emergency evacuations with County OES.
      Make available 24-hour staff for coordination and communication.




                                                      8
6. Signatures

The following representatives of Santa Barbara County, the City of Santa Barbara, and the City of Goleta
were involved in the development of this EAP, approve of its contents and agree to the responsibilities
outlined herein.




_____________________________________________________________________________________
Scott McGolpin, Public Works Director, Santa Barbara County             Date



_____________________________________________________________________________________
Christine Anderson, Public Works Director, City of Santa Barbara        Date



_____________________________________________________________________________________
Steven Wagner, Community Services Director, City of Goleta              Date




                                                     9
                                                         APPENDIX A

                                ESTABLISHED EMERGENCY CONTRACT INFORMATION

      Vendor             Contract No.         Type of Service                Contact             Main           Cell
                                                                                               Number
   AJ Sanders             BL0032            Rock, gravel, rip rap                            805-482-1237
 Aceco Equipment          BL00048          Tools, equipment rental        John Lizarraga     805-733-5595   805-588-2041
                                                                          Eric Landthaler    805-736-5615   805-588-2049
       Bales             IN PROCESS               Trucking                                   805-967-4885
Baron Bag & Supply         BL01562                Sandbags                 Larry Deman       800-562-6055
                                        General contracting/equipment
   Bob’s Backhoe          CN06516             rental w/operator             Toni Hearn       805-967-5849
   Buellflat Rock         CN06517            Aggregate sandfill           Mike Nedegaard     805-688-7169   805-315-6259
    Central Coast
      Transfer             BC07176             Truck and crane           Mike Cunningham     805-202-1324
   Cetti Services          BL00266       Welding, mechanical repair       Leonard Cetti      805-686-9985
     Charlenes           IN PROCESS               Trucking                                   805-683-0991
                                        General contracting/equipment
Coastline Equipment       BL00292             rental w/operator            Ted Paxton        805-922-8329   805-896-4916
     Comsweep             CN03811            Vacuum sweeping              Debbie Wright      805-736-4957
Continental Janitorial    DP00563            Sweeping services            Rudy Castillo      805-687-0884
                                        General contracting/equipment
Cushman Contracting       DP01060             rental w/operator           Shane Alexander    805-964-8661
                                          Heavy equipment parts &
   Dal Pozzo Tire         BL00343                   repair                Randal Vasquez     805-967-3917
                                        General contracting/equipment
  Ecco Equipment           BL00374            rental w/operator           Dennis Unholz      800-729-3226
                             IN         General contracting/equipment
   Elevation Eng          PROCESS             rental w/operator                              805-922-4366
   Giffin Rental           BL00463         Tools, equipment rental         John Santrizos    805-967-6484   805-451-4562
                                                                            Tom Giffin       805-967-6484
                                        General contracting/equipment
Granite Construction      BL00479             rental w/operator         SB - Bruce McGowan   805-964-9951   805-331-8196
                                                                         SM – Doug Barnes    805-614-0196   805-331-5010
Hanson Aggregates         BL00479        Highway materials, supplies      James Norwood      858-715-5653
                                                                10
  Hertz Equipment                   Construction heavy equipment
       Rental           BL00521                 rental                   Mike Sheldon        805-297-5685
  La Cumbre Feed        BL02297              Straw bales                 Maggie Robles       805-687-1880
                                    General contracting/equipment
 Lash Construction      CN06521           rental w/operator                 Jim Lash         805-963-3553   805-896-8886
     Marborg            BL01752             Roll off rental             Theresa Borgatello   805-963-1852
                                    General contracting/equipment
Mid Co Construction                       rental w/operator               Greg Hansen        805-688-9501   805-896-4644
   Milpas Rental        BL00706        Tools, equipment rental            Bob Schoppe        805-679-3488
Mission Ready Mix       BL00709          Cement/transit mix                Mike Hunt         805-896-7116
 Newton Building
     Supplies           BL00753          Building materials              David Stanwood      805-967-4549   805-705-3228
    OST Crane           BC07173             Truck & crane               L Dennis Zermeno     805-633-9963   805-643-9963
                                    General contracting/equipment
       Papich           DP01062           rental w/operator               Jason Papich       805-473-3016   805-431-8952
 Patt Scott Masonry     CN04850      Building construction repair            Cassie          805-683-9194
Peterson’s Tree Care    DP00056             Tree removal                                     805-969-3352
                                      Construction earth moving
    Quinn Co            BL00875               equipment                    Dan Walker        805-925-8611   805-441-6564
   Quinn Rental         BL00876      Equipment rental w/operator           Jerry Robles      805-922-3529   805-310-3280
                                    General contracting/equipment
     R Burke            DP01068           rental w/operator                Rob Burke         805-543-3209
                                                                         Randy Anderson      805-788-0730
   Rain for Rent         BL01673    Parts/supplies to repair projects     Bruce Wyant        805-525-3306
        RLF            IN PROCESS              Trucking                                      805-688-1492
     Rockwood                       General contracting/equipment
    Construction                           rental w/operator             Tom Chambers        805-343-7738
     RW Scott                       General contracting/equipment
    Construction        CN04851            rental w/operator              Mike Scott         805-925-5540
  Santa Maria Tire      BL00950      Heavy equipment parts/repair        Craig Stephens      805-928-2501   805-310-7570
  Santa Ynez Feed       BL01520               Straw bales               Quinn Spaulding      805-688-6404   805-448-4507
  Schwan Brothers                   General contracting/equipment
     Excavating                            rental w/operator               Jim Schwan        805-683-5116   805-331-9558
Shaw Excavating and                 General contracting/equipment
      Grading          IN PROCESS          rental w/operator                Jeff Shaw                       805-331-4729
Southwestern Bag Co      BL01025               Sandbags                                      213-622-6108
                                                               11
  Specialty Crane       BC07171             Truck & crane             Seth Hammond – Owner   805-967-7700   805-886-2000
                                                                           Mike Dawson       805-649-3078   805-680-9600
                                                                         Brett Parish - SM   805-344-1054   805-886-2002
     Specialty                      General contracting/equipment
   Construction        IN PROCESS         rental w/operator                                  805-543-1706
  Speeds Trucking        BC07175            Truck & crane                  Don Gheno         805-925-1369   805-680-6367
                                                                          Frank Nunez                       805-680-1611
Steve’s Wheel & Tire    BL01046        Heavy equipment repair                                805-688-6565
 Stewart’s Plumbing
     De-Rooting         CN06524     Video drain inspection services       Skip Stewart       805-965-8813
   Sunbelt Rentals      CL00764      Equipment rental w/operator          Paul Marshall      800-600-3446   805-331-0100
   T&T Trucking         BC07174               Trucking                       On call         805-648-3048
T&T Crane Services      BC07172            Crane Services                    On call         805-648-3348
                                    General contracting/equipment
 Tierra Construction    CN04853           rental w/operator              Randy Douglas       805-967-7045   805-331-4411
                                                                         Arlie Williford     805-968-9834   805-331-4413
                                                                         Blair Douglas                      805-331-3486
                                        Highway materials and
   Union Asphalt        CN06525               supplies                     Bill Marsalek     805-929-1234   805-896-9390
                                                                         Randy Hermreck      805-680-0607   805-896-9370
  United Rentals        CN06527      Equipment rental w/operator              On call        805-647-9716   805-966-6653
V&J Rock/Trucking       BL01144            Rock transport                Linda McCaffrey     805-736-1910
                                                                          Steve Johnson      805-736-7495
    Valley Rock         BL01152           Cement/transit mix               Rick Kaylor       805-431-2915
                                                                           Tom Cooper        805-315-6923
Valley Tool Rentals     BL001154       Tools, equipment rental             Steve Sawin       805-688-7213   805-350-0486
                                                                                                            805-686-3582
                                    General contracting/equipment
      Whitaker                            rental w/operator               Matt Bousman       805-226-4020   805-440-3619




                                                               12
                  APPENDIX B

GAP FIRE WATERSHED PLANNING AND RESPONSE GROUP

               MEETING MINUTES




                      13
                     GAP FIRE Watershed Planning Response Group
                         Monday, August 11, 2008 @ 10:00 a.m.
                                     MINUTES
                                     (revised 8.15.08)


     I. Roll Call:

Attendees:

Tom Fayram, Deputy Public Works Director, County of Santa Barbara
Dace Morgan, County of Santa Barbara, Transportation Division
Jon Frye, Santa Barbara County Flood Control District
Matt Naftaly, Santa Barbara County Water Agency
Matt Griffin, Santa Barbara County Flood Control
Rochelle Camozzi, County of Santa Barbara, Public Works Department
John McGray, County of Santa Barbara, Transportation Division
Chris Sneddon, County of Santa Barbara, Transportation Division
Steve Wagner, City of Goleta
Larry Fausett, Santa Barbara County Flood Control
Candice Constantine, Santa Barbara County Flood Control
Ryder Bailey, County of Santa Barbara, Auditor-Controller’s Office
Pete Endsley, Santa Barbara County Flood Control
Joe Guzzardi, County of Santa Barbara, OES
Michael Harris, County of Santa Barbara, OES
Dana Zertuche, Santa Barbara County Flood Control
Maureen Spencer, Santa Barbara County Flood Control


Conference Call:

Dave Rickard, County of Santa Barbara, Public Works Department
Dave Lewis, County of Santa Barbara, Transportation Division
Matthew Pawlak, John Bechtold, and Dan Little, NRCS
Charles Rabamad, State OES
Karen Ramsdell and Andrew Bermond, City of Santa Barbara Airport
Chang Lee, DWR
Jim Calacal, FEMA




                                             14
     II. Opening Remarks (Tom Fayram):
         The Board of Supervisors is scheduled at their August 19th hearing to:
              o Approve the Gap Fire Watershed Response Plan,
              o Proclaim a local emergency to respond to Gap Fire, and
              o Set a hearing on the September 2nd to receive an update on the status of the
                 projects and work identified in the Gap Fire Watershed Response Plan
         The Gap Fire EAP will be distributed shortly.
         Fire Station 14 will have sand and bags available to the public (joint effort from the City
          of Goleta and County)


    III. Reports/Updates:


Agency            Person Reporting      Report/Update:


Flood Control     Maureen Spencer               Annual Plan creek clearing has started.
                  (Environmental)               Tecolote Creek clearing u/s of check
                                                                                   th
                                                 structure will started on July 28 .
                                                San Jose Creek clearing from Vineyard
                                                 to Hollister will start today.
                                                Tecolote Basin desilting started August
                                                   th
                                                 4 .
                                                Los Carneros Basin desilting will start
                                                             st
                                                 August 21 .
                                                San Jose Creek and San Pedro Creek
                                                 desilting will begin during the week of
                                                             th
                                                 August 25 once we complete a second
                                                 round of tidewater goby surveys.
                                                Will start taking material to Goleta Beach
                                                 in September if the material passes grain
                                                 size tests and we get approval from EPA
                                                 and ACOE.
                                                Received Emergency Permits from Corps
                                                 for desilting at four locations, debris rack
                                                 installations and culvert replacement on
                                                 Fremont Creek.
                                                Submitted F&G 1610 emergency permit
                                                 application for emergency work. This
                                                 covers the brushing activities, and debris
                                                 rack installations. The desilting work in
                                                 and around the airport was already
                                                 covered by existing permits.
                                                Permitting issues have not been a
                                                 problem.
                                                Steve Wagner asked about adding City
                                                 projects to FC’s emergency
                                                 permits/application process. Steve will
                                                 submit list of projects to Maureen.
                                                Larry Fausett has been working with the
                                                 private property owners on permitting
                                                 their individual projects as needed as
                                                 well as acquiring rights of entry for the
                                                 District projects.
                                                   15
                                     We expect to begin additional creek
                                      clearing (removing
                                      dead/down/overhanging vegetation or
                                      live obstructive vegetation growing within
                                      the creeks) above the routinely
                                      maintained sections of creeks (upper
                                      watersheds) during the week of August
                                         th
                                      18 ) once we get either CDG, Sheriff , or
                                      a crew from our Transportation Division.


Flood Control    Rick Tomasini       Covered by Maureen Spencer (above)
                 (Maintenance)



Flood Control    Jon Frye            Staff working on DSRs to submit to
                 (Engineering)        NRCS.
                                     Mapping information and DSR information
                                      available on County Public Works FTP
                                      site: ftp://pwftp.countyofsb.org/Water/FTP/
                                     USGS and NWS will be in town the next
                                      couple of days to determine if the Gap
                                      Fire qualifies to be named this years'
                                      official USGS/NWS Intensive Research
                                      Area, and to identify basins, hill slopes
                                      and locales for instrument installations.
                                     Finalizing debris rack plans. Installation of
                                      racks should begin early September.
                                     Not mentioned, but also being pursued is
                                      installation of a proposed box culvert
                                      along Fremont Creek to replace two side
                                      by side existing culverts to help prevent
                                      debris blockage.

Transportation   Dave Lewis          Focusing on impacts on County bridges;
County of SB                          erosion and capacity reduction.
                                      Embarcadero and Tecolote bridges show
                                      no impacts.
                                     Glenn Annie Creek u/s of Cathedral Oaks
                                      one of the box culverts is about ½ full and
                                      will need to be desilted. Maureen will add
                                      to project list for permitting.
                                     Patterson Bridge @ Queen Anne looks
                                      ok. Culverts need to be looked at.
                                     Discussion took place regarding Goleta
                                      Beach Bridge. Dave will look into a
                                      temporary structure to provide two lanes.
                                     Dave will begin working on traffic control
                                      plans.

OES, County of   Michael Harris      Talked about coordinating public outreach
SB                                    efforts to let the public know what
                                      currently is being done in response to the
                                      fire and what the public needs to know so
                                      they can be prepared for this winter.
                                     Joint public meeting is now being
                                      scheduled for September.
Public Works     Dave Rickard        Dave Rickard asked State OES regarding
Department                            reimbursement for repairing West Camino

                                         16
                                       Cielo Road. Jim Calacal from FEMA
                                       replied that FEMA only covers temporary
                                       repair work that would make the road
                                       passable. FEMA would not pay for a
                                       permanent fix. Emergency protection
                                       measures on the road would be
                                       addressed on site by site bases.
                                      Rickard ask Calacal if the entire length of
                                       West Camino Cielo road (all damage was
                                       caused by tractors from beginning to end)
                                       could be emergency opening repaired up
                                       to the point of laying down of asphalt.
                                       Charles Rabamad (PAO/OES) stated it is
                                       debatable as to the degrees of damage
                                       (all of the roadway has deep tearing from
                                       the tractors which is a hazard to bicycles
                                       and motorcyclist) FEMA said “NO” don’t
                                       go there…FEMA did agree that the 100%
                                       torn up road is a hazard and should be
                                       repaired under emergency measures by
                                       patching…that is all they would reimburse.
                                      Rickard told FEMA that the PDA missed
                                       by 50% the Emergency Cost for the EOC,
                                       Sheriff’s, County Fire, and Public Health
                                       along with General Services – the PDA
                                       should have been $800,000 for Cat “B”
                                       non-roads work
                                      Rickard mentioned he is having a hard
                                       time achieving NEG (National Emergency
                                       Grant) funds for crews to work in the
                                       creeks – Currently the DOL is also
                                       confused if FEMA-3287 qualifies as the
                                       correct disaster to trigger the NEG grants.
                                       Rickard has conferred with State OES
                                       Charles Rabamad and County (Workforce
                                       Investment Board) WIB Executive Director
                                       Raymond L. McDonald


City of Goleta    Steve Wagner        Currently preparing an emergency
                                       response plan and assessing City bridges
                                       and roadways.
                                      Coordinating Public Information Plan with
                                       County OES.
                                      Will be mapping critical areas and
                                       communities at risk.
                                      City will be leasing a building for a new
                                       Corporate Yard.
                                      Lake Carneros may be used as a woody
                                       debris deposal site.

City of Santa     Karen Ramsdell      Working on advance planning for
Barbara Airport                        buildings and facilities, sandbag operation
                                       set up, emergency purchasing contracts,
                                       and system for tenant notification.
                                      Airport conference room will used as an
                                       EOC during winter if necessary.
                                      Currently inventorying bridges on
                                       Hollister, Carneros, and San Pedro.
                                      Will be cleaning Firestone Ditch but will
                                          17
                                           report back on any additional channel or
                                           bridge work needed.
                                          Steve Wagner and Tom Fayram voiced
                                           concerns about debris getting clogged
                                           under Hollister Bridge over San Pedro
                                           Creek. Karen indicated that there was a
                                           project identified but the project timing
                                           would not work to respond in time for this
                                           year. She also indicated that it was not
                                           their project but the Goleta Sanitary
                                           District’s Sewer lift project. Steve offered
                                           to contact the sanitary district to see if
                                           they could work on a temporary solution to
                                           be in place for the next couple of winters.

City of Santa   Pat Kelly                 Not in attendance
Barbara
DWR             Chang Lee                 No report

State OES       Charles Rabamad           Letter from OES to FEMA regarding the
                                           emergency declaration will be sent in a
                                           couple of weeks. Charles wasn’t sure
                                           what categories would be included.
                                          Indicated that he would approve the
                                           immediate cost sharing between the State
                                           and NRCS DSRs – see below -

NRCS            John                      NRCS received DSR information last
                Bechtold/Matthew           Friday. Tom indicated that there were
                Pawlak                     changes made to the DSRs and revised
                                           info would be sent ASAP. Currently there
                                           are seven DSRs being submitted.
                                           According to the NRCS the projects and
                                           benefit cost ration looks good. Once
                                           approved by local office DSRs will be sent
                                           to Davis for approval.
                                          Once DSRs are approved by NRCS they
                                           will be sent to State OES for their review
                                           and approval.
                                          NRCS will also need to approve plans for
                                           all engineered projects.
                                          John has had a problem contacting
                                           private landowners in the affected area.
                                           Larry offered to call him later and give him
                                           contact information for some of the land
                                           owners.




Adjourn: Next meeting on Monday, August 18, 2008 @ 10:0 a.m. in the Flood Control Conference
Room




                                              18
                      GAP FIRE Watershed Planning Response Group
                          Monday, August 18, 2008 @ 10:00 a.m.
                                      MINUTES

     I. Roll Call:

Attendees:

Scott McGolpin, County of Santa Barbara
Tom Fayram, County of Santa Barbara
Jon Frye, Santa Barbara County Flood Control District
Matt Naftaly, Santa Barbara County Water Agency
Matt Griffin, Santa Barbara County Flood Control
Rochelle Camozzi, County of Santa Barbara, Public Works Department
Steve Wagner, City of Goleta
Larry Fausett, Santa Barbara County Flood Control
Candice Constantine, Santa Barbara County Flood Control
Juan Izquierdo, County of Santa Barbara, Auditor-Controller’s Office
Pete Endsley, Santa Barbara County Flood Control
Dana Zertuche, Santa Barbara County Flood Control
Cindy Chojnacky, USFS


Conference Call:

Dace Morgan, Dave Lewis, John McGray, Chris Sneddon, County of Santa Barbara,
Transportation Division
Matthew Pawlak and Dan Little, NRCS
Charles Rabamad and Dave Gillings, State OES
Karen Ramsdell, City of Santa Barbara Airport
Michael Harris, County of Santa Barbara, OES




                                              19
     II. Opening Remarks (Tom Fayram and Michael Harris):
         The Board of Supervisors is scheduled at their August 19th hearing to:
              o Approve the Gap Fire Watershed Response Plan,
              o Proclaim a local emergency to respond to Gap Fire, and
              o Set a hearing on the September 2nd to receive an update on the status of the
                  projects and work identified in the Gap Fire Watershed Response Plan
         Aerial Photos of the burn area are available both digital and hard copies.
         Regional Community Meeting requested by Supervisors Wolf and Firestone regarding
          the Gap Fire Response is scheduled for September 11, 2008 @ 6:00 p.m. at San
          Marcos High School. Michael Harris sees this meeting as the kick off meeting to the
          more specific neighborhood meetings that will be held to address individual areas of
          concern.
         Ray Ford from the Santa Barbara Independent met with Tom and is writing the first
          article addressing the potential flood threat caused by the fire. Article will be in
          Thursday’s Independent.


    III. Reports/Updates:


Agency           Person Reporting     Report/Update:


Flood Control    Dana Zertuche               Fish & Game permit has not been
                 (Environmental)              received for emergency work.


Flood Control    Tom Fayram                  Seven crew members from Transportation
                 (Maintenance)                started work today on Annual Plan work
                                              on San Pedro and San Jose Creeks.
                                             A second crane started on Carneros
                                              Creek.
                                             Tecolotito Basin is being cleaned out.

Flood Control    Jon Frye/Candice            Looking into lining up a representative
                                                                                th
                 Constantine                  from FEMA for the September 11 Public
                 (Engineering)                Information Meeting to answer flood
                                              insurance questions.
                                             Refining DSRs cost estimates.
                                             Finishing up plans for projects. Should
                                              have out to contractors by the end of the
                                              week.
                                             The USGS/NWS were in town last week
                                              to go over plans for instrumentation for the
                                              upcoming winter. USGS staff visited the
                                              burn area and decided to put up a rainfall
                                              gage just off of West Camino Cielo and
                                              another upstream of La Patera Ranch;
                                              both are in the San Pedro watershed.
                                              They are also planning to put in a webcam
                                              on San Pedro Creek at the location of a
                                              waterfall. A stream gage may also be
                                              installed. The purpose of the gages and
                                              webcams is in part to assist with
                                                 20
                                           advanced warning and also to help
                                           constrain regional debris flow models.
                                          One of the USGS groups is considering
                                           using the Gap fire area as their annual
                                           intensive research area. If they do, they
                                           will be putting in instruments to measure
                                           overland flow, stream flow, rainfall, and
                                           various other parameters on a select
                                           number of hill slopes in Glen Annie
                                           Canyon. A webcam would also be
                                           installed there.
                                          Matt Naftaly and Shawn Johnson will be
                                           contacting the USGS about the rainfall
                                           gaging and will coordinate with Flood
                                           Control efforts.

Transportation    Dave Lewis              Temporary two lanes on Goleta Beach
County of SB                               Bridge (Bridge 158) does not seem
                                           feasible. Also, interim fix will cost a few
                                           hundred thousand dollars and it does not
                                           appear that Caltrans will fund the interim
                                           project. Scott will schedule meeting later
                                           will appropriate staff to discuss in more
                                           detail.
                                          Will continue to work on permanent fix but
                                           permitting issues exist including obtaining
                                           a Corps permit and Coastal Commission
                                           Coastal permit.

OES, County of    Michael Harris          Talked about advance warning needs to
SB                                         be hooked into reverse 911. Also, talked
                                           about how we will deal with the NWS
                                           issuing Flood Watches and Warnings from
                                           an operational stand point.

Public Works      Dave Rickard (Juan      FEMA will be here on Thursday @ 1:00
Department        covered for Dave)        p.m. to work on PWs for Gap Fire
                                           damages.


City of Goleta    Steve Wagner            Working on project list.
                                          Looking at:
                                              o Splitter walls on San Pedro @
                                                  Calle Real and Las Vegas @
                                                  Stow Canyon.
                                              o Culvert protection measures at
                                                  Ellwood at Winchester Canyon.
                                              o Bank Stabilization (sheet pile) @
                                                  Glenn Annie Creek.
                                              o City of Goleta’s Response Plan is
                                                  going to their City Council on
                                                                 nd
                                                  September 2 . Steve will let Tom
                                                  know what time.

City of Santa     Karen Ramsdell          Public Works is inspecting their bridges
Barbara Airport                            this week.
                                          FAA had questions regarding BAER
                                           Report relating to funding. The Airport
                                           responded back and sent a copy of the
                                           draft BAER Report for their information.
                                              21
City of Santa   Pat Kelly                 Not in attendance
Barbara
DWR             Chang Lee                 Not in attendance

State OES       Charles Rabamad           No report just waiting for lists of project
                                           from agencies to determine eligibility.

USFS            Cindy Chojnacky           BAER Report has been tentatively
                                           approved by regional forester. Waiting for
                                           final approval from the Secretary of
                                           Agriculture in Washington, D.C.
                                          Tom asked if the modifications requested
                                           were included in the final BAER Report
                                           and Cindy said that the changes were
                                           included.
                                          Cindy also said that because the USFS
                                           has expended 75% of their budget for the
                                           year on fires that there may be a slight
                                           hold up on the report being approved.

NRCS            John                      Will be finalizing DSRs today and will be
                Bechtold/Matthew           sending to Tom and John Bechtold for
                Pawlak                     signature.
                                          Approximately $3-$3.5 million in DSRs.
                                          Will need to review design plans when
                                           complete.




Adjourn: Next meeting on Monday, August 25, 2008 @ 10:0 a.m. in the Flood Control Conference
Room




                                              22
                      GAP FIRE Watershed Planning Response Group
                          Monday, August 25, 2008 @ 10:00 a.m.
                                      MINUTES

   IV. Roll Call:

Attendees:

Tom Fayram, County of Santa Barbara
Jon Frye, Santa Barbara County Flood Control District
Rochelle Camozzi, County of Santa Barbara, Public Works Department
Steve Wagner, City of Goleta
Candice Constantine, Santa Barbara County Flood Control
Juan Izquierdo, County of Santa Barbara, Auditor-Controller’s Office
Dana Zertuche, Santa Barbara County Flood Control
Maureen Spencer, Santa Barbara County Flood Control
Ricky Tomasini, Santa Barbara County Flood Control
Pat Kelly, City of Santa Barbara, Public Works Department

Conference Call:

Dave Lewis, County of Santa Barbara, Transportation Division
Dave Rickard, County Public Works Department
Chang Lee, DWR
Don Cardenas and Dave Gillings, State OES
Lance Gorman, Martin Sanchez, and Ross Merrill, Caltrans




                                              23
     V. Opening Remarks (Tom Fayram and Michael Harris):
        DSRs were signed last week. Cooperative Agreement will be signed by Flood Control
         today and sent up to NRCS. Bill Ward has spoken to NRCS Headquarters and money
         has been obligated for the projects.

          There will be no meeting next Monday (September 1st) due to Labor Day.

          Tom met with Colonel Magness last week and he pledged to help anyway he can.



    VI. Reports/Updates:


Agency            Person Reporting    Report/Update:


Flood Control     Maureen Spencer            Fish & Game permit has not been
                  (Environmental)             received for emergency work.
                                             Mary Larsen will review plans for San
                                              Pedro.
                                             Regional Board requested copy of the
                                              State Declaration of Emergency.
                                             Working on permitting with County
                                              Transportation on Tecolotito Culvert.
                                             The District continues to employ
                                              tidewater goby protective measure in Los
                                              Carneros and Tecolotito Basins during
                                              the desilting operations even though pre
                                              project surveys in these basins did not
                                              find any gobies. They have been found
                                              in both of these basins in the recent past-
                                              -last year and in 2006.
                                             We also just completed a second round
                                              of tidewater goby surveys in San Jose,
                                              San Pedro and Atascadero Creeks on
                                              August 13th and 14th. No gobies were
                                              found in San Pedro or San Jose Creeks
                                              and one goby was found in the upper
                                              reaches of Atascadero Creek within the
                                              Goleta Slough Dredging
                                              limits downstream of the check structure
                                              at Ward Drive. No tidewater goby
                                              protective measures will be employed in
                                              San Jose or San Pedro Creeks during
                                              desilting operations.

Flood Control     Rick Tomasini              Tecolote Basin desilting is complete.
                  (Maintenance)               Trucking will start tomorrow.
                                             Wally from the Airport has not lined up
                                              street sweeping on Hollister yet.
                                             Los Carneros – cranes will start tomorrow.
                                             San Jose work will start today.
                                             San Pedro will start tomorrow.

                                                24
                                      Filling sandbags with the Sherriff’s
                                                                              nd
                                       Department will start on September 2 .
                                      Rick will make sure that Fire Station 14
                                       has sand and bags.
                                      Tom indicated that CDF crews should be
                                       available next week to start creek clearing
                                       work.
                                      County Hot Shot crews may be another
                                       option if NRCS will reimburse costs.

Flood Control     Jon Frye            Debris rack project bids will open
                                                    nd
                  (Engineering)        September 2 .
                                      Hope to have Fremont Culvert plan/spec
                                       out to contractors by end of this week.
                                      Developing a plan for access to Goleta
                                       Beach off of Highway 217 for submittal to
                                       Caltrans.
                                      Tom mentioned that we need to keep in
                                       mind is that we cannot issue a notice to
                                       proceed for any of this work until the
                                       NRCS has executed all the DSRs, any
                                       work performed before that is ineligible for
                                       reimbursement.
Transportation    Dave Lewis          Goleta Beach Bridge (Bridge 158) will not
County of SB                           support two lanes of traffic without
                                       supplemental support.

OES, County of    Michael Harris      Not present
SB
Public Works      Dave Rickard        Kick off meeting with State OES was last
Department                             Thursday. Category B work was
                                       discussed. FEMA was also in attendance.
                                      FEMA and State OES have a meeting
                                       today at 2:00 p.m.


                                   
                                                        nd
City of Goleta    Steve Wagner         On September 2 the City Council of
                                       Goleta is scheduled to approve their
                                       Response Plan, Emergency Proclamation,
                                       and Emergency Contracting procedures.
                                      San Pedro Creek culvert modification will
                                       include a splitter wall, lowering the
                                       parapet wall, and replacing the chain link
                                       fence with cable railing.
                                      Las Vegas @ Stow Canyon will have a
                                       similar splitter wall. Steve will coordinate
                                       permitting with Maureen.
                                      Steve asked about if shortage of
                                       resources occurs during this winter with
                                       contractors how that will be handled. Tom
                                       said that the ICS System will kick in and
                                       all resources will be shared. Work will be
                                       prioritized and resources will be
                                       distributed as appropriate.
                                      Working on cleaning out culverts.

City of Santa     Karen Ramsdell      Not present
Barbara Airport
City of Santa     Pat Kelly           City is inspecting their bridges and is

                                          25
Barbara                                    developing an EAP.
                                          Looking into overland escape route on
                                           San Pedro @ Hollister. Looking for ideas
                                           from Tom and Scott.
                                          Will contact Goleta Sanitary District
                                           regarding encased sewer line at Hollister
                                           Bridget (Pat to report back on status in
                                           two weeks).
DWR             Chang Lee                 No report. Tom asked Chang to
                                           coordinate with DWR in Sacramento to
                                           ensure that if a PL84-99 request is sent by
                                           the County to DWR this winter that if DWR
                                           is unable to offer assistance that they will
                                           immediately forward the request to the
                                           Corps.

Caltrans        Lance Gorman              Decision for HWY 217 access will be
                                           made by Headquarters.
                                          Los Carneros, Tecolote, Las Vegas, and
                                           San Pedro structures are clean.
                                          Looking at San Jose 101 corridor – needs
                                           input.
                                          Will mobilize equipment and have on
                                           standby if needed.
                                          Las Vegas Creek – no feasible plans.
                                          San Pedro Creek Caltrans has no plans.
                                           Flood Control and City of Goleta are
                                           coordinating.
                                          Carneros Creek looking into debris
                                           removal.
                                          Lance believes that sediment will be the
                                           big issue this winter. Tom warned that we
                                           should also be prepared to deal with
                                           woody debris and that d/s culverts and
                                           bridges may be at risk.
                                          Lance said funding is an issue. FHWA
                                           does not fund preventative type work.
                                           FHWA funding covers responding to
                                           flooding once it occurs. Lance requested
                                           the BAER report to see if that could
                                           potentially help with obtaining funding for
                                           pre disaster work.

State OES       Donald                    Meeting with FEMA today will be to
                Cardenas/Dave              discuss method of repair of roads and
                Gillings                   eligibility of road repair.
                                          Dave said that Charles will write up the
                                           cost share with estimated cost and then
                                           will adjust when final costs are known.

USFS            Cindy Chojnacky           Not present

NRCS            John                      Not Present
                Bechtold/Matthew
                Pawlak


Adjourn: Next meeting on Monday, September 8, 2008 @ 10:00 a.m. in the Flood Control
Conference Room
                                              26
                      GAP FIRE Watershed Planning Response Group
                        Monday, September 8, 2008 @ 10:00 a.m.
                                      MINUTES

   VII. Roll Call:

Attendees:

Tom Fayram, County of Santa Barbara
Jon Frye, Santa Barbara County Flood Control District
Rochelle Camozzi, County of Santa Barbara, Public Works Department
Steve Wagner, City of Goleta
Juan Izquierdo, County of Santa Barbara, Auditor-Controller’s Office
Dana Zertuche, Santa Barbara County Flood Control
Maureen Spencer, Santa Barbara County Flood Control
Pat Kelly, City of Santa Barbara, Public Works Department
Dace Morgan, County of Santa Barbara, Transportation Division
Jim Webb, USFS
Cindy Chojnacky, USFS
Jeff Salt, Goleta Sanitation District
Scott McGolpin, County of Santa Barbara, Public Works Department



Conference Call:

Dave Rickard, County Public Works Department
Chang Lee, DWR
Don Cardenas and Dave Gillings, State OES
Matthew Pawlak, NRCS




                                               27
      I. Reports/Updates:


Agency          Person Reporting      Report/Update:


Flood Control   Maureen Spencer              Beth Ford (FC) sent Glenn Annie Road
                (Environmental)               Culvert Project info to regulatory
                                              agencies. F&G will add project to
                                              emergency list – no word from Corps.
                                             Beth sent emergency declaration to all
                                              the regulatory agencies.
                                             City of Goleta projects have been sent to
                                              regulatory agencies.
                                             Sediment testing for San Pedro, Los
                                              Carneros, and San Jose should be
                                              complete this week.
                                             About 8 miles of the 16 miles of brushing
                                              are completed.

Flood Control   Maureen Spencer for          Tecolote Creek u/s of Cathedral Oaks is
                Rick Tomasini                 complete. Will begin d/s work.
                (Maintenance)                Los Carneros Basin will be complete early
                                              this week.
                                             San Jose and San Pedro Basins are
                                              about 2/3 done. Should be complete next
                                              week.
                                             Tecolotito Basin is complete.
                                             Los Carneros Creek started this morning
                                              with the County Fire crews.
                                             San Pedro Creek u/s of Cathedral Oaks is
                                              being done by CDF crews.

Flood Control   Jon Frye                     Bid opening for debris racks was last
                (Engineering)                 Wednesday. Tierra was the low bid for all
                                              five racks; FC will issue a notice to
                                              proceed. Contract is for 20 working days.
                                             Fremont Creek Culvert will go out to bid
                                              today – bid opening next Monday (Sept.
                                              15).
                                             FC Hydrology staff is working with the
                                              USGS to install 4 streamgages (3 in the
                                              San Pedro watershed and 1 in the
                                              Tecolote watershed) and 2 webcams.
                                              This in addition to the work being done in
                                              the Special Study Area.
                                             Working on developing a HWY 217
                                              conceptual plan.
                                             FC will contact the hydromulching
                                              contractors from the USGS bid list to
                                              notify them that the District would be
                                              interested in extending their contract with
                                              the USFS to hydromulch on non-federal
                                              land. County contract will double the
                                              acreage and add about 1,500 acres of
                                              work. USFS will open bids on
                                              Wednesday and FC will contact the lowest
                                                28
                                         bidder.
                                        Sent out draft Cooperative Agreement to
                                         the Cities for hydromulching – requested
                                         comments back.
                                        DSR for hydromulching was approved at
                                         $3.3 million given the unit rates.

Transportation      Dace Morgan         Dace met with Steve Price to discuss the
County of SB                             HWY 217 and access to Goleta Beach.
                                         The meeting went well. Will following up
                                         with Tom regarding the specifics.
                                        Looking at constructed a “super bent” on
                                         the Goleta Beach bridge by December.

OES, County of      Michael Harris      Not present
SB
Public Works        Dave Rickard        Sent DSRs to State OES in overnight mail
Department                               on Thursday. Don (State OES) will start
                                         reviewing immediately. We should be
                                         notified if DSRs are approved by the end
                                         of the week. State OES will be in town on
                                         Wednesday for PWs (Category B).

City of Goleta      Steve Wagner        City Council approved emergency
                                         declaration, emergency response plan,
                                         and emergency procurement policy at
                                                            nd
                                         their September 2 meeting.
                                        Working on pulling together engineering
                                         plans for City projects.
                                        Had comments for the hydromulching
                                         cooperative agreement among with the
                                         Cities and the Flood Control District. Both
                                         Cities and FC will meet briefly to discuss
                                         after meeting.

City of Santa       Karen Ramsdell      Not present
Barbara Airport
City of Santa       Pat Kelly           Karen is working on the EAP for the City.
Barbara                                 There will be a meeting on Thursday to
                                         discuss the Mutual Aid Agreement to
                                         discuss how the agreement works. The
                                         Airport will be the main contact for the
                                         Mutual Aid Agreement.
                                        There are no construction projects
                                         identified on Airport property at this time.
                                     
Goleta Sanitation   Jeff Salt           There is a meeting tomorrow with the
District                                 Airport regarding Hollister Bridge. P&S is
                                         working on the project.
                                        Surveyed creek crossings last year. Is
                                         looking at stabilizing (rip-rap) at the Las
                                         Vegas Creek crossing. Maureen talked to
                                         Ginger from P&S regarding permitting
                                         issues.
DWR                 Chang Lee           No report. Tom asked Chang (again) to
                                         coordinate with DWR in Sacramento to
                                         ensure that if a PL84-99 request is sent by
                                         the County to DWR this winter that if DWR
                                         is unable to offer assistance that they will

                                            29
                                           immediately forward the request to the
                                           Corps.

Caltrans        Lance Gorman              Not present

State OES       Donald                    Report combined with Dave Rickard.
                Cardenas/Dave
                Gillings
USFS            Cindy Chojnacky           Gap BAER Report was approved by
                                                                      th
                                           Washington on August 29 . Cindy
                                           indicated that the main changes were that
                                           costs are now reduced (like
                                           hydromulching from $5.6 million to $4.8
                                           million). Specific areas will have the
                                           ability to go back and request additional
                                           funding. Interagency coordinator funding
                                           was not approved in the BAER Report.
                                          Gap BAER team is coming into town
                                           today.


NRCS            Matthew Pawlak            Tom asked if DSR costs are under for
                                           some projects if we could shift costs to
                                           help pay for the construction costs for the
                                           Goleta Slough Bridge work. Matthew
                                           didn’t see a problem with that at this point.
                                          Asked FC to start documenting projects
                                           and providing updates and photos. Needs
                                           plans for engineered projects. Jon will
                                           send plans to for both Bill and Matthew.
                                          Matthew suggested identifying and
                                           coordinating hydromulching work with
                                           landowners (FC has already notified land
                                           owners). Also suggested to send specs
                                           with a notice of what is being applied to
                                           affected landowners.




Adjourn: Next meeting on Monday, September 15, 2008 @ 10:00 a.m. in the Flood Control
Conference Room




                                              30
                      GAP FIRE Watershed Planning Response Group
                        Monday, September 15, 2008 @ 10:00 a.m.
                                      MINUTES

  VIII. Roll Call:

Attendees:

Tom Fayram, County of Santa Barbara
Jon Frye, Santa Barbara County Flood Control District
Rick Tomasini, Santa Barbara County Flood Control District
Rochelle Camozzi, County of Santa Barbara, Public Works Department
Steve Wagner, City of Goleta
Juan Izquierdo, County of Santa Barbara, Auditor-Controller’s Office
Dana Zertuche, Santa Barbara County Flood Control
Maureen Spencer, Santa Barbara County Flood Control
Pat Kelly, City of Santa Barbara, Public Works Department
Dace Morgan, County of Santa Barbara, Transportation Division
Jim Webb, USFS
Jeff Salt, Goleta Sanitation District
Scott McGolpin, County of Santa Barbara, Public Works Department



Conference Call:

Chang Lee, DWR
Jay McAmis, County OES
Dan Little, NRCS




                                              31
     II. Opening Comments:
Public Meeting on Thursday went pretty well. City of Goleta will take the lead on setting up additional
public information meetings.


    III. Reports/Updates:


Agency             Person Reporting        Report/Update:


Flood Control      Maureen Spencer                Will be taking sediment samples of
                   (Environmental)                 desilting on Wednesday. Will send
                                                   results to EPA and Corps for approval to
                                                   move material to Goleta Beach.
                                                  The District was not exempt from 401b
                                                   certification from the Regional Board.
                                                   Will submit after the fact emergency
                                                   mitigation for work. May need to submit
                                                   application – Regional Board is not
                                                   allowed to waive permit.
                                                  Specific language in State Declaration
                                                   needs to be added to exempt us from
                                                   401 waiver. Tom asked County OES
                                                   (Jay McAmis) to keep that in mind for
                                                   next State emergency.

Flood Control      Rick Tomasini                  Currently brushing Los Carneros Creek.
                   (Maintenance)                   Basin is complete.
                                                  Winchester/Bell Creek work is complete.
                                                  Ellwood is about ¾ complete.
                                                  Red flag alert – lost County Fire crews for
                                                   a couple of days.
                                                  San Pedro Basin ¾ complete.
                                                  San Jose should be done tomorrow.
                                                  Hauling material to Foothill landfill.
                                                  Sand bag pallets are being delivered to
                                                   Fire Station 14, City of Goleta corporate
                                                   yards, and will store extra bags at the
                                                   Airport.

Flood Control      Jon Frye                       Fabrication work for debris racks is
                   (Engineering)                   underway. Pre-con meeting is tomorrow.
                                                  Fremont Creek Culvert – bid opening is
                                                   tomorrow.
                                                  Will be entering into a contract will Aero
                                                   Tech for aerial hydromulching. Working on
                                                   Cooperative Agreement with Cities for
                                                   cost sharing. Pat asked Jon to send
                                                   Cooperative Agreement to Karen. Will
                                                   need to meet with Cities and USFS to
                                                   coordinate work.
                                                  Will start plans for K-rail on San Pedro
                                                   and Los Carneros Road (will work with
                                                   Steve on this).

                                                      32
Transportation      Dace Morgan         Closed Goleta Beach Bridge to one lane
County of SB                             over the weekend – worked well.
                                        Coordinating permit with Steve Senate
                                         from Caltrans. Will submit application to
                                         Caltrans to submit to headquarters.
                                        Working on Road Closure plans for this
                                         winter with the City.
                                        Super bend project is on schedule.
                                     
OES, County of      Jay McAmis          No report
SB
Public Works        Dave Rickard        Not present
Department
City of Goleta      Steve Wagner        Working on plans and specs for City
                                         projects. Getting ready to go out to bid.
                                        City of Goleta will be hosting meetings on
                                                        rd
                                         September 23 @ Goleta Valley Jr. High
                                                             nd
                                         and on October 2 at the Goleta Valley
                                         Community Center at 6:30 p.m.

City of Santa       Karen Ramsdell      Not present
Barbara Airport
City of Santa       Pat Kelly           Pat brought up that there are logistical
Barbara                                  issues with the Airport with
                                         hydromulching. Jon said that the
                                         contractor is working on this directly with
                                         the Airport.
                                        Looking at accelerating Hollister Bridge
                                         project. There is a meeting with Goleta
                                         Sanitary tomorrow.
                                        Tom asked Pat for a traffic closure plan
                                         for the City of Santa Barbara for the
                                         Sheriff’s Department.
Goleta Sanitation   Jeff Salt           Requested copy of emergency declaration
District                                 to give to his board to see if this will help
                                         get the sewer crossing project out to bid
                                         sooner.

DWR                 Chang Lee           No report.

Caltrans            Lance Gorman        Believes putting in a bull nose at Los
                                         Carneros and Tecolotito will be more of a
                                         hindrance than help.
                                        At the Public Meeting a question came up
                                         regarding the chain link fence at Las
                                         Vegas that it may cause debris to clog.
                                         Lance brought up liability issues with
                                         some of the fixes. Lance will report back
                                         on what Caltrans will do.


State OES           Donald              Not present
                    Cardenas/Dave
                    Gillings
USFS                Jim Webb            Hydromulching – planes will start flying on
                                                        th
                                         September 24 . Team leader moving in
                                                   th
                                         on the 20 . 22 day contract.
                                        USFS will conduct meetings regarding
                                         project with community members.

                                            33
                                           General contact for project is Kathy Good;
                                           Implementation contact is Mary Moore.
                                          BAER Team was here last week. They do
                                           not believe that debris racks on USFS
                                           land will work.
                                          Lance asked about the USFS about HWY
                                           154. USFS coordinate work with Caltrans
                                           – dozer line remediation measures have
                                           been completed.

NRCS            Dan Little                Tom told Dan that he had emailed the
                                           direct deposit form to the NRCS as they
                                           requested.
                                          Received DRS from Goleta Water District.
                                          Working with private land owners. Tom
                                           asked NRCS to contact Slippery Rock
                                           Ranch to see if they could assist them.
                                          Tom asked Dan to talk to Bill Ward about
                                           reallocating DSR money to Goleta Beach
                                           Bridge project. Debris racks and channel
                                           clearing came in under budget.




Adjourn: Next meeting on Monday, September 22, 2008 @ 10:00 a.m. in the Flood Control
Conference Room




                                             34
                     GAP FIRE Watershed Planning Response Group
                       Monday, September 22, 2008 @ 10:00 a.m.
                                     MINUTES

   IX. Roll Call:

Attendees:

Tom Fayram, County of Santa Barbara
Jon Frye, Santa Barbara County Flood Control District
Rochelle Camozzi, County of Santa Barbara, Public Works Department
Steve Wagner, City of Goleta
Jane Lee, County of Santa Barbara, Auditor-Controller’s Office
Dana Zertuche, Santa Barbara County Flood Control
Maureen Spencer, Santa Barbara County Flood Control
Pat Kelly, City of Santa Barbara, Public Works Department
Dace Morgan, County of Santa Barbara, Transportation Division
Jim Webb, USFS
Jeff Salt, Goleta Sanitation District
Scott McGolpin, County of Santa Barbara, Public Works Department



Conference Call:

Chang Lee and Brian Moniz, DWR
Jay McAmis, County OES
Dan Little and Mathew Pollack, NRCS
Dave Rickard, County of Santa Barbara, Public Works Department




                                             35
    IV. Opening Comments:


     V. Reports/Updates:


Agency           Person            Report/Update:
                 Reporting

Flood Control    Maureen                     Last Friday, Beth filed a CEQA Notice of Exemption for the
                 Spencer                      Aerial Hydromulching Project.
                 (Environmental)             Sent information to Corps for all of the additional projects.
                                              Corps will send out the info to all of the regulatory agencies for
                                              comment by the end of the week. Should have authorization
                                                                                  th      th
                                              from the Corps by the October 29 or 30 for the additional
                                              work.
                                             Application for the Regional Board will be mailed today.
                                             Sediment samples were taken last Wednesday. Should have
                                              results by next week.

Flood Control    Tom Fayram                  Stream clearing should be completed today or tomorrow.
                 (Maintenance)               Sediment removal is completed except for the upper end of San
                                              Pedro.
                                             Debris rack at Ellwood should be done today. Will start debris
                                              rack on Las Vegas next. Each rack takes about a week to
                                              complete.
                                             Aerial hydromulching is in the process and will go the Board on
                                              Tuesday.

Flood Control    Jon Frye                     Debris rack work in progress, Ellwood nearly complete.
                 (Engineering)                Notice to Proceed for Fremont Creek Culvert to be dated
                                                              th
                                               September 30 .
                                          
                                                                                                        rd
                                               Aerial hydro mulch contract to Board on September 23 . Final
                                               acreage 1,000 acres. Informational packages sent to all
                                               property owners on which hydro mulching will take place.
                                              San Pedro K-Rail protective measure out to bid this week.
                                              USGS (& ALERT) telemetry stations include two rain gauges
                                               (Upper Burn area, and Lower Burn area), one Stream Gauge
                                               (PT – San Pedro Crk @ Stow Cyn Rd)), and a Web-Cam (@
                                               Fairview Falls).
                                              The USGS (different study group) will also be installing self-
                                               recording (non-telemetry) flow gauges in other areas of the
                                               Burn.
                                              The District will also install one ALERT rain gauge in the upper
                                               Tecolote watershed. The permit application for this was
                                                                                                           nd
                                               submitted to the USDA Forest Service on September 22 .
                                              http://www.wrh.noaa.gov/lox/scripts/getlocal.php?prod=LAXRR
                                               MSBA
                                              The above link includes a NWS grouping of Burn area gauges.


Transportation   Dace Morgan                 Goleta Beach Bridge permitting working with Maureen.
County of SB                                 Kevin will have draft of road closure map. Working with City of
                                              Goleta. Dace will send Pat the GIS files.
                                      
OES, County      Jay McAmis                  No report
                                                            36
of SB
Public Works     Dave Rickard       NRCS DSRs in process with State OES.
Department                          There will be an exit review meeting with State OES.
                                    Dave will give update at Project Reporting
City of Goleta   Steve Wagner       Public meetings:
                                                                                      rd
                                        o Goleta Valley Jr. High on September 23 @ 6:30 p.m.
                                                                                            nd
                                        o Goleta Valley Community Center on October 2 at 6:30
                                             p.m
                                                                                         th
                                        o Business Outreach Meeting on October 7 @ 12:00 p.m.
                                             location TBD
                                    Has draft traffic closure plan.

City of Santa    Karen              Not present
Barbara          Ramsdell
Airport
City of Santa    Pat Kelly          Cooperative Agreement for Hydromulching will go to City Council
Barbara                              tomorrow for approval.
                                    Working on Hollister Bridge and sewer lift station with Goleta
                                     Sanitation District.
                                    Had questions regarding webcams being installed by the USGS.
                                     Jon will get the USGS contact info to Pat.

Goleta           Jeff Salt          No report
Sanitation
District
DWR              Chang Lee          No report. Brian Moniz will call in next week for Chang.

Caltrans         Lance Gorman       Not present


State OES        Donald             Not present
                 Cardenas/Dave
                 Gillings
USFS             Jim Webb           Hydromulching meeting today, equipment will be here tomorrow,
                                     and planes will start flying on Wednesday (weather permitting).
                                     200 to 300 flights per day for 22 calendar days.
                                    Working with Dace to close County roads during aerial mulching.

NRCS             Dan Little         Ok to reallocate channel clearing money to Goleta Beach Bridge
                                     project since bridge support work was included in the DSRs.
                                    Asked to keep them information on status of projects. NRCS will
                                     come down for site visit when all projects are complete.


Adjourn: Next meeting on Monday, September 29, 2008 @ 10:00 a.m. in the Flood Control
Conference Room




                                                   37
                       GAP FIRE Watershed Planning Response Group
                         Monday, September 29, 2008 @ 10:00 a.m.
                                        MINUTES

    X. Roll Call:

Attendees:

Tom Fayram, County of Santa Barbara
Jon Frye, Santa Barbara County Flood Control District
Steve Wagner, City of Goleta
Juan Izquierdo, County of Santa Barbara, Auditor-Controller’s Office
Pat Kelly, City of Santa Barbara, Public Works Department
Dace Morgan, County of Santa Barbara, Transportation Division
Jeff Salt, Goleta Sanitation District
Scott McGolpin, County of Santa Barbara, Public Works Department
Dave Rickard, County of Santa Barbara, Public Works Department
Kamil Azoury, Goleta Sanitation District
Cindy Chojnacky, USFS
Rick Tomasini, Santa Barbara County Flood Control District

Conference Call:

Brian Moniz, DWR
Jay McAmis, County OES
Maureen Spencer, Santa Barbara County Flood Control




                                                38
    VI. Opening Comments:
         a. State OES SEAT Team will have draft report out for review today. OES is anticipating a
            three day review period before finalizing the report.

           b. Annual operations meeting with the National Weather Services is this Thursday @ 1:30 p.m.
              in the Flood Control conference room.

           c. Will discuss next week when we should end these weekly meetings. Steve suggested holding
              the meetings monthly starting on October 13th.


   VII. Reports/Updates:


Agency           Person            Report/Update:
                 Reporting

Flood Control    Maureen                     Should receive authorization from the Corps on Wednesday for
                 Spencer                      the additional projects.
                 (Environmental)             Submitted application to Regional Board last week.
                                             The USFWS had submitted comments to the ACOE saying they
                                              had concerns regarding tidewater gobies at the San Pedro
                                              Creek sewer line project and Winchester Canyon Culvert project
                                              locations. Maureen said there was no worry about the San
                                              Pedro Creek location because it is bone dry and would check
                                              further into the Winchester Canyon Creek project to see if
                                              surveys needed to be done. Maureen will check the site for red-
                                              legged frogs prior to the start of construction - probably going to
                                              go out tomorrow to check for frogs.

Flood Control    Rick Tomasini               16 miles of stream clearing is complete.
                 (Maintenance)               Basin work is complete.
                                             Hauling should be complete next week.
                                             County Fire crews are still available if needed.

Flood Control    Jon Frye                     Debris racks at Ellwood, Las Vegas, and San Pedro are
                 (Engineering)                 complete.
                                              Carneros and Glenn Annie racks are being installed next.
                                              Pre-con meeting for Fremont Culvert Project is today. Project
                                               should start this week.
                                              K-rail project bid opening is this Friday.
                                              Contract for aerial hydromulching is in the process.


Transportation   Dace Morgan                 Goleta Beach Bridge waiting for permit to start work. Once work
County of SB                                  starts it should take two weeks to complete.
                                             Received traffic control plans from Joyce.
                                             Road closure plans are complete for County and City of Goleta.
                                              The City of Goleta incorporated City of Santa Barbara in their
                                              plan.
                                             There are archeological sites off of HWY 217 – looking at
                                              alternative sites.
                                             Ricky will be opening the Slough.


                                                             39
OES, County      Jay McAmis           Currently transitioning out operation mode.
                                   
                                                                                         th
of SB                                  First cut of response plan should be out on the 16 .

Public Works     Dave Rickard         State DSRs and FEMA have tentatively approved Transportation
Department                             projects.
City of Goleta   Steve Wagner         Public meetings:
                                                                                         nd
                                           o Goleta Valley Community Center on October 2 at 6:30
                                               p.m
                                                                                    th
                                           o Business Outreach Meeting on October 9 @ 11:30 a.m.
                                               at City Hall Council’s Chambers.

City of Santa    Karen                Not present
Barbara          Ramsdell
Airport
City of Santa    Pat Kelly            Wrapping up Action Plan.
Barbara                               FYI - City is conducting a Tsunami exercise this Thursday.

Goleta           Jeff Salt            No report
Sanitation
District
DWR              Brian Moniz          No report

Caltrans         Lance Gorman         Not present


State OES        Donald               Not present
                 Cardenas/Dave
                 Gillings
USFS             Cindy Chojnacky      Hydromulching is going well and moving very quickly. As of last
                                       night 602 acres have been mulched. USFS is working with
                                       County roads on closing West Camino Cielo during the aerial
                                       mulching.

NRCS             Dan Little           Not present


Adjourn: Next meeting on Monday, October 6, 2008 @ 10:00 a.m. in the Flood Control
Conference Room




                                                     40
                      GAP FIRE Watershed Planning Response Group
                          Monday, October 6, 2008 @ 10:00 a.m.
                                      MINUTES

   XI. Roll Call:

Attendees:

Tom Fayram, County of Santa Barbara
Juan Izquierdo, County of Santa Barbara, Auditor-Controller’s Office
Pat Kelly, City of Santa Barbara, Public Works Department
Dace Morgan, County of Santa Barbara, Transportation Division
Jeff Salt, Goleta Sanitation District
Rochelle Camozzi, County of Santa Barbara, Public Works Department
Rick Tomasini, Santa Barbara County Flood Control District

Conference Call:

Brian Moniz, DWR
Jay McAmis, County OES
Steve Wagner, City of Goleta
Dave Rickard, County of Santa Barbara, Public Works Department
Jeff Benson, USFS




                                              41
   VIII. Opening Comments:
          a. After the October 13th Gap Fire Watershed Meeting – Meetings will be held on the first
             Monday of the month. The next two scheduled are on November 3rd and December 1st.


    IX. Reports/Updates:


Agency           Person            Report/Update:
                 Reporting

Flood Control    Tom Fayram                  Received authorization from the Corps for all emergency
                 (Environmental)              projects.

Flood Control    Rick Tomasini               All emergency maintenance projects are complete.
                 (Maintenance)               We will be finishing up hauling from San Pedro and San Jose
                                              this week.


Flood Control    Tom Fayram                   All debris racks are complete except for Glenn Annie – there is
                 (Engineering)                 a dewatering issue there.
                                              Fremont Creek Culvert project will start this week.
                                              K-Rail protective measures – bids opened on Friday. Granite
                                               was low bid. Work should start in approximately 10 days and
                                               contract gives Granite 10 days to complete.
                                              Aerial Mulching project – County contract likely to begin this
                                               afternoon. All property owners have been notified in writing
                                               and by telephone and are aware of what’s going on. Contract
                                               is fully executed.


Transportation   Dace Morgan                 Received Corp permit and Coastal Commission permit for Goleta
County of SB                                  Beach Bridge. Installing piles at the bridge starting tomorrow
                                              night. Work should be completed in two weeks.
                                             Tierra to start work on Glen Annie box culvert.
                                             Jon emailed Eric regarding keeping West Camino Cielo closed
                                              during the County’s portion of the hydromulching. Tom and
                                              Dace will discuss details later.

OES, County      Jay McAmis                  No report
of SB
Public Works     Dave Rickard                No report
Department
City of Goleta   Steve Wagner                Calle Real Culvert project – bid opening this morning.
                                             Winchester bid opening is next week.
                                             Working on emergency contracts for debris removal for this
                                              upcoming winter.
                                      
                                                                                                 th
                                              Business Outreach Lunch Meeting is on October 9 @ Council’s
                                              Chambers. Tom is out of town – Jon Frye will cover Tom’s
                                              presentation.

City of Santa    Karen                       Not present
Barbara          Ramsdell
Airport
City of Santa    Pat Kelly                   Tom asked if City has emergency contracts for debris removal in

                                                            42
Barbara                            place. Pat will have to ask Karen on the status of the contracts.
                                  Pat brought up if there is a shortage of contractors to hire during
                                   this winter who will receive the priority. Tom said that would be
                                   worked out through the Emergency Operation Council members.

Goleta       Jeff Salt            Emergency permit application submitted this week. Anticipating
                                                                st
Sanitation                         starting work November 1 .
District                          The draft MOU for the project has been given to the County and
                                   Cities for comment. The MOU will be discussed at the Goleta
                                   Sanitation District board meeting tonight. The City of Goleta has
                                   a meeting with their City manager to discuss. The City of Santa
                                   Barbara already has a cost sharing agreement with the
                                   sanitation district for the project but Pat will look into for there
                                   needs to be further City Council action taken. The County not
                                   planning on playing a role but Scott will discuss at the Unified
                                   Command meeting today.


DWR          Brian Moniz          No report

Caltrans     Lance Gorman         Not present


State OES    Donald               Not present
             Cardenas/Dave
             Gillings
USFS         Jeff Benson          USFS Hydromulching work will be completed today.

NRCS         Dan Little           Matthew asked Dan to pass along to Tom that he and Bill Ward
                                   are still looking into reallocating channel clearing funds to pay for
                                   the Goleta Beach Bridge project.




Adjourn: Next meeting on Monday, October 13, 2008 @ 10:00 a.m. in the Flood Control
Conference Room




                                                  43
                      GAP FIRE Watershed Planning Response Group
                         Monday, October 13, 2008 @ 10:00 a.m.
                                      MINUTES

   XII. Roll Call:

Attendees:

Tom Fayram, County of Santa Barbara
Scott McGolpin, County of Santa Barbara, Public Works Department
Juan Izquierdo, County of Santa Barbara, Auditor-Controller’s Office
Dave Hetyonk, Santa Barbara School District
Pat Kelly, City of Santa Barbara, Public Works Department
Eric Pearson, County of Santa Barbara, Transportation Division
Jeff Salt, Goleta Sanitation District
Rochelle Camozzi, County of Santa Barbara, Public Works Department
Mike Kanno, Goleta Water District
Rosemarie Gaglione, City of Goleta

Conference Call:

Mitra, DWR
Maureen Spencer, Santa Barbara County Flood Control District




                                              44
     X. Opening Comments:
         a. Next two Gap Fire meetings are scheduled for November 3rd and December 1st.
         b. Scott reported that the Business Outreach Meeting last week went well. At the
            meeting, Dan Singer commented on the cooperative manner in which all of the local,
            state, federal agencies are working together.

    XI. Reports/Updates:


Agency           Person            Report/Update:
                 Reporting

Flood Control    Maureen                     Have all of the required approvals or permits for emergency
                 Spencer                      projects. Maureen will follow up with regulatory agencies. Tom
                 (Environmental)              asked Maureen to draft up a thank you letter from Scott to all of
                                              agencies for their cooperation and assistance with permitting of
                                              emergency work.
                                             Sediment samples passed. Will send results to the Corps and
                                              the EPA.

Flood Control    Tom Fayram                  All maintenance work is complete. Will complete hauling
                 (Maintenance)                material this week.



Flood Control    Tom Fayram                   Aerial hydromulching fixed winged work will be done on
                 (Engineering)                 Tuesday. Helicopter has a couple more days of work.
                                              Debris racks are complete.
                                              Fremont Creek culvert – contractor will be pouring concrete
                                               floor today.
                                              K-Rail work – Granite will start October 20, work should be
                                               completed in 10 days.


Transportation   Dace Morgan                 Shoring up steel piles on both sides of bridge. Set to start
County of SB                                  pounding this week. Bridge should be completed by next
                                              Tuesday.
                                             Tierra was hired to clean out Glenn Annie culvert.

OES, County      Jay McAmis                  Not present
of SB
Public Works     Dave Rickard                Not present
Department
City of Goleta   Rosemarie                   Granite to start work on culvert modifications on San Pedro and
                 Gaglione                     Las Vegas @ Stow.
                                             Will be grinding down 7.6” at Calle Real.
                                             Winchester bid opening is on Wednesday.

City of Santa    Karen                       Not present
Barbara          Ramsdell
Airport
City of Santa    Pat Kelly                   P&S has submitted a permit to the City for a CDP – will have
                                                                                              st
Barbara                                       permit by Friday. Bid opening will be on Oct. 21 , Board will
                                                               rd
Goleta           Jeff Salt                    award on Oct. 23 . Will issue a notice to proceed on November
                                               st                             rd
Sanitation                                    1 . Work should start on Nov. 3 and be completed in 25
District                                      working days.
                                                             45
                                 Jeff asked about the status of the MOU. The Sanitation District
                                  does not want more than 25% exposure of unknown risk. Board
                                  feels that risk should be split between County and Cities – but
                                  ultimately it doesn’t matter to them who splits the remaining risk.
                              
DWR          Mitra               No report

Caltrans     Lance Gorman        Not present


State OES    Donald              Not present
             Cardenas/Dave
             Gillings
USFS         Jeff Benson         Not present
                              
NRCS         Dan Little          Not present

Dave Kanno   Goleta Water        Will be grading around the treatment and also hydromulching
             District             about 9 acres.
                                 Minor work to provide backup for water.


Adjourn: Next meeting on Monday, November 3, 2008 @ 10:00 a.m. in the Flood Control
Conference Room




                                                46

								