Designing an Ethylene Plant Control Room
                   and
         Operator User Interface
          Using Best Practices


                  J. Errington
              NOVA Chemicals Inc.
                    I. Nimmo
          User Centered Design Services

       Prepared for presentation at 2001 Annual Meeting, Houston, Texas.

      Copyright  Jamie Errington, NOVA Chemicals Corp, Joffre, AB and
                  Ian Nimmo, User Centered Design Services
 Acknowledgements
     The authors wish to acknowledge the support of:
        – Tim DeMaere - NOVA Chemicals Inc.
        – Peter Bullemer - Honeywell Technology Center




Copyright                                 2
                                                         01/03/20
 Objective & Outline
     Objective:
        – Outline the design process and results of NOVA Chemicals’ E3
          Manufacturing Building and User Interface



     Presentation Outline
        – Background
        – Overview of ASM (Abnormal Situation Management) and Best Practices
        – E3 Manufacturing Center
            • Building Location
            • Building Design
        – E3 User Interface




Copyright                                 3
                                                                           01/03/20
 Background
     Ethylene 3
        –   2.8 Blbs/y - ethane cracker
        –   project kick-off 1997
        –   mid-2000 startup
        –   located in Joffre Alberta, Canada
        –   joint venture between NOVA Chemicals and Union Carbide


     Designing for Abnormal Situation Management
        – AIChE paper presented in 1998 at New Orleans
        – Described how NOVA Chemicals was applying ASM Best Practices
          information to the design of new facilities




Copyright                                  4
                                                                         01/03/20
 Joffre Opportunity in 1998
     Concurrently Building New Facilities
        – Utilities Plant Expansion
        – Ethylene 3
        – Polyethylene 2
     Training Simulators
        – E3
        – PE2
     Exposure to ASM - AEGIS Prototype
     Management Support of ASM program




Copyright                               5
                                             01/03/20
 ASM - Abnormal Situation Management
     Consortium of companies and university affiliates:
        – NOVA Chemicals, Exxon/Mobil, BP/Amoco, Shell, Chevron, Texaco,
          Celanese, Union Carbide, Phillips
        – Honeywell (IAC, HTC)
        – BAW
        – Purdue, Ohio State, University of Toronto
     NOVA Chemicals joined in 1994




Copyright                                6
                                                                           01/03/20
 Goals of the ASM Consortium
     Reduce preventable process upsets by 90%
     Understand the problem
        – Site Surveys
     Develop better methods for aiding operators during process disruptions
        – AEGIS prototype
     Improve other Supporting Systems
        – Collateral Studies
        – Other technology Deliverables




                         Not by Technology alone!



Copyright                                 7
                                                                         01/03/20
 ASM Best Practices
     Compiled from extensive site reviews across a wide spectrum
      including:
        –   Training
        –   Procedures
        –   Tracking and Reporting
        –   Communication Systems
        –   Work Context and Environment




Copyright                                  8
                                                                    01/03/20
 Control Centre Location
     Goal
        – “to build a control center that will enhance the human performance in and
          around the control room”
     Location Design Process
        – literature survey
        – multi-discipline team examined alternative locations
        – evaluated on cost, impact on people, safety implications, business issues
     Review Solutions
        – remote - centralized control building - multiple plants
        – centralized control building within battery limits
        – individualized distributed control buildings
     Selection
        – individual distributed control buildings
     Driving forces
        – communications within unit
        – higher personnel safety
Copyright                                     9
                                                                                 01/03/20
 Manufacturing Building
     Goal
        – to enhance how the manufacturing team (Operations, Maintenance and
          Technical) control system works together in and around the control system
     Building Design Process
        – Created design vision for the building
        – Interviewed primary users at adjacent Joffre units for needs and
          requirements
        – Iterative process to refine key elements and share vision
     Key components
        – control room was the center of focus
        – communication patterns in the control room and the building
        – determined adjacency matrix
             • prioritized the layout and size of rooms
             • task segregation (permitting, meetings, etc.)
             • traffic flow patterns
        – control console layout

Copyright                                        10
                                                                                01/03/20
 E3 Control Room




Copyright          11
                        01/03/20
 User Interface
     The goal of the User Interface Design is to improve operator access to
      information thereby improving plant performance.
     Principal design aspects which have been considered in the design
      were:
        – Navigation
        – Visual Coding
        – Alarm Information
            • live alarms
            • AOA design information
        – Control Information
            • cascades
            • critical / redundant instrumentation
        – Trend Information
        – On-line Documentation




Copyright                                        12
                                                                          01/03/20
 User Interface

                         Status View
                                             Alarm
                                             Summary
              Level 1


                  Operations View
              Level 2                            Level 3
                    TagNam
                    e        SP
                             PV
                             OP        Level 4




Copyright                         13
                                                           01/03/20
 User Interface
     Status View
        – Level 1 - Area Overview
        – Alarm Summary
     Operations View
        – Level 2 - Unit Summary
        – Level 3 - Sub-unit
        – Level 4 - Group Displays




Copyright                            14
                                          01/03/20
 Status View




Copyright      15
                    01/03/20
            Operations View




Copyright                     16
                                   01/03/20
Task- and System-based model integration
     Research Project
        – University of Toronto / Honeywell/ NOVA and ASM Consortium
     Task Modelling
        – focus on the user’s tasks, plans and goals
     System Modelling
        – functional structure of the plant or system
        – captures the physical and chemical principles




Copyright                                   17
                                                                       01/03/20
 Conclusion
     Manufacturing building design has been successful
     User interface design is a bold step that will get even better with new
      developments
        – online information,
        – new modelling approaches, and
        – faster computers




Copyright                                 18
                                                                            01/03/20

				