Monthly Status Report
Project Name: Project Manager: Project Sponsor: Project Owner: ITS Manager: Project Description: REGIS Planning William O’Brien Laura King Tim Stoddard Joanne Chabot Reporting Period: July 23rd, 2009 Actual Proj. End Date: Jun. 30th, 2009
REGIS is both a framework to promote integrated business planning and a program that will make more efficient and effective, the manual and electronic processes related to student registration from first click to final payment. This project : 1. Defines an executable strategy for the REGIS program (completed, July/August 2008), 2. Develops a plan to implement the REGIS program (completed, July/August 2008), and The project scope has been changed to now create a business case (or cases) for Single Registration and Single Billing / Payment, two of the “Students First” priorities identified during combined planning meetings of the REGIS and ISS (Integrated Student Services) steering committees. Single Registration and Single Bill / Payment includes accounts receivable (AR) enhancements and integrated displays (for student and business office) for reporting financial aid, and will transform the AR module of ISRS into a Java (J2EE) web application. A 2nd element is to create a business plan for the first implementing project: REGIS-Phase I (Backbone).
Executive Summary
Status
Green (Controlled) Yellow (Caution) Red (Critical) Blue (Complete) Schedule
Description
Reason for Deviation
Estimated project end date has been moved to June 30, 2009, to reflect business case planning for Single Registration and Single Bill / Payment. The project timeline has been revised.
Combined ISS-REGIS planning sessions developed “Students First” priorities of Single Registration and Single Bill / Payment. These priorities were determined to fall within the scope of the REGIS program. See revised Timeline (attached) See Reason for Schedule Deviation.
Scope
There has been both program and project scope impact from Students First planning meetings on March 24-25, April 9, and May 12. REGIS Planning project budget is funding the Students First planning sessions and Single Registration and Single Bill / Payment planning.
Budget
Comments:
The REGIS Steering Committee met at Quarry Center (Waite Park) on July 29 & 30, 2008. Development priorities were broken into 4 phases. Resource constraints delayed further planning prior to the Students First planning sessions and resulting development priorities.
07/31/2009
Monthly Status Report
Page 1 of 5
Minnesota State Colleges and Universities
New/Updated Issues
Issues
Status (New, Newly Completed)
Mitigation Plan
Pre-April 2009 Migration Plan: 1. Late-March/early April: BAs define highlevel stories from the sixteen Phase 1 project components. 2. Early April: REGIS Steering Committee (a Finance-ASA cross-divisional group) meets to confirm the scope for the REGIS-Phase I project. Steering committee determines priority for at least the “top 5” stories, to be targeted for initial development and deployment. 3. Early April: Project planning team will complete a business case for REGIS Phase 1 project to be considered by the EIC for FY2010 funding.
Planning resource constraints: Due in part to the delay in the Rdb to Oracle migration, maintenance and other development projects, ITS business analysts (BAs) have not been available to support the REGIS planning project as originally envisioned. NOTE: The deadline for submitting project business cases (to be considered for FY2010 funding) to the PMO for IT review will likely be sometime in May or June, 2009.
No longer applicable to the project (see issue below)
4. April – June: Detailed planning business
requirements for “top 5” stories of REGIS – Phase 1 project.
Students First, a combination and expansion of the REGIS and ISS (Integrated Student Services) steering committees, met on March 24-25, April 9, and May 12 to discuss collaboration / integration between the two groups and their development project priorities.
Newly completed
The results of the Students First planning meetings have modified / broadened the scope of the original REGIS – Phase 1 project that is now labelled Single Registration and Single Bill / Payment.
Milestones / Deliverables
Milestones/Deliverables
Estimated Completion Date Feb - Mar, 2008
Actual Completion Date July, 2008
Status (On Schedule, Complete, At Risk) Complete
Create a plan defining the strategy of how best to implement the REGIS Program.
07/31/2009
Monthly Status Report
Page 2 of 5
Minnesota State Colleges and Universities
Identification of a REGIS Steering Committee with representation from all channels impacted (i.e., process, policy or technology change) with clear role definition. Validate, reject or modify the initial hypothesis for this strategy which focuses on development of an integrated, web-based core processing functionality--a critical path (backbone). Creating a prioritized list of component projects based on the validated strategy. Revised: Components grouped into possible projects, and the projects were prioritized Analysis of remaining paths of REGIS and determining appropriate order for implementation. Revised: Components grouped into possible projects, and the projects were prioritized Preliminary analysis of policy and/or technology implications for prioritized list of component projects. Note: ISS steering committee to work on strategy for policy implications of first REGIS implementation project, REGIS – Phase 1 (Backbone). REGIS planning group determined to use JAVA 2 Platform, Enterprise Edition (J2EE) as the platform and programming language for REGIS-related project development. Determine how component projects will be managed with respect to the overall REGIS Program. This likely would involve a Program Manager for the REGIS component projects and the REGIS Steering Committee. NEW: Initial Meetings of Students First, the combined and expanded ISS-REGIS Steering Committees REVISED: Focus on "Students First" Priorities for Single Registration & Single Bill / Payment REVISED: EIC Meeting: Review of Single Registration & Single Bill / Payment preliminary planning REVISED: Further Students First planning for Single Registration & Single Bill / Payment
Feb - Mar, 2008
July, 2008
Complete
Feb - Mar, 2008
July, 2008
Complete
Feb - Mar, 2008
July, 2008
Complete
Feb - Mar, 2008
July, 2008
Complete
April, 2008
August,2008
Complete
August, 2008
No longer valid for this project March 24-25 and April 9, 2009
Late
March 24-25 and April 9, 2009
Complete
April 10 thru May 3, 2009
April 10 thru May 3, 2009
REVISED: Complete
May 4, 2009
May 4, 2009
REVISED: Complete
May thru mid-June, 2009
May thru mid-June, 2009
REVISED: Complete
07/31/2009
Monthly Status Report
Page 3 of 5
Minnesota State Colleges and Universities
REVISED: Determine how Single Registration & Single Bill / Payment will be managed with respect to the overall Students First program. This likely would involve a Program Manager for these programs /projects. REVISED: Initial Iteration Planning for Single Registration & Single Bill / Payment REVISED: REGIS Planning targeted project completion date
mid-May thru June 30, 2009
mid-June, 2009
REVISED: Complete
mid-May thru July, 2009
mid-May thru July, 2009
REVISED: Complete
June 30, 2009
June 30, 2009
REVISED: Complete
Project Assumptions and Dependencies
Assumptions
The REGIS Steering Committee will be the decision makers for this program. (assumption is valid until determined otherwise by the joint
meetings of the REGIS and ISS steering committees in March and April, 2009)
There will be (system-wide) support for the REGIS Program and the plan that is developed for its implementation. (assumption is valid) All channels will continue support for creating a seamless, integrated, web-based experience for students for the entire registration-to-payment process (dependent on EIC support) Availability of steering committee members. (no impact on project
planning)
Dependencies
Availability of Business Analysis resources. (project was significantly
delayed due to ITS Staff constraints)
Authorization level of REGIS Steering Committee (no longer
applicable to project)
07/31/2009
Monthly Status Report
Page 4 of 5
Minnesota State Colleges and Universities
REGIS Planning REGIS Program and “Students First” Priorities: Single Registration & Single Bill / Payment
3/24/09 to 3/35/08 “Students First”, combined REGIS and ISS Steering Committees, Planning Meeting 5/4/09 EIC Meeting: Review of Draft Project Planning 6/1/09 EIC Meeting: Review of Draft Project Planning 6/30/09 REGIS Planning Project Completion Date 7/31/09 End of Initial Iteration Planning for Students First Single Registration & Single Bill / Payment
3/5/09 Begin RdB to Oracle Migration
4/9/09 Students First Planning Meeting
5/12/09 Students First Planning Meeting
6/4/09 Single Registration & Single Bill / Payment Initial Iteration Planning Meeting
2/1/09 1/1/2009 1/1/09 - 3/16/09 Resource Constraint: ITS BA Support for Rdb to Oracle Conversion
3/1/09
4/1/09
5/1/09
6/1/09
7/1/09 7/31/2009
4/10/09 - 5/10/09 5/13/09 - 6/3/09 Initial Planning for Additional Students First" Planning for Priorities of Single Registration Single Registration & Single Bill & Single Bill / Payment / Payment
6/5/09 - 7/31/09 Iteration Planning for Single Registration & Single Bill / Payment
Page 1
07/31/2009
Monthly Status Report
Page 5 of 5