TADIPUDI LIFT IRRIGATION SCHEME

Document Sample
TADIPUDI LIFT IRRIGATION SCHEME Powered By Docstoc
					                  TADIPUDI LIFT IRRIGATION SCHEME




                                                                                                                             80.45 KM
                                                                     L1      L2           L3         L4
GODAVARI                                                            KM 5   KM 15.90     KM 33.50    KM 80
 RIVER
                       0.00 KM

            1st   Pump House, Pressure Mains, Cistern : Progress
                                                                            Lift Height             : 27.00 Mts
            2nd Pump House, Pressure Mains             : Progress
                                                                            Pumps                  : 6 Nos. of 4,000 HP
                                                                            each
            Main Canal                                 : Progress
                                                                            Discharge              : 700 Cusecs.
              Lift Pumps, Pump Houses, Pres. Mains : Designs
            2nd
            &Drawings                                Under                  Agreement Date         : 23-1-2004
            Approval                                                        Present Stage          : work in progress
            Utilisation : 14.40 TMC                                         Length of the canal    : 80.45 Km.
            Ayacut       : 2,06,600 Acres
                                                                            Ayacut                 : 2,06,572 Acres
                                                                            Power required         : 28 MW
                                              DELIVERY                      Tender Amount          : Rs. 302.64 Cr.
                        PUMP
                                              CISTERN
                        HOUSE
                                                                    MAIN   CANAL
 GODAVARI
  RIVER
                                                       0.00 KM




                                                                                                                        80.45 KM
                                                                     L1      L2           L3         L4
                              PSC PRESSURE                          KM 5   KM 15.90     KM 33.50    KM 80

    TADIPUDI (V)               MAINS (2 x 6
                                   Nos.)
(WEST GODAVARI (DT))
                                                                                                      PROGRESS

             4 Nos. of 3,000 HP each
             For each pump house (2 Pump houses)
              TADIPUDI LIFT IRRIGATION SCHEME
1   PROJECT PROFILE : Located near Tadipudi (V) of West Godavari District about km 26.20
                          upstream of SACB, Dowlaiswaram
                                                         1)Rs. 132.00 Crs.,(G. O. Ms. No. 127, Dt: 27-8-
                                                         03
2   Administrative Sanction Rs. 295.80 Crs.          : 2) Rs. 105 Crs G., O. Ms. No. 9, Dt: 20-1-2004
                                                         3) Rs. 58.40 Crs.,G. O. Ms. No. 13, Dt: 20-1-
                                                         2005
    No. of EPC Packages (2 old packages + 2 new
3                                                    : 4 Nos
    packages)
4   Agreement value of 4 packages                    : 302.65 Crs.
    Budget provision for 2006-
5                                                    : Rs.100 Crs.
    07
6   Expenditure of the project
                                           2004 – 05 : Rs. 48.06 Crs.
                                           2005 – 06 : Rs. 43.11 Crs.
                                 Cum. Exp.           : Rs. 91.17 Crs
7   Utilisation                                      : 14.47 TMC
    Drinking water                                   : 5.3 lakh population
8   Ayacut                       By gravity          : 1,38,000 acres
                                 By lift             :   68,600 acres
Lift-I @ Km 5.0
             Lift Height            : 21.305 M
             No. of Pumps           : 1 No.
             Total pumps capacity   : 1 x 370 HPs
Lift-II @ Km 30.25
             Lift Height            : 23.13 M
             No. of Pumps           : 2 Nos.
             Total pumps capacity   : 2 x 510 HPs
Lift-III @ Km 39.45
             Lift Height            : 24.108 M
             No. of Pumps           : 3 No.
             Total pumps capacity   : 3 x 900 HPs
Lift-IV @ Km 80.891
             Lift Height            : 12 M
             No. of Pumps           : 3 Nos.
             Total pumps capacity   : 3 x 1230 HPs
Power required                      : 23 MW
10   Land Acquisition

                        Required             : 2047 acres


                        Acquired             :   733 acres


12   Estimated cost of L.A.                  : Rs.41.51 Crs


13   Mob. Advance (Rs. in Crores.)               Paid         Recovered

                                     2004-05 : 15.04             5.34

                                     2005-06 : 3.15               --

                                      Total : 18.19              5.34
            TADIPUDI LIFT IRRIGATION SCHEME


                                                                                      Name of the
PKG                                                 Agt. Value &        Agt.           contractor
                     Description
No.                                                     Date           Period


 1    Supply, commissioning of pumping              Rs. 30.47 Cr      18 Months    M/s KBL Ltd, Pune
      machinery construction of pump house,         Dt: 23-1-2004
      delivery cistern, 1st pump house


 2    Supply, commissioning of pumping               Rs. 30.81 Cr     18 Months    M/s NCC Ltd, Hyd
      machinery construction of pump house,          Dt: 22-07-04
      delivery cistern, 2nd pump house

 3    Execution of main canal from KM 0.0 to        Rs. 178.36 Cr     24 Months   M/s Maytas Infra Ltd,
      Km 80.450 to irrigate an ayacut of 1,38,000   Dt: 04-10-2004                       Hyd
      Acres

 4    Construction of 4 Nos. of Lift Irrigation      Rs. 63.00 Cr.    18 Months     M/s Unity Infra
      Schemes (II lift), commissioning of           Dt:. 09-04-2005               projects Ltd, Mumbai
      pumping machinery, construction of
      pump house
                 TADIPUDI LIFT IRRIGATION SCHEME
Pkg.No.     : Pump house – I, supply and                        Name of the Contractor      : M/s. Kirloskar Brothers
                                                                Ltd.
commissioning of pumping machinery, transformer,
substation raising main including construction of               Agreement Amount            : Rs. 30.48 Crs.
pump house and delivery cistern etc., at Km 26.200              Agreement Date              : 23-01-2004
on AGRB near Tadipudi (V), Tallapudi (M), West                  Mile stones                 :9
Godavari (D).                                                   Date of Completion          : 3/2006
    Investigation                       : Completed
    Designs approved                    : 30 Nos. against 40 Nos.
    Structures approved                 : 2 Nos. against 3 Nos.
    Execution (laying pressure mains)   : 12 Kms length against 16 Kms
                 Pumps                   : All 4 Nos. at site

                 Pump houses             : Completed
                 Cistern                 : Completed
                 Lifts                   : Lift Completed
Pressure mains                           : 5 Nos completed against 6 Nos

    Qty. of concrete work done          : 5550 cum against 6000 cum
    No. of Machinery                    : 7 Nos. (3 Cranes, 4 Tippers)

    Expenditure                         :    2004-2005                              - Rs. 12.70 Crs.
                                              2005-2006                              - Rs. 12.14 Crs.
                                              Cum. Inc. Mob. Adv. only               - Rs. 24.84 Crs.
    LA                                  : Required 722.78 acres, acquired 434.44 acres
                 TADIPUDI LIFT IRRIGATION SCHEME
Pkg.No. : Pump House – II,            supply and           Name of the Contractor    : M/s. Nagarjuna Cont.
commissioning of pumping machinery, transformer,           Co.,
substation raising main including construction of          Agreement Amount          : Rs. 30.81 Crs.
pump house and delivery cistern etc., at Km 26.250         Agreement Date            : 22-07-2004
on AGRB near Tadipudi (V), Tallapudi (M), West             Period of completion      : 24 Months (8 Mile
Godavari (D).                                              Stones)
                                                           Target date of Completion : 6/2006
      Investigation                         : Completed
      Designs approved                      : 27 Nos. against 40 Nos.
      Structures approved                   : 2 Nos. against 3 Nos.
      Execution (laying Pressure mains) : 6 Kms length against 16 Kms
                   Pumps                     : All 4 Nos. of pumps at site
                   Pump house                : work is in progress in 1 pump house
                   Pressure mains            : 2 Nos. against 6 Nos. laid
                   Cistern                   : Completed
                   Lifts                     : work commenced.
      Qty. of concrete work done            : 2500 cum against 3500 cum.
      No. of Machinery                      : Deployed 3 Nos. of Cranes
      Expenditure                           :           2004-2005                       - Rs. 9.09
       Crs.
                                                         2005-2006                       - Rs. 9.41
       Crs.
                                                         Cum. Inc. Mob. Adv. only        - Rs. 18.50
                 TADIPUDI LIFT IRRIGATION SCHEME
Pkg.No. : Execution of main canal Km 0.00 to 80.45        Name of the Contractor   : M/s. Mytas Infra Projects Lt
and its distributaries, FCs including CM & CD works       Agreement Amount         : Rs. 178.36 Crs.
complete to irrigate an ayacut of 1,38,000 acres          Agreement Date           : 04-10-2004
(appr.)                                                   Period of completion     : 24 Months (8 Milestones
                                                          Date of Completion       : 10/2006


     Investigation                  : Completed

     Designs (Canal)                : 60.45Kms. against 80.45Kms

      Structures                     : 20 Nos. against 216 Nos.

     Execution (Canal)              : 13 Kms length against 80.45 Kms

     Qty. of earth work done        : 16.21 Lakh cum against 1,00,00,000 cum

     Qty. of concrete work done : 13,600 cum

     No. of Machinery               : 60 Nos. (12 executers, 30 tippers, 5 tractors, 5 dozers etc)

     Expenditure                    :        2004-2005                        - Rs. 26.27 Crs.
                                              2005-2006                        - Rs. 17.21 Crs.
                                              Cum. Inc. Mob. Adv. only         - Rs. 43.48 Crs Land
      Acquisition                    : Required 796.33 acres, acquired 112.62 acres
                  TADIPUDI LIFT IRRIGATION SCHEME
Pkg.No. : Construction of 4 Nos. of LI Schemes (II stage)     Name of the Contractor    : M/s. Unity Infra Projects Ltd
at KM 5.00, KM 15.90, KM 33.50 and KM 80.80 of main           Agreement Amount          : Rs. 63.00 Crs.
canal of Tadipudi LIS. Supply installation, testing and
                                                              Agreement Date            : 09-04-2005
commissioning of pumping machinery transforms,
substations,    raising   mains,     approach     channels,   Period of completion      : 16 Months
construction of pump house, pressure mains one, delivery
system, electrical works etc., and excavation of main canal
and distributaries FCs including construction of CM & CD
works etc.,

 Investigation                       : Completed

 Designs                             : In progress

 Execution                           : 5 KM against 200 Km

 Laying of pipe line                 : Pump house 1 No. against 4 Nos., Pressure mains : 1 No.
     against                                                  4 Nos., Cistern : 1 No. against 4 Nos., Lift
     1 No. against 4 Nos.

 No. of Machinery                    : 5 (Crane-1 No., Tippers – 4 Nos.)

 Expenditure                         : 2005-2006 - Rs. 4.35 Crs. Inc. Mob. Adv. only


      Land acquisition               : Required 401 acres, acquired 20 acres

				