Docstoc

Water Tank Demo Request For Bid

Document Sample
Water Tank Demo Request For Bid Powered By Docstoc
					                          CAHILL CONTRACTORS, INC.                                 TELEPHONE
                                  CONTRACTING ENGINEERS                            (415) 986-0600
                                                                                        FAX
                                   425 CALIFORNIA STREET                           (415) 986-4406
                                  SAN FRANCISCO 94104-2277


01/21/09

WATER TANK DEMO AT MASONIC HOMES, Job #199
Mission Blvd, Union City, CA
                                   REQUEST FOR BID
Cahill requests Water Tank demo bids on: Tuesday February 3, 2009 at 2 pm.

Address & fax or email bids to:
          Cahill Contractors, Inc.            Attn: Mark Zaleski
          425 California Street, Suite 2200, San Francisco, CA 94104
          Phone: 415-986-0600           Fax: 415-986-4406
          Email: mzaleski@cahill-sf.com,

This is a Cahill job. Project located at Masonic Homes on 34400 Mission Blvd. in Union City,
94587 CA. Bid Scope includes demolition of an existing 200,000 gallon, concrete, in the
ground, open air, tank and associated site work. Eventually a new 450,000 gallon tank will
replace it. Subs are encouraged to view & download the documents off our ftp site which
currently has site photos, drawings for the new tank & as-builts mainly for the existing tank
to remain and a geotech soils letter.

Only the demo is bidding now. The geotech engineer requires additional soil investigation
under this existing tank to be demo’d to confirm his design requirements for the new tank.
Once this is confirmed (or not) and the new tank design finalized, the remaining scope will
be bid.

Hardcopy of the Bid documents including drawings will not be sent to the bidders. See
instructions below to download them from our ftp site.

For the demo scope focus on new tank drawings C5 & P1. Specific demo scopes:
Complete removal of the existing 200,000 gallon concrete tank.
Removal of some chain link w/ barb wire on top fencing as shown on C5.
Removal of “X” marked trees and their stumps as located on C5.
Removal of a shed including its slab & foundation (outlined but not labeled on C5).
Assume no abatement.
Obtain a “J” number if required.
Minimize potential for soil erosion on the tank site & the road access.
Assume no off haul of soil but leave any onsite in an orderly fashion.
Removal & cap (e) 6” outgoing irrigation line off the tank to be demo shown on P1.
Removal & temporarily cap (e) 6” incoming water line to demo’d tank on P1.
Any demo at vaults at details 1/P3 & 2/P3 is not included in this scope.
Removal of (e) 4” water line between the existing tanks & vault on P1.
Cap the existing 4” water line outside of the 400,000 gallon tank.
Provide own dust control.
REQUEST FOR BID – PAGE 2

General bid requirements:

1.    There will be a mandatory jobsite walk on Wednesday January 28, 2009 at 9 am at
      Cahill’s Acacia Creek job site trailor. We will have a brief discussion and then from
      there “cavaran” up to the water tank site.

2.    Deliver a detailed scope letter with your bid.

3.    There are no SBE/DBE/LBE requirements.

4.    Subcontract will be awarded on the standard Cahill Contractors, Inc. Subcontract
      Agreement form with exhibits. Copies will be provided if you are not familiar with it.

5.    Retention will be 10%.

6.    Maximum allowable mark-up for overhead & profit on Change Orders will be 15%.

7.    All hoisting & hoist rigging shall be the Subcontractor's responsibility.

8.    Sub’s primary liability insurance cannot have residential construction exclusion.

9.    Certificate of Insurance will be required for the construction work. Minimum
      insurance limits are required as follows:
                 Subcontract Amount Minimum Insurance Limits
                          0 - $ 100,000       $1,000,000 Insurance
                 $100,001 - $ 499,999         $2,000,000 Insurance
                        Over $500,000         $5,000,000 Insurance (preferred)

10.   Subcontractors are responsible to furnish their own flagmen & traffic control as
      required for their work.

11.   Subcontractors are responsible for their own clean up & for hauling their debris
      properly offsite. Should a subcontractor fail to cleanup after themselves on a daily
      basis, Cahill reserves the right to perform the cleanup and back charge the
      subcontractor.

12.   Schedule: Demo work to be performed starting in February ’09 and ending in March
      ’09 pending weather and owner authorization to proceed.

13.   All Subcontracts shall include all Contract Documents as listed in the attached
      Contract Document List - Exhibit A, dated 01/21/09.

14.   All subcontracts shall include the attached Environmental, Health and Safety (EHS)
      Requirements - Exhibit B, dated 01/21/09.

15.   For overtime authorized by Cahill, Cahill will pay the actual premium costs only. No
      additional overhead & profit will be allowed on overtime premium costs. Subs should
      include the straight time & premium time rates for all trades in their employ.

                                                              CAHILL CONTRACTORS, INC.
       REQUEST FOR BID – PAGE 3


16.   The owner will provide parking area on their premises. Overflow parking will not be
      adjacent the construction site but near the main entrance gate of the facility.

17.    A complete set of plans & specifications are available in our main office.
      Plans & specs are available electronically on our FTP site. Access instructions are:
            o Go to www.fordgraphics.com
            o Click on Northern California.
            o On the left-hand column, select “FTP”, and then “San Francisco, Mission
               Street”.
            o The Login is: cahill, and the Password is 8136.
            o Click “Page” then “Open FTP site in Windows Explorer”.
            o Click “Masonic Water Tank”.

18.   See attached Exhibits A, B & C that will be incorporated into all subcontracts.

19.   A Liquidated Damages clause may be included in all subcontracts.

20. All labor is to be Union. Subcontractors are advised that Cahill Contractors, Inc. is a
     union contractor signatory to the carpenters & laborers union, & requires that all
     subcontractors utilizing these crafts or falling under the jurisdiction of these unions
     also be signatory to the applicable unions.

21. The owner will provide the general building permits. Subcontractors are responsible to
     provide & pay for any other permits & fees necessary for completion of their work.

22.   On project award, Cahill will not provide additional plans or specs to subcontractors
      unless prior arrangements have been made in writing. Subcontractors & suppliers
      are responsible for obtaining all necessary construction documents at their cost.

23.   Bids are to be firm prices for the duration of the project. Escalation will not be
      allowed. This applies to all tiers of subcontractors & suppliers.

24.   Bidders must note any & all exceptions that are being taken to the plans & specs,
      particularly any exclusion which would be assumed as being included with the
      bidder’s trade.

25.     The following paragraph will be included in the subcontract standard requirements:
       “Subcontractor shall indemnify Contractor from and against any liability, damages,
       losses and expenses incurred by reason of claims by third parties, including Owner,
       arising out of or related to the presence or existence of toxic or non-toxic mold, at,
       upon or in the Project Site, to the extent caused by Subcontractor.”

26.   There is no OCIP, owner’s wrap insurance policy on this project.

27.   Subcontractors are required to submit any deviation (IB, Addendum, RFI, Bulletin,
      etc.) pricing within ten (10) working days of receipt of the change in construction
      documents. Any pricing submitted after (10) working days will not be accepted and
                                                            CAHILL CONTRACTORS, INC.
      REQUEST FOR BID – PAGE 4


      costs associated with implementing the change in work will be borne by the
      subcontractor.

28.   Subcontractor shall furnish shop drawings as required, free of charge, for approval &
      use by the General Contractor. Number of drawings required shall be reasonably
      determined by the General Contractor. Subcontractor is to verify all reference
      measurements or other dimensions designated to be field measured before ordering
      materials or proceeding with the work.

29.   Subcontractor has closely inspected existing job site conditions that affect their work,
      and has included in his contract price all work, adjustments, or revisions necessary to
      provide a complete job as shown or called for in the Contract Documents. Change
      Orders will not be allowed for conditions that were clearly apparent at bid time.
      Work of this contract is expected to start immediately with design, followed by
      construction per the attached schedule and should be priced accordingly. Bidders
      are assumed to be knowledgeable of this type of work and shall include all normal
      requirements to produce a complete project ready for its intended use as described
      by these documents.
      The Contract Documents are presented as complete and with the intention to
      provide a complete project. Any errors, discrepancies or omissions shall be brought
      to Cahill Contractor's attention prior to bid. Any bid qualifications must be related to
      a document conflict and/or omission and must be specifically spelled out in Bid
      Proposal.
      It is the intent of Cahill Contractor's, Inc. to provide a complete and operational
      building. We will not accept change orders for requirement conflicts in/or between
      the plans and/or specifications, manufactures installation requirements, or
      applicable codes. All subcontractors and suppliers are required to call our attention
      to potential conflicts or items included in the specifications that are not intended to
      be provided. Bids received with no qualifications/exclusions will be assumed to be in
      strict accordance with both the plans and specifications. Bidders are required to list
      all specification sections included in the applicable bid proposal. Bids will be
      assumed to include the entire specification sections referenced unless there are
      corresponding exclusions. Bidders are required to make a site tour and become
      familiar with the site and existing conditions prior to bidding.

30.   Cahill's Superintendent is authorized to order premium time work to expedite the
      schedule. The premium time so ordered will not be "extra work" but will be directed
      only to expedite completion of the work contracted for. Cahill's Superintendent will
      authorize the work and must sign daily - acknowledgment of hours worked. Cahill
      will pay the actual cost of premium time for the work so directed. Additional mark
      up of premium time, labor based equipment charges, etc., will not be paid.

31.   The Subcontractor agrees to defend, indemnify and hold Cahill Contractors, Inc.
      harmless from or against any claim, damage, liability or expense, including
      reasonable attorney's fees, the Owner, Subcontractor or Cahill Contractors, Inc. may
      sustain arising out of, or during, or as a result of the Subcontractor's use of any
      scaffolding, regardless of who has rented or erected this scaffolding, notwithstanding
                                                           CAHILL CONTRACTORS, INC.
      REQUEST FOR BID – PAGE 5


      the fact that the claim, loss, damage, liability or expense may arise wholly or in part
      out of the negligence of Cahill Contractors, Inc., its officers, or employees. The
      Subcontractor agrees to indemnify Cahill Contractor, Inc. as listed above, regardless
      of the fact that the Subcontractor's personnel or material men may have utilized any
      scaffolding with or without Cahill Contractors, Inc.'s permission.

32.   Cahill is not furnishing any line and grade elevations.

33.   The subcontractor shall notify Cahill immediately if they discover that work
      performed by another trade is not installed per the contract documents. The
      subcontractor shall not continue to install their work if they are aware that this work
      will not allow another trade to correct their deficiencies, if any.

34.   The General Contractor is not furnishing any temporary power. Temporary water shall
      be furnished at a single location at the Acacia Creek jobsite. Locations shall be
      determined by the General Contractor. Subcontractors are responsible for furnishing
      their own temporary electrical distribution, task lighting and ventilation as necessary
      beyond that provided by Cahill.

35.    If a subcontractor removes or modifies temporary barricades or railings installed by
      others, then it is the subcontractor's responsibility to reinstall the barricades or railings
      in such a manner as to maintain a safe working area. If additional
      barricades/railings are required by a subcontractor's work, they shall be that
      subcontractor's responsibility to furnish & install.




                                                               CAHILL CONTRACTORS, INC.
                                                                         TELEPHONE
                          CAHILL CONTRACTORS, INC.                       (415) 986-0600
                                CONTRACTING ENGINEERS                         FAX
                                                                         (415) 986-4406
                                 425 CALIFORNIA STREET                  www.cahill-sf.com
                               SAN FRANCISCO, CA 94104-2277



Job 199: Masonic Homes Water Tank Demo, Union City, CA

                                   EXHIBIT A

                           DOCUMENT LIST 01/21/09

1.   Civil drawings dated 11/26/08 prepared by RJA & Associates: C1, C2, C3, C4
     & C5.

2.   Survey drawing not dated, not labeled.

3.   Structural drawings dated 11/26/08 prepared by Murphy Burr Curry: S1.0, S2.0 &
     S2.1.

4.   Plumbing drawings dated 11/26/08 prepared by Gerber Engineering: P1, P2 &
     P3.

5.   Various “As-Built” drawings of the existing water tank to remain

6.   Geotech Letter dated 1/15/09 prepared by Engeo, Inc.

                            End of Document List




Cahill Contractors, Inc                                                     1
                            CAHILL CONTRACTORS, INC.                                   TELEPHONE
                                    CONTRACTING ENGINEERS                              (415) 986-0600
                                                                                            FAX
                                     425 CALIFORNIA STREET                             (415) 986-4406
                                    SAN FRANCISCO 94104-2277




               JOB #199 – MASONIC HOMES WATER TANK DEMO, UNION CITY
                              LABOR RELATIONS
                                     EXHIBIT B
                                     01.21.09

Subcontractor acknowledges that Contractor has entered into labor agreements covering
work at its construction job sites with the labor unions listed in Article "T" and incorporated
herein by reference.

Subcontractor agrees to comply with all of the terms and conditions of those labor
agreements including signatory status if required. Subcontractor further agrees to make trust
fund payments into the respective labor trust funds set forth in the respective labor
agreements referenced in Article "T", insofar as Subcontractor may lawfully do so.
Subcontractor agrees to comply with the terms and provisions of said agreements setting
forth the jurisdiction and scope of work therein for resolution of jurisdictional disputes. In the
absence of any such procedure or if such procedure fails to promptly resolve the jurisdictional
dispute, Subcontractor agrees, at its own cost and expense and upon request by Contractor,
to take any and all lawful steps to secure a binding and final determination of said
jurisdictional dispute by the National Labor Relations Board.

Subcontractor acknowledges that terms and conditions of the labor agreements with the
unions listed in Article "T" may require that Subcontractor comply with additional labor
agreements with unions affiliated with the AFL-CIO but not listed therein. When the terms and
conditions of the referenced labor agreements so require, Subcontractor shall perform its job
site work pursuant to all terms and conditions of an appropriate labor agreement with a union
affiliated with the AFL-CIO.

Should there be picketing on Contractor's job site and the Contractor establishes a reserved
gate for Subcontractor's purpose; it shall be the obligation of Subcontractor to continue the
proper performance of its work without interruption or delay.

Subcontractor further promises and agrees that it will bind and require all of its subcontractors
and their subcontractors performing job site work of the type covered by any of the labor
agreements specified in Article "T" to agree to all of the foregoing promises and undertakings,
to the same effect as herein provided with respect to Subcontractor.

Subcontractor shall comply with all equal employment opportunity and affirmative action
requirements promulgated by any governmental authority, including, without limitation, the
requirements of the Civil Rights Act of 1964, Presidential Executive Orders No. 10925, 11114 and
11246, the California Fair Employment Practices Act and the Americans with Disabilities Act of
1991. Subcontractor shall comply with and agrees to be bound by all applicable Federal,
State and local laws and regulations, including, but not limited to, all Fair Labor Standards Act
provisions and California Labor Code provisions covering the work. Upon request,
Subcontractor agrees to submit certified payroll reports to Contractor no later than three (3)
working days after labor has been paid.
                                                                                         EXHIBIT C
                   JOB# 199 – MASONIC HOMES WATER TANK DEMO, UNION CITY
                                                  01.21.09

             ENVIRONMENTAL, HEALTH, & SAFETY (EHS) REQUIREMENTS

1.   General

A.   Subcontractor agrees to comply with:

     1.   All applicable EHS rules, regulations, policies, procedures and guidelines when performing work in
          facility or site. EHS Laws in the United States of America (US) include, but are not limited to: the
          Occupational Safety and Health Act (OSHA); Title 8, California Code of Regulations (CAL-OSHA);
          the Resource Conservation and Recovery Act (RCRA); the Uniform Fire Code (UFC) and Uniform
          Building Code (UBC) as adopted by the local jurisdiction; and, the Hazardous Materials and
          Transportation Act (HMTA).

     2.   Contractor’s Injury and Illness Prevention Program (Safety Program) or Subcontractor’s Injury and
          Illness Prevention Program (Safety Program), whichever is more stringent. Refer to California Code
          of Regulations, Title 8, Section 1509.

B.   Subcontractor agrees to submit to Contractor’s project manager copies of all appropriate safety
     related documents to include but not limited to Subcontractor Injury and Illness Prevention Program
     (Safety Program), safety meetings minutes, accident investigation reports, Material Safety Data Sheets
     (MSDS), and workers compensation insurance claims. Subcontractor will notify Contractor within four (4)
     hours of any accident(s) requiring medical care, worker’s compensation claims, first-aid administered,
     near misses or any EHS or potential liability issues and assist in the necessary accident investigation. The
     accident investigation will document all facts related to the incident for future reference and establish
     a corrective action to prevent future major accidents. Subcontractor will identify the competent
     person responsible for monitoring EHS requirements on site. The competent person shall be
     knowledgeable in EHS rules, regulations, policies, procedures and guidelines and have the authority to
     mitigate hazards relative to subcontractor’s operations.

2.   Subcontractor agrees that it is solely responsible for ensuring that its employees, agents, suppliers and/or
     sub-subcontractors (“Subcontractor’s Employees”) performing Work on Facility do so in accordance
     with Subcontractor’s EHS Program, all applicable EHS Laws, and Specific Requirements.

     1.   Subcontractor agrees to attend all required job site safety meetings and to respond promptly to
          all safety-related issues that affect subcontractor’s work and other trades’ work which may be
          derivative of subcontractor’s work. Subcontractor agrees to have at least one (1) employee or
          agent at the job site at all times who speaks and understands English with ease when safety
          meetings are held and who will disseminate the safety information to said subcontractor’s
          employees and agents. Subcontractor also agrees to have an English-speaking and
          understanding employee or agent readily-accessible when safety issues are discussed, which may
          arise at any time during the work day.

3.   Subcontractor agrees to allow Contractor, to monitor, audit and inspect Subcontractor operations for
     compliance with all the terms of this Addendum.

     1.   Agrees to notify Contractor of any observed noncompliance with any requirement of this
          Addendum that is within the responsibility or control of the Subcontractor.


                                                                                         Please        Initial
EHS Requirements – Page 2



     2.   Subcontractor agrees that work may stop if Contractor, in its sole judgment, determines that
          noncompliance may present a risk of an incident, accident, injury, illness or a violation of EHS Laws.

     3.   Subcontractor agrees to take immediate action to correct any noncompliance that may present
          a risk of an incident, accident, injury, illness or a violation of EHS Laws.

     4.   Should Subcontractor discover an unsafe condition on facility, Subcontractor shall immediately
          notify the Contractor and take immediate action to correct any such condition that is under or
          within the responsibility or control of the Subcontractor.

     5.   Subcontractor agrees that should Subcontractor’s Employee(s) fail to take immediate action to
          correct any noncompliance. Subcontractor shall, at request of Contractor, exclude the
          noncompliant Subcontractor’s Employee(s) from facilities until such time as Subcontractor
          provides evidence of compliance that in Contractor’s sole judgment, is determined to be
          sufficient.

4.   Subcontractor and all associated suppliers, office personnel, delivery personnel or anyone visiting the
     site shall wear an American National Standards Institute (ANSI) approved hard hat.

     1.   Anyone not complying with this requirement will be removed from the site.

     2.   At the sole discretion of the Contractor site superintendent, the hard hat requirement may be
          modified when conditions permit. For example, when above ceiling work is complete. Employees
          working in protected areas may not be required to wear hard hats. When workers leave
          protected areas on site, the hard hat program will once again be enforced. The use of hard hats
          and the identification/determination/designation of protected areas are at the sole discretion of
          the site superintendent.

     3.   Subcontractor will supply their own ANSI approved hard hats. If Contractor supplies hard hats for
          the use of Subcontractor’s employees, these hard hats will be charged to Subcontractor at a rate
          of fifteen dollars ($15.00) per hard hat.

5.   Subcontractor agrees that failure to follow EHS requirements as stated in this Exhibit to the subcontract
     agreement will result in the following action by the Contractor:

     1.   The first incident will result in a verbal warning by the Contractor’s superintendent on site.

     2.   The second incident will result in a letter sent to Subcontractor by Contractor’s project manager.
          This letter will refer to the lack of response to verbal warning given by Contractor site
          superintendent and describe the EHS requirements.

     3.   The third incident will result in a second letter sent to Subcontractor by Contractor’s project
          manager. This second letter will result in a deductive change order in the amount of five hundred
          dollars ($500.00) and/or termination of contract.




                                                                                        Please        Initial

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:5
posted:2/25/2012
language:
pages:9