					  P10005 Balence Training Video Game Team
                                                                                  Weekly Status Report MSD I : WEEK 2
                                                                             Submitted:

                                                                                             Team Members
                                                             Rochelle Perry
                                                             Mike Davies

Major Milestone chart(Milestones from 11 Week Schedule)
                           Task                         Responsible Member
Benchmarking                                                      All
Overall Balence Training                                Rochelle/All
Previous Projects                                       All
Games                                                   Andy/Jeff
Team Values and Norms                                             All
Add changes                                             Rochelle
Approval from DeBartolo- Team Values and norms          All
Risk Assessment                                                   All

assign risks to owners                                       Jeff
change spreadsheet to excel                                  Rochelle
Work Breakdown Structure                                                  All
Create baseline to be modified by team                                 Rochelle
Add schedule                                                           Rochelle
Customer Needs                                                            All
Customer Interaction                                                      All
Approval from Dr. DeBartolo                                               All
Engineering Specs                                                         All
Hardware/ergonomic component                                       Mike/Jeff/Rochelle
software component                                                       Andy
Approval from Dr. DeBartolo                                               All
Ideal and target values                                                   All
Team Evaluations                                                          All
Rubric for Team Evals                                                  Rochelle
Needs vs. Engineering Specs                                  All
Concept generation                                           All
first cut concept generation
Approval from JJ                                             All
Brainstorming                                                All
Concept Screening-target                                     Jeff
Concept Screening-structure                                  Luke/Mike
Concept Screening-game                                       Andy
Concept selection                                            All
Concept Improvement                                          All
Evaluation of hardware interface                             Mike/Luke
Approval from JJ
System Analysis
Engineering analysis                                         Luke
Ergonomic analysis to fit patient                            Luke
Customer Needs translated to system-level functional specs   All- WBS
functional specs flow down to engineering specs              All- WBS
ideal/marginal target values                                 All-WBS
Identify Risks                                               All
System Design
Block diagram
flow chart
Math models
interface clearly defined
Risk Assessment
Target-cost                                                    Jeff
Target-Refresh rate, software, hook ups ( hardware,            Jeff
Target-Durability, mobility                                    Jeff
Structure-cost                                                 Luke/Mike
Structure-Refresh rate, software, hook ups ( hardware,         Luke/Mike
Structure-Durability, mobility                                 Luke/Mike
Computer- cost                                                 Andy
Computer-software                                              Andy
Computer- hardware                                             Andy
Scope
Detailed design plan/strategy
Sensor hardware                                                Jeff
Team Values and Norms Reevaluation
Bill of Materials
Complete - long lead time items known
Complete- producers identified
Drawing Schematics
Drawing of parts to be custom made are complete
Assembly drawing complete
Feasibility of consturcution known
Feasibility Anslysis
Analysis to demostrate feasibiity of all systems and
Appropriate links to risk assessment activities are complete
Risk Assessment
Target-cost                                                    Jeff
Target-Refresh rate, software, hook ups ( hardware,            Jeff
Target-Durability, mobility                                    Jeff
Strurcture-costs                                               Luke/Mike
Structure-Refresh rate, software, hook ups ( hardware,         Luke/Mike
Structure-Durability, mobility                                 Luke/Mike
Computer- cost                                                 Andy
Computer-software                                              Andy
Computer- hardware                                             Andy
Scope
Detailed design plan/strategy
Sensor hardware                                                Jeff
Final list of Customer Needs
Final list of Specifications
Final costs and BOM
Detailed Test plan
Detailed Design Review!
Project Management Review
Schedule for MSD II                                            All
Weekly Status Report MSD I : WEEK 2
    =DATE()

              Team Members
    Luke Holsen                          Andy Caola
    Jeff Hansley


       Expected Date           c           Date Completed
               9/18/2009                           9/25/2009
               9/18/2009                           9/25/2009
               9/18/2009                           9/25/2009
               9/18/2009                           9/25/2009
               9/15/2009                           9/15/2009
               9/18/2009                           9/18/2009
               9/18/2009                           9/18/2009
               9/18/2009                           9/25/2009

               9/25/2009                              9/25/2009
               9/25/2009                              9/23/2009
               9/25/2009     10/1/2009
               9/19/2009                              9/19/2009
               9/25/2009
               9/25/2009                              9/25/2009
               9/18/2009                              9/22/2009
               9/25/2009                              9/25/2009
               9/25/2009                              9/25/2009
               9/23/2009                              9/23/2009
               9/23/2009                              9/23/2009
               9/25/2009                              9/25/2009
               9/25/2009     10/2/2009
               9/27/2009                              9/29/2009
               9/25/2009                              9/23/2009
               9/25/2009     9/29/2009                9/29/2009
               9/25/2009     9/29/2009
               9/25/2009     9/29/2009                9/29/2009
               9/30/2009
               9/30/2009                              9/30/2009
               9/30/2009     10/6/2009                10/6/2009
               9/30/2009     10/6/2009                10/6/2009
               9/30/2009     10/6/2009                10/6/2009
               10/2/2009                              10/2/2009
               10/2/2009       13-Oct
               10/2/2009       13-Oct
                               13-Oct
              10/13/2009
              10/16/2009
              10/16/2009
              10/16/2009
              10/16/2009
              10/13/2009
              10/16/2009
               10/9/2009
 10/9/2009
 11/5/2009
 11/5/2009
 11/5/2009
 11/5/2009
 11/5/2009
 11/5/2009
 11/2/2009
 11/2/2009
 11/2/2009
 11/6/2009
 11/5/2009
10/20/2009
 10/9/2009
 11/6/2009
10/30/2009
10/30/2009
 11/6/2009
10/30/2009
10/30/2009
10/30/2009
 11/6/2009
 11/3/2009
 11/3/2009
 11/6/2009
 11/5/2009
 11/5/2009
 11/5/2009
 11/5/2009
 11/5/2009
 11/5/2009
 11/2/2009
 11/2/2009
 11/2/2009
 11/6/2009
 11/5/2009
10/20/2009
11/13/2009
11/13/2009
11/13/2009
11/13/2009
 11/6/2009
11/20/2009
11/20/2009
Main goal
Breakdown of of we can accomplish
Completed
Almost Complete
Critical



                                                   Comments
Split up by major below


posted on edge
Our changes need to be added and approved by DeBartolo


See "weekly assignment" for details of who is responsible weekly



Needs to extend the current one past Week 3 and we need to discuss our best method of displying the information,

Page two of this document- added after concept generation

Populate google doc with questions for JJ so she can answer them over the weekekend




Still need to update some components


posted as a google doc!

need to add in more concepts
done after lecture


need to add more of the brainstorming concepts
Completed, simple to run, motion capture mapping, history of users, games, visual and sound cues, fixable,
Memory, graphics, processor speed, hook ups, ( not complete)

define what each need to do and feasibility assessed




Completed, simple to run, motion capture mapping, history of users, games, visual and sound cues, fixable,
Memory, graphics, processor speed, hook ups, ( not complete)

define what each need to do and feasibility assessed
Reminders
If you insert a column make sure you insert a column in the schedule tab or everything will be off!
Comments
     Main goal              Complete                                        2 2 2 2 2 2 2 3 3
     Critical Path          Almost                                          M T WR F S U M T




                                                                            9/16/2009
                                                                            9/15/2009
                                                                            9/16/2009
                                                                            9/17/2009
                                                                            9/18/2009
                                                                            9/19/2009
                                                                            9/20/2009
                                                                            9/21/2009
                                                                            9/22/2009
                                                             Date
                            Responsib Expected Moldified Complete
             Task           le Member     Date    Deadline    d
 1 Benchmarking                 All     9/18/2009          9/25/2009
   Overall Balence          Rochelle/Al
 2 Training                 l           9/18/2009          9/25/2009
 3 Previous Projects        All         9/18/2009          9/25/2009
 4 Games                    Andy/Jeff   9/18/2009          9/25/2009
   Team Values and
 5 Norms                       All        9/15/2009             9/15/2009
 6 Add changes              Rochelle      9/18/2009             9/18/2009
   Approval from
   DeBartolo- Team
 7 Values and norms         All           9/18/2009             9/18/2009
 8 Risk Assessment                 All    9/18/2009             9/25/2009
 9
10 assign risks to owners   Jeff          9/25/2009             9/25/2009
   change spreadsheet to
11 excel                    Rochelle      9/25/2009             9/23/2009
   Work Breakdown
12 Structure                       All    9/25/2009 10/1/2009
   Create baseline to be
13 modified by team          Rochelle     9/19/2009             9/19/2009
14 Add schedule              Rochelle     9/25/2009
15 Customer Needs              All        9/25/2009             9/25/2009
16 Customer Interaction        All        9/18/2009             9/22/2009
   Approval from Dr.
17 DeBartolo                       All    9/25/2009             9/25/2009
18 Engineering Specs               All    9/25/2009             9/25/2009
   Hardware/ergonomic       Mike/Jeff/R
19 component                 ochelle      9/23/2009             9/23/2009

20 software component             Andy    9/23/2009             9/23/2009




     Approval from Dr.
21   DeBartolo                 All        9/25/2009           9/25/2009
22   Ideal and target values   All        9/25/2009 10/2/2009
23   Team Evaluations          All        9/27/2009           9/29/2009
24   Rubric for Team Evals   Rochelle     9/25/2009           9/23/2009
25   Needs vs. Engineering All            9/25/2009 9/29/2009 9/29/2009
26   Concept generation          All          9/25/2009   9/29/2009
27   first cut concept                        9/25/2009   9/29/2009 9/29/2009
28   Approval from JJ            All          9/30/2009
29   Brainstorming               All          9/30/2009             9/30/2009
30   Concept Screening-          Jeff         9/30/2009   10/6/2009 10/6/2009
31   Concept Screening-          Luke/Mike    9/30/2009   10/6/2009 10/6/2009
32   Concept Screening-          Andy         9/30/2009   10/6/2009 10/6/2009
33   Concept selection           All          10/2/2009             10/2/2009
34   Concept Improvement         All          10/2/2009      13-Oct
35   Evaluation of hardware      Mike/Luke    10/2/2009      13-Oct
36   Approval from JJ                                        13-Oct
37   System Analysis                         10/13/2009
38   Engineering analysis        Luke        10/16/2009
39   Ergonomic analysis to       Luke        10/16/2009
40   Customer Needs              All- WBS    10/16/2009
41   functional specs flow       All- WBS    10/16/2009
42   ideal/marginal target       All-WBS     10/13/2009
43   Identify Risks              All         10/16/2009
44   Approval from JJ                        10/19/2009
45   System Design                            10/9/2009     16-Oct
46   Block diagram                                          16-Oct
47   flow chart                                             16-Oct
48   Math models                                            16-Oct
49   interface clearly defined                              16-Oct
50   Risk Assessment                          10/9/2009
51   Target-cost                 Jeff         11/5/2009
52   Target-Refresh rate,        Jeff         11/5/2009
53   Target-Durability,          Jeff         11/5/2009
54   Structure-cost              Luke/Mike    11/5/2009
55   Structure-Refresh rate,     Luke/Mike    11/5/2009
56   Structure-Durability,       Luke/Mike    11/5/2009
57   Computer- cost              Andy         11/2/2009
58   Computer-software           Andy         11/2/2009
59   Computer- hardware          Andy         11/2/2009
60   Scope                                    11/6/2009
61   Detailed design                          11/5/2009
62   Sensor hardware             Jeff        10/20/2009
63   Approval from JJ                        10/26/2009
     Team Values and                          10/9/2009
64   Bill of Materials                        11/6/2009
65   Complete - long lead                    10/30/2009
66   Complete- producers                     10/30/2009
67   Drawing Schematics                       11/6/2009
68   Drawing of parts to be                  10/30/2009
69   Assembly drawing                        10/30/2009
70   Feasibility of                          10/30/2009
71   Feasibility Anslysis                     11/6/2009
72   Analysis to demostrate                   11/3/2009
73   Appropriate links to risk                11/3/2009
74   Risk Assessment                          11/6/2009
75   Target-cost                 Jeff         11/5/2009
76   Target-Refresh rate,        Jeff         11/5/2009
77   Target-Durability,          Jeff         11/5/2009
78   Strurcture-costs            Luke/Mike    11/5/2009
79   Structure-Refresh rate,     Luke/Mike    11/5/2009
80   Structure-Durability,       Luke/Mike    11/5/2009
81   Computer- cost           Andy    11/2/2009
82   Computer-software        Andy    11/2/2009
83   Computer- hardware       Andy    11/2/2009
84   Scope                            11/6/2009
85   Detailed design                  11/5/2009
     Sensor hardware          Jeff   10/20/2009
     Final list of Customer          11/13/2009
     Final list of                   11/13/2009
     Final costs and BOM             11/13/2009
     Detailed Test plan              11/13/2009
     Detailed Design                  11/6/2009
     Project Management              11/20/2009
     Schedule for MSD II      All    11/20/2009
9/23/2009
9/24/2009
9/25/2009
9/26/2009
9/27/2009
9/28/2009
9/29/2009
9/30/2009
10/1/2009
10/2/2009
10/3/2009
10/4/2009
10/5/2009
10/6/2009
10/7/2009
10/8/2009
10/9/2009
10/10/2009
10/11/2009
10/12/2009
10/13/2009
10/14/2009
10/15/2009
10/16/2009
10/17/2009
10/18/2009
10/19/2009
10/20/2009
10/21/2009
10/22/2009
10/23/2009
10/24/2009
10/25/2009
10/26/2009
10/27/2009
10/28/2009
10/29/2009
10/30/2009
10/31/2009
11/1/2009
11/2/2009
11/3/2009
             3 3 3 3 3 3 4 4 4 4 4 4 5 5 5 5 5 5 5 6 6 6 6 6 6 6 7 7 7 7 7 7 7 8 8 8 8 8 8 8 9 9 9




11/4/2009
             WR F S U M T WR F S U M T WR F S U M T WR F S U M T WR F S U M T WR F S U M T W
11/5/2009
11/6/2009
11/7/2009
11/8/2009
11/9/2009
11/10/2009
11/11/2009
11/12/2009
11/13/2009
11/14/2009
11/15/2009
11/16/2009
11/17/2009
11/18/2009
11/19/2009
11/20/2009
11/21/2009
11/22/2009
11/23/2009
11/24/2009
             9 9 9 9 # # # # # # # # # # # # # # Break




11/25/2009
11/26/2009
             R F S U M T WR F S U M T WR F S U M T WR F




11/27/2009
                     Finalize Design and documentation, MSD II Readiness
                                      Finalize Design and documentation, MSD II Readiness
              Task                  Week 2     Week 3              Week 4
Team Evaluations                               All
Weekly Status Update                Rochelle   Rochelle            Rochelle-finish
Risk Management                     Rochelle   Jeff                Luke
Notes at Team Meeting               Andy       Mike Friday 11am    Rochelle
Notes at Friday Meeting             Andy       Luke-meet w DBalo   Jeff
Notes at Meeting with DeBartolo                                    Mike
Notes at customer Visit                                            Rochelle



Post to edge


customer needs/engineering specs
concept generation - Luke


brainstorming in a node with
Notes from today's meeting - Jeff


Notes from meeting with DeBartolo
Week 5     Week 6     Week 7   Week 8          Week 9
           All                                 All
Rochelle
Rochelle   All
Jeff       Rochelle            Andy
Mike       Mike                Mike
Andy       Luke                Jeff
                               Rochelle/Luke
Week 10   Week 11
                                                                                            P10005 Balance Training Device

                                                                                                     Bill of Materials                                                                                          put project number on receipt and description


                  Part Name             Material    Manuf.     Manufact Manufa    Distributor   Distributor Part Quantity   Unit    Total       Quant   Unit Price   Total   Lead   Owner   Status   Comments
                                                    Method       urer    cturer                        #         Needed     MFG     MFG          ity                 Price   Time
                                                                        Part #                                              Time    Time        Order
                                                                                                                            (hrs)   (hrs)        ed
Electrical
Structure
What else




                                                                    Totals                                                                  0           $      -
             * Shipping Not Included
                           Legend
                                         Ready to order
                                       Know what needs to
                                       Do not know all info.
                WBS



   ME          Systems        Electrical



Structure                Game         Target
              Users
              Manual
                          ?          Material
Material
              Ease of
               Use
Calculation


 System
 Design

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:5
posted:2/15/2012
language:
pages:28