					              SOUTH FLORIDA WATER MANAGEMENT DISTRICT

   LIMITED TO THOSE FIRMS PREQUALIFIED UNDER “CONTRACTOR PRE-QUALIFICATION; SOUTH FLORIDA WATER
                    MANAGEMENT DISTRICT CONSTRUCTION PROJECTS, RFQ 6000000213”
 BIDS SHALL BE ACCEPTED FROM CONTRACTORS PRE-QUALIFIED FOR: FLOW CONTROL STRUCTURE IN THE $500,000-
                           $2,000,000 AND ABOVE RANGE ONLY FOR THIS PROJECT.
 REQUEST FOR BIDS (RFB)                                           Number: 6000000316
                                                                  Issue Date: November 16, 2009

       GATE OPERATOR REPLACEMENT AND CONCRETE
 Title: S-60
 REPAIRS, OSCEOLA COUNTY, FLORIDA
 Direct all Inquiries in Writing to:                              Inquiry Period:
 Senior Contract Specialist: Bonnie Batchelor                     From November 16, 2009 to November 24, 2009
 Phone No.        (561) 242-5520 ext. 4057
 Fax No.          (561) 682-5319                                  Dollar Range: $695,000.00 to $770,000.00
 E-Mail:          bbatchel@sfwmd.gov
                                                                  Small Business Enterprise (SBE) Utilization: 25%
 Inquiries must reference Contract: 6000000316

                                                                  Bid Equalization Percentage: 5%
                                                                  See SBE Guidelines & Information
 An Optional pre-bid conference will be held:                     Liquidated Damages to Substantial Completion:
 TIME:    10:00 a.m.                                              $1,000.00 Per Day plus all efforts required by the Contractor to
 DATE:    Thursday, November 19, 2009                             insure that the structure has a flow capacity of 450 cfs.
 PLACE: Onsite at S-60: From Florida Turnpike: Exit               Liquidated Damage from Substantial to Final Completion:
 242 to US192; East on US192 to County Road 534                   $500.00 Per Day
 (CR 534); South on CR 534 to South Florida Water
 Management District Canal 33 (SFWMD C33); North
 on the SFWMD C33 East Levee to S-60.
  For directions call 561-307-4457.
                                                                  CONTRACT TIME:
       A SITE VISIT WILL IMMEDIATELY FOLLOW                       Substantial Completion May 1, 2010
                                                                  * Final Completion June 1, 2010
                                                                  *Includes punchlist work and close out documentation.
                                          Deadline For SEALED Bid Submission:

              THURSDAY, DECEMBER 3, 2009 - 2:30 P.M.
                               One (1) Original and One (1) Copy of the Bid Required
                       Confirmation of timely receipt of bid may be made by calling (561) 682-6391.
               Bid results and official award information may be obtained 24 hours a day by calling the 24-hour
                                        BID HOTLINE (800) 472-5290 or (561) 682-6391.
                Bids Must Be Submitted to the                         BIDS MUST BE SUBMITTED IN A SEALED PACKAGE AND
                      Following Address:                              MARKED WITH THE CONTRACT NUMBER AND TITLE, AND THE
            South Florida Water Management District                   BIDDER'S NAME AND ADDRESS. THE DISTRICT WILL NOT
                 Attn: Procurement Department                         ACCEPT BIDS THAT ARE NOT SUBMITTED IN ACCORDANCE
              B-1 Building, 3301 Gun Club Road                        WITH THESE INSTRUCTIONS.
                  West Palm Beach, FL 33406
                                                       Document Availability:
  Contract Documents will be available after 8:30 a.m. on the Issue Date, in the SFWMD Procurement Office, call (561) 682-6391 for
                                                               directions.
 Attachments:                                                         Solicitation Costs:
 Drawings Numbered: 1-36                                              Not applicable
 List of SBE Subcontractors
 Lead Testing Report for S-60

REQUEST FOR BIDS                                                                                                  00001-1
                          PROJECT DESCRIPTION:
CONTRACT TITLE:                S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS,
                               OSCEOLA COUNTY, FLORIDA
CONTRACT NUMBER:               6000000316


   Project Description:
   This project involves replacing existing stem operator system with a Cable Drum Hoist System; concrete repairs to
   the abutment walls and slab; sandblast and recoat all four steel sheet pile wing walls replace reinforced concrete
   operator platform with prefabricated cable drum hoist system and steel platform; dewatering; provide dry and wet
   season by pass requirements; replace and add staff gauges upstream and downstream; and add stainless steel plating at
   the weir crest and along all corners of the gate recess; and painting.

   Directions:
   From Florida Turnpike: Exit 242 to US192; East on US192 to County Road 534 (CR 534); South on CR 534
   to South Florida Water Management District Canal 33 (SFWMD C33); North on the SFWMD C33 East
   Levee to S-60.

   For directions call 561-307-4457.




REQUEST FOR BIDS                                                                                       00001-2
                       SUPPLEMENTAL CONDITIONS:
The Supplemental Conditions are provided, if necessary, to clarify, revise or amend the terms and conditions of the Instructions to Bidders,
General Terms & Conditions and Bid Form for this particular project. Refer to the specific paragraph noted. Bidders are encouraged to
read the following conditions carefully. Failure to comply with these conditions may cause the bid to be declared non-responsive.

00700 - GENERAL TERMS & CONDITIONS:

Article 4.01. District shall furnish the Site. Must remain within the limits of construction and the District’s Right-Of -Way.
 Article 4.02.A. Subsurface and Physical Conditions. The Lead Testing Report (DPS Corp S-60 LBP Survey) is part of the Bid Solicitation
as a referenced document.

Article 4.06.A. Hazardous Environmental Condition at Site. Not Applicable.

Article 5. Bonds and Insurance Requirements. Bidders are reminded to read Article 5 regarding the minimum requirements of the bonds.
Bidders must use the bond forms enclosed herein. Specific insurance limits are included in the Insurance Requirements Checklist attached
herein. South Florida Water Management District shall be listed as additional insured for General Liability and Auto Liability.

Article 5.02.A Performance & Payment Bonds. Bidders must use the bond forms enclosed herein.

Article 5.05 Licenses. Item 1, Certified General Contractor.

Article 6.06. Concerning Subcontractors, Suppliers, and Others. Bidders are strongly encouraged to verify, with Florida's Secretary of
State, the corporate status and standing of all subcontractors they will be utilizing to ensure the firm’s ability to do business in the state of
Florida.

Article 6.08. Permits. The District has obtained/ is obtaining the following environmental permit(s) for this project:
          a.      FDEP – NGP (Notice General Permit) (requested)
          b.      USACE Section 404 Permit (obtained)

In the event the permits are not obtained prior to bid opening, the District has the option of holding the bids for an additional ninety (90)
days after bid opening.

Article 6.13. Safety. Item C. Not Applicable.

Article 7.02. Coordination. Not Applicable.

Article 14. Payments to Contractors and Completion.

Requirements for Substantial Completion and Final Acceptance are to be found in the General Terms & Conditions and in Section 01700
of the General Requirements.

Delete: General Terms and Condition – Article 1 Definitions/Interpretations Paragraph 54 and Replace with the following –
“Substantial Completion: As Part of the Project Substantial Completion, but not exclusive to, the structure shall be flow
capable as of May 1, 2010. The time at which the Work (or a specified part thereof) has progressed to the point where, in the
opinion of DISTRICT, the Work (or a specified part thereof) is sufficiently complete, in accordance with the CONTRACT
Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is intended and shall begin
the warranty period. The terms "substantially complete" and "substantially completed" as applied to all or part of the Work
refer to Substantial Completion thereof.”

Article 20. Partnering. Item A.


SUPPLEMENTAL CONDITIONS                                                                                                             00002-1
Article 29. Davis Bacon Act. Not Applicable.

Article 30. Copeland Act. Not Applicable.

01010 – TECHNICAL SPECIFICATIONS:

Use of District Standard Details and Guideline Drawings:

Users of District Standard Details and Guideline Drawings are advised that the users are responsible for the function and safety of the
intended facilities. Any changes must be approved by the District. District approval does not relieve the user of their responsibility.

    1.   Clarification: Drawing No. C002B; Sheet 31 of 36; Suggested Dewatering Scheme; Note 5: This note is a Contractual
         Requirement. This note is not a suggested item. This note pertains to the entire Project.

    2.   Clarification: Drawing No. C002B; Sheet 31 of 36; Suggested Dewatering Scheme; Note 5: Delete current Note 5 “Install
         pumps to maintain a minimum bypass flow capacity 200 CFS to Substantial Completion of May 1, 2010. After May 1,
         2010 the Contractor shall provide an additional 250 CFS at the contractor’s expense.” and replace with “Install pumps
         to maintain a continuous minimum bypass flow capacity of 200 CFS throughout the Project to Substantial
         Completion date of May 1, 2010. As of May 1, 2010 the structure shall be flow capable. If the structure is not flow
         capable which means the Substantial Completion date has not been met, then As of May 1, 2010 the Contractor shall
         furnish, install, and have in operation A Total Flow Capacity of 450 CFS at the Contractor’s expense.”

    3.   Clarification: Technical Specifications: 02401: Dewatering and Cofferdam: 3.05 A1: By-Pass: This paragraph is a
         Contractual Requirement and pertains to the entire Project.

    4.   Clarification: Technical Specifications: 02401: Dewatering and Cofferdam: 3.05 A1: By Pass: Delete the current By-Pass
         Paragraph “The Contractor shall maintain a pump bypass capacity of 200 CFS, To Substantial Completion of May 1,
         2010. After May 1, 2010 The Contractor shall Provide An additional 250 CFS at the Contractor’s expense.” and
         replace with “The Contractor shall maintain a pump bypass capacity of 200 CFS throughout the Project to Substantial
         Completion Date of May 1, 2010. As of May 1, 2010 the structure shall be flow capable. If the structure is not flow
         capable which means the Substantial Completion date has not been met, then as of May 1, 2010 the Contractor shall
         furnish, install, and have in operation a total flow capacity of 450 CFS at the Contractor’s expense.”

    5.   Clarification: All bypass requirements shall apply when the structure is inoperable due to the contractual gate
         operator replacement and the concrete repairs.

    6.   Clarification: Appendix A is an attachment to the Technical Specifications and part of the Contract Documents.

    7.   Technical Specifications: Table of Contents: DELETE: “02435” Environmental Protection. ADD: “02436” Environmental
         Protection.

    8.   Technical Specifications: 01010: Summary of Work: 1.09 A.1: Contract Drawings: DELETE: …“1-36”… REPLACE:
         …“1-23 and 30-36”.

    9.   Technical Specifications: 01010: Summary of Work: 1.09 A.2: Contract Drawings: ADD: … (6 sheets) “Drawing Sheets
         24-29”. Reference Drawings are provided “as is”.

    10. Clarification: Technical Specifications: 01010: Summary of Work: 1.07 C.1: The date specified of June 1, 2010 is the
        Final Completion Date.




SUPPLEMENTAL CONDITIONS                                                                                                    00002-2
                             TABLE OF CONTENTS
BIDDING AND CONTRACT REQUIREMENTS

INVITATION TO BID:
00001-1-2   RFB Information & Project Description
00002-1-2   Supplemental Conditions
00003-1-2   Table of Contents
00050-1     Request for Bid

SBE GUIDELINES:
00060-1-2   SBE Guidelines & Information

INSTRUCTIONS TO BIDDERS:
00100-1-5  Instructions to Bidders

BID FORMS:
00310-1       Bid Forms Checklist (Item 1)
00320-1-4     Bid Form (Item 2)
00330-1-2     Bid Bond (Item 3A)
00341-1       Statement of Intent to Perform as a SBE Subcontractor (Item 4A)
00342-1       SBE Subcontractor Participation Schedule (Item 4B)
00350-1       Statement of Business Organization (Item 5)
00370-1       Affidavit of Non-collusion and Non-interest of DISTRICT Employees (Item 6)
00380-1       Trench Safety Act (Item 7)
00400-1       Statement of No Response (Item 8)

CONTRACT:
00500-1   Sample Contract

INSURANCE AND BOND FORMS:
00600-1    Insurance Requirements Checklist
00610-1-2  Common Law Performance Bond
00620-1-2  Statutory Payment Bond
00630-1-2  Affidavit for Surety Company

GENERAL TERMS & CONDITIONS:
00700-1-2    Table of Contents
00700-2-1-40 General Terms & Conditions

POST AWARD FORMS:
00900-1    Table of Contents
00910-1-2  Notice of Apparent Low Bidder
00920-1    Notice to Proceed
00930-1    Schedule of Values
00935-1    Stored Materials
00940-1-4  Application for Payment/Contractor's Affidavit
00950-1    SBE Utilization Report – Exhibit “E”
00955-1-2  Contractor’s Periodic Performance Evaluation
00960-1    Shop Drawing Submittal
00965-1    Request for Information
00970-1-2  Change Order

TABLE OF CONTENTS                                                                          00003-1
00980-1     Certificate of Substantial Completion
00990-1     Certificate of Final Acceptance
00994-1     SBE Final Subcontractor Utilization Report – Exhibit “F”
00995-1-2   Contractor's Affidavit and Final Release
00996-1     Consent of Surety to Final Payment

TECHNICAL SPECIFICATIONS - INDEX

TECHNICAL SPECIFICATIONS

SBE CONTRACTORS LIST

LEAD TESTING REPORT FOR S-60




TABLE OF CONTENTS                                                      00003-2
                     REQUEST FOR BID 6000000316
   LIMITED TO THOSE FIRMS PREQUALIFIED UNDER “CONTRACTOR PRE-QUALIFICATION; SOUTH FLORIDA WATER
                    MANAGEMENT DISTRICT CONSTRUCTION PROJECTS, RFQ 6000000213”.
 BIDS SHALL BE ACCEPTED FROM CONTRACTORS PRE-QUALIFIED FOR: FLOW CONTROL STRUCTURE IN THE $500,000-
                           $2,000,000 AND ABOVE RANGE ONLY FOR THIS PROJECT.

The South Florida Water Management District will receive sealed bids through the Procurement Office, B-1 Bldg.,
3301 Gun Club Road, West Palm Beach, Florida 33406, for S-60 Gate Operator Replacement and Concrete
Repairs, Osceola County, Florida, on Thursday, December 3, 2009 at 2:30 p.m. local time, at which timely
submitted bids will be opened and publicly read. The bid can be obtained by downloading a free copy of the
solicitation from the District web site www.sfwmd.gov, by obtaining a CD at the above address or by calling (561)
682-6391.

Refer to "Instructions to Bidders" for more information on the bidding process. Bids must be accompanied by a bid
bond, cash or certified check made out to the South Florida Water Management District, or other security as
provided by law, in an amount not less than five percent (5%) of the total base bid. All questions about the
meaning/intent of the Contract Documents must be submitted in writing via mail or facsimile during the Inquiry
Period indicated on the cover page of this RFB, to the Senior Contract Specialist, Procurement Department, P.O.
Box 24680, West Palm Beach, Florida 33416-4680, fax (561) 682-5319. Questions will be answered in accordance
with Article 4 of the "Instructions to Bidders," replies will be given at a later date. The District reserves the right to
waive any informality, to reject any or all Bids, or to re-advertise for Bids. Award, if made, will be to the lowest
responsive and responsible bidder.




REQUEST FOR BID                                                                                                00050-1
       BID SBE GUIDELINES AND INFORMATION
The DISTRICT's Small Business Enterprise (SBE) Program is designed to help small businesses, including those owned by
women and minorities, to participate in DISTRICT procurement and contract activities. The purpose of the program is to spur
economic development and support small businesses, including women-owned and minority-owned businesses, to
successfully expand in the marketplace. Certain pre-bid requirements are defined herein. Failure to comply with these
requirements or to submit any of the information required herein shall result in a finding that the Bid is non-responsive and
will result in rejection of the Bid.

1.1       SBE Rule

The DISTRICT has implemented Chapter 40E-7, Part 6, F.A.C., the "Small Business Enterprise Contracting Rule" ("SBE
Rule"). The provisions of the Rule shall apply to all competitive solicitations for commodities, construction, professional and
other contractual services and any resulting contract documents including change orders, and amendments.

1.2       Minimum Goal

The DISTRICT has established a minimum SBE participation goal for this solicitation. The Bid shall either meet the
established SBE goal, or be deemed non-responsive.

1.3      Submission of SBE Subcontractor Utilization Plan

Any participation by firms not certified with the DISTRICT at the time of Bid submission will not count towards SBE goal
attainment. Bidders are strongly encouraged to contact the DISTRICT’s Small Business Enterprise Section at (561) 682- 6446
well in advance of the date set for receipt of Bids to allow sufficient time for review and determination of SBE eligibility and
certification.

A. Bidders shall identify all SBE firms which will be used as subcontractors in this Procurement. The Bid must contain
   proof that each firm to be utilized as a SBE prime or subcontractor is certified as a DISTRICT SBE. Each SBE
   subcontractor and prime shall be listed in the SBE Subcontractor Utilization Plan (as defined below) and shall be
   submitted with the Bid. The listing of SBE's in the SBE Subcontractor Utilization Plan attached with each Bid shall
   constitute the Bidder's representation to the DISTRICT that the SBE firms are technically and financially qualified and
   available to perform the assigned work. Failure to provide complete and accurate information shall result in the Bid being
   deemed non-responsive. In addition, in accordance with General Terms & Conditions, Article 6.06 the Prime Contractor
   must self perform at a minimum forty percent (40%) of the Work as defined by the General Terms & Conditions.

      The SBE Subcontractor Utilization Plan shall consist of the following documentation which must be attached to the Bid:

      1. The Statement of Intent to Perform as a SBE Subcontractor form, which confirms (1) the intent of the prime to
         establish a business relationship with each SBE subcontractor; and (2) the SBE participation percent. One form must
         be completed and signed by each proposed SBE subcontractor. The form Bidders must use to fulfill this requirement
         is attached to this solicitation. Provide proof that each proposed firm to be utilized as an SBE prime or subcontractor
         is certified by the DISTRICT.
      2. The SBE Subcontractor Participation Schedule form, which identifies all SBE firms which will be utilized as
         subcontractors, delineates the specific elements of work each SBE firm will be responsible for performing, and
         identifies the dollar value of the SBE work as a percentage of the total contract value. The form Bidders must use to
         fulfill this requirement is attached to this solicitation.

If the Prime Contractor is an SBE and is not subcontracting any portion of the work to another subcontractor, then the SBE
Subcontractor Participation Schedule Form and Proof of certification are all that are required to be submitted with the bid.
The Statement of Intent to Perform as a SBE Subcontractor Form will not be required.

If more subcontractors are utilized than space allows on the SBE Subcontractor Participation Schedule Form, a photocopy of
the page continuing the list will be acceptable.

SBE GUIDELINES & INFORMATION                                                                                       00060-1
1.4       Bid Equalization (if applicable – see RFB Cover Page)

Pursuant to the DISTRICT's SBE Rule, Bid Equalizations may be used by the DISTRICT to increase the participation of
available SBE’s in competitive contracting activity by creating a more level playing field when bids are submitted to the
DISTRICT.

The maximum Bid Equalization percent shall be determined by the estimated contract value and the dollar ranges as defined
below. For solicitations where it is determined by the DISTRICT to use bid equalizations, the DISTRICT shall implement a
one percent (1%), five percent (5%) and ten percent (10%) maximum Bid Equalization. In cases where the adjusted lowest
SBE firm’s responsive and responsible Bid does not exceed the lowest non SBE firm’s unadjusted responsive and responsible
Bid by the Bid Equalization percentage, the award shall be made to the lowest responsive and responsible SBE firm. Below is
an example of Bid Equalization:
                                Bid Equalization Example using 10% as Incentive Bonus

              Bid Incentive example               Lowest Non-Certified Firm               Lowest Certified SBE Firm
                       Bid                                $100,000                               $103,000 *
              Bid Equalization (10%)                          -0-                                <$10,300>
                    Tabulation                            $100,000                                 $92,700
                                                              Note:
        *In this example, the DISTRICT will pay the $103,000 award, with the difference between the $100,000 bid and
        the $103,000 bid, being the cost the DISTRICT is willing to incur to advance the SBE Program commitment.


      NOTE: Bid Equalization shall not apply to DISTRICT Procurements identified as Sheltered Market (see paragraph 1.5
      below) or when all bids received are from SBE firms.

1.5 Sheltered Market (if applicable – see RFB Cover Page)

      Pursuant to the DISTRICT's SBE Rule, the DISTRICT shall provide for Sheltered Markets. Sheltered Markets allow for
      only SBE firms to bid on designated solicitations. Sheltered Market shall be used by the DISTRICT to increase the
      participation of available SBE’s in competitive contracting activity; thereby increasing the capacity and expertise of SBE
      firms. The DISTRICT shall be guided to select sheltered market solicitations by selecting industries in which small
      businesses have usually not had an opportunity to compete.

1.6 – SBE Compliance and Substitution

The contractual provisions that will apply in the event of a contract award are delineated in Article 19 of the General
Terms and Conditions attached to this solicitation. The following is an excerpt of key aspects of Article 19.

A.      Compliance. The DISTRICT shall monitor and evaluate compliance with the provisions of the SBE Rule.
During the term of any subsequent contract, the CONTRACTOR shall comply with all SBE plans made in its bid.
Compliance for use of SBE’s shall include tasks and proportionate dollar amounts throughout the term of the contract,
including amendments and change orders. After CONTRACT execution, the CONTRACTOR shall maintain the level of
SBE participation established in the CONTRACT. Failure to comply with the SBE requirements of an awarded
CONTRACT can result in the DISTRICT enforcement any of the compliance provisions in the Rule and the attached
sample contract.

B.      SBE Substitution. The CONTRACTOR must contact the DISTRICT’s Small Business Enterprise when the need
to replace an SBE subcontractor occurs. The CONTRACTOR must submit to the DISTRICT’s SBE Section an updated
version of the following:
        1. SBE Subcontractor Participation Schedule form
        2. Statement of Intent to Perform as an SBE Subcontractor form




SBE GUIDELINES & INFORMATION                                                                                       00060-2
                          INSTRUCTIONS TO BIDDERS
ARTICLE 1 - DEFINED TERMS                                           4.04 Failure of any Bidder to receive any such addenda shall not
                                                                    relieve such Bidder from any obligation under its Bid as
1.01    Definitions                                                 submitted. Bidders are advised to contact the DISTRICT prior
Terms used in these INSTRUCTIONS TO BIDDERS have the                to submitting Bids to satisfy themselves as to the existence and
meanings assigned to them in the General Terms & Conditions.        number of all such addenda. All addenda so issued shall
                                                                    become part of the Contract Documents. The Bid shall be
ARTICLE 2 - EXAMINATION OF INSTRUCTIONS TO                          construed as though the addendum(a) have been received and
BIDDERS                                                             acknowledged by the Bidder.

2.01      Bidders are encouraged to carefully read these            ARTICLE 5 - EXAMINATION                       OF    CONTRACT
Instructions. Deviations, changes, modifications or failures to     DOCUMENTS AND SITE
properly complete the Bid can, and in some instances shall,
cause the Bid to be non-responsive.                                 5.01      Before submitting a Bid, each Bidder must (a)
                                                                    examine the Contract Documents thoroughly, (b) visit the site to
ARTICLE 3 - COPIES OF BIDDING DOCUMENTS                             familiarize itself with local conditions that may in any manner
                                                                    affect cost, progress or performance of the Work, (c) familiarize
3.01     Complete sets of Bidding Documents shall be used in        itself with federal, state and local laws, ordinance, rules,
preparing Bids; neither DISTRICT nor DESIGN ENGINEER                regulations and policies that may in any manner affect cost,
assume any responsibility for errors or misinterpretations          progress or performance of the Work; and (d) study and
resulting from the use of incomplete sets of Bidding                carefully correlate Bidder's observations with the Contract
Documents.       DISTRICT, in making copies of Bidding              Documents; and (e) make written requests for interpretations
Documents available on the above terms, does so only for the        promptly after discovering any conflicts, errors, ambiguities or
purpose of obtaining Bids on the Work and does not confer a         inconsistencies. If a Bidder intends to protest the specifications
license or grant for any other use.                                 contained in an request for bid or a request for proposals, the
                                                                    notice of protest shall be filed in writing within 72 hours after
ARTICLE 4 - INTERPRETATIONS AND ADDENDA                             the receipt of the plans and specifications in an request for bid
                                                                    or a request for proposals and the formal written protest shall be
4.01     Verbal interpretations of the meaning of the Drawings,     filed within ten days after the date the notice of protest is filed.
Specifications, or other Contract Documents will not be valid.      Any Bidder who files a formal written protest pursuant to
Every request for interpretations shall be in writing and           Chapter 28-110, Florida Administrative Code and Section
addressed to the Contract Specialist identified on the cover page   120.57(3), Florida Statutes, shall post with the District at the
of this RFB, and to be given consideration must be received by      time of filing the formal written protest, a bond pursuant to
the end of the Inquiry Period, prior to the date fixed for the      Section 287.042(2)(c), Florida Statutes (2000). Failure to file a
opening of Bids. Inquiries may be faxed or emailed.                 notice of protest or failure to file a formal written protest within
                                                                    the time prescribed in Chapter 28-110, Florida Administrative
4.02     Bidders are cautioned not to contact any other             Code and Section 120.57(3), Florida Statutes, or failure to post
representative of the DISTRICT, DESIGN ENGINEER or                  the bond or other security required by law within the time
RESIDENT ENGINEER, manufacturer or supplier referenced              allowed for filing a bond shall constitute a waiver of
herein, without the written permission of the DISTRICT's            proceedings under Chapter 120, Florida Statutes. Notices of
Contract Specialist. Such contact may invalidate the Bid            Protest and Formal Written Protests along with bond or other
supplied by the Bidder.                                             security must be timely filed with the District Clerk.

4.03      The DISTRICT will record its responses to written and     5.02      Reference is made to the General Requirements for the
faxed inquiries and any supplemental instructions in the form of    identification of those reports of investigations and tests of
written addenda. Any and all such interpretations and any           subsurface and latent physical conditions at the site or otherwise
supplemental instructions will be in the form of written addenda    affecting cost, progress or performance of the Work which have
to the Contract Documents which, if issued, will be posted on       been relied upon by DESIGN ENGINEER in preparing the
the DISTRICT’s website (www.sfwmd.gov) not later than five          Drawings and Specifications. DISTRICT shall make copies of
(5) calendar days prior to the Bid opening date fixed for the       such reports available. These reports are not guaranteed as to
opening of Bids. Verbal and other interpretations or                accuracy or completeness, nor are they part of the Contract
clarifications will be without legal effect. It is the              Documents; they are provided for guidance only. If this
responsibility of all respondents to ascertain whether any          information is used by Bidder in preparing its Bid, the Bidder
addenda have been issued before the solicitation deadline           shall assume all risks resulting from actual conditions differing
by either calling or checking the District’s web site. All          from the conditions indicated in the reports.
addenda placed on the District’s web site can be
downloaded.                                                         5.03     When a log of test borings showing a record of the
                                                                    data obtained by the investigation of subsurface conditions by
                                                                    the DISTRICT, the DESIGN ENGINEER or its consultants is
                                                                    included with the plans or other documents, it is expressly

INSTRUCTIONS TO BIDDERS                                                                                                   00100-1
understood and agreed that said log of test borings does not         Declaration Page of Policy for the insurance requirements set
constitute a part of the contract, represents only the opinion of    forth in the General Terms & Conditions, and the Insurance
the DISTRICT, or the DESIGN ENGINEER or its consultants              Requirements Checklist included herein.
as to the character of the materials encountered by them in the
test borings, is included in the plans or other documents only for   6.02      Power of Attorney. Attorneys-In-Fact who sign bonds
the convenience of Bidders, and its use is subject to all of the     must file with such bond a certified copy of their power of
conditions and limitations set forth in this article.                attorney to sign said bonds.

5.04     Before submitting a Bid, each Bidder shall, at Bidder's     ARTICLE 7 - SBE PARTICIPATION
own expense, make or obtain any additional investigations,           (See Bid and Contract SBE Information)
examinations, explorations and tests and obtain any additional
information which pertain to the physical conditions (surface,       ARTICLE 8 - CONTRACT TIMES
subsurface and Underground Facilities) at or contiguous to the
site or otherwise which may affect cost, progress or                 The time of completion is the essence of the contract, and the
performance of the Work and which Bidder deems necessary to          Bidder awarded the Contract shall proceed with the Work in
determine its Bid for performing the Work in accordance with         accordance with the Contract Times specified in the Contract
the time, price and other terms and conditions of the Contract       Documents. The Contract Time is specified on the cover page
Documents.                                                           of this RFB. In the event of failure to complete the Work within
                                                                     the time specified, the DISTRICT may assess damages as
5.05      Upon request, DISTRICT will attempt to provide each        provided by law or the Contract Documents, unless an
Bidder reasonable access to the site to conduct such                 appropriate extension of time has been grated by the
investigations and tests as each Bidder deems necessary for          DISTRICT.
submission of its Bid. If access is provided, Bidder shall restore
site to condition existing prior to conducting said investigations   ARTICLE 9 - LIQUIDATED DAMAGES
and tests.
                                                                     Provisions for liquidated damages, if any, are set forth in the
5.06      The lands upon which the work is to be performed,          Request for Bids (RFB). The Bidder agrees to pay liquidated
rights-of-way for access thereto and other lands designated for      damages to the DISTRICT as described herein and as provided
use by CONTRACTOR in performance the Work are identified             in the Contract Documents, which shall be in addition to such
in the Contract Documents. All additional lands and access           other amounts for actual damages.
thereto required for temporary construction facilities or storage
of materials and equipment are to be provided by Contractor.         ARTICLE 10 - BIDDER'S RESPONSIBILITY

5.07     The submission of a Bid shall constitute a conclusive       10.01 To be eligible for contract award, a bidder must be
representation by the Bidder that it has complied with every         responsive and responsible, as determined by the District. To
requirement of this Article 5 and that the Contract Documents        be determined responsible, a bidder must:
are sufficient in scope and detail to indicate and convey             a) have been selected as pre-qualified for the construction
understanding of all terms and conditions for performance of             project type resulting from solicitation No. 6000000213;
the Work.                                                             b) provide an updated Statement of Status via Item 13 on
                                                                         page 00320-1 that states the Bidder:
5.08      The submission of the Bid shall be an indication that             a. is financially solvent and has sufficient financial
the Bidder has considered normal local weather conditions                      resources to perform the contract;
(daily and monthly variations) for the previous ten years from              b. has maintained a satisfactory performance record;
the date of the Bid as compiled by the National Weather Service             c. has maintained a satisfactory record of integrity and
(NWS) and measured at the observation site closest to the                      business ethics;
project site or other such local data as provided by the District.          d. has maintained the necessary management
                                                                               organization, experience, accounting and operational
ARTICLE 6 - BONDS AND INSURANCE                                                controls, and technical skills, as appropriate;
                                                                            e. has maintained the necessary production capacity,
6.01      Article 5 of the GENERAL TERMS & CONDITIONS                          construction, and technical equipment and facilities,
sets forth the DISTRICT's requirements as to Bonds and                         or the ability to obtain them;
Insurance. The successful Bidder shall have seven (7) working               f. is otherwise qualified and eligible to perform the
days after receipt of the Notice of Apparent Low Bidder Letter                 work under applicable laws and regulations;
from the DISTRICT, to produce the required Bonds, Insurance          c) provide proof of required licensure as indicated in the
Certificates and Endorsements on forms prescribed by                     Supplemental Conditions.
DISTRICT. The successful Bidder must supply copies of all
insurance policies for the insurance requirements set forth in the   THIS INFORMATION MUST BE RECEIVED BY
General Terms & Conditions, and the Insurance Requirements           DISTRICT WITH THE BID. Submittals requested pursuant
Checklist included herein.                                           to this paragraph are in addition to those required elsewhere.

The successful Bidder shall have ninety (90) business days after
CONTRACT execution, to produce the required Insurance
INSTRUCTIONS TO BIDDERS                                                                                                00100-2
10.02 As part of the Bid, the DISTRICT shall receive from all           f.   Trench Safety Act
Bidders documentation related to the Small Business
Enterprise requirements as described herein.                          ARTICLE 15 - DELIVERY OF BIDS

10.03 In evaluating the responsibility of the Bidders, the            15.01 The Bid shall be submitted in an opaque, sealed
DISTRICT will consider the following. (A) The information             envelope, marked on the outside with the name and address of
that the DISTRICT requires all Bidders to submit with the Bid.        the Bidder, the Project title, and the contract number. The
(B) The information gathered by the DISTRICT regarding                DISTRICT shall not be responsible for Bids improperly
Bidder performance on past or current contracts, including but        identified or delivered. If forwarded by U.S. Postal Service
not limited to the Contractor’s Periodic Performance                  regular mail or express mail, the sealed envelope containing the
Evaluations from past and present District projects. (C) Upon         Bid and marked as directed above, shall be addressed to the
request by the DISTRICT, the Apparent Low Bidder, within              U.S. Mail address indicated on the cover page. If forwarded by
seven (7) working days of receipt of Notice of Apparent Low           a service other than United States Postal Service, the sealed
Bidder, shall provide a current financial statement, certified by a   envelope containing the Bid and marked as directed above, shall
Certified Public Accountant, for Bids over $1,000,000. For Bids       be enclosed in another envelope addressed to the street address
under $1,000,000, the information shall be sworn and attested to      indicated on the cover page. Bids may be hand-delivered to the
by the owner, partner or corporate offices. The financial             Procurement Department, B-1 Building.
statements shall be provided in a separate sealed envelope,
marked with the Bidder's Name, Contract Number and Title,             15.02 Facsimile Bids will NOT be accepted. The
and      the    words      "FINANCIAL           INFORMATION,          DISTRICT cautions Bidders to assure actual delivery of
CONFIDENTIAL”.                                                        mailed or hand-delivered Bids directly to the Procurement
                                                                      Department. Telephone confirmation of timely receipt of the
ARTICLE 11 - BIDDERS'S DISCLOSURE                                     Bid may be made by calling (561) 682-6391 before Bid opening
                                                                      time. Bids received after the established deadline will be
In each Bid there shall be stated the name and address of every       returned unopened to the Bidder.
person having an interest in the Bid; and in case of a corporation
the names and addresses of its officers. Bids shall be signed by      ARTICLE 16 - MODIFICATION AND WITHDRAWAL
the person or member of the firm making the same, and in the          OF BIDS
case of a corporation, by some authorized officer or agent
subscribing the name of the corporation and his own name.             16.01 Bids may be modified or withdrawn by an appropriate
                                                                      document duly executed (in the manner that a Bid must be
ARTICLE 13 - PUBLIC ENTITY CRIMES                                     executed) and delivered to the place where Bids are to be
                                                                      submitted at any time prior to the opening of Bids. Withdrawal
Any Bidder, or any of his suppliers, subcontractors, or               of a Bid will not prejudice the rights of Bidder to file a new Bid.
consultants who shall perform work which is intended to benefit
the DISTRICT, shall not be a convicted vendor or, if the Bidder       16.02 If within 24 hours after Bids are opened, any Bidder
or any of his suppliers, subcontractors, or consultants of the        files a duly signed written notice with DISTRICT, and within
Bidder has been convicted of a public entity crime, a period          48 hours thereafter demonstrates to the reasonable satisfaction
longer than 36 months shall have passed since that person was         of the DISTRICT that: a) there has been a material and
placed on the convicted vendor list. The Bidder further               substantial mistake in the preparation of the Bid; b) the mistake
understands and accepts that any contract issued as a result of       is of such great consequence that to enforce the Contract would
this solicitation shall be either voidable by the DISTRICT or         be unconscionable; and c) the mistake occurred notwithstanding
subject to immediate termination by the DISTRICT, in the              the exercise of reasonable care in the preparation of the Bid; the
event there is any misrepresentation or lack of compliance with       Bidder may withdraw its Bid, and the Bid Security will be
the mandates of Section 287.133, Florida Statutes. The                returned provided that the DISTRICT is not seriously
DISTRICT, in the event of such termination, shall not incur any       prejudiced, except for the loss of its bargain. Bidder shall not
liability to the respondent for any work or materials furnished.      be allowed to correct a Bid with a material and substantial
                                                                      mistake. Thereafter, that Bidder shall be disqualified from
ARTICLE 14 - PREPARATION OF BIDS                                      further Bidding on the work to be provided under the Contract
                                                                      Documents.
Bids shall be submitted on the Bid Forms furnished, or upon an
exact copy thereof, and must be signed by an authorized               ARTICLE 17 - DATE AND PLACE OF BID OPENING
representative of the firm submitting the Bid. Bidders must
quote on all items listed and failure to do so may disqualify the     17.01 Sealed Bids will be received by the Procurement
Bid. The intent of the Bid form is to secure a price for the work     Department, South Florida Water Management District, 3301
described in these Contract Documents entitled as shown on the        Gun Club Road, West Palm Beach, Florida 33406, at the time
cover page. Bids shall be accompanied by the following items:         set forth on the cover page.
  a. Bid Form
  b. Bid Bond                                                         17.02 Bids received after the time and date specified in the
  c. SBE Utilization Forms                                            Request for Bids shall not be considered and will be returned
  d. Statement of Business Organization                               unopened.
  e. Affidavit of Non-collusion
INSTRUCTIONS TO BIDDERS                                                                                                    00100-3
17.03 Bids will be publicly opened and read. In case of a tie,         19.03 Discrepancies between words and figures shall be
a selection among the lowest tied responsive and responsible           resolved in favor of the lowest dollar value. Discrepancies
Bidders shall be made in accordance with the DISTRICT's                between the indicated sum of any column of figures and the
Procurement Policy and SBE Rule.                                       correct sum thereof shall be resolved in favor of the LOWEST
                                                                       sum. Discrepancies in the extension of the unit price times the
17.04 Once Bids are opened, they become the property of the            estimated quantity for any line item shall be resolved in favor of
DISTRICT and will not be returned. The Bids become "public             the correct extension.
records" and shall be subject to disclosure consistent with
Chapter 119, Florida Statutes, ten (10) days after the Bid             19.04 The apparent low Bidder shall submit, upon request of
opening.                                                               DISTRICT, documentation evidencing its capability to perform
                                                                       classes of work contemplated, and the necessary plant and
ARTICLE 18 - NOTICE OF INTENDED AWARD                                  sufficient capital to execute the work properly within the time
                                                                       specified. This information must be received by DISTRICT
Tentative Bid tabulations will be posted for review by interested      within seven (7) working days of Bidder receiving written
parties at the Procurement Department offices within two (2)           request.
working days of the Bid opening. After completion of the
review of the Bids, a final Bid tabulation (official Notice of         19.05 DISTRICT may consider the qualifications and
Intended Award) will be posted for a period of not less than           experience of Subcontractors and other persons and
seventy-two (72) hours. Interested parties may inquire by              organizations (including those who are to furnish the principal
calling the DISTRICT's Bid Hotline at 1-800-472-5290 for Bid           items of material or equipment). Use of Subcontractors and
results, or visit the DISTRICT for information as to the intended      other persons and organizations must be submitted as provided
award. If a Bidder intends to protest the District's intent to         in the Supplementary Conditions and Article 10 of these
award, the notice of protest must be filed in writing within 72        Instructions. Operating costs, maintenance considerations,
hours after the posting of the bid tabulation or after receipt of      performance data and guarantees of materials and equipment
the notice of the District’s decision or intended decision and         may also be considered by DISTRICT.
shall file a formal written protest within 10 days after filing the
notice of protest. Any Bidder who files a formal written protest       19.06 DISTRICT may conduct such investigations and
pursuant to Chapter 28-110, Florida Administrative Code and            require supplemental information as it deems necessary to assist
Section 120.57(3), Florida Statutes shall post with the District at    in the evaluation of any Bid and to establish the responsibility
the time of filing the formal written protest, a bond pursuant to      and financial ability of the Bidder, including proposed
Section 287.042(2)(c), Florida Statutes (2000). Failure to file a      Subcontractors, proposed equipment and material suppliers, and
notice of protest or failure to file a formal written protest within   other persons and organizations to do the Work in accordance
the time prescribed in Chapter 28-110, Florida Administrative          with the Contract Documents to DISTRICT's satisfaction within
Code, and Section 120.57(3), Florida Statutes, or failure to post      the Contract Times.
the bond or other security required by law within the time
allowed for filing a bond shall constitute a waiver of                 ARTICLE 20 - STATEMENT OF NO RESPONSE
proceedings under Chapter 120, Florida Statutes. Notices of
Protest and Formal Written Protests along with bond or other           Potential Bidders who chose not to respond to this RFB should
security must be timely filed with the District Clerk.                 submit the enclosed "Statement of No Response" to the
                                                                       Procurement Department via facsimile or in an envelope
ARTICLE 19 - REVIEW ACCEPTANCE AND/OR                                  marked with the RFB number and the reference "No Bid".
REJECTION OF BIDS
                                                                       ARTICLE 21 - CONTRACT
19.01 Pursuant to Rule 40E-7.301, Florida Administrative
Code, the DISTRICT reserves the right to reject any and all            21.01 This Request for Bids does not constitute a Contract
Bids when (i) such rejection is in the interest of the DISTRICT;       with the Bidder. An official Contract does not exist until the
(ii) such Bid is void per se; or (iii) the Bid contains any            Contract has been executed by both parties. The award of the
irregularities, PROVIDED, however, that the DISTRICT                   Contract shall be made to the lowest responsive and responsible
reserves the right to waive any minor irregularities and to accept     Bidder, unless the DISTRICT rejects all Bids.
the lowest responsible and responsive Bid as determined by the
DISTRICT.                                                              21.02 The Bidder to whom the award is made shall, within
                                                                       seven (7) working days after receipt of Notice of Apparent Low
19.02 The DISTRICT reserves the right to request a written             Bidder, provide the required bonds and insurance to the
confirmation of the Bid and the responsibility of the Bidder           DISTRICT. The Bidder whom the award is made shall, within
prior to the awarding of the Contract. Failure of the Bidder to        seven (7) working days after receipt of the Contract document,
confirm the Bid within seven (7) working days from the date of         provide the executed Contract to the DISTRICT.
the DISTRICT's request may render the Bid unresponsive and
will entitle the DISTRICT to award to the next apparent lowest         21.03 If the Bidder fails to provide the bonds and insurance
responsive and responsible Bidder and may require forfeiture of        or execute the Contract within the seven (7) working day
the Bid security.                                                      period, there shall be just cause for the annulment of the award
                                                                       and forfeiture of the Bid Security to the DISTRICT. Bidder
                                                                       shall be liable to the DISTRICT for all damages resulting
INSTRUCTIONS TO BIDDERS                                                                                                    00100-4
therefrom including reasonable attorneys' fees and costs, and       CONTRACTOR if acceptable to DISTRICT application for
attorneys' fees and cost on appeal. The Bid Security forfeited      such acceptance will not be considered by DISTRICT until after
shall not be a limitation thereon. Award may then be made to        the Effective Date of the CONTRACT.
the next lowest, responsible, and responsive Bidder or the work
may be re-advertised at the DISTRICT's sole discretion.             ARTICLE 25 - EQUAL OPPORTUNITY

21.04 Award of this Contract is subject to further                  The DISTRICT recognizes fair and open competition as a basic
DISTRICT approval. All awards are subject to the approval of        tenet of public procurement. Contractors doing business with
the DISTRICT's Governing Board or Executive Office. In the          the DISTRICT are prohibited from discriminating on the basis
event a firm is not awarded the CONTRACT, the DISTRICT              of race, color, creed, national origin, handicap, age or sex.
shall not be responsible for any costs related to bidding or
securing award, including, but not limited to, bid preparation,     ARTICLE 26 - SPECIAL REQUIREMENTS
bond and insurance costs.
                                                                    There may be special requirements pertaining to Warranty,
21.05 The respondent understands that this solicitation or          Guarantee, Bonds, Insurance, Maintenance and the Correction
the response shall not constitute a contract with the District.     Period, which are described in the Contract Documents.
No contract is binding or official until responses are reviewed     Bidders should review all of the Contract Documents to
and accepted by appointed District staff, approved by the           determine whether there are special requirements, and if
appropriate level of authority within the District, and an          applicable, reflect in their Bids all costs associated therewith.
official contract is duly executed by the parties. A sample
contract is attached to this solicitation. The District requires    ARTICLE 27 - LOBBYING
that the final official contract will be in full conformance with
the sample contract. The District will not consider any             All respondents, their agents and proposed subconsultants or
changes to contract terms and conditions. Any deviations            subcontractors, are hereby placed on notice that neither the
from the sample contract will result in the respondent              District’s Governing Board, employees of the District or
being deemed non-responsive.                                        employees of any other project sponsoring agencies shall be
                                                                    lobbied either individually or collectively regarding this
ARTICLE 22 - SUBCONTRACTORS                                         solicitation. Respondents, their agents and proposed
                                                                    subconsultants or subcontractors are hereby placed on notice
In addition to the DISTRICT's Small Business Enterprise (SBE)       that they are prohibited from contacting any of these
submittal requirements described in the Bid SBE Requirements,       individuals for any purpose relating to the solicitation (e.g.,
the DISTRICT will receive from the apparent low bidder,             general information, meetings of introduction, meals, etc.).
within seven (7) working days after receipt of Apparent Low
Bidder Letter, a list of all Subcontractors and other persons and   Any bid submitted by a respondent, its agents and potential
organizations, including those who are to furnish the principal     subconsultants or subcontractors who violate these guidelines
items of material and equipment. If DISTRICT has reasonable         will not be considered for review. The Contract
objection to any proposed Subcontractor, other person or            Specialist/Purchasing Agent (identified on the cover page of
organization, it may, before CONTRACT execution, request the        this solicitation) shall be the only point of contact for
apparent low bidder to submit an acceptable substitute without      questions and/or clarifications concerning the solicitation and
an increase in Bid price. If the apparent low bidder declines to    the award process.
make any such substitution, the contract may not be awarded to
such Bidder at the DISTRICT's sole discretion. DISTRICT does
not waive any right it may have against the Contractor because
of the actions or omissions of said Subcontractor, other person
or organization.

ARTICLE 23 - DRAWINGS AND SPECIFICATIONS

Six (6) sets of the Contract Documents and reproducibles will
be provided free of charge to the successful Bidder upon award;
additional sets may be obtained at the cost specified in the
Request for Bid.

ARTICLE 24         -   SUBSTITUTE         MATERIAL         AND
EQUIPMENT

The Contract, if awarded, will be on the basis of material and
equipment described in the Drawings or specified in the
Specifications without consideration of possible substitute or
"or-equal" items. Whenever it is indicated in the Drawings or
specified in the Specifications that a substitute or "or-equal"
item of material or equipment may be furnished or used by
INSTRUCTIONS TO BIDDERS                                                                                                00100-5
                         BID FORMS CHECKLIST (ITEM 1)
                                            CONTRACT NO. 6000000316
  This Bid Forms Checklist and following forms MUST be submitted with the bid response.
 ITEM       ITEM                                                                          ITEM
 NO.                                                                                      ATTACHED?
                                                                                          (Indicate with a X)
 1.         BID FORMS CHECKLIST (must be signed)                                          1.
 2.         BID (must be completed and signed)                                            2.
 3.         A. DISTRICT'S BID BOND (must be signed and sealed)                            3A._______
               Substitute bid bond form will NOT be accepted.
            B. ALLOWABLE ALTERNATE SECURITY, submitted in lieu of Item 3A.                3B._______
 4.         SBE UTILIZATION FORMS: (if using SBE firm)
            A.    STATEMENT OF INTENT TO PERFORM AS AN SBE
                  SUBCONTRACTOR, submitted for and signed by EACH SBE                     4A._______
                  Subcontractor. Prime Contractor cannot sign the form for the SBE.
                  Both parties must sign this form. Please fill both the price and
                  percentage of work columns on this form.
                  Include proof of SBE Certification.
            B.    SCHEDULE OF SUBCONTRACTOR/SBE PARTICIPATION,                            4B._______
                  completed by the Bidder.

 5.         STATEMENT OF BUSINESS ORGANIZATION                                            5.________
 6.         AFFIDAVIT OF NON-COLLUSION                                                    6. ________
 7.         TRENCH SAFETY ACT (Choose option A or B)                                      7. ________
 8.         STATEMENT OF NO RESPONSE - Required if NOT submitting a Bid                   8. ________

The Bidder, by execution of this Bid Checklist Form, hereby certifies to the District that all required forms, as listed
above, are complete, accurate, and attached to the Bid.


BIDDER'S NAME:_________________________________SIGNATURE BY:______________________




  BID FORMS CHECKLIST                                                                                           00310-1
                                       BID (ITEM 2)
                                   CONSTRUCTION OF
S-60 GATE OPERATOR REPLACEMENT AND CONCRETE
       REPAIRS, OSCEOLA COUNTY, FLORIDA
                                          CONTRACT NO. 6000000316

 Bidder's Name:                                             Florida Contractor Licensee's Name:
 Street Address:                                            License Number:
 City, State, Zip:                                          License Type:
 Telephone No.:                                             State or County:
 Fax No.:                                                   License Limitations, if any (Attach a separate
                                                            sheet, if necessary):
 FEID No.:

TO:     Contracts Manager, Procurement Department
        South Florida Water Management District

1. Pursuant to and in compliance with the DISTRICT'S notice inviting sealed Bids (Request for Bids), Contract Documents
   and the other documents relating thereto, the undersigned Bidder, having familiarized itself with the terms of the Contract
   Documents, as defined in the General Terms & Conditions, site and local conditions affecting the performance of the
   CONTRACT, and the cost of the work at the place where the work is to be done, hereby bids and agrees to perform
   within the Contract Times, including all of its component parts and everything required to be performed, and to provide
   and furnish any and all of the labor, material, and tools, expendable equipment, and all utility and transportation services
   necessary to perform the contract and complete in a workmanlike manner, all of the work required in connection with the
   construction of said work all in strict conformity with the plans and specifications and other Contract Documents,
   including all Addenda filed.

2. The undersigned Bidder agrees that the Work shall be completed according to the schedule set forth in the Contract
   Documents. The undersigned Bidder further agrees to pay liquidated damages as described herein and as provided in the
   Contract Documents, which shall be in addition to such other amounts for actual delay damages. Bid prices must be
   stated in words in the blank space(s) provided for that purpose.

3. The undersigned as Bidder, declares that the only persons or parties interested in this Bid as principals are those named
   herein; that this Bid is made without collusion with any person, firm or corporation; and the Bidder bids and agrees, if the
   Bid is accepted, that the Bidder will execute a contract with the DISTRICT in the form set forth in the Contract
   Documents; that the Bidder will furnish the Contract Security, Insurance Certificates, Endorsements, and Policies, that the
   Bidder will comply with all Small Business Enterprise requirements, that the Bidder is aware that failure to properly
   comply with the requirements set out in the "Instructions to Bidders" and elsewhere in the Contract Documents may result
   in a finding that the Bidder is non-responsive and a forfeiture of the Bid Security. Bids shall only be considered from
   those Bidders who have obtained these Contract Documents directly from the DISTRICT.

4. Pursuant to and in compliance with the DISTRICT's Request for Bid, the Contract Documents, Supplemental Conditions,
   and other documents relating thereto, the undersigned hereby agrees to furnish all labor, materials, and equipment to do

BID FORM                                                                                                      00320-1
    the work in strict accordance with the Contract Documents and all addenda, if any, issued prior to the date of this Bid at
    the price herein as follows:

                                         SCHEDULE OF BID PRICES

ITEM NO.          ITEM DESCRIPTION              UNIT       QUANTITY           UNIT PRICE                TOTAL PRICE

     A.              TOTAL PROJECT               JOB            1              LUMP SUM

BASE BID:                                                                                        $
WRITTEN AMOUNT:

5. If this Bid is accepted, it is understood that the terms and conditions of the Bid provisions and documents shall prevail. In
   the event that the Bidder believes that the cost of any part of the Work is not reflected in the Bid items listed in the Bid
   Form, the cost for that part of Work should be included in a listed Bid item or items.

6. The DISTRICT and Bidder recognize that time is of the essence of this Contract and Bidder recognizes that the
   DISTRICT will suffer financial loss if the Work is not completed within the Contract Times, plus any extensions thereof
   allowed in accordance with Article 12 of the General Terms & Conditions. The DISTRICT and Bidder also recognize the
   delay, expense and difficulties involved in proving actual delay damages (excluding engineering fees and inspection costs)
   suffered by the DISTRICT in a legal or arbitration proceeding if the work is not completed on time. Accordingly, Bidder
   agrees to pay DISTRICT as liquidated damages $1,000.00 per day, plus all efforts required by the Contractor to insure
   that the structure has a flow capacity of 450 cfs, for each day CONTRACTOR exceeds the time specified for Substantial
   Completion as indicated on the front cover of this solicitation. After Substantial Completion, the Bidder agrees to pay
   DISTRICT as liquidated damages $500.00 per day for each day CONTRACTOR exceeds the time specified for Final
   Completion as indicated on the front cover of this solicitation.

7. ACCOMPANYING THIS BID IS a ______________________________________________
   (insert the word(s): "Bid Bond," "certified check," or other security as provided by law, as the case may be)
   in an amount equal to at least 5% of the total Base Bid, payable to the SOUTH FLORIDA WATER MANAGEMENT
   DISTRICT. The DISTRICT may deposit all Bid securities upon receipt. The undersigned agrees that, in case of failure
   on Bidder's part to deliver the Insurance and the Bonds within seven (7) working days after receipt of the Notice of
   Apparent Low Bidder, or failure to execute and deliver the said Contract within seven (7) working days after receipt, any
   Bid Bond, or securities accompanying the Bid, shall be paid into the funds of South Florida Water Management District,
   otherwise, any securities accompanying this Bid shall be returned to the undersigned. Bid bonds will be returned only
   upon request.

8. The undersigned provides above-named Bid Security as a Bid guaranty and agrees that it shall be forfeited to the
   DISTRICT in case this Bid is accepted by the DISTRICT and the undersigned fails to execute a contract with the
   DISTRICT as specified in the contract documents, accompanied by the required statutory payment and common law
   performance bonds with sureties satisfactory to the DISTRICT, and accompanied by the required certificates of insurance
   coverage, and endorsements. Should the DISTRICT be required to engage the services of an attorney in connection with
   the enforcement of this Bid, Bidder promises to pay DISTRICT's reasonable attorney's fees and costs (including attorney's
   fees and costs on appeals) incurred with or without suit.

9. In addition to the Bid Security, also accompanying this Bid, are all items listed on the Bid Form Checklist and all other
   documents as may be required.

10. In accordance with General Terms & Conditions, Article 6.06 the Bidder if awarded the contract will self-perform at a
    minimum forty percent (40%) of the work to be done under this award.


BID FORM                                                                                                       00320-2
11. The names of all persons interested in the foregoing bid as principals are as follows:

If a CORPORATION, Legal Name of corporation:
President's Name:
Secretary's Name:
Treasurer's Name:
General Manager:

If a PARTNERSHIP, true names of firm:
Partners (list all individuals in firm):
INDIVIDUAL OR SOLE PROPRIETOR, full name:

OTHER( name):
Type of Entity:

12. The undersigned as Bidder agrees that substitutions or "or-equal" items will not be considered until after the
    Effective Date of the CONTRACT and will be evaluated in accordance with Article 6.05 of the General Terms
    & Conditions.

13. Statement of Status: The Bidder acknowledges that since its acceptance as a pre-qualified contractor under
    solicitation 60000000213, it is:
    a. financially solvent and has sufficient financial resources to perform the contract;
    b. has maintained a satisfactory performance record;
    c. has maintained a satisfactory record of integrity and business ethics;
    d. has maintained the necessary management organization, experience, accounting and operational
        controls, and technical skills, as appropriate;
    e. has maintained the necessary production capacity, construction, and technical equipment and facilities,
        or the ability to obtain them;
    f. is otherwise qualified and eligible to perform the work under applicable laws and regulations; and that
        no change in licensure or reduction in bonding capacity has occurred; or
    g. The Bidder confirms that the items listed below have changed since it’s acceptance as a pre-qualified
        contractor under solicitation 6000000213 with regards to items a. – f. above and the corresponding
        updated information is indicated below and submitted with this bid:
    _______________________________________________________________________________________
    _______________________________________________________________________________________
                 If applicable - Attachment ___________, consisting of ___________ pages.

NOTE: If a Bidder is a corporation, the legal name of the corporation shall be set forth below, together with
signature(s) of the officer or officers authorized to sign contracts on behalf of the corporation and corporate seal; if
bidder is a partnership, the true name of the firm shall be set forth below with the signature(s) of the partner or
partners authorized to sign contracts in behalf of the partnership; and if the bidder is an individual, Bidder's
signature shall be placed below; if a partnership, the names of the general partners.




BID FORM                                                                                                00320-3
                          BIDDER:
                                    Authorized Officer or Agent   (Type or Print)

                          By:
                                Signature                                Date

                                Printed Name: ____________________________________________

                                Title: ____________________________________________________


Attest (Required for CORPORATION)

I, __________________________________________________, CERTIFY THAT I AM THE SECRETARY/
ASSISTANT SECRETARY OF THE CORPORATION, NAMED AS PRINCIPAL IN THE WITHIN BID;
THAT THE CORPORATE OFFICIAL WHO SIGNED THE SAID BID ON BEHALF OF THE PRICIPAL,
WAS THEN A CORPORATE OFFICIAL OF SAID CORPORATION; THAT I KNOW THEIR SIGNATURE,
AND THEIR SIGNATURE THERETO IS GENUINE; AND THAT SAID BID WAS DULY SIGNED, SEALED
AND ATTESTED FOR AND IN BEHALF OF SAID CORPORATION BY AUTHORITY OF ITS
GOVERNING BODY.


Witness:_________________________________________
(Required for PARTNERSHIP OR INDIVIDUAL)


Witness:___________________________________________
(Required for PARTNERSHIP OR INDIVIDUAL)



REQUIRED FOR ALL BIDS:



FLORIDA CONTRACTOR LICENSEE'S SIGNATURE: __________________________________




BID FORM                                                                            00320-4
                                               BID BOND
                                                      (ITEM 3A)

KNOW ALL MEN BY THESE PRESENTS, that we,                                          as Principal and                     , as
Surety, are held and firmly bound unto South Florida Water Management District, in the penal sum of                dollars
($                  ) lawful money of the United States, for the payment of which sum, well and truly to be made, we
bind ourselves, our heirs, executors, administrators, and successors, jointly and severally, firmly by these presents.

THE CONDITION OF THE OBLIGATION IS SUCH, that whereas the Principal has submitted the accompanying
bid, dated   , 20  , for the Contract Documents:

        Contract Number:           6000000316
        Contract Title:            S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS,
                                   OSCEOLA COUNTY, FLORIDA

NOW, THEREFORE, if the Principal:

1. Does not withdraw said Bid within ninety (90) calendar days after date of opening of the same, and

2. Within seven (7) working days after the date of the Notice of Apparent Low Bidder:

a. Provides a Statutory Payment Bond and a Common Law Performance Bond as specified in the General Terms &
   Conditions (if the Bid Amount exceeds $200,000.00) or, in lieu of the Statutory Payment Bond or Common Law
   Performance Bond, provide an alternate form of security as specified in the General Terms & Conditions; and

b. Provides the District's insurance certificate, completed by a lawfully authorized insurance agent; and

3. Within seven (7) working days of receipt of the contract, enters into a written contract with South Florida Water
   Management District, in accordance with the Bid, as accepted,

then the above obligations of the Principal and Surety shall be null and void. However, should the Principal fail to
fully comply with the conditions of the numbered paragraphs 1. or 2. above, then the Principal and Surety, jointly
and severally, shall be liable to the District for the full penal sum of this Bond which shall be forfeited to the
District as liquidated damage, but not a penalty, as a result of the Principal’s failure to comply with the bid
instructions and conditions, regardless of whether the District ultimately decides to change the project
requirements or resolicit bids.

The remedies provided herein are not to be construed as the District’s exclusive remedies for the Principal’s
failure to enter into a contract with the District, but shall be deemed supplemental to all remedies available to the
District at law or otherwise.

DATED ON ________________________, 20___.


WHEN THE PRINCIPAL IS AN INDIVIDUAL:


                                                    By:
        (Witness)                                   (Individual Principal)


        (Witness)                                   Business Address

BID BOND                                                                                                        00330-1
WHEN THE PRINCIPAL OPERATES UNDER A TRADE NAME:
     Signed, sealed and delivered in the presence:


        (Witness)                                  (Business Name and Address)

                                                   By:
        (Witness)                                  Signature of Individual

WHEN A PARTNERSHIP:
     Signed, sealed and delivered in the presence:


        (Witness)                                  (Name of Partnership)

                                                   By:
        (Witness)                                  Signature of Individual

WHEN THE PRINCIPAL IS A CORPORATION:
ATTEST:
     (Corporate Seal)
                                 (Corporate Principal)


                                                   Business Address

                                                   By:
        (Secretary)                                President

SURETY:
ATTEST:
     (Corporate Seal)
                                                   (Corporate Surety)


                                                   Business Address

                                                   By:
        (Secretary)                                (Surety)


        Florida Resident Agent                     Resident Agent's Address


        Telephone Number

        (Surety shall provide evidence of signature authority, i.e., a certified copy of Power of Attorney.)

Note: If both the Principal and Surety are Corporations, the respective Corporate Seals shall be affixed and attached.




BID BOND                                                                                                       00330-2
            SOUTH FLORIDA WATER MANAGEMENT DISTRICT

                            STATEMENT OF INTENT TO PERFORM
                               AS A SBE SUBCONTRACTOR
                                                        (ITEM 4A)

                                                                                 CONTRACT NO.: 6000000316


A signed “Statement of Intent to Perform as a SBE Subcontractor” must be completed by the owner or authorized
principal of each SBE firm listed in the “SBE Subcontractor Participation Schedule” Form No. 0956.


                                               agrees to perform work on the above contract as (check one):
        (Name of SBE Subcontractor)
                                                  a partnership;      a corporation;     an individual;   a joint venture.

SBE Subcontractor
The SBE Subcontractor will enter into a formal agreement, conditioned upon the Bidder/Proposer executing a

contract with the District for the work with                                                                          .
                                                                     (Name of Bidder/Proposer)



Item No.                          Type of Work                                         Agreed Price             % of Work
                                                                              (For CCNA, Agreed Percentage)
    1                                                                        $                                               %
    2                                                                        $                                               %
    3                                                                        $                                               %
                                               TOTAL VALUE OF WORK           $                                               %




  SBE Subcontractor Signature                                      Title                                  Date



    Bidder/Proposer Signature                                      Title                                  Date
Form 0957 (07/2006)




STATEMENT OF INTENT TO PERFORM AS A SBE SUBCONTRACTOR                                                               00341-1
                                                     (ITEM 4B)



                    SBE SUBCONTRACTOR PARTICIPATION SCHEDULE
   Contract #                                                                      Date Submitted


   Project Name & Location                                                         Project Start Date


   Bidder / Proposer                      Address


   Contact Person                         Telephone #                              Fax #


                                              ORGANIZATION STATUS

                                                                                   Work to be Performed
                                                                      Describe Type of Work to
       Business                                           Business                                  % of        Dollar
                                                                           be Performed
      Association      Business Name   Business Address   Phone #                                   Work       Amount


    Bidder/Proposer
    Non SBE
    Subcontractor
    SBE
    Subcontractor
    SBE
    Subcontractor
    SBE
    Subcontractor
    SBE
    Subcontractor


                                                                     Total Participation            100%

                                                                     Total Contract

The listing of a SBE shall constitute a representation by the bidder/proposer to the District that the
bidder/proposer believes such SBE to be technically and financially qualified and available to perform the
described. Bidders/Proposers are advised that the information contained herein may be verified.

I certify that the above information is true to the best of my knowledge:

________________________________                _________________________               __________________
   Bidder/Proposer Signature                                 Title                                      Date


Form 0956 (07/2006)




SBE SUBCONTRACTOR PARTICIPATION SCHEDULE                                                                       00342-1
         STATEMENT OF BUSINESS ORGANIZATION
                                           SOLICITATION NO. 6000000316
                                                           (ITEM 5)
                                      BUSINESS ORGANIZATION
Business Name
Mailing Address
Remittance Address
State of Incorporation
FID # or SS #
Telephone #                 (    )                                           Fax #: (      )
Type of Organization         Corporation            Partnership               Individual

Contact Person(s)
Email Address

If respondent is a corporation, provide certification from the Florida Secretary of State verifying respondent’s corporate status
and good standing, and in the case of out-of-state corporation, evidence of authority to do business in the State of Florida.

Statements of Material Representation

The bidder, by signing below, hereby certifies to the South Florida Water Management District (District) that neither the bidder,
nor its agents, principals and proposed subconsultants or subcontractors:

    1. Is temporarily or permanently on the District's Suspension List
    2. Is temporarily or permanently debarred from participating in public contract lettings in Florida or any other state.
    3. Is now or in the past 36 months been on the State of Florida's Convicted Vendor List/Discriminatory Vendor List.
    4. Has lobbied, either individually or collectively, the District’s Governing Board members or other District employees for
       any purpose in connection with this solicitation which may influence the outcome of the selection process.
    5. Has employed or retained any person or company to solicit or obtain a contract resulting from this solicitation and
       has not paid or agreed to pay any person or company employed or retained to solicit or obtain a contract resulting
       from this solicitation any commission, percentage, brokerage or other fee contingent upon or resulting from contract
       award.
    6. Bidder represents that no actual or potential conflict of interest exists, directly or indirectly, with respect to the
       services to be provided in connection with this solicitation.

I certify that the above information is true to the best of my knowledge:

________________________________ _________________________ __________________
   Bidder Signature                             Title                                   Date




STATEMENT OF BUSINESS ORGANIZATION                                                                                00350-1
   AFFIDAVIT OF NON-COLLUSION AND
     OF NON-INTEREST OF DISTRICT
             EMPLOYEES
                                                   (ITEM 6)

CONTRACT NO.:                6000000316

CONTRACT TITLE:    S-60 GATE OPERATOR REPLACEMENT AND CONCRETE
                   REPAIRS, OSCEOLA COUNTY, FLORIDA
STATE OF_____________

COUNTY OF____________

_____________________________________________________,* being first duly sworn, deposes and says
that as the bidder in the above bid, the only person or persons interested in said bid are named therein; that all
statements of fact in the bid/proposal are true and that its bid was not made in the interest of or on behalf
of any undisclosed person, partnership, company association, organization nor corporation. Affiant
further represents that the bid has been prepared independently without collusion, consultation,
communication or written agreement with any undisclosed person, partnership, company, association,
organization or corporation and has not colluded, conspired, connived or agreed, directly or indirectly, to
commit a fraudulent, deceitful, unlawful or wrongful act, or any act which may result in an unfair
competitive advantage for one or more bidders over other bidders. Respondent certifies that no more than
one (1) bid as Prime Contractor for the Project described in this Request for Bids will be submitted from
the respondent under the same or a different name and that respondent has no financial interest in another
respondent for the same Project. The District will prosecute any violation of this representation to the
fullest extent of the law. Conviction for the commission of any fraud or act of collusion in connection
with any sale, bid quotation, proposal or other act incidental to doing business with the South Florida
Water Management District may result in suspension or permanent debarment if the respondent is placed
on the State’s Convicted Vendor List. In addition to any other rights or remedies it may have, the District
reserves the right to terminate any existing contracts that a respondent has with the District based on the
commission of any of the above wrongful acts. These rights may be exercised at any time whenever the
commission of any of the above wrongful acts comes to the District’s attention even if this occurs after
award of a contract to the bidder.


Affiant

STATE OF _____________

COUNTY OF___________

The foregoing instrument was acknowledged before me this________day of __________, 20____
by______________________________________, who is personally known to me or who has produced
_____________________________________________as identification and who did take an oath.


Notary Public
My Commission Expires:
*NOTICE: State name of Bidder followed by name of authorized individual (and title) who is signing as
Affiant. If Bidder is an individual, state only name of Bidder.


AFFIDAVIT OF NONCOLLUSION                                                                                 00370-1
                   TRENCH SAFETY ACT
              SECTION 553.60, FLORIDA STATUTE
                                                     (ITEM 7)

NOTICE TO BIDDERS:

In order to comply with the Trench Safety Act, the Contractor is required to either specify the costs of compliance or
certify that the project scope and / or his construction means and methods will not require trenching as defined by
OSHA. (See the OSHA definition of trenching on page 00380-2.)


           Bidders must fill out EITHER PART A or PART B of this form,                      BUT NOT BOTH,
           sign the form where indicated, and then submit the form with the bid.



PART A: Specify Costs of Compliance with the Trench Safety Act

These costs are not a separate pay item. The Contractor must also reference the Trench Safety Standards which will
be in effect during construction, and assure in writing that the Contractor will comply with the applicable Trench
Safety Standards.

TRENCH SAFETY                 UNITS OF                                      UNIT
MEASURE                       MEASURE                QUANTITY               COST           COST




TRENCH SAFETY ACT                                                                                          00380-1
PART B: Certification that the Trench Safety Act does not apply.

               By placing a check mark in the box to the left I certify that this project either does not include
                             trenching, or that my intended construction means and methods will not require
                             trenching, as defined by OSHA.




From 29 CFR 1926.650 Subpart P, the definition of “Trenching” or “Trench excavation" means a narrow excavation
(in relation to its length) made below the surface of the ground. In general, the depth is greater than the width, but the
width of a trench (measured at the bottom) is not greater than 15 feet (4.6 m). If forms or other structures are installed
or constructed in an excavation so as to reduce the dimension measured from the forms or structure to the side of the
excavation to 15 feet (4.6 m) or less (measured at the bottom of the excavation), the excavation is also considered to be
a trench.




                                                                               Signature




TRENCH SAFETY ACT                                                                                              00380-2
                     STATEMENT OF NO RESPONSE
                              SOLICITATION NO. 6000000316
                                                       (ITEM 8)

Recipients of this solicitation may elect not to respond. The District is interested in learning the reason(s) for
non-response. If you elect not to respond with an offer to this solicitation, the District requests that the
reason(s) be indicated below and this form returned to:

               Procurement Department
               South Florida Water Management District
               P.O. Box 24680, West Palm Beach, FL 33416-4680
               Fax Number: (561) 682-5319

               REASONS:
1.             Do not offer this product/service or an equivalent.
2.             Schedule would not permit.
3.             Insufficient time to respond to solicitation.
4.             Unable to meet specifications / scope of work.
5.             Specifications "too tight" (i.e. geared to specific brand or manufacturer).
6.             Specifications not clear.
7.             Unable to meet bond and/or insurance requirements.
8.             Unable to meet SBE Requirements.
9.             Solicitation addressed incorrectly, delayed in forwarding of mail.
10.            Other (Explanation provided below or by separate attachment.)

Explanation:



The District may delete the names of those persons or businesses who fail to respond to three (3) solicitations
and who fail to return this Statement, including reason(s) for non-response.

Desire to receive future District solicitations?  Yes  No

COMPANY:

NAME:                                                          TITLE:

ADDRESS:

TELEPHONE: (          )                        DATE:


Certified Small Business Enterprise ?  Yes  No

Certifying Agency:



STATEMENT OF NO RESPONSE                                                                               00400-1
           SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                               CONSTRUCTION CONTRACT
THE SOUTH FLORIDA WATER MANAGEMENT                            This number must appear on all Invoices and Correspondence
DISTRICT (hereinafter referred to as DISTRICT)
HEREBY ENTERS INTO THIS CONTRACT WITH:
                                                              4600000___________
Name:                                                         60000000__________
Address:
                                                              P.O. #:________________
Contact Person:                                               SBE PARTICIPATION ____________%
Telephone No:                                                 CONTRACT TIME:                 ____ DAYS - Substantial Completion
Fax No:                                                       CONTRACT TIME:                 ____ DAYS - Final Completion
Email Address:                                                LIQUIDATED DAMAGES:            $__00.00 – Substantial Completion
Hereinafter referred to as: CONTRACTOR                        LIQUIDATED DAMAGES:            $__00.00 – Final Completion
                                                              EFFECTIVE DATE:                NOTICE TO PROCEED
PROJECT TITLE:

The CONTRACTOR hereby acknowledges receipt of the following documents which are included in the
attached CD and made a part hereto of this CONTRACT:

General Terms & Conditions                  Bidding Documents                      Technical Specifications
General Requirements                           •  RFB and Addenda                  Drawings
Supplemental Conditions                        •  Bid                              Post Award Forms
Bonds & Insurance                              •  SBE Documents
TOTAL CONTRACT AMOUNT: $                                      CONTRACT TYPE:Firm Fixed Price
Multi-Year Funding (If Applicable)
Fiscal Year: October 1, 2009 – September 30, 2010 $           Fiscal Year:
Fiscal Year: October 1, 2010 – September 20, 2011 $*          Fiscal Year:
Fiscal Year: October 1, 2011 – September 20, 2012 $*          Fiscal Year:
*Subject to District Governing Board Annual Budget Approval

District Resident Engineer:                                   District Senior Contract Specialist:
Telephone No:                                                 Bonnie Batchelor, (561) 242-5520 ext. 4057
Fax No.                                                       Fax No.: (561) 682-5319 or (561) 681-6275
Email Address:             @sfwmd.gov                         Email Address: bbatchel@sfwmd.gov
SUBMIT NOTICES TO THE DISTRICT AT:                            SUBMIT NOTICES TO THE CONTRACTOR AT:
South Florida Water Management District
3301 Gun Club Road                                            Attention:
West Palm Beach, Florida 33406
          Attention: Procurement Department

IN WITNESS WHEREOF, the authorized representative hereby executes this CONTRACT on this date, and accepts
all Terms and Conditions under which it is issued.
                                                              SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                                                                       BY ITS GOVERNING BOARD
Accepted                                                      Accepted
              Signature of Authorized Representative                         Frank Hayden, Procurement Director
                                                              Date:
Title:

Date:
                                                              SFWMD PROCUREMENT APPROVED
                                                              By:                       Date:

SAMPLE CONTRACT                                                                                                            00500-1
                        SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                           INSURANCE REQUIREMENTS CHECKLIST
                FOR: S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS,
                                  OSCEOLA COUNTY, FLORIDA

                    TYPE OF COVERAGE                                        MINIMUM COVERAGE LIMITS
 Must be
                                                                          Bodily Injury & Property Damage
Included
                             General Liability                                       $1,000,000
    if
                           Comprehensive Form                                      Combined Limit
Checked
              (Please note any special instructions →)             Special instructions:
    X            Occurrence Form
    X            Premises Operations
    X            Delete XCU Exclusion
    X            Products Completed
    X            Contractual
    X            Independent Contractors
    X            Broad Form Property
    X            Personal Injury
                 Blasting
                 Demolition
                 Watercraft
                 Pollution
                          Automobile Liability
    X            Any Auto                                                 Bodily Injury & Property Damage
                 Owned                                                               $1,000,000
                 Non – Owned                                                       Combined Limit


    X                                                                             Statutory Limits
                  Workers’ Compensation and
                                                                            $100,000/Accident
                      Employer’s Liability
                                                                            $100,000/$500,000 Disease


                           Professional liability                               $_________________


                    Builder’s Risk/Installation Floater                            @100% of Value

                                                                          Bodily Injury & Property Damage
                              Aircraft Liability
                                                                                $_________________
                                                                                   Combined Limit

                                                                          Bodily Injury & Property Damage
                    Environmental Impairment Liability                          $_________________
                                                                                   Combined Limit


    South Florida Water Management District is to be named as Additional Insured for General
                             Liability and Auto Liability Coverage.
The Certificate holder shall be designated as:                  Insurance Requirements reviewed by:
South Florida Water Management District
3301 Gun Club Road                                              ______LLH_______           ____11/06/09__
West Palm Beach, FL 33406                                            Initials                  Date
Attention: Bonnie Batchelor, Contracts
        The CONTRACTOR shall have ninety (90) business days after CONTRACT execution to produce the required Insurance
                         Declaration Page of Policy for the insurance requirements set forth herein.
INSURANCE REQUIREMENTS CHECKLIST                                                                                 00600-1
            COMMON LAW PERFORMANCE BOND
BY THIS BOND, know that                                         as Principal, herewith called CONTRACTOR,
Business Address                                              , Business Phone                             , and                             , as
___________________, hereinafter called SURETY, Surety Address                                           ,
Surety Phone Number                                     , are bound to South Florida Water Management District, as Obligee, herein called
DISTRICT, in the amount of                              Dollars ($___________) for payment of which CONTRACTOR and SURETY bind
themselves, their heirs, personal representatives, executors, administrators, successors and assigns, jointly and severally, with reference to a
written CONTRACT entered into by CONTRACTOR and DISTRICT, for the following:

Contract Number:                     6000000316
Contract Title:                      S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS, OSCEOLA
                                     COUNTY, FLORIDA
General Description of Project:      This project involves replacing existing stem operator system with a Cable Drum Hoist System;
concrete repairs to the abutment walls and slab; sandblast and recoat all four steel sheet pile wing walls replace reinforced concrete
operator platform with prefabricated cable drum hoist system and steel platform; dewatering; provide dry and wet season by pass
requirements; replace and add staff gauges upstream and downstream; and add stainless steel plating at the weir crest and along all
corners of the gate recess; and painting.
Directions: From Florida Turnpike: Exit 242 to US192; East on US192 to County Road 534 (CR 534); South on CR 534 to South
Florida Water Management District Canal 33 (SFWMD C33); North on the SFWMD C33 East Levee to S-60.


THE CONDITION OF THIS BOND is that if the CONTRACTOR:
1. Performs said contract in accordance with its terms and conditions; and
2. Pays DISTRICT all losses, damages (direct and consequential including delay or liquidated damages), expenses, costs, and attorney's
   fees, including appellate proceedings, that DISTRICT sustains because of a default by CONTRACTOR under the CONTRACT; and
3. Pays DISTRICT any and all other amounts due DISTRICT by CONTRACTOR because of a default by CONTRACTOR under the
   CONTRACT; and
4. Performs the warranty and guarantee of all work and materials furnished under the CONTRACT for the time specified in the
   CONTRACT;

THEN THIS BOND IS VOID, OTHERWISE, IT REMAINS IN FULL FORCE.

SURETY’s OBLIGATIONS UNDER THIS BOND shall be that within 20 days of DISTRICT’s declaration of CONTRACTOR’s
default, SURETY shall either (1) arrange for the CONTRACTOR, with the written consent of the DISTRICT, to timely perform and
complete the contract or (2) undertake to timely perform and complete the contract either by retaining another contractor approved by
the DISTRICT or undertaking to do the contract itself. SURETY shall be liable for any and all delays caused by the CONTRACTOR,
SURETY, and/or the replacement contractor(s) provided by the SURETY. SURETY’s failure to take such action shall be deemed to
be a default on this Bond, thus entitling the DISTRICT to complete the contract with another contractor and recover all resulting
damages, including, but not limited to, all direct and consequential damages including delay or liquidated damages, engineering and
architectural fees, as well as, any and all legal costs and attorney’s fees.

Any changes in or under the Contract Documents do not affect the Surety's obligation under this bond. Surety hereby waives notice of any
alteration or extension of time made by the Owner. Any suit under this bond must be initiated before the expiration of the limitation period
applicable to common law bonds under Florida Statutes.

IN WITNESS WHEREOF, this instrument is executed this               day of                                 , 20     .

Legal Form Approved:



WHEN THE PRINCIPAL IS AN INDIVIDUAL:
Signed, sealed and delivered in the presence of:


By:                                                                By:
         (Witness)                                                           Individual Principal


PERFORMANCE BOND                                                                                                                       00610-1
WHEN THE PRINCIPAL OPERATES UNDER A TRADE NAME:
Signed, sealed and delivered in the presence of:

By:                                                              By:
         (Witness)                                                        Signature of Individual

By:
         (Witness)

WHEN A PARTNERSHIP:
Signed, sealed and delivered in the presence of:

By:                                                              By:
         (Witness)                                                        Partner

By:
         (Witness)

WHEN THE PRINCIPAL IS A CORPORATION:
ATTEST:
(Corporate Seal)

                                                                 By:
         (Type Corporate Principal Name)                                  President

By:
         (Secretary)

SURETY:
ATTEST:
(Surety Seal)
                                                                 By:
         (Type Corporate Surety Name)                                     SURETY

By:
         (Secretary)

ATTORNEY-IN-FACT

By:                                                              Name
                  (Type)

NOTE 1: Surety shall provide evidence of signature authority, i.e., a certified copy of Power of Attorney.
NOTE 2: If both the Principal and Surety are Corporations, the respective Corporate Seals shall be affixed and attached.
NOTE 3: Surety shall include evidence that Agent is licensed in Florida.

IMPORTANT: Surety companies executing BONDS must appear on the Treasury Department's most current list (Circular 570 as
amended) and be authorized to transact business in the State of Florida.

ATTACH a certified copy of Power-of-Attorney appointing individual Attorney-in-Fact for execution of Performance Bond on behalf of
Surety.

The Common Law Performance Bond and the Payment Bond and the covered amounts of each are separate and distinct from each
other.



PERFORMANCE BOND                                                                                                           00610-2
                       STATUTORY PAYMENT BOND
BY THIS BOND, know that                                   as Principal, herewith called CONTRACTOR, Business Address
                         , Business Phone                       , and                         , as ___________________,
hereinafter called SURETY, Surety Address                                   , Surety Phone Number                     ,
are bound to South Florida Water Management District, as Obligee, herein called DISTRICT, in the amount of
Dollars ($___________) for payment of which CONTRACTOR and SURETY bind themselves, their heirs, personal
representatives, executors, administrators, successors and assigns, jointly and severally, with reference to a written
CONTRACT entered into by CONTRACTOR and DISTRICT, for the following:

Contract Number:                   6000000316
Contract Title:                      S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS, OSCEOLA
                                     COUNTY, FLORIDA
General Description of Project:      This project involves replacing existing stem operator system with a Cable Drum Hoist System;
concrete repairs to the abutment walls and slab; sandblast and recoat all four steel sheet pile wing walls replace reinforced concrete
operator platform with prefabricated cable drum hoist system and steel platform; dewatering; provide dry and wet season by pass
requirements; replace and add staff gauges upstream and downstream; and add stainless steel plating at the weir crest and along all
corners of the gate recess; and painting.
Directions: From Florida Turnpike: Exit 242 to US192; East on US192 to County Road 534 (CR 534); South on CR 534 to South
Florida Water Management District Canal 33 (SFWMD C33); North on the SFWMD C33 East Levee to S-60.

THE CONDITION OF THIS BOND is that if the CONTRACTOR:

Promptly makes payments to all claimants as defined in Section 255.05(1), Florida Statutes, supplying CONTRACTOR with
labor, material, or supplies, used directly or indirectly by CONTRACTOR in the prosecution of the work provided for in the
contract;

THEN THIS BOND IS VOID, OTHERWISE, IT REMAINS IN FULL FORCE.

Any changes in or under the Contract Documents and compliance or noncompliance with formalities, connected with the
CONTRACT or with the changes, do not affect Surety's obligation under this bond. Surety hereby waives notice of any
alteration or extension of time made by the DISTRICT.

Claimants must comply with notice requirements set forth in Section 255.05(2), Florida Statutes. No action shall be instituted
against the CONTRACTOR or Surety under this bond after one (1) year from the performance of the labor or completion of
the delivery of the materials or supplies.

IN WITNESS WHEREOF, this instrument is executed this the                        day of                              , 20     .

WHEN THE PRINCIPAL IS AN INDIVIDUAL:
Signed, sealed and delivered in the presence of:

By:                                                           By:
         (Witness)                                                     (Individual Principal)




STATUTORY PAYMENT BOND                                                                                            00620-1
WHEN THE PRINCIPAL OPERATES UNDER A TRADE NAME:
Signed, sealed and delivered in the presence of:

By:                                                       By:
        (Witness)                                                  Signature of Individual

By:
        (Witness)

WHEN A PARTNERSHIP:
Signed, sealed and delivered in the presence of:

By:                                                       By:
        (Witness)                                                  Partner

By:
        (Witness)

WHEN THE PRINCIPAL IS A CORPORATION:
ATTEST:
(Corporate Seal)

                                                          By:
(Type Corporate Principal Name)                                    President

By:
        (Secretary)

SURETY:
ATTEST:
(Surety Seal)
                                                          By:
        (Type Corporate Surety Name)                               SURETY

By:
        (Secretary)                                                (Type Florida Resident's Name)


ATTORNEY-IN-FACT

By:                                                       Name
                 (Type)

NOTE 1: Surety shall provide evidence of signature authority, i.e., a certified copy of Power of Attorney.
NOTE 2: If both the Principal and Surety are Corporations, the respective Corporate Seals shall be affixed and attached

IMPORTANT: Surety companies executing BONDS must appear on the Treasury Department's most current list (Circular
570 as amended) and be authorized to transact business in the State of Florida.

ATTACH a certified copy of Power-of-Attorney appointing individual Attorney-in-Fact for execution of Performance Bond
on behalf of Surety.

The Common Law Performance Bond and the Statutory Payment Bond and the covered amounts of each are separate and
distinct from each other.




STATUTORY PAYMENT BOND                                                                                     00620-2
        AFFIDAVIT FOR SURETY COMPANY
                TO BE SUBMITTED WITH PERFORMANCE & PAYMENT BOND

TO:    South Florida Water Management District

RE:    CONTRACT NUMBER:               6000000316
       CONTRACT TITLE:                S-60 GATE OPERATOR REPLACEMENT AND CONCRETE
                                      REPAIRS, OSCEOLA COUNTY, FLORIDA

CONTRACTOR:

Name:
Address:
Telephone:

AMOUNT OF BOND:

SURETY COMPANY:

Name:
Address:
Telephone:

BEFORE ME, the undersigned authority, personally appeared the AFFIANT, who being duly sworn and
says:

(1) He/She is                                      of the Surety Company;
                      (Officership)

(2) In accordance with Section 287.0935, Florida Statutes, the Surety Company fulfills each of the
    following provisions:

 a) The Surety Company is licensed to do business in the State of Florida;

 b) The Surety Company holds a certificate of authority authorizing it to write surety bonds in Florida;

 c) The Surety Company has twice the minimum surplus and capital required by the Florida Insurance
    code at the time the request for bid is issued;

 d) The Surety Company is otherwise in compliance with the provisions of the Florida Insurance Code;
    and

 e) The Surety Company holds a currently valid certificate of authority issued by the United Stated
    Department of Treasury under 31 U.S.C. ss. 9304 to 9308.




AFFIDAVIT FOR SURETY COMPANY                                                                      00630-1
FURTHER AFFIANT SAYETH NOT.




Dated Signed Signature of AFFIANT (Officer of Surety Company)




Title of AFFIANT



STATE OF

COUNTY OF

Before me this day personally appeared                                     , who, being duly sworn,
executed this Affidavit and acknowledged to and before me the truthfulness and accuracy of the statements
in the Affidavit.

SWORN TO AND SUBSCRIBED before me this _____ day of ____________, 20_____, by AFFIANT,
who is personally known to me.

By:

Name:

NOTARY PUBLIC


Commission Expiration Date:




AFFIDAVIT FOR SURETY COMPANY                                                                    00630-2
                  GENERAL TERMS & CONDITIONS
                                                     TABLE OF CONTENTS

ARTICLE 1-DEFINITIONS / INTERPRETATIONS                      6.12    Record Documents
                                                             6.13    Safety and Protection
1.01   Defined Terms                                         6.14    Safety Representative
                                                             6.15    Hazard Communications Programs
ARTICLE 2-PRELIMINARY MATTERS                                6.16    Emergencies
                                                             6.17    Shop Drawings and Samples
2.01   Delivery of Performance and Payment Bonds             6.18    Continuing the Work
2.02   Copies of Documents                                   6.19    CONTRACTOR's General Warranty & Guarantee
2.03   Commencement of CONTRACT Time; Notice to              6.20    Truth-In-Negotiation
       Proceed
2.04   Starting the Work                                     ARTICLE 7-OTHER WORK
2.05   Before Starting Construction
2.06   Preconstruction Conference                            7.01    Related Work at Site
2.07   Initial Acceptance of Schedules                       7.02    Coordination

ARTICLE 3-CONTRACT DOCUMENTS: INTENT,                        ARTICLE 8-DISTRICT'S RESPONSIBILITIES
AMENDING, REUSE
                                                             8.01    Communications to CONTRACTOR
3.01   Intent                                                8.02    Furnish Data
3.02   Reference Standards                                   8.03    Pay When Done
3.03   Reporting and Resolving Discrepancies                 8.04    Lands and Easements; Reports and Tests
3.04   Amending & Supplementing Contract Documents           8.05    Change Orders
3.05   Reuse of Documents                                    8.06    Inspections, Tests, and Approvals
                                                             8.07    Limitations on DISTRICT's Responsibilities
ARTICLE 4-AVAILABILITY OF LANDS; SUBSURFACE &                8.08    Undisclosed Hazardous Environmental Condition
PHYSICAL CONDITIONS; REFERENCE POINTS
                                                             ARTICLE 9-CONSTRUCTION MANAGER‘S STATUS DURING
4.01   Availability of Lands                                 CONSTRUCTION
4.02   Subsurface and Physical Conditions
4.03   Differing Subsurface or Physical Conditions           9.01    DISTRICT's Representatives
4.04   Underground Facilities                                9.02    Clarifications and Interpretations
4.05   Reference Points                                      9.03    Authorized Variations in Work
4.06   Hazardous Environmental Condition at Site             9.04    Rejecting Defective Work
                                                             9.05    Shop Drawings, Change Orders and Payments
ARTICLE 5-BONDS, INSURANCE & LICENSES                        9.06    Determinations for unit Price Work for Invoices
                                                             9.07    Decisions on Requirements of CONTRACT
5.01   Bid Guaranty                                                  Documents / Acceptability of Work
5.02   Performance & Payment Bonds                           9.08    Limitations on CONSTRUCTION MANAGER
5.03   All Bonds                                                     Authority & Responsibilities
5.04   Insurance
5.05   Licenses                                              ARTICLE 10-CHANGES IN THE WORK

ARTICLE 6-CONTRACTOR'S RESPONSIBILITIES                      10.01   Authorized Changes in the Work
                                                             10.02   Unauthorized Changes in the Work
6.01   Supervision and Superintendence                       10.03   Execution of Change Orders
6.02   Labor; Working Hours                                  10.04   Notification to Surety
6.03   Services, Materials, and Equipment
6.04   Progress Schedule                                     ARTICLE 11-COST OF THE WORK FOR CHANGES; OWNER
6.05   "Or-Equals" and Substitutions                         DIRECTED ALLOWANCES; UNIT PRICE WORK
6.06   Concerning Subcontractors, Suppliers, & Others
6.07   Patent Fees and Royalties                             11.01   Cost of the Work for Changes
6.08   Permits                                               11.02   Owner Directed Allowances
6.09   Laws and Regulations                                  11.03   Unit Price Work
6.10   Taxes
6.11   Use of Site and Other Areas


    GENERAL TERMS & CONDITIONS – TABLE OF CONTENTS (Revised 11/16/2009)
   00700-1
ARTICLE 12-CHANGE OF CONTRACT PRICE; CHANGE               16.06   Auditing of Claims
OF CONTRACT TIMES
                                                          ARTICLE 17-MISCELLANEOUS
12.01   Change of CONTRACT Price
12.02   Change of CONTRACT Times                         17.01    Giving Notice
12.03   Delays Beyond CONTRACTOR's Control               17.02    Computation of Time
12.04   Delays Within CONTRACTOR's Control               17.03    Cumulative Remedies
12.05   Delays Beyond DISTRICT's and CONTRACTOR's        17.04    Survival of Obligations
        Control                                          17.05    Controlling Law
12.06   Delay Damages                                    17.06    Notice to Other Agencies
                                                         17.07    No Conflict with Laws or Regulation
ARTICLE 13-WARRANTY AND GUARANTEE, TESTS &               17.08    Advertising
INSPECTIONS,   CORRECTIONS,  REMOVAL    OR               17.09    Non-Solicitation
ACCEPTANCE OF DEFECTIVE WORK
                                                          ARTICLE 18-VALUE ENGINEERING
13.01   Warranty and Guarantee
13.02   Access to Work                                    18.01   General
13.03   Tests and Inspections                             18.02   VEP Preparation
13.04   Uncovering Work                                   18.03   Submission
13.05   Correction or Removal of Defective Work           18.04   DISTRICT Action
13.06   Acceptance of Defective Work                      18.05   Sharing
13.07   DISTRICT May Correct Defective Work               18.06   Subcontracts
13.08   Warranty Period                                   18.07   Substitution
13.09   Extended Warranties and Guarantees
13.10   Special Maintenance Requirements                  ARTICLE 19 – SMALL BUSINESS ENTERPRISE (SBE)
13.11   Extended Warranty Period Due to Defective Work    UTILIZATION

ARTICLE 14-CONTRACT PRICE / INDEMNIFICATION,              ARTICLE 20-PARTNERING
PAYMENTS TO CONTRACTOR & COMPLETION
                                                          20.01   Partnering
14.01   Prompt Payment Procedures
14.02   Schedules of Values                               ARTICLE 21-CONTRACTOR’S REPRESENTATIONS
14.03   Progress Payments
14.04   CONTRACTOR's Warranty of Title                    ARTICLE 22-STANDARDS OF COMPLIANCE
14.05   Substantial Completion
14.06   Partial Utilization of Completed Work             ARTICLE 23-RELATIONSHIP BETWEEN THE PARTIES
14.07   Final Inspection
14.08   Final Payment                                     ARTICLE 24-RECORDS

ARTICLE 15-SUSPENSION OF WORK & TERMINATION               ARTICLE 25-PUBLIC ACCESS

15.01   DISTRICT May Stop the Work                        ARTICLE 26-CONTRACT DOCUMENTS
15.02   Suspension for Convenience
15.03   Termination for Cause                             ARTICLE 27-NOTICES
15.04   Termination for Convenience
15.05   Suspension of CONTRACTOR for Material             ARTICLE 28-MISCELLANEOUS
        Breach of DISTRICT Contracts
                                                          ARTICLE 29-DAVIS BACON ACT
ARTICLE 16-CLAIMS AND DISPUTES
                                                          ARTICLE 30-COPELAND ACT
16.01   General
16.02   Notice
16.03   Step Negotiations
16.04   Mediation
16.05   Litigation




 GENERAL TERMS & CONDITIONS – TABLE OF CONTENTS (Revised 11/16/2009)                                     00700-2
ARTICLE I - DEFINITIONS AND INTERPRETATIONS                                   CONTRACT Price or the CONTRACT Times, issued on or
                                                                              after the Effective Date of the CONTRACT.
1.01 Defined Terms                                                      11.   Claim--A written demand or assertion by DISTRICT or
                                                                              CONTRACTOR seeking an adjustment of CONTRACT Price
 A. Wherever used in the CONTRACT Documents the terms                         or CONTRACT Times, or both. A demand for money or
     listed below will have the meanings indicated which are                  services by a third party is not a Claim.
     applicable to both the singular and plural thereof. Unless         12.   Construction Manager--The authorized representative of the
     stated otherwise in the CONTRACT Documents, words or                     DISTRICT for the Project who has the rights and authority as
     phrases which have a well-known technical or construction                assigned to him/her in the CONTRACT Documents.
     industry or trade meaning are used in the CONTRACT                 13.   CONTRACT--The written instrument which is evidence of the
     Documents in accordance with such recognized meaning.                    agreement between DISTRICT and CONTRACTOR covering
 B. Certain of the following definitions, as indicated with an                the Work to be performed; other CONTRACT Documents are
     asterisk "*", are extracts from Chapter 40E-7, Part VI, F.A.C.,          incorporated in or referenced in the CONTRACT and made a
     the "Small Business Enterprise Contracting Rule" ("SBE                   part thereof as provided therein.
     Rule") of the South Florida Water Management District              14.   CONTRACT Documents--Includes the CONTRACT, the
     ("DISTRICT"). Please refer to a copy of the entire SBE Rule              Request For Bids, the Supplementary Conditions, Instructions
     for a complete list of SBE definitions and a full description of         To Bidders, General Terms & Conditions, Bid Forms,
     each.                                                                    DISTRICT's Post Award forms, Specifications, the Drawings,
 1. Addenda--Written or graphic instruments issued prior to the               Addenda, the Bonds, the Insurance, SBE Utilization Plan,
     opening of Bids which modify or interpret the CONTRACT                   together with all Written Amendments, Change Orders, Field
     Documents by additions, deletions, corrections or                        Orders, and DISTRICT's and DESIGN ENGINEER's written
     clarifications.                                                          interpretations and clarifications issued on or after the
 2. Acceptance, Final Acceptance-- The formal action by the                   Effective Date of the CONTRACT. Approved Shop Drawings
     DISTRICT accepting the Work as being complete after review               and the reports and drawings of subsurface and physical
     by Construction Manager of final completion.                             conditions are not CONTRACT Documents. Only printed or
 3. Apparent Low Bidder – Bidder whom has submitted the                       hard copies of the items listed in this paragraph are
     lowest price but has not yet been deemed responsive and                  CONTRACT Documents. Files in electronic media format of
     responsible by the DISTRICT.                                             text, data, graphics, and the like that may be furnished by
 4. Application for Payment--The form furnished in the                        DISTRICT to CONTRACTOR are not CONTRACT
     CONTRACT documents which is to be used by                                Documents and such files are furnished only for the
     CONTRACTOR during the course of the Work in requesting                   convenience of the receiving party.
     progress or final payments and which is to be accompanied by       15.   CONTRACT Price--The total compensation, subject to
     such supporting documentation as is required by the                      authorized adjustments, payable by DISTRICT to
     CONTRACT Documents. Each application shall contain an                    CONTRACTOR for satisfactory completion of the Work in
     affidavit by CONTRACTOR that partial payments received                   accordance with the CONTRACT Documents as stated in the
     from DISTRICT for the Work have been applied by                          CONTRACT.
     CONTRACTOR to discharge in full all of CONTRACTOR'S                16.   CONTRACT Times--The number of days or the dates stated in
     obligations stated in prior Applications For Payment.                    the CONTRACT to complete the work.
 5. Asbestos--Any material that contains more than one percent          17.   CONTRACTOR--The individual or legal entity with whom the
     asbestos and is friable or is releasing asbestos fibers into the         DISTRICT has entered into the CONTRACT for performance
     air above current action levels established by the United States         of the Work.
     Occupational Safety and Health Administration.                     18.   Contractor’s Fee—The total compensation, payable by the
 6. Bid--The written offer of a Bidder submitted in the prescribed            DISTRICT to the CONTRACTOR, for use with Change
     manner on the prescribed forms to perform the Work in                    Orders as set forth in Article 12.01.C. The CONTRACTOR’s
     accordance with the CONTRACT Documents. It shall be                      fee shall include all costs for overhead and profit.
     considered a formal offer.                                         19.   Cost of the Work--See paragraph 11.01.A for definition.
 7. Bidding Documents--The Bidding Requirements and the                 20.   Day--A day shall constitute a calendar day of 24 hours
     CONTRACT Documents (including all Addenda issued prior                   measured from midnight to the next midnight except in cases
     to receipt of Bids).                                                     where the term Day is otherwise defined herein.
 8. Bidding Requirements--The Advertisement or Request for              21.   DISTRICT--The South Florida Water Management
     Bid, Instructions to Bidders, Bid security form, if any,                 DISTRICT, a public corporation of the State of Florida, 3301
     Statement of Intent to Perform as an SBE Subcontractor,                  Gun Club Road, West Palm Beach, Florida; the OWNER.
     Schedule of Subcontractor / SBE Participation, Statement of        22.   Drawings--That part of the CONTRACT Documents which
     Business Organization, and the Bid form with any                         graphically shows the scope, extent, and character of the Work
     supplements.                                                             to be performed by CONTRACTOR. Shop Drawings and
 9. Bonds--Bid, performance and payment bonds and other                       other CONTRACTOR submittals are not Drawings as so
     instruments of security designated in the General Terms &                defined.
     Conditions.                                                        23.   Design Engineer--The individual or legal entity named as such
 10. Change Order--A written instrument which when signed by                  in the CONTRACT Documents who designed the project and
     the DISTRICT authorizes an addition, deletion and/or revision            has the rights and authority assigned to DESIGN ENGINEER
     in the CONTRACT Documents, or an adjustment in the                       in the CONTRACT Documents. The term "DESIGN


   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                             00700-2-2
      ENGINEER" means DESIGN ENGINEER or its                                  square inch absolute), such as oil, petroleum, fuel oil, oil
      representative.                                                         sludge, oil refuse, gasoline, kerosene, and oil mixed with other
24.   Effective Date of the CONTRACT--The date indicated in the               non-Hazardous Waste and crude oils.
      CONTRACT on which it becomes effective, but if no such            42.   Project--The total construction of which the Work to be
      date is indicated, it means the date on which the CONTRACT              performed under the CONTRACT Documents may be the
      is signed and delivered by the last of the two parties to sign          whole, or a part as may be indicated elsewhere in the
      and deliver.                                                            CONTRACT Documents.
25.   Field Order--A written order issued by DISTRICT which             43.   Radioactive Material--Source, special nuclear, or byproduct
      orders minor variations in the Work, and which does not                 material as defined by the Atomic Energy Act of 1954 (42
      involve a change in the CONTRACT Price or the                           USC Section 2011 et seq.) as amended from time to time.
      CONTRACT Times.                                                   44.   Responsible--A firm is capable in all respects to fully perform
26.   Fifty Percent Completion -- 50% of the total cost of the                the CONTRACT requirements and has the integrity and
      services purchased by the DISTRICT as defined in the                    reliability which will assure good faith performance.
      contract documents, including all other costs associated with     45.   Responsive--A firm's bid conforms in all material respects to
      change orders.                                                          the request for bid and shall include compliance with SBE
27.   General Requirements--Sections of Division I of the                     goals.
      Specifications. The General Requirements pertain to all           46.   Request for Information (RFI) - A written request, from the
      sections of the Specifications.                                         Contractor to the Engineer, that asks for additional
28.   Hazardous Environmental Condition--The presence at the Site             information or to clarify some aspect of the project, such as
      of Asbestos, PCBs, Petroleum, Hazardous Waste, Radioactive              procedures,       equipment,        materials,     specification
      Material in such quantities or circumstances that may present a         details or drawing details
      substantial danger to persons or property exposed thereto in      47.   Samples--Physical examples of materials, equipment, or
      connection with the Work.                                               workmanship that are representative of some portion of the
29.   Hazardous Waste--The term Hazardous Waste shall have the                Work and which establish the standards by which such
      meaning provided in Section 1004 of the Solid Waste                     portion of the Work will be judged.
      Disposal Act (42 USC Section 6903) as amended from time to        48.   Schedule of Values— A document furnished by the
      time.                                                                   CONTRACTOR to the DISTRICT reflecting a reasonable
30.   Laws and/or Regulations--Any and all applicable laws rules,             allowance of costs associated with the various parts of the
      regulations, ordinances, codes, and orders of any and all               work totaling the entire bid amount, and used as a basis for
      governmental bodies, agencies, authorities, and courts having           reviewing the CONTRACTOR’S Applications for Payment.
      jurisdiction.                                                           Shall not be used as the basis for change orders.
31.   Lien--Charges, security interest, or encumbrances upon            49.   Shop Drawings--All drawings, diagrams, illustrations,
      Project funds, real property, or personal property.                     schedules, and other data or information which are specifically
32.   Liquidated Damages --The damages the DISTRICT might                     prepared or assembled by or for CONTRACTOR and
      incur if the Project is not completed within the time                   submitted by CONTRACTOR to illustrate some portion of the
      specified.                                                              Work.
33.   Material Breach- Any substantial, unexcused non-                  50.   Site--Lands or areas indicated in the CONTRACT Documents
      performance. The breach is either failing to perform an act             as being furnished by DISTRICT upon which the Work is to
      that is an important part of the transaction or performing an           be performed, including rights-of-way and easements for
      act inconsistent with the terms and conditions of the contract.         access thereto, and such other lands furnished by DISTRICT
34.   Milestone--A principal event specified in the CONTRACT                  which are designated for the use of CONTRACTOR .
      Documents relating to an intermediate completion date or time     51.   *"Small Business Enterprise" or "SBE"—is as defined in 40E-
      prior to Substantial Completion of all the Work.                        7.669(9), F.A.C.
35.   Notice of Intent to Award--The written official notice by         52.   Specifications--That part of the CONTRACT Documents
      DISTRICT of the apparent successful responsive and                      consisting of written technical descriptions of materials,
      responsible bidder.                                                     equipment, systems, standards, and workmanship as applied to
36.   Notice of Apparent Low Bidder--The written unofficial notice            the Work and certain administrative details applicable thereto.
      by DISTRICT of the apparent low bidder.                           53.   Subcontractor--An individual or legal entity having a direct
37.   Notice to Proceed--A written notice given by DISTRICT to                CONTRACT with CONTRACTOR or with any other
      CONTRACTOR authorizing CONTRACTOR to proceed                            Subcontractor for the performance of a part of the Work at the
      with the work and establishing the date of commencement of              Site.
      the CONTRACT Times.                                               54.   Substantial Completion--The time at which the Work (or a
38.   OWNER-- Refer to definition of DISTRICT.                                specified part thereof) has progressed to the point where, in
39.   Partial Utilization--Use by DISTRICT of a substantially                 the opinion of DISTRICT, the Work (or a specified part
      completed part of the Work for the purpose for which it is              thereof) is sufficiently complete, in accordance with the
      intended (or a related purpose) prior to Substantial Completion         CONTRACT Documents, so that the Work (or a specified part
      of all the Work.                                                        thereof) can be utilized for the purposes for which it is
40.   PCBs--Polychlorinated biphenyls.                                        intended and shall begin the warranty period. The terms
41.   Petroleum--Petroleum, including crude oil or any fraction               "substantially complete" and "substantially completed" as
      thereof which is liquid at standard conditions of temperature           applied to all or part of the Work refer to Substantial
      and pressure (60 degrees Fahrenheit and 14.7 pounds per                 Completion thereof.


  GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-3
 55. Supplementary Conditions--That part of the CONTRACT                 2.03 Commencement of CONTRACT Time; Notice to Proceed: The
     Documents which amends or supplements these General                 period of performance of this CONTRACT shall commence upon
     Terms & Conditions.                                                 the effective date of the Notice to Proceed and continue for a period
 56. Supplier--A manufacturer, fabricator, supplier, distributor,        as indicated on the cover/signature page of this CONTRACT,
     materialman, or vendor having a direct CONTRACT with                including punchlist work (Contract Time). The CONTRACTOR
     CONTRACTOR or with any Subcontractor to furnish                     shall not proceed with work under this CONTRACT until a Notice to
     materials or equipment to be incorporated in the Work by            Proceed is received from the DISTRICT.
     CONTRACTOR or any Subcontractor.
 57. Underground Facilities--All underground pipelines, conduits,        2.04 Starting the Work: CONTRACTOR shall start to perform the
     ducts, cables, wires, manholes, vaults, tanks, tunnels, or other    Work on the date indicated in the Notice to Proceed. No Work shall
     such facilities or attachments, and any encasements containing      be done at the Site prior to that date.
     such facilities, including those that convey electricity, gases,
     steam, liquid petroleum products, telephone or other                2.05 Before Starting Construction
     communications, cable television, water, wastewater, storm
     water, other liquids or chemicals, or traffic or other control      A. CONTRACTOR's Review of CONTRACT Documents: Before
     systems.                                                               undertaking each part of the Work, CONTRACTOR shall
 58. Unilateral Change Order-- A written change order issued by             carefully study and compare the CONTRACT Documents and
     DISTRICT which orders variations in the Work, and which                check and verify pertinent figures therein and all applicable
     involves a change in the CONTRACT Price or the                         field measurements. CONTRACTOR shall immediately report,
     CONTRACT Times.                                                        in writing, to DISTRICT any conflict, error, ambiguity, or
 59. Unit Price--Amount stated in the CONTRACT Documents as                 discrepancy which CONTRACTOR or any of its
     a price per unit of measurement for materials or services              Subcontractors or Suppliers may discover and shall obtain a
     required.                                                              written interpretation or clarification from DISTRICT before
 60. Unit Price Work--Work to be paid for on the basis of unit              proceeding with any Work affected thereby.
     prices.                                                             B. Preliminary Schedules: Within ten (10) days after the Effective
 61. Work--Any and all obligations, duties, responsibilities, labor,        Date of the CONTRACT (unless otherwise specified in the
     materials, equipment, temporary facilities, utilities, and             General Requirements), CONTRACTOR shall submit to
     incidentals and the furnishing thereof necessary to complete           DISTRICT for its timely review:
     the construction assigned to, or undertaken by
     CONTRACTOR pursuant to the CONTRACT Documents.                      1.   A preliminary progress schedule indicating the times (numbers
     Also, the completed construction or parts thereof required to            of days or dates) for starting and completing the various stages
     be provided under the CONTRACT Documents, including all                  of the Work, including any Milestones specified in the
     materials, equipment, and supplies incorporated or to be                 CONTRACT Documents. It shall cover the first ninety (90)
     incorporated in the construction.                                        calendar days of the CONTRACT duration unless otherwise
 62. Written Amendment--A written statement modifying the                     modified in the Supplementary Conditions.
     CONTRACT Documents, signed by the parties indicated in              2.   A preliminary schedule of Shop Drawing and Sample
     the Amendment, on or after the Effective Date of the                     submittals which will list each required submittal and the times
     CONTRACT and normally dealing with the non-engineering                   for submitting it in keeping with the GENERAL
     or non-technical rather than strictly construction-related               REQUIREMENTS; and
     aspects of the CONTRACT Documents.                                  3.   A preliminary Schedule of Values for all of the Work which
                                                                              shall include quantities and prices of items which, when added
ARTICLE 2 - PRELIMINARY MATTERS                                               together, equal the CONTRACT Price, and shall subdivide the
                                                                              Work into component parts in sufficient detail to serve as the
2.01 Delivery of Performance and Payment Bonds:                               basis for progress payments only during performance of the
CONTRACTOR shall deliver to DISTRICT such Bonds as                            Work. Such prices will include an appropriate amount of
CONTRACTOR is required to furnish within seven (7) working                    overhead and profit applicable to each item of Work.
days of the date of Notice of Apparent Low Bidder from the               4.   A tentative procurement schedule of equipment and materials.
DISTRICT.
          A. Bid/Quote Price: Bids/Quote price received will be          C. Evidence of Insurance: The CONTRACTOR shall purchase
valid for ninety (90) days after the opening date of the solicitation.      and maintain insurance coverage reflecting, at a minimum, the
                                                                            amounts and conditions as specified within the DISTRICT's
2.02 Copies of Documents: DISTRICT shall furnish to                         Insurance Requirements Checklist, as further detailed in Article
CONTRACTOR up to six copies of the CONTRACT Documents                       5. The CONTRACTOR shall provide the certificate within
free of charge. Up to six copies of change information will be              seven (7) working days of the date of the Notice of Apparent
provided during the course of the CONTRACT. CONTRACTOR                      Low Bidder.
will be responsible for preparing additional copies at his expense.         The CONTRACTOR shall have ninety (90) business days after
DISTRICT will make a reproducible set available to the                      CONTRACT execution, to produce the required Insurance
CONTRACTOR’S designated plan reproduction firm for the                      Declaration Page of Policy for the insurance requirements set
specific use of copying only.                                               forth in the General Terms & Conditions, and the Insurance
                                                                            Requirements Checklist included herein.



   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-4
2.06 Preconstruction Conference: A conference attended by              shall determine the method, details and means of performing the
CONTRACTOR, DISTRICT, and others as appropriate will be                services. The DISTRICT may provide additional guidance and
held to establish a working understanding among the parties as to      instructions to CONTRACTOR’s employees, subcontractors or hired
the Work and to discuss the schedules referred to in paragraph         workers where necessary or appropriate as determined by the
2.05.B, procedures for handling Shop Drawings and other                DISTRICT. Upon request and at the DISTRICT’s expense,
submittals, processing Applications for Payment, and maintaining       CONTRACTOR shall conduct background checks for any
required records. CONTRACTOR shall attend such conference              CONTRACTOR employee or hired worker providing services to
and shall require any or all of the subcontractors and suppliers, as   the DISTRICT.
the DISTRICT requests, to attend the conference.
                                                                       B. Contract Time/Liquidated Damages
2.07 Initial Acceptance of Schedules: Prior to the submission of the
first Application for Payment by CONTRACTOR, the schedules             1.   Unless extended or terminated, the period of performance of this
submitted in accordance with paragraph 2.05.B must be reviewed              CONTRACT shall commence upon the effective date of the
by the DISTRICT and be corrected and/or revised by the                      Notice to Proceed and continue for a period as indicated on the
CONTRACTOR if deemed necessary by the DISTRICT. No                          cover/signature page of this CONTRACT, including punchlist
progress payment shall be made to CONTRACTOR until final                    work (Contract Time). The CONTRACTOR shall not proceed
schedules are submitted to DISTRICT.                                        with work under this CONTRACT until a Notice to Proceed is
                                                                            received from the DISTRICT.
1.   The progress schedule will be acceptable to DISTRICT if it        2.   Time is of the essence for this CONTRACT. Therefore, if the
     provides an orderly progression of the Work to completion              CONTRACTOR fails, or refuses, to perform the work, or any
     within any specified Milestones and the CONTRACT Times.                separable part thereof, with such diligence as will insure the
     Such acceptance will not impose on DISTRICT's responsibility           completion of the same, or fails, for any reason, to complete
     for the progress schedule, for sequencing, scheduling, or              such work within the time limit specified, or any extension
     progress of the Work nor interfere with or relieve                     thereof granted, then the CONTRACTOR shall be liable to pay
     CONTRACTOR from CONTRACTOR's full responsibility                       the DISTRICT not as a penalty, but as liquidated damages, the
     therefore.                                                             sum as indicated in on the cover/signature page of this
2.   CONTRACTOR's schedule of Shop Drawing and Sample                       CONTRACT, for each calendar day that the work remains
     submittals will be acceptable to DISTRICT if it provides a             incomplete after the expiration of the time limit specified or any
     workable arrangement for reviewing and processing the                  extension thereof, plus any moneys which are paid by the
     required submittals.                                                   DISTRICT to any other person, firm or corporation, for services
3.   CONTRACTOR's schedule of values will be acceptable to                  rendered for the preservation or completion of the work.
     DISTRICT as to form and substance as a basis for payment if it    3.   Two-Tiered Liquidated Damages: the higher level of damages
     provides a reasonable allocation of the CONTRACT Price to              shall be assessed from the calculated Completion Date until
     component parts of the Work. The Schedule of Values shall not          such date as the CONTRACTOR attains Substantial
     be used as a basis of cost for change order work and does not          Completion. Beyond the date of attainment of Substantial
     relieve CONTRACTOR from CONTRACTOR's full                              Completion, and until the CONTRACTOR attains FINAL
     responsibility therefore.                                              COMPLETION, the lower level of Liquidated Damages shall
4.   Price for mobilization and demobilization shall be distributed         be assessed. Total Liquidated Damages shall be assessed shall
     such that the mobilization and demobilization charges are              be the sum of the upper and lower levels of Liquidated
     equal. The demobilization shall be paid in the last Application        Damages.
     for Payment.                                                      4.   Single-Tiered Liquidated Damages: the Liquidated Damages
                                                                            assessed shall be calculated from the calculated Completion
A. Statement of Work                                                        Date until such date as the CONTRACTOR attains FINAL
                                                                            COMPLETION.
The CONTRACTOR shall furnish all equipment, tools, materials,          5.   Such moneys shall be chargeable to the CONTRACTOR and
labor and everything known and necessary and shall complete all             shall be deducted from any moneys due said CONTRACTOR,
required Work as specified in the CONTRACT Documents. The                   or if no money is due or the amount due is insufficient to cover
project for which the Work under the CONTRACT Documents may                 the amount charged, then the CONTRACTOR and its Surety
be the whole or only a part is generally described on the                   shall be liable for said amount.
cover/signature page of this CONTRACT.                                 6.   The foregoing Liquidated Damages amounts are
                                                                            acknowledged by the parties to be reasonable and justified in
The CONTRACTOR shall, to the satisfaction of the DISTRICT,                  this case, given the difficulty of assessing actual damages as a
fully and timely perform all work items described in the Plans and          result of delays to the Work on the Project. The parties
Specifications attached hereto, and made a part of this CONTRACT.           understand that the foregoing amounts are NOT a penalty.
In the event CONTRACTOR employees, subcontractors or hired             7.   Payments may be reduced by any liquidated damages
workers are authorized to perform services on-site at DISTRICT              amounts properly assessed under the terms of the Contract
facilities, the CONTRACTOR hereby agrees to be bound by all                 Documents.
applicable DISTRICT policies and standards of conduct. It is the
CONTRACTOR’s responsibility to advise its employees,
subcontractors or hired workers of the nature of the project, as
described in the CONTRACT Documents. The CONTRACTOR


     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                            00700-2-5
ARTICLE 3 - CONTRACT                  DOCUMENTS:          INTENT,            applicability to the Work.
AMENDING, REUSE                                                         b.   Where compliance with an industry standard is required,
                                                                             standard in effect shall be stated in Article 3.02.A.1.
3.01 Intent                                                             c.   Where an applicable code or standard has been revised and
                                                                             reissued after the date of the CONTRACT Documents and
A. The CONTRACT Documents comprise the entire agreement                      before performance of Work affected, the DISTRICT will
   between the DISTRICT and CONTRACTOR concerning the                        decide upon the updated standard.
   Work. The CONTRACT Documents are complementary; what                 d.   Where compliance with two or more standards is specified, and
   is called for by one is as binding as if called for by all. The           they establish different or conflicting requirements for
   CONTRACT Documents will be governed by the laws of the                    minimum quantities or quality levels, the most stringent
   State of Florida.                                                         requirement will be enforced, unless the CONTRACT
B. It is the intent of the CONTRACT Documents to describe a                  Documents indicate otherwise. Refer requirements that are
   functionally complete Project (or part thereof) to be constructed         different but apparently equal, and uncertainties as to which
   in accordance with the CONTRACT Documents. Any labor,                     quality level is more stringent, to the DISTRICT for a decision
   documentation, services, materials, or equipment that may                 before proceeding.
   reasonably be inferred from the CONTRACT Documents or                e.   In every instance the quantity or quality level shown or
   from prevailing custom or trade usage as being required to                specified shall be the minimum to be provided or performed.
   produce the intended result will be provided whether or not               The actual installation may comply exactly, within specified
   specifically called for at no additional cost to DISTRICT.                tolerances, with the minimum quantity or quality specified, or it
C. Clarifications and interpretations of the CONTRACT                        may exceed that minimum within reasonable limits. In
   Documents shall be issued by DISTRICT as provided in Article              complying with these requirements, indicated numeric values
   9.04.                                                                     are minimum or maximum values, as noted, or appropriate for
                                                                             the context of the requirements. Refer instances of uncertainty
3.02 Reference Standards                                                     to the Engineer for a decision before proceeding.
                                                                        f.   Each entity engaged in construction on the Project is required to
A.       Standards, Specifications, Codes, Laws, and Regulations             be familiar with industry standards applicable to that entity’s
                                                                             construction activity. Copies of applicable standards are not
1.   Reference to standards, specifications, manuals, or codes of any        bound with the CONTRACT Documents.
     technical society, organization, or association, or to Laws or          1) Where copies of standards are needed for performance of a
     Regulations, whether such reference be specific or by                        required construction activity, the CONTRACTOR shall
     implication, shall mean the standard, specification, manual,                 obtain copies directly from the publication source.
     code, or Laws or Regulations in effect at the time of opening of        2) Abbreviation of Names: Trade association names and titles
     Bids (or on the Effective Date of the CONTRACT if there were                 of general standards are frequently abbreviated. Where
     no Bids), except as may be otherwise specifically stated in the              such acronyms or abbreviations are used in the
     CONTRACT Documents.                                                          Specifications or other CONTRACT Documents, they
2.   No provision of any such standard, specification, manual or                  mean the recognized name of the trade association,
     code, or any instruction of a Supplier shall be effective to                 standards generating organizing, authority having
     change the duties or responsibilities of DISTRICT,                           jurisdiction, or other entity applicable to the context of the
     CONTRACTOR, or DESIGN ENGINEER, or any of their                              text provision.
     subcontractors, consultants, agents, or employees from those
     set forth in the CONTRACT Documents, nor shall any such            3.03 Reporting and Resolving Discrepancies
     provision or instruction be effective to assign to DISTRICT,
     DESIGN ENGINEER, or any of DISTRICT's Consultants,                 A. Reporting Discrepancies: If, during the performance of the
     agents, or employees any duty or authority to supervise or         Work, CONTRACTOR, or any of his Subcontractors or Suppliers,
     direct the performance of the Work or any duty or authority to     discovers any conflict, error, ambiguity, or discrepancy within the
     undertake responsibility inconsistent with the provisions of the   CONTRACT Documents or between the CONTRACT Documents
     CONTRACT Documents.
                                                                        and any provision of any Law or Regulation applicable to the
B.       Industry Standards                                             performance of the Work or of any standard, specification, manual
                                                                        or code, or of any instruction of any Supplier, CONTRACTOR
1.   Applicability of Standards: Except where the CONTRACT              shall report it to DISTRICT in writing at once but in no event later
     Documents include more stringent requirements, applicable          than seventy-two (72) hours. CONTRACTOR shall not proceed
     construction industry standards have the same force and effect     with the Work affected thereby (except in an emergency as
     as if bound or copied directly into the CONTRACT                   required by paragraph 6.16.) until obtaining a written clarification
     Documents.      Such standards are made a part of the              from the DISTRICT. After CONTRACTOR's discovery of such a
     CONTRACT Documents by reference and are stated in each
                                                                        conflict, error or discrepancy, or after the date when
     section.
                                                                        CONTRACTOR should have reasonably known thereof, until the
a.   Referenced standards, referenced directly in CONTRACT              interpretation or clarification is obtained from the DISTRICT, any
     Documents or by governing regulations, have precedence over        Work done by CONTRACTOR which is directly or indirectly
     nonreferenced standards which are recognized in industry for       affected by same, will be at CONTRACTOR's own risk and


     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                              00700-2-6
CONTRACTOR shall bear all costs and delay arising therefrom.
                                                                        A. DISTRICT shall furnish the Site:
B. Resolving Discrepancies                                                 1. DISTRICT shall notify CONTRACTOR of any
                                                                                encumbrances or restrictions not of general application but
1.   Except as may be otherwise specifically stated in the                      specifically related to use of the Site with which
     CONTRACT Documents, the provisions of the CONTRACT                         CONTRACTOR must comply in performing the Work.
     Documents shall take precedence in resolving any conflict,            2. DISTRICT will obtain in a timely manner and pay for
     error, ambiguity, or discrepancy between the provisions of the             easements for permanent structures or permanent changes
     CONTRACT Documents and:                                                    in existing facilities. If CONTRACTOR and DISTRICT
     a) The provisions of any standard, specification, manual,                  are unable to agree on entitlement to or on the amount or
          code, or instruction (whether or not specifically                     extent, if any, of any adjustment in the CONTRACT Price
          incorporated by reference in the CONTRACT                             or CONTRACT Times, or both, as a result of any delay in
          Documents); or                                                        DISTRICT's furnishing the Site, CONTRACTOR may
     b) The provisions of any Laws or Regulations applicable to                 make a Claim therefore as provided in paragraph 16.02.
          the performance of the Work (unless such an                      3. In the event that the DISTRICT provides the
          interpretation of the provisions of the CONTRACT                      CONTRACTOR with keys to access to any DISTRICT
          Documents would result in violation of such Law or                    structures or Right-of-Ways through its key permitting
          Regulation).                                                          system, a deposit shall apply. Because the cost to re-key
                                                                                DISTRICT         structures    is   high,    should     the
2.   In resolving such conflicts, errors or discrepancies, the                  CONTRACTOR lose any keys provided by the
     CONTRACT Documents shall be given preference as specified                  DISTRICT, such loss shall not only result in the loss of
     in the CONTRACT.                                                           the CONTRACTOR’s deposit, but may also result in the
3.   In all cases where notes, specifications, sketches, diagrams,              assessment of progressively higher fines depending on
     details or schedules in the Specifications or Drawings, or                 how many keys may have been lost throughout the term
     between the Specifications and Drawings, conflict, the higher              of this CONTRACT or across multiple contracts between
     cost requirements shall be furnished by CONTRACTOR unless                  the CONTRACTOR and the DISTRICT. The DISTRICT
     otherwise directed by the DISTRICT.                                        reserves the right to offset the amounts owed pursuant to
                                                                                this provision against payments due to the
3.04 Amending and Supplementing CONTRACT Documents                              CONTRACTOR under this CONTRACT and/or against
                                                                                payments due under any other contracts or purchase
A. The CONTRACT Documents may be amended to provide for                         orders between the DISTRICT and CONTRACTOR.
   additions, deletions, and revisions in the Work or to modify the             Repeated loss of keys may also be used as a basis for
   terms and conditions thereof in one or more of the following                 deeming the CONTRACTOR as non-responsible in
   ways: (i) a Written Amendment or (ii) a Change Order.                        conjunction with bid or proposal submissions.
B. The requirements of the CONTRACT Documents may be                    B. Governmental Entity: The DISTRICT is a governmental entity.
   supplemented, and minor variations and deviations in the Work           Accordingly, the provisions of Chapter 713, Florida Statutes
   may be authorized, by one or more of the following ways: (i) a          concerning construction liens, do not apply to lands owned by
   Field Order; (ii) DESIGN ENGINEER's approval of a Shop                  the DISTRICT.
   Drawing or Sample; or (iii) DISTRICT's written interpretation        C. Additional Lands: CONTRACTOR shall provide for all
   or clarification, which will not require adjustments on the             additional lands and access thereto that may be required for
   CONTRACT Price or CONTRACT Times.                                       temporary construction facilities or storage of materials and
                                                                           equipment.
3.05 Reuse of Documents: CONTRACTOR and any Subcontractor
or Supplier or other individual or entity performing or furnishing      4.02 Subsurface and Physical Conditions
any of the Work under a direct or indirect CONTRACT with
DISTRICT: (i) shall not have or acquire any title to or ownership       A. Reports and Drawings: The Supplementary Conditions,
rights in any of the Drawings, Specifications, or other documents (or      identify, if any:
copies of any thereof), including electronic media editions; and (ii)      1. Reports of explorations and tests of subsurface conditions
shall not reuse any of such Drawings, Specifications, other                    at or contiguous to the Site that DESIGN ENGINEER has
documents, or copies thereof on extensions of the Project or any               used in preparing the CONTRACT Documents; and
other project without prior written consent of DISTRICT. This              2. Drawings of physical conditions in or relating to existing
prohibition will survive final payment, completion, and acceptance             surface or subsurface structures at or contiguous to the Site
of the Work, or termination or completion of the CONTRACT.                     (except Underground Facilities) that DESIGN ENGINEER
Nothing herein shall preclude CONTRACTOR from retaining                        has used in preparing the CONTRACT Documents.
copies of the CONTRACT Documents for record purposes. Please
also refer to Article 24 – Records.                                     B. Limited Reliance by CONTRACTOR on Technical Data
                                                                           Authorized: Reports and drawings are not CONTRACT
ARTICLE 4 - AVAILABILITY OF LANDS; SUBSURFACE                              Documents. CONTRACTOR may not rely upon or make any
AND PHYSICAL CONDITIONS; REFERENCE POINTS                                  claim against DISTRICT, ENGINEER or any of ENGINEER’s
                                                                           Consultants with respect to:
4.01 Availability of Lands                                                 1. The completeness of such reports and drawings for


     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                           00700-2-7
         CONTRACTOR's purposes, including, but not limited to,                  adversely impacted.         Upon such a showing,
         any aspects of the means, methods, techniques, sequences,              CONTRACTOR shall be entitled only to such an
         and procedures of construction to be employed by                       extension equivalent to such actual adverse impact in the
         CONTRACTOR, and safety precautions and programs                        critical path.
         incident thereto; or
    2.   Other data, interpretations, opinions, and information       2.   CONTRACTOR shall not be entitled to any adjustment in the
         contained in such reports or shown or indicated in such           CONTRACT Price or CONTRACT Times if:
         drawings; or                                                      a. CONTRACTOR knew of the existence of such conditions
    3.   Any CONTRACTOR interpretation of or conclusion                       at the time CONTRACTOR made a final commitment to
         drawn from any "technical data" or any such other data,              DISTRICT in respect of CONTRACT Price and
         interpretations, opinions, or information.                           CONTRACT Times by the submission of a Bid or
                                                                              becoming bound under a negotiated contract; or
4.03 Differing Subsurface or Physical Conditions                           b. The existence of such condition could reasonably have
                                                                              been discovered or revealed as a result of any examination,
A. CONTRACTOR shall promptly, but in no event later than ten                  investigation, exploration, test, or study of the Site and
   (10) days after becoming aware thereof and before the                      contiguous areas required by the Bidding Requirements or
   conditions are disturbed, give a written notice to DISTRICT                CONTRACT Documents to be conducted by or for
   of (i) subsurface or latent physical conditions at the Site                CONTRACTOR prior to CONTRACTOR's making such
   which differ materially from those indicated in the Contract               final commitment; or
   Documents, or (ii) unknown physical conditions at the Site, of          c. CONTRACTOR failed to give the written notice within
   an unusual nature, which differ materially from those                      the time and as required by paragraph 4.03.A.
   ordinarily encountered and generally recognized as inherent in
   work of the character called for by the Contract Documents.        3.   If DISTRICT and CONTRACTOR are unable to agree on
                                                                           entitlement to or on the amount or extent, if any, of any
    DISTRICT will investigate the Site conditions promptly after           adjustment in the CONTRACT Price or CONTRACT Times,
    receiving the notice. If the conditions do materially so differ        or both, a Claim may be made therefore as provided in
    and cause an increase or decrease in the CONTRACTOR's                  paragraph 16.02. However, DISTRICT, DESIGN ENGINEER,
    cost of, or the time required for, performing any part of the          and its CONTRACTORS shall not be liable to
    Work, whether or not changed as a result of the conditions, an         CONTRACTOR for any claims, costs, losses, or damages
    equitable adjustment shall be made under this clause and               (including but not limited to all fees and charges of engineers,
    the Contract Price or Times modified in writing by Change              architects, attorneys, and other professionals and all court or
    Order in accordance with Article 10.                                   arbitration or other dispute resolution costs) sustained by
                                                                           CONTRACTOR on or in connection with any other project or
    No request by CONTRACTOR for an equitable adjustment                   anticipated project.
    under this paragraph shall be allowed unless CONTRACTOR
    has given the written notice required;                            4.04 Underground Facilities

                                                                      A. Shown or Indicated: The information and data shown or
    The provisions of this paragraph are not intended to apply to a      indicated in the CONTRACT Documents with respect to
    Hazardous Environmental Condition uncovered or revealed at           existing Underground Facilities at or contiguous to the Site is
    the Site.                                                            based on information and data furnished to DISTRICT or
                                                                         DESIGN ENGINEER by the owners of such Underground
B. DISTRICT's Review: After receipt of written notice as required        Facilities, including DISTRICT, or by others. Unless it is
   by paragraph 4.03.A, DISTRICT will promptly review the                otherwise expressly provided in the Supplementary Conditions:
   pertinent condition, determine the necessity of obtaining
   additional exploration or tests with respect thereto, and advise        1.   DISTRICT shall not be responsible for the accuracy or
   CONTRACTOR in writing of findings and conclusions.                           completeness of any such information or data; and
                                                                           2.   The cost of the following will be included in the
C. Possible Price and Times Adjustments                                         CONTRACT Price, and CONTRACTOR shall have full
1. The CONTRACT Price or the CONTRACT Times, or both,                           responsibility for:
   may be adjusted to the extent that the existence of such                     a. reviewing and checking all such information and data;
   differing subsurface or physical condition causes an increase or             b. locating all Underground Facilities shown or indicated
   decrease in CONTRACTOR's cost of, or time required for,                          in the CONTRACT Documents;
   performance of the Work; subject, however, to the following:                 c. coordination of the Work with the owners of such
   a. such condition must meet any one or more of the                               Underground Facilities, including DISTRICT, during
        categories described in paragraph 4.03.A; and                               construction; and
   b. with respect to Work that is paid for on a Unit Price Basis,              d. the safety and protection of all such Underground
        any adjustment in CONTRACT Price will be subject to the                     Facilities and repairing any damage thereto resulting
        provisions of paragraphs 9.08 and 11.03, and                                from the Work.
   c. In order to be entitled to an increase in time for
        performance of the Work, CONTRACTOR must establish
        that its critical path of construction performance has been

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                            00700-2-8
B. Not Shown or Indicated                                                    of the CONTRACT Documents.
                                                                          B. Limited Reliance by CONTRACTOR on Technical Data
1.   If an Underground Facility is uncovered or revealed at or               Authorized: CONTRACTOR may rely upon the general
     contiguous to the Site which was not shown or indicated, or not         accuracy of the "technical data" contained in such reports and
     shown or indicated with reasonable accuracy in the                      drawings, but such reports and drawings are not CONTRACT
     CONTRACT Documents, CONTRACTOR shall, immediately                       Documents. Such "technical data" is identified in the
     after becoming aware thereof and before further disturbing              Supplementary Conditions. Except for such reliance on such
     conditions affected thereby or performing any Work in                   "technical data" as described in the Supplemental Conditions,
     connection therewith (except in an emergency as required by             CONTRACTOR may not rely upon or make any Claim against
     paragraph 6.16), identify the owner of such Underground                 DISTRICT, DESIGN ENGINEER or any of its Consultants
     Facility and give written notice to that owner and to                   with respect to:
     DISTRICT. DISTRICT will promptly review the Underground                 1. The completeness of such reports and drawings for
     Facility and determine the extent, if any, to which a change is              CONTRACTOR's purposes, including, but not limited to,
     required in the CONTRACT Documents to reflect and                            any aspects of the means, methods, techniques, sequences
     document the consequences of the existence or location of the                and procedures of construction to be employed by
     Underground Facility. During such time, CONTRACTOR                           CONTRACTOR and safety precautions and programs
     shall be responsible for the safety and protection of such                   incident thereto; or
     Underground Facility.                                                   2. Other data, interpretations, opinions and information
2.   If DISTRICT concludes that a change in the CONTRACT                          contained in such reports or shown or indicated in such
     Documents is required, a Change Order may be issued to reflect               drawings; or
     and document such consequences. An adjustment may be made               3. Any CONTRACTOR interpretation of or conclusion
     in the CONTRACT Price or CONTRACT Times, or both, to                         drawn from any "technical data" or any such other data,
     the extent that they are attributable to the existence or location           interpretations, opinions or information.
     of any Underground Facility that was not shown or indicated or
     not shown or indicated with reasonable accuracy in the               C. CONTRACTOR shall not be responsible for any Hazardous
     CONTRACT Documents and that CONTRACTOR did not                          Environmental Condition uncovered or revealed at the Site
     know of and could not reasonably have been expected to be               which was not shown or indicated in Drawings or
     aware of or to have anticipated. If DISTRICT and                        Specifications or identified in the CONTRACT Documents to
     CONTRACTOR are unable to agree on entitlement to or on the              be within the scope of the Work. CONTRACTOR shall be
     amount or extent, if any, of any such adjustment in                     responsible for a Hazardous Environmental Condition created
     CONTRACT Price or CONTRACT Times, DISTRICT or                           by the CONTRACTOR, Subcontractors, Suppliers, or anyone
     CONTRACTOR may make a Claim therefore as provided in                    else for whom CONTRACTOR is responsible.
     paragraph 16.02.                                                     D. If CONTRACTOR encounters a Hazardous Environmental
3.   In order to be entitled to an increase in time for performance of       Condition or if CONTRACTOR or anyone for whom
     the Work, CONTRACTOR must establish that its critical path              CONTRACTOR is responsible creates a Hazardous
     of construction performance has been adversely impacted.                Environmental Condition, CONTRACTOR shall immediately:
     Upon such a showing, CONTRACTOR shall be entitled only to               (i) secure or otherwise isolate such condition; (ii) stop all Work
     such an extension equivalent to such actual adverse impact in           in connection with such condition and in any area affected
     the critical path.                                                      thereby (except in an emergency as required by paragraph
                                                                             6.16); and (iii) notify DISTRICT and DESIGN ENGINEER
4.05 Reference Points: DISTRICT shall provide engineering                    (and immediately thereafter confirm such notice in writing).
surveys to establish reference points for construction which in           E. CONTRACTOR shall not be required to resume Work in
DISTRICT's judgment are necessary to enable CONTRACTOR to                    connection with such condition or in any affected area until
proceed with the Work. CONTRACTOR shall be responsible for                   after DISTRICT has obtained any required permits related
laying out the Work, shall protect and preserve the established              thereto and delivered to CONTRACTOR written notice: (i)
reference points and property monuments, and shall make no                   specifying that such condition and any affected area is or has
changes or relocations without the prior written approval of                 been rendered safe for the resumption of Work; or (ii)
DISTRICT. CONTRACTOR shall report to DISTRICT whenever                       specifying any special conditions under which such Work may
any reference point or property monument is lost or destroyed or             be resumed safely. If DISTRICT and CONTRACTOR cannot
requires relocation because of necessary changes in grades or                agree as to entitlement to or on the amount or extent, if any, of
locations, and shall be responsible for the accurate replacement or          any adjustment in CONTRACT Price or CONTRACT Times,
relocation of such reference points or property monuments by a               or both, as a result of such Work stoppage or such special
professional land surveyor licensed in the State of Florida.                 conditions under which Work is agreed to be resumed by
                                                                             CONTRACTOR, either party may make a Claim therefore as
4.06 Hazardous Environmental Condition at Site                               provided in paragraph 16.02.
                                                                          F. In order to be entitled to an increase in time for performance of
A. Reports and Drawings: Reference is made to the                            the Work, CONTRACTOR must establish that its critical path
   Supplementary Conditions for the identification of those reports          of construction performance has been adversely impacted.
   and drawings relating to a Hazardous Environmental Condition              Upon such a showing, CONTRACTOR shall be entitled only to
   identified at the Site, if any, that have been utilized by the            such an extension equivalent to such actual adverse impact in
   DESIGN ENGINEER and/or the DISTRICT in the preparation                    the critical path.


     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                             00700-2-9
G. The provisions of paragraphs 4.02, 4.03, and 4.04 are not                CONTRACT, furnished the Insurance Certificate and
   intended to apply to a Hazardous Environmental Condition                 endorsements, complied with the DISTRICT's SBE
   uncovered or revealed at the Site.                                       requirements, and furnished a valid and acceptable Statutory
                                                                            Payment Bond and a Common Law Performance Bond as
ARTICLE 5 - BONDS AND INSURANCE                                             specified in the General Terms & Conditions (or, in lieu of the
                                                                            Statutory Payment Bond or Common Law Performance Bond,
5.01 Bid Guaranty                                                           having provided an alternate form of security as specified in the
                                                                            General Terms & Conditions) as required under the provisions
A. Bid Bond Form. Each Bid must be accompanied by the                       of the CONTRACT. Any money order or check from the
   DISTRICT's Bid Bond form meeting the standards specified in              apparent low bidder shall be deposited upon receipt. Any
   this Article 5, including those applicable to the sureties for the       money order or certified check from the second apparent low
   Statutory Payment Bond and Common Law Performance Bond                   bidder may be deposited. Failure of the DISTRICT to execute
   specified in the General Terms & Conditions. The bond shall              the CONTRACT within Ninety (90) days after the date of the
   be on the Bid Guaranty form provided by the DISTRICT, with               bid opening shall initiate release of the Bid Bond, certified
   Power of Attorney Affidavit attached, in an amount not less              check or cash of the lowest and second lowest bidders unless
   than five percent (5%) of the amount of the bid. The Bid Bond            mutually agreed otherwise or specified in the Supplemental
   shall be in the Prime Contractor’s name. The Bidder is required          Conditions.
   to use the DISTRICT forms provided in this RFB. Alternate
   bond forms will not be accepted. Failure to provide the              5.02 Performance & Payment Bonds:
   DISTRICT's bond forms will deem the Bid non-responsive.
                                                                        A. Performance and Payment Bond: If the CONTRACT price is in
B. Alternate Security. In lieu of the Bid Bond, the Bid may be             excess of $200,000.00, the CONTRACTOR shall, within seven
   accompanied by an alternate form of security in the form of             (7) working days of date of the Notice of Apparent Low Bidder
   cash, a money order, certified check of any national or state           from DISTRICT, provide DISTRICT with a Common Law
   bank made payable to the DISTRICT, or an irrevocable letter of          Performance Bond and a Statutory Payment Bond meeting the
   credit, in an amount not less than five percent (5%) of the             standards specified herein, on the forms provided by the
   amount of the Bid. Any such alternative form of security shall          DISTRICT with Power of Attorney Affidavit attached, each in
   be for the same purpose and be subject to the same conditions           an amount not less than the CONTRACT Price. The bonds
   as those applicable to the bond for which the alternative form of       shall also be accompanied by the DISTRICT’s Affidavit for
   security is being substituted. The determination of the value of        Surety Form. The Performance and Payment Bonds shall be in
   an alternative form of security shall be made by the DISTRICT.          the Prime Contractor’s name. Failure to provide the bond(s)
C. Conditions. The Bid Bond or alternate security shall be                 within the seven (7) working day period shall be sufficient
   conditioned upon the Bidder's:                                          cause for the DISTRICT to deem the Bidder non-responsive
   1. Not withdrawing said bid within ninety (90) days after date          and nullify the CONTRACT award.
        of opening of the same, and
   2. Within seven (7) working days after of the Notice of              5.03 All Bonds
        Apparent Low Bidder Letter:
        a. executing a written CONTRACT with the DISTRICT,              A. Sureties Qualifications: All bonds required under this
             in accordance with the bid as accepted;                       CONTRACT, including, but not by way of limitation, any Bid
        b. providing evidence of insurance in the manner                   Bond, Common Law Performance Bond or Statutory Payment
             specified by the DISTRICT; and                                Bond shall be written through a reputable and responsible
        c. if the Bid exceeds $200,000.00, providing a Statutory           surety bond agency licensed to do business in the State of
             Payment Bond and a Common Law Performance                     Florida and with a surety which holds a certificate of authority
             Bond as specified in the General Terms & Conditions           authorizing it to write surety bonds in Florida meeting the
             (or, in lieu of the Statutory Payment Bond or Common          following requirements:
             Law Performance Bond, having provided an alternate
             form of security as specified in the General Terms &
             Conditions);
        d. or in the event to fully comply with all of the
             foregoing, if the Bidder shall have paid the DISTRICT
             the difference between the amount specified in said
             bid and the amount for which the DISTRICT may
             procure the required work and/or supplies, if the latter
             amount be in excess of the former.
D. Return of Bid Guaranty. Funds of any money order or check
   that may be received will be returned to all Bidders, with the
   exception of the two (2) apparent low Bidders, within thirty
   (30) days after the opening of the Bids. Bid bonds will not be
   returned to the bidders, unless specifically requested by a
   Bidder. The Bid Security of the apparent and second apparent
   low bidder shall be retained until such Bidder has executed the


   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                             00700-2-10
                                                BOND AND INSURANCE
                                      REQUIREMENTS FOR CONSTRUCTION CONTRACTS
      CONTRACT SUM                              BEST'S RATING CLASSIFICATION FOR SURETY                       BEST'S FINANCIAL
                                                AND INSURANCE FIRMS, & OTHER                                  SIZE CATEGORY FOR
                                                REQUIREMENTS                                                  SURETY AND
                                                                                                              INSURANCE FIRMS.
      From: $0.00                               Bid Bond and Insurance Required.                              No Minimum Required.
      To:   $200,000.00
                                                Performance and Payment Bond Not Required (unless             Not Applicable.
                                                specified in Supplemental Conditions)
      From: $200,000.01                         All Bonds and Insurance Required:                             No Minimum Required.
      To:   $500,000.00                         See requirements under paragraph (3) below
      From: $500,000.01                         All Bonds and Insurance Required:                             IV or larger.
      To:   $2,500,000.00                       A- or better
                                                Circular 570 requirements (paragraph 2 below)
      From : $2,500,000.01                      All Bonds and Insurance Required:                             V or larger.
         and more                               A- or better
                                                Circular 570 requirements
                                                (paragraph (2) below

     CONTRACTORs must use the DISTRICT bond forms enclosed                          State of Florida; and
     herein. Failure to use the DISTRICT forms shall deem the                  b.   The surety company holds a certificate of authority
     bidder as non-responsive.                                                      authorizing it to write surety bonds in Florida; and
                                                                               c.   The surety company has twice the minimum surplus and
     1.   Ratings by A.M. Best:                                                     capital required by the Florida Insurance code at the time
          If the CONTRACT Price is $200,000.01 or greater, the                      this Request For Bids is issued; and
          surety and insurance company or corporation shall have the           d.   The surety company is otherwise in compliance with the
          following minimum ratings by The A.M. Best Company, in                    provisions of the Florida Insurance Code; and
          addition to the surety qualifying pursuant to paragraph (3)          e.   The surety company holds a currently valid certificate of
          below:                                                                    authority issued by the United States Department of the
     2.   Circular 570, CONTRACT Price of $500,000.01 or More:                      Treasury under 31 U.S.C. ss.9304 to 9308.
          If the CONTRACT Price is $500,000.01 or greater, the
          surety shall also comply with the Circular 570 requirements          In order to qualify as an acceptable surety company under this
          as set forth in this paragraph 2. The surety shall maintain a        paragraph 3, an Affidavit for the Surety Company shall be
          current certificate of authority as an acceptable surety on          executed by an Officer of the surety bond insurer as evidence
          Federal Bonds in accordance with U.S. Department of                  that a surety company is in compliance with the foregoing
          Treasury Circular 570, current revision. If the amount of the        requirements.
          bond exceeds the underwriting limitations set forth in the
          Circular, in order to qualify, the net retention of the surety   B. Additional or replacement bond: It is further mutually agreed
          company shall not exceed the underwriting limitation in the         between the parties hereto that if, at any time, the DISTRICT
          Circular and the excess risk must be protected by co-               shall deem the surety or sureties upon any bond to be
          insurance, reinsurance, or other methods in accordance with         unsatisfactory, or if, for any reason, such bond ceases to be
          Treasury Circular 297, revised September 1, 1978 CFR                adequate, the CONTRACTOR shall, at its expense within
          Section 223.10 - Section 223.111. Further the surety                seven (7) working days after the receipt of notice from the
          company shall provide the DISTRICT with evidence                    DISTRICT to do so, furnish an additional or replacement bond
          satisfactory to the DISTRICT, that such excess risk has been        or bonds on the DISTRICT'S standard form, with the same
          protected in an acceptable manner.                                  amount, and with such surety or sureties as shall be
     3.   CONTRACT Price of $500,000 or Less:                                 satisfactory to the DISTRICT. In such event, no further
          Notwithstanding the foregoing paragraphs 1. and 2., in the          payments to the CONTRACTOR shall be deemed to be due
          event the CONTRACT price is $500,000.00 or less, in                 under this CONTRACT until such new or additional security
          accordance with Section 287.0935, Florida Statutes, bonds           for the faithful performance of the work shall be furnished in
          with a surety company in compliance with the following              the manner and form satisfactory to the DISTRICT.
          requirements shall be acceptable:
          a. The surety company is licensed to do business in the


          GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                              00700-2-
11
   In addition, the CONTRACTOR shall for any increases in                  and recision of any ensuing contract.
   the CONTRACT amount automatically increase the amount
   of the performance and payment bonds to equal the revised          C. Self-insured Provisions. If the CONTRACTOR is a self-
   amount of the contract, and shall provide the DISTRICT                insured entity, the CONTRACTOR may contact the
   with evidence of same.                                                DISTRICT'S CONTRACT Administrator, identified on the
C. Florida Resident agent: The surety company shall have a               cover page, and request the DISTRICT'S self-insurance
   Florida resident agent whose name shall be listed in the              package. It shall be the responsibility of the CONTRACTOR
   prescribed space on the forms provided by the DISTRICT                to ensure that all Subcontractors are adequately insured or
   for all bonds required by the DISTRICT.                               covered under their policies. The DISTRICT may at its
D. Alternate form of security: In lieu of the Common Law                 discretion, require the CONTRACTOR to provide a complete
   Performance Bond or Statutory Payment Bond,                           certified copy of its insurance policy(s).
   CONTRACTOR may, pursuant to Section 255.051, Florida
   Statutes, provide an alternate form of security in the form of     D. Workers' Compensation:
   cash, a money order, a certified check, or an irrevocable
   letter of credit. Any such alternative form of security shall be   1.   Workers' Compensation insurance shall comply with Chapter
   for the same purpose and be subject to the same conditions              440, Florida Statute, including Employer's Liability. If work is
   as those applicable to the bond for which the alternative               performed in/over navigable waters, an endorsement covering
   form of security is being substituted. The determination of             the U.S. Longshore and Harbor Workers' Compensation Act
   the value of an alternative form of security shall be made by           (LHWCA) 33 U.S.C. Section 901, et seq. and Jones Act, 46
   the DISTRICT.                                                           App U.S.C. Section 861, et seq. shall be included.
                                                                      2.   If CONTRACTOR claims an exemption from coverage, it
5.04 Insurance                                                             must attach proof of same for consideration in the form of a
                                                                           certified copy of your state exemption form. The DISTRICT
A. Certificate of Insurance. The CONTRACTOR shall deliver                  reserves the right to require said coverage regardless of the
   to DISTRICT and maintain insurance coverage reflecting, at              state exemption.
   a minimum, the amounts and conditions as specified within
   the DISTRICT'S Insurance Requirements Checklist,                   E. Commercial Liability Insurance
   attached herein.      All insurance required under this
   CONTRACT shall meet the requirements listed in the Table           1.   Coverage shall be no more restrictive than that identified by
   found in 5.03.A above.                                                  the Insurance Services Office, Inc. (ISO).
                                                                      2.   Coverage shall be written on an Occurrence Basis Form.
    In addition, the CONTRACTOR shall for any increases in            3.   Coverage shall provide as a minimum those limits identified
    the CONTRACT amount automatically increase the amount                  within the DISTRICT's Insurance Requirements Checklist.
    of the insurance to equal the revised amount of the contract,          Coverage shall be "first dollar" coverage. If CONTRACTOR's
    and shall provide the DISTRICT with evidence of same.                  policy    includes     a    Self-Insured      Retention    (SIR)
                                                                           CONTRACTOR may, at the DISTRICT's option, be required
    The CONTRACTOR shall provide the certificate within                    to meet established financial security requirements.
    seven (7) working days of the date of the Notice of Apparent      4.   Coverage shall include as a minimum the following coverage
    Low Bidder.                                                            endorsements: Premises / Operations, Products/Completed
                                                                           Operations,       Contractual        Liability,      Independent
    The CONTRACTOR shall have ninety (90) business days                    CONTRACTORS, Broad Form Property Damage,
    after CONTRACT execution, to produce the required                      Underground Explosion/Collapse (XCU) and Personal Injury.
    Insurance Declaration Page of Policy for the insurance                 Additional endorsements may be required as the CONTRACT
    requirements set forth in the General Terms & Conditions,              dictates. Refer to the DISTRICT's Insurance Requirements
    and the Insurance Requirements Checklist included herein.              Checklist attached herein.
                                                                      5.   The DISTRICT shall be added by endorsement as an
B. Qualifications to Do Business in Florida. All insurers must             Additional Insured. An endorsement shall also be included
   be qualified to lawfully conduct business in the State of               which specifies that the inclusion of an additional insured does
   Florida. Failure of the DISTRICT to notify the                          not exclude any pollution liability coverage otherwise afforded
   CONTRACTOR that the Certificate of Insurance provided                   by said policy.
   does not meet the CONTRACT requirements, shall not
   constitute a waiver of the CONTRACTOR's responsibility             F.   Business Auto Liability Insurance
   to meet the stated requirements. In addition, receipt and
   acceptance of the certificate of insurance by the DISTRICT         1.   Coverage shall be no more restrictive than that identified by
   shall not constitute approval of the amounts, conditions or             the Insurance Services Office, Inc. (ISO).
   types of coverage listed on the certificate. Misrepresentation     2.   Coverage shall provide as a minimum those limits identified
   of any material fact, whether intentional or not, regarding the         within the DISTRICT's Insurance Requirements Checklist.
   CONTRACTOR's insurance coverage, policies or                            Coverage shall be "first dollar" coverage. If CONTRACTOR's
   capabilities, may be grounds for rejection of the response              policy includes a Self Insured Retention (SIR)

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                00700-2-12
     CONTRACTOR may, at the DISTRICT's option, be                        489.105(3)(p), Fla. Stat.)
     required to meet established financial security requirements.    6) Mechanical Contractor (as defined in Section 489.105(3)(i),
3.   Coverage shall be "Any Auto" - Symbol 1.                            Fla. Stat.)
                                                                      7) Plumbing Contractor (as defined in Section 489.105(3)(m), Fla.
G. Builders Risk Insurance/Installation Floater                          Stat.)
                                                                      8) Other (specify):_____________________ (as defined in
1.   The insurance policy shall be "broad form," "all risk"              Section 489.105(3)(___), Fla. Stat.)
     covering all equipment and machinery; or a special               9) Occupational License from the counties in the State of Florida
     Installation Floater may be included to insure the required         within which the work will be performed or from the County in
     coverage for this exposure. The policy form shall be no             the State of Florida in which the CONTRACTOR’s principle
     more restrictive than the "inland marine type form." The            place of business is located.
     DISTRICT shall be allowed to occupy the property in
     question without voiding any of the provided coverages.          Note that with respect to the applicable license requirement, the
2.   The policy(s) shall state, "on behalf of all parties to the      CONTRACTOR must either be “certified” in accordance with
     contract." The CONTRACTOR, the DISTRICT and all                  Section 489.111, Fla. Stat., or “registered” in accordance with
     other applicable subcontractors are to be included as            Section 489.117, Fla. Stat. A CONTRACTOR that is “registered”
     "insureds" on the policy(s).                                     rather than certified must also have the appropriate occupational
3.   At a minimum, the "covered property" will include the            license and meet any other applicable local licensing requirements in
     building or structure being constructed, including all           the county in Florida where the work is to be performed.
     fixtures, materials, supplies, machinery and equipment to be
     used in, or incidental to the construction. This will extend     Unless otherwise specified in the Supplemental Conditions, the
     coverage to underground works. Coverage shall also be            required licensure must be in the Prime Contractor’s name.
     afforded to the property of others through a "care, custody or
     control" endorsement, as well as property off-site or in         B. Foreign Corporations
     transit. The following coverages shall also be included by
     endorsement, unless excluded by the DISTRICT: Boiler &           Before submitting a Bid, the CONTRACTOR must:
     Machinery, Testing, Mechanical Breakdown, Earthquake,            1) Be authorized to conduct business in the State of Florida
     and Flood.                                                           pursuant to Chapter 607, F.S.; and
4.   Coverage shall be valued on a Replacement Cost (100%)            2) Meet the DISTRICT’s licensing requirements for Florida
     basis. A maximum (SIR) of $5,000 is allowed. If multiple             Corporations (see Article 5.05A) by complying with one of the
     limits of liability are proposed for the construction site,          following options:
     property in transit, off-site storage, etc., the same value          a) Obtain a State of Florida General Contractor 's License; or
     requirement shall be used for each.                                  b) Obtain a qualifying agent (licensed as a State of Florida
5.   All coverages afforded under this policy(s) shall remain in               Certified General Contractor ) pursuant to Section 489.119,
     effect and not be excluded by a "Force Majeure Clause"                    F.S.; or
     found else where in these Bidding Documents.                         c) Obtain a "limited registration" pursuant to Section
6.   Coverage shall cease when the entire project covered by said              489.117(3), Florida Statutes; or
     policy is accepted by the DISTRICT. In the event testing by          d) Obtain an "endorsement certification" pursuant to Section
     the CONTRACTOR is conducted after acceptance by the                       489.115(3), Florida Statutes.
     DISTRICT, coverage shall remain in full force and effect
     until all testing is complete and accepted by the DISTRICT,      ARTICLE 6 - CONTRACTOR'S RESPONSIBILITIES
     and final payment is made.
                                                                      6.01 Supervision and Superintendence
5.05 Licenses:
                                                                      A. CONTRACTOR shall supervise, inspect, and direct the Work
A. Florida Corporations                                                  competently and efficiently, devoting such attention thereto
                                                                         and applying such skills and expertise as may be necessary to
Before submitting a Bid, the CONTRACTOR must have the                    perform the Work in accordance with the CONTRACT
below listed license as indicated in the Supplemental Conditions         Documents. CONTRACTOR shall be solely responsible for
as well as any other license required by law:                            the means, methods, techniques, sequences, and procedures of
1) Certified General Contractor (as defined in Section                   construction. CONTRACTOR shall be responsible to see that
    489.105(3)(a), Fla. Stat.)                                           the completed Work complies accurately with the
2) Building Contractor (as defined in Section 489.105(3)(b),             CONTRACT Documents.
    Fla. Stat.)                                                       B. At all times during the progress of the Work, CONTRACTOR
3) Underground and Utility Excavation Contractor (as defined             shall have a competent resident superintendent on site who
    in Section 489.105(3)(n), Fla. Stat.)                                shall not be replaced without written notice to DISTRICT
4) Roofing Contractor (as defined in Section 489.105(3)(e), Fla.         except under extraordinary circumstances. The resident
    Stat.)                                                               superintendent shall be a full time employee of the
5) Pollutant Storage Systems Contractor (as defined in Section           CONTRACTOR. The DISTRICT may, at its sole discretion,

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                              00700-2-13
   require replacement of the superintendent, in which case          6.03 Services, Materials, and Equipment
   CONTRACTOR shall submit an acceptable replacement at
   no increase in CONTRACT Price nor extension in                    A. Unless otherwise specified in the General Requirements,
   CONTRACT Times.              The superintendent will be              CONTRACTOR shall provide and assume full responsibility
   CONTRACTOR's representative at the Site and shall have               for all services, materials, equipment, labor, transportation,
   authority to act on behalf of CONTRACTOR. All                        construction equipment and machinery, tools, appliances, fuel,
   communications given to or received from the                         power, light, heat, telephone, water, sanitary facilities,
   superintendent shall be binding on CONTRACTOR.                       temporary facilities, and all other facilities and incidentals
C. CONTRACTOR shall ensure that all employees performing                necessary for the performance, testing, start-up, and
   or furnishing any of the Work will be prohibited from using          completion of the Work.
   firearms, engaging in hunting, fishing, trapping, using illegal   B. All materials and equipment incorporated into the Work shall
   drugs or using alcohol either on the work site, on DISTRICT          be as specified or, if not specified, shall be of good quality and
   property, or on any land adjoining the work site.                    new, except as otherwise provided in the CONTRACT
D. CONTRACTOR shall ensure that all employees performing                Documents. All warranties and guarantees specifically called
   or furnishing any of the Work will be prohibited from                for by the Specifications shall expressly run to the benefit of
   trespassing on any land adjoining the work site.                     DISTRICT.         If required by DISTRICT or DESIGN
                                                                        ENGINEER, CONTRACTOR shall furnish satisfactory
6.02 Labor; Working Hours                                               evidence (including reports of required tests) as to the source,
                                                                        kind, and quality of materials and equipment. All materials
A. CONTRACTOR shall provide competent, qualified                        and equipment shall be stored, applied, installed, connected,
   personnel to perform construction as required by the                 erected, protected, used, cleaned, and conditioned in
   CONTRACT Documents. CONTRACTOR shall employ a                        accordance with instructions of the applicable Supplier, except
   Professional Land Surveyor with current Florida registration         as otherwise may be provided in the CONTRACT Documents.
   to survey and lay out the work (in accordance with any            C. Manufacturers' or Suppliers' warranties for all materials
   additional provisions included in the General Requirements).         products and equipment to be furnished by CONTRACTOR
   CONTRACTOR is fully responsible to provide a sufficient              and to be incorporated into the completed Work shall be
   number of skilled workers and supervisory personnel to               furnished to the DISTRICT through CONTRACTOR.
   perform the Work and insure that the Work is completed               CONTRACTOR shall obtain from Suppliers of all materials,
   within the CONTRACT Time. Failure to fully man the                   products and equipment, complete information as to any
   Project with supervisory personnel and skilled workers shall         special condition or restriction to be applied in the use of these
   be cause for termination of CONTRACTOR.                              items. Should the manner or method of installation, specified
B. Except as otherwise required for the safety or protection of         performance or test results as set forth in the Specifications be
   persons or the Work or property at the Site or adjacent              contrary to the Manufacturer's recommendations for use of the
   thereto, and except as otherwise stated in the CONTRACT              product, CONTRACTOR shall notify the DISTRICT in
   Documents, all Work at the Site shall be performed during            writing of such conflict as soon as reasonably possible, but no
   regular working hours, and CONTRACTOR will not permit                later than the time of Shop Drawing submittal including those
   overtime work or the performance of Work on Saturday,                products. Failure to provide such written notice before
   Sunday, or any legal holiday without DISTRICT's written              proceeding with the Work affected thereby shall be
   consent and 48 hours notice.                                         certification by CONTRACTOR that the specification
C. The CONTRACTOR shall be responsible for verifying                    requirements will be met by the materials, products and
   employee authorization to work in the U.S. and certifying            equipment, and that the cost and time required to perform the
   that a good faith effort has been made to properly identify          Work affected thereby have been included in the CONTRACT
   employees by timely reviewing and completing appropriate             Price and in the schedule for the performance of the Work
   documentation, including but not limited to the Department           within the CONTRACT Time.
   of Homeland Security, U.S. Citizenship and Immigration
   Services Form I-9. Written verification shall be kept by          6.04 Progress Schedule:
   the CONTRACTOR and made available for inspection on
   demand by the DISTRICT.                                           A. CONTRACTOR shall adhere to the progress schedule
D. The hourly rate of pay for each employee shall comply                established in accordance with paragraph 2.07 and shall be
   with State law and industry standards for similar work               updated monthly as provided below.
   performed under the CONTRACT. The CONTRACTOR
   shall maintain records verifying the rate of pay for each         1.   CONTRACTOR shall submit to DISTRICT for acceptance (to
   employee working on this CONTRACT and make such                        the extent indicated in paragraph 2.07) proposed adjustments
   records available for inspection on demand by the                      in the progress schedule that will not result in changing the
   DISTRICT.                                                              CONTRACT Times (or Milestones). Such adjustments will
E. Failure to fully comply with these provisions shall be a               conform generally to the progress schedule then in effect and
   material breach of the CONTRACT and cause for                          additionally will comply with any provision of the General
   termination of the CONTRACT.                                           Requirements applicable thereto. CONTRACTOR further
                                                                          hereby acknowledges that the CONTRACT Time for

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-14
     performance is reasonable and that all costs for schedule               equivalent to that named and an acceptable substitute
     compliance are included in the CONTRACT Price.                          therefore. Requests for review of proposed substitute items of
2.   Proposed adjustments in the progress schedule that will                 material or equipment will not be accepted by DISTRICT from
     change the CONTRACT Times (or Milestones) shall be                      anyone other than CONTRACTOR.
     submitted in accordance with the requirements of Article 12.       c.   The procedure for review by DISTRICT will be as set forth in
     Such adjustments may only be made by a Change Order or                  paragraph 6.05.A.2.d, as supplemented in the General
     Written Amendment in accordance with Article 12. The                    Requirements and as DISTRICT may decide is appropriate
     CONTRACTOR shall not alter the schedule for proposed                    under the circumstances.
     substitutions in anticipation of a change order, but rather will   d.   CONTRACTOR shall first make written application to
     provide a proposed schedule revision with the change order,             DISTRICT for review of a proposed substitute item of material
     if requested by the DISTRICT, which will become effective               or equipment that CONTRACTOR seeks to furnish or use.
     with approval of the change.                                            The application shall certify that the proposed substitute item
                                                                             will perform adequately the functions and achieve the results
6.05 "Or Equals" or Substitutes                                              called for by the general design, be similar in substance to that
                                                                             specified, and be suited to the same use as that specified. The
A. Whenever an item of material or equipment is specified or                 application will state the extent, if any, to which the use of the
   described in the CONTRACT Documents by using the name                     proposed substitute item will prejudice CONTRACTOR's
   of a proprietary item or the name of a particular Supplier, the           achievement of Substantial Completion on time, whether or
   specification or description is intended to establish the type,           not use of the proposed substitute item in the Work will require
   function, appearance, and quality required. Unless the                    a change in any of the CONTRACT Documents (or in the
   specification or description contains or is followed by words             provisions of any other direct CONTRACT with DISTRICT
   reading that no "like," no "equivalent," no "or equal" item or            for work on the Project) to adapt the design to the proposed
   no substitution is permitted, the substitution may be                     substitute item and whether or not incorporation or use of the
   submitted to DISTRICT for review under the circumstances                  proposed substitute item in connection with the Work is
   described below.                                                          subject to payment of any license fee or royalty. All variations
                                                                             of the proposed substitute item from that specified will be
1.   "Or-Equal" Items: If in DISTRICT's sole discretion an item              identified in the application, and available engineering, sales,
     of material or equipment proposed by CONTRACTOR is                      maintenance, repair, and replacement services will be
     functionally equal to that named and sufficiently similar so            indicated. The application will also contain an itemized
     that no change in related Work will be required, it may be              estimate of all costs or credits that will result directly or indi-
     considered by DISTRICT as an "or equal" item, in which                  rectly from use of such substitute item, including costs of
     case review and approval of the proposed item may, in                   redesign and claims of other CONTRACTORs affected by any
     DISTRICT's sole discretion, be accomplished without                     resulting change, all of which will be considered by
     compliance with some or all of the requirements for                     DISTRICT in evaluating the proposed substitute item.
     approval of proposed substitute items. For the purposes of              DISTRICT may require CONTRACTOR to furnish additional
     this paragraph, a proposed item of material or equipment                data about the proposed substitute item.
     may be considered functionally equal to an item so named if:
     a. In the exercise of reasonable judgment DISTRICT                 B. Substitute Construction Methods or Procedures: If a specific
          determines that: (i) it is at least equal in quality,            means, method, technique, sequence, or procedure of
          durability, appearance, strength, and design                     construction is shown or indicated in and expressly required by
          characteristics; (ii) it will reliably perform at least          the CONTRACT Documents, CONTRACTOR may furnish or
          equally well the function imposed by the design concept          utilize a substitute means, method, technique, sequence, or
          of the completed Project as a functioning whole; and             procedure of construction approved by DISTRICT.
     b. CONTRACTOR certifies that: (i) there is no increase in             CONTRACTOR shall submit sufficient information to allow
          cost to the DISTRICT; and (ii) it will conform                   DISTRICT, in DISTRICT's sole discretion, to determine that
          substantially, even with deviations, to the detailed             the substitute proposed is equivalent to that expressly called for
          requirements of the item named in the CONTRACT                   by the CONTRACT Documents. The procedure for review by
          Documents.                                                       DISTRICT will be similar to that provided in Article 6.05.A.2.

2.   Substitute Items                                                   C. DISTRICT's Evaluation: DISTRICT will be allowed a
                                                                           reasonable time within which to evaluate each proposal or
a.   If in DISTRICT's sole discretion an item of material or               submittal made pursuant to paragraphs 6.05.A and 6.05.B.
     equipment proposed by CONTRACTOR does not qualify as                  DISTRICT will be the sole judge of acceptability. No "or
     an "or equal" item under paragraph 6.05.A.1, it may, at the           equal" or substitute will be ordered, installed or utilized until
     DISTRICT's option be considered a proposed substitute                 DISTRICT's review is complete, which will be evidenced by
     item.                                                                 either a Change Order for a substitute or an approved Shop
b.   CONTRACTOR shall submit sufficient information as                     Drawing for an "or equal." DISTRICT will advise
     provided below to allow DISTRICT to determine that the                CONTRACTOR in writing of any negative determination.
     item of material or equipment proposed is essentially                 CONTRACTOR shall not be entitled to recover any extended

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                   00700-2-15
   general condition costs, or any schedule related impacts,                or DESIGN ENGINEER may furnish to any Subcontractor or
   including but not limited to acceleration or inefficiency                other person or organization, to the extent practicable,
   costs, alleged to have been incurred resulting from the time             evidence of amounts paid to CONTRACTOR on account for
   spent by the DESIGN ENGINEER and DISTRICT in                             specific Work done. No Subcontractor, Supplier or other
   evaluating each proposal or submittal under this Article.                person or organization shall be a third party beneficiary of this
D. Special       Guarantee:      DISTRICT        may       require          CONTRACT.
   CONTRACTOR to furnish at CONTRACTOR's expense a                     D.   CONTRACTOR shall be solely responsible for scheduling and
   special performance guarantee or other surety with respect to            coordinating the Work of Subcontractors, Suppliers, and other
   any substitute.                                                          individuals or entities performing or furnishing any of the
E. DISTRICT's Cost Reimbursement: DISTRICT will record                      Work under a direct or indirect CONTRACT with
   time required by DISTRICT and DESIGN ENGINEER in                         CONTRACTOR.
   evaluating substitute proposed or submitted by                      E.   CONTRACTOR shall require all Subcontractors, Suppliers,
   CONTRACTOR pursuant to paragraphs 6.05.A.2 and                           and such other individuals or entities performing or furnishing
   6.05.B and in making changes in the CONTRACT                             any of the Work to communicate with DISTRICT through
   Documents (or in the provisions of any other direct                      CONTRACTOR.
   CONTRACT with DISTRICT for work on the Project)                     F.   CONTRACTOR shall ensure that all Subcontractors,
   occasioned thereby. Whether or not DISTRICT approves a                   Suppliers, and such other individuals or entities performing or
   substitute item so proposed or submitted by                              furnishing any of the Work will be prohibited from using
   CONTRACTOR, CONTRACTOR shall reimburse                                   firearms, engaging in hunting, fishing, trapping, using illegal
   DISTRICT for the charges of DISTRICT and DESIGN                          drugs or using alcohol either on the work site, on DISTRICT
   ENGINEER for evaluating each such proposed substitute.                   property, or on any land adjoining the work site.
F. CONTRACTOR's Expense: CONTRACTOR shall provide                      G.   The CONTRACTOR shall be solely responsible for SBE
   all data in support of any proposed substitute or "or equal" at          compliance as indicated in the CONTRACT Documents.
   CONTRACTOR's expense.                                               H.   CONTRACTOR shall ensure that all Subcontractors,
                                                                            Suppliers, and such other individuals or entities performing or
6.06 Concerning Subcontractors, Suppliers, and Others                       furnishing any of the Work will be prohibited from trespassing
                                                                            on any land adjoining the work site.
A. The amount of work that is sublet by CONTRACTOR shall               I.   The divisions and sections of the Specifications and the
   be limited by the condition that the CONTRACTOR shall,                   identifications of any Drawings shall not control
   with his own organization, perform at least forty percent                CONTRACTOR in dividing the Work among Subcontractors
   (40%) of the total dollar amount of the Work to be                       or Suppliers or delineating the Work to be performed by any
   performed under the CONTRACT.                                            specific trade.
B. The DISTRICT requires the identity of Subcontractors,               J.   All Work performed for CONTRACTOR by a Subcontractor
   Suppliers, and other individuals or entities to be submitted to          or Supplier will be pursuant to an appropriate agreement
   the DISTRICT in advance of the Work for review by                        between CONTRACTOR and the Subcontractor or Supplier
   DISTRICT. DISTRICT's acceptance of any such                              which specifically binds the Subcontractor or Supplier to the
   Subcontractor, Supplier, or other individual or entity so                applicable terms and conditions of the CONTRACT
   identified may be revoked on the basis of reasonable                     Documents for the benefit of DISTRICT.
   objection after due investigation. CONTRACTOR shall
   submit an acceptable replacement for the rejected                   6.07 Patent Fees and Royalties: CONTRACTOR shall pay all
   Subcontractor, Supplier, or other individual or entity. No          license fees and royalties and assume all costs incident to the use in
   acceptance by DISTRICT of any such Subcontractor,                   the performance of the Work or the incorporation in the Work of
   Supplier, or other individual or entity, whether initially or as    any invention, design, process, product, or device which is the
   a replacement, shall constitute a waiver of any right of            subject of patent rights or copyrights held by others.
   DISTRICT to reject defective Work.
C. CONTRACTOR shall be fully responsible to DISTRICT for               6.08 Permits: Unless otherwise provided in the Supplementary
   all acts and omissions of the Subcontractors, Suppliers, and        Conditions, CONTRACTOR shall obtain and pay for all required
   other individuals or entities performing or furnishing any of       State and Federal permits and licenses applicable for the
   the Work just as CONTRACTOR is responsible for                      performance of the Work. If CONTRACTOR believes that any
   CONTRACTOR's own acts and omissions. Nothing in the                 additional permits are required it shall notify the DISTRICT’s
   CONTRACT Documents shall create for the benefit of any              Procurement Department in writing specifying which permits the
   such Subcontractor, Supplier, or other individual or entity         CONTRACTOR believes are required. The permits shall be in
   any contractual relationship between DISTRICT or                    Prime CONTRACTOR’s name only unless required otherwise by
   DESIGN ENGINEER and any such Subcontractor, Supplier                the regulating authorities. The CONTRACTOR shall provide the
   or other individual or entity, nor shall it create any obligation   DISTRICT’s CONSTRUCTION MANAGER copies of all permits
   on the part of DISTRICT or DESIGN ENGINEER to pay or                and records required to be maintained relating to the Work.
   to see to the payment of any moneys due any such Subcon-            CONTRACTOR shall pay all governmental charges and inspection
   tractor, Supplier, or other individual or entity except as may      fees necessary for the prosecution of the Work, which are
   otherwise be required by Laws and Regulations. DISTRICT             applicable at the time of opening of Bids, or, if there are no Bids,

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                  00700-2-16
on the Effective Date of the CONTRACT. CONTRACTOR                       trespassing on any land adjoining the work site.
shall pay all charges of utility owners for connections to the       B. Removal of Debris During Performance of the Work: During
Work. If CONTRACTOR fails to obtain or renew any permit or              the progress of the Work CONTRACTOR shall keep the Site
license required by this paragraph, the DISTRICT has the option         and other areas free from accumulations of waste materials,
of stopping or suspending work, terminating the                         rubbish, and other debris. Removal and disposal of such waste
CONTRACTOR's services or procuring any permit or license                materials, rubbish, and other debris shall conform to applicable
directly. In addition, the CONTRACTOR shall not be entitled to          Laws and Regulations.
any additional time for such failure. DISTRICT shall be entitled     C. Cleaning/Restoring: Prior to Substantial Completion of the
to deduct DISTRICT's resultant costs from the CONTRACT                  Work CONTRACTOR shall clean the Site and make it ready
Price by issuing a Change Order. CONTRACTOR shall meet all              for utilization by DISTRICT. At the completion of the Work
requirements of all permits and licenses.                               or upon Termination for Convenience the CONTRACTOR
                                                                        shall remove from the Site all tools, appliances, construction
6.09 Laws and Regulations: CONTRACTOR shall give all                    equipment and machinery, and surplus materials and shall
notices and comply with all Laws and Regulations applicable to          restore to original condition all property not designated for
the performance of the Work. Except where otherwise expressly           alteration by the CONTRACT Documents, but in no event
required by applicable Laws and Regulations, the DISTRICT               later than a date determined at the sole discretion of the
shall not be responsible for monitoring CONTRACTOR's                    DISTRICT’s Construction Manager.
compliance with any Laws or Regulations.                             D. Loading Structures: CONTRACTOR shall not load nor permit
                                                                        any part of any structure to be loaded in any manner that will
6. 10 Taxes                                                             endanger the structure, nor shall CONTRACTOR subject any
                                                                        part of the Work or adjacent property to stresses or pressures
A. The DISTRICT is exempted from payment of Florida State               that will endanger it.
   Sales and Use taxes and Federal Excise tax. The
   CONTRACTOR, however, shall not be exempted from                   6.12 Record Documents
   paying Florida State Sales and Use taxes to the appropriate
   governmental agencies or for payment by the                       A. CONTRACTOR shall maintain in a safe place at the Site one
   CONTRACTOR to suppliers for taxes on materials used to               (1) record copy of all Drawings, Specifications, Addenda,
   fulfill its contractual obligations with the DISTRICT.               Written Amendments, Change Orders, Field Orders, field test
B. CONTRACTOR shall pay all sales, consumer, use, and                   records, and construction photographs and written
   other similar taxes required to be paid by CONTRACTOR                interpretations and clarifications in good order and annotated
   in accordance with the Laws and Regulations of the place of          to show changes made during construction. These record
   the Project which are applicable during the performance of           documents, together with all approved Samples and a
   the Work. The CONTRACTOR shall be responsible and                    counterpart of all approved Shop Drawings, will be available
   liable for the payment of all of its FICA/Social Security and        to DISTRICT and DESIGN ENGINEER for reference. Upon
   other taxes resulting from this CONTRACT.                            completion of the Work, these record documents, Samples,
                                                                        and Shop Drawings will be delivered to DISTRICT.
6.11 Use of Site and Other Areas                                     B. The record drawings shall be marked up as the Work
                                                                        progresses to reflect current conditions and shall become the
A. Limitation on Use of Site and Other Areas                            "as-built" plans. The revisions are to be indicated in a neat,
                                                                        well-organized manner and are to include the elevation and
1.   CONTRACTOR shall confine construction equipment, the               plan location of any utilities, structures, etc., encountered or
     storage of materials and equipment, and the operations of          installed. A "record" survey book will be kept and shall
     workers to the Site and other areas permitted by Laws and          include the following items:
     Regulations, rights-of-way, permits and easements or the           1. The location and elevation of all existing utilities,
     requirements of the CONTRACT Documents, and shall not                   structures, etc. encountered.
     unreasonably encumber the Site and other areas with                2. The finished product location and elevation of all utilities
     construction equipment or other materials or equipment.                 and structures installed, including, but not limited to, fire
     CONTRACTOR shall assume full responsibility for any                     hydrants, catch basin and manhole lids, inverts, pipes, and
     damage to any such land or area, or to the owner or occupant            any and all underground structures.
     thereof, or of any adjacent land or areas resulting from the       3. Comply with Article 24- Records.
     performance of the Work.
2.   Should any claim be made by any such owner or occupant          C. All record notes shall be kept in book(s) designated "record"
     because of the performance of the Work, CONTRACTOR                 and no other survey notes will be kept in such books.
     shall promptly settle with such other party by negotiation or      CONTRACTOR will be required to review with the DESIGN
     otherwise resolve the claim by arbitration or other dispute        ENGINEER the status of the "as-built" plans and the "record"
     resolution proceeding or at law.                                   survey notes in connection with DISTRICT's evaluation of an
3.   CONTRACTOR shall ensure that all Subcontractors,                   application for payment. Failure to maintain record documents
     Suppliers, and such other individuals or entities performing       current shall be just cause for the DISTRICT to withhold
     or furnishing any of the Work will be prohibited from              payments for work performed.

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                             00700-2-17
Upon completion of the work, CONTRACTOR shall deliver to                  use of Lockout and Tagout devices on DISTRICT equipment
the DISTRICT a reproducible set of updated CONTRACT plans.                or machinery with the DISTRICT's Construction Manager.
CONTRACTOR will transfer all its "as-built" information to                The CONTRACTOR shall supply the DISTRICT's
these reproducibles and deliver the resultant "as-built" set of           Construction     Manager       with     the   procedures   the
plans, together with the record survey book to the DISTRICT.              CONTRACTOR uses and a list of DISTRICT equipment or
Each completed set of "As-Built" drawings must include on its             machinery that will be locked or tagged out in order to
face, a certified statement by the CONTRACTOR's Principal that            accomplish the work, the anticipated start date and the
the set of "As-Built" drawings accurately depicts the actual work         anticipated end date of the lockout or tagout. The DISTRICT's
as constructed.                                                           Construction Manager shall inform DISTRICT personnel at
                                                                          the work site of DISTRICT equipment or machinery to be
6.13 Safety and Protection                                                locked or tagged out by the CONTRACTOR and the
                                                                          associated procedures, the start date and the end date. The
A. CONTRACTOR shall be solely responsible for initiating,                 DISTRICT's Construction Manager shall inform the
   maintaining and supervising all safety precautions and                 CONTRACTOR of DISTRICT equipment or machinery that
   programs in connection with the Work. CONTRACTOR                       is locked or tagged out by DISTRICT personnel at the work
   shall take all necessary precautions for the safety of, and            site, the method used and the anticipated start and end dates.
   shall provide the necessary protection to prevent damage,              The DISTRICT's Construction Manager shall coordinate the
   injury or loss to:                                                     resolution of conflicts of work that may arise between the
   1. All persons on the Site or who may be affected by the               CONTRACTOR and the DISTRICT due to equipment lockout
         works;                                                           or tagout.
   2. All the Work and materials and equipment to be
         incorporated therein, whether in storage on or off the       6.14 Safety Representative: CONTRACTOR shall designate a
         Site; and                                                    qualified and experienced safety representative at the Site whose
   3. Other property at the Site or adjacent thereto, including       duties and responsibilities shall be the prevention of accidents and
         trees, shrubs, lawns, walks, pavements, roadways,            the maintaining and supervising of safety precautions and programs
         structures, utilities, and Underground Facilities not        in accordance with applicable laws, rules and regulations.
         designated for removal, relocation, or replacement in
         the course of construction.                                  6.15 Hazard Communication Programs: CONTRACTOR shall be
B. CONTRACTOR shall comply with all applicable Laws and               responsible for complying with hazard communication standards or
   Regulations relating to the safety of persons or property          other hazard communication information requirements in
   (including, but not limited to, Florida’s Trench Safety Act,       accordance with all federal, state and local Laws and Regulations.
   for which a form has been provided in Section 00380), or to        The CONTRACTOR shall be responsible for dissemination of
   the protection of persons or property from damage, injury, or      hazard communication information to all employers on the site in
   loss; and shall develop and maintain all necessary safeguards      accordance with applicable laws, rules and regulations.
   for such safety and protection. CONTRACTOR shall notify
   owners of adjacent property and of Underground Facilities          6.16 Emergencies
   and other utility owners when prosecution of the Work may
   affect them, and shall cooperate with them in the protection,      A. In emergencies affecting the safety or protection of persons or
   removal, relocation, and replacement of their property. All           the Work or property at the Site or adjacent thereto,
   damage, injury, or loss to any property referred to in                CONTRACTOR is obligated to act to prevent threatened
   paragraph 6.13.A.2 or 6.13.A.3 caused, directly or indirectly,        damage, injury, or loss. CONTRACTOR shall give DISTRICT
   in whole or in part, by CONTRACTOR, any Subcontractor,                prompt written notice if CONTRACTOR believes that any
   Supplier, or any other individual or entity directly or               significant changes in the Work or variations from the
   indirectly employed by any of them to perform any of the              CONTRACT Documents have been caused thereby or are
   Work, or anyone for whose acts any of them may be liable,             required as a result thereof.       CONTRACTOR shall be
   shall be immediately remedied by CONTRACTOR.                          responsible for providing first aid and medical care in
   CONTRACTOR's duties and responsibilities for safety and               accordance with applicable laws and regulations.
   for protection of the Work shall continue until such time as       B. The CONTRACTOR shall be required to secure or remove
   all the Work is completed and the DISTRICT has made final             from the site, prior to a storm event, any materials or
   payment to CONTRACTOR.                                                equipment which could cause bodily injury, damage to the
                                                                         Work, the DISTRICT'S installations and/or public or private
    CONTRACTOR shall ensure that all Subcontractors,                     property. Site excavations shall be required to be secured
    Suppliers, and such other individuals or entities performing         and/or backfilled. No CONTRACTOR equipment may be
    or furnishing any of the Work will be prohibited from using          parked within 100 feet of any DISTRICT facilities. In the
    firearms, engaging in hunting, fishing, trapping, using illegal      event of the issuance of a Storm Warning, the DISTRICT will
    drugs or using alcohol either on the work site, on DISTRICT          attempt to notify the CONTRACTOR, however, the
    property, or on any land adjoining the work site.                    CONTRACTOR is responsible for preparing for a storm event.
                                                                         The CONTRACTOR shall take the necessary precautions to
C. The CONTRACTOR shall coordinate the CONTRACTOR's                      protect the walking and motoring public from harm due to

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-18
   construction activity.                                                     coordinated each Shop Drawing or Sample with other
C. The CONSTRUCTION MANAGER or delegatee may, but                             Shop Drawings and Samples and with the requirements of
   is not required to, order the work be stopped if a condition of            the Work and the CONTRACT Documents.
   eminent danger exists. Nothing shall be construed to shift
   responsibility or risk of loss for injuries and / or damages,     2.   Each submittal shall bear a stamp or specific written indication
   cost of stoppage or delay of work, from the CONTRACTOR                 that CONTRACTOR has satisfied CONTRACTOR's
   to the DISTRICT. The CONTRACTOR shall remain solely                    obligations under the CONTRACT Documents with respect to
   and exclusively responsible for compliance with all safety             CONTRACTOR's review and approval of that submittal.
   requirements and the safety of all persons and property at        3.   At the time of each submittal, CONTRACTOR shall give
   worksite and work.                                                     DISTRICT specific written notice of such variations, if any,
                                                                          that the Shop Drawing or Sample submitted may have from the
6.17 Shop Drawings and Samples                                            requirements of the CONTRACT Documents, such notice to
                                                                          be in a written communication separate from the submittal;
A. CONTRACTOR shall submit Shop Drawings to DISTRICT                      and, in addition, shall cause a specific notation to be made on
   for review and approval in accordance with the acceptable              each Shop Drawing and Sample submitted to DISTRICT for
   schedule of Shop Drawings and Sample submittals. All                   review and approval of each such variation.
   submittals will be identified as DISTRICT may require and
   in the number of copies specified in the General                  E. DISTRICT’S Review
   Requirements. The data shown on the Shop Drawings will
   be complete with respect to quantities, dimensions, specified     1.   DISTRICT will timely review and approve Shop Drawings
   performance and design criteria, materials, and similar data           and Samples in accordance with the schedule of Shop
   to show DISTRICT the services, materials, and equipment                Drawings and Sample submittals acceptable to DISTRICT.
   CONTRACTOR proposes to provide and to enable                           DISTRICT's review and acceptance will be only to determine
   DISTRICT to review the information for the limited                     if the items covered by the submittals will, after installation or
   purposes required by paragraph 6.17.E.                                 incorporation in the Work, conform to the information given in
B. CONTRACTOR shall also submit Samples to DISTRICT                       the CONTRACT Documents and be compatible with the
   for review and approval in accordance with the acceptable              design concept of the completed Project as a functioning whole
   schedule of Shop Drawings and Sample submittals. Each                  as indicated by the CONTRACT Documents.
   Sample will be identified clearly as to material, Supplier,       2.   DISTRICT's review and acceptance will not extend to means,
   pertinent data such as catalog numbers, and the use for                methods, techniques, sequences, or procedures of construction
   which intended and otherwise as DISTRICT may require to                (except where a particular means, method, technique,
   enable DISTRICT to review the submittal for the limited                sequence, or procedure of construction is specifically and
   purposes required by paragraph 6.17.E. The numbers of each             expressly called for by the CONTRACT Documents) or to
   Sample to be submitted will be as specified in the                     safety precautions or programs incident thereto. The review
   Specifications.                                                        and acceptance of a separate item as such will not indicate
C. Where a Shop Drawing or Sample is required by the                      approval of the assembly in which the item functions.
   CONTRACT Documents or the schedule of Shop Drawings               3.   DISTRICT's review and acceptance of Shop Drawings or
   and Sample submittals acceptable to DISTRICT as required               Samples shall not relieve CONTRACTOR from responsibility
   by paragraph 2.07, any related Work performed prior to                 for any variation from the requirements of the CONTRACT
   DISTRICT's review and approval of the pertinent submittal              Documents unless CONTRACTOR has in writing called
   will be at the sole expense and responsibility of                      DISTRICT's attention to each such variation at the time of
   CONTRACTOR.                                                            each submittal as required by paragraph 6.17.D.3 and
                                                                          DISTRICT has given written approval of each such variation
D. Submittal Procedures                                                   by specific written notation thereof incorporated in or
                                                                          accompanying the Shop Drawing or Sample approval; nor will
1.   Before submitting each Shop Drawing or Sample,                       any approval by DISTRICT relieve CONTRACTOR from
     CONTRACTOR shall have determined and verified:                       responsibility for complying with the requirements of
                                                                          paragraph 6.17.D.1. Nor does it relieve the CONTRACTOR of
     a. All field measurements, quantities, dimensions,
                                                                          meeting the safety and functionality of the system (or
         specified      performance      criteria,    installation        component).
         requirements, materials, catalog numbers, and similar
         information with respect thereto;                           F.   Resubmittal Procedures. CONTRACTOR shall make
     b. All materials with respect to intended use, fabrication,          corrections required by DISTRICT and shall return the
         shipping, handling, storage, assembly, and installation          required number of corrected copies of Shop Drawings and
         pertaining to the performance of the Work;                       submit as required new Samples for review and acceptance.
     c. All information relative to means, methods, techniques,           CONTRACTOR shall direct specific attention in writing to
         sequences, and procedures of construction and safety             revisions other than the corrections called for by DISTRICT on
         precautions and programs incident thereto; and                   previous submittals.
     d. CONTRACTOR shall also have reviewed and

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-19
6.18 Continuing the Work: CONTRACTOR shall carry on the                CONTRACTOR to DISTRICT. The making of Final Payment
Work and adhere to the progress schedule during all disputes or        to CONTRACTOR shall not be a waiver of DISTRICT's right
disagreements with DISTRICT. No Work shall be delayed or               to reimbursement from CONTRACTOR nor shall it discharge
postponed pending resolution of any disputes or disagreements          CONTRACTOR's obligation to refund the overpayment. The
except as the CONTRACTOR and DISTRICT may otherwise                    terms of this Article shall survive the DISTRICT's making
agree in writing. Suspension of the Work by CONTRACTOR                 Final Payment.
during any dispute or disagreement with DISTRICT shall entitle      C. CONTRACTOR shall insert a provision containing all the
DISTRICT to terminate the CONTRACT for cause.                          requirements of this Article, in all Subagreements between
                                                                       CONTRACTOR and Subcontractors or Suppliers or other
6.19 CONTRACTOR's General Warranty and Guarantee                       persons, altering the section only as necessary to identify
                                                                       properly the contracting parties.
A. CONTRACTOR warrants and guarantees to DISTRICT all
   Work shall be in accordance with the CONTRACT                    ARTICLE 7 - OTHER WORK
   Documents and will not be defective.
B. CONTRACTOR's obligation to perform and complete the              7.01 Related Work at Site
   Work in accordance with the CONTRACT Documents shall
   be absolute. None of the following will constitute an            A. DISTRICT, and its CONTRACTORS and utility owners may
   acceptance of Work that is not in accordance with the               perform work at the Project Site.
   CONTRACT Documents or a release of CONTRACTOR's                  B. CONTRACTOR shall afford each other CONTRACTOR,
   obligation to perform the Work in accordance with the               each utility owner, the DISTRICT and its other
   CONTRACT Documents:                                                 CONTRACTORs proper and safe access to the Site and a
   1. observations by DISTRICT and/or DESIGN                           reasonable opportunity for the introduction and storage of
        ENGINEER;                                                      materials and equipment and the execution of such other work
   2. payment by DISTRICT of any progress or final                     and shall properly coordinate the Work with theirs. Unless
        payment;                                                       otherwise provided in the CONTRACT Documents,
                                                                       CONTRACTOR shall do all cutting, fitting, and patching of
   3. the issuance of a certificate of Substantial Completion
                                                                       the Work that may be required to properly connect or
        or any payment related thereto by DISTRICT;                    otherwise make its several parts come together and properly
   4. use or occupancy of the Work or any part thereof by              integrate with such other work. CONTRACTOR shall not
        DISTRICT;                                                      endanger any work of others by cutting, excavating, or
   5. any acceptance by DISTRICT or any failure to do so;              otherwise altering their work and will only cut or alter their
   6. any review and approval of a Shop Drawing or Sample              work with the written consent of DISTRICT and its other
        submittal or the issuance of a notice of acceptability by      CONTRACTORs whose work will be affected. The duties and
        DESIGN ENGINEER;                                               responsibilities of CONTRACTOR under this paragraph are
   7. any inspection, test, or approval by others; or                  for the benefit of such utility owners, the DISTRICT and its
   8. any correction of defective Work by DISTRICT.                    CONTRACTORs to the extent that there are comparable
                                                                       provisions for the benefit of CONTRACTOR in said direct
6.20 Truth-In-Negotiation                                              contracts between DISTRICT and such utility owners and
                                                                       other CONTRACTORs.
A. CONTRACTOR warrants that all bid line items are true,            C. If the proper execution or results of any part of
   complete and accurate and include all costs, overhead, profit       CONTRACTOR's Work depends upon work performed by
   and all other amounts associated with such items and may be         others under this Article 7, CONTRACTOR shall inspect such
   relied upon by DISTRICT when making additions or                    other work and immediately report to DISTRICT in writing
   deductions to the CONTRACT Price. CONTRACTOR                        any delays, defects, or deficiencies in such other work that
   further warrants that all Cost and Pricing Data provided to         render it unavailable or unsuitable for the proper execution and
   DESIGN ENGINEER and DISTRICT during the term of the                 results of CONTRACTOR's Work. CONTRACTOR's failure
   CONTRACT shall be complete, accurate and current when               to so report will constitute an acceptance of such other work as
   provided. Should there be any changes in the Cost and               fit and proper for integration with CONTRACTOR's Work
   Pricing Data previously submitted, the CONTRACTOR                   except for latent defects and deficiencies in such other work.
   shall notify and provide the new information to DESIGN
   ENGINEER and DISTRICT immediately. DISTRICT shall
   be entitled to issue an appropriate Change Order to adjust       7.02 Coordination: CONTRACTOR shall be ultimately
   the CONTRACT Price and CONTRACT Times based on                   responsible for coordination of all other CONTRACTORs. If
   correcting inaccurate or incomplete information provided by      DISTRICT intends to CONTRACT with others for the
   CONTRACTOR.                                                      performance of other work on the Project at the Site, the following
B. Despite any provisions in the CONTRACT Documents to              will be set forth in Supplementary Conditions:
   the contrary, any amounts paid by DISTRICT to                    1. the individual or entity who will have authority and
   CONTRACTOR in excess of that to which it is entitled                  responsibility for coordination of the activities among the
   under the CONTRACT Documents shall be reimbursed by                   various CONTRACTORs will be identified;

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                             00700-2-20
2.   the specific matters to be covered by such authority and         9.02 Clarifications and Interpretations: CONSTRUCTION
     responsibility will be itemized; and                             MANAGER may issue such written clarifications or interpretations
3.   the extent of such authority and responsibilities will be        of the requirements of the CONTRACT Documents as
     provided.                                                        CONSTRUCTION MANAGER may determine necessary, which
                                                                      shall be consistent with the intent of and reasonably inferable from
ARTICLE 8 - DISTRICT's RESPONSIBILITIES                               the CONTRACT Documents.

8.01 Communications to CONTRACTOR: Except as otherwise                9.03 Authorized Variations in Work: CONSTRUCTION
provided in these General Terms & Conditions, DISTRICT shall          MANAGER may authorize minor variations in the Work from the
issue all communications to CONTRACTOR                                requirements of the CONTRACT Documents which do not involve
                                                                      an adjustment in the CONTRACT Price or the CONTRACT Times
8.02 Pay When Due: DISTRICT shall make payments to                    and are compatible with the design concept of the completed
CONTRACTOR when they are due as provided in Article 14.               Project as a functioning whole as indicated by the CONTRACT
                                                                      Documents. These may be accomplished by a Field Order and will
8.03 Lands and Easements; Reports and Tests: DISTRICT's               be binding on DISTRICT and also on CONTRACTOR, who shall
duties with respect to providing lands and easements and              promptly perform the Work involved.
providing engineering surveys to establish reference points are
set forth in Paragraph 4.05.       Paragraph 4.05 refers to           9.04 Rejecting Defective Work: DISTRICT will have authority to
DISTRICT's     identifying    and    making      available   to       disapprove or reject Work which DISTRICT believes to be
CONTRACTOR copies of reports of explorations and tests of             defective, or that DISTRICT believes will not produce a completed
subsurface conditions and drawings of physical conditions in or       Project that conforms to the CONTRACT Documents or that will
relating to existing surface or subsurface structures at or           prejudice the integrity of the design concept of the completed
contiguous to the Site that have been utilized by DESIGN              Project as a functioning whole as indicated by the CONTRACT
ENGINEER in preparing the CONTRACT Documents.                         Documents. DISTRICT will also have authority to require special
                                                                      inspection or testing of the Work as provided in Article 13, whether
8.04 Change Orders: DISTRICT will issue unilaterally or               or not the Work is fabricated, installed, or completed. When
negotiate, at its discretion, Change Orders and Field Orders as       CONTRACTOR has been notified of disapproval or rejection of
provided in Article 10.                                               defective work, CONTRACTOR shall take immediate action to
                                                                      correct or replace same.
8.05 Inspections, Tests, and Approvals: DISTRICT's
responsibility with respect to certain inspections, tests, and        9.05 Shop Drawings, Change Orders and Payments
approvals is set forth in Article 13.
8.06 Limitations on DISTRICT's Responsibilities: The                  A. In connection with DISTRICT’s authority as to Shop
DISTRICT shall not supervise, direct, or have control or                 Drawings and Samples, see Article 6.17.
authority over, nor be responsible for, CONTRACTOR's means,           B. In connection with DISTRICT's authority as to Change Orders,
methods, techniques, sequences, or procedures of construction, or        see Articles 10, 11, and 12.
the safety precautions and programs incident thereto, or for any      C. In connection with DISTRICT's authority as to Applications
failure of CONTRACTOR to comply with Laws and Regulations                for Payment, see Article 14.
applicable to the performance of the Work. DISTRICT will not
be responsible for CONTRACTOR's failure to perform the Work           9.06 Determinations for Unit Price Work for Invoices:
in accordance with the CONTRACT Documents.                            CONSTRUCTION MANAGER will determine the actual
                                                                      quantities and classifications of Unit Price Work performed by
8.07 Undisclosed Hazardous Environmental Condition:                   CONTRACTOR. CONSTRUCTION MANAGER will review
DISTRICT's responsibility with respect to an undisclosed              with CONTRACTOR the CONSTRUCTION MANAGER's
Hazardous Environmental Condition is set forth in Article 4.06.       preliminary determinations on such matters before rendering a
                                                                      written decision thereon (by recommendation of an Application for
ARTICLE 9 - CONSTRUCTION MANAGER’S STATUS                             Payment or otherwise). CONSTRUCTION MANAGER's written
DURING CONSTRUCTION                                                   decision thereon will be final and binding (except as modified by
                                                                      DISTRICT to reflect changed factual conditions or more accurate
9.01        DISTRICT's         Authorized         Representatives:    data) upon CONTRACTOR, subject to the provisions of Article 10.
CONSTRUCTION MANAGER will be DISTRICT's
authorized representative during the construction period. The         9.07 Decisions on Requirements of CONTRACT Documents and
duties and responsibilities and the limitations of authority of the   Acceptability of Work: DISTRICT will be the interpreter of the
CONSTRUCTION MANAGER as DISTRICT's authorized                         requirements of the CONTRACT Documents and judge of the
representative during construction are set forth in the               acceptability of the Work thereunder. Claims, disputes and other
CONTRACT Documents and will not be changed without                    matters relating to the acceptability of the Work, the quantities and
written consent of DISTRICT.                                          classifications of Unit Price Work, the interpretation of the
                                                                      requirements of the CONTRACT Documents pertaining to the
                                                                      performance of the Work, and Claims seeking changes in the

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                              00700-2-21
CONTRACT Price or CONTRACT Times will be referred to                    (except as otherwise specifically provided).
DISTRICT in writing, in accordance with the provisions of            B. If DISTRICT and CONTRACTOR are unable to agree on
Article 10, with a request for a formal decision.                       entitlement to, or on the amount or extent, if any, of an
                                                                        adjustment in the CONTRACT Price or CONTRACT Times,
9.08 Limitations on CONSTRUCTION MANAGER Authority and                  or both, a Claim may be made therefore as provided in Article
Responsibilities                                                        16.

A. CONSTRUCTION MANAGER's authority or responsibility                10.02 Unauthorized Changes in the Work: CONTRACTOR shall
   under this Article 9 or under any other provision of the          not be entitled to an adjustment in the CONTRACT Price or the
   CONTRACT Documents nor any decision made by                       CONTRACT Times with respect to any work performed that is not
   CONSTRUCTION MANAGER in good faith either to                      required by the CONTRACT Documents as amended, modified, or
   exercise or not exercise such authority or responsibility or      supplemented as provided in paragraph 3.04, except in the case of
   the undertaking, exercise, or performance of any authority or     an emergency as provided in paragraph 6.16 or in the case of
   responsibility by CONSTRUCTION MANAGER shall                      uncovering Work as provided in paragraph 13.04.B.
   create, impose, or give rise to any duty in contract, tort, or
   otherwise owed by CONSTRUCTION MANAGER to                         10.03 Execution of Change Orders
   CONTRACTOR, any Subcontractor, any Supplier, any
   other individual or entity, or to any surety for or employee or   A. DISTRICT and CONTRACTOR shall execute appropriate
   agent of any of them.                                                Change Orders (or Written Amendments) covering:
B. CONSTRUCTION MANAGER will not supervise, direct,
   control, or have authority over or be responsible for             1.   Changes in the Work which are:
   CONTRACTOR's means, methods, techniques, sequences,                    a. ordered by DISTRICT pursuant to paragraph 10.01.A,
   or procedures of construction, or the safety precautions and           b. required because of acceptance of defective Work under
   programs incident thereto, or for any failure of                          Article 13 or DISTRICT's correction of defective Work
   CONTRACTOR to comply with Laws and Regulations                            under Article 13, or
   applicable to the performance of the Work.                             c. base claims agreed to by the parties.
   CONSTRUCTION MANAGER will not be responsible for
   CONTRACTOR's failure to perform the Work in                       2.   Changes in the CONTRACT Price or CONTRACT Times
   accordance with the CONTRACT Documents.                                which are agreed to by the parties, including any undisputed
C. CONSTRUCTION MANAGER will not be responsible for                       sum or amount of time for Work actually performed in
   the acts or omissions of the CONTRACTOR or of any                      accordance with a Change Order or Amendment; and
   Subcontractor, any Supplier, or of any other individual or        3.   Unilateral Changes in the CONTRACT Price or CONTRACT
   entity performing any of the Work.                                     Times which are issued by the DISTRICT, including any
D. CONSTRUCTION MANAGER's review of the final                             undisputed and/or disputed sum or amount of time for Work
   Application for Payment and accompanying documentation                 actually performed in accordance with a Change Order or
   and all maintenance and operating instructions, schedules,             Amendment; and
   guarantees, Bonds, certificates of inspection, tests and          4.   Changes in the CONTRACT Price or CONTRACT Times
   approvals, and other documentation required to be delivered            which embody the substance of any written decision rendered
   by paragraph 14.07.A will only be to determine generally               by DISTRICT pursuant to paragraph 16.02; provided that, in
   that their content complies with the requirements of, and in           lieu of executing any such Change Order, an appeal may be
   the case of certificates of inspections, tests, and approvals          taken from any such decision in accordance with the
   that the results certified indicate compliance with the                provisions of the CONTRACT Documents and applicable
   CONTRACT Documents.                                                    Laws and Regulations, but during any such appeal,
E. The limitations upon authority and responsibility set forth in         CONTRACTOR shall carry on the Work and adhere to the
   this paragraph 9.10 shall also apply to DISTRICT,                      progress schedule as provided in paragraph 6.18.
   CONSTRUCTION             MANAGER's          Consultants    and    5.   An executed change order shall be in accord and satisfaction
   assistants.                                                            concerning all potential claims related to the Change Order
                                                                          work, including inefficiencies or acceleration based claims.
ARTICLE 10 - CHANGES IN THE WORK
                                                                     B. There shall be no CONTRACTOR delay claim based upon
10.01 Authorized Changes in the Work                                    CONTRACTOR's inability to perform change order work due
                                                                        to delay caused by DISTRICT's approval process.
A. Without invalidating the CONTRACT and without notice to
   any surety, DISTRICT may, at any time or from time to             10.04 Notification to Surety: If notice of any change affecting the
   time, order additions, deletions, or revisions in the Work by     general scope of the Work or the provisions of the CONTRACT
   a Written Amendment or Change Order. Upon receipt of any          Documents (including, but not limited to, CONTRACT Price or
   such document, CONTRACTOR shall promptly proceed                  CONTRACT Times) is required by the provisions of any Bond to
   with the Work involved which will be performed under the          be given to a surety, the giving of any such notice will be
   applicable conditions of the CONTRACT Documents                   CONTRACTOR's responsibility. The amount of each applicable

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                              00700-2-22
Bond will be adjusted to reflect the effect of any such change,           Cost of the Work and fee shall be determined in the same
and evidence of increased coverage provided to the DISTRICT.              manner as CONTRACTOR's Cost of the Work and fee as
In addition, the CONTRACTOR shall for any increases in the                provided in this paragraph 11.01.
CONTRACT amount, automatically increase the amount of the            4.   Costs of special consultants (cost of engineers, architects,
Performance and Payment Bonds to equal the revised amount of              testing laboratories and surveyors) employed for services
the CONTRACT and shall provide the DISTRICT with evidence                 specifically related to the Work.
of same.                                                             5.   Supplemental costs including the following:
                                                                          a. The proportion of necessary transportation, travel, and
ARTICLE 11 - COST OF THE WORK FOR CHANGES;                                     subsistence expenses of CONTRACTOR's employees
OWNER DIRECTED ALLOWANCES; UNIT PRICE                                          incurred in discharge of duties connected with the Work.
WORK                                                                      b. Cost, including transportation and maintenance, of
                                                                               materials, supplies, equipment, machinery, appliances,
11.01 Cost of the Work for Changes                                             office, and temporary facilities at the Site, and hand tools
A. Costs Included: The term Cost of the Work means the sum                     not owned by the workers, which are consumed in the
    of all costs necessarily incurred and paid by                              performance of the Work, and cost, less market value, of
    CONTRACTOR in the proper performance of the Work.                          such items used, but not consumed, which remain the
    When the value of any Work covered by a Change Order, or                   property of CONTRACTOR.
    when a Claim for an adjustment in CONTRACT Price is                   c. Rentals of all construction equipment and machinery, and
    determined on the basis of Cost of the Work, the costs to be               the parts thereof whether rented from CONTRACTOR or
    reimbursed to CONTRACTOR will be only those additional                     others in accordance with rental agreements approved by
    or incremental costs required because of the change in the                 DISTRICT, and the costs of transportation, loading,
    Work or because of the event giving rise to the Claim.                     unloading, assembly, dismantling, and removal thereof.
    Except as otherwise may be agreed to in writing by                         All such costs shall be in accordance with the terms of
    DISTRICT, such costs shall be in amounts no higher than                    said rental agreements. The rental of any such equipment,
    those prevailing in the locality of the Project, shall not                 machinery, or parts shall cease when the use thereof is no
    include any of the costs itemized in paragraph 11.01.B                     longer necessary for the Work.
    "Costs Excluded" and shall include only the following items:          d. Sales, consumer, use, and other similar taxes related to the
1. Payroll costs for employees in the direct employ of                         Work, and for which CONTRACTOR is liable, imposed
    CONTRACTOR in the performance of the Work under                            by Laws and Regulations.
    schedules of job classifications agreed upon by DISTRICT              e. The cost of utilities, fuel, and sanitary facilities at the Site.
    and CONTRACTOR. Such employees may include within                     f. Minor expenses such as telegrams, long distance
    limitation superintendents, foremen, and other personnel                   telephone calls, telephone service at the Site or expressage
    employed full time at the Site. Payroll costs for employees                in connection with the Work.
    not employed full time on the Work shall be apportioned on            g. When the Cost of the Work is used to determine the value
    the basis of their time spent on the Work. Payroll costs shall             of a Change Order or of a Claim, the cost of premiums for
    include, but not be limited to, salaries and wages plus the                additional Bonds and insurance required because of the
    cost of fringe benefits, which shall include social security               changes in the Work or caused by the event giving rise to
    contributions, unemployment, excise, and payroll taxes,                    the Claim.
    workers' compensation, health and retirement benefits, sick           h. When all the Work is performed on the basis of cost-plus,
    leave, vacation and holiday pay applicable thereto. The                    the costs of premiums for all Bonds and insurance
    expenses of performing Work outside of regular working                     CONTRACTOR is required by the CONTRACT
    hours, on Saturday, Sunday, or legal holidays, shall not be                Documents to purchase and maintain.
    included in the above.
2. Cost of all materials and equipment furnished and                 B. Costs Excluded: Cost of the Work for changes shall not
    incorporated in the Work, including costs of transportation         include any of the following items:
    and storage thereof, and Suppliers' field services required in
    connection therewith. All trade discounts, rebates and           1.   Payroll costs and other compensation of CONTRACTOR's
    refunds and returns from sale of surplus materials and                officers, executives, principals (of partnerships and sole
    equipment shall accrue to DISTRICT, and CONTRACTOR                    proprietorships), general managers, engineers, architects,
    shall make provisions so that they may be obtained.                   estimators, attorneys, auditors, accountants, purchasing and
3. Payments made by CONTRACTOR to Subcontractors for                      contracting agents, expediters, timekeepers, clerks, and other
    Work performed by Subcontractors. If required by                      personnel employed by CONTRACTOR, whether at the Site or
    DISTRICT, CONTRACTOR shall obtain competitive bids                    in CONTRACTOR's principal or branch office for general
    from subcontractors acceptable to DISTRICT and                        administration of the Work and not specifically included in the
    CONTRACTOR shall deliver such bids to DISTRICT, who                   agreed upon schedule of job classifications referred to in
    will then determine, with the advice of DESIGN                        paragraph 11.01.A. 1 or specifically covered by paragraph
    ENGINEER, which bids, if any, will be acceptable. If any              11.01.A.1, all of which are to be considered administrative
    subcontract provides that the Subcontractor is to be paid on          costs covered by the CONTRACTOR's fee.
    the basis of Cost of the Work plus a fee, the Subcontractor's    2.   Expenses of CONTRACTOR's principal and branch offices

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                   00700-2-23
     other than CONTRACTOR's office at the Site.                          each separately identified item of Unit Price Work times the
3.   Any part of CONTRACTOR's capital expenses, including                 estimated quantity of each item as indicated in the
     interest on CONTRACTOR's capital employed for the Work               CONTRACT. The estimated quantities of items of Unit Price
     and charges against CONTRACTOR for delinquent                        Work are not guaranteed and are solely for the purpose of
     payments.                                                            comparison of Bids and determining an initial CONTRACT
4.   Costs due to the negligence of CONTRACTOR, any                       Price. Determinations of the actual quantities and
     Subcontractor, or anyone directly or indirectly employed by          classifications of Unit Price Work performed by
     any of them or for whose acts any of them may be liable,             CONTRACTOR will be made by DISTRICT subject to the
     including but not limited to, the correction of defective            provisions of paragraph 9.08.
     Work, disposal of materials or equipment wrongly supplied,        B. Each unit price will be deemed to include an amount
     and making good any damage to property.                              considered by CONTRACTOR to be adequate to cover
5.   Other overhead or general expense costs of any kind and the          CONTRACTOR's overhead and profit for each separately
     costs of any item not specifically and expressly included in         identified item.
     paragraph 11.01.A.                                                C. DISTRICT or CONTRACTOR may make a Claim for an
                                                                          adjustment in the CONTRACT Price in accordance with
C. CONTRACTOR's Fee: When all of the Work is performed                    paragraph 16.02 if:
   on the basis of cost-plus, CONTRACTOR's fee shall be                   1. the quantity of any item of Unit Price Work performed by
   determined as set forth in the CONTRACT. When the value                     CONTRACTOR differs materially and significantly from
   of any Work covered by a Change Order or when a Claim                       the estimated quantity of such item indicated in the
   for an adjustment in CONTRACT Price is determined on the                    CONTRACT; and
   basis of Cost of the Work, CONTRACTOR's fee shall be                   2. there is no corresponding adjustment with respect to any
   determined as set forth in paragraph 12.01.C.                               other item of Work; and
D. Documentation: Whenever the Cost of the Work for any                   3. if CONTRACTOR believes that CONTRACTOR is
   purpose is to be determined pursuant to paragraphs 11.01.A                  entitled to an increase in CONTRACT Price as a result of
   and 11.01.B, CONTRACTOR shall establish and maintain                        having incurred additional expense or DISTRICT believes
   records thereof in accordance with generally accepted                       that it is entitled to a decrease in CONTRACT Price and
   accounting practices and submit in a form acceptable to                     the parties are unable to agree as to the amount of any
   DISTRICT an itemized cost breakdown together with                           such increase or decrease.
   supporting data.
                                                                       ARTICLE 12 - CHANGE OF CONTRACT PRICE; CHANGE
11.02 Owner Directed Allowances                                        OF CONTRACT TIMES

A. It is understood that CONTRACTOR has included in the                12.01 Change of CONTRACT Price
   CONTRACT Price all allowances so named in the
   CONTRACT Documents and shall cause the Work so                      A. The CONTRACT Price may only be changed by a Change
   covered to be performed for such sums as may be acceptable             Order or by a Written Amendment. Any Claim for an
   to DISTRICT. CONTRACTOR agrees that:                                   adjustment in the CONTRACT Price shall be based on written
                                                                          notice submitted to the DISTRICT in accordance with the
1.   The allowances include the cost to CONTRACTOR (less                  provisions of Article 16.02.
     any applicable trade discounts) of materials and equipment        B. The value of any Work covered by a Change Order or of any
     required by the allowances to be delivered at the Site, and all      Claim for an adjustment in the CONTRACT Price will be
     applicable taxes; and                                                determined as follows:
2.   CONTRACTOR's costs for unloading and handling on the                 1. where the Work involved is covered by Unit Prices
     Site, labor, installation costs, overhead, profit, and other              contained in the CONTRACT Documents, by application
     expenses contemplated for the allowances have been                        of such Unit Prices to the quantities of the items involved
     included in the CONTRACT Price and not in the allowance                   (subject to the provisions of paragraph 11.03 ); or
     price, and no demand for additional payment on account of            2. where the Work involved is not covered by Unit Prices
     any of the foregoing will be valid.                                       contained in the CONTRACT Documents, by a mutually
                                                                               agreed lump sum (which may include an allowance for
B. Prior to final payment, a Change Order may be issued by the                 overhead and profit not necessarily in accordance with
   DISTRICT to reflect actual amounts due CONTRACTOR                           paragraph 12.01.C); or
   on account of Work covered by allowances.                              3. where the Work involved is not covered by Unit Prices
                                                                               contained in the CONTRACT Documents and agreement
11.03 Unit Price Work                                                          to a lump sum is not reached under paragraph 12.01.B.2,
                                                                               on the basis of the Cost of the Work (determined as
A. Where the CONTRACT Documents provide that all or part                       provided in paragraph 11.01) plus a CONTRACTOR's fee
   of the Work is to be Unit Price Work, initially the                         for overhead and profit (determined as provided in
   CONTRACT Price will be deemed to include for all Unit                       paragraph 12.01.C).
   Price Work an amount equal to the sum of the unit price for

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                              00700-2-24
C. CONTRACTOR's Fee: The CONTRACTOR's fee for                          labor disputes; those reasonable delays caused by or arising
   overhead and profit shall be determined as follows:                 from minor design conflicts and issues; schedule adjustments;
                                                                       the action of CONTRACTOR's supplier and subcontractors;
a mutually acceptable fixed fee; or                                    late or out of sequence DISTRICT-furnished equipment,
if a fixed fee is not agreed upon, then a fee based on the             materials and facilities not affecting the critical path;
following percentages of the various portions of the Cost of the       reasonable turnaround or approval of CONTRACTOR's shop
Work:                                                                  drawings, schedules, or submittals; normal unfavorable
     1. for costs incurred under paragraphs 11.01.A.1 and              weather, wet grounds, or other similar unsuitable construction
         11.01.A.2, the CONTRACTOR's fee shall be ten                  conditions likely to occur in South Florida; reasonable
         percent (10%);                                                turnaround to CONTRACTOR's requests for information or
     2. for costs incurred under paragraph 11.01.A.3, the              direction; change order processing; and access and
         CONTRACTOR's fee shall be ten percent (10%);                  coordination by the DISTRICT, or CONSTRUCTION
     3. no fee shall be payable on the basis of costs itemized         MANAGER, that does not create any new critical paths in the
         under paragraphs 11.01.A.4, 11.01.A.5, and 11.01.B;           schedule. The CONTRACTOR agrees that such delays are
     4. the amount of credit to be allowed by CONTRACTOR               included in its bid price and schedule and that they shall not
         to DISTRICT for any change which results in a net             constitute the basis for a time extension or a claim for
         decrease in cost will be the amount of the actual net         additional compensation of any type.
         decrease in cost plus a deduction in CONTRACTOR's
         fee by an amount equal to ten percent (10%) percent of    12.03 Delays Beyond CONTRACTOR's Control: Where
         such net decrease; and                                    CONTRACTOR is prevented from completing any part of the
     5. when both additions and credits are involved in any one    Work within the CONTRACT Times (or Milestones) due to delay
         change, the adjustment in CONTRACTOR's fee shall be       beyond the control of CONTRACTOR, the CONTRACT Times
         computed on the basis of the net change in accordance     (or Milestones) may be extended in an amount equal to the time
         with paragraphs 12.01.C.2.a through 12.01.C.2.e,          lost due to such delay if a Claim is made therefore as provided in
         inclusive.                                                paragraph 12.02.A. Delays beyond the control of CONTRACTOR
                                                                   may include acts or neglect of utility owners or other
D. The CONTRACTOR acknowledges that agreement on any               CONTRACTORs performing other work as contemplated by
   Change Order shall constitute a final settlement and full       Article 7, fires, floods, epidemics, abnormal weather conditions or
   accord and satisfaction of all matters relating to the change   acts of God. If abnormal weather conditions are the basis for a
   directly or indirectly changed or unchanged in the Work         claim for additional time, such claim shall be documented by data
   which is the subject of the Change Order, including, but not    substantiating that (1) weather conditions were abnormal for the
   limited to, all direct, indirect costs, and impact costs        period of time, (2) the abnormal weather could not have been
   associated with such change and any and all adjustments to      reasonably anticipated, and (3) that weather conditions had an
   the CONTRACT Price and CONTRACT Times, and                      adverse effect on the scheduled construction's critical path.
   schedule.
                                                                   12.04 Delays Within CONTRACTOR's Control: The CONTRACT
12.02 Change of CONTRACT Times                                     Times (or Milestones) will not be extended due to delays within the
                                                                   control of CONTRACTOR. Delays attributable to and within the
A. The CONTRACT Times (or Milestones) may only be                  control of a Subcontractor or Supplier shall be deemed to be delays
   changed by a Change Order or by a Written Amendment.            within the control of CONTRACTOR.
   Any Claim for an adjustment in the CONTRACT Times (or
   Milestones) shall be based on written notice submitted by       12.05 Delays Beyond DISTRICT's and CONTRACTOR's Control:
   the CONTRACTOR to the DISTRICT in accordance with               Where CONTRACTOR is prevented from completing any part of
   the provisions of paragraph 16.02.All adjustments for           the Work within the CONTRACT Times (or Milestones) due to
   additional time must include a detailed Critical Path           delay beyond the control of both DISTRICT and CONTRACTOR,
   Analysis of the CONTRACT schedule.                              an extension of the CONTRACT Times (or Milestones) in an
B. Any adjustment of the CONTRACT Times (or Milestones)            amount equal to the time lost on the critical path due to such delay
   covered by a Change Order or of any Claim for an                shall be CONTRACTOR's sole and exclusive remedy for such
   adjustment in the CONTRACT Times (or Milestones) will           delay.
   be determined in accordance with the provisions of this
   Article 12.                                                     12.06 Delay Damages
C. The CONTRACTOR expressly agrees that in undertaking to
   complete the Work within the time specified, it has made        A. In no event shall DISTRICT be liable to CONTRACTOR, any
   allowances for certain foreseeable hindrances and delays           Subcontractor, any Supplier, or any other person or
   including the types described below.                               organization, or to any surety for or employee or agent of any
D. The CONTRACTOR acknowledges that certain hindrances                of them, for damages arising out of or resulting from:
   and delays are ordinarily encountered on projects of this          1. delays caused by or within the control of
   type. The parties specifically anticipate and contemplate               CONTRACTOR; or
   such hindrances and delays, including but not limited to,          2. delays beyond the control of both DISTRICT and

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                            00700-2-25
        CONTRACTOR including but not limited to fires,            defective Work, whether or not in place, may be rejected, corrected
        floods, droughts, epidemics, abnormal weather             or accepted as provided in this Article and Article 6.19. The
        conditions, acts of God, or acts or neglect by utility    obligations of CONTRACTOR under this paragraph shall be in
        owners or other CONTRACTORs performing other              addition to and not in limitation of any obligation imposed upon it
        work as contemplated by Article 7.                        by special guarantees required by the CONTRACT Documents or
                                                                  otherwise prescribed by Laws or Regulations.
B. To the extent that delays occur for which time and
   compensation are properly allowed, the DISTRICT shall not      13.02 Access to Work: DISTRICT, DESIGN ENGINEER, its
   be liable for time-related or delay damages in the following   representatives, testing agencies and governmental entities with
   categories:                                                    jurisdiction shall be permitted access to the Work for its
   1. profit on the additional costs beyond those allowed         observation, inspection and testing. CONTRACTOR shall provide
        elsewhere;                                                proper and safe conditions for such access.
   2. loss of anticipated profit:
   3. indirect expenses;                                          13.03 Tests and Inspections
   4. impact costs;
   5. loss of productivity;                                       A. CONTRACTOR shall give DISTRICT timely notice of
   6. inefficiency costs;                                            readiness of the Work for all required inspections, tests or
   7. home office overhead;                                          approvals.        Inspections, tests or observations by
   8. consequential damages, including but not limited to loss       CONSTRUCTION MANAGER, DESIGN ENGINEER,
        of bonding capacity, loss of bidding opportunities, and      DISTRICT or its agents may be performed at its discretion to
        insolvency; and                                              provide information to the DISTRICT on the progress of the
   9. legal fees, claims preparation expenses, or costs of           Work. However, such information is not intended to fulfill the
        disputes resolution.                                         CONTRACTOR's obligations in accordance with the
   CONTRACTOR hereby expressly agrees to waive its right             CONTRACT Documents.
   to such delay or time-related costs or damages, but may be     B. If any Law, Ordinance, Rule, Regulation, code or order of any
   entitled to direct any reasonable jobsite costs caused by or      public body, government entity or court having jurisdiction
   resulting from the delay. All prime CONTRACTORs and               requires any Work (or part thereof) to specifically be
   all subcontractors shall coordinate all work one with the         inspected, tested or approved, CONTRACTOR shall assume
   other, so as to facilitate the general progress of the Work.      full responsibility therefore, pay all related costs, schedule
C. Except as provided in Paragraph B., no claim for damages          related activities at appropriate times, and furnish DISTRICT
   or any claim other than for an extension of time, provided        the required certificates of inspection, testing or approval.
   solely at the discretion of the DISTRICT, shall be made or        CONTRACTOR shall also be responsible for and shall pay all
   asserted against the DISTRICT by reason of any delays             costs, in connection with any inspection or testing required in
   caused by scheduling and coordination of work of separate         connection with DISTRICT's or DESIGN ENGINEER's
   prime CONTRACTORs.                                                acceptance of a proposed manufacturer, fabricator, supplier or
D. The CONTRACTOR shall not be entitled to an increase in            distributor of materials or equipment proposed to be
   the CONTRACT Amount or payment or compensation of                 incorporated in the Work, or of material or equipment
   any kind from the DISTRICT for costs, expenses or                 submitted for approval prior to CONTRACTOR's purchase
   damages, including but not limited to costs of acceleration       thereof for incorporation of the Work. All inspections, tests or
   or inefficiency, arising because of delay, disruption,            approvals shall be performed by persons or organizations
   interference or hindrance from any cause caused by                acceptable to DISTRICT.
   scheduling and coordination of work of separate prime          C. The CONTRACTOR shall perform sufficient testing and
   CONTRACTORs, provided, however, that this provision               inspection of the Work to support the Warranty and Guarantee
   shall not preclude recovery or damages by the                     requirements.
   CONTRACTOR for hindrances or delays due solely to              D. Neither observations by DESIGN ENGINEER or DISTRICT
   fraud, bad faith or active interference on the part of the        nor inspections, tests or approvals by others shall relieve
   DISTRICT or its authorized agents. Otherwise, the                 CONTRACTOR from its obligations to perform the Work in
   CONTRACTOR shall be entitled only to extensions of the            accordance with the CONTRACT Documents.
   CONTRACT Time as the sole exclusive remedy for such            E. If any testing, inspection or approval under this paragraph
   resulting delay, in accordance with and to the extent             reveal defective Work, CONTRACTOR shall not be allowed
   specifically provided herein.                                     to receive any associated costs and DISTRICT shall be entitled
                                                                     to deduct from the CONTRACT Price, by issuing a Change
ARTICLE 13 - WARRANTY AND GUARANTEE, TESTS                           Order, DISTRICT's costs arising out of the defective Work,
AND INSPECTIONS, CORRECTION, REMOVAL OR                              including costs of repeated procedures, compensation for
ACCEPTANCE OF DEFECTIVE WORK                                         DISTRICT's and DESIGN ENGINEER's services and other
                                                                     related costs.
13.01 Warranty and Guarantee: CONTRACTOR warrants and
guarantees that all Work shall be in accordance with the          13.04 Uncovering Work
CONTRACT Documents and will not be defective. All

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                           00700-2-26
A. If any Work that is to be inspected, tested or approved is             approvals required by the CONTRACT Documents except:
   covered without written concurrence of DISTRICT, it must,              1. for inspections, tests, or approvals covered by paragraphs
   if requested by DISTRICT, be uncovered for observation.                    13.03.B;
   Such uncovering shall be at CONTRACTOR's expense and                   2. that costs incurred in connection with tests or inspections
   will exclude the right to an increase in the CONTRACT
                                                                              conducted pursuant to paragraph 13.04.B shall be paid as
   Price or CONTRACT Times unless CONTRACTOR has
   given DISTRICT timely written notice of CONTRACTOR's                       provided in said paragraph 13.04.B; and;
   intention to cover such Work and DISTRICT has not acted                3. as otherwise specifically provided in the CONTRACT
   with reasonable promptness in response to such notice.                     Documents.
B. If DISTRICT considers it necessary or advisable that
   covered Work be observed by DISTRICT or inspected or               13.07 DISTRICT May Correct Defective Work
   tested by others, CONTRACTOR, at DISTRICT's request,
   shall uncover, expose or otherwise make available for               A. If CONTRACTOR fails within ten (10) days after written
   observation, inspection or testing as DISTRICT may require,            notice from DISTRICT to correct defective Work or to
   that portion of the Work in question, furnishing all necessary         remove and replace rejected Work as required by
   labor, material and equipment. If it is found that such Work           DISTRICT in accordance with the Contract Documents, or
   is defective, CONTRACTOR shall bear all the expenses of                if CONTRACTOR fails to perform the Work in accordance
   such uncovering, exposure, observation, inspection and                 with the Contract Documents, or if CONTRACTOR fails to
   testing and of satisfactory reconstruction, including                  comply with any other provision of the Contract
   compensation for additional professional services, any                 Documents, DISTRICT may correct and remedy any such
   additional expenses experienced by the DISTRICT due to                 deficiency.
   delays to others performing additional work, other                  B. In exercising the rights and remedies under this Article,
   contractual obligations, and attorneys' fees and DISTRICT              DISTRICT shall proceed expeditiously. In connection with
   shall be entitled to issue an appropriate deductive Change             such corrective and remedial action, DISTRICT may
   Order. CONTRACTOR shall further bear the responsibility                exclude CONTRACTOR from all or part of the Site, take
   for maintaining the schedule and will not be allowed an                possession of all or part of the Work, and suspend
   increase in CONTRACT Price or CONTRACT Time due to                     CONTRACTOR's services related thereto, take possession
   the uncovering. If, however, such Work is not found to be              of CONTRACTOR's tools, appliances, construction
   defective, and paragraph 13.04.A is not applicable,                    equipment and machinery at the Site, and incorporate in the
   CONTRACTOR shall be allowed an increase in the                         Work all materials and equipment stored at the Site or for
   CONTRACT Price or the CONTRACT Time, or both,                          which DISTRICT has paid CONTRACTOR but which are
   directly attributable to such uncovering, exposure,                    stored elsewhere. CONTRACTOR shall allow DISTRICT,
   observation, inspection, testing and reconstruction if it              DISTRICT's Consultant, DISTRICT's representatives,
   makes a claim therefore as provided in Article 10.                     agents, employees, and other contractors access to the Site
                                                                          to enable DISTRICT to exercise the rights and remedies
13.05 Correction or Removal of Defective Work:                            under this Article.
CONTRACTOR shall immediately, without cost to DISTRICT                 C. All costs, losses, and damages (included but not limited to
and as specified by DISTRICT, either correct any defective                fees and charges of engineers, architects, attorneys and other
Work, whether or not fabricated, installed or completed, or, if the       professionals, all court or arbitration or other dispute
Work has been rejected by DISTRICT, remove it from the site               resolution costs and all costs of repair or replacement of
and replace it with conforming Work. The CONTRACTOR                       work of others) incurred or sustained by DISTRICT in
shall bear the cost of repairing or replacing all Work and property       exercising such rights and remedies under this Article will
of the DISTRICT or others destroyed or damaged or in any way              be charged against CONTRACTOR and a Change Order
impacted by such correction or removal.                                   will be issued incorporating the necessary revisions in the
                                                                          Contract Documents, and DISTRICT shall be entitled to an
13.06 Acceptance of Defective Work                                        appropriate decrease in the Contract Price. If the parties are
                                                                          unable to agree as to the amount thereof, DISTRICT may
A. If, instead of requiring correction or removal and                     make a Claim therefore.
   replacement of defective Work, DISTRICT prefers to accept           D. CONTRACTOR shall not be allowed an extension of the
   it, DISTRICT may do so. In such case, if acceptance occurs             Contract Times (or Milestones) because of any delay in the
   prior to Final Payment, DISTRICT shall be entitled to issue            performance of the Work attributable to the exercise by
   a Change Order incorporating the necessary revisions in the            DISTRICT of DISTRICT's rights and remedies under this
   CONTRACT Documents, including appropriate reduction in                 Article.
   the CONTRACT Price. If the acceptance occurs after such
   Final Payment, an appropriate amount shall be paid by              13.08 Warranty Period
   CONTRACTOR to DISTRICT.
                                                                      A. The Warranty Period shall commence on the date of
B. DISTRICT shall employ the services of an independent
                                                                         Substantial Completion of the entire Work or any part of the
   testing laboratory to perform all inspections, tests, or
                                                                         Work as designated by the DISTRICT, or a later date if so


   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                              00700-2-27
   specified in the CONTRACT Documents, and extend until                 date, and the date of commencement of the Warranty Period,
   one (1) year after that date (or whatever longer period may           and for such warranties and guarantees CONTRACTOR shall
   be prescribed by Laws or Regulations or by the terms of any           receive no adjustment in CONTRACT Price.
   applicable special guarantee, Supplemental Conditions, or
   specific provision of the CONTRACT Documents.)                    13.10 Special Maintenance Requirements: In special circumstances
   CONTRACTOR's obligation under this paragraph are in               where the Work, or a designated part, reaches Substantial
   addition to any other obligation or warranty. The provisions      Completion, but as provided in the CONTRACT Documents, is not
   of this paragraph shall not be construed as a substitute for or   placed in continuous service until the commencement of the
   a waiver of the provisions of any applicable statute of           Warranty Period, CONTRACTOR shall maintain the Work, or
   limitation or repose.                                             designated part, in good order and in proper working condition,
B. If within the designated Warranty Period, the Work, or any        provide suitable drainage, and take all other actions as are
   part of the Work, is discovered to be defective,                  necessary for its protection during the period between the
   CONTRACTOR shall immediately, without an adjustment               applicable Substantial Completion date and the date of
   in CONTRACT Price and in accordance with DISTRICT's               commencement of the Warranty Period, and for such maintenance
   written instructions, either correct that defective Work, or if   CONTRACTOR shall receive no adjustment in CONTRACT
   it has been rejected by DISTRICT, remove it from the site         Price. In the event that Work suffers loss or damage, however
   and replace it with non-defective Work. If circumstances          caused, CONTRACTOR shall rebuild, repair, restore, and make
   warrant it, including, but not limited to, in an emergency,       good without an increase in CONTRACT Price all losses or
   DISTRICT may have the defective Work corrected or the             damages to any portion of any Work and shall without an increase
   rejected Work removed and replaced. In that event,                in CONTRACT Price provide suitable drainage and erect such
   CONTRACTOR shall not be allowed to recover any                    temporary structures and take all other actions as are necessary for
   associated costs, and it shall reimburse DISTRICT for all         its protection. Suspension of Work or the granting of an extension
   direct, indirect and consequential costs of DISTRICT, or          in CONTRACT Time for any cause shall not relieve
   DISTRICT shall be entitled to issue a Change Order to             CONTRACTOR of its responsibility for the Work, or designated
   incorporate an appropriate decrease in CONTRACT Price if          part, as specified in this paragraph.
   prior to Final Payment. DISTRICT shall reserve and retain
   all of its rights and remedies at law and equity against          13.11 Extended Warranty Period Due to Defective Work: Any
   CONTRACTOR and its Surety for damages and for                     defective Work that is either corrected or rejected and replaced will
   corrections of any and all latent defects.                        be warranted and guaranteed for a period of one (1) year from the
                                                                     date of acceptance of such correction or removal and replacement,
13.09 Extended Warranties and Guarantees                             even if it had previously been corrected or replaced, in accordance
                                                                     with the provisions of this Article 13. If within such extended
A. DISTRICT may at its sole discretion advance or defer the          Warranty Period, that Work is once again found to be defective,
   date of commencement of the Warranty Period, in which             DISTRICT shall be entitled to all of DISTRICT's rights and
   case CONTRACTOR shall maintain the warranties and                 remedies under this Article.
   guarantees in full force and effect until the revised date for
   commencement of the Warranty Period.                  If such     ARTICLE 14 – CONTRACT PRICE / INDEMNIFICATION,
   advancement or deferral in the date for commencement of           PAYMENTS TO CONTRACTOR AND COMPLETION
   the Warranty Period causes an increase or decrease in the
   cost of the warranties and guarantees provided by                 A. The DISTRICT shall pay CONTRACTOR for performance of
   CONTRACTOR, DISTRICT shall make an adjustment in                     the Work in accordance with the CONTRACT Documents on
   CONTRACT Price or CONTRACT Times, as provided in                     the basis of the prices indicated on the Bid Form.
   Article 12.                                                       B. The total consideration, for the full and complete performance
B. In circumstances where DISTRICT undertakes Partial                   under this CONTRACT, shall be as indicated on the
   Utilization of a portion of the Work which was specifically          cover/signature page of this CONTRACT, subject only to any
   identified in the CONTRACT Documents, CONTRACTOR                     additions and/or deductions as provided in the CONTRACT
   shall maintain the warranties and guarantees in full force and       Documents and formally approved by the DISTRICT.
   effect during the period between the applicable                   C. For value received, which is hereby acknowledged, the
   commencement of Partial Utilization date, and the date of            CONTRACTOR shall indemnify and hold the DISTRICT, its
   commencement of the Warranty Period, and for such                    officers and employees harmless from liabilities, damages,
   warranties and guarantees CONTRACTOR shall receive no                losses and costs, including, but not limited to reasonable
   adjustment in CONTRACT Price.                                        attorneys’ fees, to the extent caused by the negligence,
C. In special circumstances where CONTRACTOR fails to                   recklessness or intentionally wrongful conduct of the
   complete the Work, or a separable portion of the Work                CONTRACTOR and other persons employed or utilized by the
   within the corresponding CONTRACT Time, including any                CONTRACTOR in the performance of the CONTRACT.
   authorized adjustments, and DISTRICT undertakes Partial           D. In the event the CONTRACTOR subcontracts any part or all
   Utilization , CONTRACTOR shall maintain the warranties               of the work hereunder to any third party, the
   and guarantees in full force and effect during the period            CONTRACTOR shall require each and every subcontractor
   between the applicable commencement of Partial Utilization           to identify the DISTRICT as an additional insured on all

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-28
   insurance policies as required. Any contract awarded by                  CONTRACTOR shall submit invoices marked paid by the
   CONTRACTOR for work under this Agreement shall                           supplier with the next month's request for payment to document
   include a provision whereby the subcontractor agrees to                  that CONTRACTOR has paid for said materials and equipment
   defend, indemnify, and pay on behalf, save and hold the                  or the previously paid amount for stored materials shall be
   DISTRICT harmless from all damages arising in                            deducted from any remaining payment(s) or retainage for any
   connection with the subcontract.                                         stored materials not so properly documented.
E. The CONTRACTOR further acknowledges that it is solely                2. After the work is fifty percent (50%) complete, the DISTRICT
   responsible for ensuring its compliance and the compliance               shall reduce retainage to five percent (5%) of each subsequent
   of its subcontractors, suppliers, agents, assigns, invitees              pay request.
   and employees with the terms of this CONTRACT. This                  3. The DISTRICT may maintain the retainage to ten percent
   paragraph shall survive the expiration of termination of this            (10%) after fifty percent (50%) completion if:
   CONTRACT.                                                              a) if the Work involves construction services purchased by the
F. Notwithstanding the foregoing, the amount expended                        DISTRICT which are paid for, in whole or in part, with
   under this CONTRACT shall be paid in accordance with,                     federal funds and are subject to federal grantor laws and
   and subject to the multi-year funding allocations for each                regulations or requirements that are contrary to any
   DISTRICT fiscal year indicated on the cover/signature                     provision of the Local Government Prompt Payment Act.
   page of this CONTRACT. Funding for each applicable                     b) if the construction services purchased by the DISTRICT is
   fiscal year of this CONTRACT is subject to DISTRICT                       $200,000.00 or less.
   Governing Board budgetary appropriation. In the event the            4. DISTRICT may withhold payment of retainage if
   DISTRICT does not approve funding for any subsequent                     CONTRACTOR is behind schedule or the Work is defective
   fiscal year, this CONTRACT shall terminate upon                          and it is anticipated by the DISTRICT that the Work will not be
   expenditure of the current funding, notwithstanding other                completed within the CONTRACT Times. The DISTRICT
   provisions in this CONTRACT to the contrary. The                         shall not be required to pay or release any amounts that are
   DISTRICT will notify the CONTRACTOR in writing after                     the subject of a good-faith dispute, the subject of a claim
   adoption of the final DISTRICT budget for each                           brought pursuant to s. 255.05, or otherwise the subject of a
   subsequent fiscal year if funding is not approved for this               claim or demand by the DISTRICT or CONTRACTOR.
   CONTRACT.
                                                                        D. Upon final completion and acceptance of the Work in
14.01 Prompt Payment Procedures                                            accordance with paragraph 14.08 of the General Terms &
                                                                           Conditions, DISTRICT shall pay the remainder of the
A. All pay requests shall reference the DISTRICT’S                         CONTRACT Price.
   CONTRACT Number, and shall follow the same format as                 E. It is the policy of the DISTRICT that payment for all goods
   shown on the Application for Payment provided in the                    and services shall be made in a timely manner and that
   Bidding Documents, and shall be in accordance with the                  interest payments are made on late payments. In accordance
   terms specified in the General Terms & Conditions.                      with Florida Statutes, Section 218.70, Florida Prompt
B. CONTRACTOR shall submit Applications for Payment in                     Payment Act, a “proper” invoice (Application for Payment) is
   accordance with this Article.                                           defined as an invoice (Application for Payment) that
C. DISTRICT shall make progress payments on the basis of                   conforms to all statutory requirements and all DISTRICT
   CONTRACTOR’S            Applications   for     Payment   as             requirements as specified in the CONTRACT for invoice
   recommended by CONSTRUCTION MANAGER, in                                 (Application for Payment) submission. The time at which
   accordance with this Article and pursuant to s. 218.735.                payment shall be due from the DISTRICT shall be twenty
                                                                           (20) business days (or twenty-five [25] business days if
1.   Prior to fifty percent (50%) completion progress payments             DISTRICT agent approval is required) from receipt of a
     will be in an amount equal to ninety percent (90%) of the             proper invoice (Application for Payment) and acceptance of
     Work completed in place, and at the option of the                     services, based on compliance with the statutory
     DISTRICT, the DISTRICT may pay an amount equal to                     requirements set forth in Section 218.70, F.S. and upon
     ninety percent (90%) of materials and equipment not                   satisfaction of the DISTRICT conditions as detailed in the
     incorporated in the Work in place but delivered and suitably          CONTRACT.
     stored on site, less in each case the aggregate of payments        F. Failure of the CONTRACTOR to follow the instructions set
     previously made. In no event shall payments for materials             forth in the CONTRACT regarding a proper invoice
     and equipment stored exceed ninety percent (90%) of the               (Application for Payment) and acceptable services may result
     value of the related cost for the specific item of work in place      in an unavoidable delay in payment by the DISTRICT. All
     shown in the Schedule of Values regardless of the stated              payments due from the DISTRICT for a proper invoice and
     value of the materials or equipment. DISTRICT may, at its             acceptable services and not made within the time specified in
     sole option, pay an amount equal to ninety percent (90%) of           this section shall bear interest from thirty (30) days after the
     materials and equipment not incorporated in the Work stored           due date at the rate of one percent (1%) per month on the
     offsite if stored in a manner acceptable to DISTRICT, as              unpaid balance. The CONTRACTOR shall invoice the
     stated above for on-site stored materials. When payment to            DISTRICT for payment of any accrued unpaid interest.
     CONTRACTOR is made for stored materials and equipment,             G. Any early payment discount offered by the CONTRACTOR

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-29
      shall be clearly indicated on the invoice (Application for             resubmit the Application.
      Payment), including the percentage of the discount and the        2.   DISTRICT may refuse to make the whole or any part of any
      time period for which the discount is valid. The DISTRICT              payment if, in DISTRICT's opinion, it would be incorrect to
      reserves the option to accept such early payment discounts.            make such payment because of subsequently discovered
                                                                             evidence or the results of subsequent inspections or tests,
 14.02 Schedule of Values: The schedule of values established as             revise or revoke any such payment previously made, to such
 provided in paragraph 2.07.A will serve as the basis for progress           extent as may be necessary in DISTRICT's opinion to protect
 payments and will be incorporated into a form of Application for            DISTRICT from loss because:
 Payment acceptable to DISTRICT. Progress payments on                        a. the Work is defective, or completed Work has been
 account of Unit Price Work will be based on the number of units                  damaged, requiring correction or replacement;
 completed.                                                                  b. the CONTRACT Price has been reduced by Written
                                                                                  Amendment or Change Orders;
 14.03 Progress Payments                                                     c. DISTRICT has been required to correct defective Work or
                                                                                  complete Work in accordance with Article 13; or
 A. Applications for Payments                                                d. DISTRICT has actual knowledge of the occurrence of any
                                                                                  of the events enumerated in Article 15.01, Article 15.02,
 1.   At least twenty (20) business days before the date                          Article 15.03 and Article 15.04.".
      established for each progress payment (but not more often              e. CONTRACTOR fails to comply with the SBE
      than once a month), CONTRACTOR shall submit to                              requirements as stated in the CONTRACT;
      CONSTRUCTION MANAGER for review an Application                         f. CONTRACTOR fails to submit the required Insurance
      for Payment filled out and signed by CONTRACTOR                             Policy Declaration Page as stated in the CONTRACT;
      covering the Work completed as of the date of the                      g. CONTRACTOR fails to comply with progress schedule
      Application and accompanied by such supporting                              updates in keeping with GENERAL REQUIREMENTS.
      documentation as is required by the CONTRACT                           h. CONTRACTOR has failed to comply with Article 4.01,
      Documents. Refer to Form 00940-4 “Construction Invoice                      A.3.
      Checklist”.
 2.   Each application for payment shall be accompanied by the          3.   DISTRICT may refuse to make whole or part of any payment
      DISTRICT's SBE UTILIZATION REPORT included herein                      if the CONTRACTOR fails to comply with progress schedule
      (if SBE subcontractor(s) used).                                        updates in keeping with GENERAL REQUIREMENTS.
 3.   A copy of each application for payment shall be transmitted
      by the CONTRACTOR directly to the DISTRICT’s Small                C. Reduction in Payment
      Business Enterprise Section.
 4.   If payment is requested on the basis of materials and             1.   DISTRICT may refuse to make payment of the full amount
      equipment not incorporated in the Work but delivered and               because:
      suitably stored at the Site or at another location agreed to in        a. Claims have been made against DISTRICT based on
      writing, the Application for Payment shall also be                         CONTRACTOR's performance or furnishing of the Work;
      accompanied by a bill of sale, invoice, or other                       b. Liens have been filed in connection with the Work, except
      documentation warranting that DISTRICT has received the                    where CONTRACTOR has delivered a specific Bond
      materials and equipment free and clear of all Liens and                    satisfactory to DISTRICT to secure the satisfaction and
      evidence that the materials and equipment are covered by                   discharge of such Liens;
      appropriate property insurance or other arrangements to                c. There are other items entitling DISTRICT to an off-set
      protect DISTRICT's interest therein, all of which must be                  against the amount recommended, including the
      satisfactory to the DISTRICT.                                              assessment of liquidated damages; or
 5.   Beginning with the second Application for Payment, each                d. DISTRICT has actual knowledge of the occurrence of any
      Application shall include an affidavit of CONTRACTOR                       of the events enumerated in paragraphs 14.03.B.2.a
      stating that all previous progress payments received on                    through 14.03.B.2.h or if the CONTRACTOR is
      account of the Work have been applied in full to discharge                 otherwise in breach.
      CONTRACTOR's obligations associated with prior
      Applications for Payment.                                         2.   If DISTRICT refuses to make payment of the full amount,
 4.   The amount of retainage with respect to progress payments              DISTRICT must give CONTRACTOR written notice stating
      will be as stipulated in this Article 14.                              the reasons for such action and pay CONTRACTOR any
                                                                             amount remaining after deduction of the amount so withheld.
B.    Review of Applications                                                 DISTRICT shall pay CONTRACTOR the amount so withheld,
                                                                             or any adjustment thereto agreed to by DISTRICT and
 1.   DISTRICT will, after receipt of each Application for                   CONTRACTOR, when CONTRACTOR corrects to
      Payment, either make payment or return the Application to              DISTRICT's satisfaction the reasons for such action.
      CONTRACTOR, indicating in writing the DISTRICT's                  3.   The CONTRACTOR waives all claims against the DISTRICT
      reasons for refusing to make payment. In the latter case,              other than those previously made in writing and still unsettled.
      CONTRACTOR may make the necessary corrections and

      GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-30
14.04 CONTRACTOR's Warranty of Title: CONTRACTOR                      the list or failed to perform its contractual responsibilities, if any,
warrants and guarantees that title to all Work, materials, and        with regard to the development of the list.
equipment covered by any Application for Payment, whether
incorporated in the Project or not, will pass to DISTRICT no          A. When CONTRACTOR considers the entire Work, or an
later than the time of final payment free and clear of all Liens.        agreed upon portion thereof, ready for its intended use, and has
                                                                         satisfied all prerequisites to Substantial Completion contained
14.05 Substantial Completion                                             in the GENERAL REQUIREMENTS the CONTRACTOR
Prior to issuance of the certificate of substantial completion, the      shall notify CONSTRUCTION MANAGER certifying in
CONTRACTOR and the DISTRICT shall develop a list of                      writing that the entire Work is substantially complete (except
items (punchlist) required to render complete, satisfactory, and         for items specifically listed by CONTRACTOR as
acceptable the construction services purchased by the                    incomplete), submit to DISTRICT all operation and
DISTRICT, including:                                                     maintenance manuals and instructions and spare parts required
a) the responsibilities of the DISTRICT and the                          by the CONTRACT Documents, and request that the
   CONTRACTOR in developing and reviewing the list, and;                 DISTRICT issue a certificate of Substantial Completion.
b) a reasonable time for developing the list.                            Promptly thereafter, DISTRICT, CONTRACTOR, and
c) The DISTRICT and CONTRACTOR will agree upon a                         CONSTRUCTION MANAGER shall make an inspection of
   mutually agreeable date and time to inspect the site together         the Work to determine the status of completion. If
   along with any key sponsors and constituents to develop the           CONSTRUCTION MANAGER or DISTRICT does not
   Punch List. The Punch List will be typewritten and attached           consider the Work substantially complete, CONSTRUCTION
   to the Certificate of Substantial Completion and mailed to            MANAGER will notify CONTRACTOR in writing giving the
   the CONTRACTOR for his resolution. The date of this                   reasons therefore.       If DISTRICT considers the Work
   Substantial Completion Inspection establishes the official            substantially complete, CONSTRUCTION MANAGER will
   date of Substantial Completion for the Project. In the                prepare a certificate of Substantial Completion which shall fix
   instance that there are no Punch List items, the                      the date of Substantial Completion.
   CONTRACTOR and DISTRICT will reach agreement on                    B. There shall be attached to the certificate a list of items
   the date of Substantial Completion to be reflected in the             (punchlist), which should be minor in scope and nature, to be
   Certificate, which will be issued without an attached Punch           completed       or     corrected     before    final   payment.
   List. In either case, the CONTRACTOR will then proceed                CONTRACTOR shall have thirty (30) days after receipt of the
   toward Contract Closeout inclusive of all documentary                 certificate, but not later than the contract time to complete or
   requirements of the CONTRACT to include Record                        correct items to the satisfaction of the DISTRICT.
   Drawings, equipment training sessions and ultimately,              C. DISTRICT shall have the right to exclude CONTRACTOR
   cleanup and demobilization.                                           from the Site after the date of Substantial Completion, but
d) For multi-phased construction projects or projects with               DISTRICT shall allow CONTRACTOR reasonable access to
   services on more than one building or structure, the punch            complete or correct items on the list.
   list shall be developed for each building, structure, or phase
   of the project within the time limitations corresponding to        14.06 Partial Utilization of Completed Work
   the estimated project cost provided in paragraphs c and d.
e) The CONTRACTOR shall not be relieved of its duties and             A. Use by DISTRICT at its option of any substantially completed
   responsibilities to complete all construction services                part of the Work which has specifically been identified in the
   purchased pursuant to the contract, in the event the parties          CONTRACT Documents, or which DISTRICT, and
   fail to include certain corrective work or pending on the list.       CONTRACTOR agree constitutes a separately functioning and
   All items that require correction under the contract and that         usable part of the Work that can be used by DISTRICT for its
   are identified after the preparation and delivery of the list         intended purpose without significant interference with
   shall remain the obligation of the contractor as defined by           CONTRACTOR's performance of the remainder of the Work,
   the contract.                                                         may be accomplished prior to Substantial Completion of all the
f) Upon completion of all items on the list, the                         Work subject to the following conditions.
   CONTRACTOR may submit a payment request for
   remaining retainage. However, if a good-faith dispute exists,      1.   DISTRICT at any time may request to the CONTRACTOR in
   the DISTRICT may continue to withhold an amount not to                  writing for the DISTRICT to use any such part of the Work. If
   exceed 150 percent of the total costs to complete such items.           CONTRACTOR agrees that such part of the Work is
                                                                           substantially complete, CONTRACTOR will certify in writing
Warranty items may not affect the final payment of retainage as            to DISTRICT that such part of the Work is substantially
provided in this section or as provided in the contract between            complete and request DISTRICT to issue a certificate of
the contractor and its subcontractors and suppliers.                       Substantial Completion for that part of the Work.
                                                                           CONTRACTOR at any time may notify DISTRICT and
The DISTRICT shall not pay or process any payment request                  CONSTRUCTION            MANAGER        in     writing   that
for retainage if the CONTRACTOR has, in whole or in part,                  CONTRACTOR considers any such part of the Work ready
failed to cooperate with the DISTRICT in the development of                for its intended use and substantially complete and request
                                                                           CONSTRUCTION MANAGER to issue a certificate of

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                  00700-2-31
     Substantial Completion for that part of the Work.                         accordance with the CONTRACT Documents.
2.   Within a reasonable time after either such request,                  f.   the DISTRICT's FINAL SBE UTILIZATION REPORT
     DISTRICT, CONTRACTOR, and CONSTRUCTION                                    form included herein;
     MANAGER shall make an inspection of that part of the                 g.   certification that the District furnished keys (Article 4.01
     Work to determine its status of completion. If
                                                                               A.3.) have been returned to the District.
     CONSTRUCTION MANAGER or DISTRICT does not
     consider that part of the Work to be substantially complete,
                                                                      B. Review of Application and Acceptance: If, on the basis of
     CONSTRUCTION MANAGER will notify DISTRICT and
                                                                         CONSTRUCTION MANAGER's observation of the Work
     CONTRACTOR in writing giving the reasons therefore. If
                                                                         during     construction    and    final   inspection, and
     CONSTRUCTION MANAGER considers that part of the
                                                                         CONSTRUCTION MANAGER's review of the final
     Work to be substantially complete, the provisions of
                                                                         Application for Payment and accompanying documentation
     paragraph 14.04 will apply with respect to certification of
                                                                         as    required     by    the    CONTRACT        Documents,
     Substantial Completion of that part of the Work and the
                                                                         CONSTRUCTION MANAGER and DISTRICT are satisfied
     division of responsibility in respect thereof and access
                                                                         that the Work has been completed and CONTRACTOR's
     thereto.
                                                                         other obligations under the CONTRACT Documents have
                                                                         been fulfilled, DISTRICT will make payment. Otherwise,
B. No occupancy or separate operation of part of the Work may
                                                                         CONSTRUCTION MANAGER will return the Application
   occur prior to compliance with the requirements of Article 5
                                                                         for Payment to CONTRACTOR, indicating in writing the
   regarding Insurance.
                                                                         reasons for refusing to recommend final payment, in which
                                                                         case CONTRACTOR shall make the necessary corrections
14.07 Final Inspection: Upon written notice from
                                                                         and resubmit the Application for Payment.
CONTRACTOR that the entire Work or an agreed portion
thereof is complete, and that the CONTRACTOR has satisfied
                                                                      ARTICLE 15 -             SUSPENSION          OF     WORK        AND
all prerequisites to Final Inspection contained in the GENERAL
                                                                      TERMINATION
REQUIREMENTS, CONSTRUCTION MANAGER will
promptly make a final inspection with DISTRICT and
                                                                      15.01 DISTRICT May Stop the Work: If the Work is defective and
CONTRACTOR and will notify CONTRACTOR in writing of
                                                                      the CONTRACTOR has been notified by CONSTRUCTION
all particulars in which this inspection reveals that the Work is
                                                                      MANAGER or DISTRICT, or if CONTRACTOR fails to furnish
incomplete, non-conforming or defective. CONTRACTOR shall
                                                                      or perform the Work in such a way that the completed Work will
immediately take such measures as are necessary to complete
                                                                      conform to the CONTRACT Documents, or if CONTRACTOR
such Work or remedy such deficiencies, and notify
                                                                      fails to supply sufficient supervisory personnel or skilled workmen
CONSTRUCTION MANAGER upon completion.
                                                                      or suitable materials or equipment, or if CONTRACTOR fails to
                                                                      obtain, maintain or renew insurance in conformance with the
14.08 Final Payment
                                                                      CONTRACT Documents in a form acceptable to DISTRICT, or if
                                                                      any insurance or surety company CONTRACTOR has obtained
A. Application for Payment
                                                                      insurance or bonds from declares bankruptcy or is declared
                                                                      bankrupt, or if CONTRACTOR fails to prosecute the Work or
1.   After CONTRACTOR has, in the opinion of
                                                                      endangers persons or property, DISTRICT may order
     CONSTRUCTION              MANAGER          and    DISTRICT,
                                                                      CONTRACTOR to stop the Work, or any portion thereof, until the
     satisfactorily completed all corrections identified during the
                                                                      cause for such order has been eliminated. DISTRICT's order to
     final inspection and has delivered, in accordance with the
                                                                      stop the Work may be communicated through CONSTRUCTION
     CONTRACT Documents, all maintenance and operating
                                                                      MANAGER or by DISTRICT. This right of DISTRICT to stop the
     instructions, schedules, warranties, guarantees, Bonds,
                                                                      Work shall not give rise to any duty on the part of DISTRICT or
     certificates or other evidence of insurance, certificates of
                                                                      CONSTRUCTION MANAGER to exercise this right for the
     inspection, marked-up record documents (as provided in
                                                                      benefit of CONTRACTOR or any other party. CONTRACTOR
     paragraph 6.12), and other documents acceptable to the
                                                                      shall bear all direct, indirect, and consequential costs of such order
     DISTRICT. CONTRACTOR may make application for final
                                                                      to stop the Work (including but not limited to fees and charges of
     payment following the procedure for progress payments.
                                                                      engineers, attorneys and other professionals, any additional
2.   The final Application for Payment shall be accompanied           expenses incurred by DISTRICT due to delays to others performing
     (except as previously delivered) by:                             work under a separate CONTRACT with DISTRICT, and other
     a. all documentation called for in the CONTRACT                  obligations), and CONTRACTOR shall further bear the
          Documents;                                                  responsibility for maintaining the Progress Schedule and shall not
     b. consent of the surety, if any, to final payment;              be entitled to any extension of CONTRACT Time or increase in the
     c. contractor’s affidavit and final release;                     CONTRACT Price. DISTRICT shall be entitled to deduct any
     d. complete and legally effective releases or waivers            expenses so incurred from the CONTRACT Price by issuing a
          (satisfactory to DISTRICT) of all Lien rights arising out   Change Order.
          of or Liens filed in connection with the Work; and
     e. certification that the work has been completed in

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-32
15.02 Suspension for Convenience                                       determine whether the CONTRACTOR should be suspended
                                                                       from doing future work with the DISTRICT, and if so, for what
A. Without invalidating the CONTRACT, and without notice to            period of time. The DISTRICT’s Governing Board will consider
   any surety, DISTRICT may, at any time, order                        the factors detailed in Rule 40E-7, Part II, F.A.C. in making a
   CONTRACTOR in writing to stop, delay or interrupt Work              determination as to whether a CONTRACTOR should be
   for such a period of time as DISTRICT may deem                      suspended, and if so, for what period of time. Should the
   appropriate. Upon receipt of that order, CONTRACTOR                 DISTRICT terminate for default in accordance with this
   shall immediately proceed in accordance with any specific           provision, the DISTRICT shall be entitled to recover
   provisions or instructions, protect and maintain the Work,          reprocurement costs in addition to all other remedies under law
   and make reasonable and diligent efforts to mitigate costs          and/or equity. If CONTRACTOR leaves the site at any time during
   associated with the suspension order.                               the thirty (30) day period, DISTRICT shall have the right to secure
B. In the event said suspension of work by the DISTRICT, is            the site to protect the property from damage and to insure the health
   deemed by the DISTRICT in its sole discretion to be                 and safety of the public.
   unreasonable, then an adjustment may be made for
   documented increases in the cost of performance of this             A. CONTRACTOR. DISTRICT shall be entitled to deduct these
   CONTRACT necessarily caused by the unreasonable                        costs from the CONTRACT Price by issuing a Change Order.
   suspension, and the CONTRACT modified in writing                    B. After terminating the CONTRACTOR and to the extent
   accordingly.     However, regardless of the reason for                 permitted by laws and regulations, the DISTRICT may
   suspension, the DISTRICT shall not be liable for (a) profit            exclude CONTRACTOR from the site and take possession of
   on additional costs, (b) loss of anticipated profit, (c) indirect      the Work and of all CONTRACTOR's tools, appliances,
   expenses, (d) impact costs, (e) loss of productivity, (f)              construction equipment and machinery at the site and use the
   inefficiency costs, (g) home-office overhead, (h)                      same to the full extent they could be used by CONTRACTOR
   consequential costs in connection with such suspension.                (without liability to CONTRACTOR or DISTRICT for
   Further, no adjustment shall be made under this paragraph              trespass or conversion), incorporate in the Work all materials
   for any suspension, to the extent that performance would               and equipment stored at the site or for which DISTRICT has
   have been suspended, delayed, or interrupted by any other              paid CONTRACTOR but which are stored elsewhere, and
   cause, including the fault or negligence of the                        finish the Work as DISTRICT may deem expedient.
   CONTRACTOR, or for which an equitable adjustment is                    CONTRACTOR shall assign all of its interest in any or all
   provided for or excluded under any other term or condition             Subagreements to DISTRICT upon DISTRICT's request. In
   of this CONTRACT. Claims by the CONTRACTOR for                         such case CONTRACTOR shall not be entitled to receive any
   change in the time for performance or an adjustment of the             further payment until the Work is finished. If the unpaid
   CONTRACT Price, due to work suspensions ordered by the                 balance of the CONTRACT Price exceeds the direct, indirect
   DISTRICT shall be made in accordance with the                          and consequential costs of completing the Work (including but
   requirements of Articles 10 & 11. The CONTRACTOR                       not limited to fees and charges of engineers, architects,
   shall use all means to minimize the consequences of such               attorneys and other professionals and court and arbitration
   suspension.                                                            costs including costs for appellate proceedings) such excess
                                                                          will be paid to CONTRACTOR. If such costs exceed such
15.03 Termination for Cause                                               unpaid balance, CONTRACTOR shall pay the difference to
                                                                          DISTRICT.
It is the policy of the DISTRICT to encourage good business            C. Notwithstanding the above notice period, in the event of an
practices by requiring contractors to materially perform in               emergency, the DISTRICT may take over the site and perform
accordance with the terms and conditions of the DISTRICT                  any or all of the activities set out above immediately.
CONTRACT. In accordance with DISTRICT Rule 40E-7, Part                    DISTRICT shall provide notice of such takeover within 24
II, F.A.C., “material breach” is defined as any substantial,
                                                                          hours after its occurrence.
unexcused non-performance by failing to perform an act that is
                                                                       D. Where CONTRACTOR's services have been terminated by
an important part of the transaction or performing an act
                                                                          DISTRICT, the termination shall not affect any rights of
inconsistent with the terms and conditions of the CONTRACT.
                                                                          DISTRICT against CONTRACTOR then existing or which
                                                                          may thereafter accrue. Any retention or payment due
If the CONTRACTOR materially fails to fulfill its obligations
                                                                          CONTRACTOR by DISTRICT will not release
under this CONTRACT, the DISTRICT will provide written
                                                                          CONTRACTOR from liability.
notice of the deficiency by forwarding a Cure Notice citing the
                                                                       E. In the event of such termination, the surety shall have the right
specific nature of the material breach. The CONTRACTOR
                                                                          to take over and complete the work, provided that if the surety
shall have thirty (30) days to cure the breach. If the
                                                                          does not commence performance within twenty (20) days after
CONTRACTOR fails to cure the breach within the thirty (30)
                                                                          receipt of written notice from the DISTRICT to
day period, the DISTRICT shall issue a Termination for
                                                                          CONTRACTOR and Surety, the DISTRICT may take over
Default Notice. Once the DISTRICT has notified the
                                                                          and prosecute the work to completion, at the
CONTRACTOR that it has materially breached its
                                                                          CONTRACTOR's and Surety's expense, by CONTRACT or
CONTRACT with the DISTRICT, by sending a Termination
                                                                          otherwise.      Upon the termination of the services of
for Default Notice, the DISTRICT’s Governing Board shall

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                 00700-2-33
    CONTRACTOR,   the    DISTRICT       shall   exclude                ARTICLE 16 – CLAIMS AND DISPUTES
    CONTRACTOR from the Site, and take possession of the
    Work.                                                              16.01 General

15.04 Termination for Convenience                                      A. Claims and disputes, as defined herein and under the
                                                                          CONTRACT, include disagreements, claims, counterclaims,
A. DISTRICT may, without prejudice to any other right or                  matters in question, and differences of opinion between the
   remedy, terminate this CONTRACT in whole or in part at                 DISTRICT and CONTRACTOR, regarding the Work and
   any time for its convenience by giving CONTRACTOR and                  modifications or changes to the work. Disputes may involve
   surety seven (7) days written notice. DISTRICT shall have              interpretation of CONTRACT Documents, acceptability of the
   the right, in that event, to take over any or all of                   Work, costs and/or time for performance.
   CONTRACTOR's materials (whether stored on or off site),             B. The procedures specified herein shall be the sole and exclusive
   supplies, equipment, Subagreements or other obligations to             procedures for the resolution of disputes between the parties
   complete the Work and CONTRACTOR shall assign them                     arising out of or relating to this CONTRACT. The parties will
   to DISTRICT upon DISTRICT's request. CONTRACTOR                        participate in good faith in the procedures specified in this
   shall proceed to complete any part of the Work, as directed            Article.
   by DISTRICT, and shall settle all its claims and obligations        C. All applicable statutes of limitation and defenses based upon
   under the CONTRACT.                                                    the passage of time shall be tolled while the procedures
B. In any such termination for the convenience of DISTRICT,               specified in this Article are pending. The parties will take such
   CONTRACTOR shall be paid for Work completed in                         action, if any, required to effectuate such tolling.
   accordance with the CONTRACT Documents prior to                     D. In the event any dispute occurs under this CONTRACT which
   receipt of the notice of termination, and for termination              cannot be readily resolved, it shall be referred to the
   settlement costs that in the District’s sole discretion relate to      appropriate executives of the respective parties to this
   commitments which had become firm prior to the                         CONTRACT (hereinafter “Party” or “Parties”) for negotiation
   termination. Any payment made to CONTRACTOR after                      and resolution as described below.
   the termination and as settlement of any claim submitted by
   the CONTRACTOR as a result of the termination for                   16.02 Notice
   convenience will exclude any and all anticipated
   supplemental costs, administrative expenses overhead and            A. Notice: Written notice stating the general nature of each
   profit. CONTRACTOR shall justify its claims as requested               Claim, dispute, or other matter shall be delivered by the
   by DISTRICT with thorough, accurate records and data.                  CONTRACTOR to DISTRICT immediately, but in no event
                                                                          later than ten (10) days after the start of the event giving rise
15.05 Suspension of Contractor for Material Breach of                     thereto. Notice of the amount or extent of the Claim, dispute,
DISTRICT Contracts                                                        or other matter with supporting data shall be delivered to the
                                                                          DISTRICT within thirty (30) days after the start of such event
A. Pursuant to Rule 40E-7, Part II, F.A.C., the DISTRICT’s                (unless DISTRICT allows additional time for CONTRACTOR
   Governing Board, upon recommendation by the Director of                to submit additional or more accurate data in support of such
   Procurement, may temporarily or permanently suspend                    Claim, dispute, or other matter). A Claim for an adjustment in
   CONTRACTORS from doing business with the                               CONTRACT Price shall be prepared in accordance with the
   DISTRICT whenever a CONTRACTOR materially                              provisions of paragraph 12.01.B. A Claim for an adjustment in
   breaches its CONTRACT with the DISTRICT. Any bid                       CONTRACT Times shall be prepared in accordance with the
   submitted by a bidder shall not be considered where either             provisions of paragraph 12.02.           Each Claim shall be
   the bidder or its proposed subcontractors are included on              accompanied by CONTRACTOR's written statement that the
   the DISTRICT’s Suspension List.                                        adjustment claimed is the entire adjustment to which the
B. During the term of any contract, CONTRACTOR shall                      CONTRACTOR believes it is entitled as a result of said event.
   have an ongoing obligation to fully inform the DISTRICT             B. DISTRICT's Decision: DISTRICT will render a formal
   by providing immediate written notice of any suspension                decision in writing within sixty (60) days after receipt of the
   or debarment proceedings that it, or any of its affiliates are         last submittal of the CONTRACTOR, if any. DISTRICT's
   presently involved with or were involved with, including               written decision on such Claim, dispute, or other matter will be
   any with Federal, State or local agencies.                             final and binding upon DISTRICT and CONTRACTOR
C. CONTRACTOR shall have an ongoing obligation to fully                   unless an appeal from DISTRICT's decision is taken within the
   inform the District by providing immediate written notice              time limits and in accordance with the dispute resolution
   of any prosecution, conviction, or finding of guilt of the             procedures set forth in Article 16. DISTRICT may issue
   CONTRACTOR, any director, or officer of the                            unilateral change orders as referenced in Article 8.05.
   CONTRACTOR or any of its affiliates, by a Federal, State
   or Local tribunal or other public agency.




   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                00700-2-34
16.03 Step Negotiations                                                         law having jurisdiction in Palm Beach County, FL.

A. Either party must give the other party written notice of any        16.05 Litigation
     dispute not resolved in the normal course of business.
1. STEP1: Executives of both Parties at level one step above           A. If the dispute has not been resolved by negotiation or
     the project personnel (DISTRICT Division Director Level)             mediation as provided herein within sixty (60) days of the
     who have not previously been involved in the dispute shall           initiation of such mediation procedure, either Party may
     meet at a mutually acceptable time and place within ten (10)         initiate litigation upon ten (10) days written notice to the other
     days after delivery of such notice and thereafter as often as        Party; provided, however, that if one Party has requested the
     they reasonably deem necessary, to exchange relevant                 other to participate in a nonbinding procedure, as provided for
     information and to attempt to resolve the dispute.                   under this Article, and the other has failed to participate, the
2. STEP 2: If the matter has not been resolved, then executives           requesting Party may initiate litigation before expiration of the
     of both Parties at levels one step above the personnel               above period.
     (DISTRICT Department Director Level) who have not                 B. The parties hereto agree that all actions or proceedings
     previously been involved in the dispute shall meet at a              arising in connection with this agreement shall be tried and
     mutually acceptable time and place within ten (10) days              litigated exclusively in the State and Federal courts of
     after delivery of such notice and thereafter as often as they        competent jurisdiction located in the State of Florida, Palm
     reasonably deem necessary, to exchange relevant                      Beach County. The aforementioned choice of venue is
     information and to attempt to resolve the dispute.                   intended by the parties to be mandatory and not permissive in
3. STEP 3: If the matter has not been resolved by these persons           nature, thereby precluding the possibility of litigation
     within thirty (30) days from the referral of the dispute to          between the parties with respect to or arising out of this
     senior executives (DISTRICT Deputy Executive Director                Agreement in any jurisdiction other than that specified in this
     Level), or if no meeting of senior executives has taken place        paragraph. The CONTRACTOR agrees to waive any
     within fifteen (15) days after such referral, either Party may       objections to venue or jurisdiction in Palm Beach County,
     initiate mediation as provided hereinafter.                          Florida, for the purpose of litigating any dispute, controversy,
To the extent allowed by law, all negotiations, Settlement                or proceeding arising out of or related to this Agreement.
Agreements and/or other written documentation pursuant to this         C. Each party, to the extent permitted by law, knowingly,
Article shall be confidential and shall be treated as compromise          voluntarily, and intentionally waives its right to a trial by jury
and settlement negotiations for purposes of the Federal Rules of          in any action or other legal proceeding arising out of or
Evidence and Florida Rules of Evidence.                                   relating to this Agreement and the transactions it
                                                                          contemplates. This waiver applies to any action or legal
16.04 Mediation                                                           proceeding, whether sounding in contract, tort or otherwise.

A. If the dispute has not been resolved by the negotiation as          16.06 Auditing of Claims: All claims filed by CONTRACTOR
   provided herein, the Parties shall endeavor to settle the           shall be subject to audit at any time following the filing of the claim
   dispute by mediation. Either Party may initiate a mediation         whether or not such claim is the subject of litigation. The audit and
   proceeding by a request in writing to the other Party,              review of records may be performed by the DISTRICT or its
   thereupon, both Parties will be obligated to engage in              consultants. Such right of audit shall include the records of the
   mediation. The proceeding will be conducted at DISTRICT             CONTRACTOR and its Subcontractors and Suppliers. The audit
   Headquarters, 3301 Gun Club Road, West Palm Beach, FL               may begin on 10 days notice to the CONTRACTOR,
   33406:                                                              Subcontractors, or Suppliers. The CONTRACTOR, Subcontractors
   1. If the Parties have not agreed within thirty (30) days of        and Suppliers shall be required to cooperate with the auditors and
        the request for mediation on the selection of a mediator       provide such information and records as are necessary for analysis
        willing to serve, the DISTRICT will provide a list of          of the claim.
        mediators from which the CONTRACTOR shall
        choose; and                                                    ARTICLE 17 - MISCELLANEOUS
   2. Efforts to reach a settlement will continue until the
        conclusion of the proceeding, which is deemed to occur         17.01 Giving Notice: Whenever any provision of the CONTRACT
        when: (a) a written settlement is reached, or (b) the          Documents requires the giving of written notice, it will be deemed
        mediator concludes and informs the Parties in writing          to have been validly given if delivered in person to the individual or
        that further efforts would not be useful, or (c) the Parties   to a member of the firm or to an officer of the corporation for
        agree in writing that an impasse has been reached.             whom it is intended, or if delivered at or sent by registered or
        Neither Party may withdraw before the conclusion of            certified mail, postage prepaid, to the last business address known
        the proceeding.                                                to the giver of the notice.
   3. The Parties regard the aforesaid obligation to mediate as
        an essential provision of this CONTRACT and one that           17.02 Computation of Times: When any period of time is referred
        is legally binding on them. In case of violation of such       to in the CONTRACT Documents by days, it will be computed to
        obligation by either Party, the other may bring an action      exclude the first and include the last day of such period.
        to seek enforcement of such obligation in any court of

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                   00700-2-35
17.03 Cumulative Remedies: The duties and obligations imposed
by these General Terms & Conditions and the rights and                 17.09 Non-Solicitation: CONTRACTOR shall not directly or
remedies available hereunder to the parties hereto are in addition     indirectly, or through any other person, agency, company or
to, and are not to be construed in any way as a limitation of, any     organization solicit employees of the DISTRICT to undertake
rights and remedies available to any or all of them which are          employment with it, its parent company, or any subsidiary
otherwise imposed or available by Laws or Regulations, by              company or any affiliated company during the performance of
special warranty or guarantee, or by other provisions of the           this CONTRACT and for a period of one (1) year thereafter (the
CONTRACT Documents, and the provisions of this paragraph               “Non-solicitation Period”). CONTRACTOR acknowledges that
will be as effective as if repeated specifically in the CONTRACT       actual or threatened violations of this paragraph may give rise to
Documents in connection with each particular duty, obligation,         irreparable injury to the DISTRICT, inadequately compensable in
right, and remedy to which they apply.                                 damages and, therefore, the DISTRICT may seek and obtain
                                                                       injunctive relief against the breach or threatened breach of
17.04 Survival of Obligations: All representations,                    CONTRACTOR's obligations and undertakings thereunder, in
indemnifications, warranties, and guarantees made in, required         addition to any other legal remedies which may be available.
by, or given in accordance with the CONTRACT Documents, as             This paragraph will survive the termination of this agreement.
well as all continuing obligations indicated in the CONTRACT           Violation of this paragraph during the Non-solicitation Period
Documents, will survive final payment, completion, and                 will be deemed a material breach of CONTRACT.
acceptance of the Work or termination or completion of the
CONTRACT.                                                              ARTICLE 18 - VALUE ENGINEERING

17.05 Controlling Law: This CONTRACT shall be governed by              18.01 General: The CONTRACTOR is encouraged to develop,
the Laws of the State of Florida and be decided in the appropriate     prepare, and submit value engineering proposals (VEPs)
State or Federal Court having jurisdiction in Palm Beach County,       voluntarily. The CONTRACTOR shall share in any CONTRACT
FL, as agreed to in the CONTRACT Documents, which shall                savings realized from accepted VEPs in accordance with paragraph
have exclusive jurisdiction and venue in Palm Beach County, FL         18.05 below.
over all matters in question between the DISTRICT and
CONTRACTOR.                                                            18.02 VEP Preparation: As a minimum, the CONTRACTOR shall
                                                                       include in each VEP the information described in subparagraphs
17.06 Notice to Other Agencies: CONTRACTOR shall notify all            below:
public and private entities or agencies in accordance with any         A. A description of the difference between the existing
and all ordinances, laws, agreements, licenses, and any other               CONTRACT requirement and that proposed, the comparative
directions of construction activity, disruption of access or                advantages and disadvantages of each, a justification when an
services. DISTRICT shall not be responsible for any such                    item's function or characteristics are being altered, and the
notification.                                                               effect of the change on the end item's performance.
                                                                       B. A list and analysis of the CONTRACT requirements that must
17.07 No Conflict with Laws or Regulations: The duties,                     be changed if the VEP is accepted, including any suggested
obligations, criteria or procedure imposed by these General                 specification revisions.
Terms & Conditions and the rights and remedies made available          C. A separate, detailed cost estimate for: 1) the affected portions
are in addition to, and are not to be construed in any way as a             of the existing CONTRACT requirement, and 2) the VEP.
limitation of any rights and remedies available to any or all of            The cost reduction associated with the VEP shall take into
them which are otherwise imposed or available by Laws or                    account the CONTRACTOR's costs, including any amount
Regulations, except that in the event that a specific part or               attributable to subcontracts.
detailed requirement of a provision, criterion or procedure in         D. A description and estimate of costs that the DISTRICT may
these General Terms & Conditions and a specific part or detailed            incur in implementing the VEP, such as test and evaluation,
requirement of a provision, criterion or procedure imposed or               operating, maintenance and support costs.
available by Laws or Regulations are in conflict the specific part     E. A prediction of any effects the proposed change would have on
or detailed requirement of Laws and Regulations shall govern.               the operating costs of the DISTRICT.
All other specific parts or detailed requirements in the provisions,   F. A statement of the time by which a CONTRACT amendment
criteria or procedures of the applicable Laws or Regulations and            accepting the VEP must be issued in order to achieve the
these General Terms & Conditions not in conflict shall remain in            maximum cost reduction, noting any effect on the
full force and effect and be read with the controlling specific part        CONTRACT completion time.
or detailed requirement.                                               G. Identification of any previous submissions of the VEP,
                                                                            including the dates submitted, the CONTRACT numbers
17.08 Advertising: No advertising shall be permitted upon any               involved, and previous DISTRICT actions.
part of the site or structures located on the site. News or press      H. Any design change to the plans and specifications must be
releases pertaining to the services, work product(s), or                    prepared under the supervision of a Professional Engineer in
performance of CONTRACTOR under this CONTRACT or the                        the State of Florida at the CONTRACTOR's expense. Such
Project to which it relates shall be at the sole discretion of              changes must be approved by the CONSTRUCTION
DISTRICT.                                                                   MANAGER.

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                00700-2-36
                                                                     competitive solicitation and contracting activity in accordance
18.03 Submission: The CONTRACTOR shall submit VEPs to                with DISTRICT Rule 40E-7, Part VI, F.A.C. ("SBE Rule"). The
the CONSTRUCTION MANAGER.                                            purpose of the program is to spur economic development and
                                                                     support small businesses, including women-owned and minority-
18.04 DISTRICT Action                                                owned businesses, to successfully expand in the marketplace.

A. The CONSTRUCTION MANAGER shall notify the                         As consideration for being awarded this CONTRACT
   CONTRACTOR of the status of the VEP within fourteen               CONTRACTOR shall maintain the level of SBE participation
   (14) calendar days after CONSTRUCTION MANAGER                     agreed upon and as indicated on the cover/signature page of this
   receives it. If additional time is required, the                  CONTRACT.
   CONSTRUCTION MANAGER shall provide the reason for
   the delay and the expected date of the decision. The              The CONTRACTOR shall take all necessary steps to achieve and
   DISTRICT will review VEPs timely however, it shall not be         maintain its SBE utilization commitment. At any time during the
   liable for any delay in acting upon a VEP.                        term of this CONTRACT, the DISTRICT may request
B. If the VEP is not accepted, the CONSTRUCTION                      information on the SBE status of the CONTRACTOR and/or any
   MANAGER shall notify the CONTRACTOR in writing,                   and all of its subcontractor(s). The CONTRACTOR shall notify
   explaining the reasons for rejection. The CONTRACTOR              the DISTRICT immediately of any change in the status of the
   may withdraw any VEP, in whole or in part, at any time            CONTRACTOR or any of its subcontractor(s), that could affect
   before it is accepted by the DISTRICT.                The         the CONTRACTOR's SBE status or the CONTRACTOR's ability
   CONSTRUCTION MANAGER may require that the                         to comply with the SBE requirements of this CONTRACT
   CONTRACTOR provide written notification before                    including but not limited to gross revenue and licensing.
   undertaking significant expenditures for VEP effort.
C. At the sole discretion of the DISTRICT, any VEP may be            19.02 SBE Utilization Plan. The CONTRACTOR shall identify
   accepted, in whole or in part, by the DISTRICT's execution        all SBE firms which will be utilized as subcontractors. The
   of a Change Order to this CONTRACT. Until a Change                CONTRACTOR should provide proof that each firm to be
   Order is executed which applies a VEP to this CONTRACT,           utilized as an SBE subcontractor is certified with the DISTRICT.
   the CONTRACTOR shall perform in accordance with the               The CONTRACTOR, as the prime and each SBE subcontractor
   existing CONTRACT. The DISTRICT's decision to accept              shall be listed in the Utilization Plan and submitted to the
   or reject, all or part of any VEP, shall be final and not         DISTRICT. The listing of the SBE's in the Utilization Plan shall
   subject to the Disputes clause or otherwise subject to            constitute the CONTRACTOR's representation to the DISTRICT
   litigation.                                                       that the SBE firms are technically and financially qualified and
                                                                     available to perform the assigned work.
18.05 Sharing
A. The CONTRACTOR's share of savings is determined by                The Utilization Plan shall consist of the following DISTRICT
    subtracting DISTRICT costs (as listed herein) from               forms and information as submitted by the CONTRACTOR in its
    CONTRACT savings and multiplying the result by fifty             bid:
    percent (50%) for fixed-price contracts.                              1. SBE Subcontractor Participation Schedule
B. Payment of any share due the CONTRACTOR for use of a                   2. Statement of Intent to Perform as a District Certified SBE
    VEP on this CONTRACT shall be authorized by a Change                       Contractor Form with proof of DISTRICT certification
    Order to this CONTRACT to:
    1. Accept the VEP; and                                           Items (1) through (2) above are hereinafter collectively referred to
    2. Reduce the CONTRACT price by the net savings of the           as the "SBE Plan".
         VEP less CONTRACTOR's share.
                                                                     19.03 Subcontractor Substitution. The CONTRACTOR must
18.06 Subcontracts: The CONTRACTOR is encouraged to                  receive written approval from the DISTRICT's Small Business
include an appropriate value engineering clause in any               Enterprise Section prior to substituting an SBE subcontractor for
subcontract and to share any cost savings with its subcontractors.   any reason, or otherwise modifying the SBE Plan as defined
                                                                     above. The CONTRACTOR must submit to the DISTRICT an
18.07 Substitution: Substitution of materials and/or equipment in    amended version of the following:
lieu of that specified shall not necessarily be considered a VEP.
To be considered as a VEP, the substitution must involve cost              1. SBE Subcontractor Participation Schedule
savings other than a simple reduction in price of the equipment or         2. Statement of Intent to Perform as a District
materials.                                                                 Certified SBE Contractor form for each substituted firm.

ARTICLE 19 – SMALL BUSINESS ENTERPRISE (SBE)                         19.04 Utilization Reporting. In an effort to monitor the
UTILIZATION                                                          achievement of the SBE goal the CONTRACTOR agrees to
                                                                     submit, a completed SBE Utilization Report form, attached hereto
19.01 SBE Utilization. The DISTRICT has implemented a                as Exhibit "E" and made a part of this CONTRACT. The timing
Small Business Enterprise Program as part of the DISTRICT's          of these reports must coincide with invoice submission. The

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-37
CONTRACTOR understands that each SBE utilized for the                      partnering meetings will be scheduled in conjunction with
CONTRACT must be certified by the DISTRICT. The                            progress meetings or at other times as mutually agreed to with
CONTRACTOR shall submit a completed Final SBE                              the DISTRICT.
Utilization Report form, attached hereto as Exhibit "F" and
made a part of this CONTRACT, at the time a final invoice is               Partnering is a management technique which would not create
submitted. These utilization reports must be submitted to the              new duties or obligations not otherwise existing in this
District Resident Engineer at the location as indicated on the             CONTRACT.
cover page of the CONTRACT, with a copy forwarded directly
to the DISTRICT’s Small Business Enterprise Section.                  [OR]

19.05 Compliance. The DISTRICT shall monitor and evaluate             B. FORMAL PARTNERING - In order to most effectively and
compliance with the provisions of the SBE Rule. During the               efficiently accomplish the work provided for in this contract,
term of the CONTRACT, the CONTRACTOR shall comply                        the DISTRICT encourages the formation of a cohesive,
with the SBE Utilization Plan which can only be amended with             mutually beneficial partnership with the CONTRACTOR and
the prior written approval from the DISTRICT's Small Business            its subcontractors. This partnership would strive to draw on
Enterprise Section. Compliance shall include tasks and                   the strengths, skills and knowledge of each organization to
proportionate dollar amounts throughout the term of the                  achieve a quality project done right the first time, within
CONTRACT, including amendments, change orders, and work                  budget, safely and on schedule. The focus of partnering is to
orders. The CONTRACTOR shall maintain the level of SBE                   build cooperative relationships, avoid or minimize disputes,
utilization as established in the CONTRACTOR's SBE Plan                  and actively pursue the attainment of common goals by the
and as indicated on the cover/signature page of this                     contracting parties.     Success will be dependent upon
CONTRACT. Failure to comply with the SBE requirements of                 teamwork      characterized    by     open    and    effective
this CONTRACT will be considered a material breach of                    communication while adhering to the high professional
CONTRACT and may further result in suspension or                         standards. This partnership would be bilateral in make up
debarment pursuant to DISTRICT Rule 40E-7, Part II, F.A.C.               and participation will be totally voluntary. The cost
                                                                         associated with the facilitation of this partnership would be
To ensure that all SBE requirements under this CONTRACT                  paid by the DISTRICT.
are met, the CONTRACTOR's SBE efforts throughout the
performance of the CONTRACT shall be reviewed by the                  ARTICLE 21 – CONTRACTOR’S REPRESENTATIONS
DISTRICT. The CONTRACTOR shall advise the DISTRICT
of any situation in which regularly scheduled payments are not        In order to induce DISTRICT to enter into this CONTRACT,
made to any SBE subcontractor(s).                                     CONTRACTOR makes the following representations:

19.06 Prohibition of Not-To-Compete Agreements. The                   1.   CONTRACTOR has familiarized itself with the nature and
CONTRACTOR is prohibited from entering into any                            extent of the CONTRACT Documents, Work, locality,
agreements with an SBE subcontractor in which the SBE                      weather, and with all local conditions and federal, state and
subcontractor has agreed not to provide subcontracting                     local laws, ordinances, rules, policies and regulations that in
quotations to other respondents or potential respondents.                  any manner may affect cost, progress or performance of the
                                                                           Work.
ARTICLE 20 – PARTNERING                                               2.   CONTRACTOR has studied carefully all reports of
                                                                           investigations and tests of subsurface and latent physical
20.01 Partnering                                                           conditions of the site or otherwise affecting cost, progress or
                                                                           performance of the Work.
A. INFORMAL PARTNERING: It is the DISTRICT's intent to                3.   CONTRACTOR has made or caused to be made examinations,
   use partnering for this project. Partnering is a structured             investigations and tests and studies of such reports and related
   approach to improve communication between all parties and               data in addition to those referred to in paragraph 7.2 as the
   to facilitate problem solving, conflict avoidance, and issue            CONTRACTOR deems necessary for the performance of the
   resolution. The partnering objective is to maximize the                 Work at the CONTRACT Price, within the CONTRACT
   effectiveness of each project participant's resources while             Times and in accordance with the other terms and conditions of
   developing relationships based upon trust, dedication to                the CONTRACT Documents; and no additional examinations,
   common goals, and an understanding of each participant's                investigations, tests, reports or similar data are or will be
   individual expectations and values.                                     required by CONTRACTOR for such purposes.
                                                                      4.   CONTRACTOR has correlated the results of all such
    The DISTRICT does not intend to use a formal partnering                observations, examinations, investigations, tests, reports and
    process for this project. Instead, each team member will               data with the terms and conditions of the CONTRACT
    utilize the principals of partnering, learned from past                Documents.
    experiences, to achieve the specified project objectives. It is   5.   CONTRACTOR has given the DISTRICT written notice of all
    anticipated the partnering process will involve occasional             conflicts, errors or discrepancies that it has discovered in the
    meetings of project participants. The type and location of the         CONTRACT Documents and the written resolution thereof by

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                00700-2-38
     DISTRICT is acceptable to CONTRACTOR.                                  DISTRICT, in the event there is any misrepresentation. The
                                                                            DISTRICT, in the event of such termination, shall not incur
ARTICLE 22 - STANDARDS OF COMPLIANCE                                        any liability to the CONTRACTOR for any work or materials
                                                                            furnished.
1.   The CONTRACTOR, its employees, subcontractors or                  6.   Pursuant to Section 216.347, F.S., the CONTRACTOR is
     assigns, shall comply with all applicable federal, state, and          prohibited from the expenditure of any funds under this
     local laws and regulations relating to the performance of this         CONTRACT to lobby the Legislature, the judicial branch or
     CONTRACT. The DISTRICT undertakes no duty to ensure                    another state agency.
     such compliance, but will attempt to advise the                   7.   The DISTRICT is a governmental entity responsible for
     CONTRACTOR, upon request, as to any such laws of which                 performing a public service and therefore has a legitimate
     it has present knowledge.                                              interest in promoting the goals and objectives of the agency.
2.   The CONTRACTOR hereby assures that no person shall be                  The work under this CONTRACT involves a project
     excluded on the grounds of race, color, creed, national origin,        consistent with these goals and objectives. Consequently, the
     handicap, age, or sex, from participation in, denied the               DISTRICT is desirous of satisfactorily completing and
     benefits of, or be otherwise subjected to discrimination in any        successfully promoting this project with the cooperation of
     activity under this CONTRACT. The CONTRACTOR shall                     its CONTRACTOR. Therefore, the CONTRACTOR assures
     take all measures necessary to effectuate these assurances.            the DISTRICT that the CONTRACTOR, its employees,
3.   CONTRACTOR warrants that it has not employed or                        subcontractors and assigns will refrain from acting adverse to
     retained any person, other than a bona fide employee                   the DISTRICT’S legitimate interest in promoting the goals
     working solely for the CONTRACTOR, to solicit or secure                and objectives of this project. The CONTRACTOR agrees to
     this CONTRACT. Further the CONTRACTOR warrants                         take all reasonable measures necessary to effectuate these
     that it has not paid or agreed to pay any person, other than a         assurances. In the event the CONTRACTOR determines it is
     bona fide employee working solely for the CONTRACTOR,                  unable to meet or promote the goals and objectives of the
     any fee, commission, percentage, gift, or other consideration          project, it shall have the duty to immediately notify the
     contingent upon or resulting from the awarding or making of            DISTRICT. Upon such notification the DISTRICT, in its
     this CONTRACT. For breach of this provision, the                       discretion, may terminate this CONTRACT.
     DISTRICT may terminate this CONTRACT without liability
     and, at its discretion, deduct or otherwise recover the full      ARTICLE 23 - RELATIONSHIP BETWEEN THE PARTIES
     amount of such fee, commission, percentage, gift, or other
     consideration.                                                    1.   CONTRACTOR shall be considered an independent contractor
4.   The CONTRACTOR, by its execution of this CONTRACT,                     and neither party shall be considered an employee or agent of
     acknowledges and attests that neither he, nor any of his               the other party. Nothing in this CONTRACT shall be
     suppliers, subcontractors, or consultants who shall perform            interpreted to establish any relationship other than that of
     Work which is intended to benefit the DISTRICT, is a                   independent contractor between the parties and their respective
     convicted vendor or has been placed on the discriminatory              employees, agents, subcontractors, or assigns during or after the
     vendor list. If the CONTRACTOR or any affiliate of the                 performance on this CONTRACT. Both parties are free to enter
     CONTRACTOR has been convicted of a public entity crime                 into contracts with other parties for similar services. In the
     or has been placed on the discriminatory vendor list, a period         event the CONTRACTOR is providing staff who will be
     longer than thirty-six (36) months has passed since that               working on-site at DISTRICT facilities, CONTRACTOR and
     person was placed on the convicted vendor or discriminatory            the DISTRICT further agree that the DISTRICT shall not pay
     vendor list. The CONTRACTOR further understands and                    the CONTRACTOR staff any direct remuneration, expense
     accepts that this CONTRACT shall be either voidable by the             reimbursement or compensation of any kind and
     DISTRICT or subject to immediate termination by the                    CONTRACTOR’s staff shall not be eligible for any benefit
     DISTRICT, in the event there is any misrepresentation or               programs the DISTRICT offers to its employees. All benefits
     lack of compliance with the mandates of Section 287.133 or             available to the CONTRACTOR’s staff shall be exclusively
     Section 287.134, respectively, Florida Statutes. The                   provided by the CONTRACTOR. The CONTRACTOR shall
     DISTRICT, in the event of such termination, shall not incur            provide all billing, collection, payroll services and tax
     any liability to the CONTRACTOR for any work or                        withholding, among other things, for all CONTRACTOR staff
     materials furnished.                                                   performing services under this CONTRACT.
5.   The CONTRACTOR, by its execution of this                          2.   It is the intent and understanding of the Parties that this
     CONTRACT, acknowledges and attests that neither it, nor                CONTRACT is solely for the benefit of the CONTRACTOR
     any of its suppliers, subcontractors, or consultants who shall         and the DISTRICT. No person or entity other than the
     perform work which is intended to benefit the DISTRICT is              CONTRACTOR or the DISTRICT shall have any rights or
     included on the list of Specially Designated Nationals and             privileges under this CONTRACT in any capacity whatsoever,
     Blocked Persons (SDN List) which is administered by the                either as third-party beneficiary or otherwise.
     U.S. Department of Treasury, Office of Foreign Assets             3.   The CONTRACTOR shall not assign, delegate, or otherwise
     Control. The CONTRACTOR further understands and                        transfer its rights and obligations as set forth in this
     accepts that this CONTRACT shall be either void by the                 CONTRACT without the prior written consent of the
     DISTRICT or subject to immediate termination by the                    DISTRICT. Any attempted assignment in violation of this

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                00700-2-39
     provision shall be null and void.                                 maintained and made available for inspection for a period of five
4.   The CONTRACTOR shall not pledge the DISTRICT’s credit             years from completing performance and receiving final payment
     or make the DISTRICT a guarantor of payment or surety for         under this CONTRACT.
     any contract, debt, obligation, judgment, lien, or any form of            (b) Examination of Records: The DISTRICT or its
     indebtedness.                                                     designated agent shall have the right to examine in accordance with
5.   The DISTRICT assumes no duty with regard to the                   generally accepted governmental auditing standards all records
     supervision      of      the   CONTRACTOR           and     the   directly or indirectly related to this CONTRACT. Such examination
     CONTRACTOR shall remain solely responsible for                    may be made only within five (5) years from the date of final
     compliance with all safety requirements and for the safety        payment under this CONTRACT and upon reasonable notice, time
     of all persons and property at the site of CONTRACT               and place. Records which relate to any litigation, appeals or
     performance. Further, the CONTRACTOR shall be                     settlements of claims arising from performance under this
     responsible for compliance with all labor and                     CONTRACT shall be made available until a final disposition has
     unemployment laws.                                                been made of such litigation, appeals or claims.
6.   CONTRACTOR expressly understands and agrees that                          (c) Cost and Pricing Data: The CONTRACTOR, by
     CONTRACTOR, its officers, agents, and employees, are              executing this CONTRACT, certifies to truth-in-negotiation,
     not entitled to any employment benefits from the                  specifically, that wage rates and other factual unit costs supporting
     DISTRICT. CONTRACTOR expressly and voluntarily                    the consideration are accurate, complete, and current at the time of
     waives and agrees not to make any claim to participate in         contracting. The CONTRACTOR agrees that the DISTRICT may
     any of the DISTRICT’s employee benefits or benefit plans          adjust the consideration for this CONTRACT to exclude any
     should CONTRACTOR or any of its officers, agents, or              significant sums by which the consideration was increased due to
     employees be adjudicated for any reason to be an                  inaccurate, incomplete, or non-current wage rates and other actual
     employee of the DISTRICT. In the event CONTRACTOR                 unit costs. The DISTRICT shall make any such adjustment within
     is self employed, CONTRACTOR expressly represents                 one (1) year following the termination of this CONTRACT.
     that CONTRACTOR is an independent CONTRACTOR                                (d) Applicability to Authorized Agents: In the event that
     and hereby waives any entitlement to overtime or other            any of the Work is delegated by the CONTRACTOR, the
     benefits that CONTRACTOR may be entitled to receive               CONTRACTOR hereby agrees to include in any such
     should CONTRACTOR be adjudicated for any reason to                CONTRACT            a     provision      requiring   such     vendor,
     be an employee of the DISTRICT.”                                  CONTRACTOR, agent and/or subcontractor to agree to the same
7.   At its sole discretion, the DISTRICT has the right to order the   requirement for records retention, inspection and audit rights as
     immediate dismissal of any individual(s) working on behalf        set forth in this Article.
     of the CONTRACTOR at DISTRICT facilities. In such                           (e) Pursuant to Florida Statutes any part of the Work
     event, the CONTRACTOR shall be responsible for carrying           which include building plans, blueprints, schematic drawings, and
     out such dismissal and for returning DISTRICT property in         diagrams, including draft, preliminary, and final formats, which
     accordance with DISTRICT policies and procedures. The             depict the internal layout and structural elements of a building,
     CONTRACTOR may propose a replacement for the                      water treatment facility, or other structure, must be maintained in
     individual(s), subject to the optional approval of the            a confidential manner and secured by the CONTRACTOR and
     DISTRICT. The DISTRICT may also elect to terminate                parties associated with projects assigned under the CONTRACT.
     this CONTRACT, for this reason, without any liability             Review by any unauthorized provider or outside/third party not
     whatsoever to the CONTRACTOR, including but not                   performing work necessary for the assigned Work Order is
     limited to liability for unfinished work product.                 prohibited. This paragraph shall survive the expiration or
8.   CONTRACTOR expressly understands and agrees that                  termination of this CONTRACT.
     CONTRACTOR, its officers, agents, and employees, are not                    (f) The CONTRACTOR and parties associated with
     entitled to any unemployment compensation or workers’             projects assigned under the CONTRACT shall complete, comply
     compensation         benefits    from     the      DISTRICT.      with and furnish to the DISTRICT a signed copy of a Plan and
     CONTRACTOR expressly and voluntarily waives and agrees            Specification Request Form, prior to obtaining such documents
     not to make any claim for such benefits should                    for bidding purposes.
     CONTRACTOR or any of its officers, agents, or employees
     be adjudicated for any reason to be an employee of the            ARTICLE 25 - PUBLIC ACCESS
     DISTRICT.
                                                                       The CONTRACTOR shall allow public access to all project
ARTICLE 24 - RECORDS                                                   documents and materials in accordance with the provisions of
                                                                       Chapter 119, F.S. Should the CONTRACTOR assert any
The CONTRACTOR shall maintain records and the DISTRICT                 exemptions to the requirements of Chapter 119, F.S. and related
shall have inspection and audit rights as follows:                     Statutes, the burden of establishing such exemption, by way of
        (a) Maintenance of Records: The CONTRACTOR shall               injunctive or other relief as provided by law, shall be upon the
maintain all financial and non-financial records and reports           CONTRACTOR.
directly or indirectly related to the negotiation or performance of
this CONTRACT including supporting documentation for any               ARTICLE 26 - CONTRACT DOCUMENTS
service rates, expenses, research or reports. Such records shall be

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-40
The CONTRACT Documents listed below, which are listed in                   representatives in respect to all covenants, agreements and
their order of precedence for the purpose of resolving conflicts,          obligations contained in the CONTRACT Documents.
errors and discrepancies, by this reference, shall become a part of   4.   This CONTRACT states the entire under-standing between the
the CONTRACT as though physically attached as a part thereof:              parties and supersedes any written or oral representations,
       (a) Change Orders, Amendments                                       statements, negotiations, or agreements to the contrary. The
       (b) Field Orders                                                    CONTRACTOR recognizes that any representations,
       (c) CONTRACT                                                        statements or negotiations made by DISTRICT staff or
       (d) Supplemental Conditions.                                        DISTRICT consultants, do not suffice to legally bind the
       (e) General Terms & Conditions                                      DISTRICT in a contractual relationship unless they have been
       (f) General Requirements (Division 1)                               reduced to writing, approved, and signed by an authorized
       (g) Performance and Payment Bonds and Insurance                     DISTRICT representative. This CONTRACT, once properly
       (h) Bidding Documents, including but not limited to:                executed, shall bind the parties, their assigns, and successors in
            Request for Bids, Instructions to Bidders, Bid Bonds           interest.
            and Bid, SBE Utilization Plan, PROVIDED, however          5.   This CONTRACT may be amended only with the prior written
            that no exceptions to the DISTRICT’S Specifications,           approval of the parties.
            whether stated or implied in the CONTRACTOR’s             6.   The CONTRACTOR fully understands and agrees that the
            Bid, shall be allowed EXCEPT as shall be itemized,             DISTRICT shall not pay for any obligation or expenditure
            listed, approved by the DISTRICT and recorded as               made by the CONTRACTOR prior to the commencement date
            written addenda with the DISTRICT as a supplement              of this CONTRACT, unless the DISTRICT authorizes such
            to this CONTRACT.                                              payment in writing.
       (i) Technical Specifications (excluding Division 1)            7.   The CONTRACTOR shall not pledge the DISTRICT’s credit
       (j) Drawings                                                        or make the DISTRICT a guarantor of payment or surety for
       (k) Figure Dimensions                                               any CONTRACT, debt, obligation, judgment, lien or any form
       (l) Scale Dimensions                                                of indebtedness.
Addenda subject matter takes the same precedence of the               8.   Should any term or provision of this CONTRACT be held, to
respective subject matter that it is modifying. Furthermore, each          any extent, invalid or unenforceable, as against any person,
subsequent addendum takes precedence over previous addenda                 entity or circumstance during the term hereof, by force of any
released by the DISTRICT.                                                  statute, law, or ruling of any forum of competent jurisdiction,
                                                                           such invalidity shall not affect any other term or provision of
ARTICLE 27 - NOTICES                                                       this CONTRACT, to the extent that the CONTRACT shall
                                                                           remain operable, enforceable and in full force and effect to the
1.   All notices, demands, or other communications to the                  extent permitted by law.
     CONTRACTOR under this CONTRACT shall be in writing
     and shall be deemed received if sent by certified mail, return   ARTICLE 29 – DAVIS BACON ACT
     receipt requested.
2.   All notices to the DISTRICT under this CONTRACT shall            29.01 Definition.—“Site of the work”—
     be in writing and sent by certified mail.                              (a) Means—
3.   The CONTRACTOR shall also provide a copy of all notices                    (1) The primary site of the work. The physical place or
     to the DISTRICT’s Project Manager. All notices required by       places where the construction called for in the contract will
     this CONTRACT shall be considered delivered upon receipt.        remain when work on it is completed; and
     Should either party change its address, written notice of such             (2) The secondary site of the work, if any. Any other site
     new address shall promptly be sent to the other party.           where a significant portion of the building or work is constructed,
4.   All correspondence to the DISTRICT under this                    provided that such site is—
     CONTRACT shall reference the DISTRICT’s CONTRACT                              (i) Located in the United States; and
     Number.                                                                       (ii) Established specifically for the performance of
                                                                      the contract or project;
ARTICLE 28 - MISCELLANEOUS                                                  (b) Except as provided in paragraph (c) of this definition,
                                                                      includes any fabrication plants, mobile factories, batch plants,
1.   Terms used in this CONTRACT which are defined in Article         borrow pits, job headquarters, tool yards, etc., provided—
     1 of the General Terms & Conditions shall have the                         (1) They are dedicated exclusively, or nearly so, to
     meanings indicated in the General Terms & Conditions.            performance of the contract or project; and
2.   The CONTRACTOR shall not assign, delegate, or otherwise                    (2) They are adjacent or virtually adjacent to the
     transfer its rights and obligations as set forth in this         “primary site of the work” as defined in paragraph (a)(2)(i), or the
     CONTRACT without the prior written consent of the                “secondary site of the work” as defined in paragraph (a)(2)(ii) of
     DISTRICT. Any attempted assignment in violation of this          this definition;
     provision shall be void.                                               (c) Does not include permanent home offices, branch plant
3.   DISTRICT and CONTRACTOR each binds itself, partners,             establishments, fabrication plants, or tool yards of a Contractor or
     successors, assigns and legal representatives to the other       subcontractor whose locations and continuance in operation are
     party hereto, his partners, successors, assigns and legal        determined wholly without regard to a particular Federal contract

     GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                                00700-2-41
or project. In addition, fabrication plants, batch plants, borrow      if any, in a prominent and accessible place where it can be easily
pits, job headquarters, yards, etc., of a commercial or material       seen by the workers.
supplier which are established by a supplier of materials for the
project before opening of bids and not on the Project site, are        29.3 (a) The DISTRICT shall require that any class of laborers or
not included in the “site of the work.” Such permanent,                mechanics which is not listed in the wage determination and
previously established facilities are not a part of the “site of the   which is to be employed under the contract shall be classified in
work” even if the operations for a period of time may be               conformance with the wage determination. The DISTRICT shall
dedicated exclusively or nearly so, to the performance of a            approve an additional classification and wage rate and fringe
contract.                                                              benefits therefore only when all the following criteria have been
                                                                       met:
29.2 (a) All laborers and mechanics employed or working                          (1) The work to be performed by the classification
upon the site of the work will be paid unconditionally and not         requested is not performed by a classification in the wage
less often than once a week, and without subsequent deduction          determination.
or rebate on any account (except such payroll deductions as are                  (2) The classification is utilized in the area by the
permitted by regulations issued by the Secretary of Labor under        construction industry.
the Copeland Act (29 CFR part 3)), the full amount of wages                      (3) The proposed wage rate, including any bona fide
and bona fide fringe benefits (or cash equivalents thereof) due        fringe benefits, bears a reasonable relationship to the wage rates
at time of payment computed at rates not less than those               contained in the wage determination.
contained in the wage determination of the Secretary of Labor                 (b) If the CONTRACTOR and the laborers and mechanics
which is attached hereto and made a part hereof, or as may be          to be employed in the classification (if known), or their
incorporated for a secondary site of the work, regardless of any       representatives, and the DISTRICT agree on the classification and
contractual relationship which may be alleged to exist between         wage rate (including the amount designated for fringe benefits,
the CONTRACTOR and such laborers and mechanics. Any                    where appropriate), a report of the action taken shall be sent by
wage determination incorporated for a secondary site of the            the DISTRICT to the Procurement Department.                   The
work shall be effective from the first day on which work under         Administrator or an authorized representative will approve,
the contract was performed at that site and shall be incorporated      modify, or disapprove every additional classification action
without any adjustment in contract price or estimated cost.            within 30 days of receipt and so advise the DISTRICT or will
Laborers employed by the CONTRACTOR or construction                    notify the DISTRICT within the 30-day period that additional
subcontractor that are transporting portions of the building or        time is necessary.
work between the secondary site of the work and the primary                   (c) In the event the CONTRACTOR, the laborers or
site of the work shall be paid in accordance with the wage             mechanics to be employed in the classification, or their
determination applicable to the primary site of the work.              representatives, and the DISTRICT do not agree on the proposed
                                                                       classification and wage rate (including the amount designated for
(b) Contributions made or costs reasonably anticipated for             fringe benefits, where appropriate), the DISTRICT shall refer the
bona fide fringe benefits under section 1(b)(2) of the Davis-          questions, including the views of all interested parties and the
Bacon Act on behalf of laborers or mechanics are considered            recommendation of the DISTRICT, to the Administrator of the
wages paid to such laborers or mechanics, subject to the               Wage and Hour Division within the Employment Standards
provisions of paragraph (e) of this clause; also, regular              Administration of the Department of Labor for determination.
contributions made or costs incurred for more than a weekly            The Administrator, or an authorized representative, will issue a
period (but not less often than quarterly) under plans, funds, or      determination within 30 days of receipt and so advise the
programs which cover the particular weekly period, are deemed          DISTRICT or will notify the DISTRICT within the 30-day period
to be constructively made or incurred during such period.              that additional time is necessary.
                                                                              (d) The wage rate (including fringe benefits, where
(c) Such laborers and mechanics shall be paid not less than the        appropriate) determined pursuant to paragraphs b and c of this
appropriate wage rate and fringe benefits in the wage                  clause shall be paid to all workers performing work in the
determination for the classification of work actually performed,       classification under this CONTRACT from the first day on which
without regard to skill, except as provided in the clause entitled     work is performed in the classification.
Apprentices and Trainees. Laborers or mechanics performing
work in more than one classification may be compensated at             29.4    Whenever the minimum wage rate prescribed in the
the rate specified for each classification for the time actually       CONTRACT for a class of laborers or mechanics includes a
worked therein; provided that the employer’s payroll records           fringe benefit which is not expressed as an hourly rate, the
accurately set forth the time spent in each classification in          CONTRACTOR shall either pay the benefit as stated in the wage
which work is performed.                                               determination or shall pay another bona fide fringe benefit or an
                                                                       hourly cash equivalent thereof.
 (d)    The wage determination (including any additional
classifications and wage rates conformed under paragraph (c)           29.5 If the CONTRACTOR does not make payments to a trustee
of this clause) and the Davis-Bacon poster (WH-1321) shall be          or other third person, the CONTRACTOR may consider as part of
posted at all times by the Contractor and its subcontractors at        the wages of any laborer or mechanic the amount of any costs
the primary site of the work and the secondary site of the work,       reasonably anticipated in providing bona fide fringe benefits

   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)                                                                               00700-2-42
under a plan or program; provided, That the Secretary of Labor
has found, upon the written request of the CONTRACTOR,
that the applicable standards of the Davis-Bacon Act have been
met. The Secretary of Labor may require the CONTRACTOR
to set aside in a separate account assets for the meeting of
obligations under the plan or program.

ARTICLE 30 – COPELAND ACT

Compliance with Copeland Act Requirements (Feb 1988).
The CONTRACTOR shall comply with the requirements of
29 CFR Part 3, which are hereby incorporated by reference in
this contract.




   GENERAL TERMS & CONDITIONS (Revised 11/16/2009)               00700-2-43
                          POST AWARD FORMS
The following forms are part of the Contract Documents, and are required to be used during the course of
the Contract by CONTRACTOR and DISTRICT except as otherwise allowed by DISTRICT.


       00910          NOTICE OF APPARENT LOW BIDDER

       00920          NOTICE TO PROCEED

       00930          SCHEDULE OF VALUES

       00935          STORED MATERIALS

       00940          APPLICATION FOR PAYMENT/CONTRACTOR'S AFFIDAVIT

       00950          SBE UTILIZATION REPORT – EXHIBIT “E”

       00955          CONTRACTOR’S PERIODIC PERFORMANCE EVALUATION

       00960          SHOP DRAWING SUBMITTAL

       00965          REQUEST FOR INFORMATION

       00970          CHANGE ORDER

       00980          CERTIFICATE OF SUBSTANTIAL COMPLETION

       00990          CERTIFICATE OF FINAL ACCEPTANCE

       00994          SBE FINAL SUBCONTRACTOR UTILIZATION REPORT – EXHIBIT “F”

       00995          CONTRACTOR'S AFFIDAVIT AND FINAL RELEASE

       00996          CONSENT OF SURETY TO FINAL PAYMENT




POST AWARD FORMS                                                                               00900-1
[DATE]

[INSERT Name
Address
City, State, Zip]

Dear [INSERT Name]:

Subject:            Title:
                    Contract No.:
                    NOTICE OF APPARENT LOW BIDDER

ITEM 1: BID CONFIRMATION.

Bids were opened for the subject work on ___________. Your firm is the Apparent Low Bidder of the project at this
time. Please take this opportunity to review your Bid Tabulation worksheets for possible errors or omissions. Should you
consider your bid price to be correct as submitted, it is requested you provide the District a written verification to that
effect. Article 19.02 of the Instructions to Bidders requires you to submit your confirmation no later seven (7) working
days from the date of this Notice.

In the event you discover an error has been made and wish to request withdrawal of your bid, you must supply a detailed
written statement indicating the nature and cause of the error claimed. Also include your original worksheets and clearly
mark in red where the error occurred. Any requested modifications or withdrawals of bids are subject to the limitations
outlined in Article 16 of the Instructions to Bidders. Additionally, you must supply a statement to the fact that, if
permitted to withdraw, you will not participate in the work. Affirmation by you and your bonding company, for your
total bid, will be required prior to any award of this Contract. An authorized withdrawal does not prevent you from
bidding on the same project if the current bids are all rejected and the project is re-advertised.

ITEM 2: INSURANCE CERTIFICATE.

Article 5.04 of the General Terms & Conditions requires you to submit to the District evidence of insurance coverage
within seven (7) working days of the date of this Notice. Please refer to Article 5.04 for minimum requirements of
insurers and limits of coverage. Please refer your insurance agent to the DISTRICT's Insurance Requirements Checklist
provided on Page 00600 of the bidding documents and return to my attention within seven (7) working days from the date
of this Notice.
Note: The CONTRACTOR shall have ninety (90) business days after CONTRACT execution, to produce the required
Insurance Declaration Page of Policy for the insurance requirements set forth in the General Terms & Conditions, and
the Insurance Requirements Checklist.

ITEM 3: PERFORMANCE AND PAYMENT BONDS

Articles 5.02 and 5.03 of the General Terms & Conditions requires you to submit to the District performance and payment
bonds, if the bid amount exceeds $200,000.00, within seven (7) working days of this Notice. Refer to the referenced
articles for minimum bond and surety requirements. Please have an authorized surety agent complete the District bond
forms in full, attach the Affidavit for Surety Form and return to my attention within seven (7) working days of the date of
this Notice. Substitute bond forms will not be accepted by the District.




NOTICE OF APPARENT LOW BIDDER                                                                                  00910-1
ITEM 4: CORRESPONDENCE

All correspondence shall be addressed as follows:

        Bonnie Batchelor, Sr. Contract Specialist
        Procurement Department
        South Florida Water Management District
        P. O. Box 24680
        West Palm Beach, FL 33416-4680
        Fax Number: 561-682-5319

ITEM 5: SUBCONTRACTORS

Article 22 of the Instructions to Bidders requires you to submit to the District a list of all Subcontractors and other
persons and organizations you intend to use on this project, including those who are to furnish the principle items of
material and equipment. Please return this information to the District within seven (7) working days of the date of this
Notice.

ITEM 6: AWARD

Award of this Contract is subject to further District approval. You may check the District's bid postings or call the Bid
Hotline at 800-472-5290 to determine when the official Notice of Intent to Award has been posted. All awards are subject
to the approval of the District's Governing Board or Executive Office. In the event your firm is not awarded the Contract,
the District shall not be responsible for any costs related to bidding or securing award, including but not limited to, bid
preparation, bond and insurance costs. If you have any questions, please contact me at telephone number           .

Please note that failure to provide the requested items (Items 1, 2, 3 & 5) within the time specified herein shall be
sufficient cause for the District to determine your firm as non-responsive, to nullify the Contract award, and to
cause forfeiture of your Bid Guaranty.

Sincerely,



Bonnie Batchelor, CPPB, FCCM, FCCN
Senior Contract Specialist
Procurement Department

/bb
FAXED MATERIAL
CERTIFIED MAIL #




NOTICE OF APPARENT LOW BIDDER                                                                                  00910-2
                               NOTICE TO PROCEED
Date:

CONTRACTOR's NAME:

Attn:

ADDRESS:



Contract No.:                            6000000316
Contract Title:                          S-60 Gate Operator Replacement and Concrete Repairs, Osceola
                                         County, Florida
Subject:                                 NOTICE TO PROCEED
Effective Date of Notice:
Calendar Date:                           Substantial Completion – May 1, 2010
                                         Final Completion – June 1, 2010
Completion Date:                         _____ Substantial Completion
Completion Date:                         _____ Final Completion

Dear ___________:

In accordance with the terms of the Contract Documents for the performance of the Work included in the referenced
project, you are hereby authorized to begin Work on or before the Effective Date of Notice provided above, which shall
constitute the date of the Commencement of the Contract Time.

The Completion Date for all Work under this CONTRACT is as specified above.

Liquidated damages in the amount of $1,000.00 per calendar day, plus all efforts required by the Contractor to insure
that the structure has a flow capacity of 450 cfs, shall be deducted from the Contract Price for failure to complete this
Work by the Substantial Completion Date or any extension thereof. Liquidated damages in the amount of $500.00 per
calendar day shall be deducted from the Contract Price for failure to complete this Work by the Final Completion Date or
any extension thereof.

Contractor shall mobilize and be working on site within ten (10) calendar days following this date, unless agreed to
otherwise in writing.

If you have any questions or need any additional information, please contact me at (561) 682-6235.

Sincerely,

Ulrich Cordon
Director
Construction Department



NOTICE TO PROCEED                                                                                            00920-1
          SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                    SCHEDULES OF VALUES
 CONTRACT NAME:      S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS, OSCEOLA COUNTY, FLORIDA
 CONTRACT NUMBER: 6000000316
 CONTRACTOR:________________________________________________________
   ITEM     DESCRIPTION         LABOR      MATERIAL        EQUIP-      OTHER   EST        UNIT   UNIT      BID
    NO.                                                    MENT                QTY               PRICE   AMOUNT




                                             SUBTOTAL THIS PAGE                                            $



SCHEDULE OF VALUES                                                              00930-1
            SOUTH FLORIDA WATER MANAGEMENT
                        DISTRICT
                 STORED MATERIALS FORM
CONTRACT NAME:     S-60 GATE OPERATOR REPLACEMENT AND CONCRETE                           PAYMENT NO.:
REPAIRS, OSCEOLA COUNTY, FLORIDA                                                         PERIOD ENDING:
CONTRACT NUMBER: 6000000316
CONTRACTOR:
         ITEM/                             (PRIOR MONTH)         (CURRENT MONTH)                 (TOTALS TO DATE)
      DESCRIPTION
(BID ITEM NO. & DESC) LINE 1                 (A)         (B)         (C)         (D)         (E)           (F)      (G)
(SUPPLIER NAME)                           INVOICE      INVOICE    INVOICE      INVOICE    INVOICE       INVOICE    TOTAL
                               INVOICE
LINE 2                                     VALUE        VALUE      VALUE        VALUE      VALUE         VALUE    VALUE
                               NUMBER
                                         DELIVERED   INSTALLED   DELIVERED   INSTALLED   DELIVERED    INSTALLED   STORED
                                             (+)          (-)        (+)          (-)        (+)           (-)       (=)




                                             $           $           $           $           $            $          $




STORED MATERIALS                                                                                                  00935-1
SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                    APPLICATION FOR PAYMENT
                                                                                                         PAGE 1
 CONTRACT TITLE: S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS,                  INVOICE NO.:
 OSCEOLA COUNTY, FLORIDA
 CONTRACT NUMBER: 6000000316                                                           PERIOD ENDING:
 CONTRACTOR:                                             PC NO.:                       LN:
 STREET ADDRESS:                                          CITY STATE:
 VENDOR NO.:                    COMMODITY NO.:            RC NO.:
 INVOICE DATE:
  ITEM         DESCRIPTION         EST    UNIT   UNIT         BID     EARNED THIS PERIOD         EARNED
   NO.                             QTY           PRICE       AMOUNT                              TO DATE

                                                                       QTY        AMOUNT   QTY         AMOUNT




                   SUBTOTAL THIS PAGE 1                  $                    $                    $



Contractor's Remittance Address:




APPLICATION FOR PAYMENT                                                                           00940-1
SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                       APPLICATION FOR PAYMENT
                                                                                                                 PAGE 2



  ITEM            DESCRIPTION             QTY           UNIT    UNIT     BID      EARNED THIS          EARNED
   NO.                                                         PRICE   AMOUNT       PERIOD             TO DATE

                                                                                 QTY    AMOUNT   QTY         AMOUNT




           SUBTOTAL THIS PAGE 2                                                         $                $

           SUBTOTAL PAGE 1                                                              $                $

 TOTAL STORED MATERIALS (NOT INCORPORATED IN THE WORK)                                  $                $

                                                                                TOTAL   $                $

 01. TOTAL WORK COMPLETED TO DATE                                                                        $
 02. TOTAL                                                                                               $
 03. 50% OF TOTAL CONTRACT AMOUNT                                                                        $

 04. Less RETAINAGE
    A. IF LINE 02 IS LESS THAN LINE 03 – THEN 10% OF LINE 02                                             (            )

    B. IF LINE 02 IS GREATER THAN LINE 03 - THEN 10% OF LINE 03 + 5% OF LINE 02 MINUS LINE 03            (            )

 05. AMOUNT DUE TO DATE                                                                                  $

 06. Less PREVIOUS PAYMENTS                                                                              (            )

 07. GROSS AMOUNT DUE THIS PERIOD                                                                            $

 08. Less Payment Discount (Optional) ___%, ____ Days                                                    (            )

 09. NET PAYMENT DUE THIS PERIOD                                                            $




APPLICATION FOR PAYMENT                                                                                 00940-2
SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                          APPLICATION FOR PAYMENT
                           CONTRACTOR'S AFFIDAVIT
                                   CONTRACT PRICE INFORMATION
 ORIGINAL CONTRACT PRICE                                    $____________
 CONTRACT CHANGE ORDER(S) AMOUNT TO DATE                    $____________
 C.O.'S TO DATE NO. _______ TO _______
 CURRENT CONTRACT PRICE                                     $____________
 CONTRACTOR'S AFFIDAVIT
 The undersigned hereby swears under penalty of perjury that:
    1. all previous progress payments received from the DISTRICT on account of Work performed under the contract referred to above
        and have been applied by the Contractor to discharge in full all obligations of the Contractor incurred in connection with Work
        covered by prior Applications for Payment under said contract, being Applications for Payment 1 through ____ inclusive;

    2.   all materials and equipment incorporated in said Project or otherwise listed in or covered by this Application for Payment are free
         and clear of all liens, security interests and encumbrances;

    3.   all previous progress payments have been applied by the Contractor to pay in full (less retainage) all amounts owed to its
         Subcontractors, Suppliers, Materialmen and Equipment Suppliers reflected (and listed) in prior Applications for Payments, except as
         stated on the attached.

    4.   The undersigned Contractor certifies to the best of the Contractor’s knowledge, information and belief the Work covered by this
         Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the
         Contractor for Work for which previous Certificates for Payment were issued and payments received from the District and that
         current payment shown herein is now due.

    5.   The undersigned Contractor certifies that he has not received any Notices of Non-Payment and if any such notices have been
         received shall list them here: _________________________________________________________

    6.   The undersigned Contractor certifies that the percentage of the amount paid to his subcontractor(s) is as indicated below:
           Subcontractor                    Amount of Project             Payment Amount This Month                 Amount Paid to Date




 DATED__________________________________,                                          By:____________________________
                                                                                           CONTRACTOR
 COUNTY OF_____________________________)                                           _______________________________
                                                                                          (NAME AND TITLE)
 STATE OF_______________________________)

 Before            me           on             this         ___________              day          of__________________,     personally
 appeared_________________________________________________________, known to me, who duly sworn, deposes and says that (s)he
 is the _______________________ of the Contractor above mentioned; that (s)he executed the above Application for Payment and statement
 on behalf of said Contractor; and that all statements contained therein are true, correct and complete.

 __________________________________           My Commission Expires____________________
        NOTARY PUBLIC



APPLICATION FOR PAYMENT                                                                                                         00940-3
          CONSTRUCTION INVOICE CHECKLIST
The following items should accompany the monthly pay request:


 Item                  Description                                     Reference        Attached (Y or N)
Number                                                                   Section        Comments or N/A
   1   Contractor’s Schedule of Values                              00700 – 14.02

   2      SFWMD Application for Payment Form                        00700 – 14.02.A.1

   3      SFWMD SBE Utilization Report                              00700 – 14.02.A.2

   4      SFWMD Stored Materials Form (if billed)                   00700 – 14.02.A.

   5      SFWMD Contractor’s Affidavit                              00700 – 14.02.A.3

   6      SFWMD Keys                                                00700 – 14.03.B.2

   7      Contractor’s Progress Photos & Negatives                  01380 – 3.02

   8      Contractor’s Construction Schedule Updates,               01320 – 2.06+
          Cost & Activity Reports and Narrative
   9      Contractor’s Record Documents – Review                    00700 – 6.12.C
          prior to payment approval
   10     Insurance Policy Declaration Page                         00600 -1
          (Must be received within 90 days of Contract Execution)




APPLICATION FOR PAYMENT                                                                              00940-4
                                                                    EXHIBIT “E”                      SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                                                                                         SBE Subcontractor Utilization Report
Project Name S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS,                                         Contract Number                       Application Number
OSCEOLA COUNTY, FLORIDA                                                                                   6000000316
Application Date                       Reporting Period                                                   SBE Goal                              Scheduled Completion Date


Contractor Name                                                                                           Telephone Number (   )                Fax Number (   )

Contractor’s Street Address                                                Project Manager                Manager’s Telephone Number (   )      Manager’s Fax Number (   )

Current Contract Amount                Total Payment This Month            % SBE Part to Date             Total Payment on Project From Start   % Completed



Federal ID         SBE Subcontractor                                       Amount of            Payment Amount     Total Paid To        Actual Start    Scheduled
                                       Description of Work
Number             Name                                                    Project              This Month         Date                 Date            Completion Date




Company Seal                                              Company Officer Name (print)                             Title                                Date

                                                          Signature of Company Officer                                                                  Telephone Number
                                                                                                                                                        (      )-
I certify that the above information is true to the best of my knowledge.
Contractor Name (print)                Contractor Signature                Title                                   Project Name                         Date


                                                                       Form 1217 (11/2006) Page 1 of 1



SBE SUBCONTRACTOR UTILIZATION REPORT                                                                                                                        00950-1
                CONTRACTOR’S PERIODIC
               PERFORMANCE EVALUATION
        Project Name:
         Contract No:
           Contractor:
  Progress Payment #:


                          Performance Measure                     Score
     1        Quality of the Work
     2        Customer Sensitivity
     3        Cost Awareness
     4        Small Business Enterprise Goals
     5        Project Management
     6        Technical Competence
     7        Safety
     8        Schedule
     9        Submittals, RFIs, RFPs, Documentation & Close Out
     10       Environmental Compliance


                                                 Average Score:

     Construction Manager:
Construction Representative:
                      Date:

Notes:




   Score
     4        Excellent
     3        Good
     2        Satisfactory
     1        Poor
     0        Unacceptable
    NA        Not Applicable




CONTRACTOR’S PERIODIC PERFORMANCE EVALUATION                              00955-1
                          Contractor’s Periodic Performance Evaluation
                                            Glossary

1. Quality of the Work – Contractor “builds in quality” by rejecting poor quality work and materials
   without prompting by District staff. When deficient work is found, the contractor immediately
   corrects the work without argument.

2. Customer Sensitivity – Contractor understands and seeks to satisfy the needs of the District, makes
   suggestions to improve the design and constructs the project in a manner that minimizes interruptions
   to operations.

3. Cost Awareness – Contractor resolves issues in a manner that minimizes cost impacts, proposes
   “value engineering” cost savings and avoids unwarranted claims for additional compensation.

4. Small Business Enterprise Goals – Contractor is committed to the participation of small business
   groups in the project and is achieving the contract participation goals.

5. Project Management – Contractor manages, coordinates & directs his workforce, suppliers &
   subcontractors to efficiently advance the progress and quality of the work.

6. Technical Competence – Contractor studies and understands the technical requirements of the contract
   documents, specifically, the plans & specifications. The contractor exhibits the experience and
   resources necessary to accomplish project requirements.

7. Safety - Contractor complies with OSHA requirements & is attentive to safety during all construction
   activities. Contractor performs safety inspections & conducts regular safety training sessions with all
   workers.

8. Schedule – Contractor prepares a complete project schedule that fulfills the contract requirements,
   prosecutes the work as to maintain the project schedule and provides monthly schedule updates that
   reflect the progress of the work.

9. Submittals, RFIs, RFPs, Documentation & Close Out – Contractor submits all project related contract
   documentation in a timely manner. Documentation is complete and technically accurate, provides the
   information necessary to address issues, and accomplishes contract requirements.

10. Environmental Compliance – Contractor is aware of the sensitivity of the environment and takes
    necessary precautions to protect wildlife, prevent turbidity, hydrocarbon spills, etc. Contractor
    complies with all conditions of environmental permits and appropriate laws and regulations.




CONTRACTOR’S PERIODIC PERFORMANCE EVALUATION                                                     00955-2
                             SHOP DRAWING SUBMITTAL

  SOUTH FLORIDA WATER MANAGEMENT DISTRICT
         PROJECT/CONSTRUCTION MANAGEMENT                          SUBMITTAL NO. ________


TO:

FROM:
SUBJECT:
PROJECT:                                        CONTRACTOR:


SUBMITTED BY:
                                   Contractor                                   Date

ITEM NO.
Copies
Description
Prev.Sub. #
Spec. Sect.
Plan Sht.#
                  Accepted As       Accepted As          Accepted As         Accepted As
                  Submitted         Submitted            Submitted           Submitted
                  Accepted As       Accepted As          Accepted As         Accepted As
                  Noted             Noted                Noted               Noted
                  Returned For      Returned For         Returned For        Returned For
                  Revision          Revision             Revision            Revision
                  (see comments)    (see comments)       (see comments)      (see comments)
                  Not Acceptable    Not Acceptable       Not Acceptable      Not Acceptable
                  (see comments)    (see comments)       (see comments)      (see comments)
                                    Preliminary
                  Preliminary                            Preliminary         Preliminary
                                    Submittal
                  Submittal                              Submittal           Submittal
                  For Reference     For Reference        For Reference       For Reference
                  Submittal         Submittal            Submittal           Submittal
                  For Reference     For Reference        For Reference       For Reference
                  Only              Only                 Only                Only
                  Distribution      Distribution         Distribution        Distribution
                  Copy              Copy                 Copy                Copy

              Project Engineer:                       Comments:

              Date:




  SHOP DRAWING SUBMITTAL                                                               00960-1
RFI NO.

                REQUEST FOR INFORMATION
Project:     S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS, OSCEOLA
             COUNTY, FLORIDA
Contract No. 6000000316

Contractor:

                                    QUESTION

Reference: Specification Section:              Drawing No.




Requested by:                                  Date:

                                     REPLY




Reply by:                                      Date:




REQUEST FOR INFORMATION                                            00965-1
                                           CHANGE ORDER NO.
                                                   BETWEEN
                     SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                                                        AND


CONTRACT NO:
CONTRACT TITLE:

The following changes to the CONTRACT are hereby made part of the Contract Documents. All requirements of the
Original Contract Documents shall remain in full force and effect except as modified herein.

I.          ORIGINAL CONTRACT PRICE                                                                              $.00
Price of all previous Change Orders                                                                              $00
PRICE of this Change Order                                                                                     $0.00
The CURRENT CONTRACT PRICE including this Change Order:                                                          $00
II.         CONTRACT ALLOWANCE (Per Specification Section 01020)                                               $0.00
            Contract Allowance Amount for this Change Order                                                    $0.00
            Total Allowance Amount Used to Date                                                                $0.00
            Remaining Allowance Balance                                                                        $0.00
III.        ORIGINAL COMPLETION DATE:                                                                        , 20___
Original Contract Time:                                                                                         Days
Total of all previous Contract Times Adjustments                                                                Days
Contract Times Adjustment this Change Order:                                                                    Days
REVISED Total Contract Times:                                                                                   Days
Revised COMPLETION DATE including this Change Order:                                                         , 20___

All requirements of the original Contract Document shall remain in full force and effect except as modified herein.

IV.         WORK CHANGED BY CHANGE ORDER

A.

       1.   Scope of Work:
       2.   Original contract scope impacted by the change order:
       3.   Cost of Work:
       4.   Justification:




CHANGE ORDER                                                                                                 00970-1
V.    ACKNOWLEDGEMENTS

      The aforementioned change, and work affected thereby, is subject to all provisions of the original contract not
      specifically changed by this Change Order; and,

      It is expressly understood and agreed that the approval of the Change Order shall have no effect on the
      original other than matters expressly provided herein. This change order constitutes the full compensation for
      the work described, including any costs which may result from protracted performance, delays, or extended
      overhead. This Change Order is not to be construed as an admission of any liability on the part of the
      District. This Change Order states the entire understanding and agreement between the parties regarding the
      change order work and supersedes any and all written or oral representations, statements, negotiations, or
      agreements previously existing between the parties with respect to the subject matter of this change order.
      This Change Order is the final and full expression of the parties’ agreement for payment hereunder. Upon
      execution this change order shall be in accord and satisfaction concerning all potential claims related to the
      Change Order work, including inefficiencies or acceleration based claims.


VI.   APPROVAL AND CHANGE ORDER AUTHORIZATION



____________________________________________
Construction Director Reviewed          Date



____________________________________________
SFWMD Procurement Reviewed              Date


ACCEPTED BY CONTRACTOR:



____________________________________________
Title:                                  Date


APPROVED BY:


SOUTH FLORIDA WATER MANAGEMENT DISTRICT



____________________________________________
Frank Hayden, Procurement Director      Date




CHANGE ORDER                                                                                              00970-2
              CERTIFICATE OF SUBSTANTIAL
                     COMPLETION
CONTRACT NO: 6000000316

PROJECT: S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS, OSCEOLA
COUNTY, FLORIDA

CONTRACTOR:

CONTRACT FOR:

CONTRACT DATE:

This Certificate of Substantial Completion applies to all Work under the referenced Contract Documents or
the following specified parts thereof.

Work covered by this Certificate:

The Work to which this Certificate applies has been inspected by authorized representative of
CONTRACTOR, DISTRICT and RESIDENT ENGINEER, and that Work is hereby declared to be
substantially complete in accordance with the Contract Documents on the following date:


                                (DATE OF SUBSTANTIAL COMPLETION)
A Punchlist of items to be completed or corrected is attached hereto. This list may not be all-inclusive, and
the failure to include an item in it does not alter the responsibility of CONTRACTOR to complete all the
Work in accordance with the Contract Documents. The items in the tentative list shall be completed or
corrected by CONTRACTOR within thirty (30) days of the above date of Substantial Completion.

This certificate does not constitute an acceptance of Work not in accordance with the Contract Documents
nor is it a release of CONTRACTOR's obligations to complete the Work in accordance with the Contract
Documents.

Prepared by DISTRICT RESIDENT ENGINEER on                                     , 20      .

By:

CONTRACTOR accepts this Certificate of Substantial Completion

on                                  , 20   .

CONTRACTOR

By:

Title:                                                Date


CERTIFICATE OF SUBSTANTIAL COMPLETION                                                              00980-1
      CERTIFICATE OF FINAL ACCEPTANCE
      SOUTH FLORIDA WATER MANAGEMENT DISTRICT
Contract Title: S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS, OSCEOLA
                      COUNTY, FLORIDA
Contract No.: 6000000316

TO:    Contractor

       Project Manager

A joint inspection of the work described in the Contract Documents has been made by the Resident Engineer,
DISTRICT and the CONTRACTOR on ________________(date) in accordance with Article 14 of the
Contract General Terms & Conditions, and is accepted by the District, subject to the provisions of Article 13
of the Contract General Terms & Conditions, or for a period of warranty as otherwise agreed upon and
attached.

This form will be signed and approved if the following boxes are checked:
       □       Contractor’s Affidavit & Final Release
       □       Consent of Surety to Final Payment
       □       Red-Lined or Final As-Built Drawings
       □       Final Invoice

PREPARED BY DISTRICT:

By:_________________________________________________                 Date_________________
      Resident Engineer

ACCEPTED BY CONTRACTOR:


By:_________________________________________________                 Date_________________
Title:

APPROVED:
SOUTH FLORIDA WATER MANAGEMENT DISTRICT

By:_________________________________________________                 Date_________________
      Department Director

By:_________________________________________________                 Date_________________
      Division/Program Director




CERTIFICATE OF FINAL ACCEPTANCE                                                                   00990-1
                                                                EXHIBIT “F”                                SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                                                                            SBE Final Subcontractor Utilization Report
Project Name S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS,                                             Contract Number                       Application Number
OSCEOLA COUNTY, FLORIDA                                                                                       6000000316
Application Date                       Reporting Period                                                       SBE Goal                              Scheduled Completion Date


Contractor Name                                                                                               Telephone Number (   )                Fax Number (   )

Contractor’s Street Address                                                Project Manager                    Manager’s Telephone Number (   )      Manager’s Fax Number (   )

Current Contract Amount                Total Payment This Month            % SBE Part to Date                 Total Payment on Project From Start   % Completed



Federal ID         SBE Subcontractor                                       Amount of              Payment Amount       Total Paid To        Actual Start    Scheduled
                                       Description of Work
Number             Name                                                    Project                This Month           Date                 Date            Completion Date




Company Seal                                              Company Officer Name (print)                                 Title                                Date


                                                          Signature of Company Officer                                                                      Telephone Number
                                                                                                                                                            (      )-

I certify that the above information is true to the best of my knowledge.
Contractor Name (print)                Contractor Signature                Title                                       Project Name                         Date

                                                                         Form 1218 (11/2006) Page 1 of 1



SBE FINAL SUBCONTRACTOR UTILIZATION REPORT                                                                                                           00994-1
               CONTRACTOR'S AFFIDAVIT AND
                     FINAL RELEASE
                                                                                        STATE OF FLORIDA
                                                                                    COUNTY OF
CONTRACT NO.:             6000000316
CONTRACT TITLE:           S-60 GATE OPERATOR REPLACEMENT AND CONCRETE REPAIRS,
                          OSCEOLA COUNTY, FLORIDA

BEFORE ME, the undersigned authority, personally appeared                         first duly sworn and says that:

1. He/She is                                    of               authorized to do business in
                             (title)                            (company)
    the State of Florida, (hereinafter called "CONTRACTOR").

2. CONTRACTOR, pursuant to CONTRACT dated                            , (hereinafter referred to as "CONTRACT")
   with SOUTH FLORIDA WATER MANAGEMENT DISTRICT, (hereinafter referred to as "DISTRICT"), has
   heretofore furnished or caused to be furnished labor, material and services for the construction of certain
   improvements as more particularly set forth in the CONTRACT.

3. CONTRACTOR represents that all work to be performed under the CONTRACT has been fully completed; that all
   persons and firms who furnished material, labor and/or services incident to the completion of said work have been
   paid in full; and that there are no suits pending against the undersigned CONTRACTOR or anyone in connection
   with the work done and materials furnished or otherwise under said CONTRACT.

4. The CONTRACTOR, for and in consideration of final CONTRACT PRICE in the amount of $______________ ,
    does hereby waive, release, remise and relinquish the CONTRACTOR's right to claim, demand or impose a lien or
    liens for work done or materials and/or services furnished or any other class of liens whatsoever, on any of the
    premises owned by DISTRICT on which improvements have been completed in connection with the CONTRACT.
    Further, CONTRACTOR does hereby and for its heirs, executors, administrators, successors and assigns
    release, acquit and forever discharge and hold harmless the DISTRICT, and its employees, agents, servants,
    successors, heirs, executors, and administrators, of and from any and all claims, actions, causes of action,
    demands, rights, damages, costs, loss of service, expenses, and compensation whatsoever, which the
    undersigned now has or which may hereafter accrue on account of or in any way relating to the CONTRACT.

5. The undersigned further declares and represents that no promise, inducement, or agreement not herein
   expressed has been made to the undersigned, and that this Release contains the entire agreement between the
   parties hereto, and that the terms of this Release are contractual and not a mere recital.

6. The CONTRACTOR herein makes this Affidavit and Final Release for the express purpose of inducing DISTRICT
   to make final disbursement and payment to the CONTRACTOR in the amount of $         .

7. This Affidavit and Final Release is made by CONTRACTOR with full knowledge of the applicable laws of the
   State of Florida. In addition to such rights as may be afforded to DISTRICT under said applicable laws,
   CONTRACTOR expressly agrees to indemnify and save DISTRICT harmless from any and all actual costs and
   expenses, including reasonable attorneys fees, arising out of claims by laborers, sub-contractors or materialmen
   who might claim that they have not been paid for services or material furnished by or through the CONTRACTOR
   in connection with the work performed under the CONTRACT.




CONTRACTOR’S AFFIDAVIT & FINAL RELEASE                                                                     00995-1
8. To the best of CONTRACTOR's knowledge and belief, the following is a list of all employed under this
   CONTRACT who have filed a Notice to Owner with the DISTRICT:

           NAME               ADDRESS                     AMOUNT DUE (If known)
   1.
   2.
   3.
   4.


  (Attach a separate sheet if necessary)



The CONTRACTOR herein does hereby represent that he/she has the authority to execute a full and final
release for and in behalf of the CONTRACTOR as set forth above.



                           (Corporate Seal)   By:


                                              Title:



                                              SWORN TO and subscribed before me this           day of,
                                                                     20       .



                           (Notary Seal)      By:
                                                                          Notary Public

                                              Personally Known ______ OR Produced Identification _____

                                              Type of Identification Produced _______________________

                                              My Commission Expires:




CONTRACTOR’S AFFIDAVIT & FINAL RELEASE                                                        00995-2
CONSENT OF SURETY TO FINAL PAYMENT
We, the ___________________________________________ (“SURETY”), having heretofore executed the Performance and
Payment Bonds for _________________________________________ (“CONTRACTOR”) covering the Project known as
_______________________________________, in the sum of ______________________________________ Dollars
($___________________) hereby agree that the DISTRICT may make full payment of the outstanding contract balance,
including the retained percentage, to said CONTRACTOR. The SURETY concurs that full payment to the CONTRACTOR
is appropriate and the SURETY expressly releases the DISTRICT from all liability to SURETY resulting from full payment
to CONTRACTOR.

          It is fully understood that the acknowledging of the right of the DISTRICT to make payment of the final estimate to
said CONTRACTOR and/or his assigns, shall in no way relieve this SURETY company of its obligations under its bonds, as
set forth in the Contract Documents and Bonds pertaining to the above Project.


This SURETY company further hereby agrees to the following:

1.   Owner is under no obligation, as to SURETY, to conserve any additional funds on the project;


2.   Owner has not made any improper payments on the Project to the CONTRACTOR;


3.   SURETY hereby releases Owner of any potential claim that Owner’s final payment, including retainage, to
     CONTRACTOR is premature or in any way improper;


4.   SURETY has satisfied for itself that CONTRACTOR has performed all conditions precedent entitling it to final payment
     on the Project, including but not limited to the securing of all necessary releases, affidavits, and sworn statements of
     accounts that SURETY may require from CONTRACTOR on the Project;


5.   SURETY has satisfied for itself that CONTRACTOR has performed all Work that would thus entitled it to final payment
     on the Project; and


6.   SURETY’s representations in this Consent Agreement are in no way based upon the representations of the Owner,
     including but not limited to, any representations of payments CONTRACTOR allegedly made to subcontractors,
     suppliers, laborers, or any other lower-tiered persons or entities on the Project.

In no way do the representations and agreements made in this Consent Agreement affect CONTRACTOR’s obligations to the
Owner or SURETY on the Project. CONTRACTOR is not an intended third-party beneficiary to this Consent Agreement.




CONSENT OF SURETY TO FINAL PAYMENT                                                                        00996-1
         IN WITNESS WHEREOF, the _______________________ has caused this instrument to be executed on its behalf of
its ___________________________ and its duly authorized attorney in fact, and its corporate seal to be hereunto affixed, all
on this ______ day of ___________, 20___.


________________________                             __________________________
SURETY Company                                               Attorney-in-Fact

           (Power of Attorney must be attached if executed by Attorney-in-Fact)

State of                   )
                                   )ss
County of                          )

          The foregoing instrument was acknowledged before me this ___day of _________, 20___, by
_____________________________, who is personally known to me or who has produced _________________________ as
identification.



_______________________                                      Print name:____________________
       Signature                                             Notary Public in and for the County and State Aforementioned

                                                             My commission expires:________________




CONSENT OF SURETY TO FINAL PAYMENT                                                                       00996-2
                                                                                                                                  e-Hardcopy 2.0
                                                                                                                                     Automated Report



                                                                                                                                               08/24/09

                                                                                                                                                     08/24/09




                                                Technical Report for


                                               DPS Corp
                                               S-60 LBP Survey, Old Hickory Rd, St Cloud, FL


                                               Accutest Job Number: F67356

                                               Sampling Date: 08/13/09



                                               Report to:
                                               DPS Corp
                                               27915 Johnston Rd
                                               Dade City, FL 33523
                                               scrandall@dps-corp.com
                                               ATTN: Scott Crandall




                                               Total number of pages in report:                  10




                                               Test results contained within this data package meet the requirements        Harry Behzadi, Ph.D.
                                               of the National Environmental Laboratory Accreditation Conference            Laboratory Director
                                               and/or state specific certification programs as applicable.

                                               Client Service contact: Jean Dent-Smith 407-425-6700

                                               Certifications: FL (DOH E83510), NC (573), NJ (FL002), MA (FL946), IA (366), LA (03051), KS (E-10327), SC, AK
                                               This report shall not be reproduced, except in its entirety, without the written approval of Accutest Laboratories.
                                               Test results relate only to samples analyzed.



                Southeast • 4405 Vineland Road • Suite C-15 • Orlando, FL 32811 • tel: 407-425-6700 • fax: 407-425-0707 • http://www.accutest.com
                                                                                                                                                                 1 of 10
Accutest Laboratories is the sole authority for authorizing edits or modifications to this
document. Unauthorized modification of this report is strictly prohibited.
                                                                                                                                                  F67356
                                                                                                                                       Sections:
                                                Table of Contents




                                                                                                                                                   1
                                                             -1-




                                                                                                                                                   2
Section 1: Sample Summary ...................................................................................................          3
Section 2: Sample Results ........................................................................................................     4




                                                                                                                                                   3
   2.1: F67356-1: SAMPLE 1 ..................................................................................................          5
   2.2: F67356-2: SAMPLE 2 ..................................................................................................          6
   2.3: F67356-3: SAMPLE 3 ..................................................................................................          7
Section 3: Misc. Forms ............................................................................................................    8
   3.1: Chain of Custody ...........................................................................................................   9




                                                                                                                                               2 of 10
                                                                                                                                  F67356
                                                                                                                  1
Accutest Laboratories




                                             Sample Summary
DPS Corp
                                                                                         Job No:   F67356
S-60 LBP Survey, Old Hickory Rd, St Cloud, FL


Sample        Collected                         Matrix                         Client
Number        Date      Time By        Received Code Type                      Sample ID

F67356-1      08/13/09 11:00 SC        08/15/09 SO      Soil                   SAMPLE 1


F67356-2      08/13/09 11:15 SC        08/15/09 SO      Soil                   SAMPLE 2


F67356-3      08/13/09 11:30 SC        08/15/09 SO      Soil                   SAMPLE 3




Soil samples reported on a dry weight basis unless otherwise indicated on result page.

                                                                                                               3 of 10
                                                                                                      F67356
Accutest Laboratories




                                                         2
                                             Section 2




                        Sample Results




                        Report of Analysis




                                                      4 of 10
                                             F67356
                                                                                                                             2.1
Accutest Laboratories




                                                                                                                            2
                                              Report of Analysis                                           Page 1 of 1

Client Sample ID: SAMPLE 1
Lab Sample ID:    F67356-1                                       Date Sampled: 08/13/09
Matrix:           SO - Soil                                      Date Received: 08/15/09
                                                                 Percent Solids: n/a a
Project:             S-60 LBP Survey, Old Hickory Rd, St Cloud, FL

Metals Analysis

Analyte           Result     RL       MDL      Units    DF    Prep      Analyzed By      Method          Prep Method

Lead b            22.2       20       0.90     mg/kg 4        08/19/09 08/20/09    RS    SW846 6010B 1   SW846 3050B 2

(1) Instrument QC Batch: MA7437
(2) Prep QC Batch: MP16853

(a) Percent solids not analyzed due to sample matrix. Results reported on wet weight basis.
(b) Elevated reporting limit(s) due to matrix interference.




RL = Reporting Limit = PQL                                           U = Indicates a result < MDL
MDL = Method Detection Limit                                         I = Indicates a result >= MDL but < RL

                                                                                                                         5 of 10
                                                                                                          F67356
                                                                                                                             2.2
Accutest Laboratories




                                                                                                                            2
                                              Report of Analysis                                           Page 1 of 1

Client Sample ID: SAMPLE 2
Lab Sample ID:    F67356-2                                          Date Sampled: 08/13/09
Matrix:           SO - Soil                                         Date Received: 08/15/09
                                                                    Percent Solids: n/a a
Project:                S-60 LBP Survey, Old Hickory Rd, St Cloud, FL

Metals Analysis

Analyte           Result       RL      MDL     Units    DF    Prep      Analyzed By      Method          Prep Method

Lead              489          20      0.89    mg/kg 4        08/19/09 08/20/09    RS    SW846 6010B 1   SW846 3050B 2

(1) Instrument QC Batch: MA7437
(2) Prep QC Batch: MP16853

(a) Percent solids not analyzed due to sample matrix. Results reported on wet weight basis.




RL = Reporting Limit = PQL                                           U = Indicates a result < MDL
MDL = Method Detection Limit                                         I = Indicates a result >= MDL but < RL

                                                                                                                         6 of 10
                                                                                                          F67356
                                                                                                                             2.3
Accutest Laboratories




                                                                                                                            2
                                              Report of Analysis                                           Page 1 of 1

Client Sample ID: SAMPLE 3
Lab Sample ID:    F67356-3                                          Date Sampled: 08/13/09
Matrix:           SO - Soil                                         Date Received: 08/15/09
                                                                    Percent Solids: n/a a
Project:                S-60 LBP Survey, Old Hickory Rd, St Cloud, FL

Metals Analysis

Analyte           Result       RL      MDL     Units    DF    Prep      Analyzed By      Method          Prep Method

Lead b            145          19      0.87    mg/kg 4        08/19/09 08/20/09    RS    SW846 6010B 1   SW846 3050B 2

(1) Instrument QC Batch: MA7437
(2) Prep QC Batch: MP16853

(a) Percent solids not analyzed due to sample matrix. Results reported on wet weight basis.
(b) Elevated reporting limit(s) due to matrix interference.




RL = Reporting Limit = PQL                                           U = Indicates a result < MDL
MDL = Method Detection Limit                                         I = Indicates a result >= MDL but < RL

                                                                                                                         7 of 10
                                                                                                          F67356
Accutest Laboratories
                                                                   Section 3




                                                                               3
                        Misc. Forms




                        Custody Documents and Other Forms




                        Includes the following where applicable:
                        • Certification Exceptions
                        • Chain of Custody




                                                                            8 of 10
                                                                   F67356
                            3.1
                            3
F67356: Chain of Custody
              Page 1 of 2




                        9 of 10
               F67356
                            33.1
F67356: Chain of Custody
              Page 2 of 2




                        10 of 10
               F67356
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   1


GENERAL CONSTRUCTION                                                   968-42

  3 RS EQUIP INC                                   Phone: 239-597-0093
   PO BOX 113                                      Fax:   239-597-0095
  BONITA SPRINGS FL 34133                          Vendor:100591       SBE: Y
  Email : RICHARDSCOMPANY@COMCAST.NET
  Cert.Valid From Date: 01/21/2009               Cert.Valid To Date: 01/21/2012

  3C CONSTRCTN CORP                                Phone: 305-638-5511
   3601 NW 55TH ST                                 Fax:   305-638-5515
  MIAMI FL 33142-2701                              Vendor:105346       SBE: V
  Email : OJC@3CCONSTRUCTIONCORP.COM
  Cert.Valid From Date: 05/30/2007               Cert.Valid To Date: 05/29/2010

  A2 GRP INC                                       Phone: 305-668-8939
   PO BOX 432310                                   Fax:   305-668-9454
  MIAMI FL 33423-2310                              Vendor:115876       SBE: Y
  Email : RIBASA@A2GROUP.COM
  Cert.Valid From Date: 03/05/2009               Cert.Valid To Date: 03/05/2012

  AA ENGRG SVCS INC                                Phone: 561-417-0675
   1650 S DIXIE HWY STE 203                        Fax:   561-620-2619
  BOCA RATON FL 33432                              Vendor:110313       SBE: V
  Email : RP@AAENGSERVICES.COM
  Cert.Valid From Date: 03/06/2007               Cert.Valid To Date: 03/05/2010

  AARON CONSTRCTN INC                              Phone: 954-434-1831
   15011 S SAXON CIR                               Fax:   954-434-3069
  SW RANCHES FL 33331                              Vendor:114999       SBE: Y
  Email : KARARON24@AOL.COM
  Cert.Valid From Date: 03/03/2008               Cert.Valid To Date: 03/03/2011

  ACB2 ENGRG INC                                   Phone: 786-286-7574
   PO BOX 823612                                   Fax:   954-450-3219
  PEMBROKE PINES FL 33082                          Vendor:113571       SBE: V
  Email : ANTONIOAA@COMCAST.NET
  Cert.Valid From Date: 03/06/2007               Cert.Valid To Date: 03/05/2010

  ACME ORGANIZATION INC                            Phone: 305-577-3525
   1730 BISCAYNE BLVD STE 201G                     Fax:   305-577-0198
  MIAMI FL 33132                                   Vendor:106967       SBE: T
  Email : ACMEORG98@AOL.COM
  Cert.Valid From Date: 06/30/2009               Cert.Valid To Date: 06/30/2012

  ACRE ENGRG & CONSTRCTN INC                       Phone: 305-436-5102
   2500 NW 79TH AVE STE 168                        Fax:   305-436-5108
  DORAL FL 33122                                   Vendor:115343       SBE: V
  Email : JOSEANGELBUSTOS@ACRECONSTRUCTION.COM
  Cert.Valid From Date: 08/28/2008               Cert.Valid To Date: 08/28/2011

  ACROPOLIS DEV GRP INC                            Phone: 305-285-7373
   1385 CORAL WAY STE 403                          Fax:   305-285-2363
  MIAMI FL 33145                                   Vendor:114194       SBE: Y
  Email : RLONDONO@ADAAG-CONSULTING
  Cert.Valid From Date: 05/02/2008               Cert.Valid To Date: 05/01/2011
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   2

  ADVENTURE ENVIRON INC                            Phone: 305-254-8887
   12935 SW 87TH AVE                               Fax:   305-252-5962
  MIAMI FL 33176                                   Vendor:103391       SBE: Y
  Email : 4ADVENTURE@EARTHLINK.NET
  Cert.Valid From Date: 10/15/2009               Cert.Valid To Date: 10/15/2012

  AEC GENERAL INC                                  Phone: 239-479-6269
   PO BOX 1986                                     Fax:   239-332-0182
  LEHIGH ACRES FL 33970                            Vendor:106578       SBE: Y
  Email : JADON.HULL@AIMENRG.COM
  Cert.Valid From Date: 12/04/2008               Cert.Valid To Date: 12/04/2011

  AGC ELECTRIC INC                                 Phone: 305-823-2280
   2660 W 79TH ST                                  Fax:   305-828-4515
  HIALEAH FL 33016                                 Vendor:114167       SBE: V
  Email : AGC@AGCELECTRIC.COM
  Cert.Valid From Date: 06/23/2007               Cert.Valid To Date: 06/22/2010

  ALBERTZ CONSTRCTN INC                            Phone: 561-848-5150
   3648 E INDUSTRIAL WAY STE 2                     Fax:   561-848-5151
  RIVIERA BEACH FL 33404                           Vendor:107879       SBE: Y
  Email : MALBERTZ@BELLSOUTH.NET
  Cert.Valid From Date: 03/13/2007               Cert.Valid To Date: 03/12/2010

  ALL FLORIDA CONSTRCTN GRP OF                     Phone: 941-628-9131
   10050 BURNT STONE RD                            Fax:   941-639-2165
  PUNTA GORDA FL 33950                             Vendor:115911       SBE: Y
  Email : RSAMICK@SUNLINE.NET
  Cert.Valid From Date: 12/11/2008               Cert.Valid To Date: 12/11/2011

  AMERCN EMPIRE BUILDERS INC                       Phone: 305-266-5356
   250 CATALONIA AVE STE 504                       Fax:   305-266-5421
  CORAL GABLES FL 33134                            Vendor:116182       SBE: V
  Email : MPRINCE@AMERICAEMPIREBUILDERS.COM
  Cert.Valid From Date: 02/19/2009               Cert.Valid To Date: 02/19/2012

  AMERS CONSTRCTN CO                               Phone: 305-949-9456
   2831 SW 190TH AVE                               Fax:   305-704-8302
  MIRAMAR FL 33029                                 Vendor:115898       SBE: Y
  Email : VLOPEZ@AMERICASCONSTRUCTION.US
  Cert.Valid From Date: 12/11/2008               Cert.Valid To Date: 12/11/2011

  ANDALE GRP LLC                                   Phone: 305-715-7335
   2501 NW 74TH AVE                                Fax:   305-592-5937
  DORAL FL 33122                                   Vendor:117059       SBE: V
  Email : DAN@ANDALEGROUP.COM
  Cert.Valid From Date: 10/08/2009               Cert.Valid To Date: 10/08/2012

  ANTINORI MGMT GRP INC                            Phone: 386-761-2805
   5629 S RIDGEWOOD AVE                            Fax:   386-761-4311
  PRT ORANGE FL 32127                              Vendor:115282       SBE: Y
  Email : ANTINORICONSTRUCTION@YAHOO.COM
  Cert.Valid From Date: 11/03/2008               Cert.Valid To Date: 11/03/2011

  ASAP INSTALLATIONS LLC                           Phone: 813-385-7257
   4304 WATERFORD LANDING DR                       Fax:   813-948-8934
  LUTZ FL 33558                                    Vendor:116707       SBE: Y
  Email : SIMON@ASAPINSTALLATIONS.NET
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   3

  Cert.Valid From Date: 07/01/2009               Cert.Valid To Date: 07/01/2012

  ASMUSSEN ENGRG LLC                               Phone: 863-763-8546
   PO BOX 1998                                     Fax:   863-467-8560
  OKEECHOBEE FL 34973                              Vendor:106569       SBE: Y
  Email : LASMUSSE@EMBARQMAIL.COM
  Cert.Valid From Date: 02/02/2007               Cert.Valid To Date: 02/01/2010

  ASSOCIATED DIVING & MARINE                       Phone: 352-425-0384
   1473 PIONEER RD STE C                           Fax:   801-886-8130
  SALT LAKE CITY UT 84104                          Vendor:113471       SBE: Y
  Email : MARINEOPS@DIVING-MARINE.COM
  Cert.Valid From Date: 01/31/2007               Cert.Valid To Date: 01/30/2010

  AUTHENTIC CONSTRCTN LLC                          Phone: 305-529-2221
   4108 LAGUNA ST 2ND FL                           Fax:   305-675-3645
  CORAL GABLES FL 33146                            Vendor:116260       SBE: Y
  Email : RAY@AUTHENTICCONSTRUCT.COM
  Cert.Valid From Date: 03/11/2009               Cert.Valid To Date: 03/11/2012

  BALLARD CONTRACTORS INC                          Phone: 772-216-5543
   PO BOX 2281                                     Fax:
  OKEECHOBEE FL 34973                              Vendor:114182       SBE: Y
  Email :
  Cert.Valid From Date: 01/28/2009               Cert.Valid To Date: 01/28/2012

  BDI CONSTRCTN CO                                 Phone: 305-592-1210
   7270 NW 12TH ST STE 200                         Fax:   305-592-5603
  MIAMI FL 33126                                   Vendor:101435       SBE: Y
  Email : TROSELL@BDICO.COM
  Cert.Valid From Date: 10/05/2006               Cert.Valid To Date: 10/04/2009

  BENCHMARK III CORP                               Phone: 772-320-0206
   3322 GRANPARK WAY                               Fax:   772-320-0209
  STUART FL 34997                                  Vendor:116741       SBE: Y
  Email : B3AVA@AOL.COM
  Cert.Valid From Date: 07/01/2009               Cert.Valid To Date: 07/01/2012

  BETANCOURT CONSTRCTN INC                         Phone: 954-640-4400
   10831 NW 122ND ST                               Fax:   954-650-4401
  MEDLEY FL 33178                                  Vendor:115681       SBE: V
  Email : MARY@BETANCOURTCONSTRUCTION.COM
  Cert.Valid From Date: 08/25/2009               Cert.Valid To Date: 08/25/2012

  BOB ROCKWELL CONSTRCTN INC                       Phone: 239-466-8980
   11615 CHITWOOD DR STE C                         Fax:
  FT MYERS FL 33908                                Vendor:112730       SBE: Y
  Email : BRCTREE@STRATO.NET
  Cert.Valid From Date: 11/09/2006               Cert.Valid To Date: 11/08/2009

  BOYD IRRIGATION INC                              Phone: 239-543-1616
   8050 BAYSHORE RD                                Fax:   239-543-4676
  NORTH FT MYERS FL 33917                          Vendor:115895       SBE: X
  Email : JBOYD@BOYDIRRIGATION.COM
  Cert.Valid From Date: 12/04/2008               Cert.Valid To Date: 12/04/2011
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   4

  BPC GRP INC                                      Phone: 561-514-3011
   1201 BELVEDERE RD STE B                         Fax:   561-514-3061
  WEST PALM BEACH FL 33405                         Vendor:101876       SBE: U
  Email : BPANIGRAHI@BPCGI.COM
  Cert.Valid From Date: 12/19/2006               Cert.Valid To Date: 12/18/2009

  BPC GRP INC                                      Phone: 407-851-5020
   6925 LAKE ELLENOR DR STE 112                    Fax:   407-857-3154
  ORLANDO FL 32809                                 Vendor:114488       SBE: U
  Email : BPANIGRAHI@BPCGI.COM
  Cert.Valid From Date: 12/18/2006               Cert.Valid To Date: 12/18/2009

  BREAKING GROUND CONTRG CO INC                    Phone: 904-388-1350
   4218 HIGHWAY AVE                                Fax:   904-388-3440
  JACKSONVILLE FL 32254                            Vendor:104102       SBE: X
  Email : MGTAPP@EARTHLINK.NET
  Cert.Valid From Date: 01/11/2007               Cert.Valid To Date: 01/10/2010

  BRI SAND FORMING CO INC                          Phone: 561-333-3676
   8233 GATOR LN #25                               Fax:   561-333-3675
  WEST PALM BEACH FL 33411                         Vendor:115708       SBE: Y
  Email : BRISANDFORMING@AOL.COM
  Cert.Valid From Date: 10/20/2008               Cert.Valid To Date: 10/20/2011

  BRIGCON CONSULTING SVCS LLC                      Phone: 954-444-8970
   3320 KAPOT TER                                  Fax:   954-392-0315
  MIRAMAR FL 33025                                 Vendor:114084       SBE: T
  Email : VERNWILLIAMS@BELLSOUTH.NET
  Cert.Valid From Date: 06/19/2007               Cert.Valid To Date: 06/18/2010

  BUL HED CORP                                     Phone: 863-804-0044
   PO BOX 1301                                     Fax:   863-804-0055
  MULBERRY FL 33860                                Vendor:106851       SBE: Y
  Email : RHEDRICK@BULHED.COM
  Cert.Valid From Date: 06/12/2007               Cert.Valid To Date: 06/11/2010

  C SQUARED CONSTRCTN INC                          Phone: 305-669-3881
   7116 SW 47TH ST                                 Fax:   305-669-3887
  MIAMI FL 33155                                   Vendor:116189       SBE: V
  Email : CARLOS@C2SHELL.COM
  Cert.Valid From Date: 02/20/2009               Cert.Valid To Date: 02/20/2012

  C&L EXCAVATING INC                               Phone: 863-227-2004
   215 E SR 78                                     Fax:   863-946-2439
  LAKEPORT FL 33471                                Vendor:102739       SBE: X
  Email : CAROLYNS@EMBARQMAIL.COM
  Cert.Valid From Date: 07/30/2009               Cert.Valid To Date: 07/30/2012

  CALLAWAY MARINE TECHLGYS INC                     Phone: 561-471-1771
   2765 VISTA PKWY N BLDG H4                       Fax:   561-471-1793
  WEST PALM BEACH FL 33411                         Vendor:103754       SBE: Y
  Email : CMARINET@GATE.NET
  Cert.Valid From Date: 12/19/2006               Cert.Valid To Date: 12/18/2009

  CAM GRP LLC                                      Phone: 866-652-9050
   PO BOX 2481                                     Fax:
  FT PIERCE FL 34984                               Vendor:114872       SBE: Y
  Email : CAMGROUPLLC@GMAIL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   5

  Cert.Valid From Date: 03/04/2008               Cert.Valid To Date: 03/04/2011

  CAN CONSTRCTN INC                                Phone: 863-674-1002
   1080 COMMERCE DR BLDG 1                         Fax:   863-674-1003
  LA BELLE FL 33935                                Vendor:108790       SBE: Y
  Email : CANCONSTRUCTION@EMBARQMAIL.COM
  Cert.Valid From Date: 10/14/2009               Cert.Valid To Date: 10/14/2012

  CASTCO CONSTRCTN INC                             Phone: 727-585-4714
   9001 126TH AVE N                                Fax:   727-585-5091
  LARGO FL 33773                                   Vendor:104074       SBE: V
  Email : CCONSTR@TAMPABAY.RR.COM
  Cert.Valid From Date: 07/21/2009               Cert.Valid To Date: 07/21/2012

  CDL EARTH MOVING & PAVING CORP                   Phone: 561-791-8271
   7655 ENTERPRISE DR #A3                          Fax:   561-791-8273
  WEST PALM BEACH FL 33404                         Vendor:115333       SBE: Y
  Email : CDLEARTHMOVING@BELLSOUTH.NET
  Cert.Valid From Date: 06/26/2008               Cert.Valid To Date: 06/25/2011

  CEB CONSTRCTN INC                                Phone: 786-331-9499
   2451 NW 109TH AVE UNIT 4                        Fax:   305-591-4084
  MIAMI FL 33172                                   Vendor:110206       SBE: Y
  Email : CEB@CEBENGINEERING.COM
  Cert.Valid From Date: 07/25/2008               Cert.Valid To Date: 07/24/2011

  CEDARS ELECTRO MECHANICAL INC                    Phone: 561-588-4088
   1712 S DIXIE HWY                                Fax:   561-588-4087
  LAKE WORTH FL 33460                              Vendor:104483       SBE: Y
  Email : INFO@CEDARSINC.COM
  Cert.Valid From Date: 12/02/2006               Cert.Valid To Date: 12/01/2009

  CHAMPION CONTRACTING OF CENTRAL                  Phone: 321-863-4948
   9065 ELLIS RD                                   Fax:   321-726-0078
  WEST MELBOURNE FL 32904                          Vendor:110358       SBE: Y
  Email : CCHAMPION@CHAMPIONCONTRACTING.COM
  Cert.Valid From Date: 12/03/2008               Cert.Valid To Date: 12/03/2011

  CHANDLER LAND DEV CORP                           Phone: 239-334-4953
   3310 HANSON ST                                  Fax:   239-334-4957
  FT MYERS FL 33916-7513                           Vendor:111215       SBE: Y
  Email : LUKEC@CHANDLER-LAND.COM
  Cert.Valid From Date: 04/04/2007               Cert.Valid To Date: 04/03/2010

  CHESTERFIELD PROPERTIES INC                      Phone: 407-650-9964
   601 N MAGNOLIA AVE STE 300                      Fax:   407-470-1400
  ORLANDO FL 32801                                 Vendor:109118       SBE: V
  Email : RLAPORTE@LIQUIDGRASS.NET
  Cert.Valid From Date: 03/20/2007               Cert.Valid To Date: 03/19/2010

  CIGTON CONSTRCTN CORP                            Phone: 954-681-9376
   3800 S SR 7                                     Fax:   954-443-0533
  MIRAMAR FL 33023                                 Vendor:117129       SBE: V
  Email : CREOLAESTATESLLC@COMCAST.NET
  Cert.Valid From Date: 11/02/2009               Cert.Valid To Date: 11/02/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                        Page No #.   6

  CIMA ENGRG CORP                                  Phone: 305-835-0262
   7404 NW 12TH AVE                                Fax:   305-832-8511
  MIAMI FL 33150                                   Vendor:113109       SBE: V
  Email : JOSEAGONZALEZ@CIMAENG.COM
  Cert.Valid From Date: 12/14/2006                Cert.Valid To Date: 12/13/2009

  CISNEROS & SONS CONSTRCTN                        Phone: 305-872-1559
   30451 HIBISCUS LN                               Fax:   305-872-1559
  BIG PINE KEY FL 33043                            Vendor:113343       SBE: Y
  Email : CISNER@BELLSOUTH.NET
  Cert.Valid From Date: 02/08/2007                Cert.Valid To Date: 02/07/2010

  CL ELIAS CONSTRCTN INC                           Phone: 305-662-3837
   7440 SW 50 TER UNIT 103                         Fax:   305-661-5791
  MIAMI FL 33155                                   Vendor:115340       SBE: V
  Email : CHRISTI.ELIAS@CLELIASCONST.COM
  Cert.Valid From Date: 11/07/2008                Cert.Valid To Date: 11/07/2011

  CLARYS SITEWORK & DEV INC                        Phone: 239-997-4004
   4461A HANCOCK BRIDGE PKWY                       Fax:   239-997-0411
  NORTH FT MYERS FL 33903                          Vendor:110497       SBE: Y
  Email : JLCLARY@CLARYSITEWORK.COM
  Cert.Valid From Date: 08/12/2009                Cert.Valid To Date: 08/12/2012

  CLAUDE G WILLIAMS JR CONST                       Phone: 772-597-4001
   26660 SW MARTIN HWY                             Fax:   772-597-3999
  OKEECHOBEE FL 34974                              Vendor:109543       SBE: Y
  Email : CGWCONSTR@ONEARROW.NET
  Cert.Valid From Date: 09/29/2009                Cert.Valid To Date: 09/29/2012

  COASTAL EQUIP INC                                Phone: 954-931-5316
   5972 HOMELAND RD                                Fax:   561-793-5334
  LAKE WORTH FL 33467                              Vendor:114659       SBE: Y
  Email : COASTALEQUIPINC@AOL.COM
  Cert.Valid From Date: 11/10/2007                Cert.Valid To Date: 11/09/2010

  COASTAL MARINE CONSTRCTN INC                     Phone: 941-485-2101
   625 N TAMIAMI TRL                               Fax:   941-488-0164
  VENICE FL 34285                                  Vendor:100139       SBE: Y
  Email : JIM@COASTALMARINECONSTRUCTION.COM
  Cert.Valid From Date: 03/27/2007                Cert.Valid To Date: 03/26/2010

  COLBY CONSTRCTN ENTERPRISES INC                  Phone: 561-662-5714
   PO BOX 17814                                    Fax:   561-968-1309
  WEST PALM BEACH FL 33461                         Vendor:109534       SBE: Y
  Email : COLBYCONSTRUCTIONINC@YAHOO.COM
  Cert.Valid From Date: 08/25/2007                Cert.Valid To Date: 08/24/2010

  COMPASS CONSTRCTN LLC                            Phone: 863-824-3478
   1450 SW 86TH AVE                                Fax:   863-824-0273
  OKEECHOBEE FL 34974                              Vendor:116150       SBE: Y
  Email : DARRELL@COMPASSCONSTRUCTIONLLC.COM
  Cert.Valid From Date: 03/11/2009                Cert.Valid To Date: 03/11/2012

  COMPLETE SITEWORK SVCS LLC                       Phone: 478-273-9396
   112 E JOHNSON ST                                Fax:   478-273-3443
  DUBLIN GA 31021                                  Vendor:117121       SBE: Y
  Email : STEPHANIE.PHILLIPS@GRAHAMCOMPANIES.US
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   7

  Cert.Valid From Date: 10/23/2009               Cert.Valid To Date: 10/23/2012

  COMPLETE SVCS OF SOUTH FLORIDA INC               Phone: 863-634-4697
   888 US HWY 441 SE                               Fax:   863-467-7479
  OKEECHOBEE FL 34974                              Vendor:102134       SBE: X
  Email : COMPLETESERVICES17@COMCAST.NET
  Cert.Valid From Date: 04/19/2007               Cert.Valid To Date: 04/18/2010

  CONSTRCTN MGMT OF FLORIDA INC                    Phone: 561-488-9907
   20881 RAMITA TRL                                Fax:   561-488-6264
  BOCA RATON FL 33433                              Vendor:107556       SBE: V
  Email : cmflorida@adelphia.net
  Cert.Valid From Date: 06/14/2007               Cert.Valid To Date: 06/13/2010

  CONSTRCTN SLTNS PLUS INC                         Phone: 239-825-7221
   2431 JASPER AVE                                 Fax:   239-936-2491
  FT MYERS FL 33907                                Vendor:113690       SBE: Y
  Email : RERIPP@YAHOO.COM
  Cert.Valid From Date: 05/09/2007               Cert.Valid To Date: 05/08/2010

  CONSTRCTN SPECIALISTS OF                         Phone: 954-648-2969
   16800 ORANGE BLVD                               Fax:
  LOXAHATCHEE FL 33470                             Vendor:114774       SBE: X
  Email : WINTERS954@AOL.COM
  Cert.Valid From Date: 12/05/2007               Cert.Valid To Date: 12/04/2010

  CONSTRCTN TECHLGY INC                            Phone: 561-882-9696
   PO BOX 16576                                    Fax:   561-882-9697
  WEST PALM BEACH FL 33416                         Vendor:100067       SBE: Y
  Email : CONTECH@BELLSOUTH.NET
  Cert.Valid From Date: 05/24/2007               Cert.Valid To Date: 05/23/2010

  CONSTRCTNEER CORP                                Phone: 954-438-0800
   1121 SW 103RD AVE                               Fax:   954-438-0799
  PEMBROKE PINES FL 33025                          Vendor:101154       SBE: X
  Email : CONSTRUCTIONEER@AOL.COM
  Cert.Valid From Date: 08/27/2009               Cert.Valid To Date: 08/27/2012

  CONSTRUCT GRP CORP                               Phone: 305-824-8845
   12101 NW 98TH AVE STE 8                         Fax:   305-824-3224
  HIALEAH GARDENS FL 33018                         Vendor:115392       SBE: V
  Email : GUS@CONSTRUCTGROUPCORP.COM
  Cert.Valid From Date: 07/12/2008               Cert.Valid To Date: 07/11/2011

  CONSTRUCT TWO CONSTRCTN MNGRS INC                Phone: 407-295-9812
   30 S IVEY LN                                    Fax:   407-298-5482
  ORLANDO FL 32811                                 Vendor:100680       SBE: T
  Email : BDLEANDS@CONSTRUCTTWO.COM
  Cert.Valid From Date: 12/15/2006               Cert.Valid To Date: 12/14/2009

  CONTRACT SITE SVCS INC                           Phone: 561-793-4655
   1331 WYNDCLIFF DR                               Fax:   561-753-6947
  WELLINGTON FL 33414                              Vendor:101466       SBE: X
  Email : LTB21958@AOL.COM
  Cert.Valid From Date: 10/11/2006               Cert.Valid To Date: 10/10/2009
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   8

  CORE CONSTRCTN GRP INC                           Phone: 321-229-2179
   1126 S DIVISION AVE STE C                       Fax:   407-428-9584
  ORLANDO FL 32805                                 Vendor:117115       SBE: Y
  Email : CCGIF@YAHOO.COM
  Cert.Valid From Date: 10/22/2009               Cert.Valid To Date: 10/22/2012

  CORELAND CONSTRCTN CORP                          Phone: 305-233-1709
   12301 SW 128TH CT                               Fax:   305-233-1809
  MIAMI FL 33186                                   Vendor:114629       SBE: Y
  Email : CORLANDC@AOL.COM
  Cert.Valid From Date: 11/21/2007               Cert.Valid To Date: 11/20/2010

  COST MGMT INC                                    Phone: 407-293-4168
   5507 ALHAMBRA DR                                Fax:   407-293-0944
  ORLANDO FL 32808                                 Vendor:102417       SBE: U
  Email : GANESH.JIAWON@CMINC.BIZ
  Cert.Valid From Date: 09/24/2009               Cert.Valid To Date: 09/24/2012

  COUNTRY CONSTRCTN LLC                            Phone: 772-408-3394
   4038 SE 27TH ST                                 Fax:   863-467-2592
  OKEECHOBEE FL 34974                              Vendor:115197       SBE: Y
  Email : JEANTREVOR@YAHOO.COM
  Cert.Valid From Date: 05/09/2008               Cert.Valid To Date: 05/08/2011

  CSI TRUCKING INC                                 Phone: 772-260-6961
   7600 SPRINGHAVEN ESTATES                        Fax:
  INDIANTOWN FL 34956                              Vendor:114937       SBE: Y
  Email : TCULBE03@AOL.COM
  Cert.Valid From Date: 02/09/2007               Cert.Valid To Date: 02/08/2011

  CURRENT CONNECTIONS INC                          Phone: 561-863-0010
   1620 HILL AVE                                   Fax:   561-863-5380
  MANGONIA PARK FL 33407                           Vendor:101025       SBE: Y
  Email : DON@CURRENTCONNECTIONS.NET
  Cert.Valid From Date: 03/24/2007               Cert.Valid To Date: 03/23/2010

  CURTIS & ASSOCS INC                              Phone: 321-228-9939
   2212 S CHICKSAW TRL STE 102                     Fax:   407-380-3961
  ORLANDO FL 32825                                 Vendor:111170       SBE: Y
  Email : CONSTRUCT@CFL.RR.COM
  Cert.Valid From Date: 11/08/2007               Cert.Valid To Date: 11/07/2010

  CUSTOM CONTRACTING CORP THE                      Phone: 352-383-3003
   PO BOX 1349                                     Fax:   352-383-7220
  MT DORA FL 32756                                 Vendor:110223       SBE: Y
  Email : JENNIFERR@CUSTOMCONTRACTINGCORP.COM
  Cert.Valid From Date: 08/26/2009               Cert.Valid To Date: 08/26/2012

  D R SWANSON CO                                   Phone: 941-629-8822
   1720 EL JOBEAN RD                               Fax:   941-629-8846
  PRT CHARLOTTE FL 33948                           Vendor:114587       SBE: Y
  Email : SWANSON82@COMCAST.NET
  Cert.Valid From Date: 10/25/2007               Cert.Valid To Date: 10/24/2010

  DA COSTA ENTERPRISES INC                         Phone: 561-370-3530
   9208 NUGENT TRL                                 Fax:   561-828-3397
  WEST PALM BEACH FL 33411                         Vendor:116507       SBE: T
  Email : OADAMS3@GMAIL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   9

  Cert.Valid From Date: 06/11/2009               Cert.Valid To Date: 06/11/2012

  DAWSON GRP LLC                                   Phone: 808-630-9169
   3375 KOAPAKA ST B200                            Fax:   808-536-5530
  HONOLULU HI 96819                                Vendor:113680       SBE: W
  Email : DSMITH@DAWSON8A.COM
  Cert.Valid From Date: 07/03/2007               Cert.Valid To Date: 07/02/2010

  DEERPARK DEV INC                                 Phone: 561-309-4302
   1881 CORSICA DR                                 Fax:   561-791-6990
  WELLINGTON FL 33414                              Vendor:112538       SBE: Y
  Email : JRUSBRIDGE@AOL.COM
  Cert.Valid From Date: 09/28/2009               Cert.Valid To Date: 09/28/2012

  DENSON CONSTRCTN INC                             Phone: 863-709-1001
   PO BOX 3081                                     Fax:   863-709-1071
  PLANT CITY FL 33564                              Vendor:113117       SBE: T
  Email : PETE@DENSON-CONSTRUCTION.COM
  Cert.Valid From Date: 01/11/2007               Cert.Valid To Date: 01/10/2010

  DESIGN & CONSTRCTN SOLUTIONS                     Phone: 954-660-0227
   318 INDIAN TRCE STE 335                         Fax:
  WESTON FL 33326                                  Vendor:113989       SBE: Y
  Email : JPALACINO@DCSOLUTIONS-INC.COM
  Cert.Valid From Date: 05/17/2007               Cert.Valid To Date: 05/16/2010

  DEV COMM GRP OF FLORIDA                          Phone: 305-596-0611
   PO BOX 160178                                   Fax:   305-596-0615
  MIAMI FL 33116                                   Vendor:105285       SBE: Y
  Email : DEVELOPMENTFL@AOL.COM
  Cert.Valid From Date: 01/24/2007               Cert.Valid To Date: 01/23/2010

  DEVLAND SITE DEV INC                             Phone: 561-585-6370
   1302 WINGFIELD ST                               Fax:   561-732-0106
  LAKE WORTH FL 33460                              Vendor:110852       SBE: T
  Email : DEVLAND6370@AOL.COM
  Cert.Valid From Date: 10/28/2006               Cert.Valid To Date: 10/27/2009

  DEVLAND SITE INC                                 Phone: 561-585-6370
   1302 WINGFIELD ST                               Fax:   561-732-0106
  LAKE WORTH FL 33460                              Vendor:116667       SBE: T
  Email : DEVLAND6370@AOL.COM
  Cert.Valid From Date: 10/26/2009               Cert.Valid To Date: 10/26/2012

  DIVERSIFIED PROFESSIONAL SVCS CORP               Phone: 352-588-2811
   27915 JOHNSTON RD                               Fax:
  DADE CITY FL 33523                               Vendor:114134       SBE: X
  Email : SPOLANIS@DPS-CORP.COM
  Cert.Valid From Date: 07/17/2007               Cert.Valid To Date: 07/16/2010

  DORADO SVCS INC                                  Phone: 407-688-0600
   541 N PALMETTO AVE STE 104                      Fax:   407-688-0701
  SANFORD FL 32771                                 Vendor:103992       SBE: V
  Email : info@doradosi.com
  Cert.Valid From Date: 01/11/2007               Cert.Valid To Date: 01/10/2010
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   10

  DOZIER & DOZIER CONSTRCTN INC                    Phone: 305-624-5274
   3932 NW 167TH ST                                Fax:   305-625-1452
  MIAMI GARDENS FL 33054                           Vendor:102278       SBE: T
  Email : WDOZIER@DOZIERANDDOZIER.COM
  Cert.Valid From Date: 01/05/2007               Cert.Valid To Date: 01/04/2010

  DR ROGERS INC                                    Phone: 863-674-5799
   50 N SR 29                                      Fax:   863-674-5798
  FELDA FL 33930                                   Vendor:107355       SBE: Y
  Email : SCOTT.ROGERS@DRROGERSINC.COM
  Cert.Valid From Date: 01/31/2007               Cert.Valid To Date: 01/30/2010

  DRAWDY CONSTRCTN CO INC                          Phone: 561-965-8092
   10201 LANTANA RD                                Fax:   561-965-9201
  LAKE WORTH FL 33449                              Vendor:100134       SBE: Y
  Email : DRAWDYCONST@BELLSOUTH.NET
  Cert.Valid From Date: 10/08/2009               Cert.Valid To Date: 10/08/2012

  E&D CONTRACTING SVCS INC                         Phone: 912-234-5904
   2001 MILLS B LN BLVD                            Fax:   912-233-0888
  SAVANNAH GA 31405                                Vendor:113123       SBE: X
  Email :
  Cert.Valid From Date: 12/28/2006               Cert.Valid To Date: 12/27/2009

  ECOSYSTEM TECHLGYS INC                           Phone: 239-337-5310
   2223 MCGREGOR BLVD                              Fax:   239-337-4494
  FT MYERS FL 33901                                Vendor:114154       SBE: Y
  Email : BJONES@ETIFL.COM
  Cert.Valid From Date: 08/07/2007               Cert.Valid To Date: 08/06/2010

  ELECTRO HYDRAULIC MACHINERY CO INC               Phone: 954-981-0023
   2601 JOHN P LYONS BLVD                          Fax:   954-981-4022
  PEMBROKE PARK FL 33009                           Vendor:105847       SBE: Y
  Email : MHANLEY@EHMCOMPANY.COM
  Cert.Valid From Date: 10/06/2007               Cert.Valid To Date: 10/05/2010

  ENGECON CONSTRCTN INC                            Phone: 321-231-6672
   1800 S OCEAN DR #3106                           Fax:   954-874-6392
  HALLANDALE FL 33009                              Vendor:115751       SBE: Y
  Email : ENGECONCONSTRUCTION@GMAIL.COM
  Cert.Valid From Date: 11/04/2008               Cert.Valid To Date: 11/04/2011

  ENGRG & APPLIED SCIENCE INC                      Phone: 813-899-0707
   13087 TELECOM PKWY N                            Fax:   813-899-0366
  TAMPA FL 33637                                   Vendor:101705       SBE: U
  Email : EAS@EASTAMPA.COM
  Cert.Valid From Date: 09/28/2009               Cert.Valid To Date: 09/28/2012

  ENVIRO TECH SYSTS INC                            Phone: 863-763-3143
   2308 S PARROTT AVE                              Fax:   863-763-1309
  OKEECHOBEE FL 34974                              Vendor:114702       SBE: Y
  Email : ROYBL@ENVIRO-TECH.CC
  Cert.Valid From Date: 11/30/2007               Cert.Valid To Date: 11/29/2010

  ENVIRON LAND DEV INC                             Phone: 772-519-6278
   6381 PETERSON RD                                Fax:   772-462-2208
  FT PIERCE FL 34947                               Vendor:115599       SBE: Y
  Email : ELDINC2004@GMAIL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   11

  Cert.Valid From Date: 04/07/2009               Cert.Valid To Date: 04/07/2012

  EPSEC CORP                                       Phone: 877-564-5036
   PO BOX 953813                                   Fax:   877-564-5036
  LAKE MARY FL 32795                               Vendor:115341       SBE: V
  Email : JSDUREN@EPSEC.ORG
  Cert.Valid From Date: 08/18/2008               Cert.Valid To Date: 08/18/2011

  EXPERT CONSTRCTN MGRS INC                        Phone: 813-335-4765
   815 S KINGS AVE                                 Fax:   813-571-0875
  BRANDON FL 33511                                 Vendor:112268       SBE: Y
  Email : BILL@BROWN.ORG
  Cert.Valid From Date: 10/10/2007               Cert.Valid To Date: 10/09/2010

  FASTRACK MCI                                     Phone: 561-304-7881
   2540 METROCENTRE BLVD STE 4                     Fax:   561-304-7802
  WEST PALM BEACH FL 33407                         Vendor:114627       SBE: V
  Email : SASHA@FASTRACKMCI.COM
  Cert.Valid From Date: 11/05/2008               Cert.Valid To Date: 11/05/2011

  FLAVE A WILLIAMS III DOZER SVC INC              Phone: 727-856-3765
   14717 HAYS RD                                  Fax:   727-856-6298
  SPRING HILL FL 34610                            Vendor:116481       SBE: X
  Email : NWILLIAMS@FLAVEWILLIAMSDOZERSERVICE.COM
  Cert.Valid From Date: 04/27/2009              Cert.Valid To Date: 04/27/2012

  FLEMING EXECUTIVE GRP INC                        Phone: 786-295-0639
   5629 SW 19TH ST                                 Fax:   954-374-7276
  HOLLYWOOD FL 33023                               Vendor:113655       SBE: T
  Email : FLEMINGXGROUP@YAHOO.COM
  Cert.Valid From Date: 03/16/2007               Cert.Valid To Date: 03/15/2010

  FOREST HILL CONSTRCTN CO INC                     Phone: 561-790-2300
   17546 BEE LINE HWY                              Fax:   561-799-5650
  JUPITER FL 33458                                 Vendor:100321       SBE: Y
  Email : FORESTHILL@EARTHLINK.NET
  Cert.Valid From Date: 02/02/2007               Cert.Valid To Date: 02/01/2010

  GA GROUP LTD CO THE                              Phone: 772-463-4530
   906 SE 9TH ST                                   Fax:   772-219-8196
  STUART FL 34994                                  Vendor:114413       SBE: Y
  Email : JSCOOPER@GACONSTRUCTIONGROUP.COM
  Cert.Valid From Date: 10/16/2007               Cert.Valid To Date: 10/15/2010

  GANCEDO TECHLGYS INC                             Phone: 305-265-1984
   3425 NW 73 AVE                                  Fax:   305-289-8283
  MIAMI FL 33122                                   Vendor:110148       SBE: V
  Email : CARLOS@GANCEDOTECH.COM
  Cert.Valid From Date: 05/17/2007               Cert.Valid To Date: 05/16/2010

  GATOR GRADING & EXCAVATING LLC                   Phone: 561-881-5512
   1880W 10TH ST STE 104                           Fax:   561-881-5612
  RIVERIA BEACH FL 33404                           Vendor:109558       SBE: X
  Email : HBC314@YAHOO.COM
  Cert.Valid From Date: 06/30/2009               Cert.Valid To Date: 06/30/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   12

  GBA CONSTRCTN & DEV GRP INC                      Phone: 786-295-4641
   15240 SW 160TH ST                               Fax:   786-242-5446
  MIAMI FL 33187                                   Vendor:114049       SBE: Y
  Email : GBAGROUP@NETZERO.COM
  Cert.Valid From Date: 06/08/2007               Cert.Valid To Date: 06/07/2010

  GE DEV OF SO FLA INC                             Phone: 954-252-8500
   5201 THOROUGHBRED LN                            Fax:   954-252-1259
  SOUTHWEST RANCHES FL 33330                       Vendor:116886       SBE: Y
  Email : GE.DEVELOPMENT@YAHOO.COM
  Cert.Valid From Date: 08/11/2009               Cert.Valid To Date: 08/11/2012

  GENERATION ELECTRICAL SVCS CORP                  Phone: 305-252-7780
   13727 SW 152ND ST STE 320                       Fax:   305-252-9975
  MIAMI FL 33177                                   Vendor:116491       SBE: Y
  Email : GESCO@BELLSOUTH.NET
  Cert.Valid From Date: 05/12/2009               Cert.Valid To Date: 05/12/2012

  GOLD STAR HOMEIMPROVEMENT INC                    Phone: 561-997-1778
   914 CLINT MOORE RD                              Fax:   561-997-1780
  BOCA RATON FL 33487                              Vendor:114941       SBE: Y
  Email : ZMORAG@GMAIL.COM
  Cert.Valid From Date: 02/11/2007               Cert.Valid To Date: 02/12/2011

  GONZALEZ & SONS EQUIP INC                        Phone: 305-822-5455
   PO BOX 170840                                   Fax:   305-822-5454
  HIALEAH FL 33017                                 Vendor:103985       SBE: V
  Email : MAYLIN.G@GONZALEZANDSONS.NET
  Cert.Valid From Date: 09/06/2006               Cert.Valid To Date: 09/05/2009

  GREEN CONSTRCTN TECHLGYS INC                     Phone: 954-563-3379
   2130 NE 15TH TER                                Fax:   954-563-3883
  WILTON MANORS FL 33305                           Vendor:115167       SBE: X
  Email : GREENACRESGC@BELLSOUTH.NET
  Cert.Valid From Date: 05/02/2008               Cert.Valid To Date: 05/01/2011

  GREGORY LENARD WILLIAMS                          Phone: 561-622-1520
   1541 MEADS BAY LN                               Fax:   561-622-1520
  JUPITER FL 33458                                 Vendor:116816       SBE: Y
  Email : GWPC98@ATT.NET
  Cert.Valid From Date: 08/25/2009               Cert.Valid To Date: 08/25/2012

  GREY CONSTRCTN CO OF FLORIDA INC                 Phone: 561-845-2872
   2001 PALM BEACH LAKES BLVD STE 407              Fax:   561-253-0228
  WEST PALM BEACH FL 33409                         Vendor:116703       SBE: T
  Email : MILTONGREY@AOL.COM
  Cert.Valid From Date: 07/02/2009               Cert.Valid To Date: 07/02/2012

  GROUND FORCE EQUIP SVC INC                       Phone: 772-567-2062
   1465 19TH ST SW                                 Fax:
  VERO BEACH FL 32962                              Vendor:114147       SBE: Y
  Email : CSAIL@BELLSOUTH.NET
  Cert.Valid From Date: 06/23/2007               Cert.Valid To Date: 06/22/2010

  GROWING CONCERN TREE & LANDSCAPE                 Phone: 561-644-2912
   4594 WENHART RD                                 Fax:
  LAKE WORTH FL 33463                              Vendor:106012       SBE: Y
  Email : GUTHRIETREE@BELLSOUTH.NET
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   13

  Cert.Valid From Date: 02/16/2007               Cert.Valid To Date: 02/15/2010

  GULF GRP INC                                     Phone: 850-258-3545
   7402 HWY 2302                                   Fax:   850-769-6175
  SOUTHPORT FL 32409                               Vendor:100789       SBE: Y
  Email : SAM@GULFGROUP.COM
  Cert.Valid From Date: 10/30/2008               Cert.Valid To Date: 10/30/2011

  GULF STATES ELECTRIC INC                         Phone: 239-263-7137
   4585 PROGRESS AVE STE 2                         Fax:   239-263-7328
  NAPLES FL 34104                                  Vendor:116881       SBE: Y
  Email : WIERENUT@AOL.COM
  Cert.Valid From Date: 07/30/2009               Cert.Valid To Date: 07/30/2012

  GULFSTREAM RESTORATION & CONSTRCTN               Phone: 866-440-2565
   1809 S POWERLINE RD STE 107                     Fax:   866-440-2566
  DEERFIELD BEACH FL 33442                         Vendor:117104       SBE: Y
  Email : KELLY@GULFSTREAMCONST.COM
  Cert.Valid From Date: 11/02/2009               Cert.Valid To Date: 11/02/2012

  GURRI MATUTE PA                                  Phone: 305-445-5811
   2701 PONCE DE LEON BLVD STE 203                 Fax:
  CORAL GABLES FL 33134                            Vendor:108097       SBE: V
  Email : SHERNANDEZ@GURRIMATUTE.COM
  Cert.Valid From Date: 10/03/2006               Cert.Valid To Date: 10/02/2009

  GUTHOY BUILDERS INC                              Phone: 305-216-4912
   11276 NW 160TH CT                               Fax:   305-974-0284
  MIAMI FL 33196                                   Vendor:116096       SBE: Y
  Email : GUTHOY@BELLSOUTH.NET
  Cert.Valid From Date: 01/27/2009               Cert.Valid To Date: 01/27/2012

  HABER & SONS PLUMBING INC                        Phone: 305-461-8653
   4106 NW 37 AVE                                  Fax:   305-567-9976
  MIAMI FL 33142                                   Vendor:115694       SBE: Y
  Email : HABERANDPLUMBING@BELLSOUTH.NET
  Cert.Valid From Date: 10/28/2008               Cert.Valid To Date: 10/28/2011

  HATCHER CONSTRCTN & DEV INC                      Phone: 561-330-2621
   400 W ATLANTIC AVE STE 2B                       Fax:   561-330-2670
  DELRAY BEACH FL 33444                            Vendor:104610       SBE: T
  Email : HATCHERGC@BELLSOUTH.NET
  Cert.Valid From Date: 06/18/2008               Cert.Valid To Date: 06/17/2011

  HBC ENGRG CO                                     Phone: 305-232-7932
   12918 SW 133RD CT                               Fax:   305-232-7933
  MIAMI FL 33186                                   Vendor:116139       SBE: T
  Email : ACOKER@HBCENGINEERINGCO.COM
  Cert.Valid From Date: 02/24/2009               Cert.Valid To Date: 02/24/2012

  HELLER WEAVER & SHEREMETA INC                    Phone: 561-243-8700
   310 SE 1ST ST STE 4                             Fax:   561-243-8777
  DELRAY BEACH FL 33483                            Vendor:100186       SBE: Y
  Email : WROLLE@HWSCONSULTING.COM
  Cert.Valid From Date: 04/07/2009               Cert.Valid To Date: 04/07/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   14

  HERRINGTON BRADLEY CONSTRCTN INC                 Phone: 305-652-8848
   14825 NW 16 DR                                  Fax:
  MIAMI FL 33167                                   Vendor:102770       SBE: T
  Email :
  Cert.Valid From Date: 10/30/2008               Cert.Valid To Date: 10/30/2011

  HG CONSTRCTN DEV & INVESTMENT INC                Phone: 786-325-9121
   10507 SW 78 ST                                  Fax:
  MIAMI FL 33173                                   Vendor:115364       SBE: Y
  Email : HGCONSTRUCTION@BELLSOUTH.NET
  Cert.Valid From Date: 06/24/2008               Cert.Valid To Date: 06/23/2011

  HI TE INC                                        Phone: 561-996-2003
   PO BOX 136                                      Fax:   561-996-2006
  BELLE GLADE FL 33430                             Vendor:111564       SBE: V
  Email : HITEINC@BELLSOUTH.NET
  Cert.Valid From Date: 04/05/2007               Cert.Valid To Date: 04/04/2010

  HI TECH CONCRETE INC                             Phone: 305-259-5552
   11335 SW 208TH DR                               Fax:   305-259-5553
  MIAMI FL 33189                                   Vendor:114794       SBE: Y
  Email : YRHTC@AOL.COM
  Cert.Valid From Date: 09/22/2009               Cert.Valid To Date: 09/22/2012

  HOMESTEAD CONCRETE & DRAINAGE INC                Phone: 305-248-9649
   PO BOX 1273                                     Fax:   305-248-9650
  HOMESTEAD FL 33090                               Vendor:102158       SBE: V
  Email : ACORDERO@HOMESTEADCONCRETE.COM
  Cert.Valid From Date: 06/16/2009               Cert.Valid To Date: 06/16/2012

  HP CONSULTANTS INC                               Phone: 305-775-4300
   10220 SW 107TH ST                               Fax:   305-596-2857
  MIAMI FL 33176                                   Vendor:108188       SBE: U
  Email : HPCONSULTANTSINC@EARTHLINK.NET
  Cert.Valid From Date: 08/28/2009               Cert.Valid To Date: 08/28/2012

  HUMPHRIES CONSTRCTN CO INC                       Phone: 863-673-1117
   PO BOX 1116                                     Fax:   863-946-0331
  MOORE HAVEN FL 33471                             Vendor:114805       SBE: X
  Email : HUMPHRIES5767@YAHOO.COM
  Cert.Valid From Date: 02/09/2009               Cert.Valid To Date: 02/09/2012

  IGWT CONSTRCTN INC                               Phone: 305-653-3770
   633 NE 167TH ST STE 1101                        Fax:
  NORTH MIAMI BEACH FL 33162                       Vendor:107580       SBE: T
  Email :
  Cert.Valid From Date: 11/10/2007               Cert.Valid To Date: 11/09/2010

  IICON CONTRACTORS CORP                           Phone: 305-245-1700
   123 N KROME AVE STE 206                         Fax:   305-245-7200
  HOMESTEAD FL 33030                               Vendor:110501       SBE: V
  Email : IAN.IGLESIAS@IICONCONTRACTORS.COM
  Cert.Valid From Date: 09/14/2009               Cert.Valid To Date: 09/14/2012

  INLAND CONSTRCTN & EQUIP SV                      Phone: 850-872-2129
   309 E 11TH ST                                   Fax:   850-872-0532
  PANAMA CITY FL 32401                             Vendor:104954       SBE: W
  Email : INLANDEQUIPMENT@HOTMAIL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   15

  Cert.Valid From Date: 02/28/2007               Cert.Valid To Date: 02/27/2010

  INTEGRATED PROJECT SYSTS LLC                     Phone: 305-766-2455
   1008 JEFFERSON AVE STE 102                      Fax:   305-535-6323
  MIAMI BEACH FL 33139                             Vendor:116009       SBE: T
  Email : IPSFLORIDA@GMAIL.COM
  Cert.Valid From Date: 02/26/2009               Cert.Valid To Date: 02/26/2012

  INTEGRATED TELECOMMUNICATION SYSTS               Phone: 813-684-7360
   1971 W LUMSDEN RD STE 328                       Fax:   813-283-0011
  BRANDON FL 33511                                 Vendor:103902       SBE: Y
  Email : DWHITE@ITSINFO.COM
  Cert.Valid From Date: 12/02/2006               Cert.Valid To Date: 12/01/2009

  INTERLAKEN INC                                   Phone: 561-582-4651
   1960 S OCEAN BLVD                               Fax:   954-767-1081
  MANALAPAN FL 33462-6219                          Vendor:107252       SBE: Y
  Email : TKEEN@INTERLAKEN.BZ
  Cert.Valid From Date: 12/07/2006               Cert.Valid To Date: 12/06/2009

  INTRON TECHLGYS INC                              Phone: 904-731-1445
   4859 VICTOR ST                                  Fax:   904-731-1446
  JACKSONVILLE FL 32207                            Vendor:106091       SBE: Y
  Email : JODY@INTRONTECH.COM
  Cert.Valid From Date: 01/05/2009               Cert.Valid To Date: 01/05/2012

  IQ CONSTRCTNS INC                                Phone: 561-683-5535
   1520 LATHAM RD STE 4                            Fax:   561-683-5537
  WEST PALM BEACH FL 33409                         Vendor:112558       SBE: V
  Email : IQCONSTRUCTIONS@BELLSOUTH.NET
  Cert.Valid From Date: 10/16/2009               Cert.Valid To Date: 10/16/2012

  J DUKE CONSTRCTN                                 Phone: 786-397-2485
   18880 NW 57TH AVE UNIT 308                      Fax:
  MIAMI FL 33015                                   Vendor:116852       SBE: T
  Email : JDUKE@JDUKECONSTRUCTION.COM
  Cert.Valid From Date: 10/20/2009               Cert.Valid To Date: 10/20/2012

  J M SNOW CONSTRCTN INC                           Phone: 561-996-5062
   1148 STILLWELL RD                               Fax:   561-996-6665
  BELLE GLADE FL 33430                             Vendor:109717       SBE: Y
  Email : BIZZYBEE73@BELLSOUTH.NET
  Cert.Valid From Date: 12/22/2007               Cert.Valid To Date: 12/21/2010

  J RAWN ENTERPRISES INC                           Phone: 561-478-7445
  6963 WILSON RD                                   Fax:   561-478-8471
  WEST PALM BEACH FL 33413                         Vendor:102416       SBE: Y
  Email :
  Cert.Valid From Date: 05/01/2007               Cert.Valid To Date: 04/30/2010

  JACQUELIN DAVIS ENTERPRISES LLC                  Phone: 863-228-1473
   509 BEATRICE ST                                 Fax:   941-485-0380
  VENICE FL 34285                                  Vendor:115837       SBE: Y
  Email : AJACQUELIN@VERIZON.NET
  Cert.Valid From Date: 12/23/2008               Cert.Valid To Date: 12/23/2011
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   16

  JAMERICA CONCRETE SVCS CORP                      Phone: 561-902-1766
   PO BOX 596                                      Fax:   561-902-1152
  CANAL POINT FL 33438                             Vendor:114735       SBE: T
  Email : STALBION@AOL.COM
  Cert.Valid From Date: 11/27/2007               Cert.Valid To Date: 11/26/2010

  JASMINE CONSTRCTN LLC                            Phone: 561-319-8055
   54 MULBERRY GROVE RD                            Fax:   561-753-7946
  ROYAL PALM ABEACH FL 33411                       Vendor:115312       SBE: Y
  Email : JASCLLC@BELLSOUTH.NET
  Cert.Valid From Date: 06/10/2008               Cert.Valid To Date: 06/09/2011

  JE CLEARING & DEVELOPING                         Phone: 863-634-6867
   8000 NW 240TH ST                                Fax:   863-467-7082
  OKEECHOBEE FL 34972                              Vendor:111117       SBE: Y
  Email : JEDEVELOPING@HOTMAIL.COM
  Cert.Valid From Date: 06/19/2007               Cert.Valid To Date: 06/18/2010

  JHC CONTRACTORS INC                              Phone: 305-825-0834
   6187 NW 167TH ST STE H-24                       Fax:   305-825-0212
  MIAMI FL 33016                                   Vendor:115583       SBE: Y
  Email : JHCCONTRACTORS@BELLSOUTH.NET
  Cert.Valid From Date: 11/18/2008               Cert.Valid To Date: 11/18/2011

  JIJ CONSTRCTN CORP                               Phone: 561-572-1525
   11925 STURBRIDGE LN                             Fax:   561-594-4199
  WELLINGTON FL 33414                              Vendor:110000       SBE: Y
  Email : KATYCASSIANI@HOTMAIL.COM
  Cert.Valid From Date: 09/19/2008               Cert.Valid To Date: 09/18/2011

  JJ SOSA & ASSOCS INC                             Phone: 813-888-6525
   6911 PISTOL RANGE RD STE 101A                   Fax:   813-881-1285
  TAMPA FL 33635                                   Vendor:101506       SBE: V
  Email : J.J.SOSA@JJSOSA.COM
  Cert.Valid From Date: 07/15/2009               Cert.Valid To Date: 07/15/2012

  JM FRAMING INC                                   Phone: 727-514-5000
   PO BOX 171                                      Fax:   727-943-7573
  ELFERS FL 34680                                  Vendor:116120       SBE: Y
  Email : JMFRAMING2@VERIZON.NET
  Cert.Valid From Date: 02/09/2009               Cert.Valid To Date: 02/09/2012

  JM JADU CORP                                     Phone: 561-337-4788
   7726 HUFFY CIR                                  Fax:   561-689-5307
  LAKE WORTH FL 33467                              Vendor:104981       SBE: U
  Email : CONSULTANTS@JMJADU.COM
  Cert.Valid From Date: 03/27/2007               Cert.Valid To Date: 03/26/2010

  JONES CO OF SOUTH FLORIDA INC THE                Phone: 954-583-7300
   3784 NW 16TH ST                                 Fax:   954-730-9000
  LAUDERHILL FL 33311                              Vendor:103851       SBE: T
  Email : LANSINGJROCK@AOL.COM
  Cert.Valid From Date: 09/15/2006               Cert.Valid To Date: 09/14/2009

  JORDAN & ASSOCS CONSULTING INC                   Phone: 407-226-8840
   5401 S KIRKMAN RD STE 310                       Fax:   407-248-8124
  ORLANDO FL 32819                                 Vendor:113208       SBE: Y
  Email : TOMMYJORDAN@JORDANCOMPANIES.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   17

  Cert.Valid From Date: 02/21/2007               Cert.Valid To Date: 02/20/2010

  JORDAN DEV & CONSTRCTN LLC                       Phone: 407-226-8840
   4307 VINELAND RD STE H12                        Fax:   407-248-8124
  ORLANDO FL 32811                                 Vendor:115845       SBE: Y
  Email : DANIELJORDAN@JORDANCOMPANIES.COM
  Cert.Valid From Date: 12/23/2008               Cert.Valid To Date: 12/23/2011

  JOSEPH L COLE INC                                Phone: 305-778-2282
   13040 SW 80TH ST                                Fax:   305-385-7240
  MIAMI FL 33183                                   Vendor:112182       SBE: Y
  Email : JLCOLEINC@BELLSOUTH.NET
  Cert.Valid From Date: 01/18/2007               Cert.Valid To Date: 01/17/2010

  JP MURPHY INC                                    Phone: 239-415-4001
   16751 OLD US 41                                 Fax:   239-432-2654
  FT MYERS FL 33912                                Vendor:108954       SBE: Y
  Email : JIM@JPMURPHYINC.COM
  Cert.Valid From Date: 12/08/2008               Cert.Valid To Date: 12/08/2011

  KAILAS CORP                                      Phone: 305-722-0099
   3450 W 84TH ST STE 202-9                        Fax:   305-722-0299
  HIALEAH FL 33018                                 Vendor:116845       SBE: V
  Email : JPAZ@KAILASCONTRACTORS.COM
  Cert.Valid From Date: 07/30/2009               Cert.Valid To Date: 07/30/2012

  KBJ DEV SVCS INC                                 Phone: 941-575-4894
   1105 L TAYLOR RD                                Fax:   941-639-4597
  PUNTA GORDA FL 33950                             Vendor:113408       SBE: Y
  Email : GPOWELL1025@EARTHLINK.NET
  Cert.Valid From Date: 02/06/2007               Cert.Valid To Date: 02/05/2010

  KEARNS CONSTRCTN CO                              Phone: 305-975-8878
   4101 BRAGANZA AVE                               Fax:   305-461-1892
  MIAMI FL 33133                                   Vendor:115843       SBE: Y
  Email : TROPICALBROCK@AOL.COM
  Cert.Valid From Date: 11/10/2008               Cert.Valid To Date: 11/10/2011

  KIRCHMAN CONSTRCTN CO                            Phone: 772-283-4256
   2597 SE DELMAR ST                               Fax:   772-283-1570
  STUART FL 34997                                  Vendor:105326       SBE: Y
  Email : INFO@KIRCHMANSONSTRUCTION.COM
  Cert.Valid From Date: 04/26/2007               Cert.Valid To Date: 04/25/2010

  KST CONSTRCTN INC                                Phone: 863-634-4526
   3283 NW 32ND AVE                                Fax:   863-763-3088
  OKEECHOBEE FL 34972                              Vendor:114229       SBE: Y
  Email : KST@EMBARQMAIL.COM
  Cert.Valid From Date: 09/26/2007               Cert.Valid To Date: 09/25/2010

  LAMBERT BROS INC                                 Phone: 954-491-9380
   823 NW 57TH ST                                  Fax:   954-491-9425
  FT LAUDERDALE FL 33309                           Vendor:110218       SBE: Y
  Email : GL@LAMBERTBROS.COM
  Cert.Valid From Date: 10/06/2009               Cert.Valid To Date: 10/06/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   18

  LANDMARK UNDERGROUND INC                         Phone: 863-673-5821
   PO BOX 594                                      Fax:   863-675-2336
  LA BELLE FL 33975                                Vendor:114359       SBE: Y
  Email : LANDMARKUNDERGROUND@SPRINTPCS.COM
  Cert.Valid From Date: 09/13/2007               Cert.Valid To Date: 09/12/2010

  LEBOLO CONSTRCTN MGMT INC                        Phone: 561-742-7644
   2100 CORPORATE DR                               Fax:   561-742-7636
  BOYNTON BEACH FL 33426                           Vendor:114225       SBE: Y
  Email : TLEE@LEBOLO.COM
  Cert.Valid From Date: 08/21/2007               Cert.Valid To Date: 08/20/2010

  LJ CLARK CONSTRCTN INC                           Phone: 863-946-2438
   335 COUNTY RD 721 LOOP                          Fax:   863-946-2439
  MOORE HAVEN FL 33471                             Vendor:102279       SBE: Y
  Email : LJCLARKCONSTINC@AOL.COM
  Cert.Valid From Date: 07/30/2009               Cert.Valid To Date: 07/30/2012

  LOVELAND ELECTRIC INC                            Phone: 561-882-0401
   1368 N KILLIAN DR                               Fax:   561-882-0555
  LAKE PARK FL 33403                               Vendor:107234       SBE: Y
  Email : RLOVELAND@LOVELANDLEC.COM
  Cert.Valid From Date: 04/09/2009               Cert.Valid To Date: 04/09/2012

  LOVIN CONSTRCTN INC                              Phone: 941-755-4312
   6204 33RD ST E                                  Fax:   941-758-7184
  BRADENTON FL 34203                               Vendor:114786       SBE: Y
  Email : LOVIN-CONSTRUCTION@VERIZON.NET
  Cert.Valid From Date: 12/08/2007               Cert.Valid To Date: 12/07/2010

  LUNACON ENGRG GRP CORP                           Phone: 786-293-0035
   16501 SW 77 AVE                                 Fax:   786-293-0333
  PALMETTO BAY FL 33157                            Vendor:115419       SBE: Y
  Email : LUNACON@BELLSOUTH.NET
  Cert.Valid From Date: 07/11/2008               Cert.Valid To Date: 07/10/2011

  MAC CONSTRCTN INC                                Phone: 305-598-4317
   9500 NW 12TH ST BAY 1B                          Fax:   305-599-9626
  MIAMI FL 33172                                   Vendor:109297       SBE: X
  Email : KELI@MACCONSTRUCTION.NET
  Cert.Valid From Date: 07/25/2008               Cert.Valid To Date: 07/24/2011

  MAG CONSTRCUCTION INC                            Phone: 305-218-9835
   7812 SW 34TH TER                                Fax:   305-263-9369
  MIAMI FL 33155                                   Vendor:112624       SBE: V
  Email : MAGCON@BELLSOUTH.NET
  Cert.Valid From Date: 11/04/2006               Cert.Valid To Date: 11/03/2009

  MAINSTREAM CONSTRCTN CORP                        Phone: 863-983-3457
   PO BOX 1060                                     Fax:   863-983-1112
  CLEWISTON FL 33440                               Vendor:113610       SBE: V
  Email : MAINSTREAMCONSTRUCTION@EARTHLINK.NET
  Cert.Valid From Date: 06/08/2007               Cert.Valid To Date: 06/07/2010

  MAKO BUILDERS LLC                                Phone: 561-804-1226
   PO BOX 210908                                   Fax:
  ROYAL PALM BEACH FL 33421                        Vendor:113290       SBE: U
  Email : SAL@MAKOBUILDERS.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   19

  Cert.Valid From Date: 03/28/2007               Cert.Valid To Date: 03/27/2010

  MANCIL & CO INC                                  Phone: 772-260-0735
   3182 BROOK ST                                   Fax:   772-219-9932
  STUART FL 34997                                  Vendor:112710       SBE: Y
  Email : MANCILD@BELLSOUTH.NET
  Cert.Valid From Date: 03/13/2007               Cert.Valid To Date: 03/12/2010

  MARK W BRANDEL INC                               Phone: 863-763-6796
   2525 NE 131ST LN                                Fax:   863-763-9154
  OKEECHOBEE FL 34972                              Vendor:115907       SBE: Y
  Email : MBRANDEL@STRATO.NET
  Cert.Valid From Date: 02/10/2009               Cert.Valid To Date: 02/10/2012

  MATERIAL HANDLING SYSTS INC                      Phone: 954-921-1171
   720 SW 4TH CT                                   Fax:   954-921-7117
  DANIA FL 33004                                   Vendor:101653       SBE: V
  Email : RON@MHSCRANE.COM
  Cert.Valid From Date: 06/28/2007               Cert.Valid To Date: 06/27/2010

  MAXON GROUPE LLC                                 Phone: 305-710-8666
   4218 NE 2ND AVE 2ND FL                          Fax:   305-868-7887
  MIAMI FL 33137                                   Vendor:115638       SBE: Y
  Email : WILLIAM@MAXONGROUPE.COM
  Cert.Valid From Date: 09/26/2008               Cert.Valid To Date: 09/25/2011

  MB BROWN CONSTRCTN CO INC                        Phone: 561-835-9136
   2708 N AUSTRALIAN AVE STE 6                     Fax:   561-835-4816
  WEST PALM BEACH FL 33407                         Vendor:108409       SBE: T
  Email :
  Cert.Valid From Date: 01/09/2007               Cert.Valid To Date: 01/08/2010

  MEF CONSTRCTN INC                                Phone: 305-461-0603
   782 NW 42ND AVE STE 640                         Fax:   305-461-0660
  MIAMI FL 33126                                   Vendor:115830       SBE: V
  Email : MEFCONSTRUCTION@ATT.NET
  Cert.Valid From Date: 11/19/2008               Cert.Valid To Date: 11/19/2011

  MERKURY CORP                                     Phone: 305-758-9888
   7300 BISCAYNE BLVD STE 204                      Fax:   305-758-0802
  MIAMI FL 33138                                   Vendor:110270       SBE: V
  Email : RUBEN@MERKURYDEVELOPMENT.COM
  Cert.Valid From Date: 01/10/2007               Cert.Valid To Date: 01/09/2010

  MGI MORGAN GENERAL MECHANICAL GRP                Phone: 954-360-9803
   1128 S POWERLINE RD                             Fax:
  DEERFIELD BEACH FL 33442                         Vendor:102007       SBE: Y
  Email : DMORGAN@MGI-MORGAN.COM
  Cert.Valid From Date: 03/07/2008               Cert.Valid To Date: 03/07/2011

  MILIAN SWAIN & ASSOCS INC                        Phone: 305-441-0123
   2025 SW 32ND AVE                                Fax:   305-441-0688
  MIAMI FL 33145                                   Vendor:100672       SBE: V
  Email : AMILIAN@MILIANSWAIN.COM
  Cert.Valid From Date: 06/12/2009               Cert.Valid To Date: 06/12/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   20

  MITCHELL VAUGHN CUSTOM HOMES INC                 Phone: 772-631-0051
   1535 CYPRESS DR #2                              Fax:   561-747-9800
  JUPITER FL 33469                                 Vendor:116133       SBE: Y
  Email : MVCUSTOMHOMES@COMCAST.NET
  Cert.Valid From Date: 05/08/2009               Cert.Valid To Date: 05/08/2012

  MITIGATING CIRCUMSTANCES INC                     Phone: 954-923-4300
   2070C TIGERTAIL BLVD                            Fax:   954-923-3988
  DANIA BEACH FL 33004                             Vendor:106075       SBE: Y
  Email : MITIGATING@BELLSOUTH.NET
  Cert.Valid From Date: 05/16/2007               Cert.Valid To Date: 05/16/2010

  MJ WHITTEN CONTRACTORS INC                       Phone: 561-662-3201
   3562 OLD LIGHTHOUSE CIR                         Fax:   561-795-9282
  WELLINGTON FL 33414                              Vendor:115039       SBE: Y
  Email : RUCKUS0404@YAHOO.COM
  Cert.Valid From Date: 09/08/2008               Cert.Valid To Date: 09/07/2011

  MORAN GENERAL CONTRACTOR INC                     Phone: 786-234-0400
   15221 SW 109 AVE                                Fax:   305-252-7681
  MIAMI FL 33157-1304                              Vendor:115380       SBE: Y
  Email : IJMORAN@AOL.COM
  Cert.Valid From Date: 07/03/2008               Cert.Valid To Date: 07/02/2011

  MR CRICKET INC                                   Phone: 305-251-2900
   16115 SW 117 AVE STE A16                        Fax:   305-238-9095
  MIAMI FL 33177                                   Vendor:115649       SBE: Y
  Email : DEZIR@BELLSOUTH.NET
  Cert.Valid From Date: 12/11/2008               Cert.Valid To Date: 12/11/2011

  MTW SVCS INC                                     Phone: 863-673-8864
   13261 ROLLING GREEN RD                          Fax:   561-625-1781
  NORTH PALM BEACH FL 33408                        Vendor:112671       SBE: Y
  Email : MTWSERVICES@AOL.COM
  Cert.Valid From Date: 03/10/2007               Cert.Valid To Date: 03/09/2010

  MUCHATI ENGRG CONTRACTORS INC                    Phone: 754-214-0286
   6441 NW 58TH TER                                Fax:   954-346-8979
  PARKLAND FL 33067                                Vendor:115212       SBE: V
  Email : MUCHATIENG@BELLSOUTH.NET
  Cert.Valid From Date: 05/20/2008               Cert.Valid To Date: 05/19/2011

  MUZZIN BROTHERS INC                              Phone: 772-334-9506
   3552 NE CANDICE AVE                             Fax:   772-334-9509
  JENSEN BEACH FL 34957                            Vendor:116016       SBE: Y
  Email : MBI79@BELLSOUTH.NET
  Cert.Valid From Date: 02/20/2009               Cert.Valid To Date: 02/20/2012

  MY FRIEND CONSTRCTN INC                          Phone: 305-461-8653
   4106 NW 37 AVE                                  Fax:   305-567-9976
  MIAMI FL 33142                                   Vendor:115695       SBE: Y
  Email : MYFRIENDCONST.2004@BELLSOUTH.NET
  Cert.Valid From Date: 10/28/2008               Cert.Valid To Date: 10/28/2011

  NAC CONSTRCTN INC                                Phone: 305-412-2275
   9065 SW 87TH AVE STE 112                        Fax:   305-412-2278
  MIAMI FL 33176                                   Vendor:114114       SBE: Y
  Email : NESTORCASTELLON@NACCONST.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   21

  Cert.Valid From Date: 06/08/2007               Cert.Valid To Date: 06/07/2010

  NATIONAL EROSION CONTROL INC                     Phone: 863-669-9631
   3010 WATERFIELD CIR                             Fax:   863-669-9632
  LAKELAND FL 33803                                Vendor:109719       SBE: Y
  Email : LBARDEN55@MSN.COM
  Cert.Valid From Date: 01/09/2009               Cert.Valid To Date: 01/09/2012

  NATIVE POWER INC                                 Phone: 772-785-9795
   769 SW MONSOON RD                               Fax:   772-343-1133
  PRT ST LUCIE FL 34953                            Vendor:112210       SBE: Y
  Email : NATIVEPOWERINC@YAHOO.COM
  Cert.Valid From Date: 12/02/2006               Cert.Valid To Date: 12/01/2009

  NATIVE TECHLGYS INC                              Phone: 954-596-2411
   814 S MILITARY TRL                              Fax:   954-480-6249
  DEERFIELD BEACH FL 33442                         Vendor:101929       SBE: Y
  Email : RMILLER@WETLANDSBANK.COM
  Cert.Valid From Date: 02/08/2007               Cert.Valid To Date: 02/07/2010

  NSQUARE INC                                      Phone: 239-514-1173
   PO BOX 113040                                   Fax:   239-514-4161
  NAPLES FL 34108                                  Vendor:116984       SBE: Y
  Email : SSTANDRIFF@NSQUAREINC.COM
  Cert.Valid From Date: 09/30/2009               Cert.Valid To Date: 09/30/2012

  NU TECH GRP INC                                  Phone: 772-770-9589
   2120 58TH AVE STE 138                           Fax:   772-794-4582
  VERO BEACH FL 32966                              Vendor:113393       SBE: Y
  Email : LINDEL_WILLIAMS@HOTMAIL.COM
  Cert.Valid From Date: 01/27/2007               Cert.Valid To Date: 01/26/2010

  NYC BUILDERS INC                                 Phone: 561-283-3333
   2090 PALM BEACH LAKES BLVD                      Fax:   561-656-9744
  WEST PALM BEACH FL 33409                         Vendor:115284       SBE: T
  Email : ERROL@NYCBUILDERSCORP.COM
  Cert.Valid From Date: 11/25/2008               Cert.Valid To Date: 11/05/2011

  OAC ACTION CONSTRCTN CORP                        Phone: 305-256-6655
   12540 SW 130TH ST STE 3                         Fax:   305-255-1004
  MIAMI FL 33186                                   Vendor:114041       SBE: V
  Email : OZZIE@OACCONSTRUCTION.COM
  Cert.Valid From Date: 08/25/2007               Cert.Valid To Date: 08/24/2010

  OCEAN GATE GENERAL CONTRACTORS INC               Phone: 772-283-6744
   2854 SE FEDERAL HWY                             Fax:   772-283-1538
  STUART FL 34994                                  Vendor:103755       SBE: Y
  Email : MARK@OCEANGATEGC.COM
  Cert.Valid From Date: 11/03/2006               Cert.Valid To Date: 11/02/2009

  OGDEN BROTHERS CONSTRCTN INC                     Phone: 239-592-9960
   1141 SUN CENTURY BLVD                           Fax:   239-592-7549
  NAPLES FL 34110                                  Vendor:115978       SBE: Y
  Email : ROB@OGDENBROTHERS.COM
  Cert.Valid From Date: 12/22/2008               Cert.Valid To Date: 12/22/2011
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   22

  ONEL ASSOCS LLC                                  Phone: 954-665-3877
   3999 NW 36TH ST                                 Fax:   954-714-3316
  LAUDERDALE LAKES FL 33309                        Vendor:113384       SBE: T
  Email : EMOKWOR@YAHOO.COM
  Cert.Valid From Date: 02/24/2007               Cert.Valid To Date: 02/23/2010

  OPTIMUM SVCS INC                                 Phone: 863-467-2572
   208 N PARROTT AVE                               Fax:   863-467-8067
  OKEECHOBEE FL 34972                              Vendor:103595       SBE: Y
  Email : REVANS@OPTSVC.COM
  Cert.Valid From Date: 03/13/2007               Cert.Valid To Date: 03/12/2010

  OVERLAND CONSTRCTN CO INC                        Phone: 561-683-3210
   1360 W 53RD ST                                  Fax:   561-683-3219
  WEST PALM BEACH FL 33407                         Vendor:104741       SBE: Y
  Email : OVERLANDCONST@AOL.COM
  Cert.Valid From Date: 03/14/2007               Cert.Valid To Date: 03/13/2010

  OVERNIGHT SUCCESS CONSTRCTN INC                  Phone: 305-696-6655
   PO BOX 420157                                   Fax:
  MIAMI FL 33142                                   Vendor:110745       SBE: T
  Email : SGIL202433@AOL.COM
  Cert.Valid From Date: 11/01/2006               Cert.Valid To Date: 10/31/2009

  PAC COMM INC                                     Phone: 305-303-4479
   8301 SW 41 TER                                  Fax:   305-357-7978
  MIAMI FL 33155                                   Vendor:115733       SBE: Y
  Email : PACCOMMINC@BELLSOUTH.NET
  Cert.Valid From Date: 11/12/2008               Cert.Valid To Date: 11/12/2011

  PACECON GENERAL CONTRACTORS INC                  Phone: 561-827-7223
   129 TURNBERRY DR                                Fax:   561-304-1185
  ATLANTIS FL 33462                                Vendor:116995       SBE: Y
  Email : CONPACEINC@AOL.COM
  Cert.Valid From Date: 09/21/2009               Cert.Valid To Date: 09/21/2012

  PALM ENGRG GRP INC                               Phone: 305-378-8594
   12491 SW 134TH CT UNIT 20                       Fax:
  MIAMI FL 33186                                   Vendor:105440       SBE: T
  Email : CROLLE@PALMENGINEERING.COM
  Cert.Valid From Date: 01/11/2007               Cert.Valid To Date: 01/10/2010

  PAPPAS CONSTRCTN INC                             Phone: 305-496-7443
   10661 N KENDALL DR                              Fax:   305-412-9545
  MIAMI FL 33176                                   Vendor:114785       SBE: Y
  Email : BUILTBYPAPPAS@BELLSOUTH.NET
  Cert.Valid From Date: 10/06/2007               Cert.Valid To Date: 10/05/2010

  PATE CONSTRCTN CO INC                            Phone: 772-288-1600
   4355 SE COMMERCE AVE                            Fax:   772-287-1748
  STUART FL 34997                                  Vendor:115916       SBE: X
  Email : PATECONSTRUCTION@BELLSOUTH.NET
  Cert.Valid From Date: 12/05/2008               Cert.Valid To Date: 12/05/2011

  PHOENIX HAYES INC                                Phone: 561-718-9555
   8100 BELVEDERE RD UNIT 2                        Fax:   561-791-3157
  WEST PALM BEACH FL 33411                         Vendor:100923       SBE: Y
  Email : DANHAYES@PHOENIXHAYES.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   23

  Cert.Valid From Date: 10/14/2009               Cert.Valid To Date: 10/14/2012

  PRECISION ENGRG LLC                              Phone: 561-795-1771
   83 WESTBURY CLOSE                               Fax:   561-795-9980
  WELLINGTON FL 33414                              Vendor:111974       SBE: Y
  Email : PRECENG@BELLSOUTH.NET
  Cert.Valid From Date: 11/04/2006               Cert.Valid To Date: 11/03/2009

  PRIMARY CONSTRCTN INC                            Phone: 786-348-1237
   1250 NW 79TH ST STE 204                         Fax:
  MIAMI FL 33147                                   Vendor:115462       SBE: T
  Email : AMOSS@PRIMARYCONSTRUCTIONINC.COM
  Cert.Valid From Date: 01/06/2009               Cert.Valid To Date: 01/06/2012

  PROLINE GENERAL CONTRACTOR                       Phone: 954-748-3833
   10501 NW 50TH ST                                Fax:
  SUNRISE FL 33351                                 Vendor:114140       SBE: V
  Email : CSUITO@PROLINESHUTTERS.COM
  Cert.Valid From Date: 06/12/2007               Cert.Valid To Date: 06/11/2010

  PSA CONSTRUCTORS INC                             Phone: 407-898-9119
   1516 E HILLCREST ST STE 310                     Fax:   407-898-9077
  ORLANDO FL 32803                                 Vendor:102732       SBE: T
  Email :
  Cert.Valid From Date: 05/05/2007               Cert.Valid To Date: 05/04/2010

  PULL PANS LLC                                    Phone: 303-710-2099
   48 CHARLOU CIR                                  Fax:   303-969-0747
  ENGLEWOOD CO 80111                               Vendor:110288       SBE: Y
  Email : PULLPANSLLC@YAHOO.COM
  Cert.Valid From Date: 02/23/2009               Cert.Valid To Date: 02/23/2012

  R CATALA TRACTOR & TRUCK WORK LLC                Phone: 863-673-1873
   2050 MURRAY RD                                  Fax:   863-675-5836
  LA BELLE FL 33935                                Vendor:112693       SBE: V
  Email : CATALA0824@EARTHLINK.NET
  Cert.Valid From Date: 09/18/2009               Cert.Valid To Date: 09/15/2012

  RALPH WHITE CO THE                               Phone: 863-287-1864
   PO BOX 827                                      Fax:
  WAVERLY FL 33877                                 Vendor:113281       SBE: Y
  Email : BRADRWC@AOL.COM
  Cert.Valid From Date: 05/19/2007               Cert.Valid To Date: 05/18/2010

  RAM TECH CONSTRCTN INC                           Phone: 305-259-7853
   15802 SW 200TH ST                               Fax:   305-259-7856
  MIAMI FL 33187                                   Vendor:116110       SBE: X
  Email : LSORIA@RAMTECHCONSTRUCTION.COM
  Cert.Valid From Date: 01/29/2009               Cert.Valid To Date: 01/29/2012

  RCI ELECTRIC INC                                 Phone: 561-747-8150
   15429 86TH WAY                                  Fax:   561-747-6052
  PALM BEACH GARDENS FL 33418                      Vendor:116787       SBE: Y
  Email : RCIELECTRIC@COMCAST.NET
  Cert.Valid From Date: 09/11/2009               Cert.Valid To Date: 09/11/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   24

  RENLISKRIS CORP                                  Phone: 954-791-6377
   3686 NW 16TH ST                                 Fax:
  LAUDERHILL FL 33311                              Vendor:114171       SBE: X
  Email : RENLISKRIS@AOL.COM
  Cert.Valid From Date: 07/10/2007               Cert.Valid To Date: 07/09/2010

  RICK DEVELOPER INC                               Phone: 786-285-8685
   4016 SW 132ND AVE                               Fax:   954-693-7810
  DAVIE FL 33330                                   Vendor:116662       SBE: V
  Email : RICKDEVELOPER@BELLSOUTH.NET
  Cert.Valid From Date: 07/24/2009               Cert.Valid To Date: 07/24/2012

  RIDGDILL & SON INC                               Phone: 863-983-3136
   PO BOX 447                                      Fax:   863-983-9642
  CLEWISTON FL 33440                               Vendor:103468       SBE: Y
  Email : RIDGDILLINC@RIDGDILLCONSTRUCTION.COM
  Cert.Valid From Date: 06/05/2007               Cert.Valid To Date: 06/04/2010

  RJR CONSTRCTN INC                                Phone: 305-244-1837
   7025 SW 19TH TER                                Fax:   305-267-1899
  MIAMI FL 33155                                   Vendor:100197       SBE: V
  Email : RJRCONST@BELLSOUTH.NET
  Cert.Valid From Date: 11/17/2008               Cert.Valid To Date: 11/17/2011

  ROBLING ARCHITECTURE CONSTRCTN                   Phone: 561-649-6705
   4889 LAKE WORTH RD STE 103                      Fax:   561-649-6748
  GREENACRES FL 33463                              Vendor:113232       SBE: Y
  Email : DR@ROBLING.COM
  Cert.Valid From Date: 01/27/2007               Cert.Valid To Date: 01/26/2010

  ROBMAR WATERPROOFING INC                         Phone: 954-410-0478
   1331 S DIXIE HWY STE 9B                         Fax:   954-784-5093
  POMPANO BEACH FL 33060                           Vendor:110280       SBE: Y
  Email : SALES@ROBMARWATERPROOFING.NET
  Cert.Valid From Date: 02/06/2007               Cert.Valid To Date: 02/05/2011

  ROCK ENTERPRISES INC                             Phone: 863-612-0011
   180 N BRIDGE ST STE B                           Fax:   863-612-0014
  LABELLE FL 33935                                 Vendor:117068       SBE: Y
  Email : ROCK@ROCKHENDRY.COM
  Cert.Valid From Date: 10/20/2009               Cert.Valid To Date: 10/20/2012

  RONALD A BEECROFT INC                            Phone: 239-344-6559
   40811 SUZAN DR                                  Fax:   239-731-7661
  PUNTA GORDA FL 33982                             Vendor:115793       SBE: Y
  Email : RABEECROFTCGC@AOL.COM
  Cert.Valid From Date: 11/12/2008               Cert.Valid To Date: 11/12/2011

  ROSSO PAVING & DRAINAGE INC                      Phone: 561-688-0288
   350 MARTIN LN                                   Fax:   561-688-0118
  WEST PALM BEACH FL 33413-1610                    Vendor:101244       SBE: Y
  Email : ROSSOPAVING@AOL.COM
  Cert.Valid From Date: 03/08/2007               Cert.Valid To Date: 03/07/2010

  RS CONSTRCTN OF SOUTHWEST FLORIDA                Phone: 941-628-6407
   7173 SW CR 769                                  Fax:   941-235-3624
  ARCADIA FL 34269                                 Vendor:115949       SBE: Y
  Email : FRAN-RAY@COMCAST.NET
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   25

  Cert.Valid From Date: 01/06/2009               Cert.Valid To Date: 01/06/2012

  S GROUP INC                                      Phone: 561-688-2295
   1470 N CONGRESS AVE STE 119                     Fax:   561-688-2298
  WEST PALM BEACH FL 33409                         Vendor:114695       SBE: V
  Email : MSANCHEZ@SGROUPINC.NET
  Cert.Valid From Date: 11/09/2007               Cert.Valid To Date: 11/08/2010

  SA CONSULTANTS LLC                               Phone: 305-857-9220
   2150 CORAL WAY STE 7B                           Fax:   305-857-9221
  MIAMI FL 33145                                   Vendor:112483       SBE: X
  Email : SACONSULTANTS@BELLSOUTH.NET
  Cert.Valid From Date: 10/24/2006               Cert.Valid To Date: 10/23/2009

  SAFETY & EQUIP OPERATOR CERTIFICATION            Phone: 239-437-3234
   21301 S TAMIAMI TRL STE 320 PMB 1               Fax:   239-437-0515
  ESTERO FL 33926                                  Vendor:113829       SBE: X
  Email : CONNIE.SAFETYSCHOOL@EARTHLINK.NET
  Cert.Valid From Date: 06/20/2007               Cert.Valid To Date: 06/19/2010

  SEA DIVERSIFIED INC                              Phone: 561-243-4920
   1200 NW 17TH AVE STE 3                          Fax:   561-243-4957
  DELRAY BEACH FL 33445                            Vendor:108725       SBE: Y
  Email : MDONOVAN@SEADIVERSIFIED.COM
  Cert.Valid From Date: 12/23/2006               Cert.Valid To Date: 12/22/2009

  SEA WATCH CONSTRCTN INC                          Phone: 239-595-4016
   1415 PANTHER LN STE 429                         Fax:
  NAPLES FL 34110                                  Vendor:114069       SBE: Y
  Email : HWBSEAWATCH@YAHOO.COM
  Cert.Valid From Date: 12/15/2007               Cert.Valid To Date: 12/14/2010

  SEACOAST CONSTRCTN INC                           Phone: 786-888-8400
   169 E FLAGLER ST STE 1123                       Fax:   305-675-6323
  MAMI FL 33131                                    Vendor:116350       SBE: V
  Email : GEORGE.ABADIE@SEACOASTCONSTRUCTION.NET
  Cert.Valid From Date: 04/06/2009               Cert.Valid To Date: 04/06/2012

  SEACOAST INC                                     Phone: 813-925-3555
   301 DOUGLAS ROAD E                              Fax:   813-925-3553
  OLDSMAR FL 34677                                 Vendor:115981       SBE: Y
  Email : STEVE@SEACOASTINC.NET
  Cert.Valid From Date: 12/30/2008               Cert.Valid To Date: 12/30/2011

  SEALTEC CONSTRCTN GRP                            Phone: 305-558-7174
   6157 NW 167TH ST STE F15                        Fax:   305-364-4338
  MIAMI FL 33015-4356                              Vendor:111048       SBE: Y
  Email : JCPORTAJR@MINDSPRING.BIZ
  Cert.Valid From Date: 10/26/2007               Cert.Valid To Date: 10/25/2010

  SEMINOLE DESIGN BUILD INC                        Phone: 863-763-9888
   PO BOX 2567                                     Fax:   863-467-0610
  OKEECHOBEE FL 34973                              Vendor:104714       SBE: W
  Email : NUNEZD3@EARTHLINK.NET
  Cert.Valid From Date: 01/31/2007               Cert.Valid To Date: 01/30/2011
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   26

  SFM SVCS INC                                     Phone: 305-818-2424
   9700 NW 79TH AVE                                Fax:   305-818-3510
  MIAMI FL 33016                                   Vendor:112374       SBE: Y
  Email : CINFANTE@SFMSERVICES.COM
  Cert.Valid From Date: 09/13/2007               Cert.Valid To Date: 09/13/2010

  SL JAMESON CONSTRCTN SVCS INC                    Phone: 863-675-3864
   36 E HICKPOOCHEE AVE                            Fax:   863-675-8988
  LA BELLE FL 33935                                Vendor:114105       SBE: X
  Email : SLJAMESONCONST.INC@EARTHLINK.NET
  Cert.Valid From Date: 06/06/2007               Cert.Valid To Date: 06/05/2010

  SMITH & CO INC                                   Phone: 772-223-0037
   2400 S FEDERAL HWY STE 210                      Fax:   772-463-1073
  STUART FL 34994                                  Vendor:100184       SBE: Y
  Email : SSMITH@SMITHCOINC.NET
  Cert.Valid From Date: 03/11/2009               Cert.Valid To Date: 03/11/2012

  SOUTHEAST CONTRACTING SVCS INC                   Phone: 561-640-7422
   PO BOX 949                                      Fax:   561-640-7482
  LOXAHATCHEE FL 33470                             Vendor:115632       SBE: Y
  Email : DBEHRINGER@SECONTRACTING.COM
  Cert.Valid From Date: 02/01/2007               Cert.Valid To Date: 02/01/2010

  SOUTHERN GENERAL CONSTRCTN LLC                   Phone: 863-673-9339
   911 GRATTON RD                                  Fax:   863-983-9217
  CLEWISTON FL 33440                               Vendor:114494       SBE: Y
  Email : SOUTHERNGENCONST@GMAIL.COM
  Cert.Valid From Date: 01/16/2008               Cert.Valid To Date: 01/15/2011

  STERLING CONSTRCTN SVCS INC                      Phone: 954-332-3777
   101 NE THIRD AVE STE 1500                       Fax:   954-332-3778
  FT LAUDERDALE FL 33301                           Vendor:106403       SBE: T
  Email :
  Cert.Valid From Date: 09/15/2006               Cert.Valid To Date: 09/14/2009

  STRATEGO ENGRG CONSULTANTS INC                   Phone: 305-380-8440
   14415 SW 88TH ST STE G105                       Fax:   305-387-6336
  MIAMI FL 33186                                   Vendor:116240       SBE: V
  Email : PBALEPOGI@STRATEGOCONSULTANTS.COM
  Cert.Valid From Date: 03/12/2009               Cert.Valid To Date: 03/12/2012

  SUPERIOR MECHANICAL SYSTS INC                    Phone: 727-548-1711
   6482 PARK BLVD                                  Fax:   727-546-5668
  PINELLAS PARK FL 33781                           Vendor:101575       SBE: V
  Email : RAUL.PERERA@SUPERIORMECHANICAL.NET
  Cert.Valid From Date: 06/19/2009               Cert.Valid To Date: 06/19/2012

  T&E GRP INC                                      Phone: 786-486-4280
   8720 SW 82ND ST                                 Fax:   305-274-9754
  MIAMI FL 33173                                   Vendor:114037       SBE: Y
  Email : CLAIMADJUSTERS@GMAIL.COM
  Cert.Valid From Date: 05/30/2007               Cert.Valid To Date: 05/29/2010

  T&S CONSTRCTN INC                                Phone: 561-996-2308
   145 N MAIN ST                                   Fax:   561-996-2309
  BELLE GLADE FL 33430                             Vendor:115776       SBE: Y
  Email : DBSCHMIDT@AOL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   27

  Cert.Valid From Date: 10/31/2008               Cert.Valid To Date: 10/31/2011

  TALMAC INC                                       Phone: 305-468-8680
   2025 NW 102ND AVE UNIT 103                      Fax:   305-468-8682
  MIAMI FL 33172                                   Vendor:115353       SBE: Y
  Email : TALMAC@BELLSOUTH.NET
  Cert.Valid From Date: 08/18/2008               Cert.Valid To Date: 08/18/2011

  TAMPA CONTRACTING SVCS INC                       Phone: 941-721-7711
   11010 US HWY 41 N                               Fax:   941-721-7733
  PALMETTO FL 34221                                Vendor:116171       SBE: Y
  Email : TCSGCL@VERIZON.NET
  Cert.Valid From Date: 02/20/2009               Cert.Valid To Date: 02/20/2012

  TCS CONTRACTING INC                              Phone: 305-756-8700
   PO BOX 530299                                   Fax:   305-756-8707
  MIAMI FL 33153                                   Vendor:116195       SBE: X
  Email : TMS@TCSCCORP.COM
  Cert.Valid From Date: 02/24/2009               Cert.Valid To Date: 02/24/2012

  TED STARR CONSTRCTN INC                          Phone: 863-697-9713
   648 NW 50TH DR                                  Fax:   863-763-2949
  OKEECHOBEE FL 34972                              Vendor:114801       SBE: Y
  Email : STARRMAN49@YAHOO.COM
  Cert.Valid From Date: 03/07/2008               Cert.Valid To Date: 03/07/2011

  TEDCO CORP                                       Phone: 239-437-5133
   6719 WINKLER RD STE 210                         Fax:   239-437-5157
  FT MYERS FL 33919                                Vendor:115942       SBE: Y
  Email : TEDCO74@EMBARQMAIL.COM
  Cert.Valid From Date: 07/31/2009               Cert.Valid To Date: 07/31/2012

  TLMC ENTERPRISES INC                             Phone: 954-962-5358
   PO BOX 611173                                   Fax:
  NORTH MIAMI FL 33261                             Vendor:103145       SBE: X
  Email : TLMC100@BELLSOUTH.NET
  Cert.Valid From Date: 12/22/2006               Cert.Valid To Date: 12/21/2009

  TMD CONSTRCTN CO                                 Phone: 239-340-8526
   4610 ELEVATION WAY STE C                        Fax:   239-337-9383
  FT MYERS FL 33905                                Vendor:108202       SBE: Y
  Email : DILLONT@TMD-CO.COM
  Cert.Valid From Date: 03/07/2007               Cert.Valid To Date: 03/06/2010

  TRANSAMERICA CONSTRCTN CO                        Phone: 305-572-9551
   234 NE 34TH ST                                  Fax:   305-572-9552
  MIAMI FL 33137                                   Vendor:114127       SBE: V
  Email : EMERSON@TRANSAMERICACONSTRUCTION.COM
  Cert.Valid From Date: 06/13/2007               Cert.Valid To Date: 06/12/2010

  VALCOM DESIGN & CONSTRCTN INC                    Phone: 561-586-2844
   2328 TENTH AVE N STE 501                        Fax:   561-586-2834
  LAKE WORTH FL 33461                              Vendor:116558       SBE: V
  Email : LRVALDERRAMA@VALCOM-FL.COM
  Cert.Valid From Date: 07/07/2009               Cert.Valid To Date: 07/07/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   28

  VICS GENERAL SVCS INC                            Phone: 954-675-3148
   8739 SHADOW WOOD BLVD                           Fax:   954-753-2566
  CORAL SPRINGS FL 33071                           Vendor:114450       SBE: Y
  Email : JULIO17@YAHOO.COM
  Cert.Valid From Date: 09/11/2007               Cert.Valid To Date: 09/10/2010

  VTV LLC                                          Phone: 954-977-4790
   1915 MEARS PKWY                                 Fax:   954-977-3731
  MARGATE FL 33063                                 Vendor:114001       SBE: Y
  Email : MAXIMUMSERVICES@BELLSOUTH.NET
  Cert.Valid From Date: 08/24/2007               Cert.Valid To Date: 08/23/2010

  WASTE WATER MGMT INC                             Phone: 561-747-8028
   150 EVERNIA ST                                  Fax:   561-747-0642
  JUPITER FL 33458                                 Vendor:101934       SBE: Y
  Email : STEVEWWMI@BELLSOUTH.NET
  Cert.Valid From Date: 10/03/2007               Cert.Valid To Date: 10/02/2010

  WENCO SOUTH INC                                  Phone: 772-334-0050
   2560 NE INDIAN RIVER DR                         Fax:   772-334-0185
  JENSEN BEACH FL 34957                            Vendor:114747       SBE: Y
  Email : WENCOTOM@BELLSOUTH.NET
  Cert.Valid From Date: 02/16/2007               Cert.Valid To Date: 02/15/2011

  WESTBROOKS ENTERPRISES INC                       Phone: 954-557-2519
   6141 SW 51ST CT                                 Fax:   954-587-6502
  DAVIE FL 33314                                   Vendor:117024       SBE: T
  Email : DEEWSYK@COMCAST.NET
  Cert.Valid From Date: 10/14/2009               Cert.Valid To Date: 10/14/2012

  WILK CONSTRCTN CORP                              Phone: 561-248-3848
   5555 N NOB HILL                                 Fax:   954-206-6153
  SUNRISE FL 33351                                 Vendor:112105       SBE: Y
  Email : JI.CHAMBERLIN@CENTERPOINTCONST.COM
  Cert.Valid From Date: 10/29/2009               Cert.Valid To Date: 10/29/2012

  WILKINSON & JENKINS CONSTRCTN CO                 Phone: 727-527-9440
   PO BOX 530097                                   Fax:
  ST PETERSBURG FL 33747-0097                      Vendor:101103       SBE: Y
  Email :
  Cert.Valid From Date: 03/07/2007               Cert.Valid To Date: 03/06/2010

  WOODWARD & ASSOCS                                Phone: 863-353-5027
   32 PINEWOOD DR                                  Fax:
  HAINES CITY FL 33844                             Vendor:114940       SBE: Y
  Email : WOODWARDASSOCIATES@TAMPABAY.RR.COM
  Cert.Valid From Date: 03/20/2008               Cert.Valid To Date: 03/21/2011

  WORTH CONTRACTING INC                            Phone: 904-396-6363
   2112 JERNIGAN RD                                Fax:   904-396-1888
  JACKSONVILLE FL 32207                            Vendor:101638       SBE: X
  Email : WCI@WORTHCONTRACTINGINC.COM
  Cert.Valid From Date: 03/01/2007               Cert.Valid To Date: 02/28/2010

  WRANGLER CONSTRCTN INC                           Phone: 305-278-4719
   12855 SW 136TH AVE                              Fax:   305-278-4720
  MIAMI FL 33186                                   Vendor:114129       SBE: V
  Email : RAFA@WRANGLER-CONSTRUCTION.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   29

  Cert.Valid From Date: 03/21/2008               Cert.Valid To Date: 03/20/2011

  WW COMPANIES INC                                 Phone: 863-983-7977
   173 CR 720                                      Fax:   863-983-2345
  CLEWISTON FL 33440                               Vendor:113416       SBE: Y
  Email : EVERGLADESTREE@YAHOO.COM
  Cert.Valid From Date: 10/16/2009               Cert.Valid To Date: 10/16/2012

RENOVATION, STRUCTURE                                                  968-68

  3C CONSTRCTN CORP                                Phone: 305-638-5511
   3601 NW 55TH ST                                 Fax:   305-638-5515
  MIAMI FL 33142-2701                              Vendor:105346       SBE: V
  Email : OJC@3CCONSTRUCTIONCORP.COM
  Cert.Valid From Date: 05/30/2007               Cert.Valid To Date: 05/29/2010

  3D BUILDERS INC                                  Phone: 561-429-2607
   17183 80TH ST N                                 Fax:   561-429-2607
  LOXAHATCHEE FL 33470                             Vendor:116148       SBE: T
  Email : THREED_BUILDERS@HOTMAIL.COM
  Cert.Valid From Date: 03/19/2009               Cert.Valid To Date: 03/19/2012

  A2 GRP INC                                       Phone: 305-668-8939
   PO BOX 432310                                   Fax:   305-668-9454
  MIAMI FL 33423-2310                              Vendor:115876       SBE: Y
  Email : RIBASA@A2GROUP.COM
  Cert.Valid From Date: 03/05/2009               Cert.Valid To Date: 03/05/2012

  ACME ORGANIZATION INC                            Phone: 305-577-3525
   1730 BISCAYNE BLVD STE 201G                     Fax:   305-577-0198
  MIAMI FL 33132                                   Vendor:106967       SBE: T
  Email : ACMEORG98@AOL.COM
  Cert.Valid From Date: 06/30/2009               Cert.Valid To Date: 06/30/2012

  ACRE ENGRG & CONSTRCTN INC                       Phone: 305-436-5102
   2500 NW 79TH AVE STE 168                        Fax:   305-436-5108
  DORAL FL 33122                                   Vendor:115343       SBE: V
  Email : JOSEANGELBUSTOS@ACRECONSTRUCTION.COM
  Cert.Valid From Date: 08/28/2008               Cert.Valid To Date: 08/28/2011

  ACROPOLIS DEV GRP INC                            Phone: 305-285-7373
   1385 CORAL WAY STE 403                          Fax:   305-285-2363
  MIAMI FL 33145                                   Vendor:114194       SBE: Y
  Email : RLONDONO@ADAAG-CONSULTING
  Cert.Valid From Date: 05/02/2008               Cert.Valid To Date: 05/01/2011

  ALBERTZ CONSTRCTN INC                            Phone: 561-848-5150
   3648 E INDUSTRIAL WAY STE 2                     Fax:   561-848-5151
  RIVIERA BEACH FL 33404                           Vendor:107879       SBE: Y
  Email : MALBERTZ@BELLSOUTH.NET
  Cert.Valid From Date: 03/13/2007               Cert.Valid To Date: 03/12/2010

  ALL FLORIDA CONSTRCTN GRP OF                     Phone: 941-628-9131
   10050 BURNT STONE RD                            Fax:   941-639-2165
  PUNTA GORDA FL 33950                             Vendor:115911       SBE: Y
  Email : RSAMICK@SUNLINE.NET
  Cert.Valid From Date: 12/11/2008               Cert.Valid To Date: 12/11/2011
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   30

  AMBIENT TECHLGYS INC                             Phone: 727-328-0268
   4610 CENTRAL AVE                                Fax:   727-328-2477
  ST PETERSBURG FL 33711                           Vendor:101174       SBE: V
  Email : AMBTEC@AOL.COM
  Cert.Valid From Date: 09/04/2009               Cert.Valid To Date: 09/04/2012

  ANZAC CONTRACTORS INC                            Phone: 305-669-1986
   7475 SW 50TH TER                                Fax:   305-669-1180
  MIAMI FL 33155                                   Vendor:102875       SBE: Y
  Email : VIVIEN@ANZACCONTRACTORS.COM
  Cert.Valid From Date: 12/08/2006               Cert.Valid To Date: 12/07/2009

  AQUAFLORA INSTRUMENTATION SVCS INC               Phone: 863-816-8835
   6825 RANCH RD                                   Fax:   863-816-8835
  LAKELAND FL 33809                                Vendor:109393       SBE: Y
  Email : C.MONDALE@ATT.NET
  Cert.Valid From Date: 05/05/2007               Cert.Valid To Date: 05/04/2010

  ASPHALT CONSULTANTS INC                          Phone: 561-368-5797
   880 NW 1ST AVE                                  Fax:   561-750-8596
  BOCA RATON FL 33432                              Vendor:114706       SBE: Y
  Email : SANDY@ASPHALTCONSULTANTS.COM
  Cert.Valid From Date: 11/14/2007               Cert.Valid To Date: 11/13/2010

  ATLANTIC PAINTING & SANDBLASTING                 Phone: 561-740-1062
   400 S FEDERAL HWY STE 104                       Fax:   561-740-1063
  BOYNTON BEACH FL 33435                           Vendor:116773       SBE: Y
  Email : ATSANDBLAST@AOL.COM
  Cert.Valid From Date: 07/07/2009               Cert.Valid To Date: 07/07/2012

  AUTHENTIC CONSTRCTN LLC                          Phone: 305-529-2221
   4108 LAGUNA ST 2ND FL                           Fax:   305-675-3645
  CORAL GABLES FL 33146                            Vendor:116260       SBE: Y
  Email : RAY@AUTHENTICCONSTRUCT.COM
  Cert.Valid From Date: 03/11/2009               Cert.Valid To Date: 03/11/2012

  BALLARD CONTRACTORS INC                          Phone: 772-216-5543
   PO BOX 2281                                     Fax:
  OKEECHOBEE FL 34973                              Vendor:114182       SBE: Y
  Email :
  Cert.Valid From Date: 01/28/2009               Cert.Valid To Date: 01/28/2012

  BAZANJ CONSTRCTN CORP                            Phone: 786-355-5610
   14325 SW 100TH LN                               Fax:
  MIAMI FL 33186                                   Vendor:115342       SBE: Y
  Email : BAZANJCON@AOL.COM
  Cert.Valid From Date: 09/10/2008               Cert.Valid To Date: 09/09/2011

  BDI CONSTRCTN CO                                 Phone: 305-592-1210
   7270 NW 12TH ST STE 200                         Fax:   305-592-5603
  MIAMI FL 33126                                   Vendor:101435       SBE: Y
  Email : TROSELL@BDICO.COM
  Cert.Valid From Date: 10/05/2006               Cert.Valid To Date: 10/04/2009

  BENCHMARK III CORP                               Phone: 772-320-0206
   3322 GRANPARK WAY                               Fax:   772-320-0209
  STUART FL 34997                                  Vendor:116741       SBE: Y
  Email : B3AVA@AOL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   31

  Cert.Valid From Date: 07/01/2009               Cert.Valid To Date: 07/01/2012

  BETANCOURT CONSTRCTN INC                         Phone: 954-640-4400
   10831 NW 122ND ST                               Fax:   954-650-4401
  MEDLEY FL 33178                                  Vendor:115681       SBE: V
  Email : MARY@BETANCOURTCONSTRUCTION.COM
  Cert.Valid From Date: 08/25/2009               Cert.Valid To Date: 08/25/2012

  BOB ROCKWELL CONSTRCTN INC                       Phone: 239-466-8980
   11615 CHITWOOD DR STE C                         Fax:
  FT MYERS FL 33908                                Vendor:112730       SBE: Y
  Email : BRCTREE@STRATO.NET
  Cert.Valid From Date: 11/09/2006               Cert.Valid To Date: 11/08/2009

  BOYS ENGRG II INC                                Phone: 786-639-0689
   2625 W 78TH ST STE 2                            Fax:   786-639-0690
  HIALEAH FL 33016                                 Vendor:117076       SBE: Y
  Email : BOYSENGINEERING@AOL.COM
  Cert.Valid From Date: 10/23/2009               Cert.Valid To Date: 10/23/2012

  BREAKING GROUND CONTRG CO INC                    Phone: 904-388-1350
   4218 HIGHWAY AVE                                Fax:   904-388-3440
  JACKSONVILLE FL 32254                            Vendor:104102       SBE: X
  Email : MGTAPP@EARTHLINK.NET
  Cert.Valid From Date: 01/11/2007               Cert.Valid To Date: 01/10/2010

  BRI SAND FORMING CO INC                          Phone: 561-333-3676
   8233 GATOR LN #25                               Fax:   561-333-3675
  WEST PALM BEACH FL 33411                         Vendor:115708       SBE: Y
  Email : BRISANDFORMING@AOL.COM
  Cert.Valid From Date: 10/20/2008               Cert.Valid To Date: 10/20/2011

  CAM GRP LLC                                      Phone: 866-652-9050
   PO BOX 2481                                     Fax:
  FT PIERCE FL 34984                               Vendor:114872       SBE: Y
  Email : CAMGROUPLLC@GMAIL.COM
  Cert.Valid From Date: 03/04/2008               Cert.Valid To Date: 03/04/2011

  CAN CONSTRCTN INC                                Phone: 863-674-1002
   1080 COMMERCE DR BLDG 1                         Fax:   863-674-1003
  LA BELLE FL 33935                                Vendor:108790       SBE: Y
  Email : CANCONSTRUCTION@EMBARQMAIL.COM
  Cert.Valid From Date: 10/14/2009               Cert.Valid To Date: 10/14/2012

  CARROLL BROTHERS CONSTRCTN INC                   Phone: 561-684-7484
   PO BOX 18408                                    Fax:   561-684-6498
  WEST PALM BEACH FL 33406                         Vendor:101050       SBE: Y
  Email :
  Cert.Valid From Date: 04/24/2008               Cert.Valid To Date: 04/23/2011

  CDL EARTH MOVING & PAVING CORP                   Phone: 561-791-8271
   7655 ENTERPRISE DR #A3                          Fax:   561-791-8273
  WEST PALM BEACH FL 33404                         Vendor:115333       SBE: Y
  Email : CDLEARTHMOVING@BELLSOUTH.NET
  Cert.Valid From Date: 06/26/2008               Cert.Valid To Date: 06/25/2011
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   32

  CEDARS ELECTRO MECHANICAL INC                    Phone: 561-588-4088
   1712 S DIXIE HWY                                Fax:   561-588-4087
  LAKE WORTH FL 33460                              Vendor:104483       SBE: Y
  Email : INFO@CEDARSINC.COM
  Cert.Valid From Date: 12/02/2006               Cert.Valid To Date: 12/01/2009

  CISNEROS & SONS CONSTRCTN                        Phone: 305-872-1559
   30451 HIBISCUS LN                               Fax:   305-872-1559
  BIG PINE KEY FL 33043                            Vendor:113343       SBE: Y
  Email : CISNER@BELLSOUTH.NET
  Cert.Valid From Date: 02/08/2007               Cert.Valid To Date: 02/07/2010

  CL ELIAS CONSTRCTN INC                           Phone: 305-662-3837
   7440 SW 50 TER UNIT 103                         Fax:   305-661-5791
  MIAMI FL 33155                                   Vendor:115340       SBE: V
  Email : CHRISTI.ELIAS@CLELIASCONST.COM
  Cert.Valid From Date: 11/07/2008               Cert.Valid To Date: 11/07/2011

  COASTAL GUNITE CONSTRCTN CO                      Phone: 941-744-5500
   1001 3RD AVE STE 320                            Fax:   941-744-9880
  BRADENTON FL 34205                               Vendor:102707       SBE: Y
  Email : CURT@COASTALGUNITE.COM
  Cert.Valid From Date: 01/07/2009               Cert.Valid To Date: 01/07/2012

  COASTAL MARINE CONSTRCTN INC                     Phone: 941-485-2101
   625 N TAMIAMI TRL                               Fax:   941-488-0164
  VENICE FL 34285                                  Vendor:100139       SBE: Y
  Email : JIM@COASTALMARINECONSTRUCTION.COM
  Cert.Valid From Date: 03/27/2007               Cert.Valid To Date: 03/26/2010

  COMPASS CONSTRCTN LLC                            Phone: 863-824-3478
   1450 SW 86TH AVE                                Fax:   863-824-0273
  OKEECHOBEE FL 34974                              Vendor:116150       SBE: Y
  Email : DARRELL@COMPASSCONSTRUCTIONLLC.COM
  Cert.Valid From Date: 03/11/2009               Cert.Valid To Date: 03/11/2012

  CONSTRCTN SLTNS PLUS INC                         Phone: 239-825-7221
   2431 JASPER AVE                                 Fax:   239-936-2491
  FT MYERS FL 33907                                Vendor:113690       SBE: Y
  Email : RERIPP@YAHOO.COM
  Cert.Valid From Date: 05/09/2007               Cert.Valid To Date: 05/08/2010

  CONSTRCTN SPECIALISTS OF                         Phone: 954-648-2969
   16800 ORANGE BLVD                               Fax:
  LOXAHATCHEE FL 33470                             Vendor:114774       SBE: X
  Email : WINTERS954@AOL.COM
  Cert.Valid From Date: 12/05/2007               Cert.Valid To Date: 12/04/2010

  CONSTRCTNEER CORP                                Phone: 954-438-0800
   1121 SW 103RD AVE                               Fax:   954-438-0799
  PEMBROKE PINES FL 33025                          Vendor:101154       SBE: X
  Email : CONSTRUCTIONEER@AOL.COM
  Cert.Valid From Date: 08/27/2009               Cert.Valid To Date: 08/27/2012

  CORE CONSTRCTN GRP INC                           Phone: 321-229-2179
   1126 S DIVISION AVE STE C                       Fax:   407-428-9584
  ORLANDO FL 32805                                 Vendor:117115       SBE: Y
  Email : CCGIF@YAHOO.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   33

  Cert.Valid From Date: 10/22/2009               Cert.Valid To Date: 10/22/2012

  CORELAND CONSTRCTN CORP                          Phone: 305-233-1709
   12301 SW 128TH CT                               Fax:   305-233-1809
  MIAMI FL 33186                                   Vendor:114629       SBE: Y
  Email : CORLANDC@AOL.COM
  Cert.Valid From Date: 11/21/2007               Cert.Valid To Date: 11/20/2010

  CSI TRUCKING INC                                 Phone: 772-260-6961
   7600 SPRINGHAVEN ESTATES                        Fax:
  INDIANTOWN FL 34956                              Vendor:114937       SBE: Y
  Email : TCULBE03@AOL.COM
  Cert.Valid From Date: 02/09/2007               Cert.Valid To Date: 02/08/2011

  DAWSON GRP LLC                                   Phone: 808-630-9169
   3375 KOAPAKA ST B200                            Fax:   808-536-5530
  HONOLULU HI 96819                                Vendor:113680       SBE: W
  Email : DSMITH@DAWSON8A.COM
  Cert.Valid From Date: 07/03/2007               Cert.Valid To Date: 07/02/2010

  DEV COMM GRP OF FLORIDA                          Phone: 305-596-0611
   PO BOX 160178                                   Fax:   305-596-0615
  MIAMI FL 33116                                   Vendor:105285       SBE: Y
  Email : DEVELOPMENTFL@AOL.COM
  Cert.Valid From Date: 01/24/2007               Cert.Valid To Date: 01/23/2010

  DEVLAND SITE DEV INC                             Phone: 561-585-6370
   1302 WINGFIELD ST                               Fax:   561-732-0106
  LAKE WORTH FL 33460                              Vendor:110852       SBE: T
  Email : DEVLAND6370@AOL.COM
  Cert.Valid From Date: 10/28/2006               Cert.Valid To Date: 10/27/2009

  DOZIER & DOZIER CONSTRCTN INC                    Phone: 305-624-5274
   3932 NW 167TH ST                                Fax:   305-625-1452
  MIAMI GARDENS FL 33054                           Vendor:102278       SBE: T
  Email : WDOZIER@DOZIERANDDOZIER.COM
  Cert.Valid From Date: 01/05/2007               Cert.Valid To Date: 01/04/2010

  DR GREEN WHOLESALE NURSERIES INC                 Phone: 305-245-0809
   21055 SW 236 ST                                 Fax:   305-246-2977
  HOMESTEAD FL 33031                               Vendor:112686       SBE: V
  Email : MONGITA21@HOTMAIL.COM
  Cert.Valid From Date: 12/16/2006               Cert.Valid To Date: 12/15/2009

  DRAWDY CONSTRCTN CO INC                          Phone: 561-965-8092
   10201 LANTANA RD                                Fax:   561-965-9201
  LAKE WORTH FL 33449                              Vendor:100134       SBE: Y
  Email : DRAWDYCONST@BELLSOUTH.NET
  Cert.Valid From Date: 10/08/2009               Cert.Valid To Date: 10/08/2012

  EAGLE ENV ENTERPRISES INC                        Phone: 561-624-4024
   621 6TH TER                                     Fax:   561-624-8688
  PALM BEACH GARDENS FL 33418                      Vendor:104989       SBE: X
  Email : J.K.HALL@WORLDNET.ATT.NET
  Cert.Valid From Date: 12/22/2006               Cert.Valid To Date: 12/21/2009
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   34

  ENVIRO TECH SYSTS INC                            Phone: 863-763-3143
   2308 S PARROTT AVE                              Fax:   863-763-1309
  OKEECHOBEE FL 34974                              Vendor:114702       SBE: Y
  Email : ROYBL@ENVIRO-TECH.CC
  Cert.Valid From Date: 11/30/2007               Cert.Valid To Date: 11/29/2010

  ENVIRON LAND DEV INC                             Phone: 772-519-6278
   6381 PETERSON RD                                Fax:   772-462-2208
  FT PIERCE FL 34947                               Vendor:115599       SBE: Y
  Email : ELDINC2004@GMAIL.COM
  Cert.Valid From Date: 04/07/2009               Cert.Valid To Date: 04/07/2012

  EVANS IND SVCS                                   Phone: 786-402-8656
   1490 NE 156 TER                                 Fax:
  NORTH MIAMI BEACH FL 33162                       Vendor:113584       SBE: Y
  Email : EVANSINUDSTRIALS@HOTMAIL.COM
  Cert.Valid From Date: 04/12/2007               Cert.Valid To Date: 04/11/2010

  FLEMING EXECUTIVE GRP INC                        Phone: 786-295-0639
   5629 SW 19TH ST                                 Fax:   954-374-7276
  HOLLYWOOD FL 33023                               Vendor:113655       SBE: T
  Email : FLEMINGXGROUP@YAHOO.COM
  Cert.Valid From Date: 03/16/2007               Cert.Valid To Date: 03/15/2010

  GATOR GRADING & EXCAVATING LLC                   Phone: 561-881-5512
   1880W 10TH ST STE 104                           Fax:   561-881-5612
  RIVERIA BEACH FL 33404                           Vendor:109558       SBE: X
  Email : HBC314@YAHOO.COM
  Cert.Valid From Date: 06/30/2009               Cert.Valid To Date: 06/30/2012

  GBA CONSTRCTN & DEV GRP INC                      Phone: 786-295-4641
   15240 SW 160TH ST                               Fax:   786-242-5446
  MIAMI FL 33187                                   Vendor:114049       SBE: Y
  Email : GBAGROUP@NETZERO.COM
  Cert.Valid From Date: 06/08/2007               Cert.Valid To Date: 06/07/2010

  GE DEV OF SO FLA INC                             Phone: 954-252-8500
   5201 THOROUGHBRED LN                            Fax:   954-252-1259
  SOUTHWEST RANCHES FL 33330                       Vendor:116886       SBE: Y
  Email : GE.DEVELOPMENT@YAHOO.COM
  Cert.Valid From Date: 08/11/2009               Cert.Valid To Date: 08/11/2012

  GENERATION ELECTRICAL SVCS CORP                  Phone: 305-252-7780
   13727 SW 152ND ST STE 320                       Fax:   305-252-9975
  MIAMI FL 33177                                   Vendor:116491       SBE: Y
  Email : GESCO@BELLSOUTH.NET
  Cert.Valid From Date: 05/12/2009               Cert.Valid To Date: 05/12/2012

  GOLD STAR HOMEIMPROVEMENT INC                    Phone: 561-997-1778
   914 CLINT MOORE RD                              Fax:   561-997-1780
  BOCA RATON FL 33487                              Vendor:114941       SBE: Y
  Email : ZMORAG@GMAIL.COM
  Cert.Valid From Date: 02/11/2007               Cert.Valid To Date: 02/12/2011

  GULF GRP INC                                     Phone: 850-258-3545
   7402 HWY 2302                                   Fax:   850-769-6175
  SOUTHPORT FL 32409                               Vendor:100789       SBE: Y
  Email : SAM@GULFGROUP.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   35

  Cert.Valid From Date: 10/30/2008               Cert.Valid To Date: 10/30/2011

  GULFSTREAM RESTORATION & CONSTRCTN               Phone: 866-440-2565
   1809 S POWERLINE RD STE 107                     Fax:   866-440-2566
  DEERFIELD BEACH FL 33442                         Vendor:117104       SBE: Y
  Email : KELLY@GULFSTREAMCONST.COM
  Cert.Valid From Date: 11/02/2009               Cert.Valid To Date: 11/02/2012

  GUTHOY BUILDERS INC                              Phone: 305-216-4912
   11276 NW 160TH CT                               Fax:   305-974-0284
  MIAMI FL 33196                                   Vendor:116096       SBE: Y
  Email : GUTHOY@BELLSOUTH.NET
  Cert.Valid From Date: 01/27/2009               Cert.Valid To Date: 01/27/2012

  HAB CONTRACTORS INC                              Phone: 772-342-7667
   8643 N LEXINGTON DR                             Fax:   772-344-6524
  MIRAMAR FL 33025                                 Vendor:115611       SBE: T
  Email : AARON@HABCONTRACTORS.COM
  Cert.Valid From Date: 11/19/2008               Cert.Valid To Date: 11/19/2011

  HATCHER CONSTRCTN & DEV INC                      Phone: 561-330-2621
   400 W ATLANTIC AVE STE 2B                       Fax:   561-330-2670
  DELRAY BEACH FL 33444                            Vendor:104610       SBE: T
  Email : HATCHERGC@BELLSOUTH.NET
  Cert.Valid From Date: 06/18/2008               Cert.Valid To Date: 06/17/2011

  HECOL LLC                                        Phone: 786-367-2766
   12179 SW 132ND CT                               Fax:   786-573-4156
  MIAMI FL 33186                                   Vendor:113986       SBE: V
  Email : HECOLLLC@BELLSOUTH.NET
  Cert.Valid From Date: 05/17/2007               Cert.Valid To Date: 05/16/2010

  HG CONSTRCTN DEV & INVESTMENT INC                Phone: 786-325-9121
   10507 SW 78 ST                                  Fax:
  MIAMI FL 33173                                   Vendor:115364       SBE: Y
  Email : HGCONSTRUCTION@BELLSOUTH.NET
  Cert.Valid From Date: 06/24/2008               Cert.Valid To Date: 06/23/2011

  HI TE INC                                        Phone: 561-996-2003
   PO BOX 136                                      Fax:   561-996-2006
  BELLE GLADE FL 33430                             Vendor:111564       SBE: V
  Email : HITEINC@BELLSOUTH.NET
  Cert.Valid From Date: 04/05/2007               Cert.Valid To Date: 04/04/2010

  HOMESTEAD CONCRETE & DRAINAGE INC                Phone: 305-248-9649
   PO BOX 1273                                     Fax:   305-248-9650
  HOMESTEAD FL 33090                               Vendor:102158       SBE: V
  Email : ACORDERO@HOMESTEADCONCRETE.COM
  Cert.Valid From Date: 06/16/2009               Cert.Valid To Date: 06/16/2012

  HUMPHRIES CONSTRCTN CO INC                       Phone: 863-673-1117
   PO BOX 1116                                     Fax:   863-946-0331
  MOORE HAVEN FL 33471                             Vendor:114805       SBE: X
  Email : HUMPHRIES5767@YAHOO.COM
  Cert.Valid From Date: 02/09/2009               Cert.Valid To Date: 02/09/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   36

  IGWT CONSTRCTN INC                               Phone: 305-653-3770
   633 NE 167TH ST STE 1101                        Fax:
  NORTH MIAMI BEACH FL 33162                       Vendor:107580       SBE: T
  Email :
  Cert.Valid From Date: 11/10/2007               Cert.Valid To Date: 11/09/2010

  IICON CONTRACTORS CORP                           Phone: 305-245-1700
   123 N KROME AVE STE 206                         Fax:   305-245-7200
  HOMESTEAD FL 33030                               Vendor:110501       SBE: V
  Email : IAN.IGLESIAS@IICONCONTRACTORS.COM
  Cert.Valid From Date: 09/14/2009               Cert.Valid To Date: 09/14/2012

  INLAND CONSTRCTN & EQUIP SV                      Phone: 850-872-2129
   309 E 11TH ST                                   Fax:   850-872-0532
  PANAMA CITY FL 32401                             Vendor:104954       SBE: W
  Email : INLANDEQUIPMENT@HOTMAIL.COM
  Cert.Valid From Date: 02/28/2007               Cert.Valid To Date: 02/27/2010

  INTRON TECHLGYS INC                              Phone: 904-731-1445
   4859 VICTOR ST                                  Fax:   904-731-1446
  JACKSONVILLE FL 32207                            Vendor:106091       SBE: Y
  Email : JODY@INTRONTECH.COM
  Cert.Valid From Date: 01/05/2009               Cert.Valid To Date: 01/05/2012

  J M SNOW CONSTRCTN INC                           Phone: 561-996-5062
   1148 STILLWELL RD                               Fax:   561-996-6665
  BELLE GLADE FL 33430                             Vendor:109717       SBE: Y
  Email : BIZZYBEE73@BELLSOUTH.NET
  Cert.Valid From Date: 12/22/2007               Cert.Valid To Date: 12/21/2010

  J RAWN ENTERPRISES INC                           Phone: 561-478-7445
  6963 WILSON RD                                   Fax:   561-478-8471
  WEST PALM BEACH FL 33413                         Vendor:102416       SBE: Y
  Email :
  Cert.Valid From Date: 05/01/2007               Cert.Valid To Date: 04/30/2010

  JAMERICA CONCRETE SVCS CORP                      Phone: 561-902-1766
   PO BOX 596                                      Fax:   561-902-1152
  CANAL POINT FL 33438                             Vendor:114735       SBE: T
  Email : STALBION@AOL.COM
  Cert.Valid From Date: 11/27/2007               Cert.Valid To Date: 11/26/2010

  JD JAMES INC                                     Phone: 850-385-3234
   2074 RAYMOND DIEHL RD                           Fax:   850-385-3493
  TALLAHASSEE FL 32308                             Vendor:116460       SBE: X
  Email : APRIL@NATUREBRIDGES.COM
  Cert.Valid From Date: 05/12/2009               Cert.Valid To Date: 05/12/2012

  JHC CONTRACTORS INC                              Phone: 305-825-0834
   6187 NW 167TH ST STE H-24                       Fax:   305-825-0212
  MIAMI FL 33016                                   Vendor:115583       SBE: Y
  Email : JHCCONTRACTORS@BELLSOUTH.NET
  Cert.Valid From Date: 11/18/2008               Cert.Valid To Date: 11/18/2011

  JIJ CONSTRCTN CORP                               Phone: 561-572-1525
   11925 STURBRIDGE LN                             Fax:   561-594-4199
  WELLINGTON FL 33414                              Vendor:110000       SBE: Y
  Email : KATYCASSIANI@HOTMAIL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   37

  Cert.Valid From Date: 09/19/2008               Cert.Valid To Date: 09/18/2011

  JONES CO OF SOUTH FLORIDA INC THE                Phone: 954-583-7300
   3784 NW 16TH ST                                 Fax:   954-730-9000
  LAUDERHILL FL 33311                              Vendor:103851       SBE: T
  Email : LANSINGJROCK@AOL.COM
  Cert.Valid From Date: 09/15/2006               Cert.Valid To Date: 09/14/2009

  KEARNS CONSTRCTN CO                              Phone: 305-975-8878
   4101 BRAGANZA AVE                               Fax:   305-461-1892
  MIAMI FL 33133                                   Vendor:115843       SBE: Y
  Email : TROPICALBROCK@AOL.COM
  Cert.Valid From Date: 11/10/2008               Cert.Valid To Date: 11/10/2011

  KIRCHMAN CONSTRCTN CO                            Phone: 772-283-4256
   2597 SE DELMAR ST                               Fax:   772-283-1570
  STUART FL 34997                                  Vendor:105326       SBE: Y
  Email : INFO@KIRCHMANSONSTRUCTION.COM
  Cert.Valid From Date: 04/26/2007               Cert.Valid To Date: 04/25/2010

  LAKDAS YOHALEM ENGRG INC                         Phone: 954-771-0630
   2211 NE 54 ST                                   Fax:   954-771-0519
  FT LAUDERDALE FL 33308                           Vendor:100200       SBE: Y
  Email : LAKDAS22@BELLSOUTH.NET
  Cert.Valid From Date: 08/05/2008               Cert.Valid To Date: 08/05/2011

  LAMBERT BROS INC                                 Phone: 954-491-9380
   823 NW 57TH ST                                  Fax:   954-491-9425
  FT LAUDERDALE FL 33309                           Vendor:110218       SBE: Y
  Email : GL@LAMBERTBROS.COM
  Cert.Valid From Date: 10/06/2009               Cert.Valid To Date: 10/06/2012

  LATONA TRUCKING INC                              Phone: 570-760-6967
   16475 W YORKSHIRE                               Fax:
  LOXAHATCHEE FL 33470                             Vendor:111187       SBE: Y
  Email : BOBRADY52@MSN.COM
  Cert.Valid From Date: 03/23/2007               Cert.Valid To Date: 03/22/2010

  LEBOLO CONSTRCTN MGMT INC                        Phone: 561-742-7644
   2100 CORPORATE DR                               Fax:   561-742-7636
  BOYNTON BEACH FL 33426                           Vendor:114225       SBE: Y
  Email : TLEE@LEBOLO.COM
  Cert.Valid From Date: 08/21/2007               Cert.Valid To Date: 08/20/2010

  LMK PIPE RENEWAL LLC                             Phone: 954-772-0075
   1131 NW 55TH ST                                 Fax:   954-772-0086
  FT LAUDERDALE FL 33309                           Vendor:116788       SBE: Y
  Email : GRINEHART@BELLSOUTH.NET
  Cert.Valid From Date: 07/21/2009               Cert.Valid To Date: 07/21/2012

  LUCAS MARINE CONSTRCTN LLC                       Phone: 772-286-5094
   3130 SE SLATER ST                               Fax:   772-286-1139
  STUART FL 34997                                  Vendor:102591       SBE: Y
  Email : WDIEKMAN@LMCLLC.NET
  Cert.Valid From Date: 02/09/2007               Cert.Valid To Date: 02/08/2010
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   38

  MAC CONSTRCTN INC                                Phone: 305-598-4317
   9500 NW 12TH ST BAY 1B                          Fax:   305-599-9626
  MIAMI FL 33172                                   Vendor:109297       SBE: X
  Email : KELI@MACCONSTRUCTION.NET
  Cert.Valid From Date: 07/25/2008               Cert.Valid To Date: 07/24/2011

  MAG CONSTRCUCTION INC                            Phone: 305-218-9835
   7812 SW 34TH TER                                Fax:   305-263-9369
  MIAMI FL 33155                                   Vendor:112624       SBE: V
  Email : MAGCON@BELLSOUTH.NET
  Cert.Valid From Date: 11/04/2006               Cert.Valid To Date: 11/03/2009

  MAINSTREAM CONSTRCTN CORP                        Phone: 863-983-3457
   PO BOX 1060                                     Fax:   863-983-1112
  CLEWISTON FL 33440                               Vendor:113610       SBE: V
  Email : MAINSTREAMCONSTRUCTION@EARTHLINK.NET
  Cert.Valid From Date: 06/08/2007               Cert.Valid To Date: 06/07/2010

  MAKO BUILDERS LLC                                Phone: 561-804-1226
   PO BOX 210908                                   Fax:
  ROYAL PALM BEACH FL 33421                        Vendor:113290       SBE: U
  Email : SAL@MAKOBUILDERS.COM
  Cert.Valid From Date: 03/28/2007               Cert.Valid To Date: 03/27/2010

  MARK W BRANDEL INC                               Phone: 863-763-6796
   2525 NE 131ST LN                                Fax:   863-763-9154
  OKEECHOBEE FL 34972                              Vendor:115907       SBE: Y
  Email : MBRANDEL@STRATO.NET
  Cert.Valid From Date: 02/10/2009               Cert.Valid To Date: 02/10/2012

  MAXON GROUPE LLC                                 Phone: 305-710-8666
   4218 NE 2ND AVE 2ND FL                          Fax:   305-868-7887
  MIAMI FL 33137                                   Vendor:115638       SBE: Y
  Email : WILLIAM@MAXONGROUPE.COM
  Cert.Valid From Date: 09/26/2008               Cert.Valid To Date: 09/25/2011

  MERKURY CORP                                     Phone: 305-758-9888
   7300 BISCAYNE BLVD STE 204                      Fax:   305-758-0802
  MIAMI FL 33138                                   Vendor:110270       SBE: V
  Email : RUBEN@MERKURYDEVELOPMENT.COM
  Cert.Valid From Date: 01/10/2007               Cert.Valid To Date: 01/09/2010

  MGI MORGAN GENERAL MECHANICAL GRP                Phone: 954-360-9803
   1128 S POWERLINE RD                             Fax:
  DEERFIELD BEACH FL 33442                         Vendor:102007       SBE: Y
  Email : DMORGAN@MGI-MORGAN.COM
  Cert.Valid From Date: 03/07/2008               Cert.Valid To Date: 03/07/2011

  MIAMI BEACH SEAWALLS INC                         Phone: 305-945-2114
   17027 W DIXIE HWY STE 127                       Fax:   305-945-2329
  N MIAMI BEACH FL 33160                           Vendor:115732       SBE: Y
  Email : SEAWALLC@BELLSOUTH.NET
  Cert.Valid From Date: 11/04/2008               Cert.Valid To Date: 11/04/2011

  MITCHELL VAUGHN CUSTOM HOMES INC                 Phone: 772-631-0051
   1535 CYPRESS DR #2                              Fax:   561-747-9800
  JUPITER FL 33469                                 Vendor:116133       SBE: Y
  Email : MVCUSTOMHOMES@COMCAST.NET
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   39

  Cert.Valid From Date: 05/08/2009               Cert.Valid To Date: 05/08/2012

  MR CRICKET INC                                   Phone: 305-251-2900
   16115 SW 117 AVE STE A16                        Fax:   305-238-9095
  MIAMI FL 33177                                   Vendor:115649       SBE: Y
  Email : DEZIR@BELLSOUTH.NET
  Cert.Valid From Date: 12/11/2008               Cert.Valid To Date: 12/11/2011

  MTW SVCS INC                                     Phone: 863-673-8864
   13261 ROLLING GREEN RD                          Fax:   561-625-1781
  NORTH PALM BEACH FL 33408                        Vendor:112671       SBE: Y
  Email : MTWSERVICES@AOL.COM
  Cert.Valid From Date: 03/10/2007               Cert.Valid To Date: 03/09/2010

  MUCHATI ENGRG CONTRACTORS INC                    Phone: 754-214-0286
   6441 NW 58TH TER                                Fax:   954-346-8979
  PARKLAND FL 33067                                Vendor:115212       SBE: V
  Email : MUCHATIENG@BELLSOUTH.NET
  Cert.Valid From Date: 05/20/2008               Cert.Valid To Date: 05/19/2011

  NAC CONSTRCTN INC                                Phone: 305-412-2275
   9065 SW 87TH AVE STE 112                        Fax:   305-412-2278
  MIAMI FL 33176                                   Vendor:114114       SBE: Y
  Email : NESTORCASTELLON@NACCONST.COM
  Cert.Valid From Date: 06/08/2007               Cert.Valid To Date: 06/07/2010

  NATIVE POWER INC                                 Phone: 772-785-9795
   769 SW MONSOON RD                               Fax:   772-343-1133
  PRT ST LUCIE FL 34953                            Vendor:112210       SBE: Y
  Email : NATIVEPOWERINC@YAHOO.COM
  Cert.Valid From Date: 12/02/2006               Cert.Valid To Date: 12/01/2009

  NIFAH & PARTNERS CONSULTING                      Phone: 305-969-9195
   12350 SW 132 CT STE 201                         Fax:   305-969-9192
  MIAMI FL 33186                                   Vendor:109752       SBE: T
  Email : NWEBSTER@NIFAHPARTNERS.COM
  Cert.Valid From Date: 05/30/2007               Cert.Valid To Date: 05/29/2010

  NSQUARE INC                                      Phone: 239-514-1173
   PO BOX 113040                                   Fax:   239-514-4161
  NAPLES FL 34108                                  Vendor:116984       SBE: Y
  Email : SSTANDRIFF@NSQUAREINC.COM
  Cert.Valid From Date: 09/30/2009               Cert.Valid To Date: 09/30/2012

  NYC BUILDERS INC                                 Phone: 561-283-3333
   2090 PALM BEACH LAKES BLVD                      Fax:   561-656-9744
  WEST PALM BEACH FL 33409                         Vendor:115284       SBE: T
  Email : ERROL@NYCBUILDERSCORP.COM
  Cert.Valid From Date: 11/25/2008               Cert.Valid To Date: 11/05/2011

  OAC ACTION CONSTRCTN CORP                        Phone: 305-256-6655
   12540 SW 130TH ST STE 3                         Fax:   305-255-1004
  MIAMI FL 33186                                   Vendor:114041       SBE: V
  Email : OZZIE@OACCONSTRUCTION.COM
  Cert.Valid From Date: 08/25/2007               Cert.Valid To Date: 08/24/2010
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   40

  OGDEN BROTHERS CONSTRCTN INC                     Phone: 239-592-9960
   1141 SUN CENTURY BLVD                           Fax:   239-592-7549
  NAPLES FL 34110                                  Vendor:115978       SBE: Y
  Email : ROB@OGDENBROTHERS.COM
  Cert.Valid From Date: 12/22/2008               Cert.Valid To Date: 12/22/2011

  OVERLAND CONSTRCTN CO INC                        Phone: 561-683-3210
   1360 W 53RD ST                                  Fax:   561-683-3219
  WEST PALM BEACH FL 33407                         Vendor:104741       SBE: Y
  Email : OVERLANDCONST@AOL.COM
  Cert.Valid From Date: 03/14/2007               Cert.Valid To Date: 03/13/2010

  PACECON GENERAL CONTRACTORS INC                  Phone: 561-827-7223
   129 TURNBERRY DR                                Fax:   561-304-1185
  ATLANTIS FL 33462                                Vendor:116995       SBE: Y
  Email : CONPACEINC@AOL.COM
  Cert.Valid From Date: 09/21/2009               Cert.Valid To Date: 09/21/2012

  PALM CONSTRCTN & DESIGN GRP INC                  Phone: 786-251-9289
   12491 SW 134TH CT STE 20                        Fax:   305-378-8995
  MIAMI FL 33186                                   Vendor:116011       SBE: T
  Email : CROLLE@PALMENGINEERING.COM
  Cert.Valid From Date: 01/08/2009               Cert.Valid To Date: 01/08/2012

  PAPPAS CONSTRCTN INC                             Phone: 305-496-7443
   10661 N KENDALL DR                              Fax:   305-412-9545
  MIAMI FL 33176                                   Vendor:114785       SBE: Y
  Email : BUILTBYPAPPAS@BELLSOUTH.NET
  Cert.Valid From Date: 10/06/2007               Cert.Valid To Date: 10/05/2010

  PERXI INC                                        Phone: 786-275-8992
   7915 NW 8TH ST UNIT 5                           Fax:   786-275-8980
  MIAMI FL 33126                                   Vendor:114113       SBE: Y
  Email : PERXIINC@GMAIL.COM
  Cert.Valid From Date: 07/12/2007               Cert.Valid To Date: 07/11/2010

  POWELL KUGLER INC                                Phone: 561-820-4891
   500 S AUSTRALIAN AVE STE 600                    Fax:   561-651-4110
  WEST PALM BEACH FL 33401                         Vendor:108401       SBE: T
  Email : POWELLKUGLER@HOTMAIL.COM
  Cert.Valid From Date: 07/01/2009               Cert.Valid To Date: 07/01/2012

  PRECISION ENGRG LLC                              Phone: 561-795-1771
   83 WESTBURY CLOSE                               Fax:   561-795-9980
  WELLINGTON FL 33414                              Vendor:111974       SBE: Y
  Email : PRECENG@BELLSOUTH.NET
  Cert.Valid From Date: 11/04/2006               Cert.Valid To Date: 11/03/2009

  PRIMARY CONSTRCTN INC                            Phone: 786-348-1237
   1250 NW 79TH ST STE 204                         Fax:
  MIAMI FL 33147                                   Vendor:115462       SBE: T
  Email : AMOSS@PRIMARYCONSTRUCTIONINC.COM
  Cert.Valid From Date: 01/06/2009               Cert.Valid To Date: 01/06/2012

  PRINCIPLE DESIGN & DEV LLC                       Phone: 561-533-5252
   3401 S CONGRESS AVE STES 200-205                Fax:   561-533-5724
  PALM SPRINGS FL 33461                            Vendor:110509       SBE: Y
  Email : DNACATOLA@PRINCIPLEDD.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   41

  Cert.Valid From Date: 12/02/2006               Cert.Valid To Date: 12/01/2009

  PSA CONSTRUCTORS INC                             Phone: 407-898-9119
   1516 E HILLCREST ST STE 310                     Fax:   407-898-9077
  ORLANDO FL 32803                                 Vendor:102732       SBE: T
  Email :
  Cert.Valid From Date: 05/05/2007               Cert.Valid To Date: 05/04/2010

  QUALIFIED BUILDERS INC                           Phone: 863-697-0184
   PO BOX 3200                                     Fax:   863-824-8711
  OKEECHOBEE FL 34973                              Vendor:116304       SBE: Y
  Email :
  Cert.Valid From Date: 03/25/2009               Cert.Valid To Date: 03/25/2012

  RAMCONEX INC                                     Phone: 863-441-1979
   202 HILLSDIE DR                                 Fax:   863-465-7436
  LAKE PLACID FL 33852                             Vendor:110885       SBE: Y
  Email : WORMWOOD@HTN.NET
  Cert.Valid From Date: 10/05/2006               Cert.Valid To Date: 10/04/2009

  RCI ELECTRIC INC                                 Phone: 561-747-8150
   15429 86TH WAY                                  Fax:   561-747-6052
  PALM BEACH GARDENS FL 33418                      Vendor:116787       SBE: Y
  Email : RCIELECTRIC@COMCAST.NET
  Cert.Valid From Date: 09/11/2009               Cert.Valid To Date: 09/11/2012

  RENLISKRIS CORP                                  Phone: 954-791-6377
   3686 NW 16TH ST                                 Fax:
  LAUDERHILL FL 33311                              Vendor:114171       SBE: X
  Email : RENLISKRIS@AOL.COM
  Cert.Valid From Date: 07/10/2007               Cert.Valid To Date: 07/09/2010

  RJR CONSTRCTN INC                                Phone: 305-244-1837
   7025 SW 19TH TER                                Fax:   305-267-1899
  MIAMI FL 33155                                   Vendor:100197       SBE: V
  Email : RJRCONST@BELLSOUTH.NET
  Cert.Valid From Date: 11/17/2008               Cert.Valid To Date: 11/17/2011

  ROBMAR WATERPROOFING INC                         Phone: 954-410-0478
   1331 S DIXIE HWY STE 9B                         Fax:   954-784-5093
  POMPANO BEACH FL 33060                           Vendor:110280       SBE: Y
  Email : SALES@ROBMARWATERPROOFING.NET
  Cert.Valid From Date: 02/06/2007               Cert.Valid To Date: 02/05/2011

  RONALD A BEECROFT INC                            Phone: 239-344-6559
   40811 SUZAN DR                                  Fax:   239-731-7661
  PUNTA GORDA FL 33982                             Vendor:115793       SBE: Y
  Email : RABEECROFTCGC@AOL.COM
  Cert.Valid From Date: 11/12/2008               Cert.Valid To Date: 11/12/2011

  RS CONSTRCTN OF SOUTHWEST FLORIDA                Phone: 941-628-6407
   7173 SW CR 769                                  Fax:   941-235-3624
  ARCADIA FL 34269                                 Vendor:115949       SBE: Y
  Email : FRAN-RAY@COMCAST.NET
  Cert.Valid From Date: 01/06/2009               Cert.Valid To Date: 01/06/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   42

  S GROUP INC                                      Phone: 561-688-2295
   1470 N CONGRESS AVE STE 119                     Fax:   561-688-2298
  WEST PALM BEACH FL 33409                         Vendor:114695       SBE: V
  Email : MSANCHEZ@SGROUPINC.NET
  Cert.Valid From Date: 11/09/2007               Cert.Valid To Date: 11/08/2010

  SEACOAST CONSTRCTN INC                           Phone: 786-888-8400
   169 E FLAGLER ST STE 1123                       Fax:   305-675-6323
  MAMI FL 33131                                    Vendor:116350       SBE: V
  Email : GEORGE.ABADIE@SEACOASTCONSTRUCTION.NET
  Cert.Valid From Date: 04/06/2009               Cert.Valid To Date: 04/06/2012

  SEACOAST INC                                     Phone: 813-925-3555
   301 DOUGLAS ROAD E                              Fax:   813-925-3553
  OLDSMAR FL 34677                                 Vendor:115981       SBE: Y
  Email : STEVE@SEACOASTINC.NET
  Cert.Valid From Date: 12/30/2008               Cert.Valid To Date: 12/30/2011

  SEALTEC CONSTRCTN GRP                            Phone: 305-558-7174
   6157 NW 167TH ST STE F15                        Fax:   305-364-4338
  MIAMI FL 33015-4356                              Vendor:111048       SBE: Y
  Email : JCPORTAJR@MINDSPRING.BIZ
  Cert.Valid From Date: 10/26/2007               Cert.Valid To Date: 10/25/2010

  SEALY TRINBAGO INC                               Phone: 305-259-9989
   9900 SW 168TH ST STE 7                          Fax:   305-253-4545
  MIAMI FL 33157                                   Vendor:110157       SBE: Y
  Email : SEALYTRINBAGOINC@BELLSOUTH.NET
  Cert.Valid From Date: 05/17/2008               Cert.Valid To Date: 05/16/2011

  SEMINOLE DESIGN BUILD INC                        Phone: 863-763-9888
   PO BOX 2567                                     Fax:   863-467-0610
  OKEECHOBEE FL 34973                              Vendor:104714       SBE: W
  Email : NUNEZD3@EARTHLINK.NET
  Cert.Valid From Date: 01/31/2007               Cert.Valid To Date: 01/30/2011

  SOUTHEAST CONTRACTING SVCS INC                   Phone: 561-640-7422
   PO BOX 949                                      Fax:   561-640-7482
  LOXAHATCHEE FL 33470                             Vendor:115632       SBE: Y
  Email : DBEHRINGER@SECONTRACTING.COM
  Cert.Valid From Date: 02/01/2007               Cert.Valid To Date: 02/01/2010

  SOUTHERN GENERAL CONSTRCTN LLC                   Phone: 863-673-9339
   911 GRATTON RD                                  Fax:   863-983-9217
  CLEWISTON FL 33440                               Vendor:114494       SBE: Y
  Email : SOUTHERNGENCONST@GMAIL.COM
  Cert.Valid From Date: 01/16/2008               Cert.Valid To Date: 01/15/2011

  STRATEGO ENGRG CONSULTANTS INC                   Phone: 305-380-8440
   14415 SW 88TH ST STE G105                       Fax:   305-387-6336
  MIAMI FL 33186                                   Vendor:116240       SBE: V
  Email : PBALEPOGI@STRATEGOCONSULTANTS.COM
  Cert.Valid From Date: 03/12/2009               Cert.Valid To Date: 03/12/2012

  T&E GRP INC                                      Phone: 786-486-4280
   8720 SW 82ND ST                                 Fax:   305-274-9754
  MIAMI FL 33173                                   Vendor:114037       SBE: Y
  Email : CLAIMADJUSTERS@GMAIL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   43

  Cert.Valid From Date: 05/30/2007               Cert.Valid To Date: 05/29/2010

  T&S CONSTRCTN INC                                Phone: 561-996-2308
   145 N MAIN ST                                   Fax:   561-996-2309
  BELLE GLADE FL 33430                             Vendor:115776       SBE: Y
  Email : DBSCHMIDT@AOL.COM
  Cert.Valid From Date: 10/31/2008               Cert.Valid To Date: 10/31/2011

  TAMPA CONTRACTING SVCS INC                       Phone: 941-721-7711
   11010 US HWY 41 N                               Fax:   941-721-7733
  PALMETTO FL 34221                                Vendor:116171       SBE: Y
  Email : TCSGCL@VERIZON.NET
  Cert.Valid From Date: 02/20/2009               Cert.Valid To Date: 02/20/2012

  TAYLOR LAND DEV INC                              Phone: 561-792-2818
   17145 69TH ST N                                 Fax:   561-792-1965
  LOXAHATCHEE FL 33470                             Vendor:104364       SBE: Y
  Email : RTAYLOR50@BELLSOUTH.NET
  Cert.Valid From Date: 02/17/2007               Cert.Valid To Date: 02/16/2010

  TCS CONTRACTING INC                              Phone: 305-756-8700
   PO BOX 530299                                   Fax:   305-756-8707
  MIAMI FL 33153                                   Vendor:116195       SBE: X
  Email : TMS@TCSCCORP.COM
  Cert.Valid From Date: 02/24/2009               Cert.Valid To Date: 02/24/2012

  TED STARR CONSTRCTN INC                          Phone: 863-697-9713
   648 NW 50TH DR                                  Fax:   863-763-2949
  OKEECHOBEE FL 34972                              Vendor:114801       SBE: Y
  Email : STARRMAN49@YAHOO.COM
  Cert.Valid From Date: 03/07/2008               Cert.Valid To Date: 03/07/2011

  TEDCO CORP                                       Phone: 239-437-5133
   6719 WINKLER RD STE 210                         Fax:   239-437-5157
  FT MYERS FL 33919                                Vendor:115942       SBE: Y
  Email : TEDCO74@EMBARQMAIL.COM
  Cert.Valid From Date: 07/31/2009               Cert.Valid To Date: 07/31/2012

  TLMC ENTERPRISES INC                             Phone: 954-962-5358
   PO BOX 611173                                   Fax:
  NORTH MIAMI FL 33261                             Vendor:103145       SBE: X
  Email : TLMC100@BELLSOUTH.NET
  Cert.Valid From Date: 12/22/2006               Cert.Valid To Date: 12/21/2009

  TM RUSSELL CONTRACTING INC                       Phone: 561-881-8005
   210 BRANT RD BLDG E                             Fax:   561-881-8020
  LAKE PARK FL 33403                               Vendor:115354       SBE: X
  Email : RUSSELL1@BELLSOUTH.NET
  Cert.Valid From Date: 03/02/2009               Cert.Valid To Date: 03/02/2012

  TMD CONSTRCTN CO                                 Phone: 239-340-8526
   4610 ELEVATION WAY STE C                        Fax:   239-337-9383
  FT MYERS FL 33905                                Vendor:108202       SBE: Y
  Email : DILLONT@TMD-CO.COM
  Cert.Valid From Date: 03/07/2007               Cert.Valid To Date: 03/06/2010
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   44

  TRANSAMERICA CONSTRCTN CO                        Phone: 305-572-9551
   234 NE 34TH ST                                  Fax:   305-572-9552
  MIAMI FL 33137                                   Vendor:114127       SBE: V
  Email : EMERSON@TRANSAMERICACONSTRUCTION.COM
  Cert.Valid From Date: 06/13/2007               Cert.Valid To Date: 06/12/2010

  VALCOM DESIGN & CONSTRCTN INC                    Phone: 561-586-2844
   2328 TENTH AVE N STE 501                        Fax:   561-586-2834
  LAKE WORTH FL 33461                              Vendor:116558       SBE: V
  Email : LRVALDERRAMA@VALCOM-FL.COM
  Cert.Valid From Date: 07/07/2009               Cert.Valid To Date: 07/07/2012

  VANCE CONSTRCTN CO THE                           Phone: 561-650-0016
   PO BOX 4592                                     Fax:   561-650-8147
  WEST PALM BEACH FL 33402                         Vendor:113099       SBE: Y
  Email : VANCECOCJ@AOL.COM
  Cert.Valid From Date: 02/20/2009               Cert.Valid To Date: 02/20/2012

  VIKING DIVING SVCS INC                           Phone: 772-460-6710
   PO BOX 9487                                     Fax:   772-607-7200
  PRT ST LUCIE FL 34985                            Vendor:114589       SBE: Y
  Email : THOR@VIKINGDIVINGSERVICES.COM
  Cert.Valid From Date: 12/15/2007               Cert.Valid To Date: 12/14/2010

  VTV LLC                                          Phone: 954-977-4790
   1915 MEARS PKWY                                 Fax:   954-977-3731
  MARGATE FL 33063                                 Vendor:114001       SBE: Y
  Email : MAXIMUMSERVICES@BELLSOUTH.NET
  Cert.Valid From Date: 08/24/2007               Cert.Valid To Date: 08/23/2010

  WESTBROOKS ENTERPRISES INC                       Phone: 954-557-2519
   6141 SW 51ST CT                                 Fax:   954-587-6502
  DAVIE FL 33314                                   Vendor:117024       SBE: T
  Email : DEEWSYK@COMCAST.NET
  Cert.Valid From Date: 10/14/2009               Cert.Valid To Date: 10/14/2012

  WORTH CONTRACTING INC                            Phone: 904-396-6363
   2112 JERNIGAN RD                                Fax:   904-396-1888
  JACKSONVILLE FL 32207                            Vendor:101638       SBE: X
  Email : WCI@WORTHCONTRACTINGINC.COM
  Cert.Valid From Date: 03/01/2007               Cert.Valid To Date: 02/28/2010

  WW COMPANIES INC                                 Phone: 863-983-7977
   173 CR 720                                      Fax:   863-983-2345
  CLEWISTON FL 33440                               Vendor:113416       SBE: Y
  Email : EVERGLADESTREE@YAHOO.COM
  Cert.Valid From Date: 10/16/2009               Cert.Valid To Date: 10/16/2012

WATER CONTROL STRUCTURES                                               968-92

  3AW WELDING & FABRICATION INC                    Phone: 863-983-2251
   221 DESOTO AVE                                  Fax:   863-983-3351
  CLEWISTON FL 33440                               Vendor:111776       SBE: Y
  Email : BABYRAY5685@AOL.COM
  Cert.Valid From Date: 12/16/2006               Cert.Valid To Date: 12/15/2009
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   45

  3C CONSTRCTN CORP                                Phone: 305-638-5511
   3601 NW 55TH ST                                 Fax:   305-638-5515
  MIAMI FL 33142-2701                              Vendor:105346       SBE: V
  Email : OJC@3CCONSTRUCTIONCORP.COM
  Cert.Valid From Date: 05/30/2007               Cert.Valid To Date: 05/29/2010

  A TECH WELDING LLC                               Phone: 772-370-7396
   2104 TROWBRIDGE RD                              Fax:   772-460-0136
  FT PIERCE FL 34945                               Vendor:115805       SBE: Y
  Email : AARON@ATECHWELDING.COM
  Cert.Valid From Date: 11/06/2008               Cert.Valid To Date: 11/06/2011

  A&A FONTE INC                                    Phone: 305-512-4739
   12963 W OKEECHOBEE RD UNIT 8                    Fax:   305-512-4759
  HIALEAH GARDENS FL 33018                         Vendor:116809       SBE: Y
  Email : ANDRESFONTE@AAFONTE.COM
  Cert.Valid From Date: 07/21/2009               Cert.Valid To Date: 07/21/2012

  ACME ORGANIZATION INC                            Phone: 305-577-3525
   1730 BISCAYNE BLVD STE 201G                     Fax:   305-577-0198
  MIAMI FL 33132                                   Vendor:106967       SBE: T
  Email : ACMEORG98@AOL.COM
  Cert.Valid From Date: 06/30/2009               Cert.Valid To Date: 06/30/2012

  ALL FLORIDA CONSTRCTN GRP OF                     Phone: 941-628-9131
   10050 BURNT STONE RD                            Fax:   941-639-2165
  PUNTA GORDA FL 33950                             Vendor:115911       SBE: Y
  Email : RSAMICK@SUNLINE.NET
  Cert.Valid From Date: 12/11/2008               Cert.Valid To Date: 12/11/2011

  ANDERSON DIVING INC                              Phone: 904-731-0000
   4811 BOWDEN RD                                  Fax:   904-731-5493
  JACKSONVILLE FL 32216                            Vendor:115529       SBE: Y
  Email : DIVEWORXX@AOL.COM
  Cert.Valid From Date: 07/02/2009               Cert.Valid To Date: 07/02/2012

  ANTINORI MGMT GRP INC                            Phone: 386-761-2805
   5629 S RIDGEWOOD AVE                            Fax:   386-761-4311
  PRT ORANGE FL 32127                              Vendor:115282       SBE: Y
  Email : ANTINORICONSTRUCTION@YAHOO.COM
  Cert.Valid From Date: 11/03/2008               Cert.Valid To Date: 11/03/2011

  ANZAC CONTRACTORS INC                            Phone: 305-669-1986
   7475 SW 50TH TER                                Fax:   305-669-1180
  MIAMI FL 33155                                   Vendor:102875       SBE: Y
  Email : VIVIEN@ANZACCONTRACTORS.COM
  Cert.Valid From Date: 12/08/2006               Cert.Valid To Date: 12/07/2009

  ASAP INSTALLATIONS LLC                           Phone: 813-385-7257
   4304 WATERFORD LANDING DR                       Fax:   813-948-8934
  LUTZ FL 33558                                    Vendor:116707       SBE: Y
  Email : SIMON@ASAPINSTALLATIONS.NET
  Cert.Valid From Date: 07/01/2009               Cert.Valid To Date: 07/01/2012

  ASMUSSEN ENGRG LLC                               Phone: 863-763-8546
   PO BOX 1998                                     Fax:   863-467-8560
  OKEECHOBEE FL 34973                              Vendor:106569       SBE: Y
  Email : LASMUSSE@EMBARQMAIL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   46

  Cert.Valid From Date: 02/02/2007               Cert.Valid To Date: 02/01/2010

  ASSOCIATED DIVING & MARINE                       Phone: 352-425-0384
   1473 PIONEER RD STE C                           Fax:   801-886-8130
  SALT LAKE CITY UT 84104                          Vendor:113471       SBE: Y
  Email : MARINEOPS@DIVING-MARINE.COM
  Cert.Valid From Date: 01/31/2007               Cert.Valid To Date: 01/30/2010

  BELVEDERE CONTRACTING INC                        Phone: 561-747-6637
   1003 JUPITER PARK LN STE 5                      Fax:   561-747-6628
  JUPITER FL 33458                                 Vendor:116030       SBE: Y
  Email : BUCK@BELVEDERECONTRACTING.COM
  Cert.Valid From Date: 01/21/2009               Cert.Valid To Date: 01/21/2012

  BETANCOURT CONSTRCTN INC                         Phone: 954-640-4400
   10831 NW 122ND ST                               Fax:   954-650-4401
  MEDLEY FL 33178                                  Vendor:115681       SBE: V
  Email : MARY@BETANCOURTCONSTRUCTION.COM
  Cert.Valid From Date: 08/25/2009               Cert.Valid To Date: 08/25/2012

  BOYD IRRIGATION INC                              Phone: 239-543-1616
   8050 BAYSHORE RD                                Fax:   239-543-4676
  NORTH FT MYERS FL 33917                          Vendor:115895       SBE: X
  Email : JBOYD@BOYDIRRIGATION.COM
  Cert.Valid From Date: 12/04/2008               Cert.Valid To Date: 12/04/2011

  BOYS ENGRG II INC                                Phone: 786-639-0689
   2625 W 78TH ST STE 2                            Fax:   786-639-0690
  HIALEAH FL 33016                                 Vendor:117076       SBE: Y
  Email : BOYSENGINEERING@AOL.COM
  Cert.Valid From Date: 10/23/2009               Cert.Valid To Date: 10/23/2012

  BPC GRP INC                                      Phone: 561-514-3011
   1201 BELVEDERE RD STE B                         Fax:   561-514-3061
  WEST PALM BEACH FL 33405                         Vendor:101876       SBE: U
  Email : BPANIGRAHI@BPCGI.COM
  Cert.Valid From Date: 12/19/2006               Cert.Valid To Date: 12/18/2009

  BPC GRP INC                                      Phone: 407-851-5020
   6925 LAKE ELLENOR DR STE 112                    Fax:   407-857-3154
  ORLANDO FL 32809                                 Vendor:114488       SBE: U
  Email : BPANIGRAHI@BPCGI.COM
  Cert.Valid From Date: 12/18/2006               Cert.Valid To Date: 12/18/2009

  BRI SAND FORMING CO INC                          Phone: 561-333-3676
   8233 GATOR LN #25                               Fax:   561-333-3675
  WEST PALM BEACH FL 33411                         Vendor:115708       SBE: Y
  Email : BRISANDFORMING@AOL.COM
  Cert.Valid From Date: 10/20/2008               Cert.Valid To Date: 10/20/2011

  CALLAWAY MARINE TECHLGYS INC                     Phone: 561-471-1771
   2765 VISTA PKWY N BLDG H4                       Fax:   561-471-1793
  WEST PALM BEACH FL 33411                         Vendor:103754       SBE: Y
  Email : CMARINET@GATE.NET
  Cert.Valid From Date: 12/19/2006               Cert.Valid To Date: 12/18/2009
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   47

  CAN CONSTRCTN INC                                Phone: 863-674-1002
   1080 COMMERCE DR BLDG 1                         Fax:   863-674-1003
  LA BELLE FL 33935                                Vendor:108790       SBE: Y
  Email : CANCONSTRUCTION@EMBARQMAIL.COM
  Cert.Valid From Date: 10/14/2009               Cert.Valid To Date: 10/14/2012

  CARROLL BROTHERS CONSTRCTN INC                   Phone: 561-684-7484
   PO BOX 18408                                    Fax:   561-684-6498
  WEST PALM BEACH FL 33406                         Vendor:101050       SBE: Y
  Email :
  Cert.Valid From Date: 04/24/2008               Cert.Valid To Date: 04/23/2011

  CASTCO CONSTRCTN INC                             Phone: 727-585-4714
   9001 126TH AVE N                                Fax:   727-585-5091
  LARGO FL 33773                                   Vendor:104074       SBE: V
  Email : CCONSTR@TAMPABAY.RR.COM
  Cert.Valid From Date: 07/21/2009               Cert.Valid To Date: 07/21/2012

  CDL EARTH MOVING & PAVING CORP                   Phone: 561-791-8271
   7655 ENTERPRISE DR #A3                          Fax:   561-791-8273
  WEST PALM BEACH FL 33404                         Vendor:115333       SBE: Y
  Email : CDLEARTHMOVING@BELLSOUTH.NET
  Cert.Valid From Date: 06/26/2008               Cert.Valid To Date: 06/25/2011

  CEB CONSTRCTN INC                                Phone: 786-331-9499
   2451 NW 109TH AVE UNIT 4                        Fax:   305-591-4084
  MIAMI FL 33172                                   Vendor:110206       SBE: Y
  Email : CEB@CEBENGINEERING.COM
  Cert.Valid From Date: 07/25/2008               Cert.Valid To Date: 07/24/2011

  CHESTERFIELD PROPERTIES INC                      Phone: 407-650-9964
   601 N MAGNOLIA AVE STE 300                      Fax:   407-470-1400
  ORLANDO FL 32801                                 Vendor:109118       SBE: V
  Email : RLAPORTE@LIQUIDGRASS.NET
  Cert.Valid From Date: 03/20/2007               Cert.Valid To Date: 03/19/2010

  CHRISTO INC                                      Phone: 239-997-2823
   4461B HANCOCK BRIDGE PKWY                       Fax:   239-997-4672
  NORTH FT MYERS FL 33903                          Vendor:117006       SBE: Y
  Email : BOB.CHRISTO@SPIRITEDBB.NET
  Cert.Valid From Date: 09/24/2009               Cert.Valid To Date: 09/24/2012

  CLARYS SITEWORK & DEV INC                        Phone: 239-997-4004
   4461A HANCOCK BRIDGE PKWY                       Fax:   239-997-0411
  NORTH FT MYERS FL 33903                          Vendor:110497       SBE: Y
  Email : JLCLARY@CLARYSITEWORK.COM
  Cert.Valid From Date: 08/12/2009               Cert.Valid To Date: 08/12/2012

  COASTAL ENGRG CONSULTANTS INC                    Phone: 239-643-2324
   3106 S HORSESHOE DR                             Fax:   239-643-4364
  NAPLES FL 34104                                  Vendor:102040       SBE: Y
  Email : KTAYLOR@CECIFL.COM
  Cert.Valid From Date: 12/12/2006               Cert.Valid To Date: 12/11/2009

  COASTAL GUNITE CONSTRCTN CO                      Phone: 941-744-5500
   1001 3RD AVE STE 320                            Fax:   941-744-9880
  BRADENTON FL 34205                               Vendor:102707       SBE: Y
  Email : CURT@COASTALGUNITE.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   48

  Cert.Valid From Date: 01/07/2009               Cert.Valid To Date: 01/07/2012

  COASTAL MARINE CONSTRCTN INC                     Phone: 941-485-2101
   625 N TAMIAMI TRL                               Fax:   941-488-0164
  VENICE FL 34285                                  Vendor:100139       SBE: Y
  Email : JIM@COASTALMARINECONSTRUCTION.COM
  Cert.Valid From Date: 03/27/2007               Cert.Valid To Date: 03/26/2010

  COMPLETE SITEWORK SVCS LLC                      Phone: 478-273-9396
   112 E JOHNSON ST                               Fax:   478-273-3443
  DUBLIN GA 31021                                 Vendor:117121       SBE: Y
  Email : STEPHANIE.PHILLIPS@GRAHAMCOMPANIES.US
  Cert.Valid From Date: 10/23/2009              Cert.Valid To Date: 10/23/2012

  CONSTRCTN TECHLGY INC                            Phone: 561-882-9696
   PO BOX 16576                                    Fax:   561-882-9697
  WEST PALM BEACH FL 33416                         Vendor:100067       SBE: Y
  Email : CONTECH@BELLSOUTH.NET
  Cert.Valid From Date: 05/24/2007               Cert.Valid To Date: 05/23/2010

  CONTRACT SITE SVCS INC                           Phone: 561-793-4655
   1331 WYNDCLIFF DR                               Fax:   561-753-6947
  WELLINGTON FL 33414                              Vendor:101466       SBE: X
  Email : LTB21958@AOL.COM
  Cert.Valid From Date: 10/11/2006               Cert.Valid To Date: 10/10/2009

  CORE CONSTRCTN GRP INC                           Phone: 321-229-2179
   1126 S DIVISION AVE STE C                       Fax:   407-428-9584
  ORLANDO FL 32805                                 Vendor:117115       SBE: Y
  Email : CCGIF@YAHOO.COM
  Cert.Valid From Date: 10/22/2009               Cert.Valid To Date: 10/22/2012

  CURRENT CONNECTIONS INC                          Phone: 561-863-0010
   1620 HILL AVE                                   Fax:   561-863-5380
  MANGONIA PARK FL 33407                           Vendor:101025       SBE: Y
  Email : DON@CURRENTCONNECTIONS.NET
  Cert.Valid From Date: 03/24/2007               Cert.Valid To Date: 03/23/2010

  D R SWANSON CO                                   Phone: 941-629-8822
   1720 EL JOBEAN RD                               Fax:   941-629-8846
  PRT CHARLOTTE FL 33948                           Vendor:114587       SBE: Y
  Email : SWANSON82@COMCAST.NET
  Cert.Valid From Date: 10/25/2007               Cert.Valid To Date: 10/24/2010

  D&J MACHINERY INC                                Phone: 863-983-3171
   728 E TRINIDAD AVE                              Fax:   863-983-6508
  CLEWISTON FL 33440                               Vendor:101024       SBE: Y
  Email :
  Cert.Valid From Date: 10/16/2009               Cert.Valid To Date: 10/16/2012

  DAWSON GRP LLC                                   Phone: 808-630-9169
   3375 KOAPAKA ST B200                            Fax:   808-536-5530
  HONOLULU HI 96819                                Vendor:113680       SBE: W
  Email : DSMITH@DAWSON8A.COM
  Cert.Valid From Date: 07/03/2007               Cert.Valid To Date: 07/02/2010
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   49

  DENSON CONSTRCTN INC                             Phone: 863-709-1001
   PO BOX 3081                                     Fax:   863-709-1071
  PLANT CITY FL 33564                              Vendor:113117       SBE: T
  Email : PETE@DENSON-CONSTRUCTION.COM
  Cert.Valid From Date: 01/11/2007               Cert.Valid To Date: 01/10/2010

  DEV COMM GRP OF FLORIDA                          Phone: 305-596-0611
   PO BOX 160178                                   Fax:   305-596-0615
  MIAMI FL 33116                                   Vendor:105285       SBE: Y
  Email : DEVELOPMENTFL@AOL.COM
  Cert.Valid From Date: 01/24/2007               Cert.Valid To Date: 01/23/2010

  DR ROGERS INC                                    Phone: 863-674-5799
   50 N SR 29                                      Fax:   863-674-5798
  FELDA FL 33930                                   Vendor:107355       SBE: Y
  Email : SCOTT.ROGERS@DRROGERSINC.COM
  Cert.Valid From Date: 01/31/2007               Cert.Valid To Date: 01/30/2010

  DRD ENTERPRISES INC OF DAVIE                     Phone: 954-370-7944
   858 NW 81ST TER                                 Fax:   954-337-2837
  FT LAUDERDALE FL 33324                           Vendor:106850       SBE: Y
  Email : LUNARCON@AOL.COM
  Cert.Valid From Date: 02/13/2007               Cert.Valid To Date: 02/12/2010

  EDENS CONSTRCTN CO INC                           Phone: 561-996-6822
   745 NW 2ND ST                                   Fax:   561-996-4502
  SOUTH BAY FL 33493                               Vendor:100354       SBE: Y
  Email : EDENSBT@AOL.COM
  Cert.Valid From Date: 07/15/2009               Cert.Valid To Date: 07/15/2012

  ENGINEER CONTROL SYSTS CORP                      Phone: 305-895-4376
   1175 NE 125TH ST STE 316                        Fax:   305-895-0019
  NORTH MIAMI FL 33161                             Vendor:101546       SBE: Y
  Email : ECSCONSTRUCTION@HOTMAIL.COM
  Cert.Valid From Date: 07/19/2008               Cert.Valid To Date: 07/18/2011

  ENGRG & APPLIED SCIENCE INC                      Phone: 813-899-0707
   13087 TELECOM PKWY N                            Fax:   813-899-0366
  TAMPA FL 33637                                   Vendor:101705       SBE: U
  Email : EAS@EASTAMPA.COM
  Cert.Valid From Date: 09/28/2009               Cert.Valid To Date: 09/28/2012

  ENVIRO TECH SYSTS INC                            Phone: 863-763-3143
   2308 S PARROTT AVE                              Fax:   863-763-1309
  OKEECHOBEE FL 34974                              Vendor:114702       SBE: Y
  Email : ROYBL@ENVIRO-TECH.CC
  Cert.Valid From Date: 11/30/2007               Cert.Valid To Date: 11/29/2010

  ENVIRON & MARINE CONSTRCTN SVCS                  Phone: 386-339-5304
   2773 DATE PALM DR                               Fax:   386-427-3396
  EDGEWATER FL 32141                               Vendor:113923       SBE: Y
  Email : JEFF@EMCDIVERS.COM
  Cert.Valid From Date: 01/23/2008               Cert.Valid To Date: 01/22/2011

  ENVIRON LAND DEV INC                             Phone: 772-519-6278
   6381 PETERSON RD                                Fax:   772-462-2208
  FT PIERCE FL 34947                               Vendor:115599       SBE: Y
  Email : ELDINC2004@GMAIL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   50

  Cert.Valid From Date: 04/07/2009               Cert.Valid To Date: 04/07/2012

  EROSION RESTORATION LLC                          Phone: 954-327-3300
   2200 SW 14TH ST                                 Fax:   954-327-8242
  FT LAUDERDALE FL 33312                           Vendor:114304       SBE: Y
  Email : ANDRE@EROSIONRESTORATION.COM
  Cert.Valid From Date: 09/12/2007               Cert.Valid To Date: 09/11/2010

  FARMERS MFG CO INC                               Phone: 954-946-3066
   911 E ATLANTIC BLVD STE 107                     Fax:   954-946-3111
  POMPANO BEACH FL 33060                           Vendor:100133       SBE: Y
  Email :
  Cert.Valid From Date: 01/27/2007               Cert.Valid To Date: 01/26/2010

  FLAVE A WILLIAMS III DOZER SVC INC              Phone: 727-856-3765
   14717 HAYS RD                                  Fax:   727-856-6298
  SPRING HILL FL 34610                            Vendor:116481       SBE: X
  Email : NWILLIAMS@FLAVEWILLIAMSDOZERSERVICE.COM
  Cert.Valid From Date: 04/27/2009              Cert.Valid To Date: 04/27/2012

  FOREST HILL CONSTRCTN CO INC                     Phone: 561-790-2300
   17546 BEE LINE HWY                              Fax:   561-799-5650
  JUPITER FL 33458                                 Vendor:100321       SBE: Y
  Email : FORESTHILL@EARTHLINK.NET
  Cert.Valid From Date: 02/02/2007               Cert.Valid To Date: 02/01/2010

  GATOR GRADING & EXCAVATING LLC                   Phone: 561-881-5512
   1880W 10TH ST STE 104                           Fax:   561-881-5612
  RIVERIA BEACH FL 33404                           Vendor:109558       SBE: X
  Email : HBC314@YAHOO.COM
  Cert.Valid From Date: 06/30/2009               Cert.Valid To Date: 06/30/2012

  GE DEV OF SO FLA INC                             Phone: 954-252-8500
   5201 THOROUGHBRED LN                            Fax:   954-252-1259
  SOUTHWEST RANCHES FL 33330                       Vendor:116886       SBE: Y
  Email : GE.DEVELOPMENT@YAHOO.COM
  Cert.Valid From Date: 08/11/2009               Cert.Valid To Date: 08/11/2012

  GULF GRP INC                                     Phone: 850-258-3545
   7402 HWY 2302                                   Fax:   850-769-6175
  SOUTHPORT FL 32409                               Vendor:100789       SBE: Y
  Email : SAM@GULFGROUP.COM
  Cert.Valid From Date: 10/30/2008               Cert.Valid To Date: 10/30/2011

  GUTHOY BUILDERS INC                              Phone: 305-216-4912
   11276 NW 160TH CT                               Fax:   305-974-0284
  MIAMI FL 33196                                   Vendor:116096       SBE: Y
  Email : GUTHOY@BELLSOUTH.NET
  Cert.Valid From Date: 01/27/2009               Cert.Valid To Date: 01/27/2012

  HASKINS INC                                      Phone: 239-947-1846
   10956 ENTERPRISE AVE                            Fax:   239-947-3857
  BONITA SPRINGS FL 33923                          Vendor:100691       SBE: Y
  Email : JCHAMBERS@HASKINSINC.NET
  Cert.Valid From Date: 09/24/2009               Cert.Valid To Date: 09/24/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   51

  HECOL LLC                                        Phone: 786-367-2766
   12179 SW 132ND CT                               Fax:   786-573-4156
  MIAMI FL 33186                                   Vendor:113986       SBE: V
  Email : HECOLLLC@BELLSOUTH.NET
  Cert.Valid From Date: 05/17/2007               Cert.Valid To Date: 05/16/2010

  HERRINGTON BRADLEY CONSTRCTN INC                 Phone: 305-652-8848
   14825 NW 16 DR                                  Fax:
  MIAMI FL 33167                                   Vendor:102770       SBE: T
  Email :
  Cert.Valid From Date: 10/30/2008               Cert.Valid To Date: 10/30/2011

  HOMESTEAD CONCRETE & DRAINAGE INC                Phone: 305-248-9649
   PO BOX 1273                                     Fax:   305-248-9650
  HOMESTEAD FL 33090                               Vendor:102158       SBE: V
  Email : ACORDERO@HOMESTEADCONCRETE.COM
  Cert.Valid From Date: 06/16/2009               Cert.Valid To Date: 06/16/2012

  HP CONSULTANTS INC                               Phone: 305-775-4300
   10220 SW 107TH ST                               Fax:   305-596-2857
  MIAMI FL 33176                                   Vendor:108188       SBE: U
  Email : HPCONSULTANTSINC@EARTHLINK.NET
  Cert.Valid From Date: 08/28/2009               Cert.Valid To Date: 08/28/2012

  IICON CONTRACTORS CORP                           Phone: 305-245-1700
   123 N KROME AVE STE 206                         Fax:   305-245-7200
  HOMESTEAD FL 33030                               Vendor:110501       SBE: V
  Email : IAN.IGLESIAS@IICONCONTRACTORS.COM
  Cert.Valid From Date: 09/14/2009               Cert.Valid To Date: 09/14/2012

  INLAND CONSTRCTN & EQUIP SV                      Phone: 850-872-2129
   309 E 11TH ST                                   Fax:   850-872-0532
  PANAMA CITY FL 32401                             Vendor:104954       SBE: W
  Email : INLANDEQUIPMENT@HOTMAIL.COM
  Cert.Valid From Date: 02/28/2007               Cert.Valid To Date: 02/27/2010

  INTERLAKEN INC                                   Phone: 561-582-4651
   1960 S OCEAN BLVD                               Fax:   954-767-1081
  MANALAPAN FL 33462-6219                          Vendor:107252       SBE: Y
  Email : TKEEN@INTERLAKEN.BZ
  Cert.Valid From Date: 12/07/2006               Cert.Valid To Date: 12/06/2009

  JAKES WELDING LLC                                Phone: 941-763-2735
   9053 SE 67TH WAY                                Fax:   863-763-9385
  OKEECHOBEE FL 34974                              Vendor:103417       SBE: Y
  Email : STREELY@EMBARGMAIL.COM
  Cert.Valid From Date: 08/07/2007               Cert.Valid To Date: 08/06/2010

  JAMERICA CONCRETE SVCS CORP                      Phone: 561-902-1766
   PO BOX 596                                      Fax:   561-902-1152
  CANAL POINT FL 33438                             Vendor:114735       SBE: T
  Email : STALBION@AOL.COM
  Cert.Valid From Date: 11/27/2007               Cert.Valid To Date: 11/26/2010

  JE CLEARING & DEVELOPING                         Phone: 863-634-6867
   8000 NW 240TH ST                                Fax:   863-467-7082
  OKEECHOBEE FL 34972                              Vendor:111117       SBE: Y
  Email : JEDEVELOPING@HOTMAIL.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   52

  Cert.Valid From Date: 06/19/2007               Cert.Valid To Date: 06/18/2010

  JEFF DOUGLAS ENTERPRISES INC                     Phone: 863-634-7416
   14151 US HWY 441 SE                             Fax:   863-763-4945
  OKEECHOBEE FL 34974                              Vendor:116419       SBE: Y
  Email : JDEI@LIVE.COM
  Cert.Valid From Date: 04/14/2009               Cert.Valid To Date: 04/14/2012

  JONES CO OF SOUTH FLORIDA INC THE                Phone: 954-583-7300
   3784 NW 16TH ST                                 Fax:   954-730-9000
  LAUDERHILL FL 33311                              Vendor:103851       SBE: T
  Email : LANSINGJROCK@AOL.COM
  Cert.Valid From Date: 09/15/2006               Cert.Valid To Date: 09/14/2009

  JP MURPHY INC                                    Phone: 239-415-4001
   16751 OLD US 41                                 Fax:   239-432-2654
  FT MYERS FL 33912                                Vendor:108954       SBE: Y
  Email : JIM@JPMURPHYINC.COM
  Cert.Valid From Date: 12/08/2008               Cert.Valid To Date: 12/08/2011

  JVA ENGRG CONTRACTOR INC                         Phone: 305-696-7902
   6600 NW 32ND AVE                                Fax:   305-696-7903
  MIAMI FL 33147                                   Vendor:114998       SBE: V
  Email : JMA@JVAENGINEERING.COM
  Cert.Valid From Date: 03/06/2008               Cert.Valid To Date: 03/06/2011

  KBJ DEV SVCS INC                                 Phone: 941-575-4894
   1105 L TAYLOR RD                                Fax:   941-639-4597
  PUNTA GORDA FL 33950                             Vendor:113408       SBE: Y
  Email : GPOWELL1025@EARTHLINK.NET
  Cert.Valid From Date: 02/06/2007               Cert.Valid To Date: 02/05/2010

  KIMBERLY ANN BROWN & ASSOCS                      Phone: 954-567-3497
   2841 N OCEAN BLVD STE 905                       Fax:   954-567-2549
  FT LAUDERDALE FL 33308                           Vendor:105115       SBE: X
  Email : kabainc@bellsouth.net
  Cert.Valid From Date: 06/25/2009               Cert.Valid To Date: 06/25/2012

  KNIGHTS CONSTRCTN INC                            Phone: 772-597-5377
   PO BOX 1968                                     Fax:   772-597-5327
  INDIANTOWN FL 34956                              Vendor:114115       SBE: Y
  Email : KNIGHTSCONST@AOL.COM
  Cert.Valid From Date: 06/12/2007               Cert.Valid To Date: 06/11/2010

  KOMCOR ENTERPRISES INC                           Phone: 561-745-6797
   1530 CYPRESS DR STE B                           Fax:   561-745-6798
  JUPITER FL 33469                                 Vendor:114598       SBE: U
  Email : RKORKES@KOMCORINC.COM
  Cert.Valid From Date: 12/13/2007               Cert.Valid To Date: 12/12/2010

  LAMBERT BROS INC                                 Phone: 954-491-9380
   823 NW 57TH ST                                  Fax:   954-491-9425
  FT LAUDERDALE FL 33309                           Vendor:110218       SBE: Y
  Email : GL@LAMBERTBROS.COM
  Cert.Valid From Date: 10/06/2009               Cert.Valid To Date: 10/06/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   53

  LATONA TRUCKING INC                              Phone: 570-760-6967
   16475 W YORKSHIRE                               Fax:
  LOXAHATCHEE FL 33470                             Vendor:111187       SBE: Y
  Email : BOBRADY52@MSN.COM
  Cert.Valid From Date: 03/23/2007               Cert.Valid To Date: 03/22/2010

  LJ CLARK CONSTRCTN INC                           Phone: 863-946-2438
   335 COUNTY RD 721 LOOP                          Fax:   863-946-2439
  MOORE HAVEN FL 33471                             Vendor:102279       SBE: Y
  Email : LJCLARKCONSTINC@AOL.COM
  Cert.Valid From Date: 07/30/2009               Cert.Valid To Date: 07/30/2012

  LOVIN CONSTRCTN INC                              Phone: 941-755-4312
   6204 33RD ST E                                  Fax:   941-758-7184
  BRADENTON FL 34203                               Vendor:114786       SBE: Y
  Email : LOVIN-CONSTRUCTION@VERIZON.NET
  Cert.Valid From Date: 12/08/2007               Cert.Valid To Date: 12/07/2010

  LUCAS MARINE CONSTRCTN LLC                       Phone: 772-286-5094
   3130 SE SLATER ST                               Fax:   772-286-1139
  STUART FL 34997                                  Vendor:102591       SBE: Y
  Email : WDIEKMAN@LMCLLC.NET
  Cert.Valid From Date: 02/09/2007               Cert.Valid To Date: 02/08/2010

  MAG CONSTRCUCTION INC                            Phone: 305-218-9835
   7812 SW 34TH TER                                Fax:   305-263-9369
  MIAMI FL 33155                                   Vendor:112624       SBE: V
  Email : MAGCON@BELLSOUTH.NET
  Cert.Valid From Date: 11/04/2006               Cert.Valid To Date: 11/03/2009

  MAXON GROUPE LLC                                 Phone: 305-710-8666
   4218 NE 2ND AVE 2ND FL                          Fax:   305-868-7887
  MIAMI FL 33137                                   Vendor:115638       SBE: Y
  Email : WILLIAM@MAXONGROUPE.COM
  Cert.Valid From Date: 09/26/2008               Cert.Valid To Date: 09/25/2011

  MERICO INC                                       Phone: 863-634-7725
   8606 SW 2ND ST                                  Fax:   863-763-0952
  OKEECHOBEE FL 34974                              Vendor:110194       SBE: Y
  Email : ERUCKS@EMBARQMAIL.COM
  Cert.Valid From Date: 07/21/2009               Cert.Valid To Date: 07/21/2012

  MGI MORGAN GENERAL MECHANICAL GRP                Phone: 954-360-9803
   1128 S POWERLINE RD                             Fax:
  DEERFIELD BEACH FL 33442                         Vendor:102007       SBE: Y
  Email : DMORGAN@MGI-MORGAN.COM
  Cert.Valid From Date: 03/07/2008               Cert.Valid To Date: 03/07/2011

  MIAMI BEACH SEAWALLS INC                         Phone: 305-945-2114
   17027 W DIXIE HWY STE 127                       Fax:   305-945-2329
  N MIAMI BEACH FL 33160                           Vendor:115732       SBE: Y
  Email : SEAWALLC@BELLSOUTH.NET
  Cert.Valid From Date: 11/04/2008               Cert.Valid To Date: 11/04/2011

  MILIAN SWAIN & ASSOCS INC                        Phone: 305-441-0123
   2025 SW 32ND AVE                                Fax:   305-441-0688
  MIAMI FL 33145                                   Vendor:100672       SBE: V
  Email : AMILIAN@MILIANSWAIN.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   54

  Cert.Valid From Date: 06/12/2009               Cert.Valid To Date: 06/12/2012

  MSE SYSTS INC                                    Phone: 407-931-1221
   603 VERONA ST                                   Fax:   407-931-1222
  KISSIMMEE FL 34741                               Vendor:101950       SBE: V
  Email : MSESYS@AOL.COM
  Cert.Valid From Date: 07/03/2007               Cert.Valid To Date: 07/02/2010

  MTW SVCS INC                                     Phone: 863-673-8864
   13261 ROLLING GREEN RD                          Fax:   561-625-1781
  NORTH PALM BEACH FL 33408                        Vendor:112671       SBE: Y
  Email : MTWSERVICES@AOL.COM
  Cert.Valid From Date: 03/10/2007               Cert.Valid To Date: 03/09/2010

  MUZZIN BROTHERS INC                              Phone: 772-334-9506
   3552 NE CANDICE AVE                             Fax:   772-334-9509
  JENSEN BEACH FL 34957                            Vendor:116016       SBE: Y
  Email : MBI79@BELLSOUTH.NET
  Cert.Valid From Date: 02/20/2009               Cert.Valid To Date: 02/20/2012

  NAC CONSTRCTN INC                                Phone: 305-412-2275
   9065 SW 87TH AVE STE 112                        Fax:   305-412-2278
  MIAMI FL 33176                                   Vendor:114114       SBE: Y
  Email : NESTORCASTELLON@NACCONST.COM
  Cert.Valid From Date: 06/08/2007               Cert.Valid To Date: 06/07/2010

  NATIVE POWER INC                                 Phone: 772-785-9795
   769 SW MONSOON RD                               Fax:   772-343-1133
  PRT ST LUCIE FL 34953                            Vendor:112210       SBE: Y
  Email : NATIVEPOWERINC@YAHOO.COM
  Cert.Valid From Date: 12/02/2006               Cert.Valid To Date: 12/01/2009

  NATIVE TECHLGYS INC                              Phone: 954-596-2411
   814 S MILITARY TRL                              Fax:   954-480-6249
  DEERFIELD BEACH FL 33442                         Vendor:101929       SBE: Y
  Email : RMILLER@WETLANDSBANK.COM
  Cert.Valid From Date: 02/08/2007               Cert.Valid To Date: 02/07/2010

  OCEAN BREEZE CONSTRCTN CO INC                    Phone: 561-624-1020
   PO BOX 30459                                    Fax:   561-624-1464
  PALM BEACH GARDENS FL 33420                      Vendor:100464       SBE: Y
  Email : OBCHACKETT@EARTHLINK.NET
  Cert.Valid From Date: 07/25/2008               Cert.Valid To Date: 07/24/2011

  OPTIMUM SVCS INC                                 Phone: 863-467-2572
   208 N PARROTT AVE                               Fax:   863-467-8067
  OKEECHOBEE FL 34972                              Vendor:103595       SBE: Y
  Email : REVANS@OPTSVC.COM
  Cert.Valid From Date: 03/13/2007               Cert.Valid To Date: 03/12/2010

  OVERLAND CONSTRCTN CO INC                        Phone: 561-683-3210
   1360 W 53RD ST                                  Fax:   561-683-3219
  WEST PALM BEACH FL 33407                         Vendor:104741       SBE: Y
  Email : OVERLANDCONST@AOL.COM
  Cert.Valid From Date: 03/14/2007               Cert.Valid To Date: 03/13/2010
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   55

  PALM BEACH MARINE CONST INC                      Phone: 561-588-7690
   1410 FORSYTHE RD                                Fax:   561-697-3238
  W PALM BEACH FL 33405                            Vendor:110312       SBE: V
  Email : SARAH@PBMCINC.COM
  Cert.Valid From Date: 02/07/2007               Cert.Valid To Date: 02/06/2010

  POWELL KUGLER INC                                Phone: 561-820-4891
   500 S AUSTRALIAN AVE STE 600                    Fax:   561-651-4110
  WEST PALM BEACH FL 33401                         Vendor:108401       SBE: T
  Email : POWELLKUGLER@HOTMAIL.COM
  Cert.Valid From Date: 07/01/2009               Cert.Valid To Date: 07/01/2012

  PRINCIPLE DESIGN & DEV LLC                       Phone: 561-533-5252
   3401 S CONGRESS AVE STES 200-205                Fax:   561-533-5724
  PALM SPRINGS FL 33461                            Vendor:110509       SBE: Y
  Email : DNACATOLA@PRINCIPLEDD.COM
  Cert.Valid From Date: 12/02/2006               Cert.Valid To Date: 12/01/2009

  QUALIFIED BUILDERS INC                           Phone: 863-697-0184
   PO BOX 3200                                     Fax:   863-824-8711
  OKEECHOBEE FL 34973                              Vendor:116304       SBE: Y
  Email :
  Cert.Valid From Date: 03/25/2009               Cert.Valid To Date: 03/25/2012

  R2T INC                                          Phone: 561-265-3485
   310 SE FIRST ST STE 2                           Fax:   561-265-3485
  DELRAY BEACH FL 33483                            Vendor:112912       SBE: T
  Email : KIM.AJY@R2TINC.COM
  Cert.Valid From Date: 12/02/2006               Cert.Valid To Date: 12/01/2009

  RCS EXCAVATION INC                               Phone: 863-441-9385
   1155 NW 160TH ST                                Fax:   863-592-9292
  OKEECHOBEE FL 34972                              Vendor:114289       SBE: Y
  Email : RCSEXCAVATION@AOL.COM
  Cert.Valid From Date: 11/08/2007               Cert.Valid To Date: 11/08/2010

  RJR CONSTRCTN INC                                Phone: 305-244-1837
   7025 SW 19TH TER                                Fax:   305-267-1899
  MIAMI FL 33155                                   Vendor:100197       SBE: V
  Email : RJRCONST@BELLSOUTH.NET
  Cert.Valid From Date: 11/17/2008               Cert.Valid To Date: 11/17/2011

  ROCK ENTERPRISES INC                             Phone: 863-612-0011
   180 N BRIDGE ST STE B                           Fax:   863-612-0014
  LABELLE FL 33935                                 Vendor:117068       SBE: Y
  Email : ROCK@ROCKHENDRY.COM
  Cert.Valid From Date: 10/20/2009               Cert.Valid To Date: 10/20/2012

  RS CONSTRCTN OF SOUTHWEST FLORIDA                Phone: 941-628-6407
   7173 SW CR 769                                  Fax:   941-235-3624
  ARCADIA FL 34269                                 Vendor:115949       SBE: Y
  Email : FRAN-RAY@COMCAST.NET
  Cert.Valid From Date: 01/06/2009               Cert.Valid To Date: 01/06/2012

  S GROUP INC                                      Phone: 561-688-2295
   1470 N CONGRESS AVE STE 119                     Fax:   561-688-2298
  WEST PALM BEACH FL 33409                         Vendor:114695       SBE: V
  Email : MSANCHEZ@SGROUPINC.NET
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   56

  Cert.Valid From Date: 11/09/2007               Cert.Valid To Date: 11/08/2010

  SEARCH SURVEY & RECOVERY INC                     Phone: 772-781-1234
   2853 SE ST LUCIE BLVD                           Fax:   772-781-0103
  STUART FL 34997-5419                             Vendor:102115       SBE: X
  Email :
  Cert.Valid From Date: 01/10/2007               Cert.Valid To Date: 01/09/2010

  SEMINOLE DESIGN BUILD INC                        Phone: 863-763-9888
   PO BOX 2567                                     Fax:   863-467-0610
  OKEECHOBEE FL 34973                              Vendor:104714       SBE: W
  Email : NUNEZD3@EARTHLINK.NET
  Cert.Valid From Date: 01/31/2007               Cert.Valid To Date: 01/30/2011

  SHORELINE SEAWALL INC                            Phone: 863-634-3189
   3826 US HWY 441 SE                              Fax:   772-673-0362
  OKEECHOBEE FL 34974                              Vendor:113424       SBE: Y
  Email : SHORELINESEAWALL@YAHOO.COM
  Cert.Valid From Date: 01/07/2009               Cert.Valid To Date: 01/07/2012

  SOUTHERN GENERAL CONSTRCTN LLC                   Phone: 863-673-9339
   911 GRATTON RD                                  Fax:   863-983-9217
  CLEWISTON FL 33440                               Vendor:114494       SBE: Y
  Email : SOUTHERNGENCONST@GMAIL.COM
  Cert.Valid From Date: 01/16/2008               Cert.Valid To Date: 01/15/2011

  T&E GRP INC                                      Phone: 786-486-4280
   8720 SW 82ND ST                                 Fax:   305-274-9754
  MIAMI FL 33173                                   Vendor:114037       SBE: Y
  Email : CLAIMADJUSTERS@GMAIL.COM
  Cert.Valid From Date: 05/30/2007               Cert.Valid To Date: 05/29/2010

  TAMPA CONTRACTING SVCS INC                       Phone: 941-721-7711
   11010 US HWY 41 N                               Fax:   941-721-7733
  PALMETTO FL 34221                                Vendor:116171       SBE: Y
  Email : TCSGCL@VERIZON.NET
  Cert.Valid From Date: 02/20/2009               Cert.Valid To Date: 02/20/2012

  TAYLOR LAND DEV INC                              Phone: 561-792-2818
   17145 69TH ST N                                 Fax:   561-792-1965
  LOXAHATCHEE FL 33470                             Vendor:104364       SBE: Y
  Email : RTAYLOR50@BELLSOUTH.NET
  Cert.Valid From Date: 02/17/2007               Cert.Valid To Date: 02/16/2010

  TM RUSSELL CONTRACTING INC                       Phone: 561-881-8005
   210 BRANT RD BLDG E                             Fax:   561-881-8020
  LAKE PARK FL 33403                               Vendor:115354       SBE: X
  Email : RUSSELL1@BELLSOUTH.NET
  Cert.Valid From Date: 03/02/2009               Cert.Valid To Date: 03/02/2012

  TMD CONSTRCTN CO                                 Phone: 239-340-8526
   4610 ELEVATION WAY STE C                        Fax:   239-337-9383
  FT MYERS FL 33905                                Vendor:108202       SBE: Y
  Email : DILLONT@TMD-CO.COM
  Cert.Valid From Date: 03/07/2007               Cert.Valid To Date: 03/06/2010
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   57

  TRANSAMERICA CONSTRCTN CO                        Phone: 305-572-9551
   234 NE 34TH ST                                  Fax:   305-572-9552
  MIAMI FL 33137                                   Vendor:114127       SBE: V
  Email : EMERSON@TRANSAMERICACONSTRUCTION.COM
  Cert.Valid From Date: 06/13/2007               Cert.Valid To Date: 06/12/2010

  UNDERWATER SVCS INC                              Phone: 305-652-1410
   600 NE 185TH ST                                 Fax:   305-652-1917
  MIAMI FL 33179                                   Vendor:109493       SBE: W
  Email : usi@underwaterservicesusi.com
  Cert.Valid From Date: 07/18/2007               Cert.Valid To Date: 07/17/2010

  VAN LINDA IRON WORKS INC                         Phone: 561-586-8400
   3787 BOUTWELL RD                                Fax:   561-586-8877
  LAKE WORTH FL 33461                              Vendor:103236       SBE: Y
  Email : TVANLINDA@VANLINDAIRONWORKS.COM
  Cert.Valid From Date: 12/17/2007               Cert.Valid To Date: 12/17/2010

  VANCE CONSTRCTN CO THE                           Phone: 561-650-0016
   PO BOX 4592                                     Fax:   561-650-8147
  WEST PALM BEACH FL 33402                         Vendor:113099       SBE: Y
  Email : VANCECOCJ@AOL.COM
  Cert.Valid From Date: 02/20/2009               Cert.Valid To Date: 02/20/2012

  VIKING DIVING SVCS INC                           Phone: 772-460-6710
   PO BOX 9487                                     Fax:   772-607-7200
  PRT ST LUCIE FL 34985                            Vendor:114589       SBE: Y
  Email : THOR@VIKINGDIVINGSERVICES.COM
  Cert.Valid From Date: 12/15/2007               Cert.Valid To Date: 12/14/2010

  WBI CONTRACTING & SVC INC                        Phone: 561-640-5540
   2415 CECEILE AVE                                Fax:   561-697-8329
  WEST PALM BEACH FL 33417                         Vendor:106018       SBE: V
  Email : WBICONTRACTING@GMAIL.COM
  Cert.Valid From Date: 07/07/2009               Cert.Valid To Date: 07/07/2012

  WILKINSON & JENKINS CONSTRCTN CO                 Phone: 727-527-9440
   PO BOX 530097                                   Fax:
  ST PETERSBURG FL 33747-0097                      Vendor:101103       SBE: Y
  Email :
  Cert.Valid From Date: 03/07/2007               Cert.Valid To Date: 03/06/2010

  WORTH CONTRACTING INC                            Phone: 904-396-6363
   2112 JERNIGAN RD                                Fax:   904-396-1888
  JACKSONVILLE FL 32207                            Vendor:101638       SBE: X
  Email : WCI@WORTHCONTRACTINGINC.COM
  Cert.Valid From Date: 03/01/2007               Cert.Valid To Date: 02/28/2010

  WRANGLER CONSTRCTN INC                           Phone: 305-278-4719
   12855 SW 136TH AVE                              Fax:   305-278-4720
  MIAMI FL 33186                                   Vendor:114129       SBE: V
  Email : RAFA@WRANGLER-CONSTRUCTION.COM
  Cert.Valid From Date: 03/21/2008               Cert.Valid To Date: 03/20/2011

  WRIGHTS EXCAVATING INC                           Phone: 407-892-1070
   917 13TH ST                                     Fax:   407-892-7007
  ST CLOUD FL 34769                                Vendor:110352       SBE: Y
  Email : ESTIMATES@WRIGTHSINC.COM
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                       Page No #.   58

  Cert.Valid From Date: 09/15/2009               Cert.Valid To Date: 09/15/2012

  ZFI ENGRG & CONSTRCTN INC                        Phone: 407-281-1100
   651 DANVILLE DR STE 100                         Fax:   407-281-1108
  ORLANDO FL 32825                                 Vendor:104097       SBE: U
  Email : GENERAL@ZF-INC.COM
  Cert.Valid From Date: 09/01/2009               Cert.Valid To Date: 09/01/2012
                   SOUTH FLORIDA WATER MANAGEMENT DISTRICT
                            PROCUREMENT DEPARTMENT
                              Detail Vendor list

Tuesday,November 03,2009                                     Page No #.   59

  Classification Description

  A    Dist Certified_Asian
  B    Dist Certified_Afric
  C    Small Business-Distr
  D    Non-Minority
  F    Dist Certified_Woman
  G    Small Business - Sta
  H    Dist Certified_Hispa
  I    Dist Non-Certified_A
  J    Dist Non-Certified_H
  K    Dist Non-Certified_A
  L    Dist Non-Certified_N
  M    Dist Non-Certified_W
  N    Dist Certified_Nativ
  O    Small Business - Fed
  P    > 51% Minority Board
  Q    > 51% Minority Offic
  R    > 51% Minority Commu
  S    Other Non-Profit
  T    SBE_African
  U    SBE_Asian
  V    SBE_Hispanic
  W    SBE_Native
  X    SBE_Woman
  Y    SBE_Non-Minority

  Selected Classification Description

  T    SBE_African
  U    SBE_Asian
  V    SBE_Hispanic
  W    SBE_Native
  X    SBE_Woman
  Y    SBE_Non-Minority

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:27
posted:2/12/2012
language:
pages:174