a.   Testing Cylinder Compression
     Operate the engine until normal operating temperature is reached. Remove all spark plugs. Set the
     throttle to wide open position and leave it open for the test. Crank the engine with the starter and test
     the compression of each cylinder with a compression gauge.
     The compression of all cylinders should be uniform within 15 pounds.
     A reading of more than 15 pounds above normal indicates carbon or lead deposits in cylinder.
     A reading below normal indicates leakage at the rings, valves, or gaskets.

b.   Tighten Cylinder Head and Manifold
     Compression leaks may be stoped by tightening cylinder head nuts or bolts, providing the heads are
     not warped and the head gasket is in good condition.
     Tighten cylinder head nuts to 50-60 foot-pounds torque.
     Tighten the intake and exhaust manifold bolts and nuts to 25-30 foot-pounds torque.


c.   Clean, Adjust, and Install Spark Plugs
     Sandblast the spark plugs, wipe the porcelain clean, file the electrode tips lightly and adjust the spark
     gap to 0.025. Using a 14 mm spark plug socket, tighten the plug to 24-30 foot-pound torque.

d.   Clean and Inspect Battery Cables
     Remove the cables from the battery. Clean the battery terminals and cable connectors. After
     connecting cables to the battery, cover the terminals and connectors with a film of petrolatum to retard
     further corosion.

e.   Test Generating System
     Have the battery tested. If the battery was low in charge, have the generator and regulator tested.

f.   Clean and Test Distributer
     Clean grease and dirt from the distributor housing, distributor caps, and ignition wires. Have the
     distributor advance tested.

g.   Time Ignition
     Check the initial timing with a distributor timing fixture.(4o B.T.C.); Total Advance 17-19o
     (See "I. Road Test")

h.   Test Spark Intensity
     A quick check on spark intensity can be made with the engine idling. Disconnect one spark plug lead
     at a time and hold it 3/16 inch from the cylinder head. If the spark jumps this gap regularly, it is
     satisfactory.
     If unsatisfactory at all spark plugs, trouble exists in the coil, condenser, rotor, internally in the
     distributor or the external primary circuit.
     If unsatisfactory at some but not all spark plugs, trouble exists with the plug wires.

i.   Check Manifold Vacuum
     Check the manifold vacuum with a vacuum gauge. The vacuum should be 18-21 inches (of mercury)
     with the engine idling.

j.   Clean and Test Fuel Pump
     Remove and clean the fuel pump sediment bowl. Test the fuel pump pressure and vacuum. The
     pressure for a V8 should be 3.5 to 4.5 p.s.i. The vacuum should be 10 inches (of mercury).
     A general check of the pump condition can be made by measuring the amount of fuel it will deliver in
     a definite period of time. At idle speed, the pump should displace one pint in 45 seconds or less.
k.   Clean and Adjust Carburetor
     Wipe off dust and dirt from carburetor.
     For "Dry-Type" air cleaners, wash filter element in kerosine. Re-oil the element with engine oil.
     For" Oil-Bath" air cleaners, clean the oil sump and refill to the level mark with engine oil. DO NOT
     ALLOW THE FELT PAD TO GET OILY.
     Adjust engine idle speed to 475-500 r.p.m.
     Adjust the idle mixture screw in until the engine starts to miss, then back the screw out until it runs
     smoothly. The "97" carburetor has two idle mixture screws. Both must be adjusted to balance the
     engine at idle speed.

l.   Road Test
     After the tune-up is complete, road test the vehicle by accelerating rapidly several times on the
     highway. If the eingine "pings", tighten the vacuum brake on the distributor until the "ping"
     disappears.

     Engine firing order: 1-5-4-8-6-3-7-2
     Breaker Point Spacing: 0.014-0.016 in.
     Breaker Point Spring Tension: 20-24 oz.
     Condenser Capacity: 0.29-0.32 mfd.
     Battery Capacity: 100 amp.
     Generator: 6 volt 30 amp.
     Oil Pan bolts 15-18 foot-pounds torque.
     Fuel Pump push rod length: >8.870 in.

						
Related docs
Other docs by wuzhengqin
be_11_e356_n4126
Views: 0  |  Downloads: 0
Tw o Ind ep e nde nt Sa mples
Views: 2  |  Downloads: 0
Current Semen Centres
Views: 1  |  Downloads: 0
FAQ0004
Views: 0  |  Downloads: 0
time.series.regression
Views: 1  |  Downloads: 0
sources _types_
Views: 34  |  Downloads: 0
REVISI_PENUGASAN_BLOK_II
Views: 27  |  Downloads: 0