                        TYPE OF PROJECT
                              Renovation

                                   OWNER
                     City of Cedar Rapids
                                 Mike Jager
      Veterans Memorial Facilities Manager
                             nd
                         50 2 Ave Bridge
                   Cedar Rapids, IA 52401
                              319-286-5039
                m.jager@cedar-rapids.org

               CONSTRUCTION MANAGER
                   Neumann Brothers, Inc.
                             Josh Braby
                           515-243-0156
                brabyj@neumannbros.com

                                ARCHITECT
             Alt Architecture and Research.

                                       SIZE
                                 110,000 SF

               CONSTRUCTION SCHEDULE
                                               THE CEDAR RAPIDS VETERANS MEMORIAL BUILDING         will be an interior renovation and flood
                July 2011 – November 2012      restoration project broken into three construction phases. The existing building is split into
                 CONSTRUCTION BUDGET*          three “Towers,” or sections, that will be broken out into three separate bid packages. This
                      Total = $22,000,000
                                               building will replace damaged elements from the flood, as well as completely renovate and
                           BID PACKAGES*
Phase I (2nd Ave Tower) - General Contractor   restore the 1st Avenue tower back to it’s original design intent. This project will include
                       Budget* = $7,000,000
        Bid Advertisement Date* = May 2011     restoration of the existing auditorium, a community/ballroom, a café, museum space,
 Phase II (1st Ave Tower) – General Contract   conference centers, meeting rooms, office space, storage space, a fitness center, new
                       Budget* = $8,000,000
      Bid Advertisement Date* = June 2011
                                               mechanical/electrical systems and elevators. The Veterans Memorial Building is the heart
 Phase III (Auditorium) - General Contractor
                                               of the city and will be a gathering place for veterans and all members of the community.
                       Budget* = $7,000,000
 Bid Advertisement Date* = December 2011       Major systems in this facility include:
      PROJECT SPECIFIC REQUIREMENTS
       FEMA Funding – Reporting Required           •    New mechanical, electrical, and fire sprinkler systems.
       IJOBS Funding – Reporting Required
                                                   •    Structural steel roof support and a two-story addition in the auditorium.
                                                   •    New stand alone precast generator building.
 * Bid Advertisement Dates and Budgets are
        approximate and are subject to vary.
                                                   •    New windows, doors, storefront, curtain wall, operable partitions and glazing.
                                                   •    Wood and terrazzo flooring restoration.
                                                   •    Plaster cove restoration, wall restoration, new metal stud and masonry walls.
                                                   •    ACT, plaster and metal ceilings.
                                                   •    Food service equipment.
                                                   •    Existing elevator replacements.

				