Embed
Email

ERP

Document Sample

Shared by: ewghwehws
Categories
Tags
Stats
views:
0
posted:
2/9/2012
language:
pages:
40
Module 10



Setup

for

Production

Plant Parameters

 Configuring the SAP R/3 system for production is one

of the most challenging tasks in R/3 configuration

 CO will not be configured for production in this



exercise

 Configuring the CO module to accurately track



manufacturing costs is extremely challenging

 Requires balance between accurate cost

allocations and data collection requirements. To

much detail can make the SAP system difficult to

use, which means it is not likely to be used

correctly.

Planning vs. Scheduling

 Configuring the production planning (PP)

module is complicated by the fact that planning

and scheduling are two separate, but highly

related, activities.

 Planning, typically implemented via Material

Requirements Planning (MRP), is used to

create planned orders and purchase

requisitions—suggestions by the SAP system

as to what should be produced on the shop

floor or procured from suppliers (vendors),

respectively.

Planning vs. Scheduling

 Scheduling is the process of converting planned

orders into production orders and purchase

requisitions into purchase orders, then

managing these orders in detail.

Planned Scheduled



Internal Planned Production

Procurement Order Order



External Purchase Purchase

Procurement Requisition Order

Floats

 In both planning and scheduling, floats can be

added to planning times to provide for a buffer

against uncertainty. The production lead time

for a material might be 12 days. Of that 12

days, 10 days might be the expected

production time with a float of 2 days added to

allow for production disruptions.

 Floats are organized in the SAP R/3 system

using Schedule Margin Keys.

Floats



 Four floats are defined in a schedule/margin

key:

 Opening period: Workdays prior to order start.

 Float Before Production: Workdays between order

start and scheduled start.

 Float after Production: Workdays between order

due date and scheduled finish date.

 Release Period: Workdays in release period.

Planning Parameters

 The MRP 2 view of the material master gives:

 In-house production time



 Goods Receipt (GR) processing time



 Schedule Margin Key, which gives:



 Opening period



 Float Before Production



 Float After Production



 Release Period

Schedule Margin Material Master

Key MRP 2 View

Planning Parameters

MRP

 Planning, which is done by the MRP process, needs:

 In-house production time



 GR processing time



 Opening Period



 The MRP process will determine the order start and

order finish date, as well as the planned opening date

 The planned opening date can be used by planners to

convert planned orders to production orders by groups

rather than individually. The MRP planner can convert

groups of planned orders based on the planned

opening date.

Material Requirements Planning



Demand



Opening GR

In-house production

Period process

Opening Date

Planned









Order Start









Order Finish







for Planning

Available

Example in SAP

Available for Planning Demand (Independent Requirement)









Order start

Planned Order Detail Order finish

Planned opening date

Production Order Scheduling

 The float before production and float are used to

calculated the scheduled start and scheduled finish

dates when the planned order is converted into a

production order.

 The float before production is a start float. It has two

functions:

 It can compensate for delays in the staging of

 the material components.

 If there is a capacity bottleneck at the work

centers involved, the production dates can be

moved forward in the future. In this way it serves

as a float for capacity leveling.

Production Order Scheduling

 The float after production is a finish float. It is

used to compensate for unexpected

disturbances in the production process, so that

they do not delay the scheduled finish date.

 The system calculates the scheduled start of

the order by adding the float before production

to the order start date. It calculates the

scheduled finish of the order by subtracting

the float after production from the order finish

date.

Production Order Scheduling



In-house production



Float before Float after

Production Production

Release

Period

Release

Scheduled



Order Start







Start

Scheduled









Finish

Scheduled









Order Finish

Production Order Scheduling

 Note how the float before production and float

after production are used to calculate the

scheduled start and scheduled finish time.

The in-house production time specified on the

MRP 2 View of the material master should be

the sum of the expected processing time plus

the float before production plus the float after

production.

Release Period

 The SAP system can be configured so that a

production order is released as soon as it is created.

This means that the production facility can begin

production.

 The SAP system can also be configured to make the

release of the production order a separate step. In this

case, the SAP system deducts the number of days

defined in the release period from the scheduled start

of the order to determine the scheduled release date

of the order. This date can be used by the production

scheduler to perform collective release, i.e., release a

group of production orders based on the scheduled

release date.

Number Ranges

 Every transaction in SAP is numbered. Some

companies are very interested in the format of

numbers assigned to different objects. The

SAP R/3 system gives the user the ability to

define different number ranges (number of

digits, numeric or alphanumeric, starting

number, etc.) and then assign them to different

objects.

Number Ranges

 In defining plant parameters, number ranges

must be defined and assigned to:

 Planned orders



 Reservations/Dependent requirements



 Purchase requisitions



 MRP lists



 Simulated dependent requirement

MRP Controllers

 In the SAP system, the person designated to

manage the production and inventory levels for

a material is called the MRP Controller.

 Each material can be assigned to a particular

MRP Controller.

 The MRP Controller is used to select materials

for reports like the Stock/requirements list.

 The Stock/requirements list, is an interactive

transaction for managing the production and

inventory levels for a material

Production Scheduling Profile

 The production scheduling profile determines

how production scheduling is to be carried out

in the plant. Settings in the production

scheduling profile control things like:

 When production orders are released for



production (upon creation, for example).

 When production orders are scheduled (on



release, for example).

Production Scheduler

 Similar to the MRP Controller, a Production

Scheduler must be defined in the SAP system

to control detailed production scheduling for a

material. A production scheduling profile is

assigned to the Production Scheduler, and the

Production Schedule is defined in the Work

Scheduling view of the Material Master.

Material Availability Check

 When the MRP system creates a planned

order, it can also check whether the

components and sub-assemblies required to

complete the planned order will be available.

Bill of Material

 The Bill of Material (BOM) defines the

relationship between materials that make up

an assembled product:

 It is the “recipe” for ## NRG–A

(case)



a material

## Dough NRG–A

(lb)









## Oats ## Wheat Germ ## Cinnamon ## Nutmeg

(lb) (lb) (lb) (lb)







## Cloves ## Canola ## Honey ## Carob Chips ## Raisins ## Vit/Min Powder

(lb) (gal) (gal) (lb) (lb) (lb)

Routings

 Routings define the relationship between a material

and the sequence of workcenters (operations) that are

required to produce the material. Routings determine:

 The operations (work steps) to be carried out during

production of a material

 The activities to be performed in the operations as a

basis for determining dates (start, finish, available,

etc.), capacity requirements, and costs for a

production order

 The use of materials during production



 The use of work centers



 The quality checks to be carried out during

production

BOM and Routing Selection ID



 Different routings and BOMs may be defined

for a material. These routings may be

applicable for different production quantities,

for example. When products change, the BOM

and/or routing may change, so BOMs and

routings can have validity periods to define

when the changes occur.

 BOM and Routing Selection IDs determine

how the SAP system will find the correct BOM

and routing for a production order.

BOM and Routing Selection ID



 With the routing selection ID 01, when an order is

created, the system looks for a routing that is valid for

the date the production order is being created and the

lot size of the production order. If more than one

routing is valid for a production order, the SAP

system selects the first valid routing.

 Similarly, with BOM selection ID 01, the system looks

for a BOM for the material with the correct status

(active), lot size and validity date.

Creating Production Orders



Manual MRP Automatic





Copy Routing



Read in First Copy Bill of Material

Forms Backbone

Generates Lead Time Scheduling



Material and/or Capacity Availability Checks



Save Order

Planning Horizon

 The planning horizon (measured in days)

determines how far in the future the MRP

planning process looks to create production

orders.

 A production scheduler can structure the MRP

process to create production orders for all

demand (forecast demand, customer orders)

recorded in the system, or only that demand

that is within the number of days in the

planning horizon into the future.

Production Order Availability Checks



 For standard production order type PP01, availability

checks can be specified on a plant-by-plant basis.

 Availability checks can be performed for:

 Materials: availability of component materials



 Production Resources and Tools (PRT)



 Production Capacity



 Checks can be specified to be determined when a

production order is created, a production order is

released, or both times.

Production Order Availability Checks



 If availability checks are specified, then production

orders cannot be created if the availability check is not

passed.

 For example, if a material availability check is specified

at order creation, then a production order for a batch of

snack bar dough cannot be created unless all raw

materials (oats, wheat germ, cinnamon, etc. are in

stock in sufficient quantities. ## Dough NRG–A

(lb)







## Oats ## Wheat Germ ## Cinnamon ## Nutmeg

(lb) (lb) (lb) (lb)







## Cloves ## Canola ## Honey ## Carob Chips ## Raisins ## Vit/Min Powder

(lb) (gal) (gal) (lb) (lb) (lb)

Forward and Backward Scheduling



 Two basic methods of production order

scheduling are available

 Forward Scheduling, where a production

order is scheduled to start immediately and

finish as soon as possible

 Backward Scheduling, where the scheduling

begins at the due date and works backward.

 Most students use backward scheduling



 Backward scheduling can lead to

problems if there is not enough float time

in the schedule to account for disruptions

Backward Scheduling



Scheduled Scheduled Planned

Today Planned Start Start Finish Finish









Float after

production

In-house production time





Float before

production

Forward Scheduling



Today Scheduled Scheduled Planned

Planned Start Start Finish Finish









Float after

production

In-house production time





Float before

production

Material Master Views for Production



 The MRP views in the Material Master define a

range of parameters for planning.

 There are four MRP views (MRP 1, MRP 2,

MRP 3 and MRP 4) that contain Production

Planning Parameters

 Production scheduling parameters are entered

in the Work Scheduling View

MRP 1 View



MRP Type: How the material is planned

PD—Using MRP logic

VB—Consumption-based planning



Lot Size: How many units to make in a

production order



FX—Fixed, make the fixed lot size

EX—Lot-for-lot, make exactly the

quantity required



MRP Controller: Controller responsible for

this material

MRP 2 View



In-house production: Number of days

required to produce the material



GR processing time: Number of days

required to process the material

after production before it can be

used. May allow for quality

inspection, for example.



Schedule margin key: Set of floats used.

MRP 3 View



Strategy group: setting for how inventory,

forecasts and customer orders affect

the MRP planning process.



Tot. repl. lead time: Total replenishment

lead time. This is used in the sales

order process. If there is no stock

on hand for this material, then the

sales order process will assume

the material will be available in

this number of days if an order is

placed. The SAP system will

calculate a promised delivery date

using the total replenishment lead

time as well as a delivery time

calculated from other system settings.

Work Scheduling View



Production Scheduler: Production scheduler

responsible for this material.



Prod. Sched. Profile: Production scheduling

profile for this material.



As described previously, the production

scheduler and production scheduling

profile determines the way production

orders are created and managed.

MRP Run

 In Single-item, Single-level

planning, only the material is

planned, not other materials that

may be required to make the

material

 For example, if single-item, single-

level planning is used on the dough

material, then only the dough is

planned and not the materials

needed to make dough, like oats,

wheat germ, etc.

A number of parameters are

set that in MRP planning to determine

how planning is to proceed and what

it is to produce (planned orders vs.

purchase requisitions, for example).

Stock/Requirements List

 The Stock/requirements list is an

interactive report that provides a

comprehensive set of information

about a material, including

inventory, planned orders, forecast

demand, customer orders.

 In addition, by double-clicking on

specific items, the user can access

a variety of data like material

masters, detailed stock overviews,

production order details, etc.

 The Stock/requirements list is the

primary tool used by planners and

schedulers.



Related docs
Other docs by ewghwehws
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!