   Westside Wastewater Treatment Plant




          SUMMARY STATUS REPORT

              February 12, 2008


             MILESTONE
             SCHEDULE CONSULTANTS
                                     WESTSIDE WASTEWATER FACILITIES

                                                  SUMMARY / STATUS

                                                     February 12, 2008



The basis for today’s Job Coordination Meeting was the Near Term Schedule and Action Item Agenda dated January 10,
2008. Schedule adjustments, based on discussion and commitments provided during today's meeting, are reflected on
the attached new Near Term Schedule dated February 12, 2008.

Also enclosed for review are the Action Item Agenda, the anticipated Equipment Startup Schedule for March and April
2008, and the updated Overall Project Schedule reflecting remaining construction activities.

SUMMARY

Project substantial completion continues to trend to late May 2008. This assessment is based on the current and
projected progress of equipment functional testing and construction completion of the Bio-Solids Processing Building.

The functional testing of process equipment, which began mid December 2007, continues to track as required in order to
maintain project completion commitments. Filling of the Flow Equalization Basin for operational checkout is rescheduled
to begin the week of February 18, 2008.

Building dry-in is complete with the exception of the Filter Facilities and Bio-Solids Processing Building. Dry-in of these
two remaining structures is critical in order to maintain project completion commitments. Holmes Erection provided
roofing and exterior skin completion commitments during today's meeting for these two structures, which is reflected in the
attached Near Term Schedule.

All previously noted outstanding issues were resolved prior to today’s meeting with the exception of overhead door
interferences. Additional items requiring resolution noted during today's meeting are identified on the attached Action
Item Agenda.

STATUS

        SITEWORK

        The installation of site water and drain piping is complete. Testing and chlorination of water piping is retargeted to
        begin this week. Power electrical ductbank installation is complete. Fiber-optic ductbank continues with cable
        installation scheduled to begin next week. Telephone ductbank and cable installation is also scheduled to begin
        next week although confirmation of conductors needs to be provided.

        The installation of sidewalks and roadway grading continues. Light pole base installation is complete and site
        lighting is in progress. Irrigation piping is underway and installation of trees is expected to begin February 18,
        2008. Spreading of topsoil and site grassing continues.


        BIOLOGICAL UNITS

        Equipment functional testing is complete and operational checkout is scheduled to begin March 12, 2008.


        OPERATIONS BUILDING

        The installation of acoustical ceilings and ceiling devices is complete. Finish paint and wall covering installation is
        in progress. Ceramic tile installation is complete although remedial work will be required prior to installation of
        fixtures. Casework installation is in progress and retargeted to complete next week. The installation of flooring is
        scheduled to begin the week of March 3, 2008.
RAS/WAS PUMP STATION

Interior and exterior finish activities are substantially complete with the exception of final trimout and HVAC
startup. Pump startup is scheduled the week of March 24, 2008.


FINAL CLARIFIERS

The installation of remaining instrumentation is expected to complete this week. Clarifier startup is scheduled the
week of March 20, 2008. The startup of aeration equipment for the clarifier splitter box is complete. The testing
of scum pumps is scheduled the week of March 10, 2008. Construction completion and aeration startup for the
clarifier effluent collection box is also complete.


FILTER FACILITIES

The erection of structural steel and masonry is complete. Roofing is in progress and is committed to complete
this week for the electrical room. Air scour testing is in progress and the installation of filter media is expected to
begin today. Process piping and miscellaneous steel installation is substantially complete. Electrical equipment
has been installed and electrical raceways and wire installation is in progress. Plumbing and HVAC installation is
also underway.


UV DISINFECTION FACILITIES

Parshall flume installation is complete. The installation of gates and UV equipment is schedule next week.
Plumbing and HVAC installation is underway. Electrical installation is targeted to begin early March 2008 and
equipment checkout is scheduled early April 2008.


POST AERATION BASIN

Process piping and equipment installation is complete. The installation of miscellaneous is complete. Parshall
flume installation is underway. Electrical wiring is in progress and targeted to complete next week following
installation of pump motors. Plumbing is complete. Functional testing is in progress and targeted to complete
February 19, 2008. The start of aluminum covers is scheduled the week of March 3, 2008.


POST AERATION BLOWER BUILDING

Functional testing of process equipment is complete. HVAC startup is scheduled this week.


CHEMICAL FEED BUILDING

The installation and functional testing of blower room equipment is complete. Chemical pump room equipment
and piping will continue through March 2008. Electrical wiring and HVAC installation continues. Overhead crane
installation is schedule next week. Door installation is underway although interferences with the overhead door
must be resolved. The delivery of ceiling panels is scheduled later this month.


SITE PUMP STATION

Construction activities are substantially complete and functional testing is scheduled the week of March 10, 2008.
BIO-SOLIDS PROCESSING BUILDING

Masonry wall construction completed the week of January 12, 2008. Roofing and exterior skin activities are in
progress. Roofing is committed to complete by February 29 and exterior skin by March 14, 2008. Interior
painting continues as dry-in permits. The installation of lower level equipment and piping is complete with the
exception of the polymer area. Plumbing, HVAC and electrical continue as dry-in permits.


WAS STORAGE TANKS

Exterior walkway concrete activities are complete.      The installation of aeration equipment is underway and
targeted to complete early March 2008.


VEHICLE STORAGE BUILDING

Exterior dry-in is complete. Sidewalk installation continues. Interior plumbing, HVAC and electrical continue. The
installation of overhead doors is in progress although direction pertaining to interferences is required.


FLOW EQ. BASIN

Filling of the basin for operational checkout is scheduled next week.


FLOW EQ. PUMP STATION

Membrane roof installation continues with completion retargeted next week. Process pipe and equipment
installation is complete and checkout will begin next week. Plumbing and HVAC installation is substantially
complete and startup is scheduled this week. Electrical equipment installation is complete and electrical
raceways, wire and light fixtures continue.


ODOR CONTROL BUILDILNG

Exterior dry-in is complete. Process piping is complete. Interior HVAC is complete. Approximately two days
remain for completion of fiberglass duct at the tank farm area. Finish painting is substantially complete. Electrical
terminations are in progress. Equipment checkout is scheduled to begin the week of March 3, 2008. The delivery
of acoustical panels is rescheduled later this month.


GRIT/SCUM DIVISION BOX

Construction activities are scheduled to complete the week of March 3, 2008 following delivery of the VFD.
Functional testing of equipment is targeted to begin March 10, 2008.


GRIT/SCUM REMOVAL UNITS

The grouting of basins and equipment is complete. The installation of remaining miscellaneous metals and
controls is scheduled to complete prior to startup, which is targeted to take place the week March 10, 2008.


GRIT/SCUM PUMP STATION

Construction activities, with the exception of HVAC startup and controls, are complete. Equipment checkout for
this structure is scheduled the week March 17, 2008.
INLET FACILITIES

Exterior dry-in is complete. Interior block fill is complete. The installation of process equipment continues with
completion targeted next week. HVAC installation is underway. Plumbing installation continues. Electrical
equipment installation is complete and electrical raceways are in progress.


INFLUENT METERING STRUCTURE

Underground pipe installation is complete.    Slab-on-grade construction is complete and wall construction is
expected to finish this week.
                                                                                Start-up Schedule Dates
                                                                                                                                                                           Startup Complete
                  Equipment                             Company                   Contact Name       Contact Number       Specification Section   Scheduled Startup Date                                        Notes
                                                                                                                                                                                 Date
                                                 Eimco Water Technologies/
1           Influent Screening System
                                                   Formally Bracket Green
                                                                                    Chad Cooley        225-295-1200               11217                  03//31/08

                                                  H. Fontaine c/o Pump &                                                                                                                          initial inspection complete. Final to
2      SS Downward Opening Weir Gates
                                                    Process Equipment
                                                                                      Bill Uhrig       205-987-3337               11306                  1/3/2008           1/4/2008 see note
                                                                                                                                                                                                                   follow
                                                  H. Fontaine c/o Pump &                                                                                                                          initial inspection complete. Final to
3                SS Slide Gates
                                                    Process Equipment
                                                                                      Bill Uhrig       205-987-3337               11307                  1/3/2008           1/4/2008 see note
                                                                                                                                                                                                                   follow
                                                  H. Fontaine c/o Pump &                                                                                                                          initial inspection complete. Final to
4         Stainless steel channel gates
                                                    Process Equipment
                                                                                      Bill Uhrig       205-987-3337               11308                  1/3/2008           1/4/2008 see note
                                                                                                                                                                                                                   follow
                                                                                                                                                                                                    pumps @ 10 & 12 checked out
5              Submersible Pumps                   Jack Tyler Engineering           Rick Carney        901-794-1413               11311                  2/4/2008            2/5/08 see note     pumps @ 2, 8A, 8B, 21 will checkout
                                                                                                                                                                                                                3/10/2008
                                                Municipal Sales & Equipment,                         501-268-6999 c501-
6           Progressing Cavity Pumps
                                                             Inc.
                                                                                     Mark Ellis
                                                                                                         626-5050
                                                                                                                                  11312                  3/20/2008

     Horizontal, Severe Duty, Non-Clogging,     WEMCO c/o Municipal Sales                            501-268-6999 c501-
7          Vortex- Type Slurry Pumps                  & Equipment, Inc.
                                                                                     Mark Ellis
                                                                                                         626-5050
                                                                                                                                  11313                  3/21/2008

                                                  Hayward Gordon c/o Jack                            479-756-3660 c479-
8           Screw Centrifugal Pumps
                                                Tyler Engineering of Arkansas
                                                                                   Terry Hissong
                                                                                                         841-1827
                                                                                                                                  11314                  3/24/2008

9            Vertical Turbine Pumps               Instrument & Supply, Inc.        Newton White        501-262-3282               11315                  2/20/2008
                                                EIMCO Water Technologies,
10    Circular Grit and Scum Removal Units
                                                   LLC c/o Hydronics, Inc.
                                                                                     Ron Mayo          972-387-3339               11331                  3/10/2008

                                                WEMCO c/o Municipal Sales                              501-268-6999
11     Cyclone/Classifier Degritter System
                                                      & Equipment, Inc.
                                                                                     Mark Ellis
                                                                                                      c501-626-5050
                                                                                                                                  11333                  4/2/2008

                                                                                                                                                                                                 Blowers in Structure 13 & 16 checked
     Rotary Helical-Lbe Positive Displacement   Blocker & Wallace c/o Shupe
12                    Blower                         & Associates, Inc.
                                                                                   George Young        800-843-0551               11336                  1/22/2008         1/23/2008 see note   out - Remaining-Blowers in Structure 19
                                                                                                                                                                                                      will be checked out on 3/5/08
                                                  Andritz-Ruthner, Inc. c/o
13         Belt Filter Press Equipment            Environmental Technical           Mark Lewis         817-419-1795               11340                  4/22/2008
                                                         Sales Inc
14                                                                                                                               11340A
                                                EIMCO Water Technologies,
15   Carrousel Biological Treatment Process
                                                  LLC c/o Hydronics, Inc.
                                                                                     Ron Mayo          972-387-3339               11341                  3/12/2008

16       FRP Ductwork and Accessories                                                                                             11349
                                                EIMCO Water Technologies,
17     Platform Mounted Mechanical Mixers
                                                  LLC c/o Hydronics, Inc.
                                                                                     Ron Mayo          972-387-3339               11351                  3/12/2008

                                                EIMCO Water Technologies,
18             Submersible Mixers
                                                  LLC c/o Hydronics, Inc.
                                                                                     Ron Mayo          972-387-3340               11352                  3/12/2008

19              Jet Mixing System                Instrument & Supply, Inc.         Newton White        501-262-3282               11354                  2/25/2008
20                Bioscrubbers                   Instrument & Supply, Inc.         Newton White        501-262-3282               11356
                                                USFilter/RJ Environmental c/o
21              Carbon Adsorbers                  Environmental Technical           Chad Cooley        225-295-1200               11357                     n/a
                                                          Sales, Inc.
22             Air Filtration System              Instrument & Supply, Inc.        Newton White        501-262-3282               11358
23              Odor Control Fans                Instrument & Supply, Inc.        Greg Kokemueller     501-321-5562               11359                  3/6/2008
                                                USFilter/RJ Environmental c/o
24         Grease and Mist Eliminators            Environmental Technical           Chad Cooley        225-295-1200               11360                     n/a
                                                          Sales, Inc.
25             Clarifier Equipment                        Westec                    Brent Olson        801-265-1000               11361                  3/17/2008




           Westside WWTP                                                                                                                                                                                           2/22/2008
                                                                                                                                                               Air Scour, High rate Backwash Test
                                                   F.B. Leopold Company, Inc.
26           Deep Bed Effluent Filters
                                                   c/o Instrument & Supply, Inc.
                                                                                    Chris Parinella   724-453-2030   11366   2/12/2008   2/15/2008 see note        Complete. Media installation
                                                                                                                                                                           Commenced
     Ultraviolet Disinfection System - Alternate    WEDCO c/o Environmental
28                       Two                           Process Systems
                                                                                      Jim Hohler      704-409-9778   11374   4/7/2008

                                                                                                                                                                Aeration in Structure 7A, 9, & 12
29       Membrane Disc Aeration System               Instrument & Supply, Inc.     Greg Kokemueller   501-321-5562   11376   1/28/2008   1/28/2008 see note   Checked out - Remaining- Was Tanks-
                                                                                                                                                                   will be checkout 3/17/2008
       Retrievable Membrane Disc Aeration
31                  Systems
                                                     Instrument & Supply, Inc.     Greg Kokemueller   501-321-5562   11377   1/28/2008       1/28/2008

32                  Decanter                         Instrument & Supply, Inc.     Greg Kokemueller   501-321-5562   11381
33       Gravity Belt Thickener Relocation                                                                           11383   5/5/2008
                                                   USFilter/RJ Environmental c/o
34          Chemical Metering Pumps                  Environmental Technical         Chad Cooley      225-295-1200   11392   4/28/2008
                                                             Sales, Inc.
35     Polymer Blending and Feed Systems                  Fluid Dynamics                                             11393   4/21/2008
            Oxygen Generation System                 Adaptive Ozone Solutions        Dale Eltiste                    11398   4/3/2008




           Westside WWTP                                                                                                                                                       2/22/2008
                                                       March‐08
     Sunday        Monday               Tuesday             Wednesday            Thursday               Friday                Saturday
                                                                                                                         1




2             3                    4                   5                                                                 8
                                                                            6                    7
              VFD Delivers         Install VFD‐Oil     Install VFD‐Oil
                                                                            Install VFD‐ Oil     Install VFD‐ Oil
              *Conservatec to      Capital Electric    Capital Electric
                                                                            Capital Electric     Capital Electric
              Start covers at 12                       * Blowers in 19
                                                                            *Newyork Fans in     *Newyork Fans in
                                                       checkout‐Blocker
                                                                            17 & 15              17 & 15
                                                       Wallace
9             10                   11                                                                                    15
                                                       12                   13                   14
              KSB Pumps 2, 8A, Eimco ‐‐ G&S
                                                      Eimco ‐‐ Mixers & Eimco ‐‐ Mixers & Eimco ‐‐ Mixers &
              8B, 12              removal unit
                                                      Denitir Gate        Denitir Gate        Denitir Gate
              * Eimco to begin    Checkout (Structure
                                                      Checkout (Structure Checkout (Structure Checkout (Structure
              G&S removal unit 3)‐‐‐>
                                                      6)‐‐‐>              6)‐‐‐>          * 6)‐‐‐>
              Checkout (Structure
                                                                          Bauman‐Magmeter
              3)
                                                                          in 18
16            17                   18                  19                   20                   21                      22

              Westech‐ Final      Westech‐ Final       Westech‐ Final       Monyo Pumps          Wemco Grit Pumps
              Clarifiers          Clarifiers           Clarifiers           4‐P‐4 & 4‐P‐5        4‐P‐1, 4‐P‐2, 4‐P‐3
              *Sanitaire Diffuser
              in WAS Tanks

23            24                   25                  26                   27                   28                      29

              RAS/WAS Pumps @      RAS/WAS Pumps @     RAS/WAS Pumps @      RAS/WAS Pumps @
              Structure 7          Structure 7         Structure 7          Structure 7
              Hayward Gordon       Hayward Gordon      Hayward Gordon       Hayward Gordon
              Bauman Present       Bauman Present      Bauman Present       Bauman Present

30            31

              Screening System Screening System Screening System Screening System Screening System
              Startup at Structure Startup at Structure Startup at Structure Startup at Structure Startup at Structure
              1                    1                    1        *Grit       1        *Grit       1        *Grit
                                                        Classifiers          Classifiers          Classifiers
                                                             April‐08
     Sunday        Monday                  Tuesday               Wednesday            Thursday             Friday             Saturday
                                       1                     2                    3                    4                 5

                                   Screening System Screening System Screening System Screening System
                                   Startup at Structure Startup at Structure Startup at Structure Startup at Structure
                                   1                    1        *Grit       1        *Grit       1        *Grit
                                                        Classifiers @ 1      Classifiers @ 1      Classifiers @ 1
                                                                             **Oxygen Booster **Oxygen Booster
                                                                             System               System
6             7                    8                    9                    10                   11                     12

              UV Disinfection      UV Disinfection      UV Disinfection      UV Disinfection      UV Disinfection
              System Checkout      System Checkout      System Checkout      System Checkout      System Checkout
              Structure 11         Structure 11         Structure 11         Structure 11         Structure 11


13                                                                                                                       19
              14                   15                   16                   17                   18

              *Filters Control     *Filters Control     *Filters Control     *Filters Control     *Filters Control
              Checkout             Checkout             Checkout             Checkout             Checkout
              Keystone             Keystone             Keystone             Keystone             Keystone
              Conveyors 1&19       Conveyors 1&19       Conveyors 1&19       Conveyors 1&19       Conveyors 1&19


20            21                   22                   23                                                               26
                                                                             24                   25
              Polymer Feed      Polymer Feed          Polymer Feed
                                                                            Belt Filter Press‐    Belt Filter Press‐
              System (Structure System (Structure System (Structure
                                                                            Andritz               Andritz
              19)               19)            * Belt 19)            * Belt
                                filter Press ‐Andritz filter Press ‐Andritz

27            28                   29                   30

              Belt Filter Press‐   Belt Filter Press‐   Belt Filter Press‐   Belt Filter Press‐   Belt Filter Press‐
              Andritz              Andritz              Andritz              Andritz              Andritz
              *Chemical            *Chemical            *Chemical
              Metering Pumps       Metering Pumps       Metering Pumps
                                                                                                                                                                             Brasfield & Gorrie
Near Term Schedule                                           Westside Wastewater Facilities                                                                              Report Date: 12FEB08
                                                                                                                                                                               Page 1A of 10A
By: Milestone Consultants


                                                                                                                                           2008
      Act                                              Orig Rem    Early      Early
                               Description                                                              FEB                                           MAR                            APR
      ID                                               Dur Dur     Start      Finish
                                                                                        04   11          18         25           03         10          17        24         31        07
SITEWORK

  455         Test/Chlorinate W1-W3 Pipe                10   10 15FEB08 *   28FEB08                                        Test/Chlorinate W1-W3 Pipe
  460         Install Water Meters                       4    4 29FEB08     05MAR08                                                   Install Water Meters
  470         Complete Ductbank Conductors              10    4 04FEB08 A   15FEB08                   Complete Ductbank Conductors
  475         Fiber Optic Ductbanks                     20    4 04DEC07 A   15FEB08                   Fiber Optic Ductbanks
  480         Fiber Optic Cable                         10   10 18FEB08 *   29FEB08                                            Fiber Optic Cable
  485         Complete Phone Ductbank/Cable             10   10 18FEB08     29FEB08                                            Complete Phone Ductbank/Cable
  490         Complete Sidewalks                        30   14 11DEC07 A   29FEB08                                            Complete Sidewalks
  495         Complete Structure Thorocoat              15   15 18FEB08     07MAR08                                                      Complete Structure Thorocoat
  500         Roadway Finish Grade & Base               45   32 07JAN08 A   26MAR08 *                                                                                   Roadway Finish Grade &
  510         Chain Link Fencing                        28   28 18FEB08 *   26MAR08                                                                                     Chain Link Fencing
  515         Ornamental Fence                          20   20 27MAR08     23APR08
  520         Site Lighting                             20   17 07JAN08 A   05MAR08                                                   Site Lighting
  525         Site Grounding                            16   10 04FEB08 A   25FEB08                                   Site Grounding
  530         Irrigation                                20    4 21JAN08 A   15FEB08                   Irrigation
  535         Landscape                                 20   20 18FEB08     14MAR08                                                                   Landscape
  540         Final Grassing                            30   30 27MAR08     07MAY08
  545         Asphalt Paving                            30   30 07APR08     16MAY08 *
BIOLOGICAL UNITS-6
  BIOLOGICAL UNITS 1 & 2
  1400        EIMCO Mixer & Denitir Gate Operational     3    3 12MAR08     14MAR08                                                                   EIMCO Mixer & Denitir Gate Operational Ch
NORTH ELECTRICAL BUILDING-24

  2297        Controls/Instrumentation                   4    1 21NOV07 A   13FEB08                Controls/Instrumentation
  2302        Electrical Devices/Trim                    1    1 14FEB08     14FEB08                  Electrical Devices/Trim
  2307        A/C Startup                                1    1 12FEB08     12FEB08               A/C Startup
SOUTH ELECTRICAL BUILDING-25

  2497        Controls/Instrumentation                   4    1 29NOV07 A   13FEB08                Controls/Instrumentation
  2502        Electrical Devices/Trim                    1    1 14FEB08     14FEB08                  Electrical Devices/Trim
  2507        A/C Startup                                1    1 12FEB08     12FEB08               A/C Startup
                                                                                                                                                                                  Brasfield & Gorrie
Near Term Schedule                                                Westside Wastewater Facilities                                                                              Report Date: 12FEB08
                                                                                                                                                                                    Page 2A of 10A
By: Milestone Consultants


                                                                                                                                                   2008
      Act                                                   Orig Rem    Early      Early
                               Description                                                                   FEB                                          MAR                                APR
      ID                                                    Dur Dur     Start      Finish
                                                                                             04   11          18          25           03          10       17         24          31          07
OPERATIONS BUILDING-22

  8290        Casework                                       10    9 23JAN08 A   22FEB08                                Casework
  8295        Ceramic Tile                                    3    4 08JAN08 A   15FEB08                   Ceramic Tile
  8298        Fire Extinguishers                              1    1 22FEB08     22FEB08                                Fire Extinguishers
  8302        Above Ceiling Inspection/Punch                  5    5 18FEB08 *   22FEB08                                Above Ceiling Inspection/Punch
  8303        Ceiling Tile                                    5    5 25FEB08     29FEB08                                            Ceiling Tile
  8305        Resilient Flooring                             11   11 03MAR08     17MAR08                                                                     Resilient Flooring
  8306        Finish Paint                                   10   10 11MAR08     24MAR08                                                                                 Finish Paint
  8307        Chair Rail & Oak Trim                           5    5 18MAR08     24MAR08                                                                                 Chair Rail & Oak Trim
  8311        Controls/Instrumentation                        3    3 20MAR08     24MAR08                                                                                 Controls/Instrumentation
  8316        Electrical Devices & Trim                       3    3 25MAR08     27MAR08                                                                                       Electrical Devices & Trim
  8319        Bathroom Partitions & Accessories               5    5 11MAR08     17MAR08                                                                     Bathroom Partitions & Accessories
  8321        Set Plumbing Fixtures                           2    2 18MAR08     19MAR08                                                                         Set Plumbing Fixtures
  8322        Recessed Floor Mats                             2    2 18MAR08     19MAR08                                                                         Recessed Floor Mats
  8323        Seal Floors                                     3    3 25MAR08     27MAR08                                                                                       Seal Floors
  8326        Carpet Tile                                     1    1 25MAR08     25MAR08                                                                                    Carpet Tile
  8331        Wall Base                                       2    2 26MAR08     27MAR08                                                                                       Wall Base
  8334        Punch & Clean                                  10   10 28MAR08     10APR08                                                                                                             P
RAS/WAS PUMP STATION-7

  5929        Pull Wire                                      30    1 31JUL07 A   12FEB08               Pull Wire
  5943        Controls / Instrumentation                      2    1 14JAN08 A   12FEB08               Controls / Instrumentation
  5948        Electrical Devices/Trim                         1    1 13FEB08     13FEB08                Electrical Devices/Trim
  5953        HVAC Startup                                    1    1 13FEB08     13FEB08                HVAC Startup
  5958        Functional Testing/Pump Startup                 4    4 24MAR08 *   27MAR08                                                                                       Functional Testing/Pum
FINAL CLAIRIFIERS-8
  FINAL CLARIFIERS #1 - 4
  5592        Touch up Paint                                 20    1 24JUL07 A   12FEB08 *             Touch up Paint
  5594        Misc Instrumentation                            4    3 17JAN08 A   14FEB08                  Misc Instrumentation
  5595        Westech Functional Testing - all clarifiers     3    3 17MAR08 *   19MAR08                                                                         Westech Functional Testing - all clar
SCUM PUMP HOUSING-8A & 8B

  5955        Controls/Instrumentation                        1    1 12FEB08     12FEB08               Controls/Instrumentation
  5960        Electrical Devices/Trim                         1    1 13FEB08     13FEB08                Electrical Devices/Trim
                                                                                                                                                                 Brasfield & Gorrie
Near Term Schedule                                 Westside Wastewater Facilities                                                                            Report Date: 12FEB08
                                                                                                                                                                   Page 3A of 10A
By: Milestone Consultants


                                                                                                                             2008
      Act                                    Orig Rem    Early      Early
                               Description                                              FEB                                         MAR                                  APR
      ID                                     Dur Dur     Start      Finish
                                                                             04   11     18          25          03           10       17       24                  31     07
  5965        KSB Pump Checkout                1    1 10MAR08 *   10MAR08                                                       KSB Pump Checkout
FILTER FACILITIES-10

  3545        Electrical Room Roof             5    4 11FEB08 A   15FEB08              Electrical Room Roof
  3550        Electrical Room Siding           5    5 18FEB08     22FEB08                          Electrical Room Siding
  3552        Canopy Roofing                  15   15 03MAR08 *   21MAR08                                                                          Canopy Roofing
  3565        Paint                           15    9 24JAN08 A   22FEB08                          Paint
  3566        Quaker Windows                   2    2 25FEB08     26FEB08                                  Quaker Windows
  3567        Doors & Hardware                 5    5 27FEB08     04MAR08                                             Doors & Hardware
  3568        Fire Extinguisher                1    1 05MAR08     05MAR08                                               Fire Extinguisher
  3576        Set A/C Unit                     2    2 27FEB08     28FEB08                                    Set A/C Unit
  3577        Install PTAC                     2    2 29FEB08     03MAR08                                          Install PTAC
  3578        HVAC Startup                     2    2 04MAR08     05MAR08                                               HVAC Startup
  3585        Electrical Raceway              20   18 08FEB08 A   10MAR08                                                       Electrical Raceway
  3590        Pull Wire                       10   10 04FEB08 A   17MAR08                                                                   Pull Wire
  3595        Light Fixtures                   5    5 18MAR08     24MAR08                                                                               Light Fixtures
  3600        Controls/Instrumentation        10   10 25MAR08     07APR08                                                                                                     Contro
  3605        Electrical Devices & Trimout     2    2 08APR08     09APR08                                                                                                        Ele
  3610        Clean & Seal Floor               5    5 10APR08     16APR08
UV DISINFECTION FACILITIES-11

  2826        Gates                            1    1 18FEB08 *   18FEB08                  Gates
  2827        UV Equip                         8    8 19FEB08     28FEB08                                    UV Equip
  2828        FRP Grating                      2    2 29FEB08     03MAR08                                          FRP Grating
  2830        Checker Plate                    2    2 04MAR08     05MAR08                                               Checker Plate
  2834        Oxygen Boosters                  1    1 29FEB08     29FEB08                                     Oxygen Boosters
  2836        Small Piping                     1    1 03MAR08     03MAR08                                          Small Piping
  2838        Doors Hardware                   3    3 04MAR08     06MAR08                                                Doors Hardware
  2840        Fire Ext                         1    1 07MAR08     07MAR08                                                   Fire Ext
  2847        Install AHU & Lines              3    3 04MAR08     06MAR08                                                Install AHU & Lines
  2848        HVAC Startup                     2    2 20MAR08     21MAR08                                                                          HVAC Startup
  2850        Electrical Equipment             5    5 03MAR08 *   07MAR08                                                   Electrical Equipment
  2855        Electrical Raceway               5    5 10MAR08     14MAR08                                                               Electrical Raceway
  2860        Pull Wire                        3    3 17MAR08     19MAR08                                                                      Pull Wire
  2865        Light Fixtures                   2    2 20MAR08     21MAR08                                                                          Light Fixtures
  2870        Controls/Instrumentation        10   10 24MAR08     04APR08                                                                                                Controls/In
                                                                                                                                                                      Brasfield & Gorrie
Near Term Schedule                                  Westside Wastewater Facilities                                                                                Report Date: 12FEB08
                                                                                                                                                                        Page 4A of 10A
By: Milestone Consultants


                                                                                                                                    2008
      Act                                     Orig Rem    Early      Early
                               Description                                                     FEB                                           MAR                                APR
      ID                                      Dur Dur     Start      Finish
                                                                               04   11          18           25            03        10        17           24         31         07
  2875        Electrical Devices & Trim         2    2 07APR08     08APR08                                                                                                             Elec
  2890        Clean & Seal Floors               2    2 09APR08     10APR08                                                                                                               C
  2895        Startup Gates                     2    2 03APR08     04APR08                                                                                                      Startup Ga
  2897        Startup Oxygen                    2    2 03APR08     04APR08                                                                                                      Startup Ox
  2900        Startup UV Equip                  5    5 07APR08 *   11APR08
POST AERATION BASIN-12

  3126        Parshall Flume                    5    2 29JAN08 A   13FEB08                Parshall Flume
  3136        Vertical Turbine Pumps & Pipe     7    2 17JAN08 A   13FEB08                Vertical Turbine Pumps & Pipe
  3157        HVAC Startup                      2    2 14FEB08     15FEB08                   HVAC Startup
  3170        Pull Wire                         3    2 31JAN08 A   13FEB08                Pull Wire
  3175        Light Fixtures                    1    1 14FEB08     14FEB08                  Light Fixtures
  3180        Controls/Instrumentation          2    2 15FEB08     18FEB08                        Controls/Instrumentation
  3190        Electrical Devices                1    1 19FEB08     19FEB08                            Electrical Devices
  3280        Functional Testing                5    2 11FEB08 A   19FEB08 *                          Functional Testing
  3285        Aluminum Covers                  10   10 03MAR08 *   14MAR08                                                                    Aluminum Covers
POST AERATION BLOWER BUILDING-13

  3880        Install AHU & Lines               3    1 26DEC07 A   12FEB08               Install AHU & Lines
  3882        HVAC Startup                      2    2 13FEB08     14FEB08                  HVAC Startup
  3894        Controls/Instrumentation          2    2 13FEB08     14FEB08                  Controls/Instrumentation
CHEMICAL FEED BUILDING-16

  4377        Set Pipe & Exterior Tanks        10    8 08JAN08 A   21FEB08                               Set Pipe & Exterior Tanks
  4378        Pump Room Pipe & Equipment       10   10 22FEB08     06MAR08                                                      Pump Room Pipe & Equipment
  4379        Crane                             5    5 18FEB08 *   22FEB08                                Crane
  4380        Misc Metals/Grating               3    3 22FEB08     26FEB08                                        Misc Metals/Grating
  4388        Doors & Hdwe                      2    2 21FEB08     22FEB08                                Doors & Hdwe
  4390        Extend Vent thru Roof             2    2 21FEB08     22FEB08                                Extend Vent thru Roof
  4397        Install Fans                      4    4 25FEB08     28FEB08                                           Install Fans
  4406        Install AHU & Lines               2    2 08JAN08 A   03MAR08                                                  Install AHU & Lines
  4408        HVAC Startup                      2    2 11MAR08     12MAR08                                                                 HVAC Startup
  4420        Electrical Raceway                6    5 28JAN08 A   06MAR08                                                      Electrical Raceway
  4425        Pull Wire                         3    2 05FEB08 A   10MAR08                                                              Pull Wire
  4430        Light Fixtures                    2    2 11MAR08     12MAR08                                                                 Light Fixtures
  4432        Finish Paint                     10   10 13MAR08     26MAR08                                                                                       Finish Paint
                                                                                                                                                                      Brasfield & Gorrie
Near Term Schedule                                             Westside Wastewater Facilities                                                                     Report Date: 12FEB08
                                                                                                                                                                        Page 5A of 10A
By: Milestone Consultants


                                                                                                                                  2008
      Act                                                Orig Rem    Early      Early
                                Description                                                        FEB                                   MAR                                   APR
      ID                                                 Dur Dur     Start      Finish
                                                                                         04   11    18      25         03        10         17          24             31        07
  4440        Measure, Fab & Deliver Acoustical Panels    20   11 10DEC07 A   26FEB08                            Measure, Fab & Deliver Acoustical Panels
  4445        Acoustical Panels                           15   15 27FEB08     18MAR08                                                             Acoustical Panels
  4450        Controls/Instrumentation                     8    8 13MAR08     24MAR08                                                                         Controls/Instrumentation
  4455        Electrical Devices                           2    2 25MAR08     26MAR08                                                                            Electrical Devices
SITE PUMP STATION-21

  4150        Controls/Instrumentation                     2    2 05MAR08 *   06MAR08                                          Controls/Instrumentation
  4160        Electrical Devices                           1    1 07MAR08     07MAR08                                           Electrical Devices
  4161        Fan Startup                                  1    1 07MAR08     07MAR08                                           Fan Startup
  4180        Functional Testing                           3    3 10MAR08     12MAR08                                                    Functional Testing
BIOSOLIDS PROCESSING BUILDING-19

  6345        Roofing                                     20   14 14JAN08 A   29FEB08                                Roofing
  6350        Exterior Skin                               20   20 04FEB08 A   14MAR08                                                       Exterior Skin
  6352        Quaker Windows                               2    2 13MAR08     14MAR08                                                       Quaker Windows
  6353        Ceiling Structural Grid                     10   10 25FEB08 *   07MAR08                                           Ceiling Structural Grid
  6354        Plywood Ceiling                             20   20 10MAR08     04APR08                                                                                           Plywood C
  6355        Blockfill & Prime Paint Walls               20   12 03DEC07 A   14MAR08                                                       Blockfill & Prime Paint Walls
  6378        BFP & Piping                                10   10 07MAR08     20MAR08                                                                 BFP & Piping
  6379        Auger/Conveyor                               5    5 21MAR08     27MAR08                                                                             Auger/Conveyor
  6380        Platform @ BFP                               4    4 28MAR08     02APR08                                                                                        Platform @ BF
  6382        Bathroom Partitions                          2    2 17MAR08     18MAR08                                                             Bathroom Partitions
  6385        Doors/Hardware                              10   10 19MAR08     01APR08                                                                                       Doors/Hardware
  6387        Fire Extinguishers                           1    1 02APR08     02APR08                                                                                        Fire Extinguish
  6392        Polymer Tank, Blending & Pipe                5    5 28MAR08     03APR08                                                                                         Polymer Tan
  6393        Compressed Air                               2    2 04APR08     07APR08                                                                                                 Comp
  6394        Dilution Piping                              2    2 08APR08     09APR08                                                                                                    Dil
  6395        Aluminum Stairs 1,2,3                       15   15 17MAR08     04APR08                                                                                           Aluminum
  6396        Handrails                                    5    5 07APR08     11APR08
  6400        Run Sanitary Sewer                          10    5 07JAN08 A   18FEB08               Run Sanitary Sewer
  6402        Run Water Lines                             10   10 19FEB08     03MAR08                                     Run Water Lines
  6404        Install Gas Lines                            7    7 04MAR08     12MAR08                                                    Install Gas Lines
  6406        Set Plumbing Fixtures                        2    2 13MAR08     14MAR08                                                       Set Plumbing Fixtures
  6408        Makeup Air SOG                               2    2 17MAR08     18MAR08                                                             Makeup Air SOG
  6410        Set MAU                                      2    2 19MAR08     20MAR08                                                                 Set MAU
  6411        Set Pump                                     3    3 21MAR08     25MAR08                                                                          Set Pump
                                                                                                                                                                              Brasfield & Gorrie
Near Term Schedule                                           Westside Wastewater Facilities                                                                               Report Date: 12FEB08
                                                                                                                                                                                Page 6A of 10A
By: Milestone Consultants


                                                                                                                                           2008
      Act                                              Orig Rem    Early      Early
                                Description                                                            FEB                                           MAR                                 APR
      ID                                               Dur Dur     Start      Finish
                                                                                       04   11          18         25         03           10          17          24           31         07
  6413        Install IRH                                2    2 26MAR08     27MAR08                                                                                        Install IRH
  6414        Install Louvers                            3    3 28MAR08     01APR08                                                                                                Install Louvers
  6415        Install Fans                               2    2 31MAR08     01APR08                                                                                                Install Fans
  6416        Install SS Duct                           19   16 07FEB08 A   04MAR08                                                Install SS Duct
  6417        Install Flue Connection                    1    1 05MAR08     05MAR08                                                 Install Flue Connection
  6418        Connect Duct to Units                      3    3 21MAR08     25MAR08                                                                                     Connect Duct to Units
  6419        HVAC Startup                               2    2 31MAR08     01APR08                                                                                                HVAC Startup
  6435        Electrical Equipment                      10    9 11FEB08 A   22FEB08                              Electrical Equipment
  6440        Electrical Raceway                        30   20 03DEC07 A   04APR08                                                                                                      Electrical R
  6445        Pull Wire                                 17   17 27MAR08     18APR08
  6447        Light Fixtures                            15   15 07APR08     25APR08
  6449        Controls/Instrumentation                  25   25 07APR08     09MAY08
  6454        Finish Paint                              20   20 07APR08     02MAY08
  6466        Bollards                                  10   10 17MAR08     28MAR08                                                                                         Bollards
  6467        Sidewalks                                 10   10 31MAR08     11APR08
  6468        Checkout Blowers                           2    2 05MAR08 *   06MAR08                                                     Checkout Blowers
WAS STORAGE TANKS-20

  6078        Stair case & Ladder                        5    4 11FEB08 A   15FEB08                  Stair case & Ladder
  6079        Walkway/Trusses                            5    5 18FEB08     22FEB08                              Walkway/Trusses
  6080        Aeration Equipment                        20   19 11FEB08 A   07MAR08                                                      Aeration Equipment
  6082        Gravity Decanter                           2    2 10MAR08     11MAR08                                                             Gravity Decanter
  6084        Wallsleeves/Camlocks                       5    5 05MAR08     11MAR08                                                             Wallsleeves/Camlocks
  6086        Finish Grade                               2    2 12MAR08     13MAR08                                                               Finish Grade
  6088        Point Patch Grind                         10   10 14MAR08     27MAR08                                                                                        Point Patch Grind
  6100        Aluminum Covers                           20   20 07APR08     02MAY08
  6126        Aeration Startup & Testing                 3    3 28MAR08     01APR08                                                                                                Aeration Startup
  6128        Decanter Startup & Testing                 3    3 02APR08     04APR08                                                                                                      Decanter S
  6130        Functional Testing-Aeration & Decanter     6    6 28MAR08     04APR08                                                                                                      Functional
VEHICLE STORAGE BLDG-23

  6544        Install OH Doors                           5    4 10JAN08 A   15FEB08                  Install OH Doors
  6547        Grating Over Drains                        1    1 12FEB08     12FEB08              Grating Over Drains
  6555        Sidewalks                                  5    4 10JAN08 A   15FEB08                  Sidewalks
  6590        Run Vents, Terminate thru Roof             2    2 12FEB08     13FEB08               Run Vents, Terminate thru Roof
  6592        Install & Pipe Power Washer                2    2 12FEB08     13FEB08               Install & Pipe Power Washer
                                                                                                                                                                              Brasfield & Gorrie
Near Term Schedule                                     Westside Wastewater Facilities                                                                                     Report Date: 12FEB08
                                                                                                                                                                                Page 7A of 10A
By: Milestone Consultants


                                                                                                                                       2008
      Act                                        Orig Rem    Early      Early
                               Description                                                        FEB                                             MAR                                   APR
      ID                                         Dur Dur     Start      Finish
                                                                                  04   11          18          25           03          10          17           24            31         07
  6593        Install Gas Lines                    2    2 14FEB08     15FEB08                   Install Gas Lines
  6602        Install IRH                          3    2 05DEC07 A   19FEB08                          Install IRH
  6603        Install FRP Duct                     4    4 20FEB08     25FEB08                                      Install FRP Duct
  6606        Flue Connection                      2    2 18FEB08     19FEB08                          Flue Connection
  6608        HVAC Startup                         2    2 10MAR08     11MAR08                                                                 HVAC Startup
  6618        Electrical Raceway                  23   14 16JAN08 A   29FEB08                                            Electrical Raceway
  6623        Pull Wire                           12   10 07FEB08 A   07MAR08                                                         Pull Wire
  6627        Light Fixtures                       6    6 10MAR08     17MAR08                                                                           Light Fixtures
  6628        Finish Paint                         8    8 17MAR08     26MAR08                                                                                            Finish Paint
  6633        Controls/Instrumentation             3    3 18MAR08     20MAR08                                                                                Controls/Instrumentation
  6635        Electrical Devices                   3    3 21MAR08     25MAR08                                                                                         Electrical Devices
  6643        Seal Concrete Floor                  5    5 27MAR08     02APR08                                                                                                       Seal Concrete
  6680        Functional Testing                   5    5 03APR08     09APR08                                                                                                                  Fu
FLOW EQ BASIN-14

  7019        Deliver/Install Fiberglass Doors     2    2 25FEB08 *   26FEB08                                        Deliver/Install Fiberglass Doors
  7029        FRP Duct                             3    3 25FEB08     27FEB08                                         FRP Duct
  7034        Startup FRP Pipe                     5    5 06MAR08     12MAR08                                                                  Startup FRP Pipe
FLOW EQ PUMP STATION-15

  6752        Membrane Roof                       10    4 02JAN08 A   22FEB08 *                               Membrane Roof
  6775        Paint Walls                         10    6 10JAN08 A   03MAR08                                                   Paint Walls
  6785        Set A/C Unit                         2    1 11FEB08 A   12FEB08               Set A/C Unit
  6788        HVAC Startup                         2    2 18FEB08     19FEB08                          HVAC Startup
  6795        Electrical Raceway                  12    6 24JAN08 A   19FEB08                          Electrical Raceway
  6800        Pull Wire                            4    4 11FEB08 A   15FEB08                   Pull Wire
  6805        Light Fixtures                       3    3 11FEB08 A   14FEB08                  Light Fixtures
  6810        Controls/Instrumentation             3    3 15FEB08     19FEB08                          Controls/Instrumentation
  6815        Electrical Devices                   1    1 20FEB08     20FEB08                              Electrical Devices
  6830        Functional Test Pumps                2    2 18FEB08     19FEB08                          Functional Test Pumps
  6835        Checkout Newyork Fans                2    2 06MAR08 *   07MAR08                                                         Checkout Newyork Fans
ODOR CONTROL BUILDING-17

  8395        FRP Pipe                            24    2 16OCT07 A   13FEB08                FRP Pipe
  8397        HVAC Startup                         2    2 18FEB08     19FEB08                          HVAC Startup
  8440        Retaining Wall Handrails             1    1 12FEB08     12FEB08               Retaining Wall Handrails
                                                                                                                                                                        Brasfield & Gorrie
Near Term Schedule                                  Westside Wastewater Facilities                                                                                  Report Date: 12FEB08
                                                                                                                                                                          Page 8A of 10A
By: Milestone Consultants


                                                                                                                                2008
      Act                                     Orig Rem    Early      Early
                               Description                                                     FEB                                           MAR                                   APR
      ID                                      Dur Dur     Start      Finish
                                                                               04   11          18         25         03            10         17            24           31         07
  8468        Electrical Raceway                7    3 10DEC07 A   14FEB08                  Electrical Raceway
  8470        Pull Wire                         5    4 16JAN08 A   15FEB08                   Pull Wire
  8474        Controls/Instrumentation          3    3 20FEB08     22FEB08                               Controls/Instrumentation
  8480        Acoustical Panels                20   20 27FEB08 *   25MAR08                                                                                        Acoustical Panels
  8482        Electrical Devices                2    2 26MAR08     27MAR08                                                                                           Electrical Devices
  8484        Clean & Seal Floors               3    3 28MAR08     01APR08                                                                                                     Clean & Seal Fl
  8485        Checkout Newyork Fans             2    2 06MAR08     07MAR08                                                    Checkout Newyork Fans
  8486        Startup Bioscrubbers              2    2 02APR08     03APR08                                                                                                        Startup Bios
  8488        Startup Carbon Absorbers          2    2 04APR08     07APR08                                                                                                              Startu
GRIT/SCUM DIVISION BOX-2

  7115        Paint                            10    2 20NOV07 A   13FEB08 *              Paint
  7125        FRP Duct                          2    1 11FEB08 A   12FEB08               FRP Duct
  7130        Deliver VFD                       0    0             04MAR08 *                                               Deliver VFD
  7162        Electrical Raceway               10    2 11DEC07 A   07MAR08 *                                                  Electrical Raceway
  7164        Pull Wire                         2    2 06MAR08     07MAR08                                                    Pull Wire
  7166        Light Fixtures                    2    2 10MAR08     11MAR08                                                               Light Fixtures
  7168        Controls/Instrumentation          1    1 12MAR08     12MAR08                                                                Controls/Instrumentation
  7170        Electrical Devices                1    1 13MAR08     13MAR08                                                                  Electrical Devices
  7180        Functional Testing- KSB Pumps     2    2 10MAR08     11MAR08                                                               Functional Testing- KSB Pumps
GRIT/SCUM REMOVAL UNITS & COLLECTION BOX-3 & 3A

  7662        Alum Steps                        4    4 03MAR08 *   06MAR08                                                   Alum Steps
  7712        Controls/Instrumentation          3    3 05MAR08     07MAR08                                                    Controls/Instrumentation
  7714        Startup EIMCO                     2    2 10MAR08     11MAR08                                                               Startup EIMCO
  7720        Aluminum Covers                  15   15 17MAR08 *   04APR08                                                                                                         Aluminum
  7725        FRP Pipe & Duct, Vent Caps        5    5 31MAR08     04APR08                                                                                                         FRP Pipe &
GRIT/SCUM PUMP STATION-4

  7920        Install & Pipe MAU                3    1 11DEC07 A   12FEB08               Install & Pipe MAU
  7924        HVAC Startup                      1    1 12FEB08     12FEB08               HVAC Startup
  7968        Controls/Instrumentation          1    1 13FEB08     13FEB08                Controls/Instrumentation
  7972        Clean & Seal Floor                2    2 13FEB08     14FEB08                  Clean & Seal Floor
  7976        Moyno Startup                     1    1 20MAR08 *   20MAR08                                                                                Moyno Startup
  7978        Wemco Startup                     1    1 21MAR08     21MAR08                                                                                 Wemco Startup
                                                                                                                                                                       Brasfield & Gorrie
Near Term Schedule                                  Westside Wastewater Facilities                                                                                 Report Date: 12FEB08
                                                                                                                                                                         Page 9A of 10A
By: Milestone Consultants


                                                                                                                                     2008
      Act                                     Orig Rem    Early      Early
                                Description                                                   FEB                                            MAR                                APR
      ID                                      Dur Dur     Start      Finish
                                                                              04   11          18           25          03           10        17           24           31       07
BIOPROCESS MAGMETER VAULT-18

  6649        Ladder                            1    1 12FEB08     12FEB08              Ladder
  6653        Sump Grating                      1    1 12FEB08     12FEB08              Sump Grating
  6663        Controls/Instrumentation          1    1 12FEB08     12FEB08              Controls/Instrumentation
  6670        Start up Magmeter                 1    1 13MAR08 *   13MAR08                                                                  Start up Magmeter
INLET FACILITIES-1

  7399        Small Piping                      5    3 03JAN08 A   14FEB08                 Small Piping
  7401        Catwalk & Checkerplate            5    5 17MAR08 *   21MAR08                                                                              Catwalk & Checkerplate
  7402        Handrails Interior & Ladder       1    1 24MAR08     24MAR08                                                                                   Handrails Interior & Ladder
  7405        Blockfill & Prime Paint Walls    15    9 03DEC07 A   22FEB08                                Blockfill & Prime Paint Walls
  7410        Run Water Lines                   7    7 25FEB08     04MAR08                                                   Run Water Lines
  7412        Run Gas Lines                     2    2 05MAR08     06MAR08                                                     Run Gas Lines
  7414        Install Louvers                   2    2 25FEB08     26FEB08                                       Install Louvers
  7416        Install Fans                      4    4 27FEB08     03MAR08                                                Install Fans
  7420        Install IRH                       2    2 12FEB08     13FEB08               Install IRH
  7422        Install SS Duct                   2    1 07FEB08 A   12FEB08              Install SS Duct
  7426        Flue Connections                  1    1 13FEB08     13FEB08               Flue Connections
  7427        HVAC Startup                      2    2 21MAR08     24MAR08                                                                                   HVAC Startup
  7432        Install Liquid Seperator          5    5 18FEB08 *   22FEB08                                Install Liquid Seperator
  7442        Electrical Raceway               40   20 19DEC07 A   10MAR08                                                             Electrical Raceway
  7444        Pull Wire                        10   10 11MAR08     24MAR08                                                                                   Pull Wire
  7446        Light Fixtures                   10   10 25FEB08     07MAR08                                                         Light Fixtures
  7448        Controls/Instrumentation          7    7 25MAR08     02APR08                                                                                                    Controls/Instru
  7449        Finish Paint                     15   15 03MAR08     21MAR08                                                                              Finish Paint
  7450        Electrical Devices                3    3 03APR08     07APR08                                                                                                            Electr
  7452        Exterior Misc Metals              5    5 12FEB08     18FEB08                       Exterior Misc Metals
  7460        Fire Ext & Access                 2    2 17MAR08     18MAR08                                                                          Fire Ext & Access
  7462        Doors & Hardware                  5    5 19MAR08     25MAR08                                                                                       Doors & Hardware
  7463        Clean & Seal Floors               3    3 26MAR08     28MAR08                                                                                           Clean & Seal Floors
  7464        Start Up Bracket Green            5    5 31MAR08 *   04APR08                                                                                                       Start Up Br
  7466        Start Up Grit Classifier          2    2 07APR08     08APR08                                                                                                             Start
  7468        Start Up Conveyor & Gates         5    5 09APR08     15APR08
                                                                                                                                                      Brasfield & Gorrie
Near Term Schedule                                 Westside Wastewater Facilities                                                                 Report Date: 12FEB08
                                                                                                                                                      Page 10A of 10A
By: Milestone Consultants


                                                                                                                            2008
      Act                                    Orig Rem    Early      Early
                              Description                                               FEB                                           MAR                     APR
      ID                                     Dur Dur     Start      Finish
                                                                             04   11     18            25         03         10         17   24       31        07
INFLUENT METERING STRUCTURE-26

  8030        Walls                            5    4 28JAN08 A   15FEB08              Walls
  8032        Wreck                            2    2 18FEB08     19FEB08                      Wreck
  8034        Complete Backfill                3    3 20FEB08     22FEB08                         Complete Backfill
  8037        Flanged Piping & Accessories     2    2 20FEB08     21FEB08                        Flanged Piping & Accessories
  8050        Pipe Supports                    3    3 22FEB08     26FEB08                                   Pipe Supports
  8055        Point & Patch Concrete           1    1 27FEB08     27FEB08                                    Point & Patch Concrete
  8060        Handrails                        1    1 27FEB08     27FEB08                                    Handrails
Filter Backwash 5
Deep Bed Filters Underdrain Blocks
Structure 10
    Deep Bed Filter Pipe Gallery




Filter Backwash 1
Filter Backwash 2




Filter Backwash 3
Filter Backwash 4
SUMMARY OVERALL PROJECT SCHEDULE
                                                                                      2005                        2006                                            2007                                       2008
     Act                                          Orig Rem     Early      Early
                              Description                                           NOV D    J   F   M   A   M   J   J   A   S   O   N   D   J   F   M   A   M   J   J   A    S   O    N       D   J    F    M A       M    J
     ID                                           Dur Dur      Start      Finish

+PRECONSTRUCTION
                                                   63    0 07NOV05 A    03FEB06 A
+SITEWORK
                                                   580   69 06FEB06 A   16MAY08
+BIOLOGICAL UNITS-6
                                                   494   3 06MAR06 A    14MAR08
+NORTH ELECTRICAL BUILDING-24
                                                   409   3 05JUL06 A    14FEB08
+GENERATOR
                                                    2    0 06JUL06 A    07JUL06 A
+SOUTH ELECTRICAL BUILDING-25
                                                   381   3 14AUG06 A    14FEB08
+OPERATIONS BUILDING-22
                                                   417   43 18AUG06 A   10APR08
+RAS/WAS PUMP STATION-7
                                                   416   33 07AUG06 A   27MAR08
+FINAL CLARIFIER SPLITTER BOX-7A
                                                   456   0 10APR06 A    28JAN08 A
+FINAL CLAIRIFIERS-8
                                                   478   27 01MAY06 A   19MAR08
+SCUM PUMP HOUSING-8A & 8B
                                                   240   20 28MAR07 A   10MAR08
+FINAL CLARIFIER EFF. COLLECTION BOX-9
                                                   405   0 22JUN06 A    29JAN08 A
+FILTER EFFLUENT BOX-18A
                                                   154   0 05OCT06 A    11MAY07 A
+FILTER FACILITIES-10
                                                   279   67 09APR07 A   14MAY08
+UV DISINFECTION FACILITIES-11
                                                   321   40 02JAN07 A   11APR08
+POST AERATION BASIN-12
                                                   324   24 04DEC06 A   14MAR08
+POST AERATION BLOWER BUILDING-13
                                                   168   3 14JUN07 A    14FEB08
+CHEMICAL FEED BUILDING-16
                                                   264   57 16APR07 A   30APR08
+SITE PUMP STATION-21
                                                   320   6 13NOV06 A    12MAR08
+BIOSOLIDS PROCESSING BUILDING-19
                                                   494   72 12JUN06 A   21MAY08
+WAS STORAGE TANKS-20
                                                   251   59 07MAY07 A   02MAY08

Data date        12FEB08                                                                                                                                                                               Early bar
Start date       07NOV05       Page 1A of 2A                                                                                                                                                           Progress bar
Finish date      21MAY08       Summary Schedule
                                                                                           Brasfield & Gorrie                                                       By Milestone Consultants           Critical bar
Must finish date 30MAY08                                                             Westside Wastewater Facilities                                                                                    Start milestone point
  © Primavera Systems, Inc.                                                                                                                                                                            Finish milestone point
                                                                                      2005                        2006                                            2007                                       2008
     Act                                          Orig Rem     Early      Early
                              Description                                           NOV D    J   F   M   A   M   J   J   A   S   O   N   D   J   F   M   A   M   J   J   A    S   O    N       D   J    F    M A       M    J
     ID                                           Dur Dur      Start      Finish

+VEHICLE STORAGE BLDG-23
                                                   229   42 11MAY07 A   09APR08
+FLOW EQ BASIN-14
                                                   499   13 13MAR06 A   12MAR08
+FLOW EQ PUMP STATION-15
                                                   192   19 04JUN07 A   07MAR08
+ODOR CONTROL BUILDING-17
                                                   428   40 31JUL06 A   07APR08
+GRIT/SCUM DIVISION BOX-2
                                                   464   23 15MAY06 A   13MAR08
+GRIT/SCUM REMOVAL UNITS & COLLECTION BOX-3 & 3A
                                                   413   25 31JUL06 A   04APR08
+GRIT/SCUM PUMP STATION-4
                                                   343   29 13NOV06 A   21MAR08
+BIOPROCESS MAGMETER VAULT-18
                                                   524   23 20FEB06 A   13MAR08
+INLET FACILITIES-1
                                                   479   46 25MAY06 A   15APR08
+INFLUENT METERING STRUCTURE-26
                                                   211   12 25APR07 A   27FEB08
+EFFLUENT DISCHARGE STRUCTURE-27
                                                   215   0 05DEC06 A    08OCT07 A
+COMMISSIONING/COMPLETION
                                                    0    0 21MAY08      21MAY08




Data date        12FEB08                                                                                                                                                                               Early bar
Start date       07NOV05       Page 2A of 2A                                                                                                                                                           Progress bar
Finish date      21MAY08       Summary Schedule
                                                                                           Brasfield & Gorrie                                                       By Milestone Consultants           Critical bar
Must finish date 30MAY08                                                             Westside Wastewater Facilities                                                                                    Start milestone point
  © Primavera Systems, Inc.                                                                                                                                                                            Finish milestone point

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:5
posted:2/1/2012
language:
pages:32
jianghongl jianghongl http://
About