This report lists restricted asbestos access areas which have been abated and are NO LONGER RESTRICTED. See comment section for additional


                                                   NO LONGER RESTRICTED ACCESS REPORT
   BUILDIN                     LOCATIO                            DESCRIPTIO                                  COMMENT

   3018 Western Avenue         Crawl spaces                       Asbestos debris on soil.                   Demolished. Was 55. This was a space in
                                                                                                             the old bagley annex building.



   Art Building                Attic                              Deteriorated asbestos elbows on pipe.      Deteriorated elbows abated November




   Benson Hall                 Above ceiling, NW corner of        Debris containing asbestos may be on       This area was cleaned in August, 1991.
                               basement                           top surface of ceiling tiles.



   CHDD School                 First floor hallways; spaces       Damaged hard mudded fittings exist in      Abatement project completed October
                               above suspended ceilings           some areas of these spaces.



   Commodore Duchess           Attic mechanical spaces            Deteriorated asbestos insulation on        Access is through roof hatches,insulation
                                                                  pipes.                                     is air cell 50% chrysotile. Future project
                                                                                                             currently being planned as a leasor
                                                                                                             development. Abated in lease development
                                                                                                              remodel, contractor was TLH.




REPORT            09-Sep-02
PAGE 1 OF 6
                                                NO LONGER RESTRICTED ACCESS REPORT
  BUILDIN                  LOCATIO                              DESCRIPTIO                                 COMMENT

  Communications           Attic-East End                       Deteriorated asbestos containing tape      Abated in August 1990.
                                                                on exterior of ventilation ductwork.



  Cyclotron Building       Mezzanine storage area               Asbestos-containing spray-on               Abatement project completed March 1992.
                                                                insulation exists on the ceiling of this
                                                                space.


  Denny Hall               Univents                             Deteriorated asbestos material inside      Abatement completed October 1990.
                                                                univents.



  Gerberding Hall          First floor, area above ceiling in   Deteriorated pipe elbow insulation.        Abated July, 1992.
                           main entrance lobby



  Guthrie Annex 1          Dirt crawl space                     Poly over dirt and pipe insulated with     Area abated during previous project.
                                                                fiberglass.                                EH&S checked December 1990



  Guthrie Annex 1          Dirt crawl space                     Deteriorated asbestos insulation in dirt   Abatement project completed May 1991.
                                                                crawl space.



  Guthrie Annex 2          Dirt crawl space                     Dirt crawl space with asbestos piping      Abatement project completed May 1991.
                                                                in poor condition.




REPORT         09-Sep-02
PAGE 2 OF 6
                                                NO LONGER RESTRICTED ACCESS REPORT
  BUILDIN                    LOCATIO                           DESCRIPTIO                                COMMENT

  Johnson Hall               North/South attic space above     Most deteriorated asbestos                Abated fall of 1995. New fiberglass
                             4th floor                         encapsulated, but some surfaces are       insulation installed.
                                                               considered contaminated.


  Johnson Hall               East/West attic space above 3rd   Asbestos containing pipe insulation in    Asbestos abatement was completed in
                             floor                             southeast corner of attic is damaged.     December 1993.



  Johnson Hall               Air plenum under building         Asbestos insulated pipes were             The asbestos containing material in this
                                                               encapsulated in 1985.                     space was repaired/encapsulated in



  Kincaid Hall               Basement mechanical room          Asbestos - containing spray-on material   Project completed April 1992.
                                                                on ceiling (up to 40% chrysotile
                                                               asbestos).


  Lander/Terry Hall          Unabated pipe chases              Damaged pipe insulation in chases.        Pipe chases #01, 02, 03, and 04 were
                             surrounding lavatory core                                                   abated in June 1998. In chase #4 there is
                                                                                                         still a vertical steam line which is asbestos
                                                                                                         insulated. This line is in good condition,
                                                                                                         and has been encapsulated and jacketed for
                                                                                                         additional protection.

  Magnuson Health            J-wing mechanical rooms J-003     Spray-on material on ceiling. 15-20%      Spray-on material was abated fall of 1995.
                             & J-007                           chrysotile.                               Reinsulating product is non asbestos and
                                                                                                         has a blue tint.


  Magnuson Health            T-276 Mechanical space behind     Silicate pipe and autoclave insulation.   Area has been abated but debris still seen
                             autoclaves                                                                  on surfaces. 1 of 3 wipe samples contained
                                                                                                         asbestos. work order submitted for clean up
                                                                                                          on 11/1/90.




REPORT           09-Sep-02
PAGE 3 OF 6
                                             NO LONGER RESTRICTED ACCESS REPORT
  BUILDIN                 LOCATIO                           DESCRIPTIO                                COMMENT

  Magnuson Health         T-wing utility                    Utility closet with structural steel      Abatement project completed May 1991. If
                          closets:300C,300Y,400Y            insulation debris.                        debris is found please contact EHS
                                                                                                      immediately.


  Magnuson Health         F-001 mechanical room             Spray-on material on ceiling. 97%         Spray-on material was abated fall 1995.
                                                            amosite.



  Magnuson Health         RR-155A                           Autoclave has deteriorated asbestos       Clean up completed and inspected January
                                                            insulation.                               1991.



  Magnuson Health         RR-wing - basement mechanical     Spray-on material on ceiling. Up to 10%   Spray-on material was abated fall 1995.
                          room                              chrysotile.



  Magnuson Health         B-wing 4 th floor, area above     Temporarily restricted during project.    Area above 4th floor suspended ceiling has
                          suspended ceiling from elevator                                             been abated.
                          #18 south


  Magnuson Health         F-001 mechanical room, hatches    Asbestos debris in space.                 Abatement project completed.
                          below stairs



  Magnuson Health         T-10 & T-50 mechanical rooms      Spray-on material on ceiling. Up to 25%   Abatement completed for both mechanical
                                                            chrysotile asbestos.                      rooms.




REPORT        09-Sep-02
PAGE 4 OF 6
                                               NO LONGER RESTRICTED ACCESS REPORT
  BUILDIN                  LOCATIO                           DESCRIPTIO                               COMMENT

  Magnuson Health          BB-17th floor mechanical room     Spray-on material on ceiling.            Spray-on material was abated fall 1995.




  Mary Gates Hall          Crawl space                       Dirt crawl space with piping insulated   EHS conducted bulk sampling of the soil
                                                             with ACM.                                in this area and all samples and no asbestos
                                                                                                       detected.


  Parrington Hall          Basement mech room & sprinkler    Reported to have deteriorated asbestos   Confirmed past abatement action removed
                           room                              insulation.                              hazard.



  President's Residence    Dirt crawl space under sunporch   Dirt crawl space with asbestos debris    The area under the sun porch and the
                                                             contaminating space.                     crawlspace accessed via the laundry room
                                                                                                      were encapsulated with concrete in August
                                                                                                       2000.

  Purchasing/Accounting/   Orig. construction (excludes      Suspended ceiling tiles contain 3-5%     Abatement completed in October, 1991
  Parking                  parking div./acct.payable add.)   asbestos.



  Student Union Building   Room 112J, above suspended        Surface above ceiling tiles is           Area abated 10/98. Asbestos ceiling
  (HUB)                    ceiling (Foyer to auditorium).    contaminated with damaged asbestos       material debris and suspect pipe insulation
                                                             material from old textured ceiling       were all abated.


  U of W Medical Center    Incinerator - Room CC013A         Deteriorated asbestos pipe insulation.   Clean-up project previously conducted but
                                                                                                       suspicious material remained. EH&S took
                                                                                                      4 samples October 1990 and all had no
                                                                                                      asbestos detected.




REPORT         09-Sep-02
PAGE 5 OF 6
                                             NO LONGER RESTRICTED ACCESS REPORT
  BUILDIN                 LOCATIO                         DESCRIPTIO                               COMMENT

  U of W Medical Center   Cement crawl space off of old   Deteriorated asbestos existed in some    Abatement was completed in January 1992.
                          B-mechanical room               pipe chases and the crawlspace floor
                                                          below the chases.


  U of W Medical Center   Mechanical space at bottom of   Asbestos debris in space.                Abatement project completed May 1991.
                          BB-1 stair at -1 level



  U of W Medical Center   BB-306B (medical records)       Damaged pipe insulation above ceiling    Clean-up of area completed 12/93 after
                                                          at east side of room and in some other   discovery of damaged asbestos.
                                                          locations


  Utilities               MC-7 past MC-6                  Deteriorated asbestos insulation on      Area cleaned July 1990 from MC-7 past
                                                          pipework and floor.                      MC-6. MC-7 is not restricted and may be
                                                                                                   accessed either through Suzzallo or MC-6.
                                                                                                   West of MC-7 to the central parking garage
                                                                                                   is still restricted.

  Utilities               Abandoned MC trunk behind       Deteriorated asbestos insulation on      Abatement project conducted May 1991.
                          chiller bay in power plant      pipework and floor.




REPORT        09-Sep-02