Embed
Email

ABC Watermains Lemieux Island to Fleet Street PS

Document Sample

Shared by: yurtgc548
Categories
Tags
Stats
views:
0
posted:
1/22/2012
language:
pages:
38
City of Ottawa’s Lemieux Island Transmission

Main Replacement Program

Low and High Pressure Transmission Mains





by

Mike Willmets, City of Ottawa

Derek Potvin, P.Eng., Robinson Consultants

Presentation Outline



 Water Works History

 Existing Conditions

 Construction









2

Project Location









3

Project Overview

5 km of 1200, 1675, 1980 mm diameter

Transmission Main

 Serves 400,000 people within

City of Ottawa.

 Replaces three discharge

mains from Purification Plant.

 One of the Transmission

Mains operates as a low

pressure (gravity) suction

supply for a Fleet Street

Pumping Station and the other

operates at distribution system

pressure.





4

Water Wagon – Pre 1874









5

Why Supply Drinking Water?



 Water delivered by horse & wagon in

wooden barrels

 Era of Great Fires: Quebec City in 1845,

Montreal in 1852, Carleton County in

1870, Chicago in 1871

 Fire Insurance Underwriters

 Toronto - 1841, Kingston - 1850, Hamilton

- 1860





6

Thomas Coltrin Keefer

1821 - 1915

 Father of the Ottawa Water

Works

 One of Canada‟s greatest

engineers

 Built similar water systems

in Montreal, Hamilton &

Toronto







7

Harnessing the

Chaudiere Falls









8

Fleet Street Pumping Station



 Commissioned 1874

 Utilizing hydraulic energy

of Chaudiere Falls

 765m open aqueduct

built

 Capital Cost of $266,000







9

Ottawa Fire Brigade 1874









10

Great Fire of

Ottawa-Hull

1900

11

Ottawa’s Great Fire - 1900









12

Typhoid Epidemics









 1 epidemic in 1911, 2 epidemics in 1912

 1900 to 1915 - 512 related deaths

 1916 to 1925 - 18 related deaths

 Nepean Bay pollution

13

ABC Lines



Lemieux WPP









Fleet P.S.









 Three of the most important mains

 Critical to operation of system

 Unique Pipes in a Unique Setting







14

Lock Bar Pipe









 Two semi-circular sections joined by a „lock bar‟

 Lock bar is long strip of metal with an „H‟ shaped cross

section

 Riveted joints to join pipe to pipe



15

Delivery of “A” Line Piping 1915









16

“C” Line Construction 1937 - 50









17

Existing Pipe Condition

 Corrosion pitting leads to leakage.

 Corrosion of rivets & lock bar can

lead to pipe failure.

 “A” & “B” Line‟s cement lining (circa

1950) was delaminating which

accelerated internal corrosion.

 “C” Line was in good condition but

required relocation for planned

development.









18

Site Constraints



 Federal Land

 LeBreton Flats

Development

 Past Land Uses

 Breezehill/Scott

Feedermains

 Subsurface

Conditions









19

Existing Site Conditions

 Adjacent to former Municipal Waste Site » Contaminated Soils and Groundwater

» Highly Corrosive Environment.

 Area formerly part of Ottawa River » Significant area of unconsolidated fill

material.

 Adjacent to Ottawa River » Dewatering issue during construction.

 Area formerly an industrial development » Subsurface remnants and

contamination.

 Crossing major Lemieux Island WPP

transportation corridors »

Traffic Implications.

 Construction within existing

aqueduct channel »

Protection of watermain.

 Construction within existing

AWWA Canadian

Waterworks Landmark and Fleet Street

Heritage Structure » Fleet Pumping Station

Street Pumping Station.

20

Historical

Land Uses









21

Subsurface Conditions

Lemieux Island WPP









Bayview Yards

Low Pressure WM



Nepean Bay









High Pressure Transmission Main









22

Geotechnical Conditions









 Unconsolidated fill from Nepean Bay and Ottawa River Parkway

over bedrock

 Long term settlement concerns and significant dewatering



23

Dynamic Compaction

 Large Un-consolidated Fill Zone on reclaimed land » former bay of

the Ottawa River.

 Dynamic Compaction used to prepare watermain alignment prior to

construction.

 Large steel weight dropped from crane to achieve consolidation.



 Compaction can be achieved to

over 10m depth.

 Compaction carried out using

grid pattern to cover area.

 Compaction testing carried out

after completion.







24

Corrosion Potential Investigation









25

Preferred Alignment









26

Design Requirements

 100 Year Design Life Required.

 Must maintain water supply to customers.

 LPTM to serve dual purpose » Operate

primarily at low pressure with conversion to

high pressure based on demand.

 HPTM to supply water to distribution system

from pumping station at WPP.









 Must maintain access to existing

purification plant.

 Must protect existing heritage

structures » Fleet Street Pumping

Station and Open Aqueduct.





27

Watermain Materials

 Concrete encased, polyurethane coated, steel

pipe and concrete pressure pipe utilized to

protect against corrosion.

 Gasketless, double lap welded, bell and spigot

joints specified to protect against groundwater

ingress in landfill zones.

 Transition between material types at valve

chambers.

 Cathodic protection installed throughout.









28

Ruins from Previous Development

 Previous railway structures, bridge abutments, building foundations and

superstructure debris uncovered in the watermain excavations.

 Previous factory foundation and tunnel uncovered within the

excavations.









29

Concrete

Encasement

 150 mm concrete encasement

 Pipe strapped to concrete slabs to

counterbalance buoyancy









30

Open Aqueduct Installation

 Coated concrete pressure pipe installed in

existing open aqueduct channel.

 Channel is a “neighbourhood feature” and a

designated heritage structure.

 High density polyethylene shield added to protect

watermain from objects falling or being thrown

into water.

 Gasketless expansion joints used between fixed

supports to allow for temperature movements.









31

Fleet Street Pumping Station

 Existing AWWA Canadian Water Works

Landmark and heritage structure.

 Turbine pumps driven by water from

Ottawa River » fed by aqueduct system.

 Connection of new transmission main with

valve chamber to switch to high pressure

operation » by-passes pumping station.









 Included replacement of existing suction

header piping in station.

 Installation of sluice gates to isolate

pump turbines from aqueduct flows

during maintenance.

 Included measures to protect existing

structure from damage during

construction.

32

Bridge Pipe Rehabilitation



 Couplings repaired and

internal joints seals

installed.









33

Tunnel Construction

 Transmission Main constructed in casings across major roads,

parkways, railways and rapid transit bus route.

 Steel pipe electrically isolated from casing pipe via casing

spacers.

 Annular space grouted.









34

Ottawa River Parkway Crossing

 Crossing of existing federally owned

four-lane, divided parkway required.

 Open trenching construction due to

presence of methane from landfill »

explosion hazard during jacking and

boring operation.

 Existing fill material not suitable for

jacking and boring » large boulders.

 Installation of concrete casing pipe

completed over one weekend road

closure.

 Welded steel watermain inserted by

jacking methods after completion of

casing.









35

Not all goes as planned!





 Steel pipe partially

collapsed during grouting.



 Protrusion cut out, grout

removed and new repair

sleeve welded in place.









36

Valve Chambers

 Steel pipe continued through the valve chambers.

 Features: air valves, drain valves, line valves, branches and

access manholes









37

Thank you !

Merci !



38



Related docs
Other docs by yurtgc548
AC120 lecture 26
Views: 1  |  Downloads: 0
ABSTRACT - GPCET MCA EMERALDS
Views: 0  |  Downloads: 0
Absolute Garbage Systems
Views: 1  |  Downloads: 0
Abnormal Psychology
Views: 0  |  Downloads: 0
ABC of Arterial and venous Disease
Views: 0  |  Downloads: 0
Abacus Fund Management LLC Presentation
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!