Embed
Email

Target Price Contract

Document Sample
Target Price Contract
Description

Target Price Contract document sample

Shared by: krb13351
Categories
Tags
Stats
views:
17
posted:
1/20/2012
language:
pages:
4
62







ECONOMICS

ANALYSIS . .FACTS FORECAST









Procurement Target price contracts

In today’s overheated market, clients need all the help they can get to deliver good-value, low-risk

projects. Some clients are turning to collaborative working – and contracts such as the NEC – to

provide an extra incentive. Simon Rawlinson of Davis Langdon examines the issues







01 Introduction



Construction is a high-risk activity and design-and-build procurement accounts covering all project risks, are intended in

much effort has been focused over the years for more than 43% of the market. part to help eliminate sources of

on eliminating this risk. Studies, such as As risk transfer to the contractor does not unproductive and risk-averse working

Improving Public Services Through Better necessarily improve the project outcome, practice by project participants motivated

Construction by the National Audit Office, there are many initiatives focused on by the need to manage their design-related

suggest that many of these initiatives, business improvement, particularly on insurance liabilities on an individual basis

which are often focused on transferring enabling participants to collaborate ■ Contractual arrangements, including

rather than managing risk, reduce effectively. These include: standard partnering contracts such as

contractors’ motivation and performance. ■ The development of information exchange PPC2000 and the recently launched

Even so, many clients continue to transfer standards and processes to help JCT Constructing Excellence contract.

risk to contractors through design-and-build project teams to promote effective, Procurement policy is especially important

contracts, arguably giving contractors information-enabled collaborative working for public sector clients, who must set high

greater control over projects. The latest ■ Financial arrangements such as insurance standards as employers, be accountable to

RICS Contracts in Use survey indicates liabilities. Single project insurance policies, the public and deliver best value.







02 NEC contracts and co-operative working



The NEC exemplifies many aspects of The NEC promotes many aspects of Focusing the team on achieving these goals

co-operative working. The target cost co-operative working, including: is important if the full benefits of the NEC are

options allow public sector clients to provide ■ Focusing the whole team on delivery to be secured. However, a number of ways of

off-the-shelf incentives, and back this up with ■ Equal sharing of risk circumventing its processes have emerged,

systems that allow for performance payments ■ Managing risk rather than transferring it through contract amendments or variable

within a framework of accountability. ■ Continually assessing cost, time and quality. commitment to sound administrative practice.







03 Target contracts



The most widely used variants of the NEC are Target contracts are best used on client, it can modulate its exposure to risk.

options C and D, both target contracts. The well-defined projects, where the contractor Used effectively, target contract options

main difference between a target contract has a motivation to reduce costs, rather than should give the incentive to deliver a project

and a conventional contract is the mechanism on projects that are loosely defined, as on time and to budget. However, if costs fall

for sharing risk and opportunity. While the changes in project definition are likely to out of control, the contractor may seek to

client retains the cost and time risk linked to change the value of the target price. increase the target via compensation events.

contractual changes, the financial effects Using this approach, equitable risk transfer In this case, a greater burden of cost overrun

of cost overruns can be shared between the is often adopted to encourage positive risk may transfer to the client than intended.

client, contractor and supply chain. This is behaviour. That said, as contractual share of As such, effective administration by the

often termed the gain/pain share mechanism. risk and gain/pain mechanism are set by the project manager and contractor is vital.









BUILDING MAGAZINE 14.09.2007

economics.procurement 63









04 How a target cost contract works



Under a target contract, a contractor is with a combination of lump-sum and actual the pain option is exercised. This could involve

reimbursed for the cost of the works, including costs incurred, the incentive mechanism and the contractor taking 100% of the liability

those of subcontractors, some elements commitment to deliver the project on time and, as such, suffering the loss. Alternatively,

of establishing the site and the fee for the are fixed. However, should any allowable the client may shoulder part of the loss.

items listed in the contract as actual or compensation events occur that result in a The contractor would ideally meet the target

defined costs. These include management change to cost or programme, the target will cost, in which case it would receive full

costs, overheads and profit. be adjusted by the actual cost incurred or by remuneration. Savings against the target

The contractor is contractually committed a lump sum, depending on how the contractor would be shared with the client. The worst

to meeting the target cost, which comprises and project manager agree them. outcome for the client is the contractor being

the cost of the works described in the works After the project is completed, payments paid more than the revised target cost.

information, activity schedule or bill of made to the contractor are compared to the The difference between the target cost and

quantity, plus a fixed percentage fee. revised target cost. Depending on the the actual cost is, of course, fundamental to

The target cost and the contractor’s outcome, the gain/pain share mechanism the incentive model. However, the lack of

reimbursement are not linked until the end agreed in the contract will come in to play. a direct link during construction means there

of the project, when the gain/pain share Typically, the gain share involves splitting is a risk that the project team could lose sight

mechanism is applied. What the contractor the amount of money saved, that is, the of its target and incentive. Therefore:

recovers through regular payments is the difference between the target cost and the ■ The target cost should be realistic, based on

actual cost incurred, along with the actual expenditure, between the client, a fully set of works information. Target cost

percentage fee. contractor and possibly some subcontractors. contracts are sometimes misunderstood as

While the contractor is paid in accordance If the project’s costs exceed the target cost, being incentivised develop-and-construct

approaches, where a project team is

encouraged to work from an outline concept

to deliver a solution focused on a client’s

needs. Unfortunately, a project let without

well-defined works information resulting from

incomplete design development is highly likely

to require substantial changes and result in

compensation events and amendments to the

target cost. In reality, the documentation

required to support the contract will be as

detailed as a lump-sum contract.

■ It should be set at a level that acts as an

incentive. Too low, and the contractor will

recover costs by other means. Too high, and

inefficient working may be rewarded.

■ It should be based on a detailed programme.

The target cost mechanism cannot be properly

administered without considering the impact

of compensation events. Without this, it is not

possible to assess the responsibility for delay.

■ The client must understand that it is not a

lump-sum contract and should co-operate

with the project manager in administering

the contract. Failing to comply with timescales

can lead to a client creating liabilities for

itself under the NEC.

■ It is important for the contractor to keep

track of costs incurred relative to the

adjusted cost, so its own commercial position

is protected. In some cases, where

subcontractors are also incentivised, this may

involve the project manager and contractor

in the audit of material supply invoices and

labour returns, to confirm levels of

A target price contract has helped control costs on the £4.2bn Heathrow Terminal 5 expenditure.





BUILDING MAGAZINE 14.09.2007

64 economics.procurement









05 Effective management and maintenance of incentives on target cost contracts



Target contracts operate by encouraging events being grouped together for programme. Many clients and project

good purchasing and contract management assessment. However, as long as the managers do not feel comfortable agreeing

so long as the incentive is understood by the assessment is kept up to date, the contractor these impacts in advance as the contractor

contractor and the target remains visible. and client will understand their position. may on some occasions secure an upside.

Given the administrative demands of the Other challenges include: Early assessment does, however, facilitate

NEC contract, there is a risk that the link ■ Managing alternative financial good decision-making. A degree of risk

between target and actual cost entitlements motivations, such as: sharing is also built into the assessment.

could be lost, and the client could be ● Chasing turnover. As contractors are If impacts are assessed retrospectively once

exposed to a significant transfer of cost risk. compensated, in part, by a fee, there may costs are known, they are more likely to

This exposure can be managed by the be pressure to increase recovery through be awarded on the basis of cost and time

gain/pain mechanism. defined costs during the contract rather rather than as a target.

There are a number of characteristics of than secure gain share at the close. Where the employer has a well-defined

target contracts that clients and their project ● Optimism with regard to cost recovery. scheme that presents opportunities for

managers need to manage to maintain the Owing to the disconnect between the cost saving via effective procurement and

incentive. These include: contractor’s costs and their entitlement management, a co-operative approach based

■ Management of the information flow. The under the adjusted target cost, it is essential on risk sharing may be an incentive. The

NEC workflow is extensive and complex, so contractors appreciate what their entitlement employer must appreciate, however, that the

a management system should be in place to is likely to be and what their costs are. project has to be sufficiently well defined

support the project manager and contractor ● Assessing compensation events in advance. to enable a realistic target to be set and that

in meeting timescales and updating reports. The NEC gives the option for the target cost the contractor and project manager must

On projects worth more than £10m, to be amended by means of agreed understand the relationship between target

web-based extranet systems designed to quotations, addressing both future cost and and actual costs.

support the NEC workflow are invaluable.

■ Dealing with the learning curve. The

cultural changes associated with incentivised

contracts and the NEC are substantial. Many

parties may not fully appreciate the benefits

to innovation or project management.

■ Use of the contract. On a JCT-based project

the contract stays in the drawer unless there

is a problem; under NEC the opposite applies.

If the contract is not referred to regularly,

problems are likely to build up.

■ Rebalancing risk transfer. Some of the

compensation events under NEC can expose

the client to risk. Examples include the

prevention event, which transfers risk of many

remote events to the employer. A common

but less equitable amendment deals with

the impacts of poor project management

performance linked to the issue of notices.

■ Effective use of the contract’s risk

management provisions.

■ Maintaining the programme. Assessment

of the programme in real time is an essential

element of the NEC philosophy. It is essential

that the programme is kept up to date. Under

the target cost option, adjustments should be

based on a pre-assessment of the impact of

specific compensation events. Under a typical

post-hoc assessment extension of time, the

pressure is to recover all the delay costs, even

if some result from aspects of the contractor’s

management. In practice, programme impacts

are often managed imperfectly under NEC

with, for example, a series of compensation The high-speed rail link to St Pancras also benefited from a target price contract







BUILDING MAGAZINE 14.09.2007

economics.procurement 65









06 Case study



The case study is based on a commercial preliminaries, overheads and profits. procedures. The compensation system also

project using NEC2 with both the main The actual cost was assessed through came under pressure owing to the volume

contractor and some subcontractor packages guaranteed payment and audited costs. of changes required. That said, specialists

being subject to target cost incentives. The There was no pain share mechanism, which quickly understood the importance of the

employer adopted a target cost approach to meant the only allowable upward increase process, although it was difficult to agree

achieve a balance between risk transfer and in costs came from the assessment of “upfront” adjustments to the target costs.

demand on in-house administration. compensation events. These could trigger an In the final analysis, the project was a

The agreed gain/pain share was based on increase in the value of the target costs considerable success, delivered below budget

a combination of fixed-sum preliminaries, related to the value of the work, together with and ahead of programme. Most specialists did

overheads and profits. It rewarded early an uplift for overhead, profit and preliminaries well out of the project, although some lost

completion and provided some cushion for related to duration. control of their own administration and costs.

cost overruns. The gains would be divided In practice, not all subcontractors were able Some specialists introduced real innovation

50:25:25, between the client, main to buy into the opportunities represented by in their procurement and management to

contractor and subcontractors respectively. the gain share. Reasons included: secure maximum savings and to maintain

The target cost was established using a ■ Wondering why it was needed. Guaranteed control over their own costs.

well-developed design produced after a preliminaries helped to gain their confidence In general, cost control was heavily

two-stage procurement process. In stage one, ■ In the late stages of design, cost-saving incentivised and the project was sufficiently

specialist contractors competed on overhead, opportunities related to buying power only well defined for the inducement to make an

profit, preliminaries and schedules of rates. ■ Contractors’ control of their own costs. impact, even though there continued to be

In stage two, the specialist either agreed Some specialists were ineffective in significant commercial issues affecting the

a lump sum or, where there were genuine controlling costs and accounting and could project throughout. Whether in less positive

opportunities for performance improvement, not track target and actual costs accurately. circumstances the target cost mechanism

a target cost approach was adopted. The administration processes used on the could have provided the right balance of

The target cost was settled from quotations contract took some time to settle down, control and motivation is difficult to conclude,

and guaranteed lump-sum payments for emphasising the need for a familiarity with but on this project it played a part.







07 Advantages 08 Disadvantages



■ Provides contractors and subcontractors ■ Requires contractor to share savings

with an incentive to improve performance derived from improved performance with the

and enables the client to secure a share of client and other members of the supply chain

the benefits of a well-managed project ■ Client and contractor must share gain and

■ Encourages active and equitable risk pain if the full benefits are to be secured. The

sharing, based on a clearly defined allocation client may have greater exposure to cost risk

of risk agreed at the outset of the project. ■ Potential for failure on insufficiently

■ Can incorporate lump-sum and prime-cost defined projects owing to misunderstandings

subcontracts under a single target price of the operation of the incentive mechanism

■ Target costs provide incentive for ■ Complex target price, gain/pain share and

the timely administration of change change controls may not be understood by all

control mechanisms ■ Separation of target and actual costs

■ Provides an accountable mechanism to before completion creates the potential

enable public sector clients to use incentives. for loss of control

■ Provides an incentive for the effective ■ Relies on administration best practice and

management of prime cost contracts. a competent project manager.





Coming up … Data toolkit

21 Sep The tracker; Building’s extensive database of cost data

Country focus: Hungary is an essential resource for anyone in the

28 Sep Specialist cost business of procuring buildings. Gain

update instant access to this valuable information

5 Oct Cost model at www.building.co.uk/datatoolkit









BUILDING MAGAZINE 14.09.2007


Related docs
Other docs by krb13351
Suzuki Market Strategy
Views: 7  |  Downloads: 0
Tax Deduction Account No
Views: 4  |  Downloads: 0
Swat Medical History Form
Views: 3  |  Downloads: 0
Swot Analysis Aircraft Industry
Views: 19  |  Downloads: 0
Surgical Technology Student Answer Key
Views: 12  |  Downloads: 0
Target Retail Employment
Views: 0  |  Downloads: 0
Talent Hunt Competition Event Presentation
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!