Project Progress
between review meeting #2 and #3
Peik Jenssen
Copenhagen 25 May 2000
DNV - 19/01/2012 - 1
DET NORSKE VERITAS
Progress
Overall status per May 2000:
• Cost statements for year one accepted with comments by CEC
• Deliverables due this period were:
T3.2D1 Prototype code for integration tool (month 11)
T4.1D1 Validation of prototype (month 15)
T3.1D2 Final specification of software and interfaces (month 15)
• T3.2D1 demonstrated for project team PSG members in month 13
• T4.1D1 and T3.1D2 will be delivered next month
DNV - 19/01/2012 - 2
DET NORSKE VERITAS
Progress
WP 1: Analysis and modelling of agile maritime
enterprises (GL)
T1.1: Analysis and modelling of business processes
• Scenario specification and process model finished for both
scenarios
• Data exchange events identified in both scenarios
• Ongoing work concerning the process description of the P&I Club
DNV - 19/01/2012 - 3
DET NORSKE VERITAS
Progress
T 1.2: Analysis and modelling of business information
objects and product data
• Completion, harmonisation and refinement of data models
• New structure of AP234
• Introduced BB
• Other MARVIN BB’s renamed and re-structured
• Syntax refinement of the EXPRESS and EXPRESS-G models
• Creation of EXPRESS long form of the models to be used in
first prototype and interface implementation
DNV - 19/01/2012 - 4
DET NORSKE VERITAS
Progress
T1.3: Virtual enterprise architecture
• Feedback from Task 3.1 and 2.3 incorporated in T1.3D2
• Refinements in the Design of the Virtual Enterprise Architecture,
especially concerning the interface specification
DNV - 19/01/2012 - 5
DET NORSKE VERITAS
Progress
T1.4: Legal framework of virtual organisations
• Review of security issues: Confidentiality, encryption and
digital signature
• Review of contractual issues: choice of law, liability, etc.
• Study of use of tool for special maritime contracts
DNV - 19/01/2012 - 6
DET NORSKE VERITAS
Progress
WP 2: Interfacing of business processes with web (LMS)
T2.1: Contribution to emerging standards
• New structure of AP234
• Ship_Operational _logs is now formally a Building Block
• Further improvements in models of AP215 and AP234
• Further validation of existing BBs of the ship product model,
especially AP215 and AP234
DNV - 19/01/2012 - 7
DET NORSKE VERITAS
Progress
T2.2: Prototyping of interface modules
• Information for Data Exchange in Emergency Response
Scenario gathered for:
Express Data Models
Virtual Enterprise Architecture Concept
• Information gathered for the legacy systems to be interfaced
• Development of the interface software
DNV - 19/01/2012 - 8
DET NORSKE VERITAS
Progress
T2.3: Development of interfaces
• Analysis of the need for data exchange both scenarios
• Identification of Express Data Models
• Information gathered on integration of interfaces into Virtual
Enterprise Architecture
• Information gathered for the legacy systems to be interfaced
DNV - 19/01/2012 - 9
DET NORSKE VERITAS
Progress
WP 3: Development of MEIT (IWi)
T3.1: Specification of tool and interfaces
• Functionality of MEIT and interfaces determined and described
for final release (preliminary)
• Architecture of MEIT and agent architecture described for final
release
DNV - 19/01/2012 - 10
DET NORSKE VERITAS
Progress
T3.2: Prototyping of integrating tool
• Debugging of major parts performed
DNV - 19/01/2012 - 11
DET NORSKE VERITAS
Progress
T3.3: Development of integration tool
• Developed agents and user interfaces for
ship crew
ERC
ship owner
• Design and construction of database for
ship crew
ERC
ship owner
• Re-design of communication layer
• Generator of intermediate file for interfaces
DNV - 19/01/2012 - 12
DET NORSKE VERITAS
Progress
WP 4: Validation of software tools (Neorion)
T4.1: Validation of prototypes
• Collected user requirements
• Described the validation methodology
• Created validation report forms
• Collected data for validation
DNV - 19/01/2012 - 13
DET NORSKE VERITAS
Progress
WP 5: Project management, public demonstrations
and exploitation of results (DNV)
T5.1: Local project management
• Co-ordination at site and nationally
• Quality audit at partner sites in progress
DNV - 19/01/2012 - 14
DET NORSKE VERITAS
Progress
T5.2: Global Project management
• Meetings
WP meeting #5 in Patras on 2000-01-17/19 (LMS)
WP meeting #6 in Oslo on 2000-04-5/7 (IRI)
PSG meeting #2 Patras on 2000-01-18
PSG meeting #3 in Oslo on 2000-05-06
Telephone conferences normally every second week (12 in total)
• Continuous follow-up of actions
• Most important quality improvement items identified
DNV - 19/01/2012 - 15
DET NORSKE VERITAS
Progress
T5.3: Public demonstrations
• First public demonstration of prototype planned at Ship Repair
and Conversion 15 - 16 November
DNV - 19/01/2012 - 16
DET NORSKE VERITAS
Progress
T5.4: Preparation of dissemination and exploitation
of results
• Papers presented:
Software 2000, Oslo (Norway) 2000-02-08
COMPIT, Potsdam (Germany) 2000-03-30
PDT Europe 2000, Noordwijk (The Netherlands) 2000-05-02
• Papers accepted:
E-business and e-work, Madrid (Spain) 2000-10-18/20
MITIP 2000, Plsen, (Czech Republic) 2000-06-05/06
SMM, Hamburg (Germany), 2000-09-29
DNV - 19/01/2012 - 17
DET NORSKE VERITAS
Progress
T5.4: Preparation of dissemination and exploitation
of results
• Exploitation:
Established contact with 3 Norwegian ship owners
Developed the Exploitation plan further
Considered MARVIN results in business development in DNV and GL
Plan to carry out market research this year
DNV - 19/01/2012 - 18