EAST COAST RAILWAY

TENDER NOTICE



No. WHS / 24 / VSKP COLONY CONTRACT / WEST / 1636 Dated: 06-08-.2009



Chief Medical Superintendent, East Coast Railway, Waltair for and on behalf of the President of

India invites tenders in sealed cover along with name / address of the tenderer, from

experienced conservancy contractors for the under mentioned work within the jurisdiction of

Chief Medical Superintendent, East Coast Railway, Waltair, for a period of TWO YEARS from

the date of Awarding the Contract. .

Name and Value of contract, cost of the tender form & Earnest money are furnished hereunder.



Name ofthe Contract for collection of 750 Cft., of garbage per day from

Work various West Sector Railway colonies of Visakhapatnam i.e.,

Gurkhaline Colony, MSM Colony, S & C Colony, DLS Colony, MPM

South & North colonies and final disposal to the nominated dumping

ground of Greater Visakhapatnam Municipal Corporation ( G.V.M.C.)

at Kapuluppada, by engaging a Mechanised carrier along with

Driver, Fuel , Labour, equipments, etc., required for the same, for a

PERIOD OF TWO YEARS.

Value of the Rs. 14,21,680 /- (Rupees Fourteen lakhs Twenty One thousand Six

work for TWO hundred and Eighty only).

Years.

Cost of the Rs. 2,000/- (Rupees TWO thousand only).

Tender Form.

Earnest Money Rs. 28,434 /- Rupees Twenty Eight thousand Four hundred and

Deposit. Thirty Four only.



1. The prescribed tender Document (non-transferable) with full particulars can be

obtained up to 11.00 Hrs. of 30-09-09 from the office of the Chief Medical

Superintendent/ East Coast Railway / Visakhapatnam, on any working day on

production of a Money Receipt for Rs.2, 000/-(Rupees TWO Thousand only) per

set (non refundable) issued by the Divisional Cashier, East Coast Railway, Waltair

towards the cost of “Tender Form”. No money orders towards cost of tender

form will be accepted.



2. The last date and time of issue of tender form Up to 11-00 hrs. of 30-09-2009

The last date and time of receipt of tenders Up to 15-00 hrs. of 30-09-2009

Date and time of opening of tenders At 15-30 hrs. of 30-09-2009



If the date of opening happens to be a Bandh or holiday the tender will be opened

at the same time on the following working day.

Contd..P.2



West Sector Contract -2009-pro.doc9

Page – 2



3. The documents will also be available in the Websites at

www.eastcoastrailway.gov.in & http://tenders.gov.in during the period from

30-08-09 to 30-09-09 and can be down loaded and used as tender documents for

submitting the offer. Separate remittance towards the cost of tender documents

of Rs.2,000/- (Rupees Two Thousand only) have to be enclosed in the form of

demand draft drawn in favour of F.A. & C.A.O, East Coast Railway, Bhubaneswar,

payable at Visakhapatnam, along with the tender, otherwise, the tender will be

summarily rejected. Railway Administration shall not be responsible for any delay /

difficulties / inaccessibility of the down loading facility for any reason whatsoever.



4. In case of any discrepancy between the tender documents down loaded from

internet and the master copy of the same available in the office of Chief Medical

Superintendent / E.Co.Raiway / Waltair, the latter shall prevail and will be binding

on the Tenderer(s). No claim on this account will be entertained.



5. A Crossed Demand Draft / Bank FDR drawn on any Nationalised / Scheduled Bank

for Rs. 28,434 /- (Rupees Twenty Eight thousand Four hundred and Thirty Four

only. ) has to be enclosed with the tender form towards EMD while submission

of Tender document, duly issued in favour of FA & CAO / East Coast Railway /

Bhubaneswar, payable at Visakhapatnam.



6. The complete Tender Document to be dropped up to 15.00 Hrs. of 30-09-2009

in a sealed tender box kept in the office of Chief Medical Superintendent, East

Coast Railway, Waltair, and opened at 15.30 Hrs. on the same day in the

presence of the tenders or their authorized representatives in the Seminar Hall

of the Divisional Railway Hospital, East Coast Railway, Visakhapatnam. No tender

will be accepted or considered if received after the aforementioned date & time.



7. The complete Tender Document can also be sent in sealed cover under Registered

Post with Acknowledgement Due / Speed post / Courier to the address of Chief

Medical Superintendent, East Coast Railway, Waltair, Visakhapatnam – 530 004

( A. P. ) So as to reach on or before the time and date mentioned above. The

Railway Administration will not be responsible for any postal delay.



8 The Tenderer is supposed to have surveyed the work (as per the work Schedule)

and assess the quantum of work personally before dropping the tender.



9. Guarantee Bonds are not accepted for EMD.



Contd..P.3



West Sector Contract -2009-pro.doc9

Page – 3



10. The Contract will be for a period of TWO YEARS from the date of issuing the

Letter of Acceptance.



11. No intimation will be sent to unsuccessful Tenderers.



12. The Railway Administration reserves all the rights to modify / cancel / discharge

a part or complete tender without assigning any reasons to Tenderers.



13. The rate quoted should be in figures and words, in case of any discrepancy in the

words and figures, the rate quoted in words will be taken into cognizance as final

rate.



14. The Tender Document contains as given below:

Tender Form including Tender instructions, Terms & Conditions, Schedule

of work, Special Conditions of the Contract and Financial Bid.



16. For any other information, the office of the Chief Medical Superintendent, East

Coast Railway, Waltair, may be contacted on any working day.









Chief Medical Superintendent,

East Coast Railway, Waltair.







Copy to Sr.DFM/WAT,Sr.DPO/WAT, Sr.DEN(Co-Ordn)/WAT, Sr.DCM/WAT,Sr.DSTE/WAT,

Sr.DOM/WAT, Sr.DSC/WAT, Dy.CE ( S & C )/WAT for information.

Copy to CMD / E.Co.Railway / BBS for kind information please.

Copy to DRM( Engg.) E.Co.Railway / WAT for information & to upload the same in the Railway

and Govt.Web-sites.

Copy to CPRO / BBS with a request to publish this Tender Notice in all leading News papers

of Telugu, Oriya, Hindi and English as per DAVP norms.









West Sector Contract -2009-pro.doc9

EAST COAST RAILWAY



NAME OF THE WORK :

Contract for collection of 750 Cft. of garbage per day from various West Sector

Railway colonies of Visakhapatnam i.e., Gurkhaline Colony, MSM Colony, S & C Colony, DLS

Colony, MPM South & North colonies and final disposal to the nominated dumping

ground of Greater Visakhapatnam Municipal Corporation ( G.V.M.C.) at Kapuluppada, by

engaging a Mechanised carrier along with Driver, Fuel , Labour, equipments, etc.,

required for the same, for a PERIOD OF TWO YEARS.



TENDER NOTICE No: WHS / 24 / VSKP COLONY CONTRACT / WEST /1636, Dt:06-08-09



APPROXIMATE TENDER VALUE FOR TWO YEARS - Rs. 14, 21,680 /-



EARNEST MONEY DEPOSIT - Rs. 28,434/-



SECURITY DEPOSIT: Rs.71,085/-



COST OF THE TENDER FORM: Rs 2000 /-



TENDER FORM SOLD TO Sri / Smt /Ms.-------------------------------------------



MONEY RECEIPT / D.D./ NO: ------------------------------------------------------



DATE ---------------------------------------------------------------------------------









Signature of Issuing Authority with Stamp









West Sector Contract -2009-pro.doc9

EAST COAST RAILWAY







TENDER NOTICE No: WHS / 24 / VSKP COLONY CONTRACT / WEST / 1636, Dt:06-08-09.



NAME OF THE WORK:

Contract for collection of 750 Cft. of garbage per day from various West Sector

Railway colonies of Visakhapatnam i.e., Gurkhaline Colony, MSM Colony, S & C Colony, DLS

Colony, MPM South & North colonies and final disposal to the nominated dumping

ground of Greater Visakhapatnam Municipal Corporation ( G.V.M.C.) at Kapuluppada, by

engaging a Mechanised carrier along with Driver, Fuel , Labour, equipments, etc.,

required for the same, for a PERIOD OF TWO YEARS.



To

The President of India,

Representing the East Coast Railway through

Chief Medical Superintendent

East Coast Railway, Waltair,



Sub: Contract for daily collection of 750 Cft.,per day of garbage from various West

Sector Railway colonies of Visakhapatnam i.e., Gurkhaline Colony, MSM Colony,

S & C Colony, DLS Colony, MPM South & North colonies and final disposal to the

nominated dumping ground of Greater Visakhapatnam Municipal Corporation

( G.V.M.C.) at Kapuluppada, by engaging a Mechanised carrier along with

Driver, Fuel , Labour, equipments, etc., required for the same, for a PERIOD

OF TWO YEARS.



Ref: Your tender Notice No. -------------------------------------------dt.----------------



Published in the Newspaper of ----------------------------------dt------------------



Dear Sir,



I/We…………………………………………………………………………………….………………………………………………….



of……………………………………………………………… do hereby tender for entering into an Agreement

with the President of India acting in the premises through the Divisional Railway

Manager(Medical), East Coast Railway, Waltair, for the subject work as detailed in

Schedule of Work in Annexure- “B” at the rate quoted/ recorded by me /us in

Annexure “D” for various West Sector Railway colonies of Visakhapatnam under East

Coast Railway Administration.







Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.





West Sector Contract -2009-pro.doc9

1. The rate quoted by me/us in Annexure “D” attached herewith is in full

satisfaction of all claims.

2. In the event of acceptance of this tender, I/We agree to observe and kept to

be bound by the “TERMS & CONDITIONS” set out in the Annexure “E” to this

tender from which is subject to such modifications as may be deemed

necessary by the Divisional Railway Manager (Medical) for and on behalf of the

President of India and agreed by me/us and I/We will be prepared to enter into

the License Agreement with or without modifications to those set out in the

Tender Schedule with all its enclosures, with the President of India acting in

the premises through the Divisional Railway Manager(Medical), within 15 days

from the date of intimation of the acceptance of my /our tender.

3. I/We agree to abide by the conditions and stipulations explicit or implied laid

down in the “INSTRUCTION TO TENDERERS” attached as Annexure “A” as well

as “SPECIAL CONDITIONS OF THE CONTRACT” attached as Annexure “C”.

4. The tender offer submitted by me/us shall remain open for a period of 120 days

from the date of submission of the tender and I/We also agree that in the

event of withdrawal of the said offer by me / us the amount deposited towards

earnest money is liable to be forfeited by the Railway administration and my /

our tender shall not be considered for acceptance.

5. This tender is submitted is INCLUDING FINANCIAL OFFER as instructed.

6. This tender is submitted on the understanding that if it is accepted, I/We shall

within 15 days from the date of intimation of acceptance of the tender by the

Railway administration:-

i) Execute the Agreement in the form prescribed, with or without

modifications to those set out in the Tender Schedule with all its

enclosures , for carrying out the work according to the South Eastern

Railway GCC and standard specifications as in Volume – II, and

ii) Take up the Conservancy work as prescribed in the Agreement.

iii) I/We ,further agree that in default of my/our taking up the work within

a period of 15(fifteen) days from the date of intimation of acceptance

of the tender by the Railway administration,/ I/We shall have no claim

on the forfeiture of the EMD deposited by me/us.

iv) Until a formal agreement is prepared and executed acceptance of this

tender shall constitute binding contract between us subject to

modifications as may be mutually agreed to between us and indicated in

the letter of acceptance of my / our offer for this work.









. Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.









West Sector Contract -2009-pro.doc9

7. A money receipt on………………………………dated……………………granted by the Divisional



Cashier, E.Co Rly, Visakhapatnam, OR / Pay Order / Demand Draft No------------



dated--------------for Rs.----------------------(Rupees-------------------------------



-------------------------------------------------------------------------only) issued by



the----------------------------------------(Scheduled/ Nationalized bank) showing

the requisite/required amount of earnest money for the tender, in favour of

the Financial Advisor & Chief Accounts Officer, East Coast Railway,

Bhubaneswar, Payable at Visakhapatnam, is attached herewith in original.



8. I/We are enclosing herewith the FINANCIAL OFFER duly filled in attached as

Annexure “D” along with original EMD receipt and necessary certificates/

document in support.



Encl: As above.



Yours faithfully,







Signature(s) of Tenderer(s) with Seal.



Name(s) of Tenderer(s):-____________________________________________

(In Block Letters)



Address: Office: - ___________________________________________



___________________________________________



Residence: - ___________________________________________



___________________________________________



Place: ________________



Date: ________________







Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.









West Sector Contract -2009-pro.doc9

ANNEXURE “A”



INSTRUCTIONS TO TENDERERS IN CONNECTION WITH THE COLLECTION

AND DISPOSAL OF GARBAGE BY MECHANISED CARRIER FROM WEST SECTOR

RAILWAY COLONIES OF VISAKHAPATNAM.

DEFINITIONS:-

Throughout this tender document the following definitions shall apply.

i) The “Railway Administration” means Indian Railways, East Coast Railway acting

through DRM (Medical), Waltair on behalf of the President of India.

ii) The “Inspecting Officer” / Inspector mean the official, firm or department

nominated by the “Railway Administration” to inspect the work on his behalf and

the deputies of the inspecting officer so nominated.

iii) The “Contractor” means the person, firm or company on whom the order for the

execution of the work is placed and shall be deemed to include the contractors’

successors (approved by the “Railway Administration”) representatives, heirs,

executors and administrators as the case may be unless excluded by the terms of

the contract.

iv) “Contract” means and including the notice inviting tenders, instructions to the

Tenderers, technical specifications and drawings, general conditions of contract,

acceptance of tender, special conditions of contract, particulars and others

specified or acted upon by the contractor and a formal agreement if executed.

v) “Equipment” means the material / part / component proposed to be used during

the contract (the required materials will not be provided by the “Railway

Administration”) according to the specifications of the schedules of work items

of the Tender Document. It shall also include spare parts for the purpose, which

will not be provided by the “Railway Administration”.





INSTRUCTIONS: -

Tender in the prescribed form addressed to the President of India, acting through the

Chief Medical Superintendent, E. Co. Railway, Waltair, should be submitted along

with name and address of the tenderer in a sealed cover super scribed :-

“Contract for collection of 750 Cft. of garbage per day from various West

Sector Railway colonies of Visakhapatnam i.e., Gurkhaline Colony, MSM Colony,

S & C Colony, DLS Colony, MPM South & North colonies and final disposal to the

nominated dumping ground of Greater Visakhapatnam Municipal Corporation

( G.V.M.C.) at Kapuluppada, by engaging a Mechanised carrier along with

Driver, Fuel , Labour, equipments, etc., required for the same, for a PERIOD

OF TWO YEARS ”.



Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.







West Sector Contract -2009-pro.doc9

1. All offers in the prescribed form should be submitted in a sealed cover.

2. All offers shall be submitted before the time and date fixed for the, Receipt of the

offers, as set forth in the tender papers. Offers Received after the stipulated time

and date shall be rejected.

3. Sealed covers containing the tender delivered by hand should be put into the tender

box kept in the office of the Chief Medical Superintendent, E. Co. Railway, Waltair

with a superscription as mentioned in the instructions above. The sealed Tender cover

should contain the Tender Notice Number, name of the work, and the name and

address of the tenderer.

4. Tender Box will be sealed at 15.00 Hrs. and opened at 15.30 Hrs. on 30-09-2009 (Last

date) in the Seminar Hall of the Divisional Railway Hospital, East Coast Railway,

Waltair, in presence of the Tenderers or their authorized representative.

5. The Tenderer should provide satisfactory evidence acceptable in the Railway

Administration to show that:

i) He is a reputed firm / contractor who undertakes the work similar to this tender

and has adequate technical knowledge and experience.

ii) He can provide the mechanized carrier, as specified in the schedule of work.

6. A satisfactory work completion certificate along with a performance statement giving

a list of similar works in Government, Semi Government, And Industrial Organization,

including nature of the works, executed in the recent past, giving details of customer

names, addresses, order no (s) and dates and also Labour License, etc., allotted to

them. Tenderers not submitting the requisite information may note that their offers

are liable to be ignored.



7. Tender papers are not transferable.

8. Time Schedule.

The basic consideration and essence of the contract shall be the strict adherence to

the time schedule, for the completion of the work, as prescribed in the special

conditions of the contract.

9. METHOD OF TENDERING.

The tender will contain the following information.

i) Experience and details of past performance for similar works, if any.

ii) Availability of Mechanized Carrier, if any and

iii) Earnest Money Deposit.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.









West Sector Contract -2009-pro.doc9

The Financial Bid will contain the following information:

Name / Description of work, Approximate annual quantity, Departmental

Estimated Rate & Rate offered by the Tenderer(s)

N O T E :-

i) The tender documents in original containing the Tender Form including Tender

instructions, Terms & Conditions, Schedule of work, Special Conditions of the

Contract and Financial Bid should be sealed in the envelope. However, the

Tenderers if they desire to stipulate any special conditions or special rates

not included in the tender schedule or wish to furnish any information which

they feel necessary, they may furnish the same on separate paper and

enclose the same to the tender documents placing on top for consideration.

ii) The tenderer are required to drop the envelop containing the above

documents in the tender box before the scheduled time and date mentioned in

the Tender.



iii) The envelope will be opened at the time and date mentioned in clause 3 above

10. The tender document shall be accompanied by a sum of Rs. 28,434/-/-(Rupees

Twenty Eight thousand Four hundred and Thirty Four only) as Earnest Money in

the form of FDR / Bank draft drawn in favour of FA & CAO / East Coast Railway

/ Bhubaneswar, payable at Visakhapatnam or Cash receipt for the cash deposited

with the Divisional Cashier, East Coast Railway, Visakhapatnam, failing which the

tender will summarily be rejected. No interest shall be allowed on the earnest

money deposit. The earnest money deposited by the successful Tenderers will be

retained as a part of the security amount for the due fulfillment of the contract

but shall be forfeited, if the contractor fails to deposit the balance of the

security amount and / or execute the agreement or start the work within the

prescribed time limit after notification of the acceptance of his / their tender.



11. The earnest money of unsuccessful Tenderers will be refunded after finalization

of the tender or after six months from the date of the tender whichever is

earlier.

12. In the event of the tender being submitted by the partnership firm / private

limited company, it must be signed by all partner(s) / Director as, the case may

be and in the absence of the partner (s) / Director, it must be signed on his /

their behalf by a person holding a valid power of attorney authorizing him to do

so. A copy of partnership deed or a registration certificate of a private – limited

company and / or power of attorney is submitted along with the tender. Tender

not accompanied by such documents will not be considered and is liable to be

rejected.

13. Acceptance or non-acceptance of any tender shall rest with the Divisional Railway

Manager, E.Co.Raiway, Waltair for and on behalf of the President of India at his

discretion and he shall not be bound to accept the lowest or any other offer and

shall have full authority and discretion to divide or reduce or increase the volume

of work or to accept the tender partly and he shall not be bound to assign any

reason what-so-ever for any of his actions.

14. The tender forms are not transferable.







West Sector Contract -2009-pro.doc9

15. The Tenderer shall hold the offer open for a period of 120 (One Hundred and

Twenty) days from the date of opening of the tender and the tenderer(s) shall

not withdraw his / their offer within this period. In the event of such

withdrawal, his / their earnest money shall be forfeited by the Railway

Administration.

16. If a tenderer expires after the submission of the tender or after the acceptance

of his tender, the Railway should deem such tender of contract as cancelled. If a

partner of a firm expires after the submission of that tender or after

acceptance of these tenders, the Railway should deem such tender or contract as

cancelled unless the firm retains its original character.

17. Non-compliance with any of the conditions given herein above is liable to result in

the tender being rejected.

18. SCHEDULE OF WORK: Schedule of work is given in the enclosure attached

herewith in Annexure “B”.

19. The Contractor shall indemnify the Railway Administration and shall make good

any losses to the Railway Premises / Buildings during their conservancy work.

20. The Licensee (s) shall not under any circumstances whatsoever, appoint Minor /

Child Labour which is offensive under such laws.

21. The contractor must supply all necessary records as may be required by the

inspecting officials.

22. The Tenderers are further requested to affix his / their signatures on each page

of the Tender documents / Annexures / Terms And Conditions / Instructions to

Tenderers / Special Conditions, etc. as a token of his / their acceptance and also

for the purpose of authentication.



23. PAYMENT TERMS:

The standard payment terms subject to recoveries of any amount under the

liquidated damages clause of contract will be as under.

a) The contractor shall submit their monthly bills containing, each item vide

schedule of work duly certified by the Railway Administration or their

representative (i.e., CHI / Health Inspector, and countersigned by the

Sr.D.M.O. / H & FW / WAT) and finally forwarded to the Chief Medical

Superintendent, E.Co.Raiway, Waltair, for the purpose of settlement and

payments.

b) The first monthly payment, shall be released only after the contractor has

fulfilled his responsibility of submitting necessary documents and maintaining

records in compliance with labour laws, rules and regulations and as required

by Railway Administration.

c) The payment will be made to the firm / contractor, on completion of

satisfactory work, Bills in four copies accompanied with Challan, inspection

certificate should be submitted to the Office of the Chief Medical

Superintendent, for arranging payment through Accounts Department.





Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.





West Sector Contract -2009-pro.doc9

24. DEDUCTIONS :

a) Payments, as in clause 23 above, shall be subject to deductions of any

amount for which the contractor is liable under the contract against this

tender or any other contract in respect of which the President of India is

the contracting authority.

b) Taxes shall be deducted at source as per laws & rules in force.

25. PENALTY:

The Railway Administration reserves the rights for imposing penalty on the

contractor if garbage removal is not up to the mark and the penalties will be

deduced from the payment of bills,. If the contractor is not taking up the work

as per the schedule of work and complaints received from the colony residents,

the contract will be terminated.

26. THE PROCEDURE FOR OBTAINNG PERFORMANCE GUARANTEE IS OUTLINED

BELOW : -

(a) The successful bidder may give Performance Guarantee amounting to 5% of the

Contract value in any of the following forms:-

i) A deposit of cash.

ii) Irrevocable Bank Guarantee.

iii) Government Securities including State Loan Bonds at 5% below the market

value.

iv) Deposit receipts, Pay Orders, Demand Drafts and Guarantee Bonds. These

forms of Performance Guarantee could be either of the State Bank of India or

of any of the Nationalized Banks.

v) Guarantee Bonds executed or Deposit Receipts tendered by all Scheduled Banks.

vi) A deposit in the Post Office Savings Bank.

vii) A deposit in the National Savings Certificates.

viii) 12 Years National Defence Certificates.

ix) 10 Years Defence Deposits.

x) National Defence Bonds, and

xi) Unit Trust Certificates at 5% below market value or at the face value. Which

ever is less.

xii) Also FDR in favor of FA & CAO / C, (free from any encumbrance) may be

accepted.

(b) A Performance Guarantee shall be submitted by the successful bidder after the

Letter of acceptance has been issued, but before signing of the agreement. The

agreement should normally be signed within 15 days after the issue of LOA and the

Performance Guarantee shall also be submitted within this time limit. This Guarantee

shall be initially valid up to the stipulated date of completion plus 60 days beyond

that. In case, the time for completion of work gets extended, the Contractor shall

getup the validity of Performance Guarantee extended to cover such extended time

for completion of work plus 60 days.







Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.









West Sector Contract -2009-pro.doc9

(c ) The Performance Guarantee (PG) shall be released after the physical completion of

the work based on the ‘Completion Certificate’ issued by the Competent Authority

stating that the Contractor has completed the work in all respects satisfactorily.

The Competent Authority shall normally be the authority who is competent to sign

the Contract. If this Competent Authority is of the rank lower than JA Grade,

then a JA Grade Officer (concerned with the work), issues the Certificate. The

Certificate inter alia, should mention that the work has been completed in all

respects and that all the Contractual obligations have been fulfilled by the

Contractors and that there is no due from the Contractor to Railways against the

contract concerned. Before releasing the Performance Guarantee an unconditional

and unequivocal No Claim Certificate from the Contractor concerned should be

obtained.

(d) Wherever the contract is rescinded, the security deposit shall be forfeited and the

Performance Guarantee shall be encashed and the balance work shall be got done

independently without risk and cost of the failed Contractor. The failed Contractor

shall be debarred from participating in the tender for executing the balance work.

If the failed Contractor is a J.V. or a Partnership firm, then every member /

partner of such a firm shall be debarred from participating in the tender for the

balance work either in his / her individual capacity or as a partner of any other J.V.

/ Partnership Firm.



(e) The Railway shall not make a claim under the Performance Guarantee except for

amounts to which the President of India is entitled under this Contract ( not with

standing and / or without prejudice to any other provisions in the contract

agreement ) in the event of :

1) Failure by the Contractor to extend the validity of the Performance Guarantee

as described herein above, in which event the Engineer may claim the full

amount of the Performance Guarantee.

2) Failure by the Contractor to pay President of India any amount due, either as

agreed by the Contractor or determined under any of the clauses / conditions

of the agreement, within 30 days of the service of notice to this effect by the

Railway.

3) The Contract being determined or rescinded under provisions of the G.C.C. the

Performance Guarantee shall be forfeited in full and shall be absolutely at the

disposal of the President of India.







Signature(s) of the Tenderer(s) (Seal if any)

Name of the Tenderer(s) & Full Address

(In Block letters.)



Signatures of Witnesses with address:

1.



2.



Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.







West Sector Contract -2009-pro.doc9

ANNEXURE “B”



SCHEDULE OF WORK FOR WEST SECTOR RAILWAY COLONIES OF

VISAKHAPATNAM



1. WORK SCHEDULE :-Collection of 750 Cft., of garbage per day from various

West Sector Railway colonies of Visakhapatnam i.e., Gurkhaline Colony, MSM

Colony, S & C Colony, DLS Colony, MPM South & North colonies and final

disposal to the nominated dumping ground of Greater Visakhapatnam Municipal

Corporation ( G.V.M.C.) at Kapuluppada, by engaging a Mechanised carrier along

with Driver, Fuel , Labour, equipments, etc., required for the same, for a

PERIOD OF TWO YEARS through open tender.



2. Quantity: - Average accumulation of garbage /refuse each day and disposal

there of will be 750 Cft approximately.



3. Period of Contract: - TWO YEARS from the date of issue of Acceptance Letter.



4. Approximate value of the Contract is - Rs. 14,21,680 /-



5. Transportation of Refuse / Garbage for final disposal to the nominated dumping

area of GVMC, at Kapuluppada during the day time, as per the directions given

by the concerned authorities. Necessary certificates from the GVMC

authorities should be submitted on daily basis to the CHI / Waltair regarding

dumping of the garbage.



6. The Mechanised Carrier along with Driver, Labour, Fuel, tools & tackles,

equipments and consumables etc., required for the contractual work will be

supplied by the contractor.



7. The Mechanised Carrier should report daily at the office of the CHI, Waltair,

at 06-00 Hrs. and perform the work between 06-00 Hrs. to 17-00 Hrs.,



8. The work will be carried out on a daily basis to a fixed Programme approved by

the Railway. The method and system of carrying out the works will be prescribed

the official in charge of the work or his representative.



9. The Conservancy contractual work shall be carried out in the frequency

preferably without affecting the movement of colony residents and vehicles.



10. Chief Health Inspector or his nominated representative of the Railways shall be

responsible for daily inspection and supervision of this contract and for

certifying the quantum and quality of work done by recording the same in the log

book / measurement book for purposes of payment of the Contractors bills.









West Sector Contract -2009-pro.doc9

11. Garbage / Refuse along with debris, muck should be removed and disposed every

day. Anti-fly & Anti-Larval measures should invariably be undertaken in and

around the dust bins and other places of garbage heaps after disposal of

the garbage.



12. The quantities entered into” QUANTITY” column of the Schedule of Work are

only approximate and the President of India acting through DRM ( Medical ),

Waltair, does not bind himself to give into the whole or any of the quantity

or enumerated in the schedule nor does not guarantee that the

quantities will be evenly distributed through out the period or any part

thereof. The understanding being that such quantities that actually

required will only be executed and the actual requirement during the period or

any part thereof be in excess of the approximate estimate indented in the

quantity column of the schedule, the Contractor shall be bound to execute in the

same on the same terms and conditions as detailed herein as well as in the

Agreement form. Variation limit up to 10% on either side of the quantities will

be applied.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair









West Sector Contract -2009-pro.doc9

ANNEXURE “C”

SPECIAL CONDITIONS OF THE CONTRACT



1) Successful Tenderers shall be allowed to operate the contract, and no subletting would

be permitted without the permission of Railways.

2) Successful Tenderers will have to abide by the labour laws in force and shall have to pay

minimum wages as declared from time to time by State Government. Any claims in this

regard whatsoever will have to be borne by the successful tenderer only. Such labour

engaged is the liability of the contractor and Railway bears no liability, whatsoever on

such engagement.

3) All labour must be provided with distinct uniforms as approved by the Railways at the

contractor‘s own cost.

4) All labour is to be supplied soap daily for washing at the cost of contractors.

5) Name badges, duly authenticated by the CHI / WAT have to be prominently displayed

by the labour. Cost of such incurrence would be borne by the contractor and no extra

cost would be paid by the Railway.

6) During the course of execution of contract, meeting would be called at periodic

intervals , to review the performance and to take corrective action to avoid recurrence

of complaints from the colony residents . Additional meeting may also be held in case of

any emergency. The contractor should make him self available for the meetings.

7) Contractor has to keep their tools and plants and machineries in their own custody.

Theft or any unusual occurrence will be the full responsibility of the contractor.

8) After duly certified by the nominated Railway Official, Contractor shall submit the bill

for the work executed by him once in a month duly countersigned by Sr.DMO(H&FW) –

WAT to the Chief Medical Superintendent, E. Co. Railway, Waltair, for the purposes of

payment of his bills.

9) WORK EVALUATION:-

The effectiveness of the contractual work for proper collection and disposal of garbage

in terms of quantity as well as quality will be evaluated and the same will be recorded

daily in the log book / measurement book by the Railway Administration through his

authorized representative i.e., Health Inspector / Chief Health Inspector. These

entries in the log book / measurement book should also be signed daily by the

Contractor or his authorized representative.

The Contractor should strictly adhere to the Clauses of the schedule of work.

PENALTY CLAUSE:-

The contractor should ensure that the overall daily performance should be

SATISFACTORY so as to entitle him for 100% payment for the day.

If the evaluation is found to be UNSATISFACTORY in terms of quantity and quality,

then a penalty as specified below shall be imposed and recovered from the monthly bills.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair









West Sector Contract -2009-pro.doc9

i) Failure to undertake the work on any day, the Contractor will not be entitled

to claim the bill on that particular day and also a penalty of Rs.1000/- per

day will be levied for non execution of work, in addition to recovery of the

difference in the actual expenditure incurred by the Railway Administration

to undertake the work on the same day for maintaining the colony cleanliness.

This will be certified by the Supervisor In-Charge at the work spot, duly

entering the same in the log / measurement book and countersigned by the

Official In charge.

ii) If the Contractor fails to lift and dispose the daily quantity of 750 Cft., of

garbage or part thereof, then a penalty of Rs. 500/- will be levied for partial

execution of the work, in addition to recovery of the difference in the

actual expenditure incurred by the Railway Administration to undertake the

remaining quantity of work on the same day for maintaining optimum standard

of colony cleanliness. This will be certified by the Supervisor In charge at

the work spot, duly entering the same in the log / measurement book and

countersigned by the Official In charge. As such, the Contractor will be

entitled to claim for the actual quantity of garbage collected and disposed on

that day.

iii) Wherever dust bins are provided for the users in the colony, there should

not be any spillage of garbage in and around the dust bins while carrying out

loading into the mechanical carrier. As such for any spillage around the dust

bins or on the colony roads a penalty of Rs.200/- will be levied which will be

decided by the Inspecting Railway Official or Sr.DMO (H & FW) – Waltair or

any other authorized representative of the Railways.

iv) Deficiency in standard of cleaning materials, tools and equipments, etc., the

contractor will be liable for a minimum penalty of Rs.200/- per day as will be

decided by the Inspecting Railway Official.

v) Railway Officials of different ranks will be inspecting the quality of work

from time to time. Incase of Adverse remarks of any inspecting official or

public complaints received on deficiency of service (Registered in the

available complaint book in the Office of the CHI / WAT) the contractor will

be liable for a penalty of Rs.200 to Rs. 500/- or the compensation awarded

to complainant in any court of law or in consumer court or both.

vi) The above penalties will be recorded daily in the log book / measurement

book by the Railway Administration through his authorized representative

i.e., Health Inspector / Chief Health Inspector. These entries in the log book

/ measurement book should also be signed daily by the Contractor or his

authorized representative.

No penalty shall be applicable during extraordinary circumstances i.e., political

mob, disaster & Bandh.

The Railway Administration will terminate the contract if the work executed by

the contractor is consecutively unsatisfactory for 15 days, at the risk and cost

of the contractor.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair





West Sector Contract -2009-pro.doc9

10) TERMINATION OF CONTRACT :- ( As per Clause- 62 of GCC )

If there is non-performance / bad workmanship / Un – satisfactory work,

contractor would be served with 7 days notice to make good. On expiry of 7 days

notice, if contractor fails to make good or the performance dose not improve,

then railways have the, liberty to issue 48 hours notice of termination, on expiry

of 48 hours notice period, contract would be terminated by issuing a letter and

on such termination, contractor’s entire security deposit available with Railways

plus any dues arising from the works executed by the contractor will be

forfeited.

11) Contractor has to submit a ‘no claims certificate’ every month.

12) In case of any dispute or claim, contractor will have the liberty to approach

Railway Administration for arbitration on this claim / dispute. Railways also can

lodge / raise their own claim / dispute.

13) Arbitrator will be appointed by General Manager, E.Co.Raiway, within one month

from the date of receipt of such a claim / dispute. Decision of Arbitrator is

binding on both the Railways as well as to the contractor. Arbitration would be

dealt in accordance with Arbitration and Conciliation Act, 1996, or what is in

force during the period of contract.

14) In case of increase of quantity of work during the Special Occasion / Festivals,

Rallies, Visit of VVIPs, other natural calamities, etc. , extra payment will be

made as per the actuals after certification from the respective HI / CHI or

any other nominated Railway Official duly countersigned by Sr.DMO (H&FW).

15) Apart from routine cleaning and maintenance work detailed in scope of work,

some occasional work like removal of animal dead bodies / carcass, etc. from

within the Railway colony premises to the nominated areas, will also have to be

done.

16) During inspections, on receipt of complaints about non-execution of the quantity

of work, the areas identified have to be attended at once for which no extra

payments would be made by the Railways.

17) Contractor shall not in any capacity employ any person of bad character or any

person whose antecedents have not been investigated by the police and shall

issue an appointment certificate, which shall contain a photograph of the

employee specifying the employee’s name, fathers name, address and the place

at which employed, with / his her left / right hand thumb impression affixed

thereon in printers ink which he will carry with him / her while on duty. The

expenses for such verification as is necessary shall be borne by the contractor.

18) Contractors should comply with all the obligations ( have general insurance

policy or ESI for their labour engaged for this work), as per the extent labour

laws / rules, in respect of labour engaged for this work.



19) The contractor shall be responsible for availability, serviceability and

maintenance, of the mechanized carrier. This mechanized carrier should be

dedicated to this contract and cannot be taken out for any other job.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair





West Sector Contract -2009-pro.doc9

20) Railway authorities or its nominated representative will supervise the work on

daily basis and a record will be maintained for the work completed. The

contractor will be penalized for the quantity of work not done or if the quality

of work is of sub-standard specifications.

21) No escalation of rates for any reason what so ever will be accepted during the

currency of the contract.

22) The Contractor has to register initially with the Greater Visakhapatnam

Municipal Corporation (GVMC) for the above work, for the purpose of dumping

garbage at nominated dumping grounds of GVMC.

23) The garbage shall be free from flies and other insects such as mosquitoes, etc..

The garbage from such ships with deratification certificates only allowed for

disposal.

24) The garbage meant for transport shall be provided with closed doors and tight

lids over top to avoid exposure and spill, etc.,

25) The vehicle that visit the dumping yard shall be subjected to inspection by the

official / officer kept in charge of dumping yard to accord approval of

emptying.

26) Any Hazardous material in the garbage shall not be transported for disposal to

the dumping yard except with proper treatment to render it from infection.

27). Greater Visakhapatnam Municipal corporation reserves the rights to revoke or

suspend

or cancel the permission, So granted even earlier or any conditions imposed by

Visakhapatnam Port Trust and customs department shall be strictly followed by

the Contractor.

28) For each load Rs.100/- per ton challan to be produced to the GVMC official at

Kapuluppada site and subsequently the same to be submitted to the CHI /

Waltair, along with the Certificate issued by the GVMC authority regarding

garbage disposal for the day .

29) Hire charges and running expenses for machineries and plants if supplied by the

Railways shall be borne by the contractor and the same shall be deducted from

his / their dues. The hire charges recoverable are embodied in special

conditions clauses of Vol.II /. S.E.Railway / Schedule of labour and material

rates 1994.

30) A certificate should invariably be attached along with the tender papers that

the tenderer (s) has / have purchased / downloaded schedule of labour and

materials rates part – I Vol.I of 1992 and Part – II, III & IV of general;

conditions of contract of standard specifications Vol. II printed in 2001 with up

to date corrections slips attached thereto of S.E. Railway and gone through all

the conditions of contract and rates and specifications, etc., embodied therein.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical),

East Coast Railway / Waltair.









West Sector Contract -2009-pro.doc9

ANNEXURE – ‘ D’

FINANCIAL BID

Sl.No. Description of work Approximate Departmental Rate quoted by the

Quantity Estimated tenderer (Uniform

Rate % rate in figures

and words to be

quoted.)

1 Contract for collection 5,47,500 CFT Rs.02.59 per

of 750 Cft. of garbage CFT _______________

per day from various

West Sector Railway _______________

colonies of Visakhapatnam

i.e., Gurkhaline Colony, _______________

MSM Colony, S & C (in words) % per

Colony, DLS Colony, CFT

MPM South & North Above / Below / at

colonies and final disposal par with the

to the nominated dumping departmental

ground of Greater estimated rate for

Visakhapatnam Municipal a period of Two (2)

Corporation ( G.V.M.C.) at years.

Kapuluppada, by engaging

a Mechanised carrier

along with Driver, Fuel ,

Labour, equipments, etc.,

required for the same

for a PERIOD OF

TWO YEARS.



Note: The rate is inclusive of garbage dumping charges payable to GVMC.

NOTE: - Any overwriting / correction has to be attested / countersigned by the

tenderer (s). The rate quoted in words shall be considered as final rate in case of any

ambiguity. The rate is inclusive of all charges and all other taxes leviable to the

government, including CST, works contract tax, VAT, Service Tax, Entry Tax, Income

Tax, etc.

Signature(s) of the Tenderer (s)

Name of the Tenderer & Full Address (In Block letters.)

Place: _____________

Date: _____________



Name & Signature of the Witnesses with address:

1.



2.

Divisional Railway Manager (Medical)

East Coast Railway / Waltair.







West Sector Contract -2009-pro.doc9

ANNEXURE “E”

TERMS & CONDITIONS OF THE CONTRACT



1. ABOUT THE CONTRACT:-

The contractor should note the following as regards to the execution of the contract



i) The contractor shall do the work as per the Description given in the “Schedule of

Work, “.

ii) The contractor shall supply mechanized Carrier strictly as detailed in the schedule of

work for collection and disposal of garbage.

iii) The contractor shall supply all consumables required for running of the mechanized

Carrier.

iv) The contractor shall provide regular maintenance of the mechanized carrier to be

Utilized for this contract and ensure 100% availability of the same in all the days. If

required, stand by mechanized carrier should be available for uninterrupted service.

v) The supervision of the cleaning will be in co-ordination with the Railways

administration under the instructions of Sr.DMO (Health & F.W. ) or his nominated

representatives. The Chief Health Inspector or his nominated representative of

these colonies shall be responsible for daily inspection and supervision of this

contractual work and for certifying the quantum and quality of work done by

recording the same in the log book / measurement book for the purposes of payment

of the contractor’s bills.

vi) The use of mechanized carrier and the work should be carried out in such a manner

that it will not affect the movement of the colony residents / vehicles.

vii) The contractor shall arrange all equipment, Tools & Plants, Consumables, etc., at his

own cost for operating the mechanized carrier to undertake the above schedule of

work. Materials required for the execution of the work will have to be carried at the

public rates and no Concessional Rate of Railway Freight is applicable.

viii) The contractor shall be responsible for maintenance of equipment / machineries

supplied by him. Railway Administration is not liable to pay any extra charge for this

purpose.

ix) Payment for contractor is detailed in S.No.6.



2. SCOPE OF WORK:

The Contractor shall undertake the work for collection of 750 Cft., of garbage per day from

various West Sector Railway colonies of Visakhapatnam, i.e., Gurkhaline Colony, MSM Colony, S

& C Colony, DLS Colony, MPM South & North colonies and final disposal to the nominated

dumping ground of Greater Visakhapatnam Municipal Corporation ( G.V.M.C.) at Kapuluppada, by

engaging a Mechanised carrier along with Driver, Fuel , Labour, equipments, etc., required

for the same, for a PERIOD OF TWO YEARS, within the sub-systems of the Railway Colony,

Visakhapatnam.

The Contractor shall provide the technical services for daily collection & disposal of garbage

from the West Sector Railway colonies of Visakhapatnam. The scope of services will be as

specified in the work schedule. The scope of work as mentioned is only indicative and not

exhaustive in any respect.







Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.





West Sector Contract -2009-pro.doc9

3. WORK SCHEDULE: The Conservancy contractual work shall be carried out in the

frequency preferably without affecting the movement of colony residents and vehicles . The

work shall also be done on a daily basis. Chief Health Inspector or his nominated representative

of the Railways shall be responsible for daily inspection and supervision of this contract and for

certifying the quantum and quality of work done by recording the same in the log book /

measurement book for purposes of payment of the Contractors bills.

4. VALIDITY: This contract shall be valid for a period of ONE YEAR with effect from Date

of issuing the Letter of Acceptance and renewal thereafter at the option of the Administration

for a period or periods as decided by the successor, Railway Administration under the same

terms and conditions of the contract.

5. RATE: The rates quoted are inclusive of the following.

a) Cost of Hiring of the mechanized carrier and cost of its operation.

b) Cost of all auxiliary and ancillary equipments, consumables for the mechanized carrier

and all operations for completing the job.

c) Cost of all maintenance of the mechanized carrier.

d) Cost of consumables required for conservancy work i.e., labour, tools, tackles and

Supervision.

e) Cost of Collection of garbage including all solid waste, muck & debris etc., and finally

transportation & dumping of these garbage / waste materials / at the nominated places

in the municipal area of GVMC at Kapuluppada .

f) All taxes and levies etc. such as sales tax, excise duty / CST, works contract tax,

income tax and VAT, etc. as applicable, as well as insurance, including third party

liability, Service tax will also be borne by the contactor.

6. PAYMENT:

a) Payment shall be made on a monthly basis to the firm / contractor, on completion of

satisfactory work. At the end of each month, the contractor shall submit their monthly

bills containing, the item vide schedule of work duly certified by the Railway

Administration or their representative i.e., Respective Colony Health Inspector,

Chief Health Inspector, Waltair, duly countersigned and finally forwarded by the

Sr.DMO / Health & Family Welfare / Waltair, to the Chief Medical Superintendent,

E.Co.Railway, Waltair for the purpose of settlement and payments.

b) These bills in four copies accompanied with Challan, inspection certificate should be

submitted within 10 days of the completion of the month to which it pertains, to the

Office of the Chief Medical Superintendent, for arranging payment through Accounts

Department.

c) Taxes shall be deducted at source as per laws & rules in force.

d) The first months payment under this agreement will be released only after the

contractor has fulfilled the responsibility of submitting the Performance Guarantee

and all other necessary documents etc. such as security deposit / ITCC and

certification of satisfactory performance received from the respective Colony Health

Inspectors and Chief Health Inspector / Waltair, and maintaining records in

compliance with labour laws, rules and regulations and as required by Railway

Administration from time to time.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.





West Sector Contract -2009-pro.doc9

7. DOCUMENTATION:

The contractor or his Principals are required to submit the following documents to the

Medical Department before commencement of the job.

a) Copies of documents showing the legal status of the firm, along with names and

addresses.

b) A declaration that the Contractor is an independent employer and all persons employed

or engaged by them are at their own cost and expense for carrying out the agreed

work under this contract, and shall be their employees, and not that of the Railway.





8. OTHER STIPULATIONS:

a) The contractor shall personally and exclusively supervise or deploy sufficient

Supervisors to exclusively supervise the work so as to ensure that the services rendered under

guidelines and to the satisfaction of the Railways.



b) Any dispute or difference arising out of the agreement shall be referred to Arbitrator,

the proceedings of which will be conducted in accordance with the Arbitration and Conciliation

Act, 1996, and amendments.



c) Any dispute and / or difference of opinion arising out of the day-to-day work concerning

this contract shall be referred to the Sr.D.M.O.(H & FW ) – Waltair, whose decision shall be

final and binding on the Contractor.



d) All disputes arising out of this contract shall be subject to courts of VSKP jurisdiction

only.



e) The above conditions shall be read in condition with the Special Conditions of the

Contract. The above terms will however, override any similar clauses mentioned anywhere in the

conditions of Contract.



9. EXECUTION:



a) The whole contract is to be executed in the most approved, substantial and workman like

manner to the entire satisfaction of the Railways Administration or its nominee, who, both

personally and by his deputies, shall be free to inspect the work at such times as he may deem

fit, and on any question of the true intent and meaning of the specification, shall be final and

conclusive.



b) A confirmation has to be given in writing by the contractor accepting that all the

material supplied / to be used are guaranteed for satisfactory performance for the entire

contractual period from the date of commencement of the contract.



c) If the Contractor deliberately gives wrong information in his tender, the Railways

Administration reserves the right to reject such tender and in the case of the successful

tenderer to cancel the contract at any stage.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.







West Sector Contract -2009-pro.doc9

10. SECURITY:





Unless otherwise specified in the special conditions, if any, the Security Deposit / rate of

recovery / mode of recovery shall be as under: -





a) Security Deposit for this contractual work should be 5% of the contract value.

b) The rate of recovery should be at the rate of 10 % of the bill amount till the full

security deposit is recovered.

c) Security Deposit will be recovered from the running bills of the contract and unless

otherwise specified in the Special Conditions, if any, the Security Deposit / Rate of

Recovery / Mode of Recovery shall be as under:-

i) Security Deposit for each work should be 5% of the Contract value.

ii) Rate of Recovery should be at the rate of 10% of the bill amount till the full

Security Deposit is recovered.

iii) Security Deposit will be recovered only from the running bills of the contract

and no other mode of collecting Security Deposit such as Security deposit in

the form of instruments like Bank Guaranty, Fixed Deposit, etc., shall be

accepted towards Security .Deposit.

iv) The Security Deposit however, shall be released only after expiry of the

maintaining period and after passing the final bill passed on - “NO CLAIM

CERTIFICATE”



d) Security Deposit shall be returned to the contractor after the physical completion of

the work as certified by the Competent Authority. The Competent Authority shall

normally be the authority who is competent to sign the contract. If this competent

authority is of the rank lower than JA Grade officer (Concerned with the work) should

issue the certificate. The certificate inter alia, should mention that the work has been

completed in all respect and that all the contractual obligations have been fulfilled by

the contractor and that there is no due from the contractor to railways against the

contract concerned. Before releasing the Security Deposit an unconditional and

unequivocal, no claim certificate form the contractor concerned should be obtained.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.









West Sector Contract -2009-pro.doc9

11. RESPONSIBILITY OF THE CONTRACTOR FOR EXECUTING CONTRACT:

RISK OF THE EQUIPMENT:

The contractor shall perform the contract in all respects in accordance with the terms

and conditions of the agreement. The equipment and every constituent part thereof, whether in

the possession or. Control of the contractor, his agents or servants, or in the joint possession of

the contractor, his agents or servant and the Railway Administration shall remain in every

respect at the risk of the contractor. The contractor shall be responsible for all losses,

destruction, damage or deterioration of or to the equipment from any cause whatsoever.Any

damage to the Railway equipment / property caused on account of negligence of contractor or

his representative shall be recoverable fully from his bill and decision of the Railway

Administration in this regard shall be final and binding with the contractor.



12. LIABILITY UNDER WORKMEN’S COMPENSATION ACT OR OTHERWISE. :

The contractor shall at all times indemnify the Railways Administration against all

claims, which may be made under the Labour laws including Workmen’s Compensation

Act 1923 for any statutory modification there of or rules made there under or

otherwise for or in respect of any damages or compensation payable in consequence of

any accident or injury sustained by any workmen, labourers or any persons in the

employment of the contractor and engaged in the performance of the business relating

to this contract, except Railway employees. The contractor at all times shall also take

all risk of accident or injury which may be the cause of failure or the performance of

the said business arising out of such accidents to such workmen, laborers or servants

except Railway staff and against all costs and expenses incurred by the Railways

Administration in connection therewith and (Without prejudice to any other means of

recovery) the Railway Administration shall be entitled to deduct form any money due or

become due to the contractor whether under this agreement of any other agreement,

all moneys paid or payable by the Railways Administration by way of compensation

aforesaid or for cost of expenses in connection with any claim there to and the

contractor shall abide by the decision of Railway Administration as the sum payable by

the contractor under the provision of this clause. The contractor shall note that no

compensation due to loss of life or loss of material shall be payable by the Railway

Administration and contractor shall have to pay all the claims due as compensation in

case of accident, injury to the laborers or any person for whatsoever reason.

13. PROGRESS REPORT:

The supervisors appointed by the contractor should remain at the work spot. The

contractor and their staff shall conduct their business in a quiet and orderly manner

and shall not allow the working of the machines, in any respect whatever to interfere

with the Railway Administration’s work executed by railway staff at the colony, or with

the comfort and convenience of the colony residents.







Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.





West Sector Contract -2009-pro.doc9

The contractor shall submit monthly progress reports as to the progress of the contract in such

form as may be called for by the Railway Administration or its nominee. The submission and

acceptance of these reports shall not prejudice the rights of the Railway Administration in any

manner, in enforcing the terms of contract.



14. LIQUIDATED DAMAGES:

In the event of contractor ‘s failures to execute the work to the satisfaction of the

Railway Administration / Inspecting Officer in the time or times respectively specified in the

letter of acceptance or as indicated in the description of work, the Railway Administration may

withhold any payment until the whole contract has been executed and may deduct or recover

from the contractor as liquidated damages (and not by way of penalty) a sum @ ½ % (half

percent) per week or part thereof on the total contract value.



Provided however, that if the delay shall have arisen from any cause which the Railway

Administration may admit as reasonable ground for further time (Railway Administration may in

their discretion allow such additional time as they may consider to have been required by the

circumstances of the case and shall forgo the whole or such part of the claim as they may

consider reasonable).



15. DEFAULTS :

Should the Contractor fail to execute the Contract by the time or times agreed upon as

aforesaid or should the contractor in any manner otherwise fail to perform the contract or

should it have a receiving order made against it, the Railway Administration has the right to

encash the performance guarantee of 5% of the contract value



16. FORCE MAJEURE:

In the event of any unforeseen event, directly interfering with the execution of works, arising

during the currency of the contract, such as insurrection, restraint imposed by the Government,

act of legislative or other authority, war, fire, floods, explosions, epidemics, quarantine

restrictions, Acts of God, etc. the contractor shall within a week from the commencement there

of notify the same in writing to the Railway Administration with reasonable evidence thereof. If

the force majeure condition mentioned above be in force for a period of 15 days or more at any

times, the Railway Administration shall have the option to terminate the contract on expiry of

15 days of commencement of such force majeure by giving 7 days notice to the contractor in

writing. In case of, such termination no damage shall be claimed by either party against the

other, save and except those, which had occurred under any other clause of the contract prior

to such termination.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.









West Sector Contract -2009-pro.doc9

17. INSPECTING OFFICER – POWERS OF REJECTION :

17.1 The inspecting officer shall have the following powers:

i) The Mechanised Carrier and all auxiliary and ancillary equipments / tools, submitted

for inspection, to certify that it is not in accordance with the contract.

ii) To reject the Mechanised Carrier and all auxiliary and ancillary equipments / tools,

submitted as not being in accordance with the requirement of the tender document.

iii) To mark the rejected Mechanised Carrier and all auxiliary and ancillary equipments /

tools with a rejection mark so that they may be easily identified if re-submitted.

17.2 The inspecting officer’s decision as regards rejection shall be final and binding on the

contractor.

18. CONSEQUENCES OF REJECTION.



18.1 REMOVAL / RFEPLACEMENT OF REJECTED MECHANISED CARRIER AND ALL

AUXILIARY AND ANCILLARY EQUIPMENTS / TOOLS:

On rejection of any equipment submitted for inspection at a place other than the

premises of the contractor, the contractor at his own cost shall remove such

equipment, subject to as hereinafter stipulated, within 14 days of the date of

intimation of such rejection. If communication in this regard is addressed and posted to

the contractor at the address mentioned in the tender, it will be deemed to have been

served on him at the time when such communication would in course of ordinary post

reach the contractor. Provided that the inspecting officer may call upon the contractor

to remove dangerous, non-functioning equipment within 48 hours on the receipt of such

communications and the decision of the Inspecting Official in this regard shall be final

in all respects.

18.2 All rejected equipment shall in any event and circumstances remain and always be at

the risk of the contractor, immediately on such rejection. If such equipment are not

removed by the contractor within the period aforementioned, the inspector may

remove the rejected equipment and will then return the same to the contractor at

his risk and cost by such mode of transport and retain such portion of the proceeds,

if any from such disposal as may be necessary to recover any expense incurred in

connection with such disposals (or any price refundable as a consequence of such

rejection). The Railways Administration shall, in addition, be entitled to recover from

the contractor the handling and storage charges for the period during which the

rejected equipment are not, removed / disposed off in accordance with the provision

thereof

.







Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.









West Sector Contract -2009-pro.doc9

19. ARBITRATION:

19.1 In the event of any question dispute or difference arising under these conditions or

any special conditions of contract or instructions to Tenderers or in connection with

this contract (except as to any matter the decision which is specifically provided for

by these conditions of instructions to Tenderers or the special conditions), the same

shall be referred for the appointment of Arbitrators by the General Manager, East

Coast Railway, Bhubaneswar.

The Gazetted Railway Officers to be appointed as Arbitrator, however, will not be

ones who had an opportunity to deal with the matters to which the contract relates or

who in the course of their duties as Railway servants had expressed views on all or any

of the matters under dispute or difference. The award of the Arbitrators shall be

final and binding on the parties to is contract. The Arbitration will be conducted under

the provisions of Arbitration and Conciliation Act 1996, and all its Amendments.

19.2 In the event of the Arbitrators denying, neglecting or refusing to act, or resigning or

being unable to act for any reason, it shall be lawful for the authority appointing the

Arbitrators to appoint other Arbitrators in place of the outgoing Arbitrator in the

manner aforesaid.

19.3 It is further a term of this contract that no person other than the persons appointed

by the authority as aforesaid should act as Arbitrators and that if for any reason

that is not possible the matter is not to be referred to arbitration at all.

19.4 Upon any and every such reference, the assessment of the cost incidental to the

reference and award respectively shall be at the discretion of the Arbitrators.

19.5 Subject to as aforesaid, the Arbitration and Conciliation Act-1996 and the rules there

under and any statutory modification thereof, for the time being in force, shall be

deemed to apply to the arbitration proceedings under this clause.

19.6 Work under the contract, as is reasonably possible, if so decided by the Railway

Administration may continue during the arbitration proceedings and no payment due to

or payable by the Railways Administration shall be with held on account of such

‘proceedings.’

19.7 Where the Arbitral award is for the payment of money, no interest shall be Payable on

whole on any part of the for any period till the date on which the award is made.

19.8 The venue of arbitration shall be the place from which the contract is issued, or such

other place as the Arbitrators at their discretion may determine.

19.9 The authority to appoint the arbitrator includes, if there be no such Authority, to the

officer, for the time being discharging the functions of that Authority, whether in

addition to other functions or otherwise.









Signature (s) of tenderer (s) Divisional Railway Manager (Medical)

East Coast Railway / Waltair.









West Sector Contract -2009-pro.doc9

20. PENALTY

1) The contractor can be penalized by way of fine amounting upto Rs.1500/- ( Rupees One

thousand Five hundred only) in each occasion by DRM or by his representative if in

his opinion the performance of the contractor in connection with the contractual work

is not up to his entire satisfaction.

2) Besides the above, clauses terms and conditions not specifically mentioned in this

document, the clauses terms and conditions as laid down by the S.E.Railway

General conditions of contract and standard specifications No .I Vol 2 with up to date

correction slips will be part of this document.





In witness whereof the said parties here to have set their hands at the place and on the

dates herein after mentioned respectively.









Signature (s) of tenderer (s)

Name of the Tenderer & Full Address

(In Block letters.)

Place:_____________________

Dated:__________



Signatures of Witnesses:



1.

Name:

Address:





2.

Name:

Address:







Divisional Railway Manager (Medical)

East Coast Railway / Waltair.



The above particular instructions and conditions are being read, understood and accepted by me.









Signature (s) of tenderer (s )









West Sector Contract -2009-pro.doc9


Related docs
Other docs by WillLawrence
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!