MANUAL REF. PMD/D/SOP/1

DATE ISSUED Nov. 2006



ISSUE NO. 1



REVISION NO. 0

SYARIKAT BEKALAN AIR SELANGOR SDN BHD PAGE NO. Page 1 of 6

PROJECT MANAGEMENT & DEVELOPMENT DIVISION

DEVELOPMENT PROCEDURES MANUAL

MANUAL FOR MONITORING OF CONSTRUCTION AND TAKING

SUBJECT

OVER OF WATER SUPPLY SYSTEM FROM DEVELOPERS



1.0 INTRODUCTION



1.1 The objective of the manual is to have a standardized procedure of taking over

water supply systems from developers by the districts.



1.2 To enable consultants and developers to know the procedures undertaken by

SYABAS and what is expected of them.



1.3 To facilitate the process of taking over the completed water supply systems

constructed by developers.



1.4 To ensure that completed water supply systems taken over are built according to

the approved plan and is of good quality.



2.0 SCOPE



2.1 The manual covers the quality control during construction stage followed by the

taking over processes for civil, mechanical & electrical and telemetry works as

follows :-



a) Taking over of External Permanent Water Supply System

b) Quality Control of Internal Plumbing System

c) Taking over of Mechanical & Electrical and Telemetry System



3.0 GENERAL POLICY



3.1 Role and Responsibility



The role and responsibility of each party involved in the implementation of

external water supply system is listed below:-



i) Authority Given to SYABAS District



a. Districts approve external plan submission for water demand less than

50,000 lpd within three (3) weeks.



b. Districts approve all internal plumbing plan approval for buildings less

than 6 storeys within three (3) weeks.

MANUAL REF. PMD/D/SOP/1

DATE ISSUED Nov. 2006



ISSUE NO. 1



REVISION NO. 0

SYARIKAT BEKALAN AIR SELANGOR SDN BHD PAGE NO. Page 2 of 6

PROJECT MANAGEMENT & DEVELOPMENT DIVISION

DEVELOPMENT PROCEDURES MANUAL

MANUAL FOR MONITORING OF CONSTRUCTION AND TAKING

SUBJECT

OVER OF WATER SUPPLY SYSTEM FROM DEVELOPERS



c. Districts to oversee and monitor all construction works of all projects,

irrespective of the size of development.



d. Districts have the right to access, monitor, check and inspect all

ongoing works based on approved plans executed by developers

during construction stage, and upon satisfaction with the quality of

works, take over the completed water supply systems.



e. Districts are in-charge of operation and maintenance of the completed

water supply system after taking over from developers.



ii) Authority Given to SYABAS Development Department (H.Q.)



a. Development Department approves plan submission on external water

supply system for water demand more than 50,000 lpd within three (3)

weeks.



b. Development Department approves all internal plumbing plan approval

for high rise buildings more than 6 storeys within three (3) weeks.



c. All approved plans will be forwarded to the districts for supervision

purpose.



d. SYABAS development section will carry out surprise independent check

for quality control based on approved plan at project site.



iii) Role of SYBAS Audit Department (H.Q.)



a. To ensure quality control, audit Department may carry out independent

site auditing on water supply system of ongoing development projects

built by developers and to check whether it complies to approved plans.



iv) Role of SYABAS Committee on Standard, Material and Product (H.Q.)



a. SYABAS Committee on Standard, Material and Product approve the use

of materials and products for SYABAS water supply installations.



b. Only material and product list approved by SYABAS committee are

allowed to be used.

MANUAL REF. PMD/D/SOP/1

DATE ISSUED Nov. 2006



ISSUE NO. 1



REVISION NO. 0

SYARIKAT BEKALAN AIR SELANGOR SDN BHD PAGE NO. Page 3 of 6

PROJECT MANAGEMENT & DEVELOPMENT DIVISION

DEVELOPMENT PROCEDURES MANUAL

MANUAL FOR MONITORING OF CONSTRUCTION AND TAKING

SUBJECT

OVER OF WATER SUPPLY SYSTEM FROM DEVELOPERS



c. Products approved by the committee shall be provided with a five (5)

years product warranty.



v) Role of Developer



a. All construction works at site must be based on approved plan.

Developer is required to ensure no construction work shall commence

without the water supply system plans already approved by SYABAS.



b. To appoint Professional Engineer registered with Board of Engineers

Malaysia from SYABAS recommended list of consultants who are

familiar with SYABAS technical requirements on water supply system. (A

list of consultants is available from SYABAS office for reference).



c. To engage the same consultant to carry out design works and supervision

of work.



d. The developer must engage consultant supervisor to do supervision of

works based on the following category :-



i). Supervision for civil works on pipeline, reservoir and pump house

shall be as follows:-



For housing development in progress at any stage less than 100 units

or equivalent to 33,000 gallon per day – intermittent supervision by

one full time technician.

For housing development in progress at any stage between 100 – 500

units or equivalent between 33,000 – 165,000 gallon per day – full

time supervision by one full time technician.



For housing development in progress at any stage between 500 –

1,000 units or equivalent between 165,000 – 330,000 gallon per day

– supervision by one full time civil engineer and one technician.



For housing development in progress at any stage more than 1,000

units or equivalent more than 330,000 gallon per day – supervision

by one full time civil engineer and two technicians.

MANUAL REF. PMD/D/SOP/1

DATE ISSUED Nov. 2006



ISSUE NO. 1



REVISION NO. 0

SYARIKAT BEKALAN AIR SELANGOR SDN BHD PAGE NO. Page 4 of 6

PROJECT MANAGEMENT & DEVELOPMENT DIVISION

DEVELOPMENT PROCEDURES MANUAL

MANUAL FOR MONITORING OF CONSTRUCTION AND TAKING

SUBJECT

OVER OF WATER SUPPLY SYSTEM FROM DEVELOPERS



ii). Supervision for works involving mechanical & electrical and telemetry

systems shall be by a qualified electrical or mechanical engineer and

be engaged when works are being carried out at project site.



e. Developer through its consultant must submit the curriculum vitae of

consultant supervisor who should have more than 5 years experience related

to water supply works and must be approved by SYABAS. Any works found at

site without the consultant supervisor as required, can be rendered as not

acceptable and lead to SYABAS not taking over the external water supply

system.



f. To appoint a contractor registered with CIDB or PKK with relevant sub head

related to water supply works.



g. To engage a registered plumber, with registration from Jabatan Kawalselia Air

Selangor.



h. Any water supply system completed without approved plan by SYABAS and

works not supervised by consultant will not be taken over by SYABAS.



i. Developer is responsible to repair and make good any defects during the

defects liability period which in general is 36 months after the date of taking

over ( but is subjected to details in SYABAS ‘s letter to REDHA ref. No(6201)

dlm.SYABAS 22/1/315 dated 8 November 2006 on the defect liability period .

Developer is also responsible to repair and make good any latent defects

which appear after defects liability period due to negligence, inferior quality of

materials and shoddy workmanship.



j. Developer is required to deposit a bank guarantee against defects as a

condition to the taking over of water supply system by SYABAS. Bank

guarantee value will be based on 5% of SYABAS estimated value of

construction cost of the water supply system involved, including civil and M &

E works.



k. Developers are expected to complete the permanent water supply system on

time for their own development. No temporary water supply will be

considered. For big development projects, developer needs to plan and

develop a complete water supply system for phased development to be

handed over to SYABAS in stages.

MANUAL REF. PMD/D/SOP/1

DATE ISSUED Nov. 2006



ISSUE NO. 1



REVISION NO. 0

SYARIKAT BEKALAN AIR SELANGOR SDN BHD PAGE NO. Page 5 of 6

PROJECT MANAGEMENT & DEVELOPMENT DIVISION

DEVELOPMENT PROCEDURES MANUAL

MANUAL FOR MONITORING OF CONSTRUCTION AND TAKING

SUBJECT

OVER OF WATER SUPPLY SYSTEM FROM DEVELOPERS



l. Developers are required to allow access at their respective project site and

assist SYABAS staff to carry out site inspection on ongoing works as directed.



m. The developer has to make sure that stealing of water does not take place

at project site.



vi) Role of Consultant



a. To prepare a quality assurance plan

b. To supervise all works through its site representative

c. To ensure all works are built according to approved drawings and

specifications

d. To prepare bimonthly progress reports and works programmes.

e. Consultant shall take full responsibility for all proper study, design,

authority approval, specification, construction drawings, supervision,

material inspection, testing and commissioning.

f. Consultant will not be relieved of its design obligation and supervision

even after the water supply system is taken over by SYABAS.



3.2 General Conditions

a. The quantity of water for construction supply and testing purposes can be given

in 2 stages:-

• Stage 1: For construction supply, the meter installed at site shall be small

(generally not more than 25 mm diameter). Water for construction supply

will be used for construction, leakage and pressure testing and general

cleaning purposes



• Stage 2: For pump testing and flushing purposes, the meter can be

increased to full bore diameter, for example 100 mm diameter (generally)

depending on water requirement of the water supply system. Water for

sterilization and flushing and pumping system test shall be obtained after

connection to the existing mains has been carried out.



b. SYABAS will take over the permanent water supply system only if developers

have completed the said system according to the approved plans. For big

developments, the taking over can be done by phases of development provided

each phase of development has completed its entire water supply system.

MANUAL REF. PMD/D/SOP/1

DATE ISSUED Nov. 2006



ISSUE NO. 1



REVISION NO. 0

SYARIKAT BEKALAN AIR SELANGOR SDN BHD PAGE NO. Page 6 of 6

PROJECT MANAGEMENT & DEVELOPMENT DIVISION

DEVELOPMENT PROCEDURES MANUAL

MANUAL FOR MONITORING OF CONSTRUCTION AND TAKING

SUBJECT

OVER OF WATER SUPPLY SYSTEM FROM DEVELOPERS



The complete water supply system shall refer to all the incoming mains, external

water reticulation mains, internal plumbing, completion of suction tank, pump

house and service reservoir, installation of M & E works and telemetry system.



c. The developer is expected to complete the permanent water supply system and

handover to SYABAS before handing over of houses to the purchasers.



d. Please refer to item 4.0 for the details of workflow procedures for construction

and post construction of the external permanent water supply system, internal

plumbing system and Mechanical & Electrical and Telemetry system.



4.0 WORK FLOW PROCEDURES



4.1 External Permanent Water Supply System Workflow Procedures



4.2 Internal Plumbing System Workflow Procedures



4.3 Mechanical & Electrical and Telemetry System Workflow Procedures


Related docs
Other docs by M.Danial Idris
Application for Employer Identification Number
Views: 91  |  Downloads: 5
Sample of Portfolio Optimization
Views: 12  |  Downloads: 0
Job Site Boxes
Views: 3  |  Downloads: 0
18072007-162559
Views: 10  |  Downloads: 0
Form KA 1-1
Views: 15  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!