3P-SOLUTIONS S.A.





 

 

Status report 



Site: PPC Power Plant Lavrion, Unit 2

Time: 19.01.2009 – 23.01.2009

Purpose: Check of PLC-system, status of main control-loops and related drives, upgrade-

possibility to C3,

Done by: 3P-Solutions S.A. Jürgen Chluba









21/22nd January 2009

In order to get an impression, how the present control-system is working, it was necessary to put the

Oil-, Air- and Boiler-Master-Control in “Automatic”. It was found, that as soon as the Oil-Control was

put in auto, the oil control valve started to swing. It was assumed that the following Contronic 2 cards

could be faulty:

• Integral card CT022,

• Interface card CS012 to the Triac Unit GV015 or GV015 itself.





On January 21, all the damping signals to the actuators for both FD-Fans and the damping of the Oil-

Flow-Control-valve actuator were checked. They were all found o.k.

On January 22, first the CS012 Card was removed, with no positive effect. The old card was used

again. In a second step, the CT022 card was replaced, using the following parameter combination:

Tn = 4,7 s and Xp = 80%. To ensure that the spare card CT022 was in a working condition, it was taken

from the atomizing-steam-temperature-controller. After the change, the Oil-Flow-Control-valve was

stable in automatic-mode.

Nothing else was changed, and the load was increased from 140MW to 290 MW with the Air-Control,

the Oil-Flow-Control and the Boiler-Master on automatic.





All control circuits were found stable in “Automatic” from this point on.

Report_LavrionII.doc

Page - 1/5



3P-Solutions S.A. Evaluation Phone: +352 / 26 36 26 73

Zone Industrielle Engineering Telefax: +352 / 26 36 26 74

L-6468 Echternach Optimization www.3p-solutions.lu

3P-SOLUTIONS S.A.







The following was observed:



The Oil-Control was following the command of the boiler-master-control. Even when burners were

switched on, it remained stable. The Air-Flow-Control was behaving the same way.









Figure 1 Oil-Flow and Aux-Steam-Flow during load change



The Furnace-Pressure at 289MW, settled at its adjusted value of 420 mmWS.

O² values were ~0.5 Vol.% on both sides at 289MW. Most of the values settled like they did before.









Figure 2: Furnace Pressure (blue) and O²

Report_LavrionII.doc

Page - 2/5



3P-Solutions S.A. Evaluation Phone: +352 / 26 36 26 73

Zone Industrielle Engineering Telefax: +352 / 26 36 26 74

L-6468 Echternach Optimization www.3p-solutions.lu

3P-SOLUTIONS S.A.



As it can be seen in Figure 2, the O²-values on low load are pretty much the same like they were before

the card-change (operation mode: manual). After the card-change (automatic-mode) the O²-figures on

high-load became more unstable, but on the other hand lower. Before, high-load O²-values were over

2% (green line O²-picture bottom right side), now they are at about 1.85%. (The red line shows the

same behavior). It is most likely that with Air-Control in automatic the O²-values are kept lower.



The Boiler-Outlet-Pressure was controlled to a low deviation by the operator. During the load change

from 140MW up to 289MW the Drum-Level increased by more than 45mmWS. It settled after 20

minutes to its set value.









Figure 3: Boiler-Outlet-Pressure (blue) Steam-Flow (red) and on the right side Drum-Level (red)



The SH-Temperature varied from 530°C to 556°during the load rise. This variation of 26°C is too

much and can be improved with a new control.





The RH-Temperature varied from 528°C to 555°during the load rise. This variation of 27°C is too

much and can be improved with a new control.





At Full load the Boiler-Outlet-Pressure remained constant, within less than one bar. The Reduction of

the load from 289MW to 140MW in the afternoon was even smoother then the load rice in the

morning.

Report_LavrionII.doc

Page - 3/5



3P-Solutions S.A. Evaluation Phone: +352 / 26 36 26 73

Zone Industrielle Engineering Telefax: +352 / 26 36 26 74

L-6468 Echternach Optimization www.3p-solutions.lu

3P-SOLUTIONS S.A.







So far so good, but still the combustion could be improved, if the Atomizing-Steam-Control would

work properly.



Above points are the main points, which have been found during our visit.



Conclusion



So everyone could be happy, and keep going on, but the situation will not improve over the next year.

What happens if more cards are failing during the next few weeks? The unit may trip or has to be run

partially on manual again. There will be continuous trouble with the repair of the Contronis 2 cards. To

ensure a reliable performance of the unit 2 during the next few years, I would like to recommend a

change of the essential control circuits to the proven more reliable Contronic 3 system.



This could be done in two phases:



Phase 1:

New Contronic 3 cubicle with the pre-wired:

• Boiler-Master-Controller

• Air-Controller

• Oil-Flow-Controller.

Optional, during Phase 1 also a new:

• Oil-Pressure-Controller

• Oil-Temperature-Controller.



For all above mentioned Control circuits I would like to recommend also to up-grade or change the

related control actuators to Contrac actuators. Which of the two options; up-grade or new actuators

depends on the economy. It makes no sense, when the upgrade-costs reach the costs of an new

actuator, especially at the smaller types of actuators.



The Opacity-Control circuit should be removed and replaced by an O²-Control, because a modern O²

measurement for both sides of the boiler is already in place.



It is important to improve also the Oil-Pressure- and Oil-Temperature-Control. With better control for

those loops the emissions will be smaller.

Report_LavrionII.doc

Page - 4/5



3P-Solutions S.A. Evaluation Phone: +352 / 26 36 26 73

Zone Industrielle Engineering Telefax: +352 / 26 36 26 74

L-6468 Echternach Optimization www.3p-solutions.lu

3P-SOLUTIONS S.A.







But it is more important, to get the Atomizing-Steam-Control probably working. A short visit to the

atomizing steam control station has shown that the arrangement of the station is causing trouble.

The direct measurement with glycerin to keep the oil measurable should be replaced by a new Delta-

Pressure-Transmitter with remote seals. Also a new I/P converter with a feedback unit could be

attached to the atomizing control valve. That gives the opportunity to control the atomizing-steam

more accurate, dependent to the oil pressure.

One last remark to the atomizing steam reducing station; a modern reducing station would control the

pressure to its set value.





Phase 2

Due to the fact that a new Contronic 3 Cubicle will exists after phase 1, the remaining important

control loops like SH-Temperature-Control, RH-Temperature-Control, Boiler-Feed-Pump-Control

with the Drum-Level-Control and last but not least the HP-Bypass-Pressure/Temperature-Control,

could also be changed to Contronic 3.









Summary



As described in the report we will submit an offer for Phase 1 separately. This provides the possibility

to plan the budget for improvement of the control system, which means more reliable running of Unit

2 for the next few Years.









Report_LavrionII.doc

Page - 5/5



3P-Solutions S.A. Evaluation Phone: +352 / 26 36 26 73

Zone Industrielle Engineering Telefax: +352 / 26 36 26 74

L-6468 Echternach Optimization www.3p-solutions.lu


Related docs
Other docs by TylerShoemaker
WEEKLY HUMANITARIAN REPORT
Views: 4  |  Downloads: 0
Draft Synthesis Report Topic 2.3 10809
Views: 79  |  Downloads: 0
Delta Report
Views: 66  |  Downloads: 0
Treasurer's Report
Views: 6  |  Downloads: 0
Exar Quarterly Quality and Reliability Report
Views: 3  |  Downloads: 0
Grant Status Report
Views: 21  |  Downloads: 0
KEY QUARTERLY PERFORMANCE MEASURES REPORT
Views: 20  |  Downloads: 2
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!