N O R T H S Y D N E Y C O U N C I L R E P O R T S









Report to General Manager





SUBJECT: Assessment of Tender Submissions for Contract 02/2010 –

Alexander/Holtermann Street Roundabout Construction



AUTHOR: Jim Moore, Senior Design Engineer, 19 August 2009



SUMMARY:



Tenders were called and received until 4.00pm on 11 August 2009 for the Alexander/Holtermann

Street Roundabout Construction



This report details the tenders received, available funding and recommends a preferred tender.



RECOMMENDATION:



1. THAT Council accept the tender of Shamrock Development International to carry out

the Alexander/Holtermann Street Roundabout Construction under Contract 02/2010 for

$166,149 (excl GST) subject to provisional items



2. THAT Council hereby authorises its Official Seal to be affixed to Contract 02/2010

under the signature of the Mayor and the General Manager.





Signed ____________________





Endorsed by _____________________________________

Director of Engineering and Property Services

ORIGINAL SIGNED





Endorsed by _____________________________________

Chairperson, Tender & Quotation Panel



Comment by Director, Finance & Information Management:

Funding for the project is appropriate.





_____________________________________

Report of Jim Moore – 19 August 2009 (2)

Re: Contract 02/2010 – Alexander/Holterman Street Roundabout Construction



BACKGROUND



The Alexander and Holtermann Street roundabout construction was identified as one of North

Sydney Council accident “Black spots”. On the 23rd February 2009, at the 3512th meeting of

North Sydney Council, Council resolved to proceed with the construction of the Alexander and

Holtermann Street roundabout.



Works include demolition and reconstruction of kerb and gutter, construction of raised threshold,

construction of median/splitter islands, drainage works, Landscaping and supply and installation of

pedestrian fencing.



The drainage works includes upgrading the existing drainage pits along Alexander St as well as

upgrading essential drainage lines within the intersection. These works also include re-sheeting of

the Alexander and Holtermann St intersection, and up to 20m along each arm of the intersection.

The drainage and re-sheeting works will be funded from their corresponding budgets.



TENDER EVALUATION CRITERIA



The methodology adopted to undertake the tender evaluation of Contract 02/2010 was based on

selection criteria outlined in the tender documents and according to Council’s “Procedures and

Guidelines for the Evaluation of Tenders for Engineering Civil Works” (2001).



The tender evaluation criteria as shown below were applied to each tender and given a point

score relative to various weightings set to each criterion, in order to provide an equitable means

of evaluating each tender.

- Price

- Duration

- Occupation Health and Safety

- Capability and Methodology



The points allocated are based on the information submitted by the tenderers in the tender and

any subsequent investigation undertaken by Council officers. They are also based on scores from

Council’s Contractor Performance Reports.



TENDERS RECEIVED



Tenders were called and closed at 4.00pm on 11 August 2009. Eight tenders were received by

the appointed time.



The tenderers were (in alphabetical order):



Tenderer

• Australian Prestressing Services

• Celtic Civil Pty Ltd

• Civil Construction Pty Ltd

• Kingston Civil Constructions Pty Ltd

• Melhemcorp Pty Ltd

• Roadworx

• Shamrock Developments International

Report of Jim Moore – 19 August 2009 (3)

Re: Contract 02/2010 – Alexander/Holterman Street Roundabout Construction



TENDER ANALYSIS



All the tenderers submitted conforming tenders. The final ranking, duration of the works and

point scores of each tender are identified in the table below. The assessment was based on

Council’s standard tender evaluation methodology.



The point scores and final ranking of each tender are identified in the table below.



Alexander/Holtermann Street Roundabout

Construction

Tenderer Point Score Rank

Australia Prestressing Services 21.0 8

Celtic Civil 43.6 5

Civil Constructions 49.3 3

Civil Edge 40.4 6

Kingston Civil 35.6 7

Melhemcorp 51.6 2

Roadworx 48.6 4

Shamrock Developments 57.0 1



Based on the final tender analysis, Shamrock Developments International tender was the highest

ranked tenderer for Contract 02/2010.



FUNDING



Funding for the works is to be provided from the current Capital Works Budget as shown below:



Estimate of Costs



Cost Description $

Contract 02/2010 166,149

Supervision 3,851

Total Costs 170,000

Report of Jim Moore – 19 August 2009 (4)

Re: Contract 02/2010 – Alexander/Holterman Street Roundabout Construction



Source of Funding



Description Proposed Funding Source

Bgt $

2009/2010 Capital Reserve Budget

Traffic Facilities: Alexander/ 125,000 Capital Works Reserve

Holtermann Street Roundabout

(62100.0654.145)

Drainage Program: 20,000 Capital Works Reserve

(58020.2496.145)

Roads Program: (54060.2611.145) 25,000 Capital Works Reserve



Funding Totals 170,000



Asset Expenditure Classification



Classification Proposed

Bgt $

Renewal (capital exp used to retain the asset at its 50,000

current standard)

Upgrade (capital exp to increase the current asset 40,000

to a higher standard)

Expansion (capital exp on new assets…) 80,000

170,000

TOTALS





Duration of Work



Anticipated Start: September 2009

Anticipated Completion: October 2009



Responsible Officer:



George Schadel, Works Engineer


Related docs
Other docs by TylerShoemaker
WEEKLY HUMANITARIAN REPORT
Views: 4  |  Downloads: 0
Draft Synthesis Report Topic 2.3 10809
Views: 79  |  Downloads: 0
Delta Report
Views: 66  |  Downloads: 0
Treasurer's Report
Views: 6  |  Downloads: 0
Exar Quarterly Quality and Reliability Report
Views: 3  |  Downloads: 0
Grant Status Report
Views: 21  |  Downloads: 0
KEY QUARTERLY PERFORMANCE MEASURES REPORT
Views: 20  |  Downloads: 2
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!