HAINES BOROUGH, ALASKA

PUBLIC FACILITIES

P.O. BOX 1209

HAINES, AK 99827

(907) 766-2257 * FAX (907) 766-2256







8/3/09



Facilities Manager Monthly Report for July



Work effort by area:



Facilities General 14%

Public Works 11%

Construction Phase 1 Roads 3%

Construction Young Road Water Tank 13%

Construction Portage Cove Harbor 20%

Water/ Sewer 15%

Ports and Harbors General 2%

Other Construction 13%

PC Restrooms/ Dock 3%

Letnikof Boarding Float 6%



Capitol Projects Summary



Chilkat Center Pedestrian Bridge: PND has redesigned the project as a Laminated Beam wood structure with the

roof addition as an alternate. RFP was sent out 8-3-09 with final completion date of 11-2-09.



Sheldon Museum Alarm Upgrades: Fire alarm system bid with the low price being submitted by Juneau Electric.

The borough is awaiting information from the contractor to complete final documents to move forward with

construction.



Barnett Drive Pump Station: After a review of the design, CE2 engineers have been instructed to move forward with

final design and issue the construction drawings for the project. We anticipate early August for final drawings and

getting the project out for RFP. CE2 is currently working with Scott Bradford on EPA requirements which will be

completed before final pump station design.



Letnikof Boarding Float Project: Tamico Inc. has floats being manufactured at this time. Submittals on materials

and equipment are being reviewed by PND. The anticipated start date for work is Sept. 23rd. Tamico has been

notified we will have them install piling for the Boarding Float.



Lily Lake Waterline: Engineering effort for the water line replacement continues to move forward. The short term

goal is gain maximum points for a Municipal Matching Grant and complete the project in the 2010 construction

season. We are on track and anticipate submitting approved for construction drawings with the application on Aug.

3rd.



Mosquito Lake Boiler Replacement: Project has been on hold pending funding. Low bid for the project was

$208,257. Cost reductions through value engineering estimates project at $165,000 for completion.



EPA Compliance Project: CE2 Engineers has sent the first draft of the Haines Borough Operation and Maintenance

manual for Wastewater Treatment for review. Scott Bradford is reviewing the document and working with CE2 to

make changes before submitting the manual to EPA. We anticipate submitting the manual in August.



Public Works Shop Improvements: RFP has been advertised to complete work on PW Shop. This includes

concrete floor and enclosing remaining bays. There is good response on this project.



Senior Center Range: A new range has been ordered for the Senior Center. We anticipate delivery and installation

in August.

Portage Cove Harbor Construction Progress 7/15/09 Contractor: Western Dock and Bridge



Portage Cove Harbor Construction is moving forward on schedule with no significant delays or issues to date. PND

Engineers has an inspector on site to observe and approve construction tasks.



Phase 1 of the project is under way with the following work being completed or substantially complete at this time.

 Mobilization is complete 100%

 Uplands site work is substantially complete at 95%

 Phase 1 Demolition work is complete 100%

 Construction of Temporary approach dock is complete 100%

 Approach Dock construction including Pile Driving, Pile Caps, Deck and Rails substantially complete at 75%

 Boat Grid Pile and Cap replacement substantially complete at 80%



Contract Pay estimate #1 was submitted by the contractor (Western Dock and Bridge). After a review of the request

by PND Engineering, it has been submitted and paid to Western Dock and Bridge. Stock Piled Materials are on site in

Haines and have been inspected by engineers. Materials are paid at 85% and will be paid in full after installation.



Pay Estimate #1

Original Contract Amount 4,395,100.00

Amount Earned Job to Date 345,000.00

Stock Piled Materials 557,237.98

Total Earned to Date 922,237.98



Two change orders have been approved for construction in addition to the original contract amount.



Change Order 001: Per owners request install 6 additional Fender Piling at boat grid as directed by engineers.

Net change to contract amount will be an increase of $20,230 for a total of $4,415,330



Change Order 002: Demolish and rebuild uplands section of approach dock per engineer’s direction.

Net change to contract amount will be an increase of $31,801 for a total of $4,447,131



Construction Start 6/1/09, days 60, completion date 12/1/09, days to go 125.



Street Improvements Phase 1 Progress Report 8/1/09 Contractor: Southeast Roadbuilders Inc.



Project is 40% complete with no significant delays; SERoad has requested a 15 day extension to the contract. The

following work is complete or substantially complete.



 Clearing and Grubbing 100%

 Curb and Gutter removal, Culvert removal 100%

 Unclassified Excavation 25%

 Culvert and Catch Basin installation 100%

 Water and Sewer installations 100%



Contract Pay Estimate #1 has been submitted and reviewed. Payment has been made to Southeast Roadbuilders.



Pay Estimate #1

Original Contract

Amount 1,058,157.00

Amount Earned Job to

Date 359,092.00

Extra

Work 25,101.56

Total Earned to Date 384,193.56



Three change orders have been approved for this work



Change Order 001: Purchase two additional Catch Basins missed on original engineering. Net change to

contract amount will be an increase of $7,000 for a total of $1,065,157

Change Order 002: Install drains rock and tile per engineer’s drawings. Net change to contract amount will be

an increase of $22,270 for a total of $1,087,427

Change Order 003: Install additional culvert per engineers instructions on 4th street and differing site conditions

incurred on FAA Road. Net change to contract amount will be an increase of $3,379.31for a total of $1,090,806.31

Change of Condition notices 7



Construction start 4/27/09, construction days 95, completion date 9/15/09, days to go 46

Young Road Water Tank Progress Report 8/1/09 Contractor: Shearer and Associates

Project is moving forward on schedule with no significant delays or issues to date. Construction Management is being

done by Haines Borough. The following work is complete or substantially complete.

 Mobilization is substantially complete at 90%



 Sub grade, foundation and slab complete 100%

 Tank erection including floor and roof substantially complete 95%

 Skyline Tank Insulation substantially complete 95%

 Young Road Tank Insulation 30%



Contract Pay Estimate #1 has been submitted and approved. Request includes mobilization costs, materials stored

on site and labor to date. Total paid to date is 90% for work completed and materials on site.

Pay Estimate #1

Original Contract

Amount 638,876.74

Amount Earned to Date 271,929.74

Stockpiled Materials 225,000.00

Total Earned to Date 496,929.74



No Change Orders have been issued to date. Currently our schedule is to begin filling water tank 7/27/09. This

should take approximately 7 days, followed by tank insulating after testing. The tank will be filled and inspected by

8/6/09.

Construction Start 6/1/09, construction days 60, completion date 9/1/09, days to go 30.





Public Works Summary (Bruce Smith)



Temporary Toilets have been moved and installed at PC Dock. Work included trenching and support for services

th

July 4 Preparation completed including street sweeping, and other tasks provided for Public Works

Howsers Water Leak Repair: Two inch water line failure

Lily Lake: Clear and Brush right-of-way in preparation for surveying including locates for valves and culverts.

Skyline Water Issues: review engineering solutions for frozen water lines.

Hazardous Waste Collection: Manage and oversee waste collection project. Report available from Carson Dorn for

event.

2nd Avenue Asphalt Patch: Material removed from around Man hole and prepped for repaving.

Preparation for Fair: Grading, water roads and fairgrounds, support as requested from fair, signs etc. required for

event.

Capitol Projects Support: As required provided support for all construction projects



In addition to the above events Public Works completed normal duties including water service installations, grading

and watering roads, assist with projects listed above when required. Vehicle and equipment maintenance, parks and

recreation duties also maintained. Review of building and ROW permits completed. The crew has been short during

the month due to various circumstances. A detailed list of work has been submitted by Bruce Smith.





Water and Sewer Summary (Scott Bradford)



Normal department duties during the month will be included in Water/ Sewer Monthly report. In addition, Scott

provided oversight and support for the Young Road Water tank project. A large part of this work was managing water

supply required to fill new tank. Other work outside normal duties included working with Carson Dorn on Lily Lake

Line engineering, CE2 Engineers on Compliance issues, Final inspections and reviews for Young road Tank project.









Regards,





Brad Maynard

bmaynard@haines.ak.us

Public Facilities Director


Related docs
Other docs by TylerShoemaker
WEEKLY HUMANITARIAN REPORT
Views: 4  |  Downloads: 0
Draft Synthesis Report Topic 2.3 10809
Views: 79  |  Downloads: 0
Delta Report
Views: 66  |  Downloads: 0
Treasurer's Report
Views: 6  |  Downloads: 0
Exar Quarterly Quality and Reliability Report
Views: 3  |  Downloads: 0
Grant Status Report
Views: 21  |  Downloads: 0
KEY QUARTERLY PERFORMANCE MEASURES REPORT
Views: 20  |  Downloads: 2
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!