Doc. No.:
* insert client here
REV.
* insert logo here * insert project name here Date: 03 -02- 2008
0
METHOD STATEMENT FOR
INSTALLATION OF CONDUIT AND FITTINGS Page No. : 1 of 7
METHOD STATEMENT FOR INSTALLATION
OF Conduit and fittings
Project : * insert project name here
Contractor : * insert CONTRACTOR NAME HERE
Document No. :
Document revision status : 0
0 03-02-2008 Issued for Review & Comments
Prepared by Checked by Approved by
Rev. Date Description
* insert CONTRACTOR NAME HERE
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINK
http://www.unfoldsecrets.com/forum
Doc. No.:
* insert client here
REV.
* insert logo here * insert project name here Date: 03 -02- 2008
0
METHOD STATEMENT FOR
INSTALLATION OF CONDUIT AND FITTINGS Page No. : 2 of 7
REVISION CONTROL SHEET
REV. NO. DATE PAGE NO. DESCRIPTION
0 03-02-2008 ALL FIRST ISSUE
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINK
http://www.unfoldsecrets.com/forum
Doc. No.:
* insert client here
REV.
* insert logo here * insert project name here Date: 03 -02- 2008
0
METHOD STATEMENT FOR
INSTALLATION OF CONDUIT AND FITTINGS Page No. : 3 of 7
TABLE OF CONTENTS
1 Purpose…………………………………………………………………………….. 4
2 Scope of Work…………………………………………………………………….. 4
3 Responsible Personnel on Site………………………………………………… 4
4 Storage…………………………………………………………….………………. 4
5 Pre-Installation…………………………………………………………………… 4
6 Installation………………………………………………………………………… 5
7 Reference Documents…………………………………………………………. 6
8 Safety……………………………………………………………………………… 6
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINK
http://www.unfoldsecrets.com/forum
Doc. No.:
* insert client here
REV.
* insert logo here * insert project name here Date: 03 -02- 2008
0
METHOD STATEMENT FOR
INSTALLATION OF CONDUIT AND FITTINGS Page No. : 4 of 7
1. Purpose
This method of statement covers the installation of conduits – Cast in situ, Concealed
on Block Walls, Surface mounted and Underground Installations as defined in the
General Specification.
2. Scope of Works
This procedure will define the method to be used to ensure that conduit installations
and workmanship are correct and acceptable and shall conform to the Contract
Documents and Specification.
3. Responsible Personnel on Site
3.1. Construction Manager
3.2. Electrical Field Engineers
3.3. Safety Officer
3.4. QA/QC Engineer
3.5. Electrical Supervisors
4. Storage
4.1 Conduits shall be properly supported and stacked on a flat surface.
4.2 Conduits shall be protected from sunlight and moisture by covering them with tarpaulin.
4.3 Conduit fittings shall be stacked properly in neat and orderly manner.
5. Pre-Installation
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINK
http://www.unfoldsecrets.com/forum
Doc. No.:
* insert client here
REV.
* insert logo here * insert project name here Date: 03 -02- 2008
0
METHOD STATEMENT FOR
INSTALLATION OF CONDUIT AND FITTINGS Page No. : 5 of 7
5.1 All materials and documentation relevant to this particular Section of works will be
checked by the Construction Department prior to the commencement of works. Ensure
that all materials to be installed are inspected and accepted by the Consultant.
5.2 Access to start the work will be confirmed that they are in a suitable condition for
permanent works to commence.
6. Installation
6.1 Conduit Installation – Cast in situ
6.1.1 Measure and mark-up shuttering for the position of the boxes.
6.1.2 Fix the boxes on their designated locations. Ensure that the Boxes are filled with
polystyrene to prevent cement sediment to accumulate inside the boxes.
6.1.3 First layer of reinforcing bar to be installed.
6.1.4 Installed in situ conduits as per requirements, tie the conduits into the reinforcing
bars. Ensure that the maximum run of conduits between two boxes shall not
contain more than three (3) quarter bends. Ensure that the maximum run of
conduit between boxes shall not exceed 25m for straight runs. In any cases that
the straight run of conduit will exceed 25m, pull boxes shall be installed.
6.1.5 Wherever necessary, nylon rope shall be pulled into the conduit run for future
purposes. Leave a slack of 300mm minimum at each end of conduit.
6.1.6 After installation of conduits, the second layer of reinforcing bar installation will
proceed. Ensure that all installed conduit shall be taken care off.
6.1.7 Raise Request for Inspection of Conduit Installation.
6.1.8 Shutter closing and concreting will commence.
6.2 Embedded Conduits on Walls
6.2.1 Mark the position of boxes and conduits on the walls.
6.2.2 Chase the wall using appropriate tools i.e., electric concrete cutter and chisel.
6.2.3 Fix the boxes on their final position. Make sure that the boxes are properly
protected with polystyrene to prevent entry of foreign materials.
6.2.4 Install embedded conduits.
6.2.5 Raise Request for Inspection of Conduit Installation.
6.2.6 After the works has been inspected, plastering of walls will commence.
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINK
http://www.unfoldsecrets.com/forum
Doc. No.:
* insert client here
REV.
* insert logo here * insert project name here Date: 03 -02- 2008
0
METHOD STATEMENT FOR
INSTALLATION OF CONDUIT AND FITTINGS Page No. : 6 of 7
6.3 Surface Mounted Conduit Installation
6.3.1 Establish the conduit route and mark using chalk liner on ceiling or walls.
6.3.2 Mark the position of the boxes.
6.3.3 Install the boxes on their proper location.
6.3.4 Install saddle clamp base. For non-metallic conduits, spacing between saddle
clamps will not exceed 1m, and for metallic conduit, spacing between saddle
clamps will not exceed 1.5m.
6.3.5 Install the conduit runs. Make sure that the conduit runs will not contain three (3)
quarter bend.
o Where in the conduit runs will cross expansion joint, expansion
coupling will be used.
o Ensure that the spacing between parallel runs of conduit is uniform
throughout the installation.
6.3.6 Raised Request for Inspection of Conduit Installation.
6.4 Underground Duct Installation.
6.4.1 Mark the route of the underground duct.
6.4.2 Excavate the underground duct route until the required depth.
6.4.3 Check the depth of the trench for proper elevation. Ensure that the trench is free
from debris and foreign materials.
6.4.4 Install the PVC duct.
6.4.5 Raise Request for Inspection of PVC duct Installation.
6.4.6 After inspection is carried out and the said works has been signed-off by the
Consultant, back fill the trench with approved back-fill material.
6.4.7 Install Warning Tapes 300mm below the finish grade.
6.4.8 Raise Request for Inspection for Warning Tape Installation.
6.4.9 After inspection is carried out and the works has been signed-off, back fill the
trench until the finish grade. Ensure that the back fill material is properly
compacted.
7. Reference Documents
7.1 Approved Electrical Shop Drawings
7.2 Approved Material Submittals for Conduits and Boxes
7.3 Approved Material Inspection Report
7.4 Approved Safety Plan
7.5 Approved QA/QC Inspection Plan.
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINK
http://www.unfoldsecrets.com/forum
Doc. No.:
* insert client here
REV.
* insert logo here * insert project name here Date: 03 -02- 2008
0
METHOD STATEMENT FOR
INSTALLATION OF CONDUIT AND FITTINGS Page No. : 7 of 7
8. Safety
8.1 All safety precautions shall be followed as per approved safety plan & procedure.
Ensure all involved persons are aware of the same.
8.2 Tradesman shall ensure that before leaving their working places, it must be clean,
tidy and free from rubbish.
------------------------ Procedure End----------------------
GENERAL INFORMATION
THIS DOCUMENT IS ENTENDED FOR REFRENCE PURPOSES
ONLY. YOU CAN EDIT & MODIFY THE CONTENT.
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINK
http://www.unfoldsecrets.com/forum
OFFICIAL UNFOLD SECRETS WEBSITE
http://www.unfoldsecrets.com
OUR BLOG ARTICLE PAGE
http://www.unfoldsecrets.com/articles
SIGN OUR GUESTBOOK
http://unfoldsecrets.com/Guest-book.php
JOIN US NOW
http://unfoldsecrets.com/login/index.php
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINK
http://www.unfoldsecrets.com/forum