Method of Statement of Building Wires

Document Sample
Method of Statement of  Building Wires
Doc. No.:

*INSERT CLIENT HERE



*INSERT LOGO HERE REV.

*INSERT PROJECT NAME HERE Date: 03 -02- 2008

0

METHOD STATEMENT

Page No. : 1 of 6









METHOD STATEMENT FOR INSTALLATION

OF building wires









Project : *INSERT PROJECT NAME HERE

Contractor : *INSERT CONTRACTOR NAME HERE

Document No. :



Document revision status : 0









0 03-02-2008 Issued for Review & Comments EM MT



Prepared by Checked by Approved by

Rev. Date Description

*INSERT CONTRACTOR HERE

Doc. No.:

*INSERT CLIENT HERE



*INSERT LOGO HERE REV.

*INSERT PROJECT NAME HERE Date: 03 -02- 2008

0

METHOD STATEMENT

Page No. : 2 of 6









REVISION CONTROL SHEET





REV. NO. DATE PAGE NO. DESCRIPTION



0 03-02-2008 ALL FIRST ISSUE

Doc. No.:

*INSERT CLIENT HERE



*INSERT LOGO HERE REV.

*INSERT PROJECT NAME HERE Date: 03 -02- 2008

0

METHOD STATEMENT

Page No. : 3 of 6









TABLE OF CONTENTS







1 Purpose…………………………………………………………………………….. 4

2 Scope of Work…………………………………………………………………….. 4

3 Responsible Personnel on Site..……………………………………………… 4

4 Storage…………………………………………………………….………………. 4

5 Pre-Installation…………………………………………………………………… 4

6 Installation………………………………………………………………………… 5

7 Reference Documents…………………………………………………………. 5

8 Safety……………………………………………………………………………… 6

Doc. No.:

*INSERT CLIENT HERE



*INSERT LOGO HERE REV.

*INSERT PROJECT NAME HERE Date: 03 -02- 2008

0

METHOD STATEMENT

Page No. : 4 of 6





1. Purpose



This method of statement covers the on-site installation of Building Wires as defined in

the General Specification.







2. Scope of Works



This procedure will define the method to be used to ensure that building wire

installations are correct and acceptable and shall conform to the Contract Documents

and Specification.







3. Responsible Personnel on Site



3.1. Construction Manager

3.2. Electrical Field Engineers

3.3. Safety Officer

3.4. QA/QC Engineer

3.5. Electrical Supervisors







4. Storage



4.1 The Building Wires shall be stored in clean and dry area.



4.2 Building Wires shall be stacked in one area. Size and colors shall be segregated to each

other.







5. Pre-Installation



5.1 All materials and documentation relevant to this particular Section of works will be

checked by the Construction Department prior to the commencement of works ensuring

that these are correct type.



5.2 Check the area where in the works to commence are ready, accessible and suitable for

permanent works.





5.3 Check the tools to be used for wire pulling such as ladders, wires, scaffoldings etc are

readily available in site and in good condition.

Doc. No.:

*INSERT CLIENT HERE



*INSERT LOGO HERE REV.

*INSERT PROJECT NAME HERE Date: 03 -02- 2008

0

METHOD STATEMENT

Page No. : 5 of 6





6. Installation



It is presumed that conduits and trunkings installation has been completed before starting

this works.



6.1 Clear all boxes from cement stains and other foreign materials.



6.2 Check all embedded conduits from blockage. If there are blockage encounter, clear the

blockage before start pulling the wires.



6.3 Scaffoldings and Ladders to be used during installation shall be erected properly to

ensure that safety of people working on it.



6.4 Prepare wires for pulling. Make sure that the wires are properly marked for their circuit

number designation.



6.5 Pull wires on the conduits and trunking. Proper care shall be exercised when pulling the

wires. Only approved pulling compound to be used if required. Where more than one

conductor is used for phase, each phase, neutral and ground wires shall be run in the

same conduit. Building wires shall be continuous from outlet to outlet and no splices

shall be made except within the outlet or junction boxes. Different phases shall not be

drawn in one conduit.



6.6 Connect the wire on the outlet boxes using plastic connectors to ensure the continuity of

wires during testing. Ensure the connections are correct.



6.7 Conduct insulation resistance test and continuity test shall be conducted in the

presence of Consultant for their acceptance.



6.8 Install Ceiling Rosette for the light points.



6.9 Raise Request for Inspection for wires Installation.







7. Reference Documents



7.1 Approved Electrical Shop Drawings

7.2 Approved Material Submittals

7.3 Approved Material Inspection Report

7.4 Approved Safety Plan

7.5 Approved QA/QC Inspection & Test Plan.

Doc. No.:

*INSERT CLIENT HERE



*INSERT LOGO HERE REV.

*INSERT PROJECT NAME HERE Date: 03 -02- 2008

0

METHOD STATEMENT

Page No. : 6 of 6





8. Safety



8.1 All safety precautions shall be followed as per approved safety plan & procedure.

Ensure all involved persons are aware of the same.



8.2 Safety Officer shall ensure that all ladders and scaffoldings are safe.



8.3 Tradesman shall ensure that before leaving their working places, it must be clean,

tidy and free from rubbish.









------------------------ Procedure End----------------------



GENERAL INFORMATION





THIS DOCUMENT IS ENTENDED FOR REFRENCE PURPOSES

ONLY. YOU CAN EDIT & MODIFY THE CONTENT.



DOWNLOAD THIS DOCUMENT ON THIS BELOW LINK

http://www.unfoldsecrets.com/forum



OFFICIAL UNFOLD SECRETS WEBSITE

http://www.unfoldsecrets.com



OUR BLOG ARTICLE PAGE

http://www.unfoldsecrets.com/articles



SIGN OUR GUESTBOOK

http://unfoldsecrets.com/Guest-book.php



JOIN US NOW

http://unfoldsecrets.com/login/index.php


Related docs
Other docs by airgil daviss
Expense Reimbursement New Version New Version
Views: 3  |  Downloads: 0
MOS Fixing Manholes Part 1
Views: 2  |  Downloads: 0
Specification of Carpentry & Joinery
Views: 3  |  Downloads: 0
Specification of Airoutlet & Inlets
Views: 4  |  Downloads: 0
Method of Statement for Cable Tray Revised
Views: 24  |  Downloads: 0
Specification of Waterproofing New Versions
Views: 2  |  Downloads: 0
Minutes of Meeting templates Part 1
Views: 1  |  Downloads: 0
Minutes of Meeting templates Part 1
Views: 1  |  Downloads: 0