  ZIMBABWE CONGRESS OF TRADE UNIONS



                 WOMEN’S DEPARTMENT

                 PROJECT DOCUMENT




Project title:               Promotion and Integration of
                             Information Technology into Trade
                             Union work and Training Programmes



Duration:                    12 Months


Starting date (indicative): April 1999


Project language:            English


Preparation date:            3 February 1999




                      PROJECT DOCUMENT PREPARED BY

                            THOKOZANI KHUPE

                    ZIMBABWE CONGRESS OF TRADE UNIONS

                                 AFRICA
               2




1.Background and Justification

       1.1     The Zimbabwe Congress of Trade Unions is the umbrella body for all Trade
               Unions in the country, it was formed in 1983. The federation is composed of 32
               affiliates who operate in different economic fields.

       1.2     The information age has arrived but alas the Z.C.T.U. affiliates have various
               problems such as lack of computer skills training.

       1.3     In some instances some affiliates do not have computers thus a very big problem
               in as far as building up Data Base of members and communicating with the
               Labour Centre and other affiliates is concerned.

       1.4     The speed of communication and access to information is critical in this ever
               changing world, without computers and skills to use computers globalisation will
               never be achieved.

       1.5     Computers are available in Zimbabwe but most of them are not connected to the
               Internet rather they are used for typing. Electronic mail is available and various
               providers are willing to connect provided you can afford the hardware and the
               relevant soft ware. It is essential that as soon as finances permit we should invest
               in computers in order to build up our Data- Base of members and to
               communicate amongst affiliates, the Labour Centre and other Labour
               Organisations World wide.


2. Target Groups

This work-plan is meant for:

   Trade Union Policy-makers
   Education officers of the Labour Centre and affiliate unions
   Administrators of the Labour Centre and Affiliates

Gender balance should be realised in all the above target groups.

3. Development objectives

This work-plan will contribute to:

   The development of training programmes in computer skills at National and Affiliate
    level.




4. Immediate objectives
                   3




Immediate objective 1:

At the end of the work-plan:

(i)       Policy makers will be able to communicate with affiliates and other organisations
          world wide over through the Internet .
(ii)      Educators will be able to teach the entire membership on how to access the Internet
          for effective communication.
(iii)     Administrators will be able to capture data of members for easy payment of dues and
          be able to communicate with other affiliates and other organisations world wide over.

Immediate objective 2:

At the end of the work-plan,

Participants will be able to communicate by means of the electronic mail
Participants will be able to capture data-base using the computer
Participants will be able to create their own work pages
Participants will be able to access and disseminate information through the Internet
Educators will be able to develop material and intergrate Information Technologies into their
Trade union work and training programmes

5. Indicators of objective achievement

5.1.      Data base management system is in place
5.2.      Increased usage of the Internet
5.3.      Information technologies intergrated into Trade Union Work

6. Activities

     Developing training material             (April 1999)
     One week workshop for Policy Makers      (May 1999)
     One week workshop for Educators          (July 1999)
     One week workshop for Administrators     (Sept 1999)
     One week annual evaluation workshop      (Nov 1999)
     End of year report to ILO                ( Dec 1999)


6.        Inputs

6.1.      In co-operation with project expert securing appointment of suitable national co-
          ordinators and suitable local resource persons able to develop training materials
6.2.      Facilitate and assist project activities
6.3.      Securing administrative support
6.4.      Releasing of course participants


(skeleton budget)
              4




Workshop for 6 experts to develop material - Transport           US$ 200
                                           -Accommodation        US$ 1030
                                           -Food                 US$ 350
                                           - Stationary          US$ 60
1facilitator at $ 1500 per day               -                   US$ 220
facilitator                                  - Transport         US$ 70

TOTAL                                                            US$ 1930



One week workshop for 10 participants (Policy makers) - Transport            US$285
                                                           - Accommodation   US$714
                                                          - Food             US$571
                                                         - Stationary        US$ 40
facilitators @ $1 500 each per day               -                           US$430
                Facilitators                             - Transport         US$ 280

TOTAL                                                                        US$2320


One week workshop for 25 participants (Educators) - Transport           US$285
                                                  - Accommodation       US$714
                                                  - Food                US$571
                                                  - Stationary          US$40
2 facilitators @ $ 1500 each per day                      -                   US$ 430
         facilitators                                     - Transport         US$ 280


TOTAL                                                                        US$2320
One week workshop for 25 participants (Administrators) - Transport           US$ 285
                                                           - Accommodation   US$714
                                                           - Food            US$571
                                                           - Stationary      US$ 40
2 facilitators @ $ 1 500 each per day                      -                 US$ 430
         facilitators                                      - Transport       US$ 280

TOTAL                                                                        US$2320

10 computers for training purposes                        -                  US$ 15000
with a Net Work Cable
Net Work Cards
I Hub

GRAND TOTAL                                                                  US$23890

8. Monitoring, Reporting and Evaluation
              5




8.1.   A daily evaluation will be conducted to access the day’s work, followed by the end of
       a week evaluation and then the final evaluation at the end of the workshop.




Date   3 February 1999

				