A Framework for Controlling Operating Procedures and LOTO Procedures

This document was moved to this

location July 2011:

Purpose

file://///tdserver2/ProEng/PC_users/

The purpose of this writeup is to describe the framework that TD will use for managing and controlling

Controlled_Documents/ProEng_Instru

operating procedures and lockout-tagout (LOTO) procedures. It is a summary of the conversations that

ctions

have taken place between the various folks involved in Magnet Systems, Support and Quality &

Materials. As such, this is an old/outdated

version.

Scope



This framework is expected to be applied to all TD departments with the exception of Test &

Instrumentation. We recognize that we will start with the Magnet Systems and SRF Development

departments, and then hopefully expand to the Machine Shop department after successfully doing this

for the other departments.



Framework



Operating Procedures (OPs) are controlled using the document control system in the Process

Engineering (ProEng) Group of the Quality & Materials Department (QMD). This includes assigning a

unique document number, formal version control, signatures to approve each version, revision history

and access control. At present we maintain the “official” signed paper copy of OPs in the ProEng library

in IB2. The “official” electronic file is managed in the OnBase document management system, and links

to them are provided through the TD policies manual. The general approach we are adopting for LOTO

procedures is to control them just like we do OPs.



Specifics for each document type:



Operating Procedures:



 Each is assigned a unique 6-digit document number. These numbers are assigned by ProEng, and

come from a block of “drawing numbers” assigned to ProEng.

 Each procedure should NOT include an embedded LOTO procedure (unless it’s “plug and cord”

equipment).

 Each procedure needs to contain a reference to the associated LOTO procedure.

 Each piece of equipment is to be given a unique “official” name/description assigned by the

appropriate engineer, and a unique “Tooling Maintenance Number” assigned by the Tooling

Group. Both these identifiers will also be put onto the equipment. The equipment name is what

is used in the OP title, and the Tooling Maintenance number is included in the procedure.

 The title of each procedure (as recorded in the document control log table) should include the

Tooling Maintenance Number(s).









http://tdserver1.fnal.gov/blowers/Projects/Tooling/LOTO/Framework.docx

25-Jul-2011 Page 1 of 3

LOTO Procedures:



 Each is assigned a unique 6-digit document number. These numbers are assigned by ProEng, and

come from a block of “drawing numbers” assigned to ProEng.

 Each is also assigned a unique “LOTO Procedure number”. These numbers are assigned by the

SSO, and have the form “5120xx” where 5120 is the FESHM chapter on LOTO and xx is a

sequential number.

 Each procedure needs to contain a reference to the associated operating procedure.

 Each piece of equipment is to be given a unique “official” name/description assigned by the

appropriate engineer, and a unique “Tooling Maintenance Number” assigned by the Tooling

Group. Both these identifiers will also be put onto the equipment. The equipment name is what

is used in the LOTO title, and the Tooling Maintenance number is included in the procedure.

 The title of each procedure (as recorded in the document control log table) should include the

LOTO procedure number (the one assigned by the SSO) and the Tooling Maintenance

Number(s).



Training



Our goal is to enter all OPs and LOTO procedures into TRAIN and ITNA, and using the TRAIN and ITNA

systems to enable us to keep track of when people need to review the procedures. At this time the

LOTO procedures are being reviewed on an annual basis, and OPs are being loaded into TRAIN as a one-

time only class.



We should seriously consider reinstituting the practice of holding training for the appropriate people

whenever a change is made to the OP or LOTO procedure. Can we handle this work load?



How should we handle the question of training vs. authorization to operate equipment unsupervised, or

to “make product”. Right now it’s very informal between the supervisors and the employee. Maybe we

should consider using the OJT part of TRAIN.



Web Access



Documents stored in OnBase are to be made accessible via the operating procedure web page (link

below). This is done through the “ProEng” MS-Access database by linking the specification number to a

location.



http://tdserver1.fnal.gov/tdweb/qm/OperationProceduresPage.asp



Signatures



We would like to standardize our approach to the signatures on the cover pages for LOTO and Operating

Procedures. In consultation with HQ, we have agreed to adopt the following framework:



Author: of course can be anyone; typically is the “owner”, or steward, of the equipment







http://tdserver1.fnal.gov/blowers/Projects/Tooling/LOTO/Framework.docx

25-Jul-2011 Page 2 of 3

Reviewer: should be a technically competent person who is able to provide a technical review of the

content of the procedure to make sure that nothing is missed. In other words, this is not an

administrative review (although having an administrative review, in addition to the technical review, is

also acceptable).



Approver: needs to be the manager responsible for the equipment; in most, if not all, cases this is

expected to be the Department Head for the department which owns/operates the equipment. We

have the department head sign to indicate that line management knows and understands what is going

to be operated within their department by their people, and that they are giving their authorization for

it to take place.









http://tdserver1.fnal.gov/blowers/Projects/Tooling/LOTO/Framework.docx

25-Jul-2011 Page 3 of 3



Related docs
Other docs by xiaoyounan
uses chart
Views: 2  |  Downloads: 0
least_squares_fit_manual
Views: 0  |  Downloads: 0
ENTERING_THE_ROADWAY_AND_BACKING_NOTES
Views: 0  |  Downloads: 0
FFaith presentation
Views: 0  |  Downloads: 0
Ward_Nutritioin
Views: 1  |  Downloads: 0
0604477_Goldburg
Views: 0  |  Downloads: 0
salary-delegation-authority-summary-temporary
Views: 0  |  Downloads: 0
August 2011 _excel format_
Views: 19  |  Downloads: 0
1350 Tally FINANCE
Views: 1  |  Downloads: 0
Ch. 6.3.Martinez
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!