Team Agile Methods Case Study







3.5 Implementation notes

This section describes two different implementations of the scenario described above.

A number of factors were identical in each case:-



Teaching and learning

Class level: SCQF level 9, ie Junior Honours

Class size: less than 35

Lab tutor: 1 with work experience of agile methods in industry

Topic duration: 2 weeks

Lab content: 2 labs (JUnit and continuous integration)



Assessment

Duration: 2 weeks

Student effort: 20 hours each

Group size: pairs

Group organisation: self-selection

Differences between the first (2004-5) and the second (2005-6) implementations

related to the number and content of lectures, the assessment topic and marking

criteria. As an extension to the agile experience, for example, scrum Error!

Reference source not found.[11] was introduced in 2005-6. A summary of the key

points from these sessions is given next.







3.5.1 Notes from 2004-5 session



Teaching and learning

Lecture content: 4 lectures (Test driven development, JUnit, mocks and stubs, and

extreme programming) and 2 hours of personal study.

Assessment

Topic: DVD rental system (see appendix 1)

Assessment: criteria provided (see appendix 1) featuring process not product

Marking: detailed marking scheme created by tutors only, and available to

tutors only; summary mark sheet available to students



Timetable of events

1. Introduction to agile methods, test driven development, and JUnit via lectures,

followed by JUnit lab.

2. Further work on test-driven development via lectures.

3. Continuous integration server launched, with 2 and then 5-minute build intervals.

4. Introduction to continuous integration via lab and private study.

5. Assignment issued, with broad marking criteria, and explanation of process

targets rather than product targets.

6. Students invited to organise pairs for assignment.

7. Created a source code repository account and project for each pair.

8. Created a source code repository account for CruiseControl and Ant to have

read access to each pair’s project.

9. Build scripts finalised to send results emails to tutors and students

10. Students given 6 hours of timetabled time to work upon assignment.



Acknowledgements:

1 Microsoft & HEA-ICS

Team Agile Methods Case Study





11. Students invited to spend up to 20 hours working upon assignment.

12. Continuous integration server and then the configuration management server

were closed down at 17.00 at the end of the assignment.

13. Student performance assessed (see appendix 2)

14. Mark results were issued (see appendix 3)





Feedback

Feedback was obtained via anonymous questionnaires and a group feedback session

at the end of the semester. In summary, students judged that “The module was

delivered well. The first piece of coursework was quite hard but very clear.”





Reflection

1. Students enjoyed the experience and welcomed the practical skills obtained.

2. Tutors were disappointed with students’ understanding of refactoring, their use

of mock objects, and their ability to reflect upon their learning.

3. Waiting 5 minute intervals for builds frustrated students, but they were not

making good use of local unit testing. Students needed to be reminded to create

their tests and code and getting tests to pass on the laboratory PC first, before

checking these into the source code repository.

4. A number of the failed builds experienced by students were the result of some

sort of dependency upon another file or a library on a laboratory PC that hadn’t

been checked into the configuration management server. Students should be

advised to check classes in before other classes that use them.

5. The project topic was not sufficiently demanding.

6. Students wanted to focus upon GUI aspects despite warnings not to.

7. Exhaustive marking of every version of every file was impossible: sampling was

necessary.

8. Pair programming was popular except where a pair of students was quite mis-

matched in terms of ability.





3.5.2 Notes from 2005-6 session



Teaching and learning

Lecture content: 6 lectures (Agile methods, Scrum, Test driven development,

Continuous Integration, refactoring, mocks and stubs)

Assessment

Topic: e-commerce for horticulture company (see appendix 4)

Assessment: criteria decided in negotiation with class (see appendix 5) featuring

process not product

Marking: detailed marking scheme agreed by all and used for mark sheet



Timetable of events

1. Introduction to agile methods, scrum, and test driven development via lectures,

followed by JUnit lab.

2. Introduction to continuous integration and refactoring via lectures.

3. Continuous integration server launched, with 30 minute intervals for builds.

4. Continuous integration lab.



Acknowledgements:

2 Microsoft & HEA-ICS

Team Agile Methods Case Study





5. Assignment issued, with explanation of process targets rather than product

targets.

6. Assignment marking scheme discussed and criteria agreed by class, in class

time, facilitated by lecturer (see next section”

7. Students advised to partner with someone at a similar ability level to themselves,

and invited to organise pairs for assignment.

8. Created a source code repository account and project for each pair

9. Created a source code repository account for CruiseControl and Ant to have

read access to each pair’s project.

10. Build scripts finalised to send results emails to tutors and students

11. Students given 4 hours of timetabled time to work upon assignment.

12. Students invited to spend up to 20 hours working upon assignment.

13. Final 2 days of assignment: students request for more frequent builds - interval

changed to 15 minutes.

14. Continuous integration server and then the configuration management server

were closed down at 17.00 at the end of week 2.

15. Student performance assessed

16. Mark results issued (see appendix 3)







Student-derived marking scheme

Identification of the assessment measures was a class undertaking via a “negotiation”

class before the assignment formally began. Discussion led to the identification of

products and processes to be rewarded with marks. Consensus was a collective

responsibility. Once agreed, the marking scheme could not be altered without

majority approval. As an example, students had to agree the relative importance of

(a) obtaining skill with the tool compared to (b) comprehending its contribution to the

discipline.









Feedback

Feedback was obtained via anonymous questionnaires, a group feedback session, and

a number of individual interviews at the end of the semester. Students’ judgements

were positive, for instance:

“great as we have learnt practical skills that we can apply immediately”

“course structured well with assignment work reinforcing materials covered in

lectures”

“the whole experience was a good one”

“The first assignment was very good. Using the Blackboard portfolio feature was very

good as it recorded when students made their notes as part of their ongoing work,

therefore, it was felt, preventing students from just coming up with their entire log at

the last minute the day before it was required.”



Students also appreciated having ownership of the marking scheme. They valued the

experience of judging the importance of different components such as participation,

performance, understanding and reflection. A sample of students interviewed said



Acknowledgements:

3 Microsoft & HEA-ICS

Team Agile Methods Case Study





they believed it contributed both to the success of their learning and to their

motivation. The scrum approach was adopted by one team in a subsequent project,

and attributed by them as one reason for receiving the top mark of the class.





Reflection

1. - as before with regard to students’ enjoyment and tutors’ marking effort.

2. Tutors remained disappointed with students’ use of mock objects, and their

ability to reflect upon their learning, but were pleased with their improved

understanding of other agile processes.

3. The initial and final build intervals were appropriate to the stage of the project.

4. The project topic was not very motivating and still insufficiently challenging.

5. Students’ involvement in agreeing the marking scheme led to their consideration

of (i) quality criteria, (ii) component relevance, and (iii) learning priorities

before the assignment formally begins, rather than wistfully afterwards when it

is too late to be influential.

6. Pair programming was successful and popular.

7. Scrum was successful and popular.

8. Students would have preferred a larger size of team, for example with 3 pairs

working on different user stories and having to integrate their implementations

at team level.

9. Fairness is felt to be very important: giving pairs a choice of user stories to

implement resulted in disappointment for some pairs “we were not to know that

some would have enabled greater use of certain practices and therefore receive

higher marks”.









Acknowledgements:

4 Microsoft & HEA-ICS



Related docs
Other docs by wuyunqing
Abstraction_of_student_and_master_work
Views: 1  |  Downloads: 0
Наталия_ здравствуйте
Views: 4  |  Downloads: 0
Embedded IP-PBX
Views: 18  |  Downloads: 0
RESPRO Comment Summary
Views: 0  |  Downloads: 0
1992-03-31
Views: 0  |  Downloads: 0
Organic Chemistry
Views: 0  |  Downloads: 0
Hello there
Views: 0  |  Downloads: 0
User Product Manual
Views: 4  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!