Example Agency Progress Report

Document Sample
Example Agency Progress Report Powered By Docstoc
					                                          Progress Report
                                                 Link Light Rail




The last of the University Link LRVs was delivered to the Operations &
    Maintenance Facility, completing the LRV fleet of 62 vehicles.




                                                August 2011
                   TABLE of CONTENTS

Program Overview ................................................................1
University Link ......................................................................3
        Early Construction Work ............................................13
        Tunnels .........................................................................14
        Stations ........................................................................18
        Systemwide ..................................................................20
North Link..............................................................................21
Initial Segment/Airport Link .................................................26
Initial Segment .....................................................................27
Airport Link ...........................................................................28
East Link….. ..........................................................................29
South Link .............................................................................32
Staffing Report......................................................................35
Acronyms ..............................................................................46
                                                                 Link Light Rail
                                                             Program Overview




Map of Sound Transit’s current and future light rail projects.
                                                                                                          0;o`

Link Light Rail
                                                                                                          //


Program Overview

Projects
University Link: The University Link work program with $1.76 billion capital budget was approved by the Board in
July 2008. The 3.15-mile light rail segment is located entirely underground with tunnels traveling from Pine Street,
under the I-5 freeway to an underground station at Capitol Hill, continuing north beneath SR 520 and the Lake Wash-
ington Ship Canal to an underground station on the University of Washington campus, near Husky Stadium.

North Link: The University of Washington Station (UWS) to Northgate project is a 4.3-mile extension of light rail
from the UWS north under campus via twin-bored tunnels to an underground station at NE 45th Street continuing to
an underground station at NE 65th Street and via tunnel, retained cut and elevated sections to Northgate. Preliminary
engineering and the Final Supplemental Environmental Impact Statement (FEIS) process has been completed for North
Link. The project is in Final Design.

Initial Segment: Completed 13.9-mile light rail line between downtown Seattle and South 154th Street in the City of
Tukwila. Revenue service began on July 18, 2009. The Initial Segment represents the Minimum Operable Segment
(MOS) for the executed Full Funding Grant Agreement (FFGA).

Airport Link: Completed 1.7-mile extension of the Initial Segment to Sea-Tac International Airport. Revenue service
began on December 19, 2009.

East Link: East Link expands light rail to East King County via I-90 from Downtown Seattle to the Overlake Transit
Center area of Redmond, with stations serving Rainier Avenue/I-90, Mercer Island, South Bellevue, Downtown Belle-
vue, Overlake Hospital, the Bel-Red corridor, Overlake Village and the Overlake Transit Center. Revenue Service to
the Overlake Transit Center forecast for early 2023 with a tunnel route in Downtown Bellevue.

South Link: South Link consists of a 1.6-mile extension of the light rail from the SeaTac/Airport Station to an elevat-
ed station at South 200th Street. Preliminary Engineering and the Environmental Impact Statement have been complet-
ed and a Record of Decision has been issued for this segment. A decision to proceed with a design/build delivery strat-
egy was approved by the Sound Transit Board in July 2011.


 Active Program Budget


                            Project               Adopted Budget            Committed              Incurred
                                                                             to Date                to Date

       University Link(3)                                    $1,947.7               $1,293.5              $776.5

       North Link(1)                                          $345.5                  $136.3               $82.0

       Initial Segment(4)                                    $2,436.9               $2,332.6            $2,291.7

       Airport Link(4)                                        $269.1                  $259.6              $255.9

       East Link(2)                                           $364.5                   $63.1               $57.9

       South Link(2)                                          $383.2                   $18.6               $17.2

       Total                                                $5,746.9               $4,103.7            $3,481.1

       Table figures in millions.
       (1) Final Design Phase
       (2) Preliminary Engineering Phase
       (3) Construction Phase
       (4) In Service


August 2011                                                                                                      Page 1 of 47
                                                           Link Light Rail
                                                       Program Overview

 Program Schedule
 Schedules for active projects are summarized below.




August 2011                                                        Page 2 of 47
Link Light Rail
University Link

Project Summary
Limits:       3.15-mile extension of the Initial Segment
              light rail transit (LRT) system from the Pine
              Street Stub Tunnel (PSST) in downtown Seat-
              tle to University of Washington (UW) cam-
              pus near Husky Stadium.
Tunnels: Two twin bored tunnels. Two contract seg-
         ments: U220 runs along the University Link
         (U-Link) alignment starting at Husky Stadi-
         um, continues beneath SR 520 and the Lake
         Washington Ship Canal and south to Capitol
         Hill underground station. U230 commences
         at Capitol Hill Station proceeding south and
         runs under I-5 freeway to PSST where Initial
         Segment terminates.
Stations: 2 underground center platform stations –
          Capitol Hill (U240) and University of Wash-
          ington (U250). U240 is approximately 65’
          underground with three station entrances.
          Meanwhile, U250, is about 100’ below
          ground, also with three station entrances but
          is connected to the UW campus by a pedestri-
          an bridge.
System:       27 LRV; direct fixation tracks, signals, trac-
              tion electrification, and SCADA communica-
              tions
Budget:       $1.948 billion including finance cost (capital
              subtotal of $1.756 billion)




Key Project Issues
  Non-structural hairline cracks continues to appear on the tunnel liners in U220. Root cause on this issue has not
   been determined. Sound Transit continues to monitor as well as investigate all work sequences from curing and han-
   dling installation of the tunnel liners. Contractor’s segment and insert manufacturer are evaluating the issue. Con-
   tractor will provide Sound Transit a complete report.
  U230 tunneling production has improved but continues to lag the planned production rates. Muck removal is also
   lagging behind the planned rate. Contractor has now started additional shift to increase the production of muck re-
   moval.
  U250 University of Washington Station: UW’s Husky Stadium renovation and the Montlake Triangle Projects add
   logistic complexities in the geographical vicinity of the project.
  Continued design discussion on the Montlake Triangle Project (MTP) and SR520 Preferred Alternative with stake-
   holders. The MTP plan includes a 30' wide pedestrian bridge (Sub-Package—SP1) over Montlake with a bike ramp
   connecting at the center of Rainier Vista Triangle (to be designed and constructed by ST) and a landbridge (SP2) over
   Pacific Place and the Burke Gilman trail (to be designed and constructed by UW). The MOA between the principal
   stakeholders – WSDOT, UW, and Sound Transit – has been signed by all parties. U250 GC/CM contractors sub-
   mitted their 60% comments and their estimate for SP1 continues to be reviewed. Preliminary estimates on SP1 seems
   to be higher than anticipated. UW has commenced Final Design for SP2 and SP3 with 60% anticipated in Septem-
   ber.


August 2011                                                                                                     Page 3 of 47
                                                                                                                    Link Light Rail
                                                                                                                    University Link

 Project Cost Summary
 The U-Link project cost is summarized in two types of cost classifications. The first table is classified in accordance to
 Sound Transit’s Work Breakdown Structure (WBS) and the second table summarizes cost in accordance to the FTA’s
 Standard Cost Categories (SCC) format. (Both tables’ figures in millions.)

                                                                        Current
                                                  Baseline                           Commitment       Incurred to     Est. Final Cost   Adopted
         WBS Phase Elements                                             Adopted
                                                   Budget                              to Date*          Date              (EFC)      Budget vs. EFC
                                                                         Budget
 ADMINISTRATION                                            115.2               115.2           28.6            29.5             115.2             0.0
 PRELIMINARY ENGINEERING                                    24.4                24.3           24.3            24.3              24.3             0.1
 FINAL DESIGN                                               77.9                87.6           77.1            66.4              87.6             0.0
 CONSTRUCTION SERVICES                                      68.5                95.7           74.2            27.1              95.7             0.0
 3rd PARTY AGREEMENTS                                       18.6                18.6           11.2             9.9              18.6             0.0
 CONSTRUCTION                                            1,180.0             1,158.2          662.2           365.0           1,076.2            82.0
 VEHICLES                                                  103.9               103.9           98.6            89.0             103.9             0.0
 ROW                                                       167.3              152.3           125.6           124.8             126.9            25.4
               Capital Total                             1,756.0             1,756.0        1,101.8           736.0           1,648.5           107.5
 FINANCE COST                                              191.7              191.7           191.7            40.6             191.7              0.0
               Project Total                             1,947.7             1,947.7        1,293.5           776.5           1,840.2           107.5
 (*)Totals may not equal column sums due to rounding of line entries.

 The August 2011 projection of U-Link Estimated Final Cost (EFC) including Finance Cost remains as previous month
 at $1.84B. This period, approximately $33.4M was incurred bringing the incurred to date to $736M (Finance Cost ex-
 cluded). Construction cost accounts for most project expenses. The construction EFC continues to trend at $1.08B with
 only two major construction contracts remain to be procured, Capitol Hill Station (U240) and the Systems (U830) con-
 tracts. The total incurred to date for the Construction phase is approximately $365M with a current commitment of
 over $662M. Cost for LRV continues to be stable as the LRV contract has now moved from manufacturing phase to
 final acceptance phase. In August, Sound Transit took delivery of the final 2 LRVs. The total incurred cost to date for
 Vehicles is at $89M with a commitment of over $98M.

 Construction EFC under the SCC format for this period remains unchanged at roughly $1.03B. Construction phase
 expenditures during August were roughly $24M, primarily in the SCC 10 (Guideway and Track Elements) and SCC 40
 (Sitework) categories. Incurred to date for SCC 20 (Station) at $76.7M clearly reflects increased activities at the U250
                                                                                                                                 continued next page
                                                                        Current
                                                  Baseline                             Commitment     Incurred to     Estimated Final   Adopted
       Project Elements by SCC                                          Adopted
                                                   Budget                                to Date*        Date           Cost (EFC)    Budget vs. EFC
                                                                         Budget

 10 Guidew ay & Track Elements                             626.8               557.6          374.2           247.8             505.4            52.2
 20 Stations                                               366.3               367.0          224.4            76.7             343.5            23.5
 30 Support Facilities: Yards, Shops                         7.0                 8.3            7.0             7.0               7.1             1.2
 40 Sitew ork & Special Conditions                          59.0                72.5           52.7            32.6              68.0             4.5
 50 Systems                                                 69.6               101.8            0.5             0.5             101.3             0.5
  Construction Subtotal (SCC 10-50)                      1,128.8             1,107.2          658.8           364.6           1,025.2            82.0
 60 Row , Land, Existing Improvements                      167.3               126.9          125.6           124.8             126.9             0.0
 70 Vehicles                                                99.8                99.8           98.6            89.0              99.8             0.0
 80 Professional Services                                  306.5               343.8          218.7           157.5             346.4            -2.6
 90 Unallocated Contingency                                 53.5                78.3            0.0             0.0              50.2            28.2
    Capital Cost Total (SCC 10-90)                       1,756.0             1,756.0        1,101.8           736.0           1,648.5           107.5
 100 Finance Cost                                          191.7               191.7          191.7            40.6             191.7             0.0
              Project Total                              1,947.7             1,947.7        1,293.5           776.5           1,840.2           107.5

 (*)Totals may not equal column sums due to rounding of line entries.

August 2011                                                                                                                               Page 4 of 47
Link Light Rail
University Link




continued from previous page
UW Station site as Contractor continues with the roof
slab concrete pours and excavation. Incurred to date for
Construction SCC is at $364.6M. When non-
construction cost (SCC 60-90) is accounted for, total cap-
ital cost incurred (excluding Finance Cost) for U-Link is
at $736M.
Overall project cost, including Finance cost as of August
2011 is approximately $776.5M. It is currently projected
that by December 2011, U-Link incurred cost will reach
$863M and by March 2012, will reach $932M or between
45-48% of project budget including Finance cost.
The EFC for project Finance Cost continues to be as
budgeted and projected at $191.7 million. This cost rep-
resents booked financing cost and is generated based on
allocation of appropriate level of financing cost to each
capital project at Sound Transit. Despite an earlier than
anticipated release of $44 million of the FFGA funds due
to the American Recovery Reinvestment Act that was
used to pay down finance charges, it is premature to pro-
ject any savings at this time.




                                                             Note: The overall construction progress above is based on a weighted combination
                                                             of duration, schedule and cost % complete for individual construction contracts as
                                                             compared to the overall U-Link construction contracts.


August 2011                                                                                                                     Page 5 of 47
                                                                                                                                                                      Link Light Rail
                                                                                                                                                                      University Link

 Cost Contingency Management
 Project contingencies continue to remain at a healthy levels due to the favorable construction bidding climate and very
 favorable ROW acquisition cost trends. August’s overall contingency balance remains practically unchanged at ap-
 proximately $367M from last period. Draws on contingency in August were nominal and was attributed to normal
 construction contract change orders. Contingency level continues to be well above the Planned Contingency Draw-
 down which was projected to be in the $231M and $205M range for 3nd QTR 2011, projected contingency balance af-
 ter planned drawdown range for 3rd QTR 2011 is between $196M and $205M, and the Contingency Buffer was pro-
 jected to be in the $204M and $198M range for this period. The Reserved Contingency at $150M was originally pro-
 jected to drawdown to $80M in the 4th QTR 2011; this is now projected to occur in the 2nd QTR 2012 (see contingen-
 cy curve at the bottom of page).

 Design Allowance: The balance of design allowance of $4.8M remains unchanged from the previous period. The level of
 design allowance currently represents less than 1% of the total remaining work in the project.
 Allocated Contingency: Allocated contingency drawdown for this period was due to contract change orders for U220 and
 U230. Allocated contingency actually increased by approximately $247K due to a credit realized in U220.
 Unallocated Contingency (UAC): The UAC balance is around $50M. UAC continues to remain stable in light of the fund-
 ing levels for Allocated Contingency. Lower than anticipated costs for ROW and major construction contracts are also
 factors contributing to lower than anticipated UAC drawdown.

                                     BCE                              Current Status
 Contingency                                                                                                                                 Contingency by Type Histogram
                                                                  R emaining % R emaining
    Status           Amount                 % of Total             A mo unt      W o rk                            $450.0
                                                                                                                                       $373                $372                   $368                   $367
                                                                                                                   $400.0
 Design                   $103.9               7.8%                           $4.8         0.7%                    $350.0                $51                $50                    $50                    $50
 Allowance                                                                                                         $300.0
 Allocated                                                                                                         $250.0
                          $264.3              19.8%                    $312.3              47.8%                   $200.0
 Contingency                                                                                                                           $315                $313                   $312                   $312
                                                                                                                   $150.0
 Unallocated                   $53.7           4.0%                       $50.2            7.7%                    $100.0
 Contingency                                                                                                        $50.0                 $5                 $5                     $5                    $5
                                                                                                                       $0
      Total:              $421.9              31.6%                    $367.3              56.3%                                     May-11                Jun-11                 Jul-11                Aug-11
                                                                                                                                 UAC                                              Allocated Contingency
 Percentage = Contingency $ /(EFC or Remain. Work $ ex-Contingencies)                                                            Design Allowance                                 Available Contingency


 MINIMUM CONTINGENCY CURVES                                                                                                                                                                             $ in millions

  $450.0
  $400.0
  $350.0
  $300.0
  $250.0
  $200.0
  $150.0
  $100.0                                    Reserved
   $50.0
      $0
                                            Contingency
                                              Dec '09




                                                                                                                 Dec '12




                                                                                                                                       Dec '13




                                                                                                                                                                                                           Dec '16
                     Dec '08




                                                                    Dec '10




                                                                                           Dec '11




                                                                                                                                                            Dec '14




                                                                                                                                                                                    Dec '15
                                  Jun '09




                                                        Jun '10




                                                                                                                           Jun '13




                                                                                                                                                                                              Jun '16




                                                                                                                                                                                                                     Jun '17
           Jun '08




                                                                                 Jun '11




                                                                                                       Jun '12




                                                                                                                                                 Jun '14




                                                                                                                                                                        Jun '15




                               Reserved Contingency                                                  Planned Contingency Draw Down                                    Contingency Balance
                               Minimum Contingency                                                   Buffer at +20% of Minimum




August 2011                                                                                                                                                                                               Page 6 of 47
Link Light Rail
University Link

Project Schedule Summary
The University Link schedule is provided below. U210 and U211 achieved Substantial Completion in past periods.
U215 is complete with commercial issues resolved. The U220 Contractor launched the southbound tunnel boring ma-
chine (TBM) on May 31, 2011 and commenced tunneling at the northbound tunnel on June 30, 2011. The U220
Northbound (NB) and Southbound (SB) TBMs are in full production. The U230 NB TBM has been launched and the
conveyor system is now installed. The U230 mining production rates have not yet reached full production. The U250
roof structure from gridline 6 north has been completed; and mezzanine level excavation is complete from gridline 20 to
9. The U820 Contractor has completed all work and is completing closeout items. The U830 Systems contract has been
repackaged to include the U840 Comm. and the U850 Emergency Ventilation Control System. U835 EMI, Vibration
and Wheel Flat Detection and the U860 Network System to update Link Control network equipment will be individual
contracts. GC/CM contract procurement for U830 Systems commenced at the end of last period and U240 Capitol
Hill Station contract procurement has commenced. The targeted Revenue Service milestone remains on September 24,
2016.




August 2011                                                                                                   Page 7 of 47
                                                                                            Link Light Rail
                                                                                            University Link

 Progress and Critical Path Analysis
 The U-Link master schedule update contains the tunnel contractors’ schedules and interfaces with the station and U830
 (track, signal, traction power and communications system) schedules. Tunneling commenced in the 2nd QTR 2011
 with TBM assembly and launch. Tunneling will continue through early 2013. Once the U230 is substantially complete
 in the 2nd QTR 2013, rail distribution will commence and the U830 contractor will mobilize. OCS installation will
 start following rail distribution in early 2015. Substations will then be completed at each station in the 2nd QTR 2015
 and U830 system-wide communication integration testing will commence in the 3rd QTR 2015.




  Critical Path
  The critical path for the University Link schedule continues to derive from the completion of the tunnels, between CHS
  to PSST, to the installation of track, signals and OCS in the tunnels. A later than expected start for mining at the U230
  site has now impacted the project critical path by 16 days. Overall impacts to the U-Link master schedule are shown in
  the August update. The Contractor is developing a mitigation plan for these delays.
  Four days of float have been utilized from the U-Link float contingency of 176 days to maintain the Revenue Service
  Date of September 24, 2016. Float contingency for this period is 172 days.




August 2011                                                                                                      Page 8 of 47
Link Light Rail
University Link
 Progress and Critical Path Analysis, continued

 Schedule Performance Index
 The Schedule Performance Index (SPI) for the project has risen slightly this period. The rise is due to the positive pro-
 duction rates at U220 and the above projection progress at U250. The slow progress at U230 continues to keep U-Link
 SPI below a 1.0 based on early forecasts. Progress will continue to be monitored closely.




 Cost Progress Analysis
 The current project productivity level improved slightly this period as U220 continues to exceed production forecasts
 and U250 continues to stay ahead of schedule. Mining at U230 continues below expected production rates. U230 is
 expected to submit a mitigation plan for the slowed production rates. Overall U-Link physical % complete is at
 36.94%. Below is a graphical representation of the progress of major construction contracts cost compared to the early/
 late projections.




August 2011                                                                                                      Page 9 of 47
                                                                                              Link Light Rail
                                                                                              University Link
 Schedule Contingency Management
 The “Minimum Schedule Contingency Curves” were established in the Project Execution Plan (PEP). The PEP segre-
 gated Schedule Contingency into “Forced Lag,” which is a built-in float on the Critical Path; “Buffer Float,” which is
 the duration between Sound Transit’s targeted Revenue Operation Date and the Schedule Revenue Operation Date;
 “Contingency Float,” which is the duration between Sound Transit targeted Revenue Operation Date and the FFGA
 Revenue Operation Date, and “Desired Minimum Float” which is the amount of schedule float the FTA requires
 Sound Transit to maintain. The current schedule contingency balance continues to be 14 months, 6 months above the
 “Desired Minimum Float” required by the PEP.




 Right-of-Way
 The U-Link project involves the acquisition of a range of property interests, including fee takings for stations and stag-
 ing areas, tunnel easements for the running tunnels, acquisitions from the University of Washington and airspace leases
 with the Washington Department of Transportation. These acquisitions required relocations of 141 owners and ten-
 ants. All required relocations have been completed. As of September 13, 2007, 242 parcels were certified for the Capi-
 tol Hill Station staging area and underground tunnel easements. The total number of certified parcels was adjusted in
 May 2009 when two parcels were decertified and one parcel was added for a total of 241 parcels. The right-of-way pro-
 gram status as of this period is summarized below.

                                                                                                      Reloca-      Reloca-
                           Total                    Signed       Admin.       Posses-
                                       Offers                                             Closings     tions        tions
     Line Section         Parcels                   Agree-       Settle-     sion and
                                       Made                                               to date       Re-         Com-
                         Certified                  ments        ments          Use
                                                                                                      quired       pleted
  Capitol Hill Station      19            19                                                  19        140          140

  Tunnel Easements          223          222                                                  222        1            1

  TOTAL                     242          241                                                  241       141          141

  Capitol Hill Station: The acquisitions and relocations for the station site are complete.
  Tunnel Easements: Appraisals have been completed and offers made on 222 tunnel easements. All 222 parcels have
  closed. A WSDOT parcel continues to be in pending status; Sound Transit may not need this parcel for the project.




August 2011                                                                                                     Page 10 of 47
Link Light Rail
University Link
                                                                                            Year to   Project to
Construction Safety                         Data/Measure                      August 2011
                                                                                             Date       Date
Safety statistics for reporting             Recordable Injury/Illness Cases       5           14         29
and year-to-date periods are                                                      0           2           5
                                            Days Away From Work Cases
summarized in the table and
charts.                                      Total Days Away From Work            0           13         201

                                       Restricted or Modified Work Cases          3           4           8

                                   Total Days Restricted or Modified Work         12         221         305

                                                           First Aid Cases        3           21         35

                                                   Reported Near Mishaps          7           32         75

                                      Ave. Nos. of Employees on Worksite         321          NA         NA

                                            Total # of Hours (GC & Subs)        68,705      458,510   1,065,688
                                                                               Monthly      Year to   Project to
                                        OSHA Incident Rates
                                                                               Average       Date       Date
                                                    Recordable Injury Rate       14.55       6.11       5.44
                                                               DART Rate         8.73        3.74       2.44
                                                Recordable National Average      4.30        4.30       4.30
                                                    DART National Average        2.30        2.30       2.30
                                               Recordable WA State Average       8.20        8.20       8.20
                                                   DART WA State Average         3.90        3.90       3.90




The charts to the right show
University Link’s Recordable
Injury Rates (RIR) and Univer-
sity Link’s Days Away, Restrict-
ed or Modified (DART) Injury
Rate as compared to the nation-
al average.




August 2011                                                                                            Page 11 of 47
                                                                                             Link Light Rail
                                                                                             University Link

 Quality Assurance Activities
 Activities
     Coordinated with Engineering team on investiga-
      tion of root cause of cracking in precast concrete
      tunnel liner segments.
   Performed QA Assessment of U220 and U230 Pre-
      cast Concrete Tunnel Liner manufacturing facility –
      report pending.
   Performed and issued reports on:
       U220 Tunnel Segment Cracks
       U230 Northbound Tunnel Excavation
   Material Review Board approved 2 NCRs.
  Issues
   U220 and U230 precast concrete tunnel liner crack-
      ing.
  Summary                                                   Outreach staff hosted a coffee hour for the Capitol Hill residents and
                       Aug                                  answered questions on U-Link construction.
       Description     2011               Notes
  No. of Audits           0
  Planned                                                   Community Outreach
  No. of Audits                                             Staff distributed the monthly U-Link e-newsletter to the
  Completed               0
                                                            project’s email list.
  Reports in Pro-         1      U821 LRV Post Delivery
  gress                          Buy America Audit          University of Washington
                                                            Staff attended tours at the UW Station site for the trans-
  No. of Audits                                             portation aides to Congressmen Norm Dicks and Jay
  Postponed               1      U220 RE Audit
                                                            Inslee. Also coordinated a site tour with Congressman
                                                            Reichert’s staff. Hosted tours for the Citizen Oversight
                                                            Panel.
 Sound Transit Board Actions
 Board motions and resolutions directly related to          Capitol Hill
 University Link are summarized in the table below.         Outreach staff hosted a coffee hour at Peet’s Coffee and
                                                            Tea for residents of Capitol Hill to discuss construction
      Motion              Description                Date   progress. Staff attended the city council briefing on the
      Number                                                Capitol Hill Transit Oriented Development.
               None to report.                              Business Mitigation
                                                            Artist Jesse Brown completed painting the Broadway
                                                            Farmers Market Poster on the community corner of the
 Environmental                                              Red Wall. Sound Transit is the presenting partner for
                                                            Three Dollar Bill Outdoor Cinema in Cal Anderson Park.
 Stormwater and industrial waste discharge permit com-      In order to qualify for a free movie and a cardboard mov-
 pliance, along with the hazardous materials oversight      ie chair (Bum Box), movie goers needed to spend $10 at
 continue for the U Link at the U220, U230, and U250        any Capitol Hill establishment the day of the movie
 construction sites.                                        showing. A total of 100 Bum Boxes have been given
                                                            away which reflected $1,000 or more retail sales for the
                                                            Capitol Hill businesses.




August 2011                                                                                                           Page 12 of 47
Link Light Rail
University Link– Early Construction Work

 Early Works Contracts (U210, U211 & U215)

 Early work contracts have been completed.


 For the U210 Contract (Advanced Utility Relocation), Final Acceptance issued in May 2011. Finalizing remaining closeout
 items.


 For the U211 Contract (Demo and Environmental Remediation), Final Acceptance has been reached; finalize closeout docu-
 ments.

 For the U215 Contract (I-5 Crossing), All issues in this contract have been resolved.




August 2011                                                                                                    Page 13 of 47
                                                                                Link Light Rail
                                                                      University Link– Tunnels

U220 Contract - TBM Tunnel (UWS to CHS)

 Current Progress
 Southbound (SB) TBM mining
 productivity levels continue to
 exceed expectations. Northbound
 (NB) TBM has exceeded expecta-
 tions. Mining is expected to con-
 tinue this positive trend.
 Physical % complete is at 67%
 against 47% contract time ex-
 pended.
 Progress will continue to be mon-
 itored closely.


  .




 Schedule/Critical Path
 The U220 SB TBM has completed approximately 2,154 feet of tunnel. The U220 NB TBM has completed 983 feet of
 tunnel this period. The U250 UW Station contractor is now on site. The schedule update for this period is reporting
 zero days of float to Milestone #4, Substantial Completion, as the Contractor prepares for future cross-passage excava-
 tion. Milestone #3, Completion of Tunneling, has improved this period and is reporting 17 days of positive float. It is
 expected the positive trends will continue.
 The Contractor has submitted two severe weather delay notices and the milestones have been adjusted to represent ap-
 proved changes. The critical path continues the completion of the tunnels and cross-passages. Production rates will be
 monitored closely to limit any additional impacts to the critical path.




August 2011                                                                                                  Page 14 of 47
Link Light Rail
University Link– Tunnels
Schedule Performance Index
The U220 Schedule Performance (SPI)
this period remains below a 1.0, based on
early finish forecasts. Progress again im-
proved this period with positive produc-
tion rates for the SB TBM and the launch
and mining by the NB TBM. Production
will be monitored closely as tunnel min-
ing continues.




Key Activities                                                    Next Period

Current Period                                                 Continue concrete segment production.
   Completed installation of elevators and received L&I       Continue southbound mining operations.
    certification.                                             Restart mining the NB tunnel to Cross Passage #19 and
   Continued production of concrete segments at a Tacoma       beyond. Complete startup proof grouting.
    plant: 59% of rings have been cast.                        Continue pre-construction surveys of residences along
   Southbound (SB) TBM: Completed cutterhead inspec-           the alignment in the neighborhood south of SR-520.
    tion and maintenance stop. Currently tunneling towards Closely Monitored Issues
    Cross Passage #17A. Total distance mined: 2,154 feet.
                                                               A draft of the Halcrow Report on segment hairline
    Total rings to date: 427
                                                                cracks has been received by TFK. The final report will be
   Northbound (NB) TBM: Completed installation of tun-
                                                                distributed to Sound Transit staff as soon as it arrives.
    nel conveyor system; of slab and rail in front of tunnel
    eye; and of electrical gantries to the NB TBM. Total dis-  Southbound TBM is beginning to ascend the slope up to
                                                                Capitol Hill.
    tance mined:963 feet. Total rings to date: 186.




Cost Summary
         Present Financial Status                   Amount
 U220 Contractor— Traylor Frontier-
 Kemper Joint Venture (TFK)
 Original Contract Value                           $309,175,274
 Change Order Value                                  $3,179,872
 Current Contract Value                            $312,355,146
 Total Actual Cost (Amount Billed)                 $211,559,270
 % of Authorized Billed to-date                          67.7%
 Physical Percent Complete:                              67.5%
 Authorized Contingency                             $30,917,527
 Contingency Drawdown                                $3,179,872
 Contingency Index*                                        6.56

 *Physical % complete / % contingency drawn down                    Excavator loading truck with muck from the muck pit.


August 2011                                                                                                                           47
                                                                                                                           Page 15 of 48
                                                                                 Link Light Rail
                                                                       University Link– Tunnels

 U230 Contract -TBM Tunnel (CHS to PSST)
 Current Progress
 The NB TBM has mined a total of 562 ft. to date. Slow TBM mining production and the installation of the conveying
 system this period has impacted the schedule this period. The conveyor installation was completed this period and is
 expected to improve production. The Contractor is expected to submit a mitigation schedule for review. Pine Street
 retrieval shaft and adit excavation is complete. Work progress continues with approximately 63% physical completion
 against 52% contract time expended.




 Schedule/Critical Path
 The Northbound TBM mining continued briefly this month as the Contractor installed the muck conveying system.
 Mining commenced at the end of the period at slower then forecast mining rates. Milestone #4, Substantial Comple-
 tion, is reporting 16 days of negative float in the August schedule update. The Contractor is expected to submit a miti-
 gation plan for current delays. The Contractor has submitted two severe weather delay notices that have been approved
 by the CM Team. The critical path continues through the assembly and launch of the TBM Northbound and retrieval
 and return to CHS for the commencement of the southbound tunneling and cross passage work.




August 2011                                                                                                   Page 16 of 47
Link Light Rail
University Link– Tunnels
 Schedule Performance Index
 The U230 Schedule Performance Index (SPI)
 remains below a 1.0 this period, based on early
 forecasts. A slight improvement to SPI was not-
 ed this period due to the commencement of min-
 ing and the installation of the conveyor system.
 Production is expected to improve now that the
 conveyor system is in place. Production will be
 monitored closely as tunnel mining contin-
 ues.




 Key Activities                                                  Closely Monitored Issues
 Current Period                                               JCM’s new hyperbaric consultant is not prepared to ap-
                                                               prove the revised compressed air plan on account of is-
  CHS – Continued tunneling of the northbound tunnel.
                                                               sues relating to industry standard practices.
   Total distance mined: 562 feet. Total rings to date: 108
                                                              TBM tunneling status continues to fall behind schedule.
  The manufacturing of the concrete tunnel lining seg-
                                                               The second tunneling shift began this past month, but
   ments continued and approximately 73% of the seg-
                                                               without much improvement. Recovery measures will
   ments have been cast.
                                                               need to be requested if this trend continues. ST to closely
  Muck removal continued and second shift added.              monitor the progress.
  Pine St.– Shaft excavation and associated activities con-  The hairline cracks that have been identified within some
   tinued. Excavation progressed down to approx. eleva-        of the precast concrete segments continue to be investi-
   tion 100. Excavation of the access drift/pile removal       gated by ST, JCM, the segment manufacturer and de-
   chamber (Adit) continued and is approx. 99% complete.       signer. Preliminary designer review indicates cracks are
 Next Period                                                   a non-structural issue.
  Continue NB tunneling towards cross passage #4.            Proof drilling within the initial 500 feet of tunnel to
  Continue muck removal with muck hauler                      check the quality of tail void grout continues to be a
   (Senneboggen) and hauling of muck to offsite location.      struggle. Results of some initial cores taken have been
  Continue receiving and staging tunnel segments.             reviewed with JCM, and further cores are being planned.
  Pine St. – Finalize the last of the excavation and begin   Ground conditions at cross passage #5 are being dis-
   installation of base slab in retrieval shaft and adit.      cussed further. The potential need for a combined ex-
  Mobilize subcontractor and equipment to begin electrical    ploratory borehole and dewatering well drilled from the
   conduit work in the PSST vent shaft.                        surface has been identified.
                                                             .
Cost Summary
         Present Financial Status                  Amount

 U230 Contractor— JCM Joint Venture

 Original Contract Value                          $153,556,000
 Change Order Value                                 $4,850,110
 Current Contract Value                           $158,406,110
 Total Actual Cost (Amount Billed)                 $98,283,519
 % of Authorized Billed to-date                           62%
 Physical Percent Complete:                               62%
 Authorized Contingency                            $15,355,600
 Contingency Drawdown                               $4,850,110
 Contingency Index*                                       1.96

*Physical % complete / % contingency drawn down                  Installation of conveyor belt support rails in the tunnel.

August 2011                                                                                                                              47
                                                                                                                              Page 17 of 48
                                                                                 Link Light Rail
                                                                       University Link– Stations
 U250 Contract –University of Washington Station

 Current Progress
 The roof structure is complete from gridlines 6 through 20. Mezzanine excavation continues from gridline 9 to 20.
 Design review and coordination discussions regarding the Montlake Triangle Project revisions continue. Work Pro-
 gress Continues with approximately 8% physical completion against 9% contract time expended.




 Schedule/Critical Path
 The roof structure is complete from gridline 6 to 20. Mezzanine level excavation continues from gridline 9 to 20. Mile-
 stone #7, Substantial Completion, is reporting zero days of float. The Contractor is meeting production forecasts at this
 time.
 The critical path continues through the installation of the station roof slabs, excavation of mezzanine, basement level
 and platform floor slabs under a modified top down construction plan. As the U220 Contractor completes tunnel bor-
 ing from UWS to CHS, the U250 Contractor will commence work on the crossover area. Systems critical rooms will be
 made available to the U830 systems contractor, as the station and crossover near completion. Final Testing and com-
 missioning will then complete the U250 work.




August 2011                                                                                                    Page 18 of 47
Link Light Rail
University Link– Stations
 Schedule Performance Index
 The U250 SPI continues to report
 above a 1.00 but is beginning to level
 off as upfront mobilization costs have
 already been paid and the impact was
 reflected in previous months. Based on
 the current schedule update, the Con-
 tractor is ahead of schedule and cur-
 rent progress is expected to contin-
 ue. Production levels will continue to
 be monitored closely.



 Key Activities                                                    Next Period
 Current Period                                                         Continue waterproofing, formwork and placing MEP
     Continued construction of roof structure including                 inserts at west station entry and roof structure.
      form work, reinforcing steel, MEP inserts and concrete            Continue mezzanine –level excavation.
      placement.                                                        Continue roof structure construction.
     Commenced waterproofing at west entry and north                   Continue concrete placement at mezzanine level and
      end of roof structure.                                             roof structure.
     Completed excavation, lagging, tiebacks and bracing at            Sub bid opening for 9 bid packages in September.
      the west station entry.                                           Review of 90% design on MTP-SP1 (Montlake Pedes-
     Commenced formwork and placing of MEP inserts at                   trian Bridge).
      the west entry and mezzanine level structure.
                                                                   Closely Monitored Issues
     Continued mezzanine-level excavation.
     BIM: GC/CM continues to develop Building Infor-                   Complexity of MTP interface and coordination with
      mation Modeling (BIM) model along with their me-                   UW Husky stadium renovation activity.
      chanical and electrical subcontractors.                           The Department of Ecology has raised concerns with
     Sub Bid: Commencement of bid solicitation process                  disposal of soils with elevated pH levels resulting from
      for Bid Phase 06 - 9 bid packages mainly for exterior              non-concrete materials (including CDF, jet grout
      and interior finish scopes, with due date on Sept 9,               spoils, etc.) used during tunneling.
      2011.

 Cost Summary

           Present Financial Status                Amount
 U250 Contractor - Hoffman Construction

 Original Contract Value                            141,745,898
 Change Order Value                                     58,500
 Current Contract Value                             141,804,398
 Total Actual Cost (Amount Billed)                   13,182,633
 % of Authorized Billed to-date                             9.3%
 Physical Percent Complete:                                 8.6%
 Authorized Contingency                               7,087,295
                                                        $8,500
 Contingency Drawdown

 Contingency Index*                                       10.75

 *Physical % complete / % contingency drawn down                       Overview of the U250 construction site.

August 2011                                                                                                           Page 19 of 47
                                                                              Link Light Rail
                                                                University Link– Systemwide
  U820 Contract - LRV Storage and Yard Expansion
  U830 Contract - Track, Signal, Traction power and Communications Systems
  P821 Contract - Light Rail Vehicles
  C802 Contract - Signals Systems

  Key Activities
  Current Period                                                Next Period
  U820- LRV Storage and Yard Expansion                          U820- LRV Storage and Yard Expansion
   Continued processing closeout documentation.                Continue processing close out documentation.
  P821 – Light Rail Vehicles                                    P821 – Light Rail Vehicles
   Completed Final Assembly activities.                        Continue Dynamic Testing of LRV.
   Completed LRV deliveries to O&M Facility.                   Continue Final Acceptance activities.
   Continued Dynamic Testing of LRV.                          C802 - Signals System
   Commenced Final Acceptance activities.                      Review test results and other submittals.
  C802 - Signals System                                         U830 Systems
   Completed of Yard Expansion testing.                        GC/CM proposal due.
   Substantial Completion.
                                                                Other Systems
  U830 Systems                                                   Continue coordination of Agency-initiated system net-
   Received GC/CM proposals.                                      work standardization.
  Other Systems                                                 Closely Monitored Issues
   Continued coordination of Agency-initiated system
                                                                     None to report this period.
      network standardization.




  P821 Cost Summary                                                  C802 Cost Summary

           Present Financial Status                Amount                    Present Financial Status                     Amount

  P821 Manufacturer — Kinkisharyo Intl.*                             C802 Train Control —GETS Global
                                                                     Signaling, LLC*
  Original Contract Value (U-Link Option)         $94,576,095
                                                                     Original Contract Value (U-Link Option)               $1,996,269
  Change Order Value                               $4,001,689
                                                                     Change Order Value                                        $6,083
  Current Contract Value                          $98,577,784
                                                                     Current Contract Value                                $2,002,352
  Total Actual Cost (Incurred To Date)            $89,029,374
                                                                     Total Actual Cost (Incurred To Date)                 $1,809,694
  % of Authorized Billed to-date                         90%         % of Authorized Billed to-date                               90%
  Financial Percent Complete:                            92%         Physical Percent Complete:                                   95%
  Authorized Contingency                           $4,608,904        Authorized Contingency                                  $103,731
  Contingency Drawdown                             $4,001,689        Contingency Drawdown                                      $6,083
  Contingency Index                                      N/A         Contingency Index                                            N/A
  *Change Order to Initial Segment LRV Contract                      *Change Order to Initial Segment Train Control Contract.
                                                                       55% of contract costs are assigned to U-Link 45% North Link.
August 2011                                                                                                                 Page 20 of 47
Link Light Rail
North Link
Scope
The North Link project consists of a 4.3-mile extension
of the light rail from the University of Washington Sta-
tion to Northgate. North Link preliminary engineering
and the Final Supplemental Environmental Impact State-
ment (FSEIS) were completed in early 2006. The Sound
Transit Board selected the final North Link route and
stations on April 27, 2006 (as shown on the map to the
right). The FTA issued a Record of Decision for North
Link in June 2006.
The project includes twin-bored tunnels from the under-
ground University of Washington Station north to an
underground station near Brooklyn Avenue NE and NE
45th Street in the University Link District. From the
Brooklyn Station, the twin-bored tunnels continue north
to the underground Roosevelt Station near NE 65th Street
and 12th Avenue NE to the tunnel portal north of the
Lake City Way ramps in the I-5 right-of-way. The route
then transitions to an aerial guideway north of NE 92nd
Street and continues north where it terminates at an ele-
vated station at Northgate.




                                                                 Map of North Link route and stations.



Key Project Activities/Issues
    Held internal meeting to review elective measures for North Link Sustainability Checklist.

    Met with Seattle Fire Department regarding station and tunnel emergency ventilation.

    Met with Environmental staff and discussed Northgate area wetland permit issues.

    Reviewed Street Improvement Permit requirements and coordinated results with Contract Unit Managers.

    Solicited and received artist submittals for Brooklyn and Roosevelt stations. Selections are anticipated for late Sep-
     tember.

    Began preparations for Standard Radio façade deconstruction and storage.

    Began preparations and inventory for plant salvage event to take place later this fall/winter.

    A Task Order contract for Project Review Services, including Value Engineering, Constructability and Risk Analy-
     sis, has been executed and the first Value Engineering/Risk review will take place September 19-23.

    Systems Coordination: Completed draft Brooklyn and Roosevelt Signal room layouts and calculated power loads
     for Communications rooms; Systems design team began layout of TPSS equipment in Brooklyn and Roosevelt
     stations.




August 2011                                                                                                      Page 21 of 47
                                                                                             Link Light Rail
                                                                                                 North Link

  Project Cost Summary
  The following table (figures in millions) summarizes the cost information for the design and right-of-way elements of
  the North Link Program; construction cost estimates will be developed as the project design is advanced.

                                 Adopted     Commitment     Incurred to    Forecasts and Estimated Final      Budget vs.
                                 Budget        to Date         Date*          Trends       Cost (EFC)           EFC

 Administration                      $49.5           $4.7           $5.2             $44.8            $49.5           $0.0

 Preliminary Engineering             $15.3          $15.1          $15.1              $0.2            $15.3           $0.0

 Final Design                        $85.9          $74.2          $20.6             $11.8            $85.9           $0.0

 Construction Services                $0.3           $0.0           $0.0              $0.3             $0.3           $0.0

 3rd Party Agreements                $21.0           $1.7           $1.2             $19.3            $21.0           $0.0

 Construction                         $8.7           $7.6           $7.5              $1.1             $8.7           $0.0

 ROW                                $164.8          $33.1          $32.4           $131.7            $164.8           $0.0

                         Total      $345.5         $136.3          $82.0           $209.2            $345.5           $0.0


 Project Schedule
 The Final Design effort for the North Link project commenced on October 5, 2010. The focus over the past periods has
 been on the Early Work contract designs in the Roosevelt and Brooklyn station areas. Right-of-Way has been involved
 in planning the property needs and processes for supporting planned early construction in 2012. The current project
 schedule reflects the Revenue Service date of 2021.




 Right of Way
 The Brooklyn and Roosevelt stations require the acquisition of a range of property interests including fee takings for
 stations and staging areas and tunnel easements for the running tunnel. These acquisitions will result in owner and ten-
 ant, residential and commercial relocations. In addition, property acquisition for the Roosevelt Station location in-
 volved the advanced acquisition of three parcels that the ST Board approved in June and October 2006.




August 2011                                                                                                    Page 22 of 47
Link Light Rail
North Link
 Right of Way, continued

 There are a combined total of 25 owners and tenants that will be relocated for the Roosevelt Station and eight for the
 Brooklyn Station. The right-of-way program status as of this period is summarized below.

     Line Section         Total         Offers    Signed    Admin.      Posses-    Closings     Baseline      Relocations
                         Parcels        Made      Agree-    Settle-    sion and    to date     Relocations    Completed
                        Certified                 ments     ments         Use                   Required

  Brooklyn Station          18            5          0        0            0           0            8               6

 Roosevelt Station          23           15          1        0            0           13           25             19

 Tunnel Easements           1             1          0        0            0           0            0               0

        Total               41           21          1        0            0           13           33             19

Brooklyn Station – Offers were made to private property owners. Condemnation has been filed on two of the three pri-
vately-held parcels. An Order of Use & Necessity was entered on January 21, 2011. Trial is scheduled for August 2011.
Negotiations on the third parcel are still in progress. Relocation discussions with owners and tenants are in progress. An
offer was made to University of Washington for two parcels. Appraisals have been completed on the two remaining UW
parcels. On July 28, 2011 the Sound Transit Board authorized the acquisition of property rights from an additional elev-
en parcels adjacent to the Brooklyn Station footprint.
Roosevelt Station – Offers have been made on the 15 properties needed for the Roosevelt Station. Thirteen parcels have
been acquired. One parcel have been filed for condemnation. The owners have signed a delayed P&U (Possession and
Use) with possession no later than September 30, 2011. A settlement has been reached on the remaining fee parcel and
the owners have signed a Purchase and Sale Agreement with closing set for September 30, 2011. Nineteen relocations
have been completed. On July 28, 2011 the Sound Transit Board authorized the acquisition of property rights from an
additional eight parcels adjacent to the Roosevelt Station footprint.
North Link Tunnel Easements – In July2010, the Sound Transit Board authorized the acquisition of a tunnel easement
from the University of Washington. The offer for this easement was made in February 2011.


 Environmental                                                    Community Outreach
     Continued working with design team to prepare the              Conducted a bus tour of North Link station sites for
      SEPA addendum.                                                  the Citizen Oversight Panel members.
                                                                     Distributed monthly e-newsletter to approximately
                                                                      1,200 subscribers.
 Quality Assurance Activities
                                                                     Distributed construction alert to Brooklyn Station
 Activities                                                           area concerning restoration work.
  Performed QA Review of N112 90% Submittal.                        Met with Seattle Public Utilities to discuss Brooklyn
                                                                      Alley impacts during construction.
 Issues
  None to report.
                                                                     Introduced the Outreach Team as a point of contact
                                                                      for the Northgate Station project to the businesses
 Summary                                                              along 1st Avenue NE. Also distributed flyers around
                                 Aug                                  the area to alert them to the geotech borings along
        Description              2011            Notes
                                                                      the 1-5 noise wall.
                                          N112 90% Design
                                                                     Sent invitation to property owners for the September
  No. of Audits Planned             1                                 12 informational meeting about the N120 tunnel
                                          Audit
                                                                      easements (meeting invitation sent with formal writ-
  No. of Audits Completed           1                                 ten notice of the Sound Transit Board action on Sept.
  Reports in Progress               1                                 22)
  No. of Audits Postponed           0

August 2011                                                                                                      Page 23 of 47
                                                                                           Link Light Rail
                                                                                  North Link Final Design

 Final Design Overview
 Sound Transit has executed two key contracts with professional services consultants for the Final Design of North Link.
 Jacobs Associates (JA) is providing civil engineering and architectural final design services and was given NTP in Octo-
 ber 2010. LTK Engineering Services (LTK) is providing systems engineering final design services and was given NTP
 in January 2011.

 Final Design Activities
 Contract Package N112 - Demolition and Hazardous Material Contract Package N140 - Brooklyn Station Civil and Finishes.
 Mitigation, Brooklyn and Roosevelt Stations.               Continued 60% design effort.
  Completed and submitted 90% design package.              Continued coordination with TOD criteria and plan-
                                                             ning.
 Contract Package N114 - North Portal Utility Relocation,
 Demolition, Excavation and Retained Fill.                 Contract Package N150 - Roosevelt Station Civil and Finishes.
  Continued 60% design effort.                                         Continued 60% design effort.
                                                                        Continued coordination with TOD criteria and plan-
 Contract Package N120 - Station Box Excavation: Roosevelt
                                                                         ning.
 and Brooklyn Stations, Bored Tunnels Roosevelt Station to UW
 Station.                                                              Contract Package N160 - Northgate Station and Aerial Guide-
  Continued 90% design effort including civil, structural,            way Civil and Finishes.
   electrical, mechanical and alignment design effort.                  Continued 30% design effort.
 Contract Package N130 – North Portal Excavation and TBM                Continued alternative analysis, Green Factor Strategy
 Operation to Roosevelt:                                                 assessment, and discipline coordination.

  Continued design development and analysis of potential
   sites for the North Portal, with additional work done to
   evaluate constructability issues and interface with
   WSDOT and City of Seattle facilities.


  Schedule
  The table below summarizes the current civil Final Design submittal schedule for each contract package.

                                                               60%                           90%                     100% to ST
                  Work Packages
                                                      Plan             F/A*         Plan             F/A*         Plan        F/A*
  N112 Advanced Work at Roosevelt Station
                                                   3/18/2011         5/6/2011    8/16/2011         9/1/2011    11/21/2011   11/22/2011

  N114 North Portal Site Preparation
                                                   12/13/2011    12/13/2011      8/28/2012         9/13/2012   2/8/2013      2/9/2013

  N120 Bored Tunnels Roosevelt Sta. to UW Sta.     6/17/2011         7/1/2011    1/13/2012         1/14/2012   7/16/2012    7/14/2012
  N130 Bored Tunnels N. Portal to Roosevelt Sta.
                                                   5/4/2012          5/4/2012    12/18/2012        1/11/2013   7/5/2013      7/5/2013

  N140 Brooklyn Station Finishes
                                                   12/24/2011        2/3/2012    9/18/2012     10/12/2012      5/10/2013     6/4/2013

  N150 Roosevelt Station Finishes
                                                   4/13/2012         2/24/2012   1/28/2013         12/6/2012   10/23/2013   8/30/2013

  N160 Northgate Sta. Civil/Finishes/Guideway
                                                   6/27/2012         6/15/2012   4/17/2013         4/16/2013   11/26/2013   11/26/2013

  N180 Trackwork
                                                   8/23/2012         8/23/2012   5/22/2013         3/22/2013   8/26/2013     8/9/2013

 F/A* = Forecast/Actual




August 2011                                                                                                                 Page 24 of 47
Link Light Rail
North Link Final Design
Schedule Performance
Based on the current schedule, the planned values for both the early start and the late start dates through this period are
$18.8M and $11.8M, respectively. When compared to the Earned Value of $17.4M, this renders a Schedule Perfor-
mance Index (SPI) of 0.9 and 1.5, respectively. The schedule is tracking below the early plan curve but within an ac-
ceptable range. The project team is closely monitoring the progress.

                                                                                                  North Link Final Design Earned Value
        North Link Final Design Schedule Performance             $70.0
  2.0
  1.8                                                            $60.0

  1.6
                                                                 $50.0
  1.4
  1.2
                                                                 $40.0
  1.0
  0.8                                                            $30.0
  0.6
  0.4                                                            $20.0

  0.2
                                                                 $10.0
  0.0
                                                                  $0.0




                  SPI Planned   SPI Early   SPI Late                     Early Start Cum. Value     Late Start Cum. Value   Earned Value Cum. Value   Actual Cum. Value




 Cost Performance
                                                                                                   Previous                    Current                Cumulative
                                                                 Performance
 JA has submitted 11 progress payments to date in the                                               Period                     Period                  To Date
 total amount of $14.0M, which is approximately 23% of         Amount                               $1,626,033                 $1,689,979             $14,022,342
 the total contract amount. The percent complete report-
 ed at the end of this period is 28%, resulting in an earned   % Complete                                      3.8%                        2.8%                   28.3%
 value of $17.4M. The cumulative Cost Performance In-
 dex (CPI) is currently 1.3, which means the expenditures      Earned Value                         $2,533,655                 $1,752,580             $17,427,432
 are lower than the earned value. Based on the current         CPI                                                 1.3                        1.2
 CPI trend, final cost is projected to be within or under
 budget.

 Other Key Design Activities                                Completed CCTV inspections on sewer and storm sew-
                                                             ers around Roosevelt station.
 Design and Project Integration
                                                           Traffic Engineering
  Third party coordination continued with the City of Se-
                                                            Continued traffic engineering support for Maintenance
   attle departments; Fire/Life Safety work session.
                                                             of Traffic efforts on all active contracts.
  Finalized 3D modeling schedule for Brooklyn and Roo- Permitting
   sevelt stations 60% design package.
                                                            Submitted MUP application for Contracts N112 and
 Geotechnical Investigation & Surveying
                                                             N120 at Brooklyn station site.
  Phase 2 of the exploration program commenced; eight
                                                            Continued permit strategy development for wetland im-
   mud rotary and two sonic core borings were completed.
                                                             pacts.
  Laboratory testing and geotechnical analysis continued. Construction Cost Estimating & Scheduling
  Continued field surveys along I-5 and 1st Avenue, and
                                                            Commenced development of construction cost estimate
   around Brooklyn and Roosevelt stations.                   for Contract N112 90% design package.
  Prepared ROW plan and survey control plans for Con-
                                                            Started preparation of construction schedule and as-
   tract N112, N114 and N120.
                                                             sumptions memo to reflect N120 60% design package.
  Revised parcel maps around Brooklyn and Roosevelt       Quality Assurance
   stations.                                                Carried out QA Audit on Contract N112 90% design
  Completed pavement restoration of potholing carried out   package.
   at Brooklyn and Roosevelt stations.


August 2011                                                                                                                                             Page 25 of 47
                                                                                                Link Light Rail
                       Initial Segment/Airport Link (Amended FFGA Project)

 Project Summary
 Scope:            The amended FFGA Initial Segment/Airport Link project is a 15.6-mile double-tracked line with 13 sta-
                   tions connecting downtown Seattle with Sea-Tac International Airport, with a fleet of 35 low-floor articu-
                   lated 90 to 95-foot cars, and an Operations and Maintenance Facility .
 Budget:           $2.706 billion (capital subtotal of $2.339 billion)
 Schedule:         Interim completion was July 2009 and final completion was December 2009.

 Project Cost Summary
 The “Estimated Final Cost” (EFC) represents the current estimate of final cost for the Initial Segment/Airport Link
 project. Additional cost and contract details are provided in the subsequent sections of this report.
                                                                                                                Adopted
                                               Lifetime      Commitment Incurred to Est. Final Cost
               Project Element                                                                                  Budget
                                               Budget          to Date     Date          (EFC)
                                                                                                                vs. EFC
 Administration                                    $196.2          $194.6         $194.6             $196.8           $(0.6)

 Preliminary Engineering                            $37.0           $36.9           $36.9             $36.9            $0.0

 Final Design                                      $160.1          $159.7         $159.5             $159.9            $0.2

 Construction Services                             $120.5          $120.9         $117.2             $121.4           $(0.9)

 3rd Party Agreements                               $62.8           $63.1           $62.4             $62.8           $(0.0)

 Construction                                     $1,429.2       $1,420.7        $1,407.0           $1,430.4          $(1.2)

 Vehicles                                          $146.4          $146.3         $144.8             $146.4            $0.0

 Right of Way                                      $219.2          $216.4         $217.3             $219.0            $0.2

 Capital Total                                   $2,371.3         $2,359          $2,340             $2,374            $(2)

 Project Reserve                                    $96.1            $0.0            $0.0               $0.0          $96.1

 Financing                                         $201.8          $201.8         $176.0             $176.0           $25.8

 Transit Art                                        $10.7            $8.1            $8.0               $8.1           $2.6

 DSTT Debt Service                                  $26.1           $23.7           $23.7             $23.7            $2.4

 Project Total                                   $2,706.0        $2,592.2       $2,547.5           $2,581.4         $124.6
 Table figures in millions.

 Project Schedule Summary
 Schedule for the amended Initial Segment/Airport Link project is summarized below.




                                                                                            REVENUE SERVICE
                                                                                            ACHIEVED 12/19/09



August 2011                                                                                                       Page 26 of 47
Link Light Rail
Initial Segment
 Scope
 Limits:         13.9-mile double-track light rail transit (LRT) system between downtown Seattle and South 154th Street in
                 Tukwila
 Stations:       12 stations (including retrofit of four existing Downtown Seattle Transit Tunnel stations)
 Budget:         $2.437 billion (capital subtotal of $2.070 billion)
 Schedule: Project completion was July 2009

 Initial Segment Close - out Activities
 The Initial Segment achieved Revenue Service as scheduled on July 18, 2009.
 Final resolution of all outstanding claims and non-conformance issues has been addressed, and final contract comple-
 tion has been reached on the Rainier Valley project. Follow-on work items, particularly in the Beacon Hill/Mt. Baker
 Station area and with certain Systems elements, continued this reporting period.
 Remaining work to achieve Full Certificate of Occupancy at all stations will be completed without affecting service.

 Project Cost Summary
 Project cost information is summarized in the table below. The “Baseline Budget” represents the budget established in
 the FFGA executed in 2003. “Adopted Budget” figures, except DSTT Debt Service, reflect the 2011 capital budget
 adopted by the Sound Transit Board. The “Estimated Final Cost” (EFC) represents the current estimate of the final
 cost for each project element.
 The current EFC is approximately $2.3B, which is approximately $117M less than the baseline budget. The EFC re-
 ported this period is the same as last month. (Table figures in millions.)

                                                                           Commit-                                                     Adopted
                                    Baseline            Adopted                              Incurred to        Est. Final Cost
        Project Element                                                    ment to                                                     Budget
                                    Budget              Budget                                  Date                 (EFC)
                                                                           Date (1)                                                    vs. EFC
  Administration                          $226.8               $184.3            $184.8               $184.8              $186.8             ($2.5)
  Preliminary Engineering                  $35.0                $33.3             $33.3                $33.3               $33.3               $0.0

  Final Design                            $123.0               $144.1            $143.9               $143.8              $144.1               $0.1

  Construction Services                    $82.5               $104.9            $105.5               $102.4              $106.0             ($1.1)
   rd
  3 Party Agreements                       $58.8                $61.4             $61.7                $61.1               $61.5             ($0.1)
  Construction                          $1,172.6             $1,235.6          $1,233.7             $1,222.4            $1,242.1             ($6.5)

  Vehicles                                $138.3               $131.8            $131.8               $130.9              $131.8               $0.0
  Right of Way                            $233.0               $206.7            $204.4               $205.2              $206.5               $0.2

  Capital Total                        $2,070.0             $2,102.2          $2,099.0             $2,083.9            $2,112.0             ($9.8)

  Project Reserve                         $128.3                $96.1               $0.0                 $0.0               $0.0              $96.1

  Financing(2)                            $201.8               $201.8            $201.8               $176.0              $176.0             $25.8

  Transit Art                              $10.7                $10.7               $8.1                 $8.0               $8.1               $2.6

  DSTT Debt Service                        $26.1                $26.1             $23.7                $23.7               $23.7               $2.4

  Project Total(3)                     $2,436.9             $2,436.9          $2,332.6             $2,291.7            $2,319.8             $117.1

 (1) Includes encumbrances beyond actual contract commitments.
 (2) Financing costs are based on an allocation of subarea bonding and related capitalized interest with paid to date and forecasts updated annually
     during the first quarter of each year.
 (3) Totals may not equal column sums due to rounding of line entries.


August 2011                                                                                                                            Page 27 of 47
                                                                                                    Link Light Rail
                                                                                                       Airport Link

 Scope
 The Airport Link project included the environmental review, design, right-of-way acquisition, and construction of the
 1.7-mile light rail extension from the Tukwila/International Boulevard Station at South 154th Street to the SeaTac/
 Airport Station at South 176th Street. Revenue service began December 19, 2009.




 Airport Link Close-out Activities
  Civil and Systems close-out work continues.




 Project Cost Summary
 The following table summarizes project cost information relative to the 2011 Adopted Budget (figures in millions). The
 EFC represents the current estimate of the final cost for each line item.
 The current estimated final cost (EFC) for the capital project is $261.6M, which is approximately $7.5M less than the
 current adopted budget. The EFC reported this month is the same as last month.


                                                      Adopted            Commitment   Incurred to    Est. Final   Adopted
              Project Element                         Budget               to Date       Date       Cost (EFC)    Budget
                                                                                                                  vs. EFC
 Administration                                               $11.9            $9.8          $9.8         $10.0         $1.9
 Preliminary Engineering                                       $3.7            $3.7          $3.7          $3.7         $0.0
 Final Design                                                 $15.9           $15.8         $15.7         $15.8         $0.1
 Construction Services                                        $15.5           $15.4         $14.8         $15.4         $0.2
 Third-Party Agreements                                        $1.4            $1.5          $1.3          $1.4         $0.0
 Construction                                               $193.6           $187.0       $184.6        $188.3          $5.3

 Vehicles                                                     $14.6           $14.5         $13.9         $14.6         $0.0
 Right of Way                                                 $12.5           $12.0         $12.0         $12.5         $0.0
                   (1)
 Project Total                                             $269.1            $259.6       $255.9        $261.6          $7.5

 Table figures in millions.
 (1)
     Totals may not equal column sums due to rounding of line entries.




August 2011                                                                                                       Page 28 of 47
Link Light Rail
East Link




 Scope
 East Link is a voter-approved project to expand light rail to East King County via I-90 from Downtown Seattle to
 Downtown Bellevue and the Overlake area of Redmond, with stations serving Rainier Avenue/I-90, Mercer Island,
 South Bellevue, Downtown Bellevue, Overlake Hospital, the Bel-Red corridor, Overlake Village and the Overlake
 Transit Center. The ST2 Plan provides for environmental review for a future expansion between the Overlake Transit
 Center and Downtown Redmond. On July 28, 2011, the Sound Transit Board selected the project route, profiles, and
 station locations, including the tunnel route in downtown Bellevue, contingent upon the City of Bellevue entering into
 a term sheet and a binding umbrella memorandum of understanding with Sound Transit to provide a financial contri-
 bution to close the affordability gap of constructing the downtown tunnel. Revenue Service to the Overlake Transit
 Center forecast for early 2023.

Key Project Activities/Issues
    Signed and executed the tunnel funding term sheet with City of Bellevue.
    I-90 Track Bridge prototype design team evaluated the two concepts selected for further design.
    Prepared a concept design and cost estimate for City of Bellevue requested design changes on 112th Avenue NE.
    Received further information from the property owner on the cost private delivery of the retained cut across the
     Spring District site.
    Drafted a concurrence letter with City of Redmond regarding the project scope at the conclusion of preliminary
     engineering.
    Consulted with the Department of Archaeology and Historic Preservation (DAHP), Federal Transit Administration
     (FTA), and the City of Bellevue to refine the draft Memorandum of Agreement and transmitted proposed revisions
     to DAHP and FTA for review and concurrence.
    Scope of work and schedule drafted for SEPA Addendum and NEPA Reevaluation that will address design refine-
     ments requested by the City of Bellevue along 112th Ave.

August 2011                                                                                                    Page 29 of 47
                                                                                               Link Light Rail
                                                                                                    East Link

  Project Cost Summary
  The following table summarizes the cost information for the East Link Program. Lifetime Budget reflects the project
  budget adopted by Sound Transit Board, which includes budget to complete Final Design. Final Design is anticipated
  to commence in early 2012. (Figures in millions.)
                                                 Commit-                       Forecasts       Estimated
                                    Lifetime                  Incurred to                                      Budget vs.
                                                 ment to                          and          Final Cost
                                    Budget                       Date                                            EFC
                                                  Date                          Trends           (EFC)
   Administration                        $63.8         $7.7            $8.3            $56.0           $63.8           $0.0
   Preliminary Engineering               $64.7        $53.6           $48.1            $11.1           $64.7           $0.0
   Final Design                         $169.4         $0.0            $0.0         $169.4           $169.4            $0.0
   3rd Party Agreements                  $25.6         $1.1            $0.9            $24.5           $25.6           $0.0
   Right-of-way                          $41.2         $0.7            $0.6            $40.4           $41.2           $0.0
                           Total        $364.5        $63.1           $57.9         $301.4           $364.6            $0.0


 Project Schedule
 Below is the schedule for the East Link Program which reflects delay in the preliminary engineering phase due to study
 of additional alternatives in the City of Bellevue. On July 28, 2011, Sound Transit Board selected the project route, pro-
 files, and station locations, including the tunnel route in downtown Bellevue. Revenue Service to the Overlake Transit
 Center forecast for early 2023.




 Sound Transit Board Actions                                    Quality Assurance Activities
  Motion                                                        Activities
  Number                       Description           Date
                                                                    None to report.
                  None to report.




August 2011                                                                                                     Page 30 of 47
Link Light Rail
East Link

Community Outreach

    Responded to emails and inquiries after the announcement of the ST Board on the East Link decision.
    Began coordination efforts with City of Bellevue pertaining to the design options for the 112th Avenue SE portion
     of the Project.
    Coordinated comment letters for inclusion with the Record of Decision.
    Updated the East Link website to reflect the ST Board decision regarding the final project to be built.
    Attended tour for Transportation aide to US Congressman Jay Inslee.



 Progress and Earned Value Curves
 As of July* 2011, the Earned Progress of the
 contract was approximately 92%. Compared
 to the actual costs through the same period,
 it resulted in the cumulative Cost Perfor-
 mance Index (CPI) of 1.0. Much of the con-
 tract contingency has been drawn down to
 address scope and schedule changes of the
 preferred alternative and the longer FEIS
 process.

 *Note: The Earned Value lags one month of reporting
 period because the actual invoice from the consultant is
 not received until the third week of the month following
 month end – later than the report cut off date.




Closely Monitored Issues                                        Cost Summary
     The updated agency financial forecast indicates lower             Present Financial Status               Amount
      revenue collection in the East King County.
                                                                East Link Environ. & PE– CH2MHill
     Differences with the City of Bellevue Council regard-
      ing the alignment in south Bellevue present budget        Original Contract Value                        $28,257,220
      and program schedule risks.                               Change Order Value                              $5,183,908
                                                                Current Contract Value                         $33,441,128
                                                                Pending Change                                   $186,070
                                                                Contract Value incld. Pending Change           $33,627,198
                                                                Total Actual Cost (not including accrual)      $30,365,959
                                                                % of Authorized Billed to-date                        91%
                                                                Physical Percent Complete:                            92%

                                                                Authorized Contingency                          $5,934,016

                                                                Contingency Drawdown (including Pending)        $5,369,978
                                                                Contingency Index                                     0.99


August 2011                                                                                                       Page 31 of 47
                                                                                            Link Light Rail
                                                                                                South Link

 Scope
 The South Link - Airport to S. 200th project is a 1.6-mile
 extension of the light rail from the SeaTac/Airport Sta-
 tion to South 200th Street. After leaving SeaTac /
 Airport Station, the route continues in an aerial configu-
 ration along the west side of International Blvd., turns
 southwest to cross South 188th Street, and continues in
 an aerial configuration along the east side of 28th Ave-
 nue South to an elevated station at South 200th Street
 sized to accommodate 4-car trains. A bus transfer facility,
 kiss and ride parking, and a 700 space structured park
 and ride facility will be located at the South 200th Street
 station. Up to 400 additional spaces may be leased for
 surface parking while the South 200th Street Station is an
 interim southern terminus of the Link system.

 Preliminary engineering (PE) and the environmental im-
 pact statement (EIS) is complete and a Record of Deci-
 sion (ROD) has been issued for this segment. A SEPA
 addendum and NEPA re-evaluation have been issued to
 document recent design refinements. The project will be
 delivered through a design/build approach to accelerate
 project completion by 2016.


                                                                   Map of South Link.




 Key Project Activities/Issues
     Submitted Conditional Use Permit application to the City of SeaTac.

     Prepared appraisals for property acquisition needed for the project.

     Continued preparation of a design-build procurement package.

     Received comments from interested design-build teams on the information sheet distributed for industry review of
      the scope and general terms.

     Continued developing draft term sheets with Port of Seattle and City of SeaTac.

     Continued design coordination of S 200th Station area with major property owner in the vicinity of the station.

     Continued working with potentially impacted utilities in the project corridor to develop agreements for relocation
      and protection during the design-build process.




August 2011                                                                                                    Page 32 of 47
Link Light Rail
South Link

Project Schedule
The South Link anticipated service launch is 2016. The project schedule is presented below.




Project Cost Summary
The following table (figures in millions) summarizes the cost information for the South Link project. The Baseline
Budget for the project including the remaining design and projected right-of-way and construction cost was approved by
the Sound Transit board in July 2011.

                                                                                              Estimated
                                  Adopted      Commitment      Incurred      Forecasts        Final Cost   Budget Ver-
              Phase               Budget         to Date        to Date     and Trends          (EFC)        sus EFC
  Administration                      $16.10          $1.30        $1.60          $14.80          $16.10          $0.00

  Preliminary Engineering              $5.90          $5.70        $5.70           $0.20           $5.90          $0.00
  Final Design                        $20.00          $0.40        $0.40          $19.60          $20.00          $0.00
   rd
  3 Party Agreements                   $6.90          $0.90        $0.60           $6.00           $6.90          $0.00
  Construction Services               $15.10          $0.00        $0.00          $15.10          $15.10          $0.00

  Construction                       $275.70          $0.00        $0.00         $275.70         $275.70          $0.00
  Right-of-Way                        $43.50         $10.30        $8.90          $33.20          $43.50          $0.00
                          Total     $383.20          $18.60       $17.20        $364.60          $383.20          $0.00




August 2011                                                                                                  Page 33 of 47
                                                                                                          Link Light Rail
                                                                                                              South Link

  Right-of-Way
  The Airport South Link – Airport to 200th St. Segment involves the acquisition of a range of property interests, including
  owner and tenant residential and commercial relocations. Property interests include compensable (e.g., easements, fee

                                                                                                                           Reloca-
                                                              Total Parcels           Parcels in         Acquisitions
                Line Section                                                                                                tions
                                                               Certified            Condemnation           to date
                                                                                                                           to date
   South Link                                                             54                       0                 3               0


  The South Link Project involved the advance acquisition of three parcels that the Board approved in April 2006 and
  June 2007; the final decree was entered in July 2009. These parcels were acquired through the Regional Fund Contin-
  gency. Sound Transit’s protective acquisition of these properties will prevent the imminent development of the parcels
  needed for the proposed South Link line. On July 28, 2011 the Sound Transit Board authorized the acquisition of prop-
  erty rights from an additional fifty-one (51) parcels along the route.




 Sound Transit Board Actions                                                  Quality Assurance Activities
                                                                               None to report this period.
  Motion                    Description                          Date
  Number
              To acquire, dispose, or lease certain real                      Environmental
              property by negotiated purchase, by con-
                                                                               None to report this period.
              demnation (including settl4ement of con-
              demnation litigation), or entering into ad-
  R2011-11    ministrative settlements, and to pay eligible     Aug 25
              relocation and re-establishment benefits to
              affected owners and tenants as necessary
                                                                              Community Outreach
              for the South Link-Airport to South 200th                        Invited the South 200th area stakeholders to a project
              Street Project.                                                   stakeholder/Tiger Grant meeting.
                                                                               Contributed to a presentation delivered to the SeaTac
                                                                                City Council about the Project.
                                                                               Distributed Agency and South 200th project material
                                                                                at the SeaTac Back to School Resource Fair.




August 2011                                                                                                                Page 34 of 47
Link Light Rail
Staffing Report

 Staffing
 Recruiting Activity
 During this reporting period (July 2011) recruiting continued for the following positions to support capital project de-
 sign, engineering and construction:

                    Position                               Project Assignment                        Planned Hire Date
   Principal Construction Manager      University Link                                            2010 Attrition
   Project Manager                     Unspecified Capital Project Support                        2010 Attrition
   Civil Engineer – Track work         University Link                                            2010 Attrition
   Systems Engineer                    University, South and East Link                            2010 Attrition
   Structural Engineer                 North Link                                                 April 2011
   Sr. Systems Engineer                Unspecified Capital Project Support                        May 2011
   Construction Manager                University Link                                            June 2011
   Construction Manager                North Link                                                 June 2011
   Sr. Civil Engineer                  South Link and East Link                                   June 2011
   Structural Engineer                 University, South and East Link                            June 2011
   Executive Project Director          North Link                                                 July 2011
   Project Director                    South Link                                                 July 2011
   Sr. Structural Engineer             East Link                                                  July 2011
   Civil Engineer                      Unspecified Capital Project Support                        July 2011
   Sr. Civil Engineer                  North Link                                                 July 2011
   Chief of Staff                      Capital Project Support                                    August 2011
   Executive Project Director          East Link                                                  September 2011
   Outreach Assistant                  University, East, South and North Link                     September 2011
   Architect                           East Link                                                  October 2011
   Construction Manager                East Link                                                  December 2011
   Construction Manager                Unspecified Capital Project Support                        2011 Attrition
   Structural Engineer                 Unspecified Capital Project Support                        2011 Attrition
   Electrical Engineer                 University Link                                            2011 Attrition
   Project Control Specialist          Unspecified Capital Project Support                        2011 Attrition



 Project Staffing
 A total of 320.5 consultant and internal staff full time equivalents (FTE) participated in the major Link design and con-
 struction projects in July versus a planned staffing level of 473.3 FTE. Internal staffing levels totaled 101.7 FTE versus
 a planned level of 143.9 FTE; consultant staffing levels totaled 218.8 FTE versus a planned staffing level of 329.4 FTE.
 As reported for the previous reporting period (June 2011), plan assumptions included significant increases in internal
 and consultant staffing levels with the transition of the East Link project from preliminary engineering to final design
 and the transition of the South Link - Airport to S. 200th project from refined preliminary engineering to design/build
 procurement development. The transition has been delayed and staffing for these projects subsequently held at levels
 required to meet revised project milestones. Final design for East Link is anticipated to begin in late 2011 following
 completion of the Record of Decision for the project; the design/build procurement strategy for South Link – Airport to
 S. 200th was approved by the Board of Directors in July 2011 increases in staffing for South Link are anticipated in the
 months ahead.



August 2011                                                                                                        Page 35 of 47
                                                                                             Link Light Rail
                                                                                            Staffing Report

 Project Staffing, continued
 Staffing and consultant utilization and variances to planned staffing levels for the major on-going Link design, engineer-
 ing and construction projects for the current reporting period follow. Utilization and variance reports for July 2011 are
 provided for the following Link projects:

                        University Link
                        North Link – University of Washington (UW) to Northgate
                        South Link – Airport to South 200th
                        East Link
 Staffing and consultant utilization is not reported for on-going planning projects for the North Corridor (North Corridor
 Transit Project) and the South Corridor (beyond S. 200th).
 University Link Staffing
 Total Internal and External Staffing – University Link

 During this reporting period 123.5 consultant and internal staff FTE were committed to the University Link project.
 This level of staffing is 4% (4.8 FTE) below the staffing level for the previous reporting period and is 7.4% (9.8 FTE)
 below planned staffing levels. Cumulatively project staffing levels are trending slightly above plan.




                                      Labor Hours to Date                                    Current Period
                                                                                               July 2011

                           Total        Total         Total      Percent      Period      Period       Period      Percent
                          Planned       Actual      Variance    Expended     Planned      Actual      Variance    Expended

   Nos. of Hours         973,604.8    988,255.0     14,650.1     101.5%      19,760.0    21,320.1     1,560.1      107.9%

   Monthly Average       16,501.8     16,750.1       248.3

   Monthly FTE               103.14       104.69      1.6                     123.5        133.3        9.8




August 2011                                                                                                      Page 36 of 47
Link Light Rail
Staffing Report

University Link Staffing, continued
Internal Resource Commitments to University Link


The equivalent of 42.1 full-time internal staff was committed to the University Link project during this reporting period.
This is 1% (4.8 FTE) below staffing for the previous reporting period and 12.5% (6 FTE) below planned staffing levels.

Cumulatively since August 2006, internal staffing levels are trending 7.8% (2.7 FTE) below the previously established
and revised baselines. This is partially attributable to the lag in filling internal staff level positions; of the approved posi-
tions planned for internal hire through July 2011 within the capital departments, 4.85 FTE that are to be assigned to
University Link remain vacant. Recruitment is on-going to fill these and other positions in the interim, delays in other
major capital programs including East Link have afforded the opportunity for staff assigned to other projects to partici-
pate in the University Link program.




                                       Labor Hours to Date                                       Current Period
                                                                                                   July 2011

                        Total           Total          Total        Percent       Period      Period       Period      Percent
                       Planned          Actual        Variance     Expended      Planned      Actual      Variance    Expended

 Nos. of Hours        323,135.8       297,986.4      -25,149.4       92.2%       7,696.0      6,732.5      -963.5       87.5%
 Monthly Average       5,476.9         5,050.6        -426.3
 Monthly FTE             34.2           31.6            -2.7                      48.1         42.1         -6.0




August 2011                                                                                                           Page 37 of 47
                                                                                          Link Light Rail
                                                                                         Staffing Report
 University Link Staffing, continued
 Consultant Resource Commitments to University Link

  During this reporting period 91.2 consultant FTE were assigned to University Link; this is approximately 12% (9.8
  FTE) above consultant staffing levels for the previous reporting period and 20.9% (15.8 FTE) above the planned con-
  sultant staffing level of 75.4 FTE. Cumulatively, consultant staffing levels are trending 6.1% above plan.




                                     Labor Hours to Date                                  Current Period
                                                                                            July 2011

                         Total         Total        Total      Percent      Period     Period       Period      Percent
                        Planned        Actual      Variance   Expended     Planned     Actual      Variance    Expended

   Nos. of Hours       650,469.0     690,268.6    39,799.6     106.1%     12,064.0    14,587.6     2,523.6      120.9%
   Monthly Average     11,024.9      11,699.5       674.6
   Monthly FTE           68.9          73.1          4.2                    75.4        91.2         15.8




August 2011                                                                                                   Page 38 of 47
Link Light Rail
Staffing Report
University Link Staffing, continued

Consultant Resource Commitments to University Link, continued

Year-to-date (January to July 2011) consultant utilization on University Link by consultant discipline is illustrated be-
low. As expected, in July, the highest consultant utilization (65.9 FTE) was for Construction Management, significant-
ly greater (27.4% 14.15 FTE) than construction management staffing levels for the previous reporting period. There
were 22.4 consultant FTE providing civil and architecture support to University Link in July a decrease of 3.7 FTE
(14%) over the previous reporting period; 2.9 consultant FTE were providing Systems support.




The following variances were observed between planned and actual civil/architecture and environmental, systems and
construction management consulting staff utilization.

    Civil/architecture consultant utilization during July exceeded plan by 109% (11.7 FTE); additional civil engineer-
     ing support continues to address project changes resulting from the Montlake Triangle Project (MTP). As reported
     in previous periods’ civil consultant utilization will likely trend higher than planned as the MTP design is advanced.

    Systems consultant utilization during July was 67% (5.9 FTE) below the 8.6 Systems consultant FTE planned to
     support University Link; staffing levels are presently adequate to meet systems design requirements.

    Construction management (CM) consultant utilization increased 28.7% (14.8 FTE) from the previous reporting
     period and was 18% (10.2 FTE) above the 55.7 FTE planned.




August 2011                                                                                                      Page 39 of 47
                                                                                           Link Light Rail
                                                                                          Staffing Report
 North Link - UW to Northgate Staffing
 During this reporting period 110 internal and consultant staff was assigned to the North Link - UW to Northgate pro-
 ject, approximately 18% above the staffing level for the previous reporting period and 20% below the planned staffing
 level of 137.5 FTE.

  Internal Resource Commitments to North Link - UW to Northgate

 In July, 24.2 internal FTE were assigned to the North Link – UW to Northgate project, a 21% (6.3 FTE) decrease from
 the previous period and 32% (11.3 FTE) below the baseline staffing plan. Currently recruitment is underway for 4.25
 FTE that are to be assigned to the North Link project.

 Cumulatively, since January 2011, internal staffing levels are trending an average of 26% (8.2 FTE) below plan.




                                         Labor Hours                                       Current Period
                                      Jan 2011– July 2011                                    July 2011

                         Total          Total        Total      Percent      Period      Period      Period         Percent
                        Planned         Actual      Variance   Expended     Planned      Actual     Variance       Expended

  Nos. of Hours         34,896.0      25,748.8      -9,147.2     74%        5,680.0     3,869.5     -1,810.5         68%
  Monthly Average       4,985.1        3,678.4      -1,306.7
  Monthly FTE             31.2          23.0          -8.2                    35.5        24.2        -11.3


 Sound Transit awarded the Final Design contract for North Link in the fourth quarter of 2010. Sound Transit is increas-
 ing staffing levels to meet design engineering deliverable and schedule milestones.




August 2011                                                                                                    Page 40 of 47
Link Light Rail
Staffing Report
North Link - UW to Northgate Staffing, continued

Consultant Resource Commitments to North Link – University of Washington to Northgate

During July, 85.9 consultant FTE were assigned to North Link, approximately 37% (23 FTE) above the previous re-
porting period and 26% (16.1 FTE) below the planned consultant staffing level of 102 FTE.




                                           Labor Hours                                       Current Period
                                        Jan 2011– July 2011                                    July 2011

                                         Total         Total                                                       Percent
                          Total                                    Percent      Period      Period      Period
                                         Actual                                                                    Expend-
                         Planned                      Variance    Expended     Planned      Actual     Variance
                                                                                                                     ed

    Nos. of Hours         95,200.0      81,699.8     -13500.20     85.8%       16,320.0    13,738.6    -2581.40     84.2%

    Monthly Average       13,600.0      11,671.4     -1928.60

    Monthly FTE               85.0           72.9      -12.05                    102.0      85.9        -16.13




Cumulatively, since January 2011, consultant staffing levels are trending 14.2% (12.1 FTE) below plan. The following
variances were observed between planned and actual civil/architecture and systems consulting staff utilization.

      Civil/architecture consultant utilization for July was 83 FTE or 87% of planned staffing levels. Cumulatively civil/
       architect consultant utilization is trending 10% below plan.

      Systems consultant utilization is trending 54% (4 FTE) below the seven Systems consultant FTE planned to support
       North Link; at this stage of the design, staffing levels are adequate to meet systems design requirements. Systems
       consultant staffing levels are projected to increase as the design is advanced.




August 2011                                                                                                       Page 41 of 47
                                                                                             Link Light Rail
                                                                                            Staffing Report

 East Link Staffing
 During this reporting period 52.5 internal and consultant staff was assigned to the East Link project, approximately 17%
 below the previous reporting period and 62% below planned staffing level of 138.5 FTE.

 Internal Resource Commitments - East Link

 During July, internal staffing levels for East Link (23.2 FTE) were11% (2.9 FTE) below staffing levels reported for June
 and 45% (19.2 FTE) less than planned. Cumulatively, since January 2011 internal staffing levels are 34% (12.4 FTE)
 below plan. As previously reported, internal staffing level variances to plan are attributable to the status of preliminary
 design activities, which have been extended to address third party concerns and alternate alignments. Internal staffing
 levels will continue to trend below plan until preliminary design deliverables have been completed and final design initi-
 ated in late 2011.




                                         Labor Hours                                         Current Period
                                      Jan 2011– July 2011                                      July 2011

                         Total          Total         Total      Percent      Period      Period       Period      Percent
                        Planned         Actual      Variance    Expended     Planned      Actual      Variance    Expended

   Nos. of Hours       41,248.0       27,305.5     -13,942.5      66%        6,800.0      3,707.6     -3,092.5      55%

   Monthly Average      5,892.6        3,900.8      -1,991.8
   Monthly FTE            36.8          24.4         -12.4                     42.5        23.2        -19.3




August 2011                                                                                                      Page 42 of 47
Link Light Rail
Staffing Report

East Link Staffing, continued

Consultant Resource Commitments – East Link

During July, 29.3 consultant FTE were assigned to the East Link project, significantly below the planned staffing level
of 96 FTE. When the staffing plan was developed it was assumed that the preliminary engineering consultant would
transition the project to the final design consultant in June 2011 with both consultant teams working concurrently on
the transition. This transition has been delayed until later in 2011following the Record of Decision for the project.




                                      Labor Hours                                         Current Period
                                   Jan 2011– July 2011                                      July 2011

                      Total         Total         Total       Percent      Period      Period       Period      Percent
                     Planned        Actual       Variance    Expended     Planned      Actual      Variance    Expended

 Nos. of Hours        78,560.0      57,937.0   -20,623.00     73.7%       15,360.0      4,687.0   -10,673.00     30.5%

 Monthly Average      11,222.9       8,276.7    -2,946.14
 Monthly FTE           70.1          51.7         -18.4                     96.0        29.3        -66.71




August 2011                                                                                                    Page 43 of 47
                                                                                             Link Light Rail
                                                                                            Staffing Report

 South Link - Airport to S. 200th Staffing
 During this reporting period 23.5 internal and consultant staff was assigned to the South Link – Airport to S. 200th pro-
 ject, approximately 67% below the planned staffing level of 71.6 FTE.


 Internal Resource Commitments South Link – Airport to S.200th

 During July, 12.2 FTE were assigned to the South Link- Airport to S. 200th project. This is approximately 18% (2.7
 FTE) below the previous reporting period and 5.6 FTE (31.4%) below the planned baseline for the reporting period.
 Staffing levels are anticipated to trend closer to plan following the July 2011 Board decision to advance the project
 through a design/build process.




                                          Labor Hours                                        Current Period
                                         Jan– July 2011                                        July 2011

                                        Total         Total       Percent      Period      Period      Period      Percent
                     Total Planned      Actual       Variance    Expended     Planned      Actual     Variance    Expended

   Nos. of Hours        17,611.2      12,296.4      -5,314.8       70%        2,849.6     1,951.3      -898.3       68%

   Monthly Average      2,515.9        1,756.6       -759.3
   Monthly FTE            15.7          11.0          -4.7                     17.8        12.2         -5.6


  Cumulatively, since January 2011, internal staffing levels are trending 30% (4.7 FTE) below plan. With the July 2011
  decision by the Board to advance the project staffing levels are anticipated to trend closer to plan.




August 2011                                                                                                      Page 44 of 47
Link Light Rail
Staffing Report


South Link - Airport to S. 200th Staffing, continued

Consultant Resource Commitments to South Link Airport to S. 200th

During July, 12.4 consultant FTE were assigned to South Link, approximately 78% (43.6 FTE) below plan. Cumula-
tively consultant staffing levels are trending 44% below plan. When the plan was developed it was anticipated that the
design/build procurement process would be initiated in March 2011 and be significantly underway by this reporting
period. Board approval for delivery of this project through a design/build procurement strategy took place in late July.
Consultant staffing levels are anticipated to trend closer to plan as the design/build program for this project is advanced.




                                         Labor Hours                                         Current Period
                                        Jan– July 2011                                         July 2011

                        Total         Total          Total       Percent      Period       Period      Period       Percent
                       Planned        Actual       Variance     Expended     Planned       Actual     Variance     Expended

  Nos. of Hours      34,080.00      19,146.00     -14,934.00     56.18%      8,960.00    1,987.00     -6,973.00      22%

  Monthly Average     4,868.57      2,735.14      -2,133.43
  Monthly FTE           30.43         17.09         -13.33                    56.00        12.42       -43.58




August 2011                                                                                                       Page 45 of 47
                                                                  Link Light Rail
                                                                       Acronyms

  ACRONYMS
  AA          Alternative Analysis
  BCE         Baseline Cost Estimate
  BCWS        Budgeted Cost of Work
  BNSF        Burlington Northern Santa Fe Railway
  CCB         Change Control Board
  CDF         Controlled Density Fill
  CHS         Capitol Hill Station
  CM          Construction Management
  CO          Change Order
  CPI         Cost Performance Index
  CPM         Critical Path Method
  DAHP        Department of Archaeology & History Preservation
  DART        Days Away, Restricted or Modified
  DPD         Seattle Department of Planning and Development
  DSDC        Design Support During Construction
  DSTT        Downtown Seattle Transit Tunnel
  EFC         Estimated Final Cost
  FD          Final Design
  FSEIS       Final Supplemental Environmental Impact Statement
  FFGA        Full Funding Grant Agreement
  FTA         Federal Transit Administration
  FTE         Full Time Employee
  GC/CM       General Contractor /Construction Management
  IWP         Industrial Waste Permit
  JA          Jacobs Associate
  KC          King County
  KCM         King County Metro
  LTK         LTK Engineering Services
  LRV         Light Rail Vehicle
  MDA         Major Discharge Authorization
  MLK         Martin Luther King, Jr. Way
  MOS         Minimum Operable Segment
  MTP         Montlake Triangle Project
  NEPA        National Environmental Policy Act

August 2011                                                                Page 46 of 47
Link Light Rail
Acronyms

 ACRONYMS, continued
 NOAA                  National Oceanic and Atmospheric Administration
 NTP                   Northlink Transit Partners
 OCS                   Overhead Catenary System
 OMF                   Sound Transit’s Operations and Maintenance Facility
 PB                    PB Americas Inc.
 PE                    Preliminary Engineering
 PEP                   Project Execution Plan
 PMOC                  Project Management Oversight Consultant
 PSST                  Pine Street Stub Tunnel
 QA                    Quality Assurance
 QC                    Quality Control
 RE                    Resident Engineer
 RFC                   Request for Change
 RFI                   Request for Information
 RIR                   Recordable Injury Rates
 ROD                   Record of Decision
 ROW                   Right of Way
 RVP                   Rainier Vista Plan
 SCC                   Standard Cost Categories
 SCL                   Seattle City Light
 SDEIS                 Supplemental Draft Environmental Impact Statement
 SEPA                  State Environmental Policy Act
 SPI                   Schedule Performance Index
 ST                    Sound Transit
 START                 Seattle Tunnel and Rail Team
 TBM                   Tunnel Boring Machine
 TFK                   Traylor Frontier Kemper Joint Venture
 TVM                   Ticket Vending Machine
 UAC                   Unallocated Contingency
 U-Link                University Link project
 USFWS                 U.S. Fish and Wildlife Service
 UW                    University Of Washington
 UWS                   University of Washington Station
 WBS                   Work Breakdown Structure
 WSDOT                 Washington Department of Transportation


August 2011                                                                  Page 47 of 47

				