      Work packages                    2010                                2011                                                2012

1. Project Management

2. Product Mapping and Review

3. Production of Core Product

4. Sector Adaption

5. Piloting

6. Dissemination, Mainstreaming
   and Exploitaion
7. Evaluation


                                      M1              M2       M3         M4                         M5             M6                            M7
                                                                                                                                                   MS4
                                               MS1        MS2                          MS3
   Meetings                                                                                                                                        MS5
   M1 – 2010 End October (1st meeting - agreement on proj man procedures, confirm terms of reference for evaluator, agree milestones, roles) - Linköping
   M2 – 2011 Jan and Feb - Bilateral Scotland/Sweden to provide materials, model
   M3 – 2011 End March (report on challenges, presentation of combined model) - Dundee
   M4 – 2011 Mid June (workshop -plans for piloting, involvement of stakeholders, evaluation of feedback etc) - Ireland
   M5 – 2011 November/December (initial feedback on piloting and refinement) - Santander
   M6 – 2012 March (end of pilot, review ) - Parma
   M7 – 2012 September (final conference) - Bryssels              Milestones
                                                                  MS1 – 2010 Dec Report on challenges
                                                                  MS2 – 2011 Feb Report on features of model
    Quarter                                                       MS3 – 2011 Aug Interim draft report on adaptation and rationale
                                                                  MS4 – 2012 Sep Final report on transferable model and customisation ”add-ons”
                                                                  MS5 – 2012 Sep Final evaluation report

								