100 Interactive Project Evaluation
102 Preliminary Roadway Design
103 Preliminary Conceptual Mitigation Design Plan
105 Environmental Resource Reports
106 Preliminary Geotech & Materials
107 Geotechnical Wetland Evaluation
108 Preliminary Survey
110 Preliminary R/W
111 Phase One S.U.E.
112 Preliminary Traffic
114 Preliminary Bridge Layout
116 Preliminary Environmental Doc. & Final Resource Reports
118 Roadway Alignment Plan
119 Conceptual Mitigation Design Plan
120 Engineering / Cadastral Survey
122 Alignment & Grade Traffic Plans
124 Finalize Align & Grade
125 Finalize Conceptual Mitigation Design Selection Meeting
126 Prepare Categorical Exclusion
128 Prepare Scope of Work
129 Prepare Wetland Scope of Work
130 Geotech & Materials for PIH
131 Final Geotechnical Revisions - Wetland
134 Prepare Plans for PIH
135 Prepare Final Mitigation Design
136 Preliminary Structure Plans for PIH
138 Preliminary R/W Plan for PIH
140 Plan In Hand
141 Final Mitigation Design Plan In Hand
142 R/W Plans
144 R/W Plan Revision
146 Structure Design
147 Final Structure Design
148 Final Environmental & Permits
149 Final Wetland Mitigation Permits & Clearances
150 Appraise R/W By Consultant
152 Final Plan Preparation
153 Final Mitigation Design Plan
154 Conduct and Complete R/W Negotiation by Consultant
156 R/W Plan Revisions
158 Materials and Geotech Revisions
160 Process For Condemnation
162 Final Plan Revisions
164 Prepare Traffic Plans for PIH
166 Utility Plans
170 Preliminary Hydraulics Report
171 Preliminary Hydraulics Report
172 Final Hydraulics Report
173 Final Wetlands Hydraulics Report
174 Final Hydraulics Updates-Permits and Miscellaneous Revisions
175 Final Plan Review
177 Cultural Resource Management - Consultant
178 Request Environmental Information
179 Traffic Noise Impact Assessment
180 Air Quality Assessment
181 Haz Mat/Sub/H2O Quality-ISA
182 Biological Resources Report
190 Utility Plan Revisions
192 Administrative Draft Environmental Document (EA-EIS Only)
195 Prepare Environmental Assessment
196 Prepare Environmental Decision Document (FONSI/EIS)
197 Prepare Draft Environmental Impact Statement
198 Prepare Final Environmental Impact Statement
199 Prepare Record of Decision
12/13/2011
MDT PROGRESS REPORT
Consultant: Project Name:
Consultant Project Manager: Project No.
MDT Project Manager: Control No. XXXX
Period: MONTH, YEAR – MONTH, YEAR Percent of Budget Expended
Actual
% Early Finish Completion
Activity Description Complete Date* Date
100 Interactive Project Evaluation 1/20/2006
170 Preliminary Hydraulics Report
106 Preliminary Geotech & Materials
114 Preliminary Bridge Layout
112 Preliminary Traffic
108 Preliminary Survey
102 Preliminary Roadway Design
110 Preliminary R/W
S 111 Phase One S.U.E.
u 177 Cultural Resource Management - Consultant
r 178 Request Environmental Information
v 179 Traffic Noise Impact Assessment
e 180 Air Quality Assessment
y 181 Haz Mat/Sub/H2O Quality-ISA
182 Biological Resources Report
P 122 Alignment & Grade Traffic Plans
h 120 Engineering / Cadastral Survey
a 118 Roadway Alignment Plan
s 116 Preliminary Environmental Doc. & Final Resource Reports
e 124 Finalize Align & Grade
126 Prepare Categorical Exclusion
192 Administrative Draft Environmental Document (EA-EIS Only)
195 Prepare Environmental Assessment
196 Prepare Environmental Decision Document (FONSI/EIS)
197 Prepare Draft Environmental Impact Statement
198 Prepare Final Environmental Impact Statement
199 Prepare Record of Decision
128 Prepare Scope of Work
172 Final Hydraulics Report
D
130 Geotech & Materials for PIH
e
134 Prepare Plans for PIH
s
138 Preliminary R/W Plan for PIH
i
164 Prepare Traffic Plans for PIH
g
136 Preliminary Structure Plans for PIH
n
140 Plan In Hand
148 Final Environmental & Permits
146 Structure Design
R 174 Final Hydraulics Updates-Permits and Miscellaneous Revisions
/ 152 Final Plan Preparation
W 158 Materials and Geotech Revisions
166 Utility Plans
142 R/W Plans
144 R/W Plan Revision
156 R/W Plan Revisions
150 Appraise R/W By Consultant
154 Conduct and Complete R/W Negotiation by Consultant
160 Process For Condemnation
190 Utility Plan Revisions
R
/
W 147 Final Structure Design
175 Final Plan Review
Version 26.2b
12/13/2011
MDT PROGRESS REPORT
Consultant: Project Name:
Consultant Project Manager: Project No.
MDT Project Manager: Control No. XXXX
Period: MONTH, YEAR – MONTH, YEAR Percent of Budget Expended
Actual
% Early Finish Completion
Activity Description Complete Date* Date
162 Final Plan Revisions
* Early Finish Date as per contract, amendment or agreement with MDT project manager.
Tasks Accomplished This Period
1 Activity 106 - The Geotech Report was submitted October 7, 2004.
2 Activity 116 -Processing MDT's comments on Draft EA.
3 Activity 118 - Alignment and Grade Plans - work is proceeding.
S 4 Activity 120 - The Cadastral Survey was submitted October 22, 2004.
u 5 Activity 170 - The LHSR and Preliminary Hydraulics Report were submitted October 5, 2004.
r
v Tasks Planned For Next Period
e 1 Prepare Activity 110
y 2 Submit Activity 118 revisions to plans
P Critical Issues
h 1 The schedule for this project needs adjustment.
a
s
e Approved by Title Date: 12/13/2011
Printed Name and Title
Version 26.2b
12/13/2011
MDT PROGRESS REPORT
Consultant: Project Name:
Consultant Project Manager: Project No.
MDT Project Manager: Control No. XXXX
Period: MONTH, YEAR – MONTH, YEAR Percent of Budget Expended
% Early Finish
Activity Description Complete Date*
100 Interactive Project Evaluation 1/20/2006
171 Preliminary Hydraulics Report
107 Geotechnical Wetland Evaluation
103 Preliminary Conceptual Mitigation Design Plan
111 Phase One S.U.E.
105 Environmental Resource Reports
108 Preliminary Survey
119 Conceptual Mitigation Design Plan
116 Preliminary Environmental Doc. & Final Resource Reports
125 Finalize Conceptual Mitigation Design Selection Meeting
126 Prepare Categorical Exclusion
192 Administrative Draft Environmental Document (EA-EIS Only)
195 Prepare Environmental Assessment
196 Prepare Environmental Decision Document (FONSI/EIS)
129 Prepare Wetland Scope of Work
173 Final Wetlands Hydraulics Report
131 Final Geotechnical Revisions - Wetland
135 Prepare Final Mitigation Design
120 Engineering / Cadastral Survey
141 Final Mitigation Design Plan In Hand
150 Appraise R/W By Consultant
149 Final Wetland Mitigation Permits & Clearances
174 Final Hydraulics Updates-Permits and Miscellaneous Revisions
153 Final Mitigation Design Plan
175 Final Plan Review
162 Final Plan Revisions
* Early Finish Date as per contract, amendment or agreement with MDT project manager.
Tasks Accomplished This Period
1 Activity 106 - The Geotech Report was submitted October 7, 2004.
2 Activity 116 -Processing MDT's comments on Draft EA.
3 Activity 118 - Alignment and Grade Plans - work is proceeding.
4 Activity 120 - The Cadastral Survey was submitted October 22, 2004.
5 Activity 170 - The LHSR and Preliminary Hydraulics Report were submitted October 5, 2004.
Tasks Planned For Next Period
1 Prepare Activity 110
2 Submit Activity 118 revisions to plans
Critical Issues
1 The schedule for this project needs adjustment.
Approved by Title Date:
Printed Name and Title
Version 26.2b
MDT PROGRESS REPORT 12/13/2011
Consultant: Project Name:
Consultant Project Manager: Project No.
MDT Project Manager: Control No. XXXX
Period: MONTH, YEAR – MONTH, YEAR Percent of Budget Expended
% Early Finish
Activity Description Complete Date*
Version 26.2b
12/13/2011
dget Expended
Actual
Completion
Date
12/13/2011
Version 26.2b
12/13/2011
dget Expended
Actual
Completion
Date
Version 26.2b
MDT Progress Report (CE Services)
Project:
From:
To:
Who Time
Date of Date of Request Made
Description Responded Spent on
Request Completion By:
to Request Request