					V9, JU, 24/03/09                                     Feb             Mar                      Apr                 May                 June                     July                August              Sept                Oct
                                             wk4 wk5 wk6 wk7 wk8 wk9 wk10 wk11 wk12 wk13 wk14 wk15 wk16 wk17 wk18 wk19 wk20 wk21 wk22 wk23 wk24 wk25 wk26 wk27 wk28 wk29 wk30 wk31 wk32 wk33 wk34 wk35 wk36 wk37 wk38 wk39 wk40 wk41 wk42
Cooldown point 6

Injection Systems:
MKI LSS8 interlock testing etc
MKI LSS8 Automatic Cond
MKI LSS8 Soft Start tests
MKI LSS8: pre-pulse, timing, etc.
Remote operation from CCC

Replacement MKI LSS2 installed
MKI LSS2 interlock testing etc
MKI LSS2 Automatic Cond
MKI LSS2 Soft Start tests
MKI LSS2 & LSS8: pre-pulse, timing, etc.
Remote operation from CCC

TL commissioning (MSI, collimators, BPMs)
TT40 beam tests (// MD)
TT60 beam tests (// MD)
TT40/TT60 interleaved (// MD)
TT40/TT60 High Intensity & seq. (dedicated MD)
TI8 beam tests, downstream TED
TI2 beam tests, downstream TED
TI2/TI8 spare data - ions
Beam 1 injection tests
Beam 2 injection tests
LHC startup with beam

HV available, pulsing locally
HV available, pulsing remote

MKQA-AC dipole commissioning
V9, JU, 24/03/09                                    Feb             Mar                      Apr                 May                 June                     July                August              Sept                Oct
                                            wk4 wk5 wk6 wk7 wk8 wk9 wk10 wk11 wk12 wk13 wk14 wk15 wk16 wk17 wk18 wk19 wk20 wk21 wk22 wk23 wk24 wk25 wk26 wk27 wk28 wk29 wk30 wk31 wk32 wk33 wk34 wk35 wk36 wk37 wk38 wk39 wk40 wk41 wk42

Beam dumping systems:
Installation cooling UA63
Installation cooling UA67
Re-testing of generators UA63
Re-testing of generators UA67
Commissioning cooling system UA63                         Always run
Commissioning cooling system UA67                         MKD/MKB per
Commissioning at full voltage UA63                        beam.
Commissioning at full voltage UA67                                                  cabling




                                                                                                                      Cabling
Test of mains stability                                   HV is needed from
Re-commissioning of BETS/IPOC.. UA63                      first test onwards
Re-commissioning of BETS/IPOC.. UA67
Re-calibration -synchro & settings UA63
Re-calibration -synchro & settings UA67


MKB63 new tanks installed
MKB63 vacuum installation & pumping
MKBH67 installed and replaced (spare)
MKBV67 replaced
New MKBV67 clean room
New MKBV67 test air + vacuum
New MKBV67 installed and aligned
MKB67 vacuum installation & pumping

Re-testing of systems UA67
Re-testing of systems UA63
Commissioning at full voltage UA67
Commissioning at full voltage UA63




                                                                                                                      Cabling
Test of mains stability                                                                                                                                                                                      50 % effecitive,
Re-commissioning of BETS/IPOC.. UA67                                                                                                                                                                         BIC availability
Re-commissioning of BETS/IPOC.. UA63
Re-calibration -synchro & settings UA67
Re-calibration -synchro & settings UA63
LBDS 2: timing, synchronisation & op. CCC
LBDS 1: timing, synchronisation & op. CCC

HV available; running in local or BETSsim
HV available, pulsing remote BETSsim
HV available, pulsing remote BETS

Timing system needed
RF F_rev needed
BIS loop closed needed
BETSsim needed
Access strap needed
Magnet powering and DCCTs needed
TCDQ/TCSG control SW needed
Injection Logging needed
Dump logging needed
XPOC needed
BI systems needed
SLP needed
Injection sequences needed
Dump sequences needed

				