Embed
Email

Project Plan Guide

Document Sample

Shared by: panniuniu
Categories
Tags
Stats
views:
6
posted:
12/11/2011
language:
pages:
2
Project Name

Managing Dept. Name



December 11, 2011





Project Plan Guidelines

A project plan, also called a work breakdown structure (WBS) is a deliverable-oriented

hierarchical outline of the tasks needed to deliver the project’s product or service. It “breaks-down”

or “decomposes” the project into low-level subtask units of work that will be scheduled, executed and

controlled. The WBS combined with the project scope defines the “what” of the project.







Guidelines for creating the project plan

Activity Strategies/Questions to consider







Begin developing the plan Start with your project team and include others with expertise in

similar projects if possible. Benefits of this approach include:

Use the Microsoft Project template

as a start (template file name is  Team members and experts bring experience from other

project-plan-template.mpp). projects

 Fosters early buy-in for the project among team

members

 Helps discover new or forgotten tasks

 Gives insight to the overall project for team members



Identify the highest level work Start with the template file, which lists high-level work

components components by project phase. What is this project going to

deliver? What needs to be done to support and complete the

project?



The Project Charter and Project plan evolve together as the

project is more clearly defined. Again, this is not a static

document and more detail will be added as more specific fine

points are understood about the project.







Break work process into small Under each high-level component, break the work into small

work components components until each component is defined to a level of detail

that allows accurate estimating for the time and cost required

for its completion.







Work components The component name should adequately describe the task.

Ensure everyone on the team has the same understanding of

the work name and definition. A glossary is an option to

consider to record the agreed to definitions.







Make sure work has been broken Apply the following guidelines to ensure work has been broken





Project Name v1 1

down to the lowest level desired. down to its lowest level:





 Each task has clearly identified results

 Tasks can be performed within a reasonable time. The

industry “8/80 hour rule” states that a work task should

equate to no less than 8 hours and no more than 80

hours: however, this is a broad rule and may or may not

be the best fit for your project.

 The task name conveys the work to be accomplished

 The task is at the level you want to track the project

 Each task is well enough defined and small enough for

credible duration estimates.







Estimate an appropriate time for  Include at least 10-20% overhead when estimating time

each task

 Estimates should consider there to be 18 working days

in a month



 Consider any holidays or impactful events (start or end

of the semester, etc.) that are upcoming









Project Name v1 2



Related docs
Other docs by panniuniu
organization_of_slp_working_files_3-23-10
Views: 1  |  Downloads: 0
Lesson 2 2011 key
Views: 0  |  Downloads: 0
Site Survey
Views: 2  |  Downloads: 0
alt energy project SP11
Views: 1  |  Downloads: 0
Effie Biography
Views: 0  |  Downloads: 0
Download-Organization-application-letter
Views: 0  |  Downloads: 0
TWIN_Nomination_form_2010
Views: 0  |  Downloads: 0
Engineering Change Order Master Log
Views: 2  |  Downloads: 0
360654.f1
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!