Embed
Email

Revised Proposal Summary Pages 1 – 3 provided with

Document Sample
Revised Proposal Summary Pages 1 – 3 provided with
Revised Proposal Summary

Pages 1 – 3 provided with Addendum #1

to replace pages PS1 – PS2

September 18, 2007

NOTICE: No substitution or revision to this Proposal Summary form will be accepted. Truckee Meadows Water

Authority will reject any Bid that is received that has changes or alterations to this document. Although

the Prevailing Wages are provided in this bid document, the bidder is responsible to verify with the Labor

Commissioner if any addendums have been issued. If different, the successful bidder will be required to

provide the current Prevailing Wages used in preparation of their bid within 24 hours of bid submission.



BID # 0708-053

BID TITLE: Hawkings Court Well



PRICES must be valid for 30 calendar days after the bid opening.



A COPY OF THE "CERTIFICATE" of eligibility to receive a preference in bidding on public works issued to him/her

by the State Contractors' Board must be submitted with his/her bid to the Contracts Division in accordance with N.R.S.

338.147 for the preference to be considered. This Statute does not apply to projects expected to cost less than $250,000.



COMPLETION of this project is expected PURSUANT TO CONTRACT DOCUMENTS.



BIDDER acknowledges receipt of _______ Addendums.



______________________________________________

(signature)

SUMMARY





Description Scheduled Unit Total

Value Unit Price Price

1. Mobilization, Bonds, and Insurance 1 LS Lump Sum

(see Note 3 below).

2. Demobilization and Cleanup. 1 LS Lump Sum



3. Sitework including, but not limited 1 LS Lump Sum

to, demolition, clearing and grubbing,

excavation, structural fill, grading,

rock slope protection, drain piping,

manholes, vaults, air gap tank,

equipment pads, sidewalk, aggregate

base, asphalt concrete, and surface

restoration.

4. Fences and gate including, but not 1 LS Lump Sum

limited to, concrete post footings,

View fence with metal posts, rails,

and pickets, Privacy gate and fence

with metal posts, HSS gate posts and

frame, wood rails and boards, clear

waterproofing sealer, fabricated latch,

and hardware.





Addendum #1 – Revised Proposal Summary Page 1 of 3

Description Scheduled Unit Total

Value Unit Price Price

5. Landscaping and irrigation 1 LS Lump Sum

including, but not limited to, trees,

shrubs, boulders, river rock, weed

barrier, piping, valves, backflow

prevention device, and irrigation

controller.

6. Pump station structure including, 1 LS Lump Sum

but not limited to, reinforced concrete

footings and slab, pump foundation,

CMU building, pre-engineered

trusses, roofing, rough and finish

carpentry, stucco finish, doors and

door hardware, roof hatch, and

painting.

7. Vertical turbine pump and motor, 1 LS Lump Sum

including but not limited to, 3000 gpm

pump, 400 HP motor, and installation

in the well casing.

8. Piping and pump station equipment 1 LS Lump Sum

including, but not limited to, piping,

valves, fittings, pipe supports,

hypochlorite storage tank,

hypochlorite solution pump, eyewash

station, signs, startup, testing,

flushing, disinfection, and

appurtenances.

9. Instrumentation including, but not 1 LS Lump Sum

limited to, providing RTU, PT, flow

meters, sensors, HVAC and other

controls, installation of TMWA

furnished instruments, and telephone

service conduit.

10. HVAC equipment including, but 1 LS Lump Sum

not limited to, providing evaporative

cooler, split system air conditioner,

supply fan, louvers, ductwork, control

piping, and electric heaters.

11. Electrical and site electrical 1 LS Lump Sum

including, but not limited to,

providing main switchgear, VFD,

manual transfer switch, panels,

lighting, gutters, conduit, conductors,

grounding, SPPC vaults, and primary

and secondary conduit.



12 Total Bid Price





13 Total Bid Price Written in Words:









Addendum #1 – Revised Proposal Summary Page 2 of 3

Notes to Bid Schedule:

1. This Project is bid on a lump sum basis and includes all necessary appurtenances for a complete in-

place, functional facility as described in the Contract Documents. Prices include all labor, equipment,

materials, supervision, profit, overheads, and incidental costs for all work required by the Contract

Documents for the full duration of the Contract Time.

2. Item pricing on this schedule is for internal TMWA use only. Item descriptions are not intended to be

all inclusive. Bidders shall include costs for work not specifically mentioned in the most appropriate

item.

3. Refer to Article 7 of the General Conditions for a list of items that may be included in the mobilization

bid item.

4. TMWA reserves the right to perform extra work using time and expense or negotiated lump sum

procedures.









Addendum #1 – Revised Proposal Summary Page 3 of 3


Related docs
Other docs by shelseaZvansky
Call for Papers Business Proposal
Views: 6  |  Downloads: 0
Temporary Bear Sealing Certificate
Views: 4  |  Downloads: 0
JOINDER IN CERTIFICATE OF PAYMENT
Views: 2  |  Downloads: 0
Certificate in Applied Social Sciences 2010
Views: 13  |  Downloads: 0