Rough Grading Inspection Certificate by shelseaZvansky

VIEWS: 26 PAGES: 1

									                   City of Rancho Cucamonga
                   Building and Safety Department
                   10500 Civic Center Dr.
                   Rancho Cucamonga, Ca.91730
                  T: (909) 477-2710 / F: (909) 477-2711


                          GRADING BOND RELEASE CHECK-OFF LIST
Applicant
              Provide a letter of request for the Grading Bond Release. The letter should have
                complete information of the project: project name, address, tract number, etc.
              Submit the letter with a copy of the Rancho Cucamonga Agreement to Install
                Improvements, which was issued prior to the issuance of the grading permit
              Submit an “As-Built” Grading Plan and Certifications from the project’s Civic Engineer

Person requesting bond release:

Address:



Phone #:

BOND #.____________________________ (BOND WILL NOT BE RELEASED WITHOUT A BOND NUMBER)

1.            Letter of request for grading releases to include PMT#, Tract # or address
              Bond release             Line of credit            Reimbursement of Cash deposit

2.       GRADING INSPECTOR: Review and check the appropriate boxes.

              As-Built Grading Plan
              Certifications form the project’s civil engineer
              Inspect job site to insure compaction completion
              Horse trails
              Concrete swales                                           Attach bond to paperwork

         Comments:

3.       BUILDING INSPECTOR:               Review and check the appropriate boxes.

              All permits are final                                       Others

4.       ASSOCIATE ENGINEER

              Review all sign-offs and forward the form letter to Office Specialist II for typing
              Discard notes and other miscellaneous back up information

5.       OFFICE SPECIALIST II

              Prepare the release grading letter
              Obtain signature from the Associate Engineer or the Building and Safety Official
              for the letter of Release and mail the letter of to the applicant
              Retain a copy of the Grading Agreement and the request letter for 90-days before
              Scan the grading bond release letter into Tidemark


Last Updated: July 2009

								
To top