MS
472.12
10
Fall 2011
Problems
ch 8
Probabilistic Activity Times
• pr 27
Network
ES, EF, LS, LF table
Probable time
Standard Deviation
bonus:
» likelihood of meeting deadline (June 1)
Crashing
• pr 33
either AON or AOA
» network
» Excel
» crash network to 26 weeks
» what is the shortest time it can be crashed to
» what would it cost at the shortest time?
Probabilistic Activity Times
estimates not exact
turning guesses into math
most likely time m
optimistic time a
pessimistic time b
a 4m b
mean (expected time) t
6
ba
2
variance v
6
Probabilistic Activity Times
Mean
Time Estimates (weeks) Time Variance
Activity a m b t v
1
2
3
4
5
6
7
8
9
10
11
Probabilistic Activity Times
Mean
Time Estimates (weeks) Time Variance
Activity a m b t v
1 8.00
2 6.00
3 3.00
4 4.00
5 3.00
6 4.00
7 2.00
8 7.00
9 4.00
10 4.00
11 10.00
Probabilistic Activity Times
Mean
Time Estimates (weeks) Time Variance
Activity a m b t v
1 6.00 8.00
2 3.00 6.00
3 1.00 3.00
4 2.00 4.00
5 2.00 3.00
6 3.00 4.00
7 2.00 2.00
8 3.00 7.00
9 2.00 4.00
10 1.00 4.00
11 1.00 10.00
Probabilistic Activity Times
a 4m b
t
6
Mean
Time Estimates (weeks) Time Variance
Activity a m b t v
1 6.00 8.00 10.00
2 3.00 6.00 9.00
3 1.00 3.00 5.00
4 2.00 4.00 12.00
5 2.00 3.00 4.00
6 3.00 4.00 5.00
7 2.00 2.00 2.00
8 3.00 7.00 11.00
9 2.00 4.00 6.00
10 1.00 4.00 7.00
11 1.00 10.00 13.00
Probabilistic Activity Times
a 4m b
t
6
Mean
Time Estimates (weeks) Time Variance
Activity a m b t v
1 6.00 8.00 10.00 8.00
2 3.00 6.00 9.00 6.00
3 1.00 3.00 5.00 3.00
ba
2
4 2.00 4.00 12.00 5.00
5 2.00 3.00 4.00 3.00 v
6 3.00 4.00 5.00 4.00 6
7 2.00 2.00 2.00 2.00
8 3.00 7.00 11.00 7.00
9 2.00 4.00 6.00 4.00
10 1.00 4.00 7.00 4.00
11 1.00 10.00 13.00 9.00
Probabilistic Activity Times
Mean
Time Estimates (weeks) Time Variance
Activity a m b t v
1 6.00 8.00 10.00 8.00 0.44
2 3.00 6.00 9.00 6.00 1.00
3 1.00 3.00 5.00 3.00 0.44
ba
2
4 2.00 4.00 12.00 5.00 2.78
5 2.00 3.00 4.00 3.00 0.11 v
6 3.00 4.00 5.00 4.00 0.11 6
7 2.00 2.00 2.00 2.00 0.00
8 3.00 7.00 11.00 7.00 1.78
9 2.00 4.00 6.00 4.00 0.44
10 1.00 4.00 7.00 4.00 1.00
11 1.00 10.00 13.00 9.00 4.00
Probabilistic Activity Times
project activities on criticalpath
Mean
Time Estimates (weeks) Time Variance
Activity a m b t v
1 6.00 8.00 10.00 8.00 0.44
2 3.00 6.00 9.00 6.00 1.00
3 1.00 3.00 5.00 3.00 0.44
4 2.00 4.00 12.00 5.00 2.78
5 2.00 3.00 4.00 3.00 0.11
6 3.00 4.00 5.00 4.00 0.11
7 2.00 2.00 2.00 2.00 0.00
8 3.00 7.00 11.00 7.00 1.78
9 2.00 4.00 6.00 4.00 0.44
10 1.00 4.00 7.00 4.00 1.00
11 1.00 10.00 13.00 9.00 4.00
Project Crashing
turning money into time
spend money on selected activities
• to reduce total project time
• which ones?
• how much?
money to spend
time saved
Project Crashing
all projects have both direct & indirect costs
Total costs
Indirect costs
$
crashing
Direct costs
optimal t
project time
2
8
4
Crashing 1
12
7
12 4
6
house 5 4
4
3
4
Normal
Activity time
1: Design house & obtain financing 12
2: Lay foundation 8
3: Order materials 4
4: Build house 12
5: Select paint 4
6: Select carpet 4
7: Finish work 4
2
8
4
Crashing 1
12
7
12 4
6
5 4
4
3
4
Normal
Activity time cost
1: Design house & obtain financing 12 $3,000
2: Lay foundation 8 $2,000
3: Order materials 4 $4,000
4: Build house 12 $50,000
5: Select paint 4 $500
6: Select carpet 4 $500
7: Finish work 4 $15,000
2
8
4
Crashing 1
12
7
12 4
6
5 4
4
3
4
Normal Crash
Activity time cost time cost
1: Design house & obtain financing 12 $3,000 7
2: Lay foundation 8 $2,000 5
3: Order materials 4 $4,000 3
4: Build house 12 $50,000 9
5: Select paint 4 $500 1
6: Select carpet 4 $500 1
7: Finish work 4 $15,000 3
2
8
12 4
Crashing 1 20 12
7
12 4
6
5 4
4
3
4
12
16
Normal Crash
Activity time cost time cost
1: Design house & obtain financing 12 $3,000 7 $5,000
2: Lay foundation 8 $2,000 5 $3,500
3: Order materials 4 $4,000 3 $7,000
4: Build house 12 $50,000 9 $71,000
5: Select paint 4 $500 1 $1,100
6: Select carpet 4 $500 1 $1,100
7: Finish work 4 $15,000 3 $22,000
2
8
4
Crashing 1
12
7
12 4
6
5 4
4
3
4
Resulting
Normal Crash time cost
Activity time cost time cost saved incurred
1: Design house & obtain financing 12 $3,000 7 $5,000
2: Lay foundation 8 $2,000 5 $3,500
3: Order materials 4 $4,000 3 $7,000
4: Build house 12 $50,000 9 $71,000
5: Select paint 4 $500 1 $1,100
6: Select carpet 4 $500 1 $1,100
7: Finish work 4 $15,000 3 $22,000
per week
2
8
4
Crashing 1
12
7
12 4
6
5 4
4
3
4
assume linear relationship
Resulting
Normal Crash time cost
Activity time cost time cost saved incurred
1: Design house & obtain financing 12 $3,000 7 $5,000 5
2: Lay foundation 8 $2,000 5 $3,500 3
3: Order materials 4 $4,000 3 $7,000 1
4: Build house 12 $50,000 9 $71,000 3
5: Select paint 4 $500 1 $1,100 3
6: Select carpet 4 $500 1 $1,100 3
7: Finish work 4 $15,000 3 $22,000 1
per week
2
8
4
Crashing 1
12
7
12 4
6
5 4
4
3
4
critical path and nodes may change
Resulting
Normal Crash time cost
Activity time cost time cost saved incurred
1: Design house & obtain financing 12 $3,000 7 $5,000 5 $400
2: Lay foundation 8 $2,000 5 $3,500 3 $500
3: Order materials 4 $4,000 3 $7,000 1 $3,000
4: Build house 12 $50,000 9 $71,000 3 $7,000
5: Select paint 4 $500 1 $1,100 3 $200
6: Select carpet 4 $500 1 $1,100 3 $200
7: Finish work 4 $15,000 3 $22,000 1 $7,000
per week
Problems
ch 8
Probabilistic Activity Times
• pr 27
Network
ES, EF, LS, LF table
Probable time
Standard Deviation
bonus:
» likelihood of meeting deadline (June 1)
Crashing
• pr 33
either AON or AOA
» network
» Excel
» crash network to 26 weeks
» what is the shortest time it can be crashed to
» what would it cost at the shortest time?