Key West Maintenance Dredging e Project

Draft Permit Completion/ Environmental Compliance Matrix

Notification and Submittal Schedule

08/05 /06

Permit Holder: US NAVY

Project Name: KEY WEST HARBOR Maintenance Dredging

Permit/Authorization No.: 0207625-0021 EI Monroe County

Issuance Date: 06/17/2003 through latest mod march 6 2006

Expiration Date: 06/17/2013

Author Karch and Mc Adams

Permit Responsible

Specification Deadline

Reference Entity

DEP Permit Pre-Construction



GC 1 Notify DEP of any deviation from authorized project prior to implementation COE

Turbidity barriers installed and maintained in all locations

Contractor/

GC 3 where possibility of transferring suspended solids to water prior to construction

COE

body exists.

Submit to the department an "Environmental resource Permit

Contractor to

Construction Commencement form" at least 48 hours prior to At least 48 hours prior to

GC 4 Ivan Soto to

commencement. Send out invitation to Pre-construction construction

DEP

Conference.









Navy Base Key

GC 8 Obtain all other applicable licenses or permits prior to implementation West

Commanding

SC 4 Send out invitation to Pre-construction Conference At least 10 days prior to Pre-Con Ivan Soto









At least 20 days prior to

SC 4 (cont.) Pre-con to be conducted w/ contractors, COE, FWC, & DEP George Cooper

commencement.









DEP Permit During Construction

Contractor to review DEP permit; copy of permit to be kept at prior to commencement and Contractor/

GC 2

work site during work COE

Notify DEP immediately in writing of any previously submitted

GC 12 during work Navy Contractor

information which is discovered to be inaccurate.

If historical or arcaeological artifacts are found, stop work. Contractor/

SC 3 during work

Report finds of archeological artifacts to SHPO/DEP COE

Beach compatible sand to be stored on Rockland Key

SC 5 during work Contractor

containment site







Page 1

Key West Maintenance Dredging e Project

Draft Permit Completion/ Environmental Compliance Matrix

Notification and Submittal Schedule

08/05 /06

Permit Holder: US NAVY

Project Name: KEY WEST HARBOR Maintenance Dredging

Permit/Authorization No.: 0207625-0021 EI Monroe County

Issuance Date: 06/17/2003 through latest mod march 6 2006

Expiration Date: 06/17/2013

Author Karch and Mc Adams

Permit Responsible

Specification Deadline

Reference Entity

Conduct all work in accordance w/ Specs 01355

during work Contractor

Environmental Protection and 01452 Dredging/Fill Placement

Navy

Meet state water quality standards during loading,

during work communicating

transporting, and discharge of dredged material

with contractor

Ensure that any anchoring activities be conducted either

within the navigation channel or in areas without sea grass, during work Contractor

algal, hard bottom, or coral communities

Monitoirng Turbidity: conduct compliance and background monitoring at Twice daily; at least 4 hours apart

Navy Contractor

Required mid-depth at dredging and disposal (State waters) sites during all dredge activity

Cease work/Notify CESAJ (Env. Branch Chief and C. O.) of Navy Contractor

any EXCEEDENCE of 29 ntu over background levels at edge Immediately to Dredge

of 150 m mixing zone Captain to Ivan

Within 7 days of test, to Ron Soto

Provide to CESAJ/DEP turbidity test reports (electronically) Navy Contractor

Williams, Richard Stalker DEP







DEP Permit Post-Construction

Send Notice of Completion to DEP. The permittee shall

Contractor to

submit a written statement of completion "Environmental Within 30 days after work is

GC 6 Ivan Soto to

resource Permit As Built Certification by a Registered completed

DEP.

Professional". Additionally any deviation from approved

Submit two copies of Final After-Dredge Surveys to DEP Within 90 days of work George Cooper

SC 9

BBCS and DEP Southeast District Office completion to request





EPA Ocean

Dumping During Construction

Permit

ODMDS Dump Tracking Logs using the ETS continuous for dredging

Daily every dump Contractor

SMMP site to the dump site. Dump to be within 600 foot of center

Contractor to stay within marked channel past reef line and

Daily every load to ODMDS Contractor

end of channel markers, then turn towards ODMDS







EPA Ocean

Dumping Post Construction

Permit

Summary of dump tracking logs to epa within 90 days Contractor to Ivan Soto to Glenn Glenn

of completion of work Schuster to EPA Schuster

Post construction survey of disposal area within 90 days of Corps survey branch to Glenn George Cooper

completion of work Schuster to EPA to request









Page 2

Key West Maintenance Dredging e Project

Draft Permit Completion/ Environmental Compliance Matrix

Notification and Submittal Schedule

08/05 /06

Permit Holder: US NAVY

Project Name: KEY WEST HARBOR Maintenance Dredging

Permit/Authorization No.: 0207625-0021 EI Monroe County

Issuance Date: 06/17/2003 through latest mod march 6 2006

Expiration Date: 06/17/2013

Author Karch and Mc Adams

Permit Responsible

Specification Deadline

Reference Entity

USFWL and

During Construction

NMFS BO



TURTLE Continuous monitoring of inflow to hoppers to assure that

Continuous monitoring of inflows Chris Slay

MONITORING marine turtles are not caught by hopper dredge



WHALE

Monitoring for whales on track to ODMDS Daily every load to ODMDS Chris Slay

MONITORING

Continuous monitoring of vicinity of hopper, survey vessels

MANATEE

and work boats to assure that manatees are not hit during Daily Continuously Chris Slay

MONITORING work.



Post construction submittal of endangered species

Chris Slay

monitoring summary



REEF Contractor to stay within marked channel past reef line and

Daily every load to ODMDS Contractor

PROTECTION end of channel markers, then turn towards ODMDS









Page 3

Date

Provided







TBD









?









?





?









TBD



TBD









Page 4

Date

Provided









TBD



TBD









Page 5

Date

Provided









TBD









Page 6

Contact Information



Contractor--?, POC Name: ? Phone: Cell: email:



CESAJ CO-W (Contracting Officer Rep/Area Engineer)--Ivan Soto; 561-683-1577 ex 11; ivan.soto@saj02.usace.army.mil



CESAJ CO-(Quality Assurance Rep)--No contact



N

CESAJ CO-C-- o contact



CESAJ EN-- No contact



CESAJ PD-Eq (WQC)--Paul Karch; (904) 232-2168; paul.a.karch@saj02.usace.army.mil



CESAJ PD-E (NEPA)--Terri Jordan; (904) 232-1817; terri.l.jordan@saj02.usace.army.mil



CESAJ PD-E (103)--Glenn Schuster; (904) 232-3691; glenn.r.schuster@saj02.usace.army.mil



CESAJ PD-E (Branch Chief)--Marie Burns; (904) 232-2202; marie.g.burns@saj02.usace.army.mil



FDEP BBCS--Steve MacLeod; (850) 414-779; Steven.MacLeod@dep.state.fl.us



FWC Imperiled Species Management--Kipp Frohlich; (850) 922-4330; kipp.frohlich@fwc.state.fl.us



USEPA Region 4 --Chris McArthur; (404) 562-9391; mcarthur.christopher@epa.gov



USFWS SFES Vero Beach--



NMFS PSMB St. Petersburg--



U.S. Coast Guard MSO Port Everglades Field Office: (954) 920-7899



Endangered Species Monitoring:

Engineer)--Ivan Soto; 561-683-1577 ex 11; ivan.soto@saj02.usace.army.mil


Related docs
Other docs by HC1112040355
Sheet1
Views: 5  |  Downloads: 0
AUGUSTA STATE UNIVERSITY
Views: 0  |  Downloads: 0
Welcome Spanish
Views: 0  |  Downloads: 0
El foro APEC, caracter�sticas y objetivos
Views: 15  |  Downloads: 0
INSTITUTO PROF
Views: 4  |  Downloads: 0
Sheet1 (3)
Views: 27  |  Downloads: 0
SECRETARIA DE EDUCACION P�BLICA
Views: 5  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!