scope of work template
							                                         Key West Maintenance Dredging e   Project
                                   Draft Permit Completion/ Environmental Compliance Matrix
                                                      Notification and Submittal Schedule
                                                              08/05 /06
                                                    Permit Holder: US NAVY
                                                    Project Name: KEY WEST HARBOR Maintenance Dredging
                                          Permit/Authorization No.: 0207625-0021 EI Monroe County
                                                   Issuance Date: 06/17/2003 through latest mod march 6 2006
                                                   Expiration Date: 06/17/2013
  Author       Karch and Mc Adams
  Permit                                                                                                              Responsible
                                       Specification                                           Deadline
 Reference                                                                                                               Entity
DEP Permit                           Pre-Construction

   GC 1             Notify DEP of any deviation from authorized project              prior to implementation              COE
                Turbidity barriers installed and maintained in all locations
                                                                                                                       Contractor/
   GC 3         where possibility of transferring suspended solids to water            prior to construction
                                                                                                                         COE
                                         body exists.
               Submit to the department an "Environmental resource Permit
                                                                                                                      Contractor to
               Construction Commencement form" at least 48 hours prior to            At least 48 hours prior to
   GC 4                                                                                                               Ivan Soto to
                 commencement. Send out invitation to Pre-construction                     construction
                                                                                                                          DEP
                                        Conference.




                                                                                                                     Navy Base Key
   GC 8               Obtain all other applicable licenses or permits                prior to implementation             West
                                                                                                                      Commanding
   SC 4             Send out invitation to Pre-construction Conference           At least 10 days prior to Pre-Con      Ivan Soto




                                                                                     At least 20 days prior to
SC 4 (cont.)   Pre-con to be conducted w/ contractors, COE, FWC, & DEP                                               George Cooper
                                                                                         commencement.




DEP Permit                         During Construction
               Contractor to review DEP permit; copy of permit to be kept at       prior to commencement and           Contractor/
   GC 2
                                           work site                                         during work                 COE
               Notify DEP immediately in writing of any previously submitted
  GC 12                                                                                    during work               Navy Contractor
                      information which is discovered to be inaccurate.
                If historical or arcaeological artifacts are found, stop work.                                         Contractor/
   SC 3                                                                                    during work
                    Report finds of archeological artifacts to SHPO/DEP                                                  COE
                   Beach compatible sand to be stored on Rockland Key
   SC 5                                                                                    during work                 Contractor
                                       containment site



                                                           Page 1
                                      Key West Maintenance Dredging e   Project
                                Draft Permit Completion/ Environmental Compliance Matrix
                                                   Notification and Submittal Schedule
                                                           08/05 /06
                                                 Permit Holder: US NAVY
                                                 Project Name: KEY WEST HARBOR Maintenance Dredging
                                       Permit/Authorization No.: 0207625-0021 EI Monroe County
                                                Issuance Date: 06/17/2003 through latest mod march 6 2006
                                                Expiration Date: 06/17/2013
 Author      Karch and Mc Adams
 Permit                                                                                                        Responsible
                                    Specification                                       Deadline
Reference                                                                                                         Entity
                   Conduct all work in accordance w/ Specs 01355
                                                                                     during work                Contractor
             Environmental Protection and 01452 Dredging/Fill Placement
                                                                                                                   Navy
                  Meet state water quality standards during loading,
                                                                                     during work              communicating
                   transporting, and discharge of dredged material
                                                                                                              with contractor
               Ensure that any anchoring activities be conducted either
              within the navigation channel or in areas without sea grass,          during work                 Contractor
                        algal, hard bottom, or coral communities
Monitoirng   Turbidity: conduct compliance and background monitoring at Twice daily; at least 4 hours apart
                                                                                                              Navy Contractor
 Required       mid-depth at dredging and disposal (State waters) sites       during all dredge activity
              Cease work/Notify CESAJ (Env. Branch Chief and C. O.) of                                        Navy Contractor
             any EXCEEDENCE of 29 ntu over background levels at edge                Immediately                 to Dredge
                                  of 150 m mixing zone                                                        Captain to Ivan
                                                                           Within 7 days of test, to Ron           Soto
              Provide to CESAJ/DEP turbidity test reports (electronically)                                    Navy Contractor
                                                                           Williams, Richard Stalker DEP



DEP Permit                       Post-Construction
               Send Notice of Completion to DEP. The permittee shall
                                                                                                               Contractor to
               submit a written statement of completion "Environmental       Within 30 days after work is
  GC 6                                                                                                         Ivan Soto to
                resource Permit As Built Certification by a Registered               completed
                                                                                                                  DEP.
               Professional". Additionally any deviation from approved
               Submit two copies of Final After-Dredge Surveys to DEP           Within 90 days of work        George Cooper
  SC 9
                      BBCS and DEP Southeast District Office                          completion                to request


EPA Ocean
 Dumping                        During Construction
  Permit
 ODMDS       Dump Tracking Logs using the ETS continuous for dredging
                                                                                  Daily every dump              Contractor
 SMMP         site to the dump site. Dump to be within 600 foot of center
             Contractor to stay within marked channel past reef line and
                                                                              Daily every load to ODMDS         Contractor
                  end of channel markers, then turn towards ODMDS



EPA Ocean
 Dumping                         Post Construction
  Permit
              Summary of dump tracking logs to epa within        90 days    Contractor to Ivan Soto to Glenn   Glenn
                                 of completion of work                             Schuster to EPA           Schuster
              Post construction survey of disposal area within 90 days of   Corps survey branch to Glenn George Cooper
                                  completion of work                               Schuster to EPA           to request




                                                       Page 2
                                        Key West Maintenance Dredging e   Project
                                  Draft Permit Completion/ Environmental Compliance Matrix
                                                     Notification and Submittal Schedule
                                                             08/05 /06
                                                   Permit Holder: US NAVY
                                                   Project Name: KEY WEST HARBOR Maintenance Dredging
                                         Permit/Authorization No.: 0207625-0021 EI Monroe County
                                                  Issuance Date: 06/17/2003 through latest mod march 6 2006
                                                  Expiration Date: 06/17/2013
   Author      Karch and Mc Adams
   Permit                                                                                                        Responsible
                                      Specification                                        Deadline
  Reference                                                                                                         Entity
 USFWL and
                                  During Construction
  NMFS BO

  TURTLE         Continuous monitoring of inflow to hoppers to assure that
                                                                              Continuous monitoring of inflows    Chris Slay
MONITORING          marine turtles are not caught by hopper dredge

  WHALE
                        Monitoring for whales on track to ODMDS                 Daily every load to ODMDS         Chris Slay
MONITORING
                Continuous monitoring of vicinity of hopper, survey vessels
 MANATEE
                and work boats to assure that manatees are not hit during           Daily Continuously            Chris Slay
MONITORING                                work.

                   Post construction submittal of endangered    species
                                                                                                                  Chris Slay
                                   monitoring summary

   REEF    Contractor to stay within marked channel past reef line and
                                                                                Daily every load to ODMDS         Contractor
PROTECTION    end of channel markers, then turn towards ODMDS




                                                         Page 3
  Date
Provided



  TBD




   ?




   ?


   ?




  TBD

  TBD




Page 4
  Date
Provided




  TBD

  TBD




Page 5
  Date
Provided




  TBD




Page 6
Contact Information

Contractor--?, POC Name: ?         Phone:           Cell:           email:

CESAJ CO-W (Contracting Officer Rep/Area Engineer)--Ivan Soto; 561-683-1577 ex 11; ivan.soto@saj02.usace.army.mil

CESAJ CO-(Quality Assurance Rep)--No contact

           N
CESAJ CO-C-- o contact

CESAJ EN-- No contact

CESAJ PD-Eq (WQC)--Paul Karch; (904) 232-2168; paul.a.karch@saj02.usace.army.mil

CESAJ PD-E (NEPA)--Terri Jordan; (904) 232-1817; terri.l.jordan@saj02.usace.army.mil

CESAJ PD-E (103)--Glenn Schuster; (904) 232-3691; glenn.r.schuster@saj02.usace.army.mil

CESAJ PD-E (Branch Chief)--Marie Burns; (904) 232-2202; marie.g.burns@saj02.usace.army.mil

FDEP BBCS--Steve MacLeod; (850) 414-779; Steven.MacLeod@dep.state.fl.us

FWC Imperiled Species Management--Kipp Frohlich; (850) 922-4330; kipp.frohlich@fwc.state.fl.us

USEPA Region 4 --Chris McArthur; (404) 562-9391; mcarthur.christopher@epa.gov

USFWS SFES Vero Beach--

NMFS PSMB St. Petersburg--

U.S. Coast Guard MSO Port Everglades Field Office: (954) 920-7899

Endangered Species Monitoring:
Engineer)--Ivan Soto; 561-683-1577 ex 11; ivan.soto@saj02.usace.army.mil

						