					                             FREMONT UNIFIED SCHOOL DISTRICT
                                  FREMONT, CALIFORNIA

                                     DISTRICT MEMORANDUM

Office of Origin                                  Subject
FACILITIES MANAGEMENT                             MONTHLY BOND STATUS REPORT

TO:                                               FROM:                            DATE:
CITIZENS’ BOND                                    Therese Gain                     February 6, 2008
OVERSIGHT COMMITTEE

This is the report for the period of December 1, 2007 to January 31, 2008.

1.      STATUS OVERVIEW:

Facilities Construction staff is currently involved in completing the punchlist and closeout of construction
activities for those projects that are substantially complete. Some projects, such as the Adult School
Alteration project are continuing through the phases during the school year.

Three Alteration project scheduled for summer 2008 construction have been issued for bids.
The bids for the Millard Elementary School Alteration were received in late January and are still being
reviewed. The Patterson Elementary School Alteration Project and the Centerville Junior High School
Alteration Project will be opened in February.

We are also involved in monitoring projects that have been submitted to DSA for plan review.

The Auditors visited the District the last week of November to do the financial and performance audit on
bond project activity during the 2006-07 Fiscal Year. The auditors sampled an even greater number of
projects than last year. Their written report was be mailed to the committee and will be reviewed at the
February 6th Board meeting. Members of the Audit team will be present to answer questions.

The tentative schedule for pending project presentations the school year is as follows:

Meeting Date             Presentation Topic               Location

February 6, 2008         Bond Audit Report            District Office Board Room
March 5, 2008            Adult School Projects        Adult School Multi-Use Building - Kitchen
April 2, 2008            Topic and Location of meeting to be determined
May 7, 2008              Topic and Location of meeting to be determined
June 4, 2008             Topic and Location of meeting to be determined

2.      PROJECT BIDS:

Issued for Bids:

Patterson Elementary School, bids due February 5, 2008 at 2:00 pm.
Centerville Junior High Alteration, bids due February 12, 2008 at 2:00 pm.

Bid Openings:
Millard Elementary School, bids opened January 15, 2008 at 2:00 pm.

Contract Awards:
None this period.
3.      SCHEDULE/PHASING ISSUES:

No specific issues at this time. We are working on the design of the remaining Phase 2 projects.

4.      FUNDING ISSUES:

The Bond Project Cash Flow Report was updated and was presented to the Board in November along
with the Staff Bond Status Report. A copy is being provided for all CBOC members.

5.      HANDOUTS:

Bond Project Cost Summary Report, dated January 31, 2008

Review of Bids Received (to Secretary only)
None.

Notice to Bidders (to Secretary only)
None.

6.      GLOSSARY:

        BIP              Bond Implementation Plan
        Bond Phase 1     May 2002 – August 2005
        Bond Phase 2     September 2005 – September 2008
        CBOC             Citizens’ Bond Oversight Committee
        CDE              California Department of Education
        DSA              Division of the State Architect
        FEMA             Federal Emergency Management Agency
        FUSD             Fremont Unified School District
        OPSC             Office of Public School Construction
        Proposition 55   State School Bond Initiative, passed March 2, 2004
        SAB              State Allocation Board
                              FREMONT UNIFIED SCHOOL DISTRICT
                                   FREMONT, CALIFORNIA

                                      DISTRICT MEMORANDUM

Office of Origin                                  Subject
FACILITIES MANAGEMENT                             MONTHLY BOND STATUS REPORT

TO:                                               FROM:                             DATE:
CITIZENS’ BOND                                    Therese Gain                      March 5, 2008
OVERSIGHT COMMITTEE

This is the report for the period of January 31, 2008 to February 29, 2008.

1.      STATUS OVERVIEW:

Facilities Construction staff is currently involved in completing the punchlist and closeout of construction
activities for those projects that are substantially complete. Some projects, such as the Adult School
Alteration project are continuing through the phases during the school year.

Four Alteration project scheduled for summer 2008 construction have been issued for bids. Bids have
been received for three of them and they have been recommended for award.
They are the Millard Elementary School Alteration, Patterson Elementary School Alteration and the
Centerville Junior High School Alteration project.

We hope that we are starting to see a trend toward lower bids. The first bids received, for the Millard
Alteration were within the 40% escalation presented to the Board, but were still quite high. The second
bids, for the Patterson Alteration, were slightly better, but still escalated from the original budget. The
third bid received, for the Centerville Alteration, was well within the original budget.

Bids for the Brookvale Elementary School Alteration Project will be opened March 18th.
We continue to monitor projects that have been submitted to DSA for plan review.

The written report on the financial and performance audit on bond project activity during the 2006-07
Fiscal Year was reviewed at the February 6th CBOC meeting. It was presented to the School Board at
their February 27th meeting.

An item was submitted to the School Board for review at the March 12th meeting to re-affirm the five
CBOC members whose terms expire as of March 2008.

The tentative schedule for pending project presentations the school year is as follows:

Meeting Date             Presentation Topic                Location

February 6, 2008         Bond Audit Report                 District Office Board Room
March 5, 2008            Adult School Projects             Adult School Multi-Use Building - Kitchen
April 2, 2008            Financial Tracking                District Office Board Room
May 7, 2008              Patterson Projects                Patterson Elementary School
June 4, 2008             Millard Projects                  Millard Elementary School
2.      PROJECT BIDS:

Issued for Bids:
Brookvale Elementary School Alteration, bids due March 18 at 2:00 pm.

Bid Openings:
Patterson Elementary School, bids received February 5, 2008 at 2:00 pm.
Centerville Junior High Alteration, bids received February 12, 2008 at 2:00 pm.

Contract Awards Pending:
Millard Elementary School Alteration.
Patterson Elementary School.
Centerville Junior High Alteration.


3.      SCHEDULE/PHASING ISSUES:

No specific issues at this time.

4.      FUNDING ISSUES:

The Bond Project Cash Flow Report was updated and was presented to the Board in November.
A copy was previously provided to all CBOC members.

5.      HANDOUTS:

Bond Project Cost Summary Report, dated February 29, 2008

Review of Bids Received (to Secretary only)
Millard Elementary School Alteration.
Patterson Elementary School.
Centerville Junior High Alteration.

Notice to Bidders (to Secretary only)
Brookvale Elementary School Alteration, bids due March 18 at 2:00 pm.

6.      GLOSSARY:

        BIP              Bond Implementation Plan
        Bond Phase 1     May 2002 – August 2005
        Bond Phase 2     September 2005 – September 2008
        CBOC             Citizens’ Bond Oversight Committee
        CDE              California Department of Education
        DSA              Division of the State Architect
        FEMA             Federal Emergency Management Agency
        FUSD             Fremont Unified School District
        OPSC             Office of Public School Construction
        Proposition 55   State School Bond Initiative, passed March 2, 2004
        SAB              State Allocation Board
                             FREMONT UNIFIED SCHOOL DISTRICT
                                  FREMONT, CALIFORNIA

                                     DISTRICT MEMORANDUM

Office of Origin                                  Subject
FACILITIES MANAGEMENT                             MONTHLY BOND STATUS REPORT

TO:                                               FROM:                            DATE:
CITIZENS’ BOND                                    Therese Gain                     April 2, 2008
OVERSIGHT COMMITTEE

This is the report for the period of March 1, 2008 to March 31, 2008.

1.      STATUS OVERVIEW:

Facilities Construction staff is currently involved in completing the punchlist and closeout of construction
activities for those projects that are substantially complete.

Several projects scheduled for summer 2008 construction have been issued for bids. They are listed
below in Section 2.

Bids were received for the Brookvale Elementary School Alteration Project on March 18th, and the project
has been recommended for award. The project bid was within the original budget.

We continue to monitor projects that have been submitted to DSA for plan review.

An item was submitted to the School Board for review at the March 12th meeting to re-affirm the five
CBOC members whose terms expire as of March 2008. The reappointments were affirmed.

The tentative schedule for pending project presentations the school year is as follows:
Meeting Date           Presentation Topic             Location

February 6, 2008         Bond Audit Report                District Office Board Room
March 5, 2008            Adult School Projects            Adult School Multi-Use Building - Kitchen
April 2, 2008            Financial Tracking               District Office Board Room
May 7, 2008              Patterson Projects               Patterson Elementary School
June 4, 2008             Millard Projects                 Millard Elementary School

2.      PROJECT BIDS:

Issued for Bids:
Warwick Elementary School Alteration, bids due April 22 at 2:00 pm.
Irvington Turf Rehabilitation, bids due April 22 at 3:00 pm.
Grimmer Elementary Traffic Separation, bids due May 1 at 2:00 pm.
Mission Valley Elementary, bids due at 2:00 pm.
Vallejo Mill Alteration, bids due May 6 at 3:00 pm.
Weibel Elementary Alteration, bids due May 7 at 2:00 pm.

Bid Openings:
Brookvale Elementary School Alteration, bids due March 18 at 2:00 pm.

Contract Awards Pending:
Brookvale Elementary School Alteration.
3.      SCHEDULE/PHASING ISSUES:

No specific issues at this time.

4.      FUNDING ISSUES:

No issues at this time. The Bond Project Cash Flow Report was updated and was presented to the Board
in November. A copy was previously provided to all CBOC members.

5.      HANDOUTS:

Bond Project Cost Summary Report, dated March 31, 2008

Review of Bids Received (to Secretary only)
Brookvale Elementary School Alteration.

Notice to Bidders (to Secretary only)
Warwick Elementary School Alteration, bids due April 22 at 2:00 pm.
Irvington Turf Rehabilitation, bids due April 22 at 3:00 pm.
Grimmer Elementary Traffic Separation, bids due May 1 at 2:00 pm.
Mission Valley Elementary, bids due at 2:00 pm.
Vallejo Mill Alteration, bids due May 6 at 3:00 pm.
Weibel Elementary Alteration, bids due May 7 at 2:00 pm.

6.      GLOSSARY:

        BIP              Bond Implementation Plan
        Bond Phase 1     May 2002 – August 2005
        Bond Phase 2     September 2005 – September 2008
        CBOC             Citizens’ Bond Oversight Committee
        CDE              California Department of Education
        DSA              Division of the State Architect
        FEMA             Federal Emergency Management Agency
        FUSD             Fremont Unified School District
        OPSC             Office of Public School Construction
        Proposition 55   State School Bond Initiative, passed March 2, 2004
        SAB              State Allocation Board
                             FREMONT UNIFIED SCHOOL DISTRICT
                                  FREMONT, CALIFORNIA

                                     DISTRICT MEMORANDUM

Office of Origin                                  Subject
FACILITIES MANAGEMENT                             MONTHLY BOND STATUS REPORT

TO:                                               FROM:                            DATE:
CITIZENS’ BOND                                    Therese Gain                     May 7, 2008
OVERSIGHT COMMITTEE

This is the report for the period of March 31, 2008 to April 30, 2008.

1.      STATUS OVERVIEW:

Facilities Construction staff is currently involved in completing the punchlist and closeout of construction
activities for those projects that are substantially complete.

Several projects scheduled for summer 2008 construction have been issued for bids. They are listed
below in Section 2.

Bids were received for the following projects:
Grimmer Traffic Separation Project, Irvington Turf & Irrigation Project, Warwick Elementary School
Alteration Project, Mission Valley Elementary, and Vallejo Mill Alteration, and the projects have been
recommended for award. The project bids were all either within the original budget, or within the
adjusted budget shown to the Board as of November 2007.

We continue to monitor projects that have been submitted to DSA for plan review.

The tentative schedule for pending project presentations the school year is as follows:
Meeting Date           Presentation Topic             Location

May 7, 2008              Patterson Projects               Patterson Elementary School
June 4, 2008             Millard Projects                 Millard Elementary School


2.      PROJECT BIDS:

Issued for Bids:

Weibel Elementary School Alteration, bids due May 14, 2008 at 2:00 PM.
Warm Springs Elementary School Alteration, bids due May 15, 2008 at 2:00 PM.
Hirsch Elementary School/Horner Junior High School Alteration, bids due May 22, 2008 at 2:00 PM.
Leitch Elementary School Alteration, bids due June 3, 2008, at 2:00 PM.

Bid Openings:

Warwick Elementary School Alteration, bids received April 22 at 2:00 pm.
Irvington Turf Rehabilitation, bids received April 22 at 3:00 pm.
Grimmer Elementary Traffic Separation, bids received May 1 at 2:00 pm.
Mission Valley Elementary, bids received at 2:00 pm.
Vallejo Mill Alteration, bids received May 6 at 3:00 pm.
Contract Awards Pending:

Grimmer Elementary Traffic Separation
Irvington Turf Rehabilitation
Mission Valley Elementary Alteration
Vallejo Mill Elementary Alteration
Warwick Elementary School Alteration

3.      SCHEDULE/PHASING ISSUES:

Several projects will not be able to go to construction during the 2008 summer, due to delays in approval
by DSA and delays at PG&E in engineering of new electrical service equipment. These projects will be
bid as soon as possible and the construction schedule determined once a contractor is selected.

4.      FUNDING ISSUES:

No issues at this time. The Bond Project Cash Flow Report was updated and was presented to the Board
in November. A copy was previously provided to all CBOC members.

PG&E Rebates were received in the 2003 PG&E Program year for Chadbourne Elementary School Multi-
Use Building, Durham Elementary School Multi-Use Building, and Mission Valley Elementary School
Multi-Use Building. These rebates have been indicated in the Resources Section on the current Bond
Project Cost Summary.

Applications for PG&E Rebates have been submitted for the following projects, which were not
successful in meeting the threshold requirements:
        Cabrillo Elementary Alteration
        Robertson High Alteration
        Kennedy High Alteration
        Maloney Elementary Alteration
        Azevada Elementary Alteration
        Gomes Elementary Alteration
        Hopkins Junior High Alteration
        Mowry Adult School Multi-Use Building

Projects for which PG&E Rebate applications are still pending are:
        Ardenwood Elementary Alteration
        American High School Student Dining,
        Irvington High School Student Dining,
        Kennedy High School Student Dining,
        Mission San Jose High Alteration,
        Mission San Jose High School Student Dining,
        Niles Elementary Alteration,
        Thornton Junior High Multi-Use Building,
        Weibel Elementary Alteration


5.      HANDOUTS:

Bond Project Cost Summary Report, dated April 30, 2008
Review of Bids Received (to Secretary only)
Centerville Junior High Alteration
Irvington High Turf Irrigation
Warwick Elementary Alteration
Grimmer Elementary Traffic Separation, bids received May 1 at 2:00 pm.
Mission Valley Elementary, bids received at 2:00 pm.
Vallejo Mill Alteration, bids received May 6 at 3:00 pm.

Notice to Bidders (to Secretary only)

Weibel Elementary School Alteration, bids due May 14, 2008 at 2:00 PM.
Warm Springs Elementary School Alteration, bids due May 15, 2008 at 2:00 PM.
Hirsch Elementary School/Horner Junior High School Alteration, Bids due May 22, 2008 at 2:00 PM.
Leitch Elementary School Alteration, bids due June 3, 2008, at 2:00 PM.

6.     GLOSSARY:

       BIP              Bond Implementation Plan
       Bond Phase 1     May 2002 – August 2005
       Bond Phase 2     September 2005 – September 2008
       CBOC             Citizens’ Bond Oversight Committee
       CDE              California Department of Education
       DSA              Division of the State Architect
       FEMA             Federal Emergency Management Agency
       FUSD             Fremont Unified School District
       OPSC             Office of Public School Construction
       Proposition 55   State School Bond Initiative, passed March 2, 2004
       SAB              State Allocation Board
                              FREMONT UNIFIED SCHOOL DISTRICT
                                   FREMONT, CALIFORNIA

                                      DISTRICT MEMORANDUM

Office of Origin                                   Subject
FACILITIES MANAGEMENT                              MONTHLY BOND STATUS REPORT

TO:                                                FROM:                             DATE:
CITIZENS’ BOND                                     Therese Gain                      June 4, 2008
OVERSIGHT COMMITTEE

This is the report for the period of May 1, 2008 to May 31, 2008.

1.      STATUS OVERVIEW:

Facilities Construction staff is currently involved in completing the punchlist and closeout of construction
activities for those projects that are substantially complete.

We are winding up the bidding for projects scheduled for summer 2008 construction.
Bids were received for the following projects:
Weibel Elementary School Alteration, Warm Springs Elementary School Alteration,
Hirsch Elementary School/Horner Junior High School Alteration, and Leitch Elementary School
Alteration (June 3rd). The Weibel Elementary and Leitch Elementary Alteration projects were both
within the original approved budget, not requiring escalation.

The low bid on the Warm Springs Elementary Alteration was over even the escalated budget due to code
issues raised by DSA in plan check. The bid was presented to the Board of Education on May 28th and
permission granted to supplement the project.

There was only one bid received for the Hirsch/ Horner Alteration project. That bid was rejected and the
project will be re-bid at a later date. We have been investigating the situation and believe that the size of
the project and the late bid date contributed to the lack of bidders. In particular, we are being told that the
General Contractors could not find a suitable pool of subcontractors.

We continue to monitor projects that have been submitted to DSA for plan review.
Those projects that are still undergoing DSA plan review will be bid at the end of the summer or in the
Fall. Some work may be done during the school year, if possible. The remaining work will be done in
the summer of 2009.

The Mission High School Student Dining project was just recently approved by DSA and will be going
out to bid shortly.

The tentative schedule for pending project presentations the school year is as follows:
Meeting Date           Presentation Topic             Location

June 4, 2008             Millard Projects                   Millard Elementary School
July 2, 2008             Board Report & Cashflow            District Office
August 20, 2008          Summer Construction                District Office
October 1, 2008          TBD
Nov. 5, 2008             TBD
Dec 3, 2008              TBD
2.      PROJECT BIDS:

Issued for Bids:

No Bond projects issued for bids this period.

Bid Openings:

Weibel Elementary School Alteration, bids received May 14, 2008 at 2:00 PM.
Warm Springs Elementary School Alteration, bids received May 15, 2008 at 2:00 PM.
Hirsch Elementary School/Horner Junior High School Alteration (projects bid together),
bids received May 22, 2008 at 2:00 PM.
Leitch Elementary School Alteration, bids received June 3, 2008, at 2:00 PM.

Contract Awards Pending:

Grimmer Elementary Traffic Separation
Irvington Turf Rehabilitation
Mission Valley Elementary Alteration
Vallejo Mill Elementary Alteration
Warwick Elementary School Alteration

3.      SCHEDULE/PHASING ISSUES:

Several projects will not be able to go to construction during the 2008 summer, received to delays in
approval by DSA and delays at PG&E in engineering of new electrical service equipment. These projects
will be bid as soon as possible and the construction schedule determined once a contractor is selected.

4.      FUNDING ISSUES:

No issues at this time, other than noted above related to bids received.

The most recent Bond Project Cash Flow Report update and was presented to the Board in November.
A new update will be presented to the Board in late June or July to reflect this summer’s bids.

PG&E Rebates were received in the 2003 PG&E Program year for Chadbourne Elementary School Multi-
Use Building, Durham Elementary School Multi-Use Building, and Mission Valley Elementary School
Multi-Use Building. These rebates have been indicated in the Resources Section on the current Bond
Project Cost Summary. The actual revenue has been credited against the specific projects.

Projects for which PG&E Rebate applications are still pending are:
        Ardenwood Elementary Alteration
        American High School Student Dining,
        Irvington High School Student Dining,
        Kennedy High School Student Dining,
        Mission San Jose High Alteration,
        Mission San Jose High School Student Dining,
        Niles Elementary Alteration,
        Thornton Junior High Multi-Use Building,
        Weibel Elementary Alteration
5.      HANDOUTS:

Bond Project Cost Summary Report, dated May 31, 2008

Review of Bids Received (to Secretary only)

Weibel Elementary School Alteration.
Warm Springs Elementary School Alteration.
Hirsch Elementary School/Horner Junior High School Alterations.
Leitch Elementary School Alteration.

Board Agenda Item B&F 11, dated May 28, 2008:
Approve Supplemental Project Funding from 2002 Health & Safety Bond Funds –
Warm Springs Elementary School Alteration

Notice to Bidders (to Secretary only)

None this period.

6.      GLOSSARY:

        BIP              Bond Implementation Plan
        Bond Phase 1     May 2002 – August 2005
        Bond Phase 2     September 2005 – September 2008
        CBOC             Citizens’ Bond Oversight Committee
        CDE              California Department of Education
        DSA              Division of the State Architect
        FEMA             Federal Emergency Management Agency
        FUSD             Fremont Unified School District
        OPSC             Office of Public School Construction
        Proposition 55   State School Bond Initiative, passed March 2, 2004
        SAB              State Allocation Board
                          FREMONT UNIFIED SCHOOL DISTRICT
                               FREMONT, CALIFORNIA

                                  DISTRICT MEMORANDUM

Office of Origin                             Subject
FACILITIES MANAGEMENT                        MONTHLY BOND STATUS REPORT

TO:                                          FROM:                         DATE:
CITIZENS’ BOND                               Therese Gain                  August 15, 2008
OVERSIGHT COMMITTEE

This is the report for the period of July 1, 2008 to August 15, 2008.

1.     STATUS OVERVIEW:

Facilities Construction staff is currently involved in management of the summer construction
activity. Under the Bond Program we have in construction two high school dining facilities,
eleven alteration projects, one traffic separation project, and the Irvington High turf
replacement. Not yet underway are several other turf projects which will start later in the
summer or early Fall.

The Mission High School Student Dining project and Kitchen alteration were bid in July and
recommended for contract award. The Student Dining project was awarded to the second
lowest bidder on the basis of irregularities with the apparent low bid. The low bidder failed to
complete their bid form as directed in the bid instructions. Both projects are part of the same
bond scope and budget.

The combined contract awards result in a project budget that is within the estimate presented
to the Board as of the July 2008 Bond Cash Flow Projections. That projection estimated a 40%
escalation for this project.

We continue to monitor projects that have been submitted to DSA for plan review.
Those projects that are still undergoing DSA plan review will be bid at the end of the summer or
in the Fall. Some work may be done during the school year, if possible. The remaining work
will be done in the summer of 2009.

The tentative schedule for pending project presentations the school year is as
follows:
Meeting Date       Presentation Topic        Location

August 20, 2008       Summer Construction            District Office
October 1, 2008       Audit Review                   District Office
Nov. 5, 2008          TBD
Dec 3, 2008           TBD
2.     PROJECT BIDS:

Issued for Bids:
No Bond projects issued for bids this period.

Bid Openings:
Mission San Jose High School Kitchen Alteration, bids received July 10, 2008 at 2:00 PM.
Mission San Jose High School Student Dining Facility, bids received July 17, 2008 at 2:00 PM

Contract Awards Pending:
All bid projects bid to date have been recommended for awarded.


3.     SCHEDULE/PHASING ISSUES:

Several projects will not be able to go to construction during the 2008 summer, due to delays in
approval by DSA and delays at PG&E in engineering of new electrical service equipment. These
projects will be bid as soon as it is practical and the construction schedule determined once a
contractor is selected.


4.     FUNDING ISSUES:

No issues at this time.

The most recent Bond Project Cash Flow Report update was presented to the Board on July 16;
that update reflected this summer’s bids.

PG&E Rebates were received in the 2003 PG&E Program year for Chadbourne Elementary
School Multi-Use Building, Durham Elementary School Multi-Use Building, and Mission Valley
Elementary School Multi-Use Building. These rebates have been indicated in the Resources
Section on the current Bond Project Cost Summary. The actual revenue has been credited
against the specific projects.

Projects for which PG&E Rebate applications are still pending are:
       Ardenwood Elementary Alteration,               American High School Student Dining,
       Irvington High School Student Dining,          Kennedy High School Student Dining,
       Mission San Jose High Alteration,              Mission San Jose High Student Dining,
       Niles Elementary Alteration,                   Thornton Junior High Multi-Use Building,
       Weibel Elementary Alteration
5.     HANDOUTS:

Bond Project Cost Summary Report, dated July 31, 2008

Review of Bids Received (to Secretary only)
Mission San Jose High School Kitchen Alteration, bids due July 10, 2008 at 2:00 PM.
Mission San Jose High School Student Dining Facility, bids due July 17, 2008 at 2:00 PM

Notice to Bidders (to Secretary only)
None this period.

6.     GLOSSARY:

       BIP               Bond Implementation Plan
       Bond Phase 1      May 2002 – August 2005
       Bond Phase 2      September 2005 – September 2008
       CBOC              Citizens’ Bond Oversight Committee
       CDE               California Department of Education
       DSA               Division of the State Architect
       FEMA              Federal Emergency Management Agency
       FUSD              Fremont Unified School District
       OPSC             Office of Public School Construction
       Proposition 55   State School Bond Initiative, passed March 2, 2004
       SAB              State Allocation Board
                          FREMONT UNIFIED SCHOOL DISTRICT
                               FREMONT, CALIFORNIA

                                  DISTRICT MEMORANDUM

Office of Origin                                Subject
FACILITIES MANAGEMENT                           MONTHLY BOND STATUS REPORT

TO:                                             FROM:                      DATE:
CITIZENS’ BOND                                  Therese Gain               October 1, 2008
OVERSIGHT COMMITTEE

This is the report for the period of August 15, 2008 to September 25, 2008.

1.     STATUS OVERVIEW:

Facilities Construction staff is currently involved in management of the ongoing construction
projects and completion activities for those that were done during the summer.
Continuing in construction are the three high school dining facilities and two turf replacement
projects.

The Mission High School Student Dining project and Kitchen alteration are both under.
Both projects are part of the same bond scope and budget.

We continue to monitor projects that have been submitted to DSA for plan review and
evaluating them for bidding. Some work may be done during the school year, if possible. The
remaining work will be done in the summer of 2009.

The tentative schedule for pending project presentations the school year is as
follows:
Meeting Date       Presentation Topic        Location

October 1, 2008       Audit Review                    District Office
Nov. 5, 2008          Warm Springs Projects           Warm Springs ES Library
Dec 3, 2008           Chadbourne Projects             Chadbourne Elementary
Jan 7, 2009           Parkmont Projects               Parkmont Elementary
Feb 4, 2009           Audit 2007-08                   District Office
Mar 4, 2009           Hirsch-Horner Projects          Horner Junior High
April 1, 2009         American Dining                 American High
May 6, 2009           Kennedy Dining                  Kennedy High
June 3, 2009          Mission High Dining             Mission High

2.     PROJECT BIDS:

Issued for Bids:
No Bond projects issued for bids this period.

Bid Openings:
No bid openings for Bond projects this period.

Contract Awards Pending:
All bid projects bid to date have been recommended for awarded.
3.     SCHEDULE/PHASING ISSUES:

Several projects were not be able to go to construction during the 2008 summer, due to delays
in approval by DSA and delays at PG&E in engineering of new electrical service equipment. As
these projects are approved by DSA they are evaluated for bidding. They will be bid as soon as
it is practical and the construction schedule determined once a contractor is selected.

4.     FUNDING ISSUES:

No issues at this time.

The most recent Bond Project Cash Flow Report update was presented to the Board on July 16.
That update reflected this summer’s bids.

PG&E Rebates were received in the 2003 PG&E Program year for Chadbourne Elementary
School Multi-Use Building, Durham Elementary School Multi-Use Building, and Mission Valley
Elementary School Multi-Use Building. These rebates have been indicated in the Resources
Section on the current Bond Project Cost Summary. The actual revenue has been credited
against the specific projects.

Projects for which PG&E Rebate applications are still pending are:
       Ardenwood Elementary Alteration,               American High School Student Dining,
       Irvington High School Student Dining,          Kennedy High School Student Dining,
       Mission San Jose High Alteration,              Mission San Jose High Student Dining,
       Niles Elementary Alteration,                   Thornton Junior High Multi-Use Building,
       Weibel Elementary Alteration

5.     HANDOUTS:

Bond Project Cost Summary Report, dated September 25, 2008

Review of Bids Received (to Secretary only)
None this period.

Notice to Bidders (to Secretary only)
None this period.

6.     GLOSSARY:

       BIP                 Bond Implementation Plan
       Bond Phase 1        May 2002 – August 2005
       Bond Phase 2        September 2005 – September 2008
       CBOC                Citizens’ Bond Oversight Committee
       CDE                 California Department of Education
       DSA                 Division of the State Architect
       FEMA                Federal Emergency Management Agency
       FUSD                Fremont Unified School District
       OPSC               Office of Public School Construction
       Proposition 55     State School Bond Initiative, passed March 2, 2004
       SAB                State Allocation Board
                          FREMONT UNIFIED SCHOOL DISTRICT
                               FREMONT, CALIFORNIA

                                  DISTRICT MEMORANDUM

Office of Origin                             Subject
FACILITIES MANAGEMENT                        MONTHLY BOND STATUS REPORT

TO:                                          FROM:                          DATE:
CITIZENS’ BOND                               Therese Gain                   November 4, 2008
OVERSIGHT COMMITTEE

This is the report for the period of September 25, 2008 to October 31, 2008.

1.     STATUS OVERVIEW:

Facilities Construction staff is currently involved in management of the ongoing construction
projects and completion activities for those that were done during the summer. We are
proceeding to close out projects as we are able.

Continuing in construction are the three high school dining facilities and two turf replacement
projects. The Mission High School Student Dining project and Kitchen alteration are both
underway. Both projects are part of the same bond scope and budget.

We are completing the plan checking of the projects that are being prepared for bidding and
developing bid schedules. Some work may be done during the school year, if possible. The
remaining work will be done in the summer of 2009.

The proposal for conducting the audit of the bond projects for the fiscal year just past will be
reviewed with the committee at the November 5th meeting.

The CBOC is scheduled to present a report to the Board on the status of the Bond program at
the November 12th Board of Trustees meeting. A draft copy of the agenda item is provided for
the CBOC members at the November 5th committee meeting.

The tentative schedule for pending project presentations the school year is as
follows:
Meeting Date       Presentation Topic        Location

Nov. 5, 2008          Warm Springs Projects          Warm Springs ES Library
Dec 3, 2008           Chadbourne Projects            Chadbourne Elementary
Jan 7, 2009           Parkmont Projects              Parkmont Elementary
Feb 4, 2009           Audit 2007-08                  District Office
Mar 4, 2009           Hirsch-Horner Projects         Horner Junior High
April 1, 2009         American Dining                American High
May 6, 2009           Kennedy Dining                 Kennedy High
June 3, 2009          Mission High Dining            Mission High
2.     PROJECT BIDS:

Issued for Bids:
No Bond projects issued for bids this period.

Bid Openings:
No bid openings for Bond projects this period.

Contract Awards Pending:
All bid projects bid to date have been recommended for awarded.

3.     SCHEDULE/PHASING ISSUES:

Several projects were not be able to go to construction during the summer of 2008, due to
delays in approval by DSA and delays at PG&E in engineering of new electrical service
equipment. As these projects are approved by DSA they are evaluated for bidding. They will
be bid as soon as it is practical and the construction schedule determined once a contractor is
selected.

4.     FUNDING ISSUES:

No issues at this time.

The most recent Bond Project Cash Flow Report update was presented to the Board on July 16.
That update reflected the bids received for summer 2008 work.

PG&E Rebates were received in the 2003 PG&E Program year for Chadbourne Elementary
School Multi-Use Building, Durham Elementary School Multi-Use Building, and Mission Valley
Elementary School Multi-Use Building. These rebates have been indicated in the Resources
Section on the current Bond Project Cost Summary. The actual revenue has been credited
against the specific projects.

Projects for which PG&E Rebate applications are still pending are:
       Ardenwood Elementary Alteration,               American High School Student Dining,
       Irvington High School Student Dining,          Kennedy High School Student Dining,
       Mission San Jose High Alteration,              Mission San Jose High Student Dining,
       Niles Elementary Alteration,                   Thornton Junior High Multi-Use Building,
       Weibel Elementary Alteration

5.     HANDOUTS:

Bond Project Cost Summary Report, dated October 31, 2008

Review of Bids Received (to Secretary only)
None this period.

Notice to Bidders (to Secretary only)
None this period.
6.   GLOSSARY

     BIP                  Bond Implementation Plan
     Bond Phase 1         May 2002 – August 2005
     Bond Phase 2         September 2005 – December 2008
     CBOC                 Citizens’ Bond Oversight Committee
     CDE                  California Department of Education
     Closed Projects      Projects for which a Notice of Completion has been filed and the
                          majority of financial transactions have been completed
     Completed Projects   Projects for which the contract work is essentially complete
     DSA                  Division of the State Architect
     FEMA                 Federal Emergency Management Agency
     FUSD                 Fremont Unified School District
     OPSC                 Office of Public School Construction
     Proposition 55       State School Bond Initiative, passed March 2, 2004
     SAB                  State Allocation Board
                          FREMONT UNIFIED SCHOOL DISTRICT
                               FREMONT, CALIFORNIA

                                  DISTRICT MEMORANDUM

Office of Origin                             Subject
FACILITIES MANAGEMENT                        MONTHLY BOND STATUS REPORT

TO:                                          FROM:                         DATE:
CITIZENS’ BOND                               Therese Gain                  December 3, 2008
OVERSIGHT COMMITTEE

This is the report for the period of October 31, 2008 to November 24, 2008.

1.     STATUS OVERVIEW:

Facilities Construction staff is currently involved in management of the ongoing construction
projects and completion activities for those that were done during the summer. We are
proceeding to close out projects as we are able.

Continuing in construction are the three high school dining facilities and two turf replacement
projects. The Mission High School Student Dining project and Kitchen alteration are both
underway. Both projects are part of the same bond scope and budget.

We are completing the plan checking of the projects that are being prepared for bidding and
developing bid schedules. Some work may be done during the school year, if possible. The
remaining work will be done in the summer of 2009.

The proposal for conducting the audit of the bond projects for the fiscal year just past, as
reviewed by the committee at the November 5th meeting will be presented to the Board on
December 12th.

The CBOC presentation to the Board on the status of the Bond program was given at the
November 12th Board of Trustees meeting. The report was well received by the Board.

The tentative schedule for pending project presentations the school year is as
follows:
Meeting Date       Presentation Topic        Location

Dec 3, 2008           Chadbourne Projects           Chadbourne Elementary
Jan 7, 2009           Parkmont Projects             Parkmont Elementary
Feb 4, 2009           Audit 2007-08                 District Office
Mar 4, 2009           Hirsch-Horner Projects        Horner Junior High
April 1, 2009         American Dining               American High
May 6, 2009           Kennedy Dining                Kennedy High
June 3, 2009          Mission High Dining           Mission High
2.     PROJECT BIDS:

Issued for Bids:
No Bond projects issued for bids this period.

Bid Openings:
No bid openings for Bond projects this period.

Contract Awards Pending:
None Contract Awards for Bond projects this period.


3.     SCHEDULE/PHASING ISSUES:

No issues at this time.
Bidding schedules are being prepared for the spring and summer 2009 projects.

4.     FUNDING ISSUES:

No issues at this time.

The most recent Bond Project Cash Flow Report update was presented to the Board on July 16.
That update reflected the bids received for summer 2008 work.

PG&E Rebates were received in the 2003 PG&E Program year for Chadbourne Elementary
School Multi-Use Building, Durham Elementary School Multi-Use Building, and Mission Valley
Elementary School Multi-Use Building. These rebates have been indicated in the Resources
Section on the current Bond Project Cost Summary. The actual revenue has been credited
against the specific projects.

Projects for which PG&E Rebate applications are still pending are:
       Ardenwood Elementary Alteration,               American High School Student Dining,
       Irvington High School Student Dining,          Kennedy High School Student Dining,
       Mission San Jose High Alteration,              Mission San Jose High Student Dining,
       Niles Elementary Alteration,                   Thornton Junior High Multi-Use Building,
       Weibel Elementary Alteration

5.     HANDOUTS:

Bond Project Cost Summary Report, dated November 24, 2008

Review of Bids Received (to Secretary only)
None this period.

Notice to Bidders (to Secretary only)
None this period.
6.   GLOSSARY

     BIP                  Bond Implementation Plan
     Bond Phase 1         May 2002 – August 2005
     Bond Phase 2         September 2005 – December 2008
     CBOC                 Citizens’ Bond Oversight Committee
     CDE                  California Department of Education
     Closed Projects      Projects for which a Notice of Completion has been filed and the
                          majority of financial transactions have been completed
     Completed Projects   Projects for which the contract work is essentially complete
     DSA                  Division of the State Architect
     FEMA                 Federal Emergency Management Agency
     FUSD                 Fremont Unified School District
     OPSC                 Office of Public School Construction
     Proposition 55       State School Bond Initiative, passed March 2, 2004
     SAB                  State Allocation Board

				