Document Sample
scope of work template
							Finance System Replacement Project
       Communication Strategy




 Sponsor:    Richard Cryer
Approvers:   Finance System Project Board


  Authors:   Bridget Boylan
1     Distribution List
1.1    Draft
         Richard Cryer                        Project Sponsor
         Roy Bent                             Project Quality Assurance
         Jeremy Ensor                         Project Training Manager
         Kirsten Gillingham                   Project Change Manager
         Mike Turner                          Project systems Coordinator
         Andy Williamson                      University of London Communications Officer



1.2    Final
         Project Board members
         Project Team
         Process Owners
         User Steering Group
         Purchasing Steering Group



1.3    Project Office Information
         Project Title                       Finance System Project
         Document Title                      Finance System Project Communication Strategy
         Contact Name                        Bridget Boylan, Project Manager
                                                          th
                                             Room 415, 4 floor, Stewart House
                                             Russell Square, London, W1W 6UP
                                             Tel: 020 7 Ext 2870


1.4    Change History
              Version         Date Issued     Issued By                     Reason for Change
              Draft 1.1        03/12/07     Bridget Boylan                      First draft




Author: Bridget Boylan                      Page 2 of 22                              Date: 03/12/2007
Version 1.1
Table of Contents

1    DISTRIBUTION LIST ..................................................................................... 2

2    INTRODUCTION ............................................................................................ 4

3    PURPOSE ...................................................................................................... 4

4    ASSUMPTIONS AND GUIDING PRINCIPLES .............................................. 5

5    COMMUNICATION APPROACH ................................................................... 5

6    SCOPE ........................................................................................................... 6

7    METHODS OF COMMUNICATION .............................................................. 11

8    COMMUNICATION STAGES ....................................................................... 13

9    COMMUNICATORS & AUDIENCE .............................................................. 14

10      COMMUNICATION ACTIVITIES ............................................................... 16

APPENDIX 1 – COMMUNICATIONS PLAN ........................................................ 18




Author: Bridget Boylan                              Page 3 of 22                                     Date: 03/12/2007
Version 1.1
2    Introduction
     This document states the communication strategy for the successful implementation of the Agresso
     system by the Finance System Replacement Project and defines all the stakeholders, their
     information needs and the methods by which accurate information will be delivered to them in the
     most effective way.



3    Purpose
     Clear, timely and effective communications will enable the project team to:
        ensure that the principal stakeholders are aware of, prepared for and committed to the
         implementation of the project;

        communicate information needed by all Divisions and Institutes that are affected by or need to
         know about the project’s progress towards its outcomes, to gain their support and commitment to
         the implementation;

        to deliver the benefits of the project and to encourage staff to speak positively about the Agresso
         system to their peers within and outside the University;

        communicate to users the direct requirements for using the system and promote the need for staff
         to make changes due to the implementation of the project and encourage them to embrace such
         changes;

        keep up to date at all times with users’ requirements and make sure the project aims and
         objectives continue to meet these needs in the light of both changes to users’ needs and as new
         information becomes apparent as the project develops;

        inform department managers and consultants to the project of all progress and developments so
         that the best available help can be received when required;

        enable appropriate action to be taken on an informed basis by those responsible for managing the
         project so that appropriate decisions can be made and the best level of support can be offered to
         the project at the right time and in the right way;

        It should be noted that if any of the users or any staff that may be affected by the project are not
        communicated to effectively, or understand the reasons for the Agresso implementation and
        resultant change this will bring, they are unlikely to support it.
        This will inevitably result in the following:
                 the change will not be fully adopted and the successful implementation will not be realised;
                 a successful implementation will not be sustained over time;
                 signs of resistance will emerge.




Author: Bridget Boylan                          Page 4 of 22                          Date: 03/12/2007
Version 1.1
4    Assumptions and Guiding Principles
     In undertaking this Communications Strategy the following assumptions and guiding principles have
     been applied:
             a cohesive, embedded communication approach is present within the University at all levels of
              hierarchy and is fully committed to by Senior Management;

             communications will be driven through the Senior Management Group within the University, who
              will be responsible for cascading communications, using generic material adapted to suit their
              functional areas;

             subject matter experts will be available to present or support when needed for communications
              activities (e.g. workshops, road shows etc.);

             communications as an integrated part of the rollout will be part of everyone’s role;

             communication must be two-way process;

             the key stakeholders will be visible in their support and commitment and this will be
              communicated to all levels in the University;

             the infrastructure will support the timely and effective distribution of communications; and,

             evaluation of communication effectiveness will be undertaken at appropriate stages throughout
              the roll out.




5    Communication Approach
     Effective communication should start at the top obtaining buy-in from key senior executives within the
     University. This will provide the platform for reinforcing key messages enabling senior management
     to demonstrate support for the roll out. This exhibits to staff that the commitment to change comes
     from their most senior executive and the management within the Divisions and Institutes. The picture
     below demonstrates this process:

                                         • High level messages
                       Senior            • Show support and commitment
                      Executives         • Importance to the University

                                v
                                                      • High level messages
                                  Senior              • Show support and commitment
                                Management            • Importance to the Divisions and Institutes



                                                                   • Detailed messages
                                       Middle Managers/            • Show support and commitment
                                         Team Leaders              • (champion) to team and individuals
                                                                     Importance



                                                                          • Detailed messages
                                                      Staff               • Show support and commitment
                                                                               (Champion and promote to peers)
                                                                           • Importance to self and peers




Author: Bridget Boylan                           Page 5 of 22                                          Date: 03/12/2007
Version 1.1
6    Scope
     The communications plan covers the implementation phase (Phase 2) of the Finance System
     Replacement Project. The project objectives have been agreed by the Project Board and are as
     stated in the Project Initiation Document. A business case and a project plan have also been agreed
     by the Board.
     The document identifies the stakeholders and the communication needs. The table in Appendix 1
     details the means and frequency of delivery of information to the different stakeholder groups.
     The following table highlights the stakeholders that need to be kept informed of progress and
     developments on the project in ways appropriate to each stakeholder’s needs:


        Stakeholder                                    Communication Needs
          Groups
       Central Offices
       Finance Division   The new Agresso system will be critical to the role of all Users within the
                          Finance division.
                          The new business processes will bring changes to User roles. The changes in
                          role will be managed through the Change Strategy which will identify how to
                          manage and support Users through the changes.
                          The Finance Division staff need to be kept up to date with progress on all
                          aspects of the project, so they can answer questions from other members of
                          staff about the project with confidence and authority.
       Estates            Within the Estates department, Users will need to be informed of the changes in
                          Purchasing procedures and the possibility for using the Enquiry and Reporting
                          functions in Agresso for controlling Project budgets and Cost Centre budgets.
                          Estates Users will need to be informed of the new codes to use on Expenses
                          and Purchasing Card claims.
                          The Maximo Systems Administrator will be working with the Project Team for
                          the development of interfaces between Agresso and Maximo and the
                          management of those interfaces ongoing.
                          The Director of Estates will need to be aware of the impact of the system to
                          changes in working practices of their staff and actively manage those changes
                          through working with the Project Team and the overall Change Strategy.
       Halls of           Within the Halls departments, Users will need to be informed of the changes in
       Residence          Purchasing procedures and the possibility for using the Enquiry and Reporting
                          functions in Agresso for controlling Project budgets and Cost Centre budgets.
                          Halls Users will need to be informed of the new codes to use on Expenses and
                          Purchasing Card claims.
                          The Kinetic Systems Administrator will be working with the Project Team for the
                          development of interfaces between Agresso and Kinetic and the management of
                          those interfaces ongoing.
                          The Heads of the Halls will need to be aware of the impact of the system to
                          changes in working practices of their staff and actively manage those changes
                          through working with the Project Team and the overall Change Strategy.
       Human              Within the HR department, Users will need to be informed of the changes in
       Resources          Purchasing procedures and the possibility for using the Enquiry and Reporting


Author: Bridget Boylan                      Page 6 of 22                             Date: 03/12/2007
Version 1.1
                         functions in Agresso for controlling Project budgets and Cost Centre budgets.
                         HR Users will need to be informed of the new codes to use on Expenses and
                         Purchasing Card claims.
                         The Northgate Systems Administrator will be working with the Project Team for
                         the development of interfaces between Agresso and Kinetic and the
                         management of those interfaces ongoing.
                         The Director of HR will need to be aware of the impact of the system to changes
                         in working practices of their staff and actively manage those changes through
                         working with the Project Team and the overall Change Strategy.
       Vice              Within the VC’s Office, Users will need to be informed of the changes in
       Chancellor’s      Purchasing procedures and the possibility for using the Enquiry and Reporting
       Office            functions in Agresso for controlling Project budgets and Cost Centre budgets.
                         Users in the VCs Office will need to be informed of the new codes to use on
                         Expenses and Purchasing Card claims.
                         The Vice Chancellor will need to be aware of the impact of the system to
                         changes in working practices of their staff and actively manage those changes
                         through working with the Project Team and the overall Change Strategy.
       Activities
       Libraries         Within the Libraries, Users will need to be informed of the changes in
                         Purchasing procedures and the possibility for using the Enquiry and Reporting
                         functions in Agresso for controlling Project budgets and Cost Centre budgets.
                         Users in the Libraries will need to be informed of the new codes to use on
                         Expenses and Purchasing Card claims.
                         The Innopac Systems Administrator will be working with the Project Team for
                         the development of interfaces between Agresso and Innopac and the
                         management of those interfaces ongoing.
                         Heads of the Libraries will need to be aware of the impact of the system to
                         changes in working practices of their staff and actively manage those changes
                         through working with the Project Team and the overall Change Strategy.
       Careers           Within the Careers department, Users will need to be informed of the changes in
                         Purchasing and Sales Invoicing procedures, and the possibility for using the
                         Enquiry and Reporting functions in Agresso for controlling Project budgets and
                         Cost Centre budgets.
                         Users in the Careers department will need to be informed of the new codes to
                         use on Expenses and Purchasing Card claims.
                         The Director of Careers will need to be aware of the impact of the system to
                         changes in working practices of their staff and actively manage those changes
                         through working with the Project Team and the overall Change Strategy.
       ULCC              Within ULCC, Users will need to be informed of the changes in Purchasing and
                         Sales Invoicing procedures, and the possibility for using the Enquiry and
                         Reporting functions in Agresso for controlling Project budgets and Cost Centre
                         budgets.
                         Users in ULCC will need to be informed of the new codes to use on Expenses
                         and Purchasing Card claims.
                         The Director of ULCC will need to be aware of the impact of the system to
                         changes in working practices affecting of staff and actively manage those
                         changes through working with the Project Team and the overall Change

Author: Bridget Boylan                    Page 7 of 22                            Date: 03/12/2007
Version 1.1
                         Strategy.
       The London        Within the London Deanery, Users will need to be informed of the changes in
       Deanery           Purchasing and Sales Invoicing procedures, and the possibility for using the
                         Enquiry and Reporting functions in Agresso for controlling Project budgets and
                         Cost Centre budgets.
                         Users in The London Deanery will need to be informed of the new codes to use
                         on Expenses and Purchasing Card claims.
                         The Director of The London Deanery will need to be aware of the impact of the
                         system to changes in working practices of their staff and actively manage those
                         changes through working with the Project Team and the overall Change
                         Strategy.
       School of
       Advanced
       Study
       Heads of the      Having responsibility for the financial control of their Institutes and departmental
       Institutes        budgets, these Users will need to be informed of changes to Purchasing and
                         Sales Invoicing processes, and the possibility for using the Enquiry and
                         Reporting functions in Agresso for controlling Project budgets and Cost Centre
                         budgets.
                         Heads of the Institutes will need to be informed of the new codes to use on
                         Expenses and Purchasing Card claims.
                         Heads of Institutes will need to be aware of the impact of the system to changes
                         in working practices of their staff and actively manage those changes through
                         working with the Project Team and the overall Change Strategy.
       Academic Staff    Academic staff in the Institutes will need to be informed of changes to
                         Purchasing and Sales Invoicing processes, and the possibility for using the
                         Enquiry and Reporting functions in Agresso for controlling Project budgets and
                         Cost Centre budgets.
                         Academic staff in the Institutes will need to be informed of the new codes to use
                         on Expenses and Purchasing Card claims.
                         Academic Staff will need to be aware of the impact of the system to changes in
                         working practices of Administrative staff.
                         Any changes in their roles will be managed through the Change Strategy.
       Research          Research Directors in the Institutes will need to be informed of changes to
       Directors         Purchasing and Sales Invoicing processes, and the possibility for using the
                         Enquiry and Reporting functions in Agresso for controlling Project budgets and
                         Cost Centre budgets.
                         Research directors in the Institutes will need to be informed of the new codes to
                         use on Expenses and Purchasing Card claims.
                         Research Directors will need to be aware of the impact of the system to
                         changes in working practices of Administrative staff.
                         Any changes in their roles will be managed through the Change Strategy.
       Administrative    Administrative Staff in the Institutes will need to be informed of changes to
       Staff             Purchasing and Sales Invoicing processes, and the possibility for using the
                         Enquiry and Reporting functions in Agresso for controlling Project budgets and
                         Cost Centre budgets.
                         Administrative Staff in the Institutes will need to be informed of the new codes to

Author: Bridget Boylan                     Page 8 of 22                              Date: 03/12/2007
Version 1.1
                         use on Expenses and Purchasing Card claims.
                         Any changes in their roles will be managed through the Change Strategy.
       The External
       System
       EISA              Users in EISA will need to be informed of changes to Purchasing and Sales
                         Invoicing processes, and the possibility for using the Enquiry and Reporting
                         functions in Agresso for controlling Project budgets and Cost Centre budgets.
                         Users in EISA will need to be informed of the new codes to use on Expenses
                         and Purchasing Card claims.
                         The EARS & ATLAS Systems Administrators will be working with the Project
                         Team for the development of interfaces / uploads between Agresso and EARS /
                         ATLAS and the management of those interfaces ongoing.
                         The Director of EISA will need to be aware of the impact of the system to
                         changes in working practices of their staff and actively manage those changes
                         through working with the Project Team and the overall Change Strategy.
       Senate House
       Services
                         Users in Senate House Services will need to be informed of changes to
                         Purchasing and Sales Invoicing processes, and the possibility for using the
                         Enquiry and Reporting functions in Agresso for controlling Project budgets and
                         Cost Centre budgets.
                         Users in Senate House Services will need to be informed of the new codes to
                         use on Expenses and Purchasing Card claims.
                         The Director of Senate House Services will need to be aware of the impact of
                         the system to changes in working practices of their staff and actively manage
                         those changes through working with the Project Team and the overall Change
                         Strategy.
       University
       Marine
       Biological
       Station,
       Millport
                         Users in Millport will need to be informed of changes to Purchasing and Sales
                         Invoicing processes, and the possibility for using the Enquiry and Reporting
                         functions in Agresso for controlling Project budgets and Cost Centre budgets.
                         Users in Millport will need to be informed of the new codes to use on Expenses
                         and Purchasing Card claims.
                         The Director of Senate House Services will need to be aware of the impact of
                         the system to changes in working practices of their staff and actively manage
                         those changes through working with the Project Team and the overall Change
                         Strategy.




Author: Bridget Boylan                    Page 9 of 22                           Date: 03/12/2007
Version 1.1
     The table below details the issues of which the project team will need to keep certain stakeholder
     groups and other departments within the University informed.


              Issues                                          Needs
           Change        All staff that will be affected by the implementation of the system need to be
         Management      aware of any changes to their roles.
                         This will be communicated and managed by the HR Director who is a member
                         of the Project Board, through the User Steering Group members and the
                         Senior Management Group and will be implemented through the Change
                         Strategy.
              Training   There will be a requirement for all users to learn how to use the system.
                         Details of the training strategy will be written in a training strategy document.
            Specific     There will be a need to communicate with intended users of the system on
          information    specific project updates that will impact on them.
          updates for
             users
        Project Plan &   The Finance Project plan is a key document and is located in: Agresso-
           updates       Project-Team/Project Plans. Progress on the project needs be communicated
                         appropriately to each stakeholder. (e.g. through the Project Board).
            General      University staff not currently directly involved in using the system will need to
          information    receive general information about the project because of its possible impact on
                         other University objectives and Division’s and Institute’s finance processing,
                         procedures and regulations.




Author: Bridget Boylan                    Page 10 of 22                            Date: 03/12/2007
Version 1.1
7    Methods of Communication
     Communication is part of the role of every member of the Finance Project Team and as such each
     person should be responsible for contributing to the communication strategy and communicate in an
     appropriate and timely manner.
     The following table highlights the media that will be used to support the communication of the project
     and the targeted audience:
              Media                                           Purpose
      Project Website     The Project Website has been in operation since January 2007 and has been
                          updated regularly. The format of the web-site will be reviewed in January 2008
                          and access to the web-site will be improved. The target audience will be all staff
                          affected by the project and will contain all up to date information from the
                          Finance Project Meetings: Project Board, Purchasing Steering Group, User
                          Steering Group.
                          Suggested content for the revised website:
                                 Front Page with countdown clock to go-live and latest news about the
                                  project.
                                 Tabs:-
                                    o Benefits expected
                                    o What’s on – Road shows, workshops
                                    o Training – who requires to be trained, schedule of training
                                    o Quick overview of Agresso functionality
                                    o Project Documentation
                                    o Key Project Dates & Progress
                                    o Project Contacts
                                    o Feedback e-mail
                                    o Process Owners for each process area
                                    o Details of User Group members for each Division
                                    o User Acceptance Testing
                                    o Questions and Answers
                                    o Supporting statements from Project sponsors: The Vice
                                       Chancellor, The Director of Administration, The Finance Director
                                       and Agresso.

          Newsletter      A newsletter will be sent out bi-monthly in electronic format from December
                          2007. The target audience is all members of staff and it will be published on the
                          intranet and highlighted in the In Focus section. It will inform of the progress,
                          including any changes on the project.
      Monthly Highlight   This document gives the detail of the project progress against plan, the number
          Report          of issues being dealt with and progress against budget. It is produced for each
                          Project Board meeting and should be used after the meeting for onward
                          communication by Project Board Members and User Group members. The
                          highlight report is designed with a commentary on the front page which can by
                          read out at meetings, or it can be pinned on notice boards. The audience is all
                          staff who are impacted directly by the project.
         Prototype        Prototype workshops will take place during the process design phase. The
         Workshops        target audience will be User Steering Group members, Managers, Finance staff
                          and key users of each process from the divisions and Institutes.
      Communications      In March 2008 a communications campaign will commence across the
      Campaign to all     University. The Senior Management Group, Project Sponsor, Project Manager,
       Divisions and      Change Manager and User Group members will lead the communications


Author: Bridget Boylan                     Page 11 of 22                           Date: 03/12/2007
Version 1.1
              Media                                           Purpose
          Institutes.    events. The target audience will be all Division and Institute staff to explain the
                         changes that the project will bring and to share the benefits of the new Agresso
                         system.
       Introduction to   Open sessions (surgeries) have been advertised on Thursday afternoons since
           Agresso       the start of the project for any member of staff to visit the Project Team and see
                         an introduction to Agresso.

         Committee       Regular meetings of the following standing Committees will be attended by the
          Meetings       Project Sponsor, Project Manager or Change Manager as requested to provide
                         updates on the progress of the project.
                         Committee:-
                                Senior Management Group
                                Finance and Property
                                Audit Committee
                                Information Management Group
                         User training will be defined in the Training Strategy document, but these
        User training
                         sessions will cover how to use the Agresso system and the benefits of the
         sessions
                         project, and the new Finance Procedures and Regulations. etc.

        Global emails    Emails will be used to relay ad hoc information to specific stakeholders during
                         the project.

           Ad-hoc        Throughout the project, the Project Manager may request to meet with Senior
     presentations and   staff throughout the University to communicate progress on a 1 to 1 basis.
      1 to 1 meetings    Additionally the Project Manager may be requested to attend Divisional or
                         Institute meetings to give an update on any aspect of the project.




Author: Bridget Boylan                    Page 12 of 22                            Date: 03/12/2007
Version 1.1
8     Communication Stages
      The diagram below shows the different stages of communication when building commitment to a
      major business change. The picture also illustrates the types of communication to be targeted at
      each stage.
      It should be remembered that different audience groups will have communication needs at a different
      stage and at different times along the commitment curve. The differing communication needs will
      need to be carefully managed. Additionally, not all audience groups need to go all the way along the
      commitment curve. For example it is desirable for end users to be at the Acceptance stage before
      go-live. Their superiors and senior management need to be fully committed in order to drive through
      the need for change.




                                                                                                      Internalization
                                                                                               ‘This is the way I do things’   Communications
                                                                                                                               taken hold:
                                                                                                     Commitment
                                                                                                                               Communications
                                                                                            ‘This is the way we do things’     successful and
   Achieving                                                                                                                   objectives
 commitment                                                                                                                    achieved
                                                                                               Acceptance
                                                                                                                               Concentrate on
                                                                                        ‘I’ll do it the new way’
                                                                                                                               praising and
                                                                                                                               celebrating
                                                                                     Engagement
                                                                              ‘I’ll look at doing it the   Communications
    Achieving                                                                         new way’             taken hold:
                                                           Understanding
    acceptance
                                                             ‘I know the                                   Concentrate on
                         Contact           Awareness       implications for                                benefits for the
                                                                 me’                 Communications        individual
                  ‘I know something    ‘I know what it is’                           taken hold:
                      is changing’                                                                         ‘What’s in it for
                                                        Communications               Concentrate on        me?’
                                                                                     overall benefits
    Setting the                       Communications beginning to
                                                                                     for the
      scene                           haven’t yet taken take hold:
                       Start                                                         organisation
                       Communications hold:             Reiterate basic
                       Basic message
                                      Reiterate basic   message
                       Focus on
                       providing an     message              Focus on reasons
                       overall                                for Finance Project
                       understanding    Focus on further
                                        overall               and why Agresso
                                        understanding        What it means
                                                             for roles and Org.
                                                             Design

                                                                            Time




Author: Bridget Boylan                                     Page 13 of 22                                        Date: 03/12/2007
Version 1.1
9     Communicators & Audience
9.1    Communicators
      The table below highlights the key communicators within the University, their key responsibilities and
      their communications objectives.
        Communicator                      Communicators objectives and responsibility

        Vice Chancellor     To demonstrate full support and communicate the importance of the Finance
        and the Senior      Project to the delivery of the overall Finance Business Change Programme.
         Management
             Group

        Finance Project     Communicate the objectives and benefits of              the   Finance      Project
           Sponsor          implementation, encouraging stakeholder buy-in.
                            Instil a culture of effective communications within the University, showing
                            commitment and support of the implementation.

        Finance Project     Communicate the objectives and benefits            of   the   Finance      Project
        Board Members       implementation, encouraging employee buy-in.
                            Demonstrate sponsorship through active and visible participation. Proactively
                            identifying, escalating and obtaining resolution to key issues and
                            communicating decisions and reasoning in a timely fashion.

        Finance Project     Be the main point of contact for Finance Project communications activities
           Manager          within the University.
                            Communicate the plans and progress of Finance Project to encourage buy-in
                            at all levels of the University.
                            Demonstrate management and control of the project through effective co-
                            ordination and leadership of the Project Team.

         User Steering      Support communications activities and deliverables.
        Group members
                            Ensure that the University is ‘ready, willing and able’ to accept the change at
                            all levels.
                            Be a point of contact for local Finance Project communications activities
                            within the Divisions and Institutes.

        Communications      Support the Project Manager with the project communications activities.
           Officer
                            Develop and implement communications activities and deliverables.

        Finance Project     Highlight any areas that need communication and provide the relevant
            Team            information to ensure that the Divisions and Institutes receive adequate
                            information to assure buy-in and acceptance of the new Finance system.


      It is important to remember that everyone from the Vice Chancellor through the University has the
      responsibility to communicate effectively about the Finance Project implementation.




Author: Bridget Boylan                     Page 14 of 22                            Date: 03/12/2007
Version 1.1
9.2 Audience Groups
       The table below highlights the audience groups within the University and the main communication
       objectives relating to each group:
              Audience                              Communication Objective
               Group

            Finance        This group will be responsible for managing the new financial system, for
          Division Staff   maintaining the supporting documentation, procedures and regulations and
                           for assisting users to cope with the change.
                           Communicate the need for the Finance Division staff to be the experts of the
                           new Finance System. Communicate the need to develop customer service
                           skills and advisory / consulting skills so Divisions and Institutes feel they
                           receive genuine Value for Money from the services provided by the Finance
                           Division.
         Finance staff     This group will be responsible for providing local advice and support to new
          in Divisions     users of the Finance system.
         and Institutes.
                           Communicate the need to be a local expert of the new Finance System and
                           to develop good relationships with members of the finance division so issues
                           can be resolved quickly.
              Managers     This group will have new management information available and new
                           methods of accessing the information.
                           Communicate the ability to access information 24/7 and to drill down to see
                           the transaction details. Communicate the importance of using data from
                           Agresso in their staff meetings and promoting Agresso as the single source of
                           financial information for their Division or Institute.
         Administrative    This group will be using the system to input purchase orders, check on their
             staff         progress through workflow, confirm goods receipts, enter sales invoices and
                           cross-charging journals.
                           Communicate the importance of data accuracy, especially of inputting data
                           right first time. Communicate the benefits to the whole University of data
                           being input once and not double or triple-keyed. Communicate how to get
                           support in use of the system and new processes.
              Academic     This group will be using the system to input / approve Purchase Requisitions,
                Staff      confirm goods receipts and manage project budgets.
                           Communicate the importance of data accuracy and the benefit of ease of
                           access to management information and control of Project budgets.
          Non Agresso      The Finance System Replacement project will change way the Purchases
             Users         and Sales are made, so staff not using Agresso need to be aware that
                           procedures have changed and adjust their working practices accordingly.
                           Communicate the new procedures for Purchasing and Sales Ordering,
                           Receipt of Cash, and the new coding required for Expenses, Purchasing
                           cards etc. Communicate who local support staff are.




Author: Bridget Boylan                      Page 15 of 22                          Date: 03/12/2007
Version 1.1
10   Communication Activities
10.1 Communication Phases

     The diagram below identifies the three key phases during the implementation and the
     communications activities that need to be completed to ensure successful implementations.



  ANALYSIS & DESIGN
                                BUILD & TEST
         Obtain buy-in of
          Key Sponsors                                       TRAINING & GO-LIVE
          Executives               Raise awareness
         Raise                     with End Users
          Awareness                Provide detailed               Focus awareness
          within the                understanding and               on what is
          University                information about               changing and the
         Engage                    the change                      impact
          Champions                Ensure messages                Ensure the
          within the                are cascaded                    University is ready
          University               Address concerns                and willing to
         Obtain feedback          Obtain feedback                 accept the change
                                   Escalate issues as             Provide
                                    appropriate                     mechanism to
                                                                    support and
                                                                    resolve queries


         Raising                      Enabling &                     Embedding
         awareness                    engaging



     Communication events are required to prepare the University for the impact of the implementation of
     Agresso in the Divisions and Institutes. This will raise awareness of the Finance Project and
     Agresso, targeted at appropriate levels of management, gaining buy-in, ensuring positive end-user
     commitment and assisting users to take ownership of the new processes.




Author: Bridget Boylan                   Page 16 of 22                          Date: 03/12/2007
Version 1.1
10.2 Communication Evaluation

    Communication is a two way process. There is a difference between delivering communications and it
    being understood. The tools we will use to assess the effectiveness and success of the communication
    activities within the University are:
        website – to provide a contact email address for feedback and questions about the project;

        telephone surveys – during the project, the University Communications Officer will carry out a
         telephone survey to staff to ensure that effective communication about the project is taking place within
         the University and given at the right levels;

        evaluation documents - e.g. training course evaluation;

        open feedback – any feedback received by any member of the project team by any member of staff to
         be fed back into appropriate members of team;

        user forums and workshops – to support communication flowing back to the project team.



10.3 Next Steps
     The following steps have been identified to take this strategy forward:


                         Action                       Responsibility                  Date                 Status
   Obtain Finance Project Board agreement          Bridget Boylan & Roy        28th February             Underway
   and commitment to the Communications                    Bent                    2008
                  Strategy
    Produce first project newsletter and re-          Bridget Boylan &     December 2007                    Done
    launch the project on the intranet with             Alison Mann
             feature in ‘In Focus’.
              Update Project Intranet site            Bridget Boylan &         January 2008                 Done
                                                        Alison Mann
                                                                                 th
   Present to the Senior Management Team               Richard Cryer,          13 February                  Done
                                                     Bridget Boylan &             2008
                                                     Kirsten Gillingham
    Organise Communications programme               Bridget Boylan &           February 2008             Underway
                                                       User Group
                                                   members and Senior
                                                   Management Team
   Cascaded Communications Programme               Senior Management           March to May              Not started
                                                        Team, Bridget             2008
                                                       Boylan, Kirsten
                                                   Gillingham, Roy Bent




Author: Bridget Boylan                         Page 17 of 22                                 Date: 03/12/2007
Version 1.1
Appendix 1 – Communications Plan
ANALYSIS AND DESIGN PHASE

    Events                Objective                    Message               Frequency       Delivered to:          Delivered by:     Feedback
                                                                                                                                      Mechanism
  Prototype          To demonstrate the        To demonstrate how the       February and   Finance staff and      Finance Project    Workshops or
  Workshops           prototype for each       new processes involving       March 2008     representatives           Team             E-mail
                      division and invite      Agresso will work and the                   from all business
                           feedback.            look and feel of the new                     areas affected
                                                        system.
   Project         To communicate to the         The importance of the       Bi-monthly    All staff within the    Project Manager     e-mail to
  newsletter        broader University the     project and who to talk to                    University via       and Project Team    members of
                   objectives of the project    for more information, or                   main Intranet site         Secretary       the Project
                     and highlight the key         where to get more                           and project                              Team
                    teams and individuals             information.                            intranet site.
                           involved.
Project Monthly    Provides progress and       Project running to plan or     Monthly        Project Board        Project Manager      At Project
Highlight report    budget update and             details of concerns                                                                Board meeting
                   details of project team      requiring management
                                                                                                                                        E-mail
                   activity in the previous     attention. Issues/risks
                    month and plans for          dependencies being
                      following month.          managed or escalated
                     Highlights issues.             appropriately.
Finance Project       Communicate all            The importance of the        Updated           All staff         Project Manager       E-mail
  Intranet site     aspects of the project          project and the           weekly                                and Project
                    and the key contacts:       commitment to keep all                                               Secretary
                     Project Team and           stakeholders informed
                       Project Board           through regular updates.
                         Members.
BUILD AND TEST PHASE
    Events          Objective                                         Message                Frequency           Delivered to:    Delivered by:     Feedback
                                                                                                                                                    Mechanism
Communications           To communicate the              The process changes will be        April and May      All affected      Finance Project       E-mail
   Cascade               process changes that         presentations and fact sheets that         2008          staff within         Team with
                                                                                                                                                    Question and
  programme                will impact on end          will detail the changes and how                       the University       support from
                                                                                                                                                   Answers forum
                            users, ensuring:             the new processes involving                                                Divisional
                                                                                                                                                      on project
                                                           Agresso will work. These                                                 Managers
                            users accept and                                                                                                        intranet site.
                                                       presentations will be tailored for
                           continue to use new
                                                          specific audiences with the                                                              Line manager
                         processes after go-live;
                                                           changes that impact that
                          all impacted areas are                    audience.
                              prepared for the
                                                          Business process change
                          changes, understand
                         them and can continue                 System changes
                          with their job role and
                                                                    Form changes
                               responsibilities.
    Project               To inform the broader          Highlight new processes and         Bi-monthly      All staff within    Project Manager    Question and
   newsletter             University of the new            benefits to be obtained.                          the University        and Project     Answers forum.
                              processes and                                                                      via main        Team Secretary
                                                                                                                                                       E-mail
                          recommend that they                                                                  Intranet site
                           book on training and                                                                and project
                         read the information on                                                              intranet site.
                           the project web-site.
Project Monthly          Provides progress and         Project running to plan or details     Monthly        Project Board       Project Manager     At Project
Highlight report          budget update and              where there are concerns that                                                             Board meeting
                         details of project team        require management attention.
                                                                                                                                                       E-mail
                         activity in the previous      Issues/risks dependencies being
                          month and plans for               managed or escalated
                            following month.                     appropriately.
                           Highlights issues.
Finance Project          Communicate project             The commitment to keep all           Updated            All staff and   Project Manager       E-mail
  Intranet site            progress and the             stakeholders informed through         weekly              students         and Project
                         changes to business                  regular updates.                                                   Team Secretary
                              processes.




Author: Bridget Boylan                              Page 19 of 22                             Date: 03/12/2007
Version 1.1
TRAINING AND GO-LIVE PHASE
    Events           Objective                                 Message               Frequency        Delivered to:     Delivered by:       Feedback
                                                                                                                                            Mechanism
Training Approach           To ensure that                 This is a key              April 2008       Heads of        Finance Project         E-mail
                          schools and central            communication to                            Divisions and      Manager and
                                                                                                                                            Question and
                          function managers           managers recognising the                         Institutes     Training Manager.
                                                                                                                                           Answers forum.
                           are committed to            importance of training.
                             providing the                                                                                                 Line manager
                                                       Highlighting the wasted
                         resource for training.
                                                        time and effort when
                               That senior             people do not turn up to
                             manager’s take                    training.
                              ownership for
                          ensuring staff attend
                         training in order to be
                         fully prepared for go-
                                   live.
                          Senior executives
                           have committed
                         resource but signoff
                          from managers is
                              essential.
Training Schedule        To communicate the              Training dates, times,       May 2008         To all End     Training Manager         E-mail
  to End Users            Training Schedule            locations, attendees and                          Users
                          and training plan.                    trainers.                              impacted
      User Ids             The objective is to        The list of identified users   Once in July      To all End     Training Manager /   Questions and
                          ensure that all user            of Agresso will be            2008             Users             Systems         Answers forum
                         ids will be known and         communicated to enable                                            Administrator
                                                                                                                                               E-mail
                            tested by Users          specific access rights to be
                             before go-live.            created and assigned.
                                                     Once issued they will need
                                                      to be tested by each user
                                                      to ensure that their profile
                                                       enables them to perform
                                                             their role and
                                                           responsibilities.




Author: Bridget Boylan                             Page 20 of 22                             Date: 03/12/2007
Version 1.1
       Events                  Objective                      Message              Frequency        Delivered to:       Delivered by:      Feedback
                                                                                                                                           Mechanism
  Implementation          The implementation         This will ensure that users   Delivered at     All impacted          Trainers       Questions and
       Pack              pack will be delivered       feel comfortable with the       training       End Users                           Answers forum
                          to each User of the         Go-live process and the      events June
                                                                                                                                             E-mail
                          system, prior to go-       support available to them      to October
                           live to ensure that        during the initial 6 weeks        2008
                           each user has the         after the system goes live.
                         necessary tools post
                                                              Includes:
                           go-live to support
                            their job role and             User id details;
                              responsibility.
                                                         Help Desk contact;
                                                      Templates & Processes
                                                      System quick reference
                                                             guides.
Project newsletter       Focused on training           Communicate training        Bi-monthly      All staff within    Project Manager    Question and
                         and new processes.          activities, change in new                     the University     and Project Team   Answers forum.
                                                    processes and procedures.                          via main           Secretary
                                                                                                                                             E-mail
                                                      How to obtain support.                         Intranet site
                                                                                                     and project
                                                                                                    intranet site.
  Project Monthly         Provides progress          Project running to plan or      Monthly       Project Board      Project Manager    At Project Board
  Highlight report        and budget update           details where there are                                                                meeting
                         and details of project        concerns that require
                                                                                                                                             E-mail
                          team activity in the        management attention.
                         previous month and         Issues/risks dependencies
                          plans for following           being managed or
                          month. Highlights           escalated appropriately.
                               issues.
  Finance Project           Communicate               Training is important –       Updated         All staff and      Project Manager       E-mail
    Intranet site        training programme         book early and let us know      weekly           students         and Project Team
                          and Questions and              of any changes.                                                  Secretary
                                Answers                Importance of user
                                                            questions.




Author: Bridget Boylan                            Page 21 of 22                            Date: 03/12/2007
Version 1.1
FOLLOWING GO-LIVE
    Events                     Objective                        Message                  Frequency         Delivered to:        Delivered by:        Feedback
                                                                                                                                                     Mechanism
Training Approach             To ensure that                 This is a key               Immediately         Heads of          Finance Project         E-mail
                           managers and staff             communication to               after training,   Divisions and        Manager and
                                                                                                                                                    Question and
                         take full responsibility      managers recognising the         then quarterly       Institutes        Training Officer.
                                                                                                                                                   Answers forum.
                          in ensuring that they       importance of post-training             and
                            retain and build on               evaluation.                 continuing                                                Line manager
                         learning from training
                                                      Highlighting potential errors
                           sessions to perform
                                                      that will be entered on the
                         their functions on the
                                                       system where staff do not
                           system accurately.
                                                           retain knowledge
    Final Project          Provides a final              Project has concluded           Bi-monthly        All staff within    Project Manager      Question and
     newsletter          update on the project         successfully, thank you to                          the University     and Project Team     Answers forum.
                            and handover               all involved for their efforts                          via main           Secretary
                                                                                                                                                       E-mail
                             process and                 in making the project a                             Intranet site
                           highlights future                     success.                                    and project
                            project activity.                                                               intranet site.
  Project Monthly           Provides a final             Project has completed             Monthly         Project Board       Project Manager     At Project Board
  Highlight report        update on progress                  successfully.                                                                            meeting
                             and budget.
                                                       Highlights any unresolved                                                                       E-mail
                                                      issues and how they will be
                                                                handled.
  Finance Project         Combine with main                Absorption of new              Updated           All staff and     Finance Managers         E-mail
    Intranet site          Finance Division             processes into Business           weekly             students            and Finance
                             Intranet site.           As Usual activities. How to                                             Division Secretary
                                                       obtain support. Changes
                                                      to process and procedures.
                                                          System changes etc.




Author: Bridget Boylan                              Page 22 of 22                                 Date: 03/12/2007
Version 1.1

						
Related docs
Other docs by hedongchenchen
Donley PE 10.8-10.19
Views: 392  |  Downloads: 0
DoMN YOG Rego form 2 pilgrims
Views: 206  |  Downloads: 0
Donchian
Views: 0  |  Downloads: 0
Donation Requests 101006f
Views: 0  |  Downloads: 0
Donation_Request
Views: 0  |  Downloads: 0
Donalyn-Miller-Book-list
Views: 0  |  Downloads: 0
don't judge
Views: 0  |  Downloads: 0
Domestic Service Groups
Views: 0  |  Downloads: 0
domainsandmeasuresnovember2012_tcm77-286624
Views: 0  |  Downloads: 0
domainsandmeasuresfinal_tcm77-287743
Views: 0  |  Downloads: 0