Embed
Email

military

Document Sample

Shared by: cuiliqing
Categories
Tags
Stats
views:
1
posted:
11/30/2011
language:
English
pages:
1
by Keith Gribbins









A

crowd of contractors and manufacturers gathered in “The biggest key to this project is that there’s no

a stretch of field inside Ft. Pickett Army Base, Va., to interruptions to this training facility,” said Isy Giuliani,

witness Premier-Pipe’s 1 millionth foot of installed president of AM-Liner East. “The other day, the Army was

cured-in-place pipe (CIPP) liner go into the ground. doing training in the houses area and right around the

The group ambled around AM-Liner East’s brand new corner, here we are putting in Premier-Pipe.”

Rush inversion truck with its tower extended and a four- The rehabilitation of Ft. Pickett’s sewer is part of a

man crew feeding 21-in. liner 570 ft under a grassy swath of congressional act dubbed the BRAC Program (Base

pasture. Just down the road sat Hueys, Humvees and train- Realignment and Closure), which requires privatization of

ing barracks for the Army’s 42,000-acre maneuver training land and facilities formerly owned and run by the

center, under which the sewer infrastructure was being Department of Defense. In Virginia, the Army and Ft. Pickett

rehabilitated with the help of will be handing over 3,500 acres

Premier’s CIPP process. of land to Nottoway County

Representatives from Premier- and the nearby municipality

Pipe (U.S. and international), of Blackstone. The City of

Applied Felts (the tube manufac- Blackstone will take charge of

turer), AM-Liner East (Premier- the sewer system, but only after

Pipe licensee), ALLPRO (the the Army has rehabilitated it.

pipe cleaning contractor) and “Under Department of

Atlantic Coast Contractors (the Defense guidelines, utility sys-

open-cut contractor) shook tems are being privatized and

hands and posed for pictures. right now, we are rehabilitating

Premier-Pipe USA and J.W.M. the system to get it into a condi-

Environmental president Jim tion where it can be privatized,”

Mortell smiled. “I think that it’s a stated Gordon Chancey, P.E. and

great feat,” he said. “It says a lot project engineer for the U.S.

about us working together and Army Corps of Engineers

how the other licensees helped Norfolk District. “In that agree-

make this happen. For us to hit ment, the Army agreed to take

one million, it kind of sets us apart care of the I/I problems.”

from other groups out there.” The Corps of Engineers need-

Premier-Pipe USA was found- Representatives from Premier-Pipe, AM-Liner East, JWM ed to come up with a plan to

ed in the spring of 1997. Environmental, Applied Felts and ALLPRO celebrate Premier-Pipe’s rehabilitate the aging system in

The company’s CIPP process 1 millionth foot of installed CIPP. less than a year, and cheaper

was imported from England than the $12 million dollars

with the help of Premier-Pipe International owner and estimators had initially assessed for a dig-and-replace

director Simon Baylis, who could also be found walking project. The Corps hired URS Corp. to inspect and evaluate

around the jobsite. Premier-Pipe USA currently has eight the system for alternative forms of rehab.

licensees. Combined, the U.S. and International branches “They were thinking about replacing the system

have performed jobs from Belgium to Blackstone, Va., because they were concerned about the offset joints,” said

installing the benchmark of one million feet of liner. The URS Corp.’s Tracy Fee, P.E. “So cured-in-place was a good

base-wide sewer system rehab of Ft. Pickett was also a match. You didn’t have to use a thick liner and you could

milestone for Premier-Pipe USA’s largest licensee, AM-Liner bridge any gaps and offset joints. And, you could have a

East, whose contract with the U.S. Army Corps of watertight system.”

Engineers was the largest ever awarded to a small business The cost of the project shrank from $12 million to $7.5.

within the Norfolk District. AM-Liner East crews have already installed more than

The project consists of the rehabilitation of 111,000 lf of 60,000 lf of liner since November. “This was an excellent

8- to 30-in. diameter sewers using Premier-Pipe CIPP lin- example of private- and public-sector design teams work-

ing. The venture includes the rehabilitation of 4,240 vf of ing together on a fast-track, coming in on time and under

manholes using Terre Hill Composites CIPP liners, removal budget,” said URS’s Christopher Garrett.

and replacement of 9,360 lf of sanitary sewer mains, rang- Army personnel had no complaints either. “This is the

ing in size from 6 to 15 in., and the installation and replace- way jobs are supposed to work,” said Army Corps district

ment of 27 sewer manholes. Construction of one new engineer Col. Allen Carroll. “I think Gordon put it best —

sewer pump station, new installation of 3,220 lf of 6-in. good design, good contractor and a great job.” TT

sewer force main and the replacement of 34,020 lf of 6-in.

laterals is also slated. Keith Gribbins is assistant editor for Trenchless Technology.



June 2002 TRENCHLESS TECHNOLOGY 41



Related docs
Other docs by cuiliqing
Table 4 _AY and CY_
Views: 0  |  Downloads: 0
August 19_ 2010 - Maine ASSE
Views: 0  |  Downloads: 0
Appointment of Counsellors
Views: 0  |  Downloads: 0
Izmir - Sportslion NL
Views: 194  |  Downloads: 0
ADASTRA BOWLING CLUB
Views: 0  |  Downloads: 0
2 August 2011 Meeting Agenda
Views: 0  |  Downloads: 0
Outline
Views: 1  |  Downloads: 0
gislergianindictmentpr
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!