Date: 26 - 11- 2011



VIJAYAWADA MUNICIPAL CORPORATION



JNNURM



STATUS ON TENDERS (CIRCLE - IV)

Estimate Tender

Name of Tender Work Order Agreement

Sl.No Name of Work Amount in received Remarks

Project Notice Date Date Date

Lakhs date







NIL

VIJAYAWADA MUNICIPAL CORPORATION

EE - 4 CIRCLE - DAILY PROGRESS REPORT FROM 21.11.2011 to 26.11.2011









Submission









Target date of

(Rs. In lakhs)







Contractor









made so far

Due date of

completion







completion

Last Bill

DATE TO

Day wise Physical Progress









Payment

Estimate









ORDER

WORK

Code

Till last Value of Work

Sl. No. Name of the work Estimated Quantities Total Qty. Rate Per

week Qty. Done

Mon Tue Wed Thu Fri Sat

21.11.11 22.11.11 23.11.11 24.11.11 25.11.11 26.11.11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23



4015 Providing Sewer lines at 6 (a) covering Revenue Colony,E9-62269/06 WORK COMPLETED

4011 Providing Sewer lines at 6 (b) area covering Film Nagar,E9-17366/07 WORK COMPLETED

4019 Providing UGD sewer network for Madhuranagar area Rc.E9-67665/06 WORK COMPLETED

4040 Construction of Sump cum Pump House in Sector - 6(b) (Rc.E9-17366/07) WORK COMPLETED

4013 Providing 300mm dia D.I. Pumping Main to Block 6(a) a Rc.E9-93096/07 WORK COMPLETED

4027 Providing Sewer line Network at Ramakrishna Puram Rc.E9-52867/07 WORK COMPLETED

4041 Providing UGD facilities in AyodhyaNagar Rc.E9-63632/06 WORK COMPLETED

4042 D.I. Pumping Main from Ayodyanagar to Ramakrishnapuram Rc.E9-111207/08 WORK COMPLETED

4024 Construction of Sump cum Pumping Station at Ayodhya Nagar Rc.E9-19068/07 WORK COMPLETED

4016 Construction of Inlet, Screen, Sump cum Pump House for 6 (a) (Rc.E9-23868/07) WORK COMPLETED

4017 Providing Pumping Main 600 mm to STP RL Nagar. Rc.E9-45671/07 WORK COMPLETED

4054 Providing 300 mm dia D.I. K7 pumping for balance length in Budameru left side bund road Rc.E9-108615/09 WORK COMPLETED

4056 Erection of 1 No 500 KVA Transformer with Chalasaninagar East (B)(Rc.E9-148517/08) WORK COMPLETED

4043 Providing Sewer Line Network at Khudush Nagar (Rc.E9-23863/07) WORK COMPLETED

4044 Providing UGD Network at Kedareswarapet Rc.E9-100641/08 WORK COMPLETED

4021 Providing 300mm dia D.I. Pumping Main from Madhuranagar sump to Mutyalampadu Sump Rc.E9-45672/07 WORK COMPLETED

4028 Providing Collection Network & Pumping Station in Zone-II (Karakatta Area) Package - II Rc.E9-106701/08 WORK COMPLETED

4020 Construction of Sump cum Pumping Station at Madhura Nagar Rc.E9-19067/07 WORK COMPLETED

4039 Collection Network in Chalasani Nagar. Rc.E9-70611/2006 WORK COMPLETED

4040 Construction of Pumping Station at Police Colony. E9-25499/07 WORK COMPLETED

4029 D.I. Pumping Main from Karakatta to H.B. Colony Rc.E9-129954/08 WORK COMPLETED

4045 Providing Trunk Main at Kedareswarapet Rc.E9-100642/08 WORK COMPLETED

4047 Design, Supply, Delivery and erecton of 100 KVA Transformer for Madhuranagar D.P. Station E9-127559/09 WORK COMPLETED

4057 Devinagar Submersible Pumps of Capacity 12.05 HP -2 Nos 25 HP 2 Nos and 40 HP 1 NO Rc.E9-125043/08 WORK COMPLETED

4058 Design of 1 No 160 KVA Transformer for Phase - IV ie. H.B.Colony, Devinagar and Veterinary Colony D.P Station. E9-148516/08 WORK COMPLETED

4062 Rising of existing compound wall and providing barbed wire fencing on East and North side of Ramalingeswara Nagar S.T.P. Rc.E9-160674/09 WORK COMPLETED

4042 Supply and erection of required capacity pumpsets with required specials to Phase-II D.P. Stationsat Chalasani nagar with one year maintenance. E9-138035/08 WORK COMPLETED

4046 Madhura Nagar Vetical Centrifugal Pumps & submercible pumps to 6A, 6B, Madhuranagar, E9-125043/08 WORK COMPLETED

4048 Design, Fabrication, Supply Delivery and erection of 1 No 500 KVA Transformer for Phase - I ie. Kabela and 6A Drainage Pumping E9-14815/08 WORK COMPLETED

4001 Sewer line collection net work in Devi Nagar block 3D E9-45789/07 WORK COMPLETED

4066 Laying of 900mm dia. NP4 class RCC Pipe casing across NH-5 by trench less technology / Pipe jacking method for Gunadala UGD Scheme Rc.E9-120644/10 WORK COMPLETED

4061 Laying of 1000mm dia MS pipe under railway track with jacking system for Devi Nagar Pumping main Rc.E9-157447/10 WORK COMPLETED

4004 Supply and erection of required capacity pumpsets with required specials to Phase-IV D.P. Stations with one year maintenance. E9-147937/08 WORK COMPLETED

&4007

4033 Supply and erection of required capacity pumpsets with required specials to Phase-I Kabela D.P. Stations with one year maintenance. Kabela, Karakatta & Ayodhanagar (Rc.E9-147935/08) WORK COMPLETED

4003 Providing UGD net work connection in Gunadala veternary colony E9-46736/07 WORK COMPLETED

4067 Providing Sluice Valve wih chamber on Chalasani Nagar Trunk Main near Geeta Nagar Bund WORK COMPLETED

4031 Rc.E9-125609/10

Providing Collection Network & Pumping Station in Zone-IV (Kabela Area) Package - III E9-106704/08 WORK COMPLETED

4065 Supply & Erection of 100 KVA transformer to Madhuranagar WORK COMPLETED









2/5

Submission









Target date of

(Rs. In lakhs)







Contractor









made so far

Due date of

completion







completion

Last Bill

DATE TO

Day wise Physical Progress









Payment

Estimate









ORDER

WORK

Code

Till last Value of Work

Sl. No. Name of the work Estimated Quantities Total Qty. Rate Per

week Qty. Done

Mon Tue Wed Thu Fri Sat

21.11.11 22.11.11 23.11.11 24.11.11 25.11.11 26.11.11

I Providing Under Ground Drainage facilities to the Un-served areas. - Rs. 56.56 Cr.

4038







1 Design, Construction, 1295.00 1) UASBR 1436 Cum 60000









M/s. APR Project Pvt

Operation and









31.10.2011









31.05.2012

Maintenance of the 20 MLD









26.02.09









09.09.10

Rod Bending Rod Bending Rod Bending Centering Centering Centering









Ltd.HYD









931.14

STP-1 at Jakkampudi in

Vijayawada with UASBR

Technology Remarks Work is in progress 60000

E9-106440/08

4052









2 Providing 750 KVA 19.62 Transformers 1 No 0









Prasada Rao,

Transformer for Market









03.11.2011









02.02.2012





31.01.2012

Sri M.R.D.

Area E9-128168/09









MTM

Remarks Work is under progress 0

4053









3 Providing Pumpsets to 175.00 Pumpsets Watering Watering Watering Pumpset Pumpset beds Pumpset beds 1 No 17000

Market area E9-128169/09 beds for 100 for 160 HP for 400 HP

HP Motors 2 Motors 2 Nos Motors is fixed

M/s. Hydro Electrical









Nos are fixed are fixed and and alignment

and alignment work work









30.11.2011

18.07.09



26.05.10







19.12.09

alignment completed completed









81.58

work

completed









Remarks Work is under progress 17000



II Providing Sewerage facilities in un-served areas of VMC covering Housing Board Colony, Gunadala, Devi Nagar, Kedareswar Peta. - Rs.19.85 Cr.

4005









1 Collection net work and 996.00 1) Sump 9 Lifts 9 Lifts 1 Lift 0

pumping station in zone-I

zone-III Bhavani puram 2) Pump house Col&slab complete 1 Job 0

area (E9-106699/08) d

3) grit chamber 5 Lifts 5 Lifts 1 Lift 0



4)Road Road Road Road Road Road Road 6 3000 1 Job 18000

Sri. V. Sanjeeva Reddy









Restoration Restoration Restoration Restoration Restoration Restoration Restoration









15.12.2011

21.03.09



31.03.11







26.09.09

5) Trunk Main 6530 6463 27 8 35 2200 1 Rmt 77000









645.05

Rmts Rmts





6) Branches 36760 39685 58 1000 1 Rmt 58000

Rmts Rmts 20 20 18

7) Manholes 790 Nos 1558 Nos 2 45000 1 Nos 90000

2



8) Ventilating 50 Nos 1 Nos 0

shaft

Remarks Work is in progress 243000



III UGD Northern Part STP's Project Cost. - Rs. 178.15 Cr.

4059









1 Laying of Trunk sewer 173.00 1) Trunk Main 2200 1327 0 4000 1 Rmt 0

M/s. M.A. Waheed, Hyd









main with RCC NP3 pipes Rmts Rmts









31.12.2011

from Chittinagar to Kabela









09.11.09



25.03.11









03.06.10

2) Man Holes 70 Nos 33 Nos 0 0 1 No 0









77.67

road junction E9-

153140/09

3) Road 0 0 1 Job 0

Restoration

Remarks Work in progress 0









3/5

Submission









Target date of

(Rs. In lakhs)







Contractor









made so far

Due date of

completion







completion

Last Bill

DATE TO

Day wise Physical Progress









Payment

Estimate









ORDER

WORK

Code

Till last Value of Work

Sl. No. Name of the work Estimated Quantities Total Qty. Rate Per

week Qty. Done

Mon Tue Wed Thu Fri Sat

21.11.11 22.11.11 23.11.11 24.11.11 25.11.11 26.11.11

4067



2 Construction of 20 MLD 1500.00 1) Aeration Tank 574 Cum 0

STP in

Ramalingeswaranagar

Rc.E9/EE-V-131346/09

2) CC Tank 170 Cum 0







3) Clarifier 410 Cum Plastering Plastering Plastering Plastering Plastering 110000

M-30

2 cum

4) Centriguge 145 Cum 0

Pump House

5) Recirculation 410 Cum 0

M/s. Ramky Infrastructure Ltd. Hyderabad Return Sludge

Sump

6) MEP Room 155 Cum M-30 M-30 Rod Bending 95000

4 cum 2.5 cum M-30

1 cum









08.06.2010

7) Inlet 125 Cum Plastering 20000









31.01.2012

11.06.11









07.12.11

977.42

8) Gas Holder 150 Cum 0





9) UASBR-1 1420 Cum M-30 M-30 M-30 M-30 M-30 M-30 450000

4 cum & 4 cum & 4 cum & 4 cum & 2 cum & 11 cum &

Plastering Plastering Plastering Plastering Plastering Plastering



10) UASBR-2 Rod Bending Centering Rod Bending Centering Plastering & 145000

& Plastering Centering



11) Division Box 0









12) Earth Filling 0





Remarks work in progress 820000

4064









3 Construction of Compound 194.00 1) Plastering 8020 Sqm 3765 1 Cum 0

Sri. Gouri Sankar









Walls and Retaing Walls Sqm

for UGD Pumping Stations









31.05.2012

27.03.10



26.08.10









02.11.10

in Circle-IV 2) Brick work 813 Cum 194 Cum 1 Cum









60.22

Rc.E9-161539/09





Remarks work in progress 0









4/5

Submission









Target date of

(Rs. In lakhs)







Contractor









made so far

Due date of

completion







completion

Last Bill

DATE TO

Day wise Physical Progress









Payment

Estimate









ORDER

WORK

Code

Till last Value of Work

Sl. No. Name of the work Estimated Quantities Total Qty. Rate Per

week Qty. Done

Mon Tue Wed Thu Fri Sat

21.11.11 22.11.11 23.11.11 24.11.11 25.11.11 26.11.11

4068



4 Providing sewer lines to 262.00 1) Trunk Main 3125 Rmt 15 4000 1 Rmt 60000

15

Iron & Commercial Yard at









M/s. M.A. Waheed, Hyd

Bhavanipuram in one town 2) Laterals 10000 3022 Rmt 113 2000 1 Rmt 226000

18 30 30 35

area. Rmt









31.03.2012

08.02.11



22.06.11







25.12.11

Rc.E9-164155/10 3) Man Holes 364 Nos 92 Nos 3 30000 1 No 90000

2 1









36.23

4) Road Road Road Road Road Road Road 6 2000 1 Job 12000

Restoration Restoration Restoration Restoration Restoration Restoration Restoration





Remarks Work in progress 388000

4069









5 Design, Construction, 1500.00 1) Clarifier 410 Cum 1 0







M/s. Ramky Infrastructure Ltd. Hyderabad

Operation and

Maintenance of the 20 MLD

STP at Jakkampudi in

Vijayawada with UASBR 2) UASBR-1 1420 Cum De-watering De-watering De-watering De-watering De-watering De-watering 60000

Technology z(2nd STP)

E9-156749/09









31.12.2012

08.06.10



10.06.11









07.12.11

529.78

3) UASBR-2 0









Remarks work in progress 60000

4070









6 Construction of Retaining 714.00 1) Piles 233 Cum 1 Cum 0

wall on River side of

Ramalingeswara Nagar

M/s. APR Project Pvt Ltd.HYD









STPs to protect from

Krishna River floods

Rc.E9-164154/10 2) Raft 1362 Cum 1 Cum 680000

M-30 M-30 M-30 M-30

17 cum 17 cum 17 cum 17 cum









02.05.2011









07.03.2012

07.03.12

3) PCC 440 Cum PCC 1 Cum 12000

3 cum

4) Retaining wall 3383 Cum 1 Cum 0





5) Earth work 26000 1500 1 Cum 0

Cum Cum



Remarks work in progress 692000



Grand Totals Rs. 1892000.00









5/5



Related docs
Other docs by cuiliqing
IMPLANTACION 5S
Views: 9  |  Downloads: 0
eaa6ceb678488193dc5a0c4f868d64b1
Views: 1  |  Downloads: 0
AbortionIdeoContribs2009
Views: 2  |  Downloads: 0
bolt on presentation Lanarkshire day 1 - 16-2
Views: 2  |  Downloads: 0
HP20110411_2
Views: 1  |  Downloads: 0
20110422134617101l218l90l211l26
Views: 7  |  Downloads: 0
M350504350e
Views: 2  |  Downloads: 0
XBLArcadeFS
Views: 1  |  Downloads: 0
SuccessfulImplementation_Final200501
Views: 1  |  Downloads: 0
NETGEAR WNR834Bv2快速安装指南
Views: 6  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!