2011 National Smart Start Conference Timeline

As of July 20, 2010

Planning Committee Members: Susan Perry Manning, Tracy Zimmerman, James Dodson, Connie Holton, Sue Totty, Lois Slade, Blanche Stokes, Yvonne

Huntley, Tery Schelling, Joyce Baffi, Maura Pherson





Group Codes: A = Planning, B = Workshops; C = Marketing; D = Registration; E = Speakers; F = Post Conference Follow-up







Person

Group # Task Due Date Completed date Comments

Responsible

Identify conference planning

Meetings scheduled through July. Will

A 1 committee & set planning mtg March 31, 2010 Sue April 23, 2010

meet every 2 weeks until further notice.

schedule

Set event schedule & get

May 2-5, 2011 with hotel arrival May 1,

A 2 President's approval (i.e. meals, April 16, 2010 Sue June 21, 2010

2011

sessions, etc)

A 3 Confirm Event Date April 16, 2010 Sue April 30, 2010

Identify tasks for conference

A 4 planner to perform; committee May 1, 2010 Joyce Delayed due to reorganization

reviews & finalizes

Determine method of managing

A 5 May 1, 2010 James May 28, 2010 CVENT selected

online workshop proposals

Identify staff or develop RFP if

needed for contractor to manage

A 6 May 1, 2010 Sue June 21, 2010 process delayed

workshop proposal recruitment

process

A 7 Update Conference Timeline May 1, 2010 Joyce ongoing

Identify potential speakers May 13, 2010 invites sent to Drs.

A 8 (Opening Keynote, Reception, May 5, 2010 Tracy Shonkoff & Heckman; waiting for

closing lunch) response

Develop RFP, if needed, for

A 9 conference planner & share draft May 10, 2010 Sue N/A NA 2011, already under 3 yr contract

with Planning Committee

Research, then determine

A 10 workshop tracks & hot topics, May 15, 2010 Lois June 18, 2010

theme





58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 1 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible

Develop contract or P.O. with

B 11 selected vendor for online May 15, 2010 James May 28, 2010

workshop entry; dates, budget

Develop workshop RFP &

B 12 May 15, 2010 Lois June 21, 2010

finalize; modify for web posting

Contract in place for contractor

B 13 to manage workshop proposal May 15, 2010 Lois June 21, 2010 process delayed

recruitment process

Advertise, select and retain used previous contractor, Meeting

A 14 May 31, 2010 Sue May 15, 2010

conference planner Details

Develop line item budget for

A 15 expenditures & review with May 31, 2010 Joyce in process

Planning Committee

Determine registration fees based

on expenditures and estimate

A 16 May 31, 2010 Sue June 21, 2010 in process

revenue; review with committee

& obtain approval of President

Email notification of conference

A 17 May 31, 2010 Lois June 4, 2010

dates to NCPC staff

IT works with CVENT for online

B 18 workshop proposal posting and May 31, 2010 James July 2, 2010 process has been delayed to July 2, 1010

testing

Email notification to all former

B 19 presenters & others regarding the June 1, 2010 Eric July 6, 2010 process delayed to July 5, 2010

Workshop RFP for the new year

C 20 Create detailed marketing plan June 10, 2010 Tracy June 23, 2010









58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 2 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible



Contractor meets with NCPC

staff on potential workshop ideas:

target presenters for specified

workshops in the tracks. Identify

B 21 June 30, 2010 Marsha June 30, 2010

key issues, best practices &

successes from NC & other states.

Consider attendee overall

evaluation comments from 2009.



Determine method of online Demo presentations: CVENT &

D 22 June 30, 2010 James

registration & payment Constant Contact

Add Conference to NCPC Staff

C 23 June 30, 2010 Tracy Done - in July

email signature

Blogs, Tweets, Facebook posts

C 24 July 1, 2010 Tracy Ongoing

about Conference

Appoint Workshop Committee &

B 25 July 5, 2010 Marsha July 6, 2010 in process - calls set for July 21-29

Set Meetings/conf calls of Same

CVENT Proposal reports

Everyone has been trained except

identified by State Programs Dept

B 26 July 9, 2010 James July 21, 2010 Marsha who will be trained July 21,

(SPD) & Workshop contractor;

2010

created by IT

Post to non-Smart Start calendars

C 27 July 12, 2010 Tracy Ongoing

and websites

Save the date email to all

C 28 constituents as part of the July 14, 2010 Eric July 19, 2010 Done

marketing plan

Creation of 2011 Conference

Done - prior to

C 29 Promotional Page on Smart Start July 14, 2010 Eric will continue to update

deadline

website









58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 3 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible



Notification of Workshop

RFP/CVENT link sent to targeted

B 30 July 15, 2010 Marsha Ongoing began distribution July 6, 2010

presenters identified by the

Workshop Planning Committee



Reminder notification of RFP

Due Date emailed to targeted

B 31 July 30, 2010 Marsha Delayed - due August 23, 2010

workshop presenter prospects not

yet entered into CVENT system

A 32 Finalize Hotel Contract July 31, 2010 Joyce Meeting Details working with hotel

C 33 Monthly marketing emails August 1, 2010 Eric Ongoing Ongoing through May 2011

Sponsor promotional information

C 34 included on conference website August 5, 2010 Tracy

and mailings sent to vendors

B 35 Workshop Proposal Deadline August 5, 2010 Marsha Due date changed to August 30, 2010

Proposals available & assigned to

B 36 subgroups for review by August 9, 2010 Marsha Delayed - to September 1, 2010

Workshop Committee



Workshop Selection Committee

B 37 August 20, 2010 Marsha Delayed to September 15, 2010

meeting to make choices



Archive data from database

Lois will check with Scott about moving

D 38 (registration) from previous September 15, 2010 James Done

archiving date forward

conference

Assess Results of Workshop

proposal Selection Committee;

B 39 September 30, 2010 Marsha

Identify gaps in subject & recruit

additional presenters

Run report for workshop

B 40 September 30, 2010 Marsha

proposal track List from CVENT





58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 4 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible



Workshop Proposal contractor

B 41 notifies Meeting Planner of October 1, 2010 Marsha Done through CVENT

accepted/ rejected presentations

Receive final information on

B 42 special track presentations October 1, 2010 Lois

(Medical Education, CSEFEL)

Send “Yes” letters to workshop

B 43 presenters selected & notify those October 5, 2010 Deirdre

not selected

Notify Tracy of approved sessions

w/ edited 60 word descriptions

B 44 and highlight "hot topics" and October 8, 2010 Marsha

well known presenters for

marketing

Create registration website with Dependent upon if we use vendor/Due

C 45 October 8, 2010 Eric Ongoing

conference content information October 30, 2010

IT works with online registration

contractor to design online

website to receive participant Overall - software reg. timeline must be

D 46 October 8, 2010 James

registrations (including interest dev.

survey) & generate invoices/

receipts

Print and mail postcard Date depends on when registration is

C 47 October 11, 2010 Tracy

announcing registration is open open

Skeleton outline of pre-conference

workshops with times to Tracy to

B 48 October 15, 2010 Susan

start building in registration

system

FINAL pre-conference workshop

descriptions, presenters, times to

B 49 October 22, 2010 Susan

Tracy - also include bios of

presenters and ideally a picture

58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 5 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible

Post information on registration

website including speaker

C 50 October 29, 2010 Eric Ongoing

information & additional content

info

Conference keynote speakers for

opening session and celebration

E 51 October 29, 2010 Tracy

dinner must be confirmed by

October

Provide Deirdre list of rooms w/

B 52 dates and times needed for special November 1, 2010 Lois

meetings

Open online participant

D 53 November 1, 2010 James dependent on when registration up

registration

ALL workshops are must be

provided to Deirdre and Tracy

B 54 November 1, 2010 Marsha

with appropriate info. Must

included DCD credits.

Post link on conf website pages to

C 55 November 1, 2010 Eric

online conference registration



Update Conference Maintenance

D 56 web based application based on November 1, 2010 James Deirdre estimates or ask online?

meals and special sessions

Coordinate posting of workshop

descriptions and schedule Cent to

conference website. Create

C 57 November 5, 2010 Deirdre

mechanism for conference

coordinator to regularly update

this section.

Finalize all logistics for planning

B 58 November 15, 2010 Contractor

for pre-Conference day







58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 6 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible

Coordination/Planning of

Wednesday Morning Discussion

B 59 December 30, 2010 Marsha

Groups “Coffee & Conversation”

with facilitators

Notify presenters

B 60 January 5, 2011 Deirdre

date/time/logistics of session.

All workshops are given a date,

day identification, time and room

assignment based on anticipated

B 61 January 5, 2011 Deirdre

size, and track identification.

Communicate dates, times &

rooms to Tracy.

Ongoing update of conference

C 62 website with additional January 13, 2011 Tracy

presenters/ sessions

Email staff to register online for

D 63 January 15, 2011 Lois

conference by Feb 11

Notify Division of Child

B 64 Development of workshops as January 31, 2011 Lois

courtesy

Send out travel form to all

E 65 speakers for whom NCPC is February 4, 2011 Blanche

paying travel expense

Send out contract or honorarium

E 66 February 4, 2011 Blanche

form to speakers we are paying

Invite NCPC Board Members to

A 67 February 9, 2011 Diane

conference

D 68 Early Bird Deadline February 11, 2011

D 69 Close staff registration February 11, 2011 Lois

Change online registration

D 70 February 11, 2011 James

payment amount to $TBD

Purchasing of t-shirts for NCPC

C 71 February 28, 2011 Yvonne

Store



58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 7 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible

Sponsor deadline to be included

C 72 in program and for names on February 28, 2011 Tracy

bags/badges

Email the lead workshop contact

B 73 March 1, 2011 Deirdre

with and for final information

Create online conference “guest”

forms that will allow local

D 74 partnerships to register guests for March 1, 2011 Scott

the Conference Celebration

Lunch

Link conf web page to online This needs to be discussed how to handle

C 75 March 1, 2011 Eric

guest registration forms after selection of vendor

Notify local partnerships of the

option to invite additional guests

C 76 to the Celebration meal. Send March 2, 2011 Tracy

web link to guest registration

form.

E 77 Speaker travel form due date March 4, 2011 Blanche

Make travel arrangements for

E 78 March 15, 2011 Blanche

selected speakers

Weekly and later daily

transmission of online payments

D 79 received by NCPC and March 15, 2011 Deirdre

electronically submitted to

Meeting Details

Identification and invitations to

C 80 VIPs for Conference Celebration March 18, 2011 Tracy

Lunch

Finalize all other orders for

conference “bag” items (bags,

C 81 March 18, 2011 Yvonne

nametag holders, nametag inserts,

etc.

C 82 Conference Program to Printer March 25, 2011 Eric



58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 8 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible

Provide ongoing support of the

D 83 March 31, 2011 James

conference web pages

Recruit all volunteers and room

B 84 March 31, 2011 Deirdre

hosts

Email Unpaid Guests that

D 85 March 31, 2011 Connie

Registration Ends

Management team sign up for

A 86 April 1, 2011 Lois

Registration Desk Area

Deadline for NCPC staff & Board

D 87 registration for conference/hotel April 1, 2011 Lois

rooms

Regular Registration Ends at

D 88 midnight; change price on April 1, 2011 James

website April 1 early.

Final airline tickets must be

E 89 April 1, 2011 Blanche

purchased for speakers

Obtain pictures from LPs for

C 90 April 1, 2011 Eric

slide show

Remind EDs about deadline for

C 91 April 4, 2011 Stephanie

guests at special meal functions.



Deadline for local partnership

D 92 registration for extra Celebration April 4, 2011 Blanche

meal tickets. Notify Deirdre of #

Reserve 17’ truck for pickup on

A 93 April 4, 2011 Yvonne

Friday before conference.

Program and all other “bag”

C 94 April 8, 2011 Yvonne

items must be at NCPC

Recruit volunteers for receptions

A 95 April 8, 2011 Yvonne

and meal set-up

Make copies of Certificate of

A 96 April 11, 2011 Yvonne

Attendance to have at desk

Participant/presenter Nametag

D 97 April 13, 2011 Blanche

Dbase prepared and proofed

58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 9 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible

Include updates memo about

A 98 special sessions for board April 13, 2011 Diane

members, the ED Forum, etc.

VIP Guest Names and Numbers

A 99 April 14, 2011 Diane

for Celebration meal due



E 100 Travel Forms to keynote speakers April 15, 2011 Blanche

Coordinate logistics related to

C 101 sponsorships, donations, benefits, April 15, 2011 Tracy

etc.

Awards – Karen W. Ponder;

A 102 April 15, 2011 Connie

Ashley Thrift Award

B 103 Finalize all room hosts April 15, 2011 Deirdre

Coordinate Lunch Centerpieces if

C 104 coming from vendor & let April 15, 2011 Tracy

Deirdre know

Send confirmation of schedules to

B 105 April 18, 2011 Deirdre

all room hosts with instructions

Finalize Count and Submit Meal

A 106 April 18, 2011 Deirdre

Guarantee to hotel

A 107 Staff Office set up April 19, 2011 Lois

Proof, edit final nametag list

D 108 April 20, 2011 Yvonne

against registration report

Development, design and printing

of all sponsorship signage, 100%

C 109 April 20, 2011 Tracy

LP board giving poster, stage

décor and logistics

Finalize Opening Reception and

C 110 April 21, 2011 Contractor

Activities

Process all registrations, checks

D 111 and invoices for on-line April 22, 2011 Deirdre

registrations, receipts, etc.

58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 10 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible

Coordination of all AV logistics

C 112 related to opening session and April 25, 2011 James Also Deirdre & Eric

conference luncheon

Determine if on-site copy machine

A 113 April 25, 2011 Sue

should be ordered

Hotel master reservation

list/master bill list due to Deirdre

D 114 (includes staff, board members, April 25, 2011 TBD

speakers that NCPC pays travel

expense)

Room Host Workshop Evaluation

B 115 April 25, 2011 TBD

Envelopes

Make Reserved tables signs for

C 116 April 25, 2011 Yvonne

VIP’s

Write, coordinate special

remarks, speeches by NCPC staff

C 117 April 25, 2011 Tracy

and board at opening session and

luncheon

B 118 Prepare all workshop signs April 26, 2011 TBD

A 119 Bag Stuffing April 26, 2011 Deirdre NCPC staff?

Prepare all CDs, DVD that will be

C 120 April 26, 2011 Eric

required

Advise Meeting Details of any

A 121 changes received during Easter April 27, 2011 Lois

Break

C 122 Coordinate Press Coverage April 27, 2011 Tracy

D 123 Review name tags April 28, 2011 Deirdre

Submit information, design and

C 124 print the final program “Change April 28, 2011 Eric

Sheet”

Coordinate & finalize logistics

C 125 April 29, 2011 Tracy

related to the Reception

Coordination of all AV logistics

B 126 April 29, 2011 James

for workshops



58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 11 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible

Plan Conference Office on-site

A 127 April 29, 2011 Deirdre

needs

DESK COPIES (3) of workshops

printed by room, number, and

B 128 April 29, 2011 Deirdre

time. These are reference

documents.

A 129 Truck Loading May 1, 2011 James

Truck unloading at Convention

A 130 May 1, 2011 James

Center

D 131 Conference On-site Registration May 2, 2011 Deirdre

A 132 Pre-Conference Day May 2, 2011 Deirdre

Oversee general conference

A 133 logistics, problems, registration, May 2, 2011 Deirdre

AV set-up, meals

Coordinate VIPs (Governors,

C 134 First Ladies, other high level May 2, 2011 Tracy

elected officials

A 135 Conference Set-Up May 2, 2011 Deirdre

A 136 Conference Begins May 3, 2011 Deirdre

Organize staff and mange NCPC

C 137 May 5, 2011 Yvonne

store area

Conference Celebration Meal (set-

C 138 May 5, 2011 Contractor

up, look, and agenda).

A 139 Conference Ends May 5, 2011 Deirdre

Conference Evaluation Form sent

F 140 May 13, 2011 TBD

to attendees by zoomerang or SM

F 141 Thank you letter to presenters May 13, 2011 TBD

Determine how to communicate,

F 142 eval results for workshops to May 18, 2011 Contractor

presenters

Create the post-conference

F 143 website, solicit handouts from May 20, 2011 Tracy

speakers and post them online

58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 12 of 13 Timeline alpha date

2011 National Smart Start Conference Timeline

As of July 20, 2010

Person

Group # Task Due Date Completed date Comments

Responsible

Clean Up all follow-up and close

F 144 June 15, 2011 Deirdre

out the conference

F 145 Follow-Up on all unpaid invoices June 15, 2011 Deirdre

F 146 Process hotel bill June 24, 2011 Connie

Start Conference Program

booklet design including

C 147 Eric Not doing 2011

certificate of attendance in

conjunction with web design.









58a564bb-2fef-454e-9997-1fb7da17e008.xlsx, 7/20/2010

Printed: 11/27/2011, 7:09 PM Page 13 of 13 Timeline alpha date



Related docs
Other docs by linzhengnd
F_Rehab
Views: 0  |  Downloads: 0
affirmative asylum
Views: 1  |  Downloads: 0
er-oz_spor_malzemeleri__fiyatlar_a_dan_z_ye
Views: 19  |  Downloads: 0
Questions to homeworks 1 and 2
Views: 0  |  Downloads: 0
_FP7_partnerkeres__int_zm_nyek_honlapra
Views: 0  |  Downloads: 0
200811251358390.November 24_ 2008
Views: 0  |  Downloads: 0
2nd Grade Summaries Theme 3
Views: 1  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!