0551D 07g - CD - Cx Comments.xlsx - State of Ohio

Document Sample

Shared by: niusheng11
Categories
Tags
Stats
views:
0
posted:
11/26/2011
language:
English
pages:
14
STAN Engineers

7887 Washington Village Drive, Suite 295, Dayton, Ohio 45459 Phone 937-438-0177 Fax 937-438-0183



Xenia City School District

Commissioning Design Review Comments

Construction Documents



School Name: Cox Elementary

Project No.: 10-1632.04

Date Issued: January 7, 2011

Issued By: Philip J. Becker, PE, LEED AP, Commissioning Authority, pbecker@stanengineers.com

Distribution: Jeff Lewis, Xenia Community Schools; James Froehlich, Scaparotti Construction Group; Keith Krzeminski, Been Kuo, OSFC





As part of the project team, we are making these comments in an effort to improve the overall quality of the project. The specific intent of these comments is to raise questions about

issues such as operation, maintainability, and safety that may impact the short or long term operation of the facility or the ability of the design to function properly. Please have the

appropriate member of the design team review and comment on the following items. We are available to discuss any questions you may have. Note: New comments are in BOLD

text.





Item Comment Response Status

BUILDING ENVELOPE GENERAL (BG)

BG1 Review comments are based on the requirements of the Ohio School Design Manual. No Response Needed N/A

BG2 The Ohio School Design Manual recommends testing of the building envelope by pressurization (no No Response Needed N/A

more than .04 cfm/sf loss through the envelope at a pressure of 1.57 psf). Comments on the

building air barrier are aimed at achieving this level of performance.

BG3 Air barrier systems for a building enclosure are materials interconnected to form assemblies (such No Response Needed N/A

as walls, roofs, windows, etc.) with flexible joints that can accommodate expected relative

movement of the assemblies. Where called for, air barriers should be installed to resist both wind

and interior fan pressures as well as movement of the structure. We recommend that these

materials and joints to be identified in the specifications and on the drawings.



BG4 Comments that reference a specific drawing are general in nature. They are intended to be applied No Response Needed N/A

to similar details, assemblies, and conditions.









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 1

Item Comment Response Status

BUILDING ENVELOPE (B)

B1 SD: This building may require an air barrier to pass an air pressurization test as recommended by DD: Testing is specified in Division 01 Closed

the Ohio School Design Manual. We recommend that the architect of record provide test Specification Section 014100 - Air Barrier

requirements to the project specifications as follows: Air leak test shall be performed and not Quality Control

exceed .04 cfm/sf at 1.57 psf. We recommend the air barrier to be identified on details with a

specific lintetype consistently throughout details. DD: Spec section 072723 (1.6)(F) identifies

testing on mock-up panel. Please confirm if testing will be performed on main building. CD:

Comment closed.

B2 SD: The Ohio School Facilities Commission "Guidelines for Commissioning" in the construction DD: Testing is specified in Division 01 Closed

phase recommends thermal imaging testing as a part of envelope commissioning . We Specification Section 014100 - Air Barrier

recommend the architect of record consider adding test requirements to project specifications to Quality Control

include thermal imaging of all parts of the building envelope. DD: Please confirm if the Owner will

incorporate this test. CD: Comment closed.

B3 SD: We recommend providing a large scale detail to include the foundation and footing. DD: --- Closed

Detail D/A5.A provided, comment closed.

B4 SD: We recommend providing cavity drainage material to base of wall cavities consistently --- Closed

throughout drawings. DD: Comment closed.

B5 SD: We recommend all exterior jamb details allow insulation to extend fully to jamb blocking. --- Closed

Consider providing large scale details. DD: Details provided on sheets A6.2 thru A6.5, comment

closed.

B6 SD: We recommend an air barrier to extend fully to door and window jambs and be sealed to the --- Closed

frame. This may require a transition strip to overlap at openings. Consider providing large scale

details. DD: Details provided on sheets A6.2 thru A6.5, comment closed.

B7 SD: We recommend that an air barrier overlap the wall system at the window head & sills and be --- Closed

sealed to the windows. This may require a transition strip to overlap at openings. Consider

providing large scale details. DD: Details provided on sheet A6.4, comment closed.

B8 SD: We recommend a continuous transition of air barriers from wall to roof. Various roof overhangs --- Closed

& parapets do not show a continuous air barrier. DD: Comment closed.

B9 SD: We recommend that vertical air barriers (walls) and roof membranes that form air barriers --- Closed

overlap between 12" and 24" to maintain integrity of air barrier. DD: Comment closed.

B10 SD: Section 2603.4 of the Ohio Building Code requires a thermal barrier between the foam plastic --- Closed

insulation and the metal deck of the roof assembly. We recommend the architect of record review

this section for compliance. DD: Comment does not apply to polyisocyanurate, comment closed.



B11 SD: We recommend the architect of record to review compliance for combustible roof materials. DD: Specifications for fire-retardant treated Closed

i.e. plywood that may need to be fire retardant. DD: Comment still applies. CD: Comment closed. plywood will be added to Specification

Section 061600, Sheathing.

B12 SD: We recommend lapping roof membrane completely over top of roof curbs and providing an --- Closed

airtight seal to maintain integrity of air barrier. Confirm if curbs or equipment will be placed on top

of roof. DD: Comment closed.









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 2

Item Comment Response Status

B13 SD: We recommend providing air and thermal barriers for roof penetrations where voids occur for --- Closed

details including drainage, curbs, plumbing, mechanical, hatches, etc. to communicate barrier

transitions. Consider providing large scale details for these items. DD: Comment closed.



B14 SD: We recommend that a wall mock-up be constructed to verify the construction methods & --- Closed

materials and assure that wall performance will be satisfactory. We recommend the mock-up

include more components found in walls and exhibit how the air barrier in the wall transitions to the

roof. A mock-up based on these recommendations will be larger than a typical masonry mock-up.

We also recommend that the mock-up be detailed on the drawings. The mock-up should include

the following building components: DD: Spec section 042000 (1.7)(G) provides adequate mock-up,

comment closed.

Foundation

Exterior wall materials

Thermal insulation

Air barrier

Wall flashings & weeps

Cell vents (top of wall)

Typical parapet/eave detail

Ventilated attic/soffit spaces

Transitions from wall to roof/roof to wall (flashing & insulation details)

Typical wall penetrations

Doors

Windows

Light Fixtures

Electrical outlets

Louvers

Etc.

Typical roof penetrations

Plumbing vents

HVAC vents

Equipment curbs

Roof & attic vents

Drains

B15 SD: We recommend providing details for sun shade devices or canopies to ensure any DD: Sunshades are being considered for Closed

penetrations through the wall cavity and air and thermal barriers are sealed properly. DD: Detail deletion as a Value Engineering item. If

sheet A6.7, we recommend to provide additional spray-foam insulation after areas are cut out for they remain in the project, a note will be

mounting. CD: Note added, comment closed. been added to cover this in the

Construction Documents (CD) Phase.

B16 SD: Care should be taken to ensure the curtain wall system is sealed to provide a continuous air --- Closed

and thermal barrier. DD: Comment closed.

B17 SD: Please review material note 58 on sheet A5.1. It appears this is a spray-foam insulation. DD: --- Closed

Material note 58 omitted, comment closed.









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 3

Item Comment Response Status

B18 SD: Wall sections 2, 4/A5.1, we recommend providing a continuous air barrier to the CMU back-up --- Closed

wall. DD: Detail 3/A2.3 provided and addresses comment, comment closed.

B19 SD: Wall section 4/A5.1, we recommend providing a continuous insulation either at top of parapet --- Closed

or between roof plane and metal wall. This occurs at other similar details. DD: Detail 4/A2.3

provided and addresses comment, comment closed.

B20 SD: Wall section 4/A5.1, we recommend providing continuous insulation in the wall cavity where DD: This has been revised and will be Closed

the wider CMU block is located. DD: Comment still applies to 12” wide CMU located at base of shown on the final CD Phase documents.

wall. CD: Comment closed.

B21 SD: Wall section 22/A5.7, we recommend providing a continuous air barrier and possibly an DD: The manufacturer does not Open

exterior substrate over the metal walls. DD: Detail reference is now 64/A5.16. Please provide recommend substrate, and continuous air

material note as drawings progress. CD: Please confirm if the air barrier is a material barrier is a part of the system. The air

incorporated on the backside of the metal wall panel as indicated with the linetype. Also, barrier is delineated.

confirm if the seams of the product prevent air flow from entering into the wall cavity.



B22 SD: Wall section 24/A5.7, we recommend providing a continuous air barrier from the lower roof DD: This will be modified and shown on the Open

plane up the wall to upper roof plane. DD: Detail 1/A2.4 provided. We recommend to provide a final CD Phase documents.

continuous air barrier behind metal wall panels. CD: Please confirm how the air barrier is

adhered to the metal framing.

B23 SD: Wall section 29/A5.8, we recommend providing a continuous air and thermal barrier above the DD: The air/thermal barrier is shown, but Open

window to underside of roof deck. DD: Detail reference is now 30/A5.8. It appears spray-foam better representation and notation will be

insulation has been provided. Please confirm with material note. CD: Also, if the spray-foam provided to clarify.

insulation is being provided and performs as an air barrier then note '2' for a separate air

infiltration barrier may not be required. Please review.

B24 SD: Wall section 32/A5.9, we recommend providing continuous insulation from the sill down to the --- Closed

roof plane. DD: Refer to detail 3/A2.4. Spray-foam insulation now provided, comment closed.



B25 SD: Wall section 41/A5.11, we recommend providing a continuous air barrier from the top of DD: Not sure if this is closed as noted, but Closed

window up to the top of the parapet. DD: Detail not located in review set, comment closed. the air barrier is shown and clarified on the

blow-ups.

B26 SD: Wall section 44/A5.12, we recommend providing a continuous air barrier at the metal wall DD: The manufacturer does not Open

panel locations. DD: Detail reference is now 47/A5.12. Comment still applies to provide an air recommend substrate, and continuous air

barrier between metal wall panels and framing where condensation may occur. CD: Please barrier is a part of the system. The air

confirm if the air barrier is a material incorporated on the backside of the metal wall panel as barrier is delineated.

indicated with the linetype. Also, confirm if the seams of the product prevent air flow from

entering into the wall cavity.

B27 SD: Wall section 65/A5.17, we recommend providing a continuous air and thermal barrier from the --- Closed

top of window to the top of the roof plane. DD: Detail reference is now 66/A5.17. Spray-foam

insulation provided, comment closed.

B28 DD: Detail 4/A2.3, we recommend to provide a continuous air barrier over the exterior substrate. DD: This is now graphically represented. Closed

CD: Comment closed.

B29 CD: For window head details similar to 7/A6.5, we recommend to review the wall cavity to Open

ensure condensation is able to weep effectively below the mortar net through the thermal

break down to the weep hole location.









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 4

Item Comment Response Status





GENERAL (G)

G1 SD: We would like to review the owner's project requirements (OPR) and the basis of design (BOD) Typically the Commissioning Agent is to Closed

or schematic design narrative. These will be used to insure that proposed systems will meet the assist the Owner in completing the Owner's

needs of the owner as stated in the OPR. We have attached an example OPR that the owner can Project Requirements (OPR). For this

use as a starting point for creating this document. We have highlighted the areas that require them project the CM has created the OPR and

to edit or add information about this project. Please contact us if anyone has questions on the has verified it with the owner.

information that needs to be included here. DD: This comment still applies. CD: OPR received

and compared to the basis of design document and we have no comments. This comment

is closed.

G2 SD: Please provide the energy model calculations for review when they are complete. OSFC Equest is used as the energy modeling Closed

requires all OSFC projects to use eQUEST (or approved equal software analysis) as part of the program. The model will be updated at

integrated design process. DD: We did not receive the energy and load model outputs, and we each design phase and outputs will be

would also like the inputs. This comment still applies. CD: Energy and load model inputs and included in phase submissions. Are you

outputs received. This comment is closed. requesting input information?

G3 SD: Please provide ventilation calculations for review when they are complete. DD: We will review Ventilation calculation will be included in Open

the ventilation calculations with the CD submission. CD: We have not received these Construction Document Phase.

calculations. Comment still applies.

G4 SD: The mechanical drawings in this package begin with Sheet M2.1. Are there drawings previous Not in Schematic Design. Additional Closed

to this that were not including in the set of drawings? DD: Additional drawings included. Comment Drawings will be added in all phases.

closed.

G5 DD: A copy of the commissioning specifications is attached for inclusion in the project book. We Open

have attempted to number the section and format it to match the project specifications as submitted

to us. If a different format or number is required, please let us know. We recommend that the

current version of the commissioning specification (23 08 00) be removed. CD: The original

commissioning spec (23 08 00) is still included in the specification, we recommend this be

removed.



PLUMBING (P)

P1 DD: We recommend that the engineer provide an automatic shut-off valve with emergency This will be incorporated in the CD Phase Open

pushbutton in addition to the manual shut-off valve for gas to kitchen stove (or other kitchen documents.

equipment) and for science labs. CD: Comment still applies.



HVAC (H)

H1 SD: We recommend that all air handling units are specified with hinged access doors to all - We will incorporate into the Specifications. Closed

sections, lights inside of all sections with access, and windows into sections with dampers or fans. - Specification Section 237313, Article

DD: Comment still applies. CD: This has been added to the specification, comment closed. 2.2,C.4 has been revised to read as follows:

( see attachment)









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 5

Item Comment Response Status

H2 DD: For any fan with a variable frequency drive, we recommend that the specifications require the - We will incorporate into the Specifications. Closed

contractors to provide a sheave change so that the fan motor is producing its full rated horsepower - This requirement was included in

at a VFD speed of 100%. In this way, the controls will keep the motor speed where it needs to be Specification Section 230593, Testing,

to satisfy the system, but if there is excess fan capacity, the control system will be able to take Adjusting, and Balancing for HVAC. See

advantage of it with no other change by the owner. Very often, we see fan motors that are 75% Article 3.6,A.5. We will also include extra

loaded or less with the VFD at 100% speed. DD: Comment still applies. CD: Specification has sheave requirements in Specification

been changed, comment closed. Section 237313.



H3 SD: We recommend the engineer show design condition assumptions near air handling unit - We will incorporate into the Air-Handling Open

schedules, e.g., heating and cooling conditions for the inside and outside, stating temperatures and Unit (AHU) schedules.

humidities. Providing this information on the drawings will be useful for the school district for any - We will incorporate into the Air-Handling

future additions or alterations. DD: More information for the DOAS would also be useful. Comment Unit (AHU) schedules and/or the

still applies. CD: Design conditions are not shown on the mechanical schedules for the air schematics.

handling units. Comment still applies.

H4 SD: Please provide an analysis of why the type of chiller was chosen for use in the design. OSFC - We will provide an analysis of both chiller Closed

would like a complete analysis of air cooled vs. water cooled chillers for the projects to make sure types during the CD Phase.

that not only first cost is considered but energy and maintenance costs as well. DD: An analysis - It would not be cost effective to design

pertaining to the chillers was not included in these documents. Comment still applies. CD: indoor water chillers for this size of a

Comment closed based on engineer's response. building. The cost would be much greater

and take up more building space. The cost

of the project is currently over the budget,

and we cannot afford to add anymore to the

project.

H5 SD: The narrative for the mechanical plans only discuss one chiller, but Sheet M2.1 shows 2 - We will revise the narrative. Closed

chillers. The drawings also show four chilled water circulating pumps and separate equipment - The narrative has been revised to indicate

accessories for the two chillers. Please review and correct this inconsistency. DD: We did not 2 chillers and the pump description has

receive an updated copy of the design narrative. Please provide the updated copy for review. CD: been revised to match the Drawings.

Comment closed.

H6 The basis of design lists the minimum chilled beam water supply temperature as 56°F, while the - We will review temperatures and revise as Closed

maximum unoccupied space dew point is listed as 58°F. This could potentially lead to necessary.

condensation issues on the beams. Please review these temperatures. DD: The entering water - No additional response is required.

temperature for the chilled beams is shown as 57° F on the mechanical schedules. This is above

the maximum space dew point of 56°F. This comment is closed.

H7 DD: We recommend that an analog temperature or pressure gage be installed adjacent to any DDC Although it is a good idea, the budget is Closed

temperature or pressure sensor installed in a water system. If the engineer is in agreement with already a concern; therefore, we do not

this, then it is recommended to have this stated in the specifications and shown on the drawings so feel we can incorporate it into this project.

that the control contractor and mechanical contractor coordinate these locations. CD: Comment

closed based on engineer's response.









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 6

Item Comment Response Status

H8 DD: The installation specifications for the air terminal units indicate the units should be installed to A detail has been created and will be Closed

maintain sufficient clearance for normal service and maintenance. We recommend that all VAVs included in the CD Drawings. A copy of the

and chilled beam units be installed so that they can be maintained. No pipe or duct be closer than detail is attached.

12” from the control panel side of the unit or meet code requirements and manufacturer’s

recommendations. The units should not be installed directly above a light fixture or a ceiling tile

with a speaker or fire sprinkler head which would limit access. Piping, ductwork, conduit, etc.

H9 DD: The winter supply leaving air temperature for the heat wheel of AHU-A201 does not match the We will revise prior to the CD Phase Open

mixed air conditions for the given outside and return air temperatures and flows. The scheduled submission. 64.1 degrees, Fahrenheit is

leaving air temperature is 64.1°F but we calculate a dry bulb temperature of 48.4° F. The entering not correct. The entering air is also a typo.

CFM also appears to be incorrect, though this is not the cause of the heat wheel calculation

discrepancy. CD: Comment still applies. The conditions have not been updated.







CONTROLS (C)

C1 SD: Controls General Comment: It is recommended that some type of controls schematics, Sequence of operations will be included Open

sequences of operation, and points list be provided in the design drawings to clearly communicate with the Specifications. We will review the

to the controls contractor the number of sensors and their specific location in the system. DD: This need for control schematics and points list

schematic is also useful in describing the use of each sensor in the system. For example, a control during future phases.

sequence may be accomplished with just one discharge air sensor in the unit. However, the owner

may desire a sensor in the mixed air section and after each coil for diagnostic purposes. A

schematic is very helpful during the commissioning process to determine if the controls contractor

is meeting the design intent. Additionally, after a period of years drawings are typically retained but

specifications are often missing, leaving no record of the designed operating sequence. CD:

Comment still applies.

C2 SD: As the specification is written, we recommend that the control graphics be described in great Would a control schematic be sufficient? Open

detail for each system. In many cases we see the specification call for graphics but with no

description of what is to be shown on them. DD: We recommend the specifications state as a

requirement that all points and alarms pertaining to that system be displayed somewhere on the

graphic screens. At a minimum, start/stop points, schedule, all set points, reset schedules, inputs,

and outputs for each system need to be shown. Labeling of alarms is also a continual problem.

We also recommend that all set points be adjustable and that the acceptable range of adjustment

be stated in the as-built sequence of control. Some control systems allow inputs to be changed

(e.g., Invensys and Honeywell allow this for some inputs). For systems that do not have this

feature, all sensor inputs should be required to be brought into a virtual point so that the virtual

point can be manipulated for system testing. CD: Comment still applies. A control schematic

would be helpful for describing some of these points, but a list of the requirements for the

graphics would ensure that all desired points, setpoints, schedules, and alarms are properly









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 7

Item Comment Response Status

C3 SD: We recommend that the engineer show the approximate location of remote sensors such as Devices will be identified in the Closed

duct static pressure sensors and hydronic system differential pressure sensors on the design M6 Drawings

drawings rather than leaving their location up to the contractor. Often, when location is left up to

the contractors, we see them placed in locations that are convenient for the contractor but not

necessarily the best location for serving their intended purpose. Also, it should be stated that the

contractor shall note the exact location of the remote sensors on the as-built control drawings for

future reference. DD: Sensor locations have been shown on the drawings. This comment is closed.





C4 SD: Heat wheel control has consistently been a problem on nearly every OSFC project we have Sequence of operations will be included Open

commissioned. The problems usually start with an ambiguous sequence of operation for the heat with the Specifications. Please review and

wheel and we recommend that close attention be paid to this part of the system. We would be comment where necessary.

happy to discuss this in more detail with the engineer to share some of the lessons learned on

other jobs. DD: The air handling units specify an integrated sequence for heat wheel control.

However, there is not a detailed set of sequences for the heat wheel in the DOAS section or the

sequence of operations for the dedicated outside air unit. We recommend more clarification to

ensure proper operation.

C4 contd CD: Sequence of operation has been included in the specification in the DOAS section. As

this unit is 100% outside air, we are confused as to what is implied by "economizer" in the

heat wheel sequences. Please clarify.







C5 SD: We recommend providing labeling for all control system sensors, panels, and actuators. The We will incorporate into the Specifications. Open

names on the labels should be required to match the point names given on the computer graphics

and also shown on the as-built drawings. We recommend that the specifications clearly state the

requirement for labeling the control system. DD: Comment still applies. CD: A labeling

requirement could not be found in the specification. Comment still applies.

C6 DD: We have seen many problems in the field involving interface of controls between the building We will review in the CD Phase and provide Closed

automation system and other equipment that is provided with manufacturer's controls. Simple as necessary

statements in the specification that require all panels to communicate via Bacnet or Lon tend to

leave the door open for problems. Where possible, we recommend that the building automation

system contractor be responsible for control of as much of the systems as is practical. We do not

recommend packaged controls for pumping systems or energy recovery units as these systems

can easily be picked up by the BAS contractor. Where interface is required, such as at boilers,









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 8

Item Comment Response Status

C6 cont'd The dedicated outside air handling unit will require more coordination with regards to integrating the

internal controls and the network interface. Please specify which points are necessary for

monitoring and include this information in the sequence of operations and the section detailing the

DOAS. CD: Information describing the equipment interfacing for the boilers, chillers, etc. is

provided in Section 23 09 00 Article 1.8. A list of points for the DOAS controls

communication is included in Section 23 73 16 article 2.13. Comment closed.









C7 DD: We recommend that the specifications note that the controls contractor shall convene a pre- We will review in the CD Phase and provide Closed

submittal meeting with the engineer and commissioning agent within one month of the notice to as necessary

proceed. The purpose of this meeting is to review the sequences of operation, outline where the

proposed system deviates from the specified sequence of operation, and identify potential

problems with the specified sequence. Once the sequences of operation are agreed to by all

parties, the contractor should proceed with the formal controls submittal process. In addition, we

recommend that the control contractor should be required to submit a print out of all graphics

C8 DD: Condensate sensors are shown on the drawings and discussed in the sequences of operation, We will review in the CD Phase and provide Open

but not mentioned in the DDC or chilled beams specifications. Please identify the party responsible as necessary

for providing this item. We also recommend that the condensate sensor be required to be

thoroughly cleaned when construction is complete but prior to owner occupancy. Previous

experience has shown that these sensors will give false readings if dirty. CD: Condensate sensors

are still not discussed in the DDC or chilled beam specifications. Comment still applies.



C9 DD: We recommend including a high temperature or enthalpy limit to disable the economizer for We will review in the CD Phase and provide Open

the air handling units. CD: Comment still applies. as necessary

C10 DD: More information should be provided to clearly communicate the lead/lag sequencing for the We will review in the CD Phase and provide Open

boilers and the chillers. This should include a time delay before the lag equipment enables or as necessary

disables as well as how often the equipment rotates the lead position. CD: Comment still applies.





ELECTRICAL (E)

E1 SD: General: We recommend the generator remote annunciator panel be located at The remote annunciator will be located for Closed

administration office area or custodial office for monitoring. DD: Comment still applies. convenient access by staff as indicated.

CD:Generator Panel is located in main mechanical room. Comment closed.









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 9

Item Comment Response Status

E2 SD - Sheet E6.1 Fire Alarm Plan: We recommend locating main fire alarm panel in the The fire alarm control panel has been Closed

administration office area for convenient monitoring and operation. Add pull stations at building located in the same room as the telephone

exits. Consider adding smoke/heat detectors in mechanical/electrical technology rooms. DD: service demarc in an effort to minimize the

Engineer's preference. communication line run distance. Pull

stations and detectors will be included as

noted.









E3 SD: Sheet E4.1, Classroom Lighting: Please provide a detailed sequence of operation for the Details will be provided with the Open

classroom dimming system including foot-candle levels required. Note: Not all light fixtures in Construction Documents. Light levels will

classroom should be dimmed at the same rate. Consider multiple zones due to more daylight near be designed around Ohio School Design

window wall and much less daylight on the corridor side of room. DD: Comment still applies. CD: Manual (OSDM) and Leadership in Energy

Lighting Control Schedule has been added. Control Schedule indicates 35FC, however and Environmental Design (LEED)

OSDM lists 50 FC for direct lighting systems. Please revise foot-candle level. recommendations. The level of daylighting

zone control will be provided to the best

extent allowed within the project budget.



E4 SD: General: We recommend emergency lighting in all electrical closets, tech closets, mechanical We will comply Closed

and electrical rooms. DD: Completed.

E5 SD - Sheet E5.1 Power Plan: Feeders to DP-B are shown installed above the ceiling. Contractors Drawings will be revised giving the Closed

install a large portion of the feeders below the floor slab to save time/cost. Please reconsider. DD: Contractor the option of installing feeders

Completed. underground or above ceilings.

E6 SD - Sheet E7.1 Single Line: Please consider 480/277 volt as the distribution voltage in lieu of Considering the length of feeders versus Closed

120/208 to save the cost of additional and larger wiring and larger capacity equipment. DD: the addition of transformers (including

Engineer's preference. space, heating load, and energy losses),

we believe that greater cost and energy

savings will be achieved using

208/120-volt distribution.

E7 SD - Sheet E7.1 Single Line: We recommend a grounding electrode detail be included on the Grounding details will be provided on the Closed

drawings. DD: Completed. E1 Series Drawings as well as in the

Project Manual.

E8 SD: Please locate spare fuse cabinet on drawings in electrical room. DD: Comment still applies. The cabinet will be shown on Construction Open

CD: Two spare fuse cabinets are now shown in main electric room Sheet E6.3. Documents.









E9 DD: Sheet E1.3: Detail #11 - Please evaluate "a/b" switching for these 6-Lamp fixtures. Far right Will evaluate and revise accordingly Open

fixture seems appropriate where "a" ballast controls (4) outboard lamps (Two on each side of

fixture). However, the other two fixtures seem to depict the "a" ballast controlling just (2) outboard

lamps (One on each side of fixture). CD: "d" night light ballast neutral/hot is shown from two

different power sources. Please correct.









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 10

Item Comment Response Status

E10 DD: Sheet E1.3: Detail #11 - Reference is made to an emergency fluorescent power unit. Should Reference to the emergency fluorescent Closed

this portion of the detail actually be depicting a night light switching scheme. Please clarify. CD: power unit will be deleted.

Comment closed.

E11 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - Neon pilot light adjacent to S2: Neon light will indicate that sufficient natural Open

Please clarify the purpose of this device. Include in sequence of operation if applicable. CD: Can daylight is present to allow manual dimming

LED pilot light be specified in lieu of neon light for longer lamp life? of electric lights when the system is in

daylight by-pass mode. See Note No. 1 on

the E4 series drawings.



E12 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - Master S2 switch at teacher's desk: Quiet Time (Study Time) control sequence Closed

"Quiet Time 1 Hour" mode is not referenced or defined in sequence of operation. CD: Completed. will be clarified.



E13 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - S1 and S2 switch master On/Off Daylighting control sequence will be Closed

button: When this button is pushed "On" will the daylight harvesting system be activated also. clarified.

Please clarify and include in the sequence of operation. CD: Completed.

E14 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - We recommend switching stations S1 Switch plates are specified to include Closed

and S2 be provided with labeling of buttons. CD: Completed. engraved or permanently silk-screened

legend in Specification Section 260943.









E15 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - In the sequence of operation "Daylight Daylighting control sequence will be Closed

Override" is said to close relay R3. This implies that the lighting fixtures controlled by R3 will come clarified.

on even tough the daylight harvesting system has them turned "Off". If this is the case please take

note that the fixtures with R3s next to them are not near the window so these would not be the

fixtures you would expect the daylight harvesting system to have turned "Off". Please evaluate.

CD: Completed.

E16 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - In the sequence of operation "Daylight Daylighting control sequence will be Closed

Override" is said to close relay R3. Will this mean that the lights come to "Full On"? Please clarify. clarified.

CD: Completed.

E17 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - The sequence of operation does not Control sequence will be clarified. Closed

mention control of relay R4. Relay R4 is shown one time at a single fixture. Please clarify. CD:

Completed.

E18 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - In the sequence of operation Control sequence will be clarified. Closed

occupancy sensor will automatically open R1 relay. Does this mean that all lights will go out?

Please clarify. CD: Completed.

E19 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - In the sequence of operation the "A/V Control sequence will be clarified. Closed

Light" mode is said to close relay R1 and open relays R2 and R3. What is the overall lighting goal

of this mode? Or what do relays R1, R2 and R3 actually control. Please clarify. CD: Completed.



E20 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - Fixtures have step dimming ballasts. Yes. Closed

Will these ballasts step the fixture lamps in a single 50% increment? Please clarify. CD:

Completed.







934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 11

Item Comment Response Status

E21 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - Fixtures have step dimming ballasts. Control sequence will be clarified. Closed

Will the day light harvesting system ever control the lamps to "Off"? Please clarify. CD: Completed.



E22 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - The "Daylight Dimming Zone" is Daylighting control zone is always the first Closed

depicted as the first two rows of lighting fixtures nearest the window. Will this zone look the same two rows of lighting nearest the windows

in the deeper kindergarten classrooms B105, B107 and B109. Also, what will the daylight dimming unless noted otherwise on the lighting plans.

zone look like in first and second floor end classrooms B112 and B207. Could these dimming

zones be depicted on the plan drawing for each individual classroom to eliminate confusion. CD:

Completed.

E23 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - We recommend defining acceptable Daylighting control sequence will be Closed

footcandle levels in the classrooms when under day light harvesting mode. We recommend clarified.

defining these levels in terms of elevation such as "at desk height". We recommend stating that the

lighting fixtures controlled by the day light harvesting system shall be at there lowest level of light

output when natural light plus the artificial light (at its lowest setting) exceeds the minimum

requirements of the space. CD: Completed.







E24 DD: Sheet E1.4: Typical Classroom Wiring Diagram Detail - We recommend lighting control Part 3 of Specification Section 260943 will Closed

representative/technician be required to provide initial set up of lighting control systems with be reviewed and revised accordingly to

demonstration and training to owner/commissioning agent and also post commissioning repairs and clarify both pre and post commissioning

adjustments based on commissioning report. It should be specifically stated that these two requirements.

requirements will be accomplished during separate time frames implying separate site trips for each

provision. (Often we find manufacturer's representatives hesitant or unwilling to return to make

repairs and adjustments needed after discovery by commissioning agent.) CD: Completed.



E25 DD: Sheet E4.1: Electrical Room A126 - We recommend rotating lighting fixtures 90º to their We will review. Closed

current orientation to run length wise with the switchgear equipment in the room. CD: Engineer's

preference.

E26 DD: Sheet E4.1: Corridor A122 - We recommend that can lighting fixture at south end of corridor We will review. Closed

near intersection of Corridor A112 be placed on emergency circuit. CD: Completed.

E27 DD: Sheet E4.1: Music A124 - This room has a photo sensor shown. However, there is no lighting The daylighting control sequence will be Closed

control detail for this space. Please clarify day light harvesting requirements for Music Room. CD: clarified.

Completed.

E28 DD: Sheet E4.1: Gymnasium A147 - North side of gymnasium plan indicates lamp ballast control Lighting plan and typical details will be Closed

configuration. This configuration information does not seem to match up with Detail #11, on Sheet reviewed, coordinated, and revised to agree.

E1.3. If this lamp ballast control configuration information and Detail #11 are to match please

provide cross reference information on plan. CD: Completed.

E29 DD: Sheet E4.3: Stairs B100 - Type "FW-1X" lighting fixture at east side of stair may be positioned We will clarify in CD Phase. Open

under the stair landing. However, there is no mounting height for the FW-1X fixtures. Please

clarify. CD: Wall mount fixtures should include mounting height. Comment still applies.









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 12

Item Comment Response Status

E30 DD: Sheet E4.4: Stairs B111 - This stair has only (2) type "F22-X" lighting fixtures at its top. Will evaluate and revise accordingly. Open

Lighting level in stairwell may be low particularly at the bottom. Please evaluate. CD: Fixtures are

now type F-8X and are not on fixture schedule. Please revise.

E31 DD: Sheet E5.1: Main Cross-Connect A101 – A minimum of two emergency 120V circuits must be Emergency circuits will be provided. Open

provided in each technology Room for UPS connection per OSFC standards, Chapter 8, Section

1.09 Technology, Item D. CD: Comment still applies.

E32 DD: Sheet E6.1: Electrical Room A126 - Provide pull station at exterior exit from room. CD: A pull station will be included. Closed

Completed.

E33 DD: Sheet E6.3: Main Electrical Room A126 – As currently depicted some pieces of the main A wider door will be provided in the Closed

switchgear may not fit through the door of the electrical room. Please evaluate. CD: Completed. electrical room.



E34 DD: Sheet E6.3: Kitchen A130 - Reminder all 120V receptacles for this area must be GFI type per Ground-fault circuit interrupter (GFCI) Open

NEC 210.7, (B), 2. CD: Comment still applies. See circuits ALX2 for reach-in refrigeration. protection will be provided. Receptacles

Please verify all kitchen circuiting for required GFCI protection. that are not readily accessible will be

protected at the circuit breakers.

E35 DD: Sheet E6.3: Mechanical Courtyard – We do not find specification for generator connection Clarification will be included in CD Phase. Open

cabinet. Please provide additional noting for this piece of equipment. CD: Comment still applies.



E36 DD: Sheet E7.1: Single Line Diagram - We do not find information in switchgear specification or on Clarification will be included in CD Phase. Open

single line diagram for kirk key switch depicted in switchgear. Please provide additional noting for

this piece of equipment. CD: Comment still applies. Also, Surge Arrestors are included in this

specification. If this is a requirement we recommend the device being shown on the single

line diagram to ensure it's installation.

E37 DD: Sheet E7.1: Single Line Diagram - For safety and maintenance purposes we recommend that Feeder protection and panel disconnect Closed

Panels ALX1 and ALX2 each be provided with a MCB as they are fed directly downstream of an means are provided ahead of the ATS for

automatic transfer switch with two potential power sources. CD: Engineer's design preference. both power sources.

Comment closed.

E38 DD: Sheet E7.1: Single Line Diagram - ATSs are shown as 4-Pole. Neutral at generator should be Grounding is shown on Drawing No. E1.2, Closed

indicated as being bonded to generator ground. CD: Completed. Detail No. 10.

E39 CD - Sheet E5.3: Recommend elevator sump pump and auto-door operators be on Open

emergency power in lieu of normal power.

E40 CD - Sheet E2.1 Site Plan: Indicate site lighting conductor sizes and homerun panel. Open

E41 CD - Sheet E4.1: Spotlights in center of gym do not appear to be protected from thrown balls. Open

Please consider another location. Switches in gym should be key operated in lieu of

standard toggle.

E42 CD - Sheet E4.1: Are two wall mount occupancy sensors needed in administrative offices? Open



E43 CD - Sheet E4.3: Lighting levels may be low in rooms B130 and B131 due to number of Open

fixtures shown. L-22 light fixture type not on fixture schedule. Same comment for room B222.



E44 CD - Sheet E6.3: Will domestic hot water recirc pump run 24/7? Pump may need a T-stat Open

controller. This motor should have a local fractional HP manual motor starter/disconnect

switch.







934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 13

Item Comment Response Status

E45 CD - Sheet E5.1: Suggest indicating grounding bar locations in all technology rooms. Smoke Open

detectors are shown twice in student dining.

E46 CD - Sheet E5.4: Smoke dampers are shown twice. Provide a schematic detail for smoke Open

damper actuator wiring and circuit requirements. "FAPS" will require 120 volt emergency

circuit and FAPS panel should be shown on the fire alarm plans.

E47 CD - Sheet E7.1 Single Line Diagram: Panels BLX1, ALX3, BLX2 are 225A on diagram and Open

100A on panel schedules.

E48 CD - Sheet E7.1 Single Line Diagram: Why (2) 400A spare switches in MSB and no Open

100/60/30A spares?

E49 CD - Generator Specification 263213: We recommend adding requirement for on-site load Open

bank testing.









934a3fdb-df4d-49a9-9fa4-522748a89ede.xlsx Page 14



Other docs by niusheng11
TEXAS ADVANCED COMPUTING CENTER Safe Travels
Views: 0  |  Downloads: 0
The Trek
Views: 3  |  Downloads: 0
article-240637
Views: 0  |  Downloads: 0
work presentation 2A
Views: 2  |  Downloads: 0
snort_configure.docx - NEOHAPSIS
Views: 1  |  Downloads: 0
Southern Maine Dressage Association
Views: 1  |  Downloads: 0
Checklists for buying a used car
Views: 17  |  Downloads: 0
mis is riin The Office of Business Services
Views: 4  |  Downloads: 0
Assisted Living_6_
Views: 2  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!