Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



1.0 INTRODUCTION



Local Authorities were required to prepare an updated Assessment of Needs for water

services capital works in their administrative areas in 2006 in view of the scale of

development in recent years. The last such assessment by Waterford County Council

was undertaken in 2004. It covered the period 2003-2006, and has provided the basis

for scheme approval and scheduling under successive Water Services Investment

Programmes.



In order to measure progress since the last assessments were completed, and to

facilitate phased advancement of the Investment Programme up to and during the next

National Development Plan 2007 – 2013, this report identifies a new Assessment of

Needs. The assessment is in accordance with the general guidelines set out in the

Department of the Environment, Heritage and Local Government (DEHLG) Circular

L2/06 and takes fully into account the following:



 Relevant National and EU environmental, public health and water quality statutory

requirements.

 The provisions of the Waterford County Development Plan 2005 – 2011 and

various Local Area Development Plans for Waterford.

 The National Spatial Strategy.

 The South Eastern and South Western River Basin District Management System.

 The Sludge Management Plan for Waterford.

 The County Waterford Rural Water Strategy.

 The National Water and Urban Waste Water Studies.

 The need to support Economic and Commercial Activities, and

 Annex 12 of the EU Commission‟s application to the European Court of Justice in

respect of Ireland‟s implementation of the Drinking Water Directive.



The primary objective of this assessment is to develop an overall strategic investment

plan for the medium to long term for the Waterford County Council administrative

area, and to set out a programme of works required to meet the identified water

services needs. Water services needs include drinking water, wastewater disposal and

storm water management.



The 2006 Census recently published by the CSO shows a population increase of 9.2%

over the 2002 to 2006 period in County Waterford. This increase was greater than the

national average (8.1%), the provincial average (6.5%) and the regional average (8.7%).

It was also significantly higher than the population increase in Waterford City (i.e.

2.6%). This increase was concentrated in the areas near Waterford City, Tramore and

Dungarvan, along the coast and in mid-County Areas. However, all rural areas in the

county showed an increase in population. The total population of Waterford County

Council„s administrative area was 62,167 in 2006, an increase of 5,215 on 2002 figures.



The steady growth in population, commercial/industrial development and tourism in

the County Waterford area over the most recent assessment period has placed

pressures on the capacity of the Council‟s water supply and wastewater treatment

systems to meet growing demand.









1

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



It should be noted that Waterford Local Authorities devote significant resources to

ensure that water quality is maintained at the highest standards. To this end Waterford

County Council operates a management and control system to ensure that water

intended for human consumption is wholesome and meets the requirements of the

Drinking Water Regulations. The aim of this system is to optimise the treatment and

provision of drinking water, and to prescribe procedures for dealing with breaches of

water quality standards, particularly with regard to ensuring public health is protected.

This is achieved by the provision of a detailed monitoring programme as follows:



 Process control monitoring at treatment plants carried out by plant operator.

 Verification/surveillance monitoring of treated water, by Waterford County

Council Laboratory located at the Adamstown Treatment Plant.

 Regulatory monitoring of raw and treated drinking water by the Health Board on

behalf of Waterford County Council

 Surveillance monitoring of drinking water quality by the Regional Water

Laboratory on behalf of Waterford County Council.

 Ancillary monitoring programmes such as Nitrate surveys and groundwater

surveys.



The most recent published report on the quality of drinking water in Ireland for the

Year 2004, notes that, “the overall rate of compliance in Waterford County Council, 95.1% was

below the national average during 2004. The reason for the lower overall quality is the lower than

average microbiological quality of drinking water. There were 11 incidents of E-Coli contamination in

11 public water supplies in Waterford County during 2004 in the Ardmore-Grange-Ballybrusa,

Ballinacourty/Deelish, Dunhill, Dunmore East Regional, Graiguerush, Joanstown, Kilcooney,

Kilgainey, Shanacoole and Stradbally supplies. All of the incidents reported were moderate with the

exception of the Ballinacourty/Deelish and East Waterford Regional incidents in which high levels of

E-coli were detected.



Though compliance with chemical parametric values in public water supplies was generally satisfactory

there were exceedences of the arsenic and nitrate standards that were of concern. Elevated levels of

arsenic were detected in two public water supplies (Ballyogarty and Kill/Bunmahon) while there were

elevated levels of nitrate in two supplies also (Ballyogarty and Adramone)



Compliance with indicator parametric values was below average particularly in the public water

supplies. The main feature of the monitoring results for indicator parameters was the low level of

compliance with the pH parametric value. A total of 40% of the samples analysed in public water

supplies were outside the permitted range.”



The EU Water Framework Directive, which is now being transposed into Irish Law is

an exceptionally important piece of environmental legislation and seeks to ensure that

waters in Ireland will be protected. Waterford County Council is involved in both the

South Eastern River Basin District and the South Western River Basin District and this

work has also been taken into account in the Assessment of Needs. The Serviced

Land Initiative introduced by the Department of the Environment Heritage and Local

Government has also been taken into account as it applies to Waterford County

Council.









2

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



This report includes a summary of the achievements of the Water Services Investment

Programme from 2003 to 2006, and an examination of the main requirements for

water services investment over the period 2007-2014.



This report includes a prioritised list of projects with outline descriptions, cost

estimates, marginal cost assessments and details of the objectives of investment in

terms of the outcomes sought and specific outputs required, to be implemented over

the 2007-2014 period.





2.0 BACKGROUND



2.1 Water Supply



There are currently 103 public water supply schemes in County Waterford many of

which are impracticably small for management purposes. 85% of public water supplies

have less than 100 connections, which highlights the difficulty of supplying water to a

predominantly rural area. In terms of production Waterford County produces

approximately 43,500 m3/day with a little over half being exported to Waterford City

from our East Waterford Water Supply Scheme. The majority of the smaller schemes

depend on relatively small independent water sources with varying levels of

vulnerability to pollution that require significant time and resources to manage on an

ongoing basis. In addition the smaller schemes cannot sustain leakage and are a large

drain on resources, as a single leak of 10 l/min can equal the normal output of a small

scheme. The available resources to manage the large number of schemes is often

stretched and consequently numerous water supply schemes have had isolated water

quality compliance failures mainly relating to chlorination equipment failure or isolated

local pollution instances. This is reflected in the 63 Public Water Supply Schemes that

recorded non-compliance with the Drinking Water Directive over the last 5 years as

listed in Annex 12 of the EU Commission‟s application to the European Court of

Justice in respect of Ireland‟s implementation of Directive 80/778/EEC (the Drinking

Water Directive) which was appended to Circular L11/03.



Current Water Supply Deficiencies:



Many of the water supplies within the county are deficient in one or more respects as

follows:



 Difficulty in the operation and management of supplies due to their age, diverse

nature and extent (103 No.). Amalgamation and rationalisation of sources,

regionalisation of supply networks and treatment is essential to increase the level of

service, improve efficiencies and facilitate increased levels of monitoring and

maintenance.



 Distribution systems that are old and subject to constant breaks and leaks. This is

highlighted by the fact that our 14 largest water supply schemes are currently

running at 40% leakage with ongoing leak detection and repair in place while many

of the smaller schemes are running at 80-90% leakage. This results in unnecessary

overtaxing of sources and a substantial reduction of supply pressures. A further









3

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



knock on effect of this excessive leakage is the ability to extend current public

schemes to amalgamate existing group schemes seeking take over. This is an

unsustainable approach that will lead to more acute supply difficulties as demand

increases and existing distribution systems age.



 Inadequate or no storage leading to major supply problems with resulting

difficulties for consumers, industry and tourism. This is a major problem at peak

summer demand for some of our schemes. For example, many areas of the

Ballinacourty/Deelish scheme experienced severe reductions in level of service for

several weeks last summer in Clonae strand, a major tourist area.



 Inadequate and sometimes no capacity for fire fighting due to small diameter

mains. Virtually all of our small schemes have no realistic fire fighting capabilities.

This is obviously an unsustainable situation.



 Increasing nitrification of groundwater supplies, which has resulted in some being

shut down, for example, the Crooked Bridge and Lefanta boreholes, which

provided necessary augmentation for the Ballinacourty/Deelish and

Lismore/Cappoquin/Ballyduff (L.C.B.) schemes respectively. In addition, elevated

nitrates at the Monument borehole currently serving the Cappoquin portion of the

L.C.B. scheme and the Ballyhane borehole currently serving the adjacent

Balyduff/Ballylemon scheme are putting this service area at risk. Similarly, the

three sources serving Kilmacthomas town are increasing in Nitrate levels and are

likely to cause supply difficulties in the near future. There is no readily available

back up in all of these cases without rationalisation of supply network and sources.



 Slow sand filtration plants incapable of removing colour in excess of the 20 Hazen

limit in the EU Drinking Water Directive. Examples of this are the L.C.B.,

Ring/Helvick, Kill/Bonmahon and Tallow water supplies. Customer complaints

are quite numerous regarding excessive colour especially after storms and high

rainfall levels.



 General lack of capacity whether source, mains or storage, which is impinging

adversely on economic and housing development. Most urban areas within the

county have come under severe pressure to service development land for housing.

Considerable development pressure exists in many settlement areas throughout the

county with numerous planning applications for multiple unit housing

developments currently under consideration. A quantified review of the current

development pressure is included in section 4 of this report. . At present

Dungarvan does not have adequate storage capacity to service its current demand.

Towns such as Lismore, Cappoquin and Tallow all have marginal water supplies

which must be urgently improved and extended to provide the necessary

infrastructure for additional housing at these locations. A similar case can be made

for villages such as Ring/Helvick, Ballinroad, Ballyduff, Kilmacthomas and

Portlaw where population growth is dependant on services being available for

zoned land.



 Apart from the East Waterford Scheme, there are no other Regional Water

Supplies in the county. Major rationalisation and regionalisation of the entire









4

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



system is therefore a critical and urgent necessity. Increasingly stringent standards

regarding quality and service can only be achieved by modern treatment methods

in schemes that are properly resourced and maintained and of a size, which can

produce high quality water in a cost effective manner.





The main problems associated with individual schemes are:



 Dungarvan - Inadequate storage. Vulnerability of Source. Increasing Nitrates.

 Lismore/Capoquin/Ballyduff – Slow sand filtration, high colour, overtaxed

capacity, taste and odour problems. This interconnected scheme has two

boreholes serving Cappoquin and its hinterland which are deemed high risk to

pollution and have had results exceeding the MAC for nitrates.

 Tallow & Portlaw - Supply shortages during summer period. Inadequate and

vulnerable source capacity and pipe network. No margin for new development – a

major constraint to meeting the significant demand for serviced housing land

especially in Portlaw.

 Kilmacthomas – inadequate sources and storage capacity. No margin for new

development.

 Bonmahon/Annestown - Lack of mains and storage capacity. Source vulnerable

to pollution.

 Ring/Helvick – Suffers from inadequate and vulnerable sources inadequate

treatment and lack of capacity during the summer where there is a large increase in

population due to summer gaeltacht schools and tourism.

 Dunmore East– Insufficient service storage capacity and inability to cater for peak

tourism demand.

 Faithlegg/Passage/Cheekpoint – Lack of source, storage and mains capacity

 Deelish/Ballinacourty (including Ballinroad – Water quality deficiencies, lack of

capacity and severe development pressure.

 Many of the smaller settlement zones are experience severe development pressure

with limited current capacity.



It is clear that immediate substantial investment is required if water supplies in County

Waterford are to be rationalised and modernised to a standard which embodies current

practice and requirements and which will allow the increasing pressure for

infrastructure capable of serving housing, tourism and industrial demand to be

adequately met.



In 2003 Waterford County Council approved the Rural Water Strategic Plan. The

focus of the plan was the existing critical water supply-demand balance, the need to

meet the projected demand and the provision of satisfactory levels of service over the

20-year period from 2001-2021. This required that adequate water resources and

associated treatment capacities would be available to cater for projected demands, that

the water supply system infrastructure would be adapted to the supply requirements

and that the appropriate operating practices would be put in place to maintain

capability.









5

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



A huge increase in new development since 2003 has accentuated the supply problems

throughout the County, with demand far exceeding supply almost everywhere.



To meet these strategic objectives and deal with the supply shortages it is proposed in

the short term to rationalise water supply within the county by amalgamating and

upgrading adjacent smaller schemes into more viable and manageable larger schemes

with a short-term goal of regionalising supplies particularly in the west and mid county

areas.



Waterford County Council is progressing a number of strategic actions in order to

deliver on the strategic plan:



 Water Conservation and Mains Leakage Control

 Mains Rehabilitation

 Capital Investment and Scheme Rationalisation

 Demand Management



Leakage Control & Demand Management



Demand management measures are necessary to ensure the sustainable use of drinking

water resources and to provide an adequate level of service to all customers.



Water conservation and leakage control will continue to be an important aspect of the

management of our water distribution system. Bursts resulting from pipe

deterioration, excavation works, ground movements, abnormal loading will continue.

However, as a result of the investment in district metering and telemetry, these

potential bursts can be identified and speedily repaired ensuring security of supply to

our customers. A € 2.6 M countywide water conservation programme is currently

progressing with 3 leak detection teams currently in operation.



Proposals for substantial mains replacement under Phase 3 of the Water Conservation

Project are currently in preparation and will be required to achieve target leakage levels.



Waterford is working towards progressively reducing levels of unaccounted for water

to economic levels as determined in detailed studies undertaken as part of the Water

Conservation Project. Target economic levels of leakage throughout the county have

been established with a 10 year glide path to reach and maintain target levels. The

necessary water conservation measures to achieve an economical level of leakage

includes the installation of monitoring equipment and dedicated personnel to improve

leakage assessment capability and to establish a strategy of repair, rehabilitation or

replacement.



Bulk Metering



Bulk metering exists on the majority of Waterford‟s water supply schemes including

the largest 14 schemes representing 95% of the water consumed in the county which

now have established district metering areas following implementation of the Water

Conservation Project.









6

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



In the principal towns of Dungarvan and Tramore systems of metering, zoning and

logging are in place to quantify and help locate system losses. The telemetry systems in

Dungarvan and Tramore are in operation for a number of years and were rationalized

under the Waterford County Water Conservation Scheme in late 2005. Both systems

have zoned out the supply system into manageable area sizes. While these are initially

costly installations it is felt they are the most appropriate and cost effective long-term

measures to manage the distribution systems. The provision of permanent logging and

telemetry on the remaining larger schemes is currently under review and it is proposed

that some level of telemetry will be installed as part of the Water Conservation Project.



On the detection and repair side the council have three teams of leakage detection

inspectors, and have added to the number of plumbers employed to maintain the pipe

networks to achieve and maintain an economic levels of leakage throughout the

county.



Customer Metering



In total there are approximately 2,700 non domestic water service connections located

within the distribution system of which 2,000 are metered and an additional 700 water

service customers currently paying fixed charges. Waterford County Council is

currently engaged in a non domestic metering project to meter all non-domestic

consumers in accordance with government water pricing policy. A database of all non-

domestic customers and existing meter stock is currently being prepared.



Connections



A preliminary study indicates that there are approximately 17,000 connections to the

public water supplies in County Waterford.



In addition to these connections, public water is also supplied to 13 number private

group water supply schemes.



Water is exported from the East Waterford Regional Water Supply Scheme to

Waterford City. The exports from the East Waterford Regional WSS are metered and

are treated as bulk exports.



Rehabilitation



The majority of the smaller schemes in Waterford County cannot sustain leakage and

are a huge drain on resources as a single leak of 10 l/min can equal the normal output

of a small scheme. The recurrence of leaks on pipe sections in some cases leads to

pipe replacement as the only feasible remedy to sustain the schemes. Larger schemes

i.e. Towns and Villages can sustain more leakage without loss of service. Leakage on

larger schemes is comprised of breakages (large losses) and accumulated minor

leakages due to age of the networks. Again specific sections of distribution pipework

need replacement to make the system sustainable.









7

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Well in excess of 50% of the council‟s supply networks are over 30 years old. Plastic

piping of 25 to 30 years is included in this figure and is a most significant problem with

respect to leakage.



A large proportion of our plastic (polythene/polyethylene) pipe has deteriorated to a

state where leaks are occurring by structural failure of the pipe walls. A detailed

countywide assessment and justification for pipe rehabilitation or replacement has

been undertaken as part of the Waterford County Water Conservation Project and a

„Rehabilitation Needs Assessment Report‟ has been prepared. The Report includes a

priority mains replacement programme recommending approximately 70 km of mains

replacement per year over the next 6 years at a total cost estimate of €14M per annum.



Capital Investment



The DEHLG Capital Investment Programme 2005-2007 identifies a range of schemes

at the planning, design/construction stage. In the case of Waterford County Council

€167,587 million of capital investment has been identified, of which €52.5 million

relates to improvements to water supply schemes and the remainder relates to

wastewater schemes. In addition, Waterford County Council will have received €2.6

million in funding towards the water conservation scheme for the initial study phase.









8

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



2.2 Wastewater



At present four strategic action lines are being pursued in parallel, to ensure the

drainage and treatment systems provided by Waterford County Council meet the needs

of its customers. The strategic action lines can be summarised as follows:



 Provision of New Sewers, Pumping Stations and Wastewater Treatment Plants.

 Rehabilitation and enhancement of Small Rural Treatment Plants

 Preparation of New Integrated Policies

 River Basin Catchment approach for Integrated Management of Water



New Sewers, Pumping Stations and Treatment Plants



There is currently a large infrastructure deficit with regard to foul sewerage collection

and treatment within County Waterford. In order to rectify this situation and to

comply with the relevant EU Regulations a number of substantial sewerage schemes

are now at various stages of stages of planning, design or construction. Dungarvan

Sewerage Scheme consisting of separate contracts for collection system, pumping

stations and wastewater treatment plant with sea outfall at a current estimated out-turn

cost of € 38,650,000 is nearing completion. Construction on the collection system was

substantially complete in October 2005 and commissioning of the treatment plant

contract has commenced.



Tramore Sewerage Scheme which consists of a new pumping station and a state of the

art wastewater treatment plant including a new 2km long marine outfall at a cost

estimate of € 20,900,000 is also well advanced with civil works nearing completion.



Preliminary proposals have been developed and costed for upgrading and extending

the combined sewer networks to partially combined sewer networks and the provision

of wastewater treatment plants for the towns of Ardmore, Cappoquin, Kilmacthomas,

Tallow, Stradbally, Ballyduff/Kilmeaden and Dunmore East. (7 Grouped Villages

Scheme) at a total estimated cost of €46,214,000. The proposals include for the

provision of new storm sewer networks to facilitate diversion of road drainage from

the existing combined sewers to the proposed storm sewer networks so as to reduce

hydraulic loading on the proposed wastewater treatment plants. Proposals for new

pumping stations are included in the scheme proposals for Ardmore, Stradbally,

Cappoquin, Kilmacthomas, Ballyduff/Kilmeaden and Dunmore East. A value

engineering process has been conducted with the DOEHLG and Contract

Document‟s are currently at draft stage.



Rehabilitation and Enhancement of Small Rural Treatment Plants



Waterford County Council is currently responsible for seventy-eight Sewerage

Schemes. These vary in size from major networks serving Dungarvan and Tramore to

small schemes serving groups of Local Authority houses consisting of simple septic

tank systems and percolation areas or direct discharge to inland and coastal waters.



Many of the towns and villages within the County are located either on the coast or on

major rivers. In the past these formed a convenient means of effluent disposal with









9

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



reliance placed on dilution and assimilative capacity to deal with pollution problems.

The enactment of various EU Directives now place serious demands on this Council

to address the deficiencies in the existing systems. To this end, Waterford County

Council has advanced preliminary proposals to develop wastewater treatment plants

providing secondary treatment to the towns of Ardmore, Cappoquin, Kilmacthomas,

Tallow, Stradbally, Ballyduff/Kilmeaden and Dunmore East (7 Grouped Villages), and

Cheekpoint. In addition contracts have recently been awarded for new wastewater

treatment plant construction for the towns of Clashmore, Aglish, and Villierstown on

which construction has commenced. The Piltown Wastewater Treatment Plant

construction is nearing completion.



Integrated Policies



Most of the larger towns in County Waterford are served by “combined drainage

systems” (storm water and foul drainage share the same pipe).

Discharge from these combined systems is generally via septic tank to rivers or directly

to sea with reliance being placed on dilution and assimilative capacity to deal with

pollution problems. With the advent of EU Directives this approach is no longer

appropriate. With the introduction of wastewater treatment plants the high flows

associated with combined drainage systems during storm conditions become

unsustainable. Addressing these problems will involve some civil works, such as the

preparation of Drainage Area Plans involving new storm drainage systems. The old

model, whereby storm water was conveyed as quickly as possible to a pipeline, which

was sized to convey peak storm flows to the nearest watercourse may not be

sufficiently robust in all situations to deal with the type and climate change conditions

which have prevailed in recent years and increasing levels of development.



Waterford County Council has adopted the principles of Sustainable Urban Drainage

Systems (SUDS) for all new development where appropriate and economically viable.

These principles include the attenuation of storm water at source or the provision of

compensation storage to minimise large storm water flows.



Catchment Based Approach



The implementation of the Water Framework Directive is being carried out on a

catchment basis and Waterford County Council is participating in both the South

Eastern River Basin District Project (lead authority Carlow County Council) and the

South Western River Basin District Project (lead authority Cork County Council).



These are four-year projects to develop a management infrastructure and measures,

which will endeavour to provide good quality water in the river systems of the South

Eastern and South Western River Basin Districts by 2013. The preparation of new

catchment based management systems will involve extensive public consultation and

will address issues giving rise to deterioration in river quality.





The pollution control measures used in County Waterford are summarised in this

section. Measures include the following;









10

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



 Water quality management planning, including groundwater protection scheme,

and sludge management plan.

 Chemical and biological monitoring of rivers, in conjunction with EPA

 Issue and review of Section 4 and 16 licences in light of Phosphorous regulations.

 Farm visits and enforcement of Water Pollution Acts, issue of advice, warnings,

Section 3, 10, 12 and 13 & 23 notices, as required.

 Monitoring of Wastewater Treatment plants and receiving waters.

 Upgrading of Wastewater Treatment Plants, where required, to provide adequate

treatment.

 Liaison with other stakeholders, particularly through the South Eastern and

South Western River Basin Management Projects

 Collaboration with Duchas in trials on constructed wetlands for treating farm soiled

water and sewage in the Dunhill River catchment special study area.









11

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





3.0 ACHIEVEMENTS TO DATE (2004-2006)



The following summarises the achievements in the provision of improved water

services and water management practices in Waterford County Council over the last

three years.



3.1 Water Supply



East Waterford Water Supply - Stage 2, Phase 1

The East Waterford Water Supply Scheme, Phase 1 at a cost of €12.9m is now

substantially complete. Final accounts for Contracts 4, 8, 19A and 19B are agreed by

the DOEHLG. Final Accounts for Contracts 9 and 10 are currently with the

DOEHLG for approval. The scheme involved upgrading the trunk distribution

capacity to both Waterford City and the east of the county including Tramore and

Dunmore East, as well as providing much increased Reservoir capacity at each

location. An 8,500m³ Reservoir was completed at Kilcaragh serving the south east city

area and the Dunmore Region and a 10,000m³ reservoir was completed at Ballydrislane

to serve the Tramore area.



Phase 1 of the East Waterford Water Supply Scheme also included interim upgrading

at Adamstown Treatment Works. The works consisted of four number additional

upward flow sedimentation tanks at a cost of €0.64m.



The last remaining contract in Phase 1 involved the construction of an 8,500m³

Reservoir at Kilcaragh, as well as construction of an improved distribution system in

the South East City area and the contiguous county area including a connection to

Foiloun Reservoir. This contract is now complete.



East Waterford Water Supply - Stage 2, Phase 2

The East Waterford Water Supply Scheme – Phase 2 involves harnessing the River

Mahon at Seaview, upriver from Bonmahon, to augment the existing source supply

capacity. From the proposed intake on the River Mahon, supply will be pumped to

Ballyshonock Dam via a 600 mm dia rising main. A new 700mm dia trunk main will

supply Adamstown from Ballyshonock Dam. Phase 2 also includes for almost

doubling the treatment capacity at Adamstown.



Phase 2 is divided into 5 separate contracts:



 Contract 2 - Extension to Adamstown, Civil Works.

 Contract 3 - Extension to Adamstown, Mechanical & Electrical Works.

 Contract 11 - Mahon Intake, Pumping Station & 600mm rising main to

Ballyshonnock, Civil Works.

 Contract 12 - Mechanical & Electrical Works for Contract 11

 Contract 13 - 700 mm Trunk Main, Ballyshonock to Adamstown



Contract 13 commenced in September 2004 and a certificate of substantial completion

was issued in October 2005. Work on Contract 11 commenced in September 2005 and

is currently ongoing. Contract 12 was signed with the Contractor in September 2005.









12

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Work commenced on Contract 2 in August 2006 following contract signing in May of

that year. A Report on Tenders for Contract 13 was issued to the DOEHLG in May

2006 with further clarification in June 2006. Approval has been received from the

DoEHLG. On completion of Phase 2 the capacity of the East Waterford Water

Supply Scheme will increase from a current production of 29,000 m³/d to a future

capacity of 52,000 m³/d.



Ring/Helvick Water Supply Scheme

The Ring/Helvick Water Supply Scheme Preliminary Report was submitted to the

Department of Environment, Heritage & Local Government in August 2003 for

approval. Proposals consist of developing a new groundwater source, with

chlorination and fluoridation to supply a future demand of 825m³/d, providing a 24

hours high level storage Reservoir at peak future demand and upgrade of the

distribution system. A suitable adequate water supply source has not been located to

date. Additional groundwater resources for the area are being progressed in parallel

with consideration of options to supply the area from the neighbouring schemes of

Dungarvan and Ardmore. The Ring/Helvick Water Supply Scheme is included in the

Government‟s Water Services Investment Programme to proceed to construction in

2007.



Deelish/Ballinacourty Water Supply Scheme

The Deelish/Ballinacourty Water Supply Scheme Preliminary Report was submitted to

the Department of the Environment in September 2003 for approval. The proposals

consist of developing a new groundwater source with chlorination and fluoridation, to

supply a future demand of 2,000m³/d, adjacent high level storage and extensive mains

replacement and upgrade. A geophysical survey for production borehole location was

completed in October 2003 and exploratory well drilling was conducted in the summer

of 2004. A suitable adequate water supply source has not been located to date.

Additional groundwater resources for the area are being progressed. The

Deelish/Ballinacourty Water Supply Scheme is included in the Government‟s Water

Services Investment Programme to proceed to construction in 2007.



Ardmore Water Supply Scheme

Following DoEHLG approval of the design brief for the Ardmore Water Supply

Scheme, Consulting Engineers were selected in January 2004 to prepare a Preliminary

Report setting out proposals for the augmentation and improvement of the Scheme. A

Draft Preliminary Report was submitted March 2005. Additional exploratory drilling

was carried out in June and September of 2005. A revised Preliminary Report was

submitted to WCC in May 2006. Following review and comments by WCC, the revised

PR will be submitted to the DoEHLG for approval. The Scheme is included in the

Department‟s Water Services Investment Programme 2005-2007 to commence in

2007.



Faithlegg Water Supply Scheme

The Faithlegg Water Supply Scheme Preliminary Report was submitted to Waterford

County Council in December 2006 and is currently under review. Following review

and comments by WCC, the revised PR will be submitted to the DoEHLG for

approval. The Faithlegg Water Supply Scheme is identified as the area supplied from

the Foilaun Reservoir which stretches from the northern edge of Dunmore East in the









13

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



south and Cheekpoint in the north and includes the zoned lands at Faithlegg, Passage

East, Crooke and Dunmore East. The Scheme is included in the Department‟s Water

Services Investment Programme 2005-2007 to advance through planning.



Dunmore East Water Supply Scheme

Consulting Engineers were selected in January 2004 to prepare a Preliminary Report

setting out proposals for upgrading Dunmore East Water Supply Scheme. Revised

Preliminary Report was forwarded to the DOEHLG in August 2006 for approval.

The scheme is included in the Department‟s Water Services Investment Programme

2005-2007 to start in 2006.



West Waterford Water Supply Scheme & Strategic Review

Consulting Engineers have been appointed to prepare:-



 A Strategic Review of water supplies in West Waterford

 A Preliminary Report setting out proposals for new water supply infrastructure in the

Stage 1 area.



The Strategic Review will identify possible water supply sources in the West Waterford

Area to resolve current source capacity and quality problems.



The Preliminary Report will concentrate on resolving current supply difficulties in the

Stage 1 Area, comprising Lismore, Cappoquin, Ballyduff and Tallow areas. Trial

drilling for water sources commenced in September 2005. Well drilling is complete.

The Project is included in the DoEHLG Water Services Investment Programme, 2005-

2007 with a start date in 2007.



Waterford County Council regards the development of a major Regional Water

Supply Scheme for the west of the county as its most important water supply

strategic objective. The current West Waterford Water Supply Scheme &

Strategic Study in the stage 1 area are considered to be interim steps towards

realising the counties overall strategic objectives.



Dungarvan Water Supply Scheme

Proposals are in place to provide additional high-level storage, rising mains and supply

mains to connect to the existing distribution system for the Dungarvan Water Supply

Scheme. A yield test was carried out on the Ballynamuck source as part of the trial

drilling for the West Waterford Strategic Review. The yield estimate of the well field

(approx 8,200 m3/d) is not as high as previously reported. Tenders have been sought

for additional drilling. Drilling contractor due to commence in early 2007. A Brief has

been prepared for the appointment of a Consulting Engineer to prepare a preliminary

report for the Dungarvan Water Supply Scheme. The scheme is included in the Water

Services Investment Programme 2005 – 2007 with a start date in 2007.



The previously unrealised limitations on the output from the Ballinamuck source, allied

to the unprecedented level of development in Dungarvan town and hinterland

underline the urgency of developing a Regional Supply capacity to augment

Ballinamuck and enable the county town to develop in a planned and sustainable

manner.









14

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





Portlaw Water Supply Scheme

Connection to the East Waterford WSS or an alternative local source augmentation if

available is proposed with distribution network rehabilitation and additional storage. A

Consultant was appointed to carry out a Preliminary Report in November 2005.

Exploratory well drilling tender was advertised in July. Drilling contractor due to

commence exploratory drilling and yield testing in October 2006. The scheme is

approved to advance through planning in the Water Services Investment Programme

2005-2007.



Carrick-on-Suir/Rathgormack Water Supply Scheme

Proposals to connect to the adjacent Carrick on Suir WSS if feasible or to provide a

new water supply source and extend the distribution network to amalgamate the

adjacent public water supply schemes at Rathgormuck, Clonae Power, Feddens,

Joanstown, Garravoone, Ballynock and Crehanagh. Demand data has been collated

and a meeting to discuss proposals is being arranged with South Tipperary County

Council. The scheme is approved to advance through planning in the Water services

Investment Programme 2005 - 2007.



Kilmacthomas Water Supply Scheme

Proposals to provide a new water supply source with distribution network

rehabilitation and additional storage. A Brief was approved by the DoEHLG in

September 2005. Procurement of Consultant‟s commenced in February 2006. Fee

proposal received from selected Consultant. The scheme is approved to advance

through planning in the Water Services Investment Programme 2005 - 2007.



Water Conservation Programme

Consultant‟s were appointed to carry out Phase 1 of the Water Conservation Project in

March 2004. Phase 1 includes establishing fully trained and equipped leakage detection

teams, developing necessary infrastructure to enable recording and monitoring,

establishing procedures and economic targets for of the networks. Teams and

procedures are established and in operation. A full suite of reports have been issued up

to September 2006. A review of the reports is ongoing.



Meter Installation Programme

Installation of non domestic meters in accordance with national policy commenced in

February 2005 and is progressing by direct labour. To date approximately 1,000 meters

have been installed. There are currently approximately 2,000 commercial meters and an

additional 700 non domestic customers paying fixed charges.



Mains Replacement

Throughout 2004-2006 Waterford County Council spent €2.5m in the provision of

new mains and necessary mains replacement and upgrading and improvement of water

supplies on numerous public water supply schemes including the following:



 Ballyduff Ballylemon WSS

 Ballyduff/Kilmeaden WSS

 Ballyguiry WSS

 Ballyheaphy WSS









15

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



 Balllymoat WSS

 Carrigeen WSS

 Carrignagower WSS

 Clonae Power WSS

 Croan WSS

 Deelish Ballinacourty

 Dunhill WSS

 Dunmore East WSS

 Garravoone WSS

 Grallagh WSS

 Grange WSS

 Joanstown

 Kereen

 Knockalisheen

 Lismore- LCB WSS

 Mellary

 Modeligo

 Monamon WSS

 Old Parish WSS

 Portlaw WSS

 Rathgormuck WSS

 Shean WSS

 Smoorebeg WSS

 Tallow WSS



In addition, full coverage of Complete Information System and digitised mapping of

County Waterford‟s water supply networks and assets have been completed.









16

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



3.2 Wastewater Treatment



Dungarvan & Environs Sewerage Scheme

The Dungarvan & Environs Sewerage Scheme consists of two elements, the Collection

System and the Wastewater Treatment Plant at a combined current out-turn estimate

cost of € 38.65M. The collection system contract commenced in April 2003 and a

certificate of substantial completion was issued in September 2005. The

mechanical/electrical contract for pumping stations on the collection network is

ongoing. The wastewater treatment contract commenced in April 2004. Civil and

Mechanical/Electrical works are substantially advanced and commissioning of the

plant has commenced.



Sludge Management Plan

A Sludge Management Plan outlining County Waterford‟s strategy for managing

sludges produced from water and wastewater treatment has been prepared. The

strategy envisages sludges from the various wastewater treatment plants being collected

and dewatered at two satellite centres, one in the east of the county and one in the

west. Dewatered sludges will be transported to a central hub treatment facility, where

the end product bio-solids produced will be suitable for sustainable reuse in

agriculture. The Plan has been submitted to the DOEHLG.



Tramore Sewerage Scheme

The Tramore Sewerage Scheme at a cost of €20.9 M involves the transfer of collected

sewage via a new pumping station at the Promenade to a proposed wastewater

treatment plant located at Corbally Upper. The scheme also provides for

improvement to the existing Cove Pumphouse and a 2km long sea outfall to convey

treated effluent well out into Tramore Bay. The scheme consists of three separate

contracts, namely the Collection System Civil Works Contract, the Collection System

Mechanical & Electrical Contract and the Wastewater Treatment Plant. A certificate of

substantial completion for collection system civil works was issued in October 2005.

The Mechanical/Electrical works on the collection system are substantially advanced.

The wastewater treatment plant contract was awarded in November 2005. To date the

civil works element is 90% complete and the Mechanical/Electrical element has

commenced.



Tramore Sewerage Scheme – Collection System, Stage 2

A brief for the Tramore Sewerage Scheme – Collection System, Stage 2 was approved

by the DoEHLG in October 2005. The brief identifies the recent increase in

population in Tramore reducing the pipe capacity reserves, high levels of infiltration of

surface water into the existing system and existing overflows discharging into the

marine environment. Following fee proposal approval from the DoEHLG in October

2006, consultants have been appointed to prepare a Preliminary Report. The scheme is

included to advance through planning in the Water Services Investment Programme

2005 - 2007.



Seven Villages Sewerage Scheme

A revised Preliminary Report for the Seven Villages Sewerage Scheme at a total capital

cost estimate of €46.2M was submitted for DoEHLG approval in December 2003.

The proposals include for the provision of wastewater treatment and collection system









17

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



upgrade for the villages of Ardmore, Cappoquin, Kilmacthomas, Tallow, Stradbally,

Ballyduff/Kilmeaden and Dunmore East. It is proposed that the seven wastewater

treatment plants be let as a single Design Build and Operate (DBO) Contract with an

operation phase of 20 years. The collection system upgrade at each location involves

the provision of new storm water networks to facilitate the transfer of surface water

connections from the existing combined system to the new storm system. All future

foul and surface water connections to the networks will be to the partially combined

system and the storm system respectively to minimise storm flow to the proposed

treatment works.



The Part 8 Planning procedure has now been approved for all villages. A Judicial

Review of the Part 8 process in respect of Ardmore Wastewater Treatment Plant is

being sought by the landowners. A Value Engineering process was conducted with the

DOEHLG for all villages. Compulsory Purchase for relevant sites commenced in

February 2006. CPO‟s have been confirmed for Cappoquin, Dunmore East and

Stradbally. Applications for Foreshore Licences to the Dept. of Marine dated April

2005, are currently awaiting grant of licences. Additional Part 8 applications for

wastewater treatment plants at Ardmore and Ballyduff/Kilmeaden commenced in July

2006 and were approved by Council members in September 2006. Seven tenders were

received for Tallow collection system in December 2006.



The Waterford Grouped Towns & Villages Sewerage Scheme is included in the Water

Services Investment Programme 2005 – 2007 with a start date in 2007.



Cheekpoint Sewerage Scheme

The scheme includes a new wastewater treatment plant, collection system and sea

outfall for the village. A revised Draft Foreshore Licence was received from DCMNR

and is currently under review. The scheme has been included in the Rural Towns &

Villages Initiative in the Government‟s Water Services Investment Programme 2005 -

2007.



Bonmahon Sewerage Scheme

Proposals to provide appropriate secondary treatment to replace the existing septic

tank prior to discharge to Mahon River Estuary. Following approval of Fee Proposal/

Planning stage budget by the DoEHLG in August 2005 a Consultant was appointed in

September 2006. The scheme is approved to advance through planning in the Water

Services Investment Programme 2005-2007.





Ballyduff (Upper) Sewerage Scheme

Proposals to provide appropriate secondary treatment to replace existing septic tank

prior to discharge to the Blackwater River and a collection system upgrade. A revised

Preliminary Report was received from the Consultant‟s in July 2006 and is currently

under review. The scheme is included in the Water Services Investment Programme

2005-2007 with a start date in 2007.



Aglish, Piltown, Clashmore and Villierstown Sewerage

The report on Tenders for the Aglish, Clashmore and Villierstown Wastewater

Treatment Plant Contracts was approved by the DoEHLG in March 2006 with









18

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



contract signing in July 2006. Detailed design review completed with works due to

commenced on site in mid October 2006.



Piltown Wastewater Treatment Plant construction by direct labour is nearing

completion.









19

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





4.0 WATER SERVICES NEEDS IDENTIFICATION



4.1 Introduction



In recent years there has been a very noticeable increase in development, particularly

housing development throughout County Waterford. Recent planning applications

suggest that this trend is set to continue as can been seen in the summary population

estimates table 4.2 in the following section. At the present time numerous water

supplies are approaching a critical supply demand balance as a result of increasing

demand. A similar water services deficit is experienced for wastewater collection and

treatment. It is deemed prudent therefore to review each area of zoned land identified

in the „Waterford County Development Plan 2005-2011‟ and the various local area

plans to quantify the water services needs at the present time and into the future. The

adequacy of the existing water services can then be assessed against the identified

existing and future water services needs.



The „Waterford County Development Plan 2005-2011‟ identifies a settlement strategy

for the county based on a settlement hierarchy reflecting the role of each settlement

type. It is noted in the Development plan that the settlement strategy was hindered by

infrastructural deficiencies in water and sewerage. The settlement hierarchy is based on

establishing a Primary and a Secondary Service Centre, District Service Centres (11

no.), Local Service Centres (18 no.) and Settlement Nodes (20 no.) The established

settlement hierarchy and the existing water, wastewater and storm water services are

summarised in Table 4.1 below.









20

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





Table 4.1 Settlement Zones Summary

Settlement Hierarchy Settlement Zone Water Supply Scheme Wastewater Scheme



Primary Service Centre Dungarvan Dungarvan Dungarvan SS

Secondary Service Ctr Tramore Tramore - EWWS Tramore SS

District Service Centre Ardmore Ardmore Ardmore SS

Ballymacarbry Ballymacarbry Ballymacarbry SS

Cappoquin LCB Cappoquin SS

Dunhill Dunhill Dunhill SS

Dunmore East D. E. Regional Dunmore East SS

Kilmacthomas Kilmacthomas Kilmacthomas SS

Kilmeaden Ballyduff/Kilmeaden No public scheme

Lismore LCB Lismore SS

Portlaw Portlaw Portlaw SS

Stradbally Stradbally Sheskin Stradbally SS

Tallow Tallow Tallow SS

Local Service Centre Aglish Aglish Dromore Aglish SS

An Sean Pobal Old Parish WSS Old Parish SS

Ballyduff Lower Ballyduff/Kilmeaden Council septic tanks

Ballyduff Upper LCB Ballyduff Upper SS

Ballynagaul Ring/Helvick/Seaview Ring Ballynagaul SS

Bunmahon Kill/Bunmahon/Annestown Bunmahon SS

Cheekpoint Dunmore East Regional Cheekpoint SS

Clashmore Clashmore Clashmore SS

Clonea Power Clonea Power Clonae Power SS

Crooke Dunmore East Regional Crooke SS

Helvick Ring/Helvick/Seaview Ring Ballinagaul SS

Kill Kill/Bunmahon/Annestown Kill SS

Kilrossanty Kilrossanty/Knockyelan No public scheme

Knockanore Strancally No public scheme

Mweelanhorna Ring/Helvick/Seaview Ring Ballinagaul SS

Rathgormuck Rathgormuck No public scheme

Tooraneena Tooraneena Tooraneena SS

Villierstown Villierstown Villierstown SS

Settlement Node Annestown Kill/Bunmahon/Annestown Annestown SS

Ballinroad Ballinacourty/Deelish Ballinroad SS

Ballylaneen Kill/Bunmahon/Annestown No public scheme

Ballymacaw Dunmore East Regional No public scheme

Ballynameelagh Ballyduff/Ballylemon No public scheme

Ballysaggart Ballysaggart WSS No public scheme

Bawnfune Tramore WSS Bawnfune SS

Butlerstown Tramore WSS No public scheme

Faha Faha WSS No public scheme

Fenor No public supply No public scheme

Fews Fews WSS No public scheme

Fourmilewater Ballymacarbry WSS Council septic tank

Grange Ardmore WSS No public scheme

Kilbrien Kilbrien/Ballinakill No public scheme

Leamybrien Kilrossanty/Knockyelan Leamybrien

Melleray Mellary WSS No public scheme

Modeligo Modeligo WSS No public scheme

Newtown No public supply No public scheme

Passage East Dunmore East Regional Passage East SS

Piltown Clashmore WSS Piltown SS









21

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________









4.2 Project Justification



Schemes included in the Assessment of Needs Programme for 2007 to 2014 are

included on the basis of examination against the following criteria and listed in Table A

& B at the end of this Report:



Water Supply Schemes



Statutory/Health Justification

Non-compliance with Drinking Water Directive and/or EU Commission application.



1. Serious public health implications

2. Moderate public health implications

3. Non health parameters



Developmental Pressures

1. Inhibition of immediate development proposals

2. Provision of reserve capacity



Supply and Level of Service Deficiencies

1. Serious supply problems

2. Moderate supply problems

3. Occasional water supply and pressure problems

4. Deficiency in fire fighting capacity.



Objectives

1. To provide or augment treatment capacity

2. To provide or augment distribution and/or storage capacity as well as fire

fighting capacity

3. To remove risk to existing system



Waste Water/Drainage Schemes



Statutory/Health Justification

1. Treatment required under Urban Waste Water Directive

2. Sludge treatment and reuse

3. Inadequate collection system

4. Surcharging and flooding



Development Pressures

1. Inhibition of immediate development proposals

2. Provision of reserve capacity



Environmental Justification

1. Causing serious pollution in receiving waters

2. Causing moderate pollution in receiving waters

3. Causing slight pollution in receiving waters









22

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





Objectives

1. To provide or augment treatment capacity

2. To provide or augment collection pumping capacity

3. To reduce or eliminate storm water overflows



The examination of public water supply, wastewater treatment and drainage schemes

against the above criteria is carried out in Table 1 and Table 2 of Appendix 1 of this

report.



General Approach to Meeting the Needs



It is the intention of Waterford County Council to advance to construction the

schemes listed in the needs assessment through a number of mechanisms:



a) Direct Exchequer funding through the Department of Environment, Heritage

and Local Government.

b) Part financing through the Rural Water Programme (DoEHLG) in

combination with locally generated revenue from the Council‟s development

levy scheme, and

c) The Serviced Land Initiative (Circular L1/00 & L1/07) in combination with

Development contributions to Waterford Local Authorities.



In procuring the necessary schemes and/or infrastructure projects, Waterford County

Council will consider traditional procurement methods as well as:



 Design and build procurement

 Design, build and operate procurement as appropriate

 Forms of public private partnerships



The decision on which form of procurement to pursue will be fully contingent on what

Waterford County Council considers the best Value for Money option in any

circumstance.









23

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





4.3 Basis of Needs Identification Quantification



4.3.1 Water Supply



A current water supply demand per person of 139 l/day is assumed based on the

„Waterford County Water Conservation Project‟ figures and „The National Water

Study‟ (NWS) prepared in 2000. Future demand figures are based on the estimated

water per capita consumption (Table 11 NWS) which identifies steady increase in per

capita demand to 157.5 l/s by 2032. The occupancy rate per dwelling is expected to

decrease over the coming years. Based on NWS figures the occupancy rate is assumed

to reduce from a current rate of 3 persons / house to 2.52 persons per house in 2032

in our future population estimates.



In the absence of detailed CSO Census 2006 figures for local areas the population

served for each development zone and within each supply scheme is calculated from

the An Post Geodirectory July 06 Building Count assuming an existing population

density of 3 per house. For the purpose of future water services needs assessment we

have assumed that all current planning applications will be developed in the period

2007-2009 with an average population density of 3 persons per house. In addition

commercial development is assumed to increase in line with residential demand in all

but the primary and secondary service centres where increased commercial and

industrial activity is expected.



From the summary Table 4.2 below it will be noted that the full development of all

residential land suggests an increase in population of 96 % or 43,723 persons within

zoned land over the design period to 2034. This compares with the CSO Population &

Labour Force Projections 2006 -2036 which estimates a national population increase

of 39% to the year 2036 based on the most optimistic population variant. The CSO

Census 2006 population statistic identified the population increase in County

Waterford over the inter census period was 9.2% marginally above the national average

of 8.1%. It is unlikely therefore that population increase in County Waterford will

exceed the CSO projections by any significant amount over the design period. In order

to reconcile the significant difference between population trends and full development

of available zoned land we have assumed design demand figures for each settlement

zone based on a percentage of peak development over a typical design period of 25

years from the end of 2009. It is intended that the level of water service provision

proposed will be sufficient as to not hinder future development within this timeframe.



In order to assess the potential peak future water services demand for specific

development areas for a 25 year design period from 2009 to 2034 we have assumed a

percentage of full development of all commercial, industrial and tourism zoned land

within the design timeframe in line with assumptions in relation to population above.

Residential development assumes a housing density of 8 houses per acre and an

occupancy rate of 2.52 persons per house based on figures from the „National Water

Study‟ to the year 2032. The full development of commercial/industrial zoned land

assumes a water services demand of 28m3/ha/day based on estimate figures from

existing water services preliminary reports for Waterford County Council. A summary

of the future demand estimates is summarised in Table 4.3 below.









24

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





Prioritization of a programme of works assumes that all current planning applications

whether approved or pending will be developed during the period 2007-2009 and that

the design demand figures for each development area will be realised over the design

period of 25 years from 2009. On this basis we have assumed a pro-rata demand

increase over the period 2010-2014 to identify all possible shortfalls in water services

provision. A summary calculation of the required water services needs at each

development area for the period up to 2009, from 2010-2014 and the design demand

for the 25 year period up to 2034 is included in Table 4.3 and in the following sections.

The available water services are compared to the estimated future water service needs

to identify and prioritize a programme of works over the next planning period.



Assessment of water supply requirements assumes proven source capacity and 24

hours storage for the design demand is required. If a source or storage capacity

shortfall is identified for the assessment period 2007-2009 or 2010-2014 then the

provision of additional water services is included in the prioritized programme of

works. The supply network capacity is generally insufficient to provide the required fire

flows outside of the larger urban areas. The requirement for increased mains capacity

for fire flows includes most water supply schemes in the county and it is therefore

considered impracticable to include on a prioritized works list. Where a supply

network capacity shortfall is identified for supply purposes this is identified in the

prioritized programme of works. It is intended that the necessary replacement of

numerous lengths of watermains deemed to be past their useful life will be catered for

under the next phase of the Water Conservation Project and therefore not included in

the programme of works.



4.3.2 Sewerage Schemes



While many of the public sewerage schemes in Waterford County fall under the

secondary treatment threshold of less than 2000 p.e. as defined in the Urban

Wastewater Treatment Regulations, it is recommended that a high standard of effluent

treatment should be provided for the protection of health and the environment,

particularly in relation to fish life in the receiving waters, and in anticipation of higher

treatment standards being required under the River Basin District Management

measures and by the EU in the future. It is proposed to adopt the following broad

design values for all small schemes considered in this report except where there is

adequate dilution to allow primary treatment only.



Treated Effluent

 BOD – maximum 25 mg/litre 0s

 Suspended Solids – maximum 35 mg/litre

 COD – maximum 125 mg/litre



Effect on Receiving Waters

 Maximum downstream increase in BOD of 1 mg/litre



Sludge Treatment

 Provision of Sludge Holding tanks at each site with suitable facilities to permit

collection and transportation to sludge satellite and hub centres.









25

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





Many sewerage schemes in County Waterford have predominantly combined

collection systems and high surface water infiltration and because of this many plants

have become hydraulically overloaded. Investment in secondary treatment should be

carried out in conjunction with the removal of surface water from sewer networks.



In this report the existing public sewerage schemes serving settlement zones in County

Waterford were assessed as to their ability to cope with existing and future loadings

and a list of proposals have been developed. The design populations to be served are

as outlined in Table 4.2 above. The sewerage schemes which are currently included

with start dates or at construction stage in the Water Services Investment Programme

2005-2007 are:



Dungarvan Sewerage Scheme

Tramore Sewerage Scheme

Waterford Grouped Towns & Villages SS - Ardmore, Tallow, Stradbally, Cappoquin,

Dunmore East, Kilmacthomas,

Ballyduff/Kilmeaden

Ballyduff Upper Sewerage Scheme

Aglish Sewerage Scheme

Clashmore Sewerage Scheme

Villierstown Sewerage Scheme

Piltown Sewerage Scheme

Cheekpoint Sewerage Scheme



Due to the long lead in period for scheme implementation and the recent huge

increase in residential and commercial development, the capacity of schemes at

construction stage have been reviewed with regard to current and future loading

estimates.



The capital cost estimates for treatment plant provision inclusive of VAT is taken from

tender costs on recent projects. For smaller schemes up to approximately 1000/pe

there is a wide selection of package plants available at very competitive rates ranging

from approx. €150,000 for a 150 p.e. plant or €1,000/pe to €450,000 for a 1000/pe

plant or €450/pe. For smaller schemes it should be noted that land acquisition costs

can represent a significant element of the overall costs over and above the unit

treatment cost. For larger sewage treatment installations where the plant is generally

more robust with less package elements and large civil works the costs tend to

increase. The cost estimate for treatment plants varying from 2,000/pe to 25,000/pe

are assumed to range from €1,000/pe to €450/pe based on recent tender prices and

estimates prepared for Waterford County Council.









26

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





4.4 Water Services Needs Assessment



4.4.1 Water Supply



4.4.1/1 Dungarvan Water Supply:



The primary source for the Dungarvan Water Supply Scheme is the Ballinamuck

Boreholes. These feed into the Dungarvan Water Tower TWL 47.58 mOD which

governs pressures throughout the town. There is an additional spring source at

Springmount connected directly to the supply network. Springmount is used primarily

in winter months to avail of night time electricity tariffs. Water from Dungarvan also

currently augments the neighbouring schemes at Ballyduff/Ballylemon and

Ballinacourty/Deelish including Ballinroad.



The existing capacity of the Ballinamuck borehole is estimated at 7,000 m³/d following

recent pump testing which is less than previous estimates. The limiting factor being

ingress of fines to the borehole. Springmount source capacity estimates at 1,200 m³/d

giving a current combined source capacity of 8,200 m³/d. Treatment for both sources

consists of chlorination and fluoridation. The Dungarvan water tower was built in

1965 and has a capacity of 1100m³.



In view of unprecedented levels of residential and commercial development in

Dungarvan and its surroundings in recent years a review of the current and future

demands was deemed appropriate to assess the adequacy of the existing scheme and

potential spare capacity to augment adjacent schemes. It is noted that proposals are

included in the Water Services Investment Programme 2005-2007 to provide for the

shortfall in storage capacity on the scheme (Est. Cost €3.47M) The existing and future

demand estimates on the scheme are as follows:



Table 4.4.1/1 Dungarvan Water Supply – Existing & Future Design Demand

Estimates

Domestic Non Domestic UFW Total

(m³/d) (m³/d) (m³/d) (m³/d)



2006 Existing 1475 1566 2517 5558

2009 2028 2150 2247 6425

2014 2221 2354 2255 6830

2034 3050 3233 2692 8975







It is clear that the existing source capacity is adequate over the strategic planning

period to 2014, beyond which additional service capacity will be required to meet

increasing demand both in the town and the region. A major increase arising from

industrial demand could shorten this time scale dramatically. Storage provision should

be at least 9000m³ to provide for 24 hours storage based on design demands.









27

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



The strategic review currently undertaken for West Waterford should identify potential

sources for the region, including Dungarvan. The development of a regional supply

capacity in West Waterford, which will, inter alia, augment Dungarvan Water Supply is

Waterford County Councils primary strategic water supply objective.



4.4.1/2 Faithlegg Water Supply Scheme (incl. Passage East, Crooke,

Cheekpoint, Woodstown and Killea)



The water supply from the Belle Lake reservoir extends from Cheekpoint to the north

and the outskirts of Dunmore East to the south and represents a separate supply area

within the Dunmore East Regional Water Supply. The supply area includes Faithlegg

and proposals for the Faithlegg Water Supply are included in the Water Services

Investment Programme 2005-2007 to advance through planning. The original source

for this supply area is Belle Lake. Water from the lake is treated locally in a dissolved

air floatation plant and filtered, augmented by activated carbon, disinfected and pH

corrected before being pumped to the adjacent 381m³ reservoir TWL 119.2 MOD at

Foilaun Hill. The reservoir at Foilaun Hill can also be supplied from the East

Waterford Water Supply Scheme (EWWSS) via Kilcaragh Hill reservoir. Water source

provision is considered secure from the latter. The Belle Lake abstraction order limits

abstraction to 506.4m3/d, whereas estimated future demand is 2,222m3/d. A new

source is therefore required to meet both existing and future demand.



The water storage for public schemes provided in the area is as follows:



318m³ (70,000 gals) Foilaun Regional Reservoir of TWL 119.2 mOD

182m³ (40,000 gals) Passage East service reservoir of TWL 57.64 mOD

45m³ (10,000 gals) Cheekpoint service reservoir of TWL 66.31 mOD

8,500m³ (1,870,000 gals) Kilcaragh Hill reservoir of TWL 83.00 mOD



A preliminary water audit of the supply area using standard methodology has identified

a demand of 808.4 m³/d going into supply with unaccounted water estimated to be

187.86 m³/d or 23.3%.



Population statistics for the three district electoral divisions (DEDs), namely Faithlegg,

Killae and Woodstown, which are primarily in the supply area, indicate a current

population of 2,492. In view of the proximity to Waterford City and the available

zoned land a population growth in the supply area of 151% is predicted (from 2,492 to

6,265 people). Taking into consideration the likely growth in all sectors and allowing

for a peak day factor, the design demand estimate for the scheme to the year 2031 is

2,322 m³/d.



A new source is required for existing and future demands. The storage capacity at

Foilaun and Cheekpoint is insufficient to cater for existing demand and there are

supply disruptions at peak demand periods due to lack of capacity in the distribution

system. It is proposed to replace the existing source at Belle Lake with water from the

East Waterford Water Supply Scheme via the Adamstown treatment plant and the

Kilcaragh Hill reservoir. Once the upgrading of the Adamstown treatment plant is

complete by end 2007, it will have sufficient capacity to supply the Faithlegg Water

Supply area to allow Belle Lake and its treatment plant to be withdrawn from service.









28

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





It is also proposed to no longer supply the northern part of the area from Foilaun

reservoir but to feed the area directly from Kilcaragh Hill reservoir. Watermains of

sufficient capacity are already installed between the Kilcaragh reservoir and Blenheim

Cross, therefore an additional length of pipework is required between Blenhiem Cross

and the Faithlegg area. A new storage reservoir at Cheekpoint is proposed with a

capacity of 470 m3 located on Faithlegg Hill with adequate elevation to provide

minimum 15m head at all locations. A booster pumping station will be required to

transfer water from the Kilcaragh reservoir to the proposed new reservoir on Faithlegg

Hill due the to relative elevations involved.



To improve water supply to the southern area of the Faithlegg Water Supply Area it is

proposed to construct an additional 1,200 m3 reservoir adjacent to the existing 318m3

Foilaun reservoir to be supplied directly from Kilcaragh reservoir via the existing

Hickey Crossroads pumping station. The existing pumps in the Hickey Crossroads

pumping station have sufficient capacity to cater for future demands. Cost estimates

for the above proposals are as follows:



Quantity Rate Capital Cost

(€) (€)

470 m³ reservoir at Faithlegg Hill 245,000

Booster Pumphouse at Faithlegg Hill 183,000

5.3 km of 150mm main Kilcaragh to Cheekpoint 5,300 212 1,090,000

0.75 km of 150/100mm in rock downstream

of Faithlegg Hill 750 195 234,000

1,200m3 reservoir at Foilaun 425,000

3.8km of 200/150mm main to Foilaun Reservoir 3,800 212 970,000

Remedial pipe works 320 95,000



Non Contract cost at 15% 486,000

Total 3,728,000





4.4.1/3 Dunmore East Water Supply Scheme



The original Dunmore East Water Supply Scheme was constructed in the 1950‟s based

on abstraction from Belle Lake, 5 km northwest of the town. Due to growth in

demand in the supply area arising from population increase, the capacity of this source

was exceeded in the late 1970‟s. Consequently, a 250mm trunk main was laid along the

coast road between Tramore and Dunmore East to supply the latter with water from

Tramore. Following the commissioning of the East Waterford Supply treatment plant

in Adamstown in 1984, water from that plant was fed into Tramore and thence to

Dunmore East with all supply to the latter currently originating at the Adamstown

waterworks via the Sporthouse Reservoir (2,500 m3)



The current population of the village is 1,650 persons approximately. This almost

doubles in the peak holiday season due to the extensive holiday developments in the

village and the local hotels and B&B‟s. There is also a seasonal demand for water in the









29

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



port area of the village arising from ice making, fish processing and servicing of fishing

trawlers.



The scheme has difficulty in meeting the demand imposed on it, particularly in

summer season due to insufficient storage capacity, high unaccounted for water and

limited distribution system capacity to cater for peak tourism demand.



A preliminary water audit on the scheme assessed the existing demand as 749.81 m3/d

with unaccounted for water at 32.45%. In view of the proximity to Waterford City, the

desirable coastal location and tourism demand, the future demand to the year 2031 is

estimated as 3,000 m3/d plus a possible 515 m3/d for Waterford Airport and

immediate environs.



It is proposed to alter the source reservoir from Sporthouse to Ballydrislane (10,000

m3) with provision of booster pumping at Corbally Cross thereby permitting balanced

regional distribution of water supply and availing of the storage provision in

Ballydrislane reservoir. Local storage provision at Coxtown East consisting of a 1,870

m3 ground level reservoir and adjacent 430 m3 water tower is also proposed to provide

24 hrs storage provision to all of the Dunmore East distribution system including

localised areas of higher elevation. Upgrade of the distribution system it also proposed

to cater for future demand estimated and fire flows. Cost estimates for the above

proposals are as follows:



Quantity Rate Capital Cost

(€) (€)

1,870 m³ reservoir at Coxtown East 495,000

430 m³ Water Tower at Coxtown East 520,000

Booster Pumphouse at Corbally Beg 180,000

3.4 km of 150/200/250mm distribution upgrade 3,400 302 1,030,000



Non Contract cost at 15% 335,000

Total 2,560,000





4.4.1/4 West Waterford Regional Water Supply Scheme



The West Waterford Water Supply Strategic Review and Stage 1 Improvements which

is included in the Water Services Investment Programme 2005-2007 is currently

assessing source availability in the region. It is envisaged that Stage 2 of the scheme

would involve advance planning and preparation of a Preliminary Report for the

development of a Regional Water supply in the west of the county, utilising the

information obtained in the Strategic Review. Stage 3 proposals include for

rationalising supply and rehabilitation of the existing schemes in the south west of the

county, including the existing schemes of Ballyduff/Ballylemon*, Colligan,

Kilgobinet/Inchindrisla*, Ballyguiry, Dungarvan*, LCB*, Clashmore*, Shanacoole*,

Villierstown, Aglish, Ticknock/Tinnabina*, Piltown, Grallagh*, Kereen*, Geoish,

Cooneen*, Ballycurrane and Tallow.









30

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





West Waterford Regional Water Supply Scheme

Stage 2 – Advance Planning & Preliminary Report



Lismore, Ballyduff and Cappoquin (LCB)

The LCB water supply scheme services the towns of Lismore, Ballyduff and

Cappoquin and the substantial hinterland in between. The scheme is made up of a

number of interconnected local sources and service storage. The primary source for

Lismore town and the hinterland to the west as far as Ballyduff is the Glenakeefe and

Owenashad streams. The Glenakeefe & Owenashad sources are treated at Monamon

and supply Lismore via a reservoir located at Ballygalane (TWL 100.88 mOD.) There is

also a local boosted supply from Monamon. A secondary borehole source at Deerpark

supplies directly to the network south of Lismore. Ballyduff Reservoir TWL 63.20

mOD services Ballyduff town and is supplied from Aglish Glencairn borehole with

augmentation from Lismore Reservoir as required. Cappoquin is serviced from

Cappoquin Reservoir TWL 70.02 mOD which is fed from the Monument borehole.

Closed valves separate Lismore from Cappoquin.



There is no test yield available for the combined Glenakeefe and Owenashad streams.

Current supply varies from 600-650 m³/d on average. Treatment consists of slow

sand filtration. The raw water quality was identified as category A2 in the Rural Water

Strategic Study therefore the treatment standard is inadequate for removal of periodic

colour. Upgrade or temporary closure of the treatment plant during periods of high

colour in the water is required.



The monument borehole in Cappoquin has a test yield of 687 m³/d and is identified as

medium risk of pollution in the Rural Water Strategic Study. High nitrates have been

recorded on the source.



The Aglish/Glencairn borehole supplying the Ballyduff Upper reservoir has not been

yield tested, however current average supply of 108 m³/d would appear to be its

capacity.



The Ballyhane borehole on the Ballyduff/Ballylemon/Ballyhane Water Supply adjacent

to Cappoquin has a test yield of 1,363 m³/d, however this source has been identified as

high risk and high nitrates have been recorded.



The Deerpark borehole to the south of Lismore supplies an average of 151 m³/d

directly to supply. This source has not been yield tested. It is expected that the

Deerpark source could supply well in excess of 150 m³/d, however the existing layout

of the network and the absence of storage at Deerpark limits the hours of pumping.

The existing sources on the scheme assuming import of water from Ballyhane would

appear in the region of 2000 m³/d but could be reduced to 1400 m³/d with poor water

quality at Glenakeefe and Owenashad rivers. The high risk status of larger source

boreholes also puts the supply at risk. Additional sources are required.



There are three local storage Reservoirs on the scheme namely Lismore Reservoir

TWL 97.93 mOD, Cap 590 m³ (1955), Ballyduff reservoirs TWL 63.2 mOD, Cap 136

m³ (1975) and Cappoquin Reservoir TWL 70.02 mOD, Cap 727 m³ (1975).









31

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





There is significant residential development pressure within the settlement zones of

Lismore, Cappoquin and Ballyduff. Commercial water supply demand is also expected

to increase in line with domestic demand within the settlement zones.



Table 4.4.1/4.1 L.C.B. Water Supply Existing & Future Demand Estimate

T

h Domestic Non Domestic UFW Total

e (m³/d) (m³/d) (m³/d) (m³/d)

2006 Existing LCB Demand 530 310 567 1407

e 2009 530

xDemand Increase Lismore 100

i Demand Increase Cappoquin 80

s Demand Increase Ballyduff 6

t Total 2009 716 419 640 1775

i 2014 530

nDemand Increase Lismore 128

gDemand Increase Cappoquin 105

Demand Increase Ballyduff 9

E Total 2014 772 452 576 1800

x 2034 530

i Demand Increase Lismore 229

s Demand Increase Cappoquin 198

t Demand Increase Ballyduff 22

i Total 1034 979 573 665 2217



Sources are close to capacity and augmentation from adjacent source at Ballyhane is

limited by network layouts and lack of storage on the source. Upgrade proposals are

required as a priority in view of the potential shortfall to accommodate demand

estimates for 2009 and 2014.



The following upgrade works are required to meet the design demand requirements.



The slow sand filters treating the Glenakeefe and Owenashad rivers requires

refurbishment and automatic shut down during flood conditions with consequent

reduced raw water quality. Alternative sources are required to provide capacity for

future development and in the event of the temporary loss of the Glenakeefe and

Owenashad river sources. A preliminary cost estimate of € 2.0 M is included for

interim new source provision, additional storage capacity and upsizing of 7.0 km of

main connecting Cappoquin, Lismore and Ballyduff. Development of a major surface

water source such as the Blackwater is considered to be the most likely option for

ensuring supply security into the future for the region.



Tallow Water Supply Scheme

Tallow has a single water source, which is extracted from a stream at Knockaun and

treated by means of slow sand filters before gravitating to the Tallow Reservoir TWL

66.45 mO.D. The scheme is close to capacity and low pressures are currently

experienced on the extremities of the scheme resulting from lengths of poor quality

main, where severe encrustation of the cast iron pipework has been identified.









32

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





There is no test yield available for the source. The minimum yield of the stream source

is estimated at approximately 400 m³/d based on observation during the summer

months. Treatment consists of settlement tank followed by 3 no. slow sand filters each

10.4m x 3.7m with a design capacity of 370 m³/d assuming a peak filter rate of 0.2

m/h and one filter bed out of operation for maintenance. The stream source is

classified as high risk and prone to pollution from cattle grazing in the vicinity. The

slow sand filter treatment process is not suitable for the removal of colour which can

be problematic following heavy rainfall events.



The reservoir capacity is 273m³. The scheme construction dates back to the 1940s.



The area currently has 395 domestic connections and 70 non-domestic connections on

the Tallow WSS with an average metered flow from the reservoir over the last 12

months of 379 m³/d. A water audit undertaken as part of the Water Conservation

Project in late 2005 identified a distribution input of 430 m³/d which included 162

m³/d UFW. It is clear from these figures that the scheme is at capacity. There is

substantial zoned land within Tallow for future residential and industrial development.

It is expected that water demand will increase steadily with developments within these

zoned lands. Future demand estimates are as follows:



Table 4.4.1/4.2 Tallow Water Supply Scheme – Existing & Future Water

Demand

Domestic Non UFW Total

m³/d Domestic m³/d m³/d

m³/d

2006 –

Existing Demand 165 101 164 430

2009 234 138 200 572

2014 270 200 200 670

2034 429 448 376 1253



As can be seen there is an expected large increase in demand on the scheme which is

evident by current planning applications for 168 houses in Tallow. The existing

scheme capacity is inadequate to meet projected demand to 2009; therefore upgrade

works are a priority.



Additional source capacity to augment or replace the existing stream is required. A

source and treatment capacity of 1,250 m³/d is required. The West Waterford Water

Supply Scheme Strategic Review which is currently included in the Water Services

Investment Programme 2005-2007 will inform on possible alternative source options.

Existing storage capacity of 273 m³ is inadequate to provide security of supply for an

increasing demand. Provision of 1250 m³ storage representing 24 hrs at design

demand at an elevation of 65 mO.D. is required. The existing distribution network

contains a substantial length of 4” cast iron mains dating back to the 1940s including

the trunk main from the reservoir to the town which will require upgrading to

accommodate increased demand. Preliminary cost estimates of €2.0 includes for new

interim source development along with storage and upgrade of the distribution

network.









33

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





West Waterford Regional Water Supply Scheme

Stage 3 - Rationalisation of Existing Supplies



Clashmore & Environs

The Clashmore Water Supply Scheme is interconnected with adjacent schemes of

Shanacoole and Grallagh. Clashmore village is currently supplied from a borehole at

Ballinamultina to the north of town. A spring at Laurentum which also supplied

Clashmore to the south is now supplying the Shanacoole scheme with the Shanacoole

groundwater supply being discontinued due to water quality issues. Grallagh has a

separate ground water source at high elevation feeding direct to supply. The Grallagh

and Shanacoole schemes are separated by closed valve. The borehole serving

Clashmore supplied an average of 75m3/d over the last 12 months. The test yield of

this source is reported as 92 m3/d. The springs at Laurentum have not been yield

tested however previous assessments suggest a significant yield. A yield estimate of 600

m3/d is assumed for assessment purposes.



The only storage available on the three schemes is located north of Clashmore at

Ballinamultina with Capacity 90.9 m3 (20,000 gals).



Future demand assessment is based on residential development within the settlement

zones of Clashmore and Piltown. For the purpose of demand assessment it is assumed

that demand outside the settlement zones will remain static over the design period.

Table 4.4.1/4.3 Clashmore & Environs WSS – Existing & Future Demand

Estimate

Domestic Non Domestic UFW Total

(m³/d) (m³/d) (m³/d) (m³/d)

2006 Existing Clashmore 50 36 18 104

Existing Shanacoole 29 8 46 83

Existing Grallagh 16 19 45 80

2006 Total 95 63 109 267

2009 95

Demand Increase Clashmore 31

Demand Increase Piltown 20

Total 2009 146 70 127 343



2014 95

Demand Increase Clashmore 40

Demand Increase Piltown 25

Total 2014 160 70 108 338

2034 95

Demand Increase Clashmore 73

Demand Increase Piltown 43

Total 1034 211 80 125 416



Preliminary cost estimates of € 0.75M. includes additional source provision, additional

storage capacity of 450 m3 on high ground between Clashmore and Piltown and

rising/distribution main provision of approx. 2.5 km.









34

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





Ballyduff, Ballylemon Ballyhane

This water supply scheme services a large rural area between Dungarvan and

Cappoquin. The scheme can be divided into two discrete water supply areas. In the

eastern half, the source is at the Glenavaddan springs that feed the Glendog reservoir,

TWL 91.44 mO.D. This area is augmented by a supply from Dungarvan Tower, TWL

47.58 mO.D. The western half of the scheme is supplied from the Ballyhane borehole.

The western section of the scheme is separated by closed valve. A closed valve also

separates the scheme from the LCB scheme.



The average flows from the Glendog reservoir outlet meter for the last 12 months are

190 m³/d with a peak flow of 264 m³/d in November 2005. Water augmentation

from Dungarvan Tower average 82 m³/d with a peak of 136 m³/d in September 2005.

The Ballyhane borehole supplied an average of 379 m³/d with a peak of 494 m³/d in

March 2005. The source capacity of the Glenavadden springs is not capable of

meeting summer demand which necessitates augmentation from Dungarvan Tower

and a reduction in the area served from Glendog in the summer months. A test yield

for the Glenavadden springs source is not available however a yield estimate of 125

m³/d is assumed from observation. The Ballyhane borehole test yield is reported at

1363 m³/d. Nitrate levels in the Ballyhane borehole are high and the long term

viability of this source is in question. Treatment at all sources consists of chlorination

and fluoridation. The storage capacity is limited to the Glendog reservoir constructed

in the 1950‟s with a capacity of 113 m³.



There are currently 343 domestic and 99 non-domestic connections on the

Ballyduff/Ballylemon/Ballyhane water supply scheme with a peak demand of

approximately 650 m³/d including approximately 350 m³/d UFW. The only zoned

land currently served by the scheme is at Ballynameelagh. It is not expected that

demand on the scheme will increase significantly outside the zoned lands. Future

demand estimates are as follows:









35

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Table 4.4.1/4.4 Ballyduff Ballylemon Ballyhane Water Supply – Existing and

Future Demand Estimates.

Domestic Non- UFW Total

m³/d Domestic m³/d m³/d

m³/d

2006 - Existing

Demand 143 150 357 650



2009 – Future 143 150

Ballynameelagh 0 0

Total 2009 143 150 308 601



2014 – 143 150

Ballynameelagh 9 0

Total 2014 152 150 250 552



2034 – 143 150

Ballynameelagh 46 0

Total 2034 189 150 225 564





As can be seen there is an expected marginal drop in water demand on the

Ballyduff/Ballylemon/Ballyhane scheme over the coming years due to the rural nature

of the scheme, the limited amount of zoned land and the expected results of ongoing

water conservation works. It should be noted that water conservation targets are

subject to substantial mains replacement under the water conservation project.



The Glenavadden springs have limited capacity; therefore augmentation from

Dungarvan Tower will be required long term in the absence of an alternative source.

Ballyhane borehole has excess capacity but elevated nitrate levels put this source at

risk. There is currently no storage on the Ballyhane source. A source protection plan

is required for the Ballyhane source. Upgrade of pipework connecting to the LCB at

Cappoquin is proposed to facilitate transfer of water in the event of a pollution

incident and to avail of storage capacity on the LCB scheme. Local storage provision

is also required. Preliminary cost estimate of €1.50M includes for local upsizing of

approx. 7.0 km of 200 dia. mains connecting west to Cappoquin and east towards

Dungarvan with additional storage capacity at an appropriate location and elevation.



West Waterford Regional Water Supply Scheme

Stage 4 – Development of Headworks, Treatment & Principle Trunk Mains



The West Waterford Regional Water Supply Scheme will replace or augment up to 53

existing water supply schemes currently producing in excess of 10,000 m3/d from

numerous sources most of which are at high risk of pollution, with inadequate or no

storage and at or near capacity. A list of the water supply schemes within the West

Waterford Regional area is included in Appendix 5. Preliminary future water demand

estimates to the year 2034 for the region indicate a regional demand of 16,000 m3/d

inclusive of 8,500 m3/d for Dungarvan Town and its environs. Current source and

storage capacities in the region are over taxed with no spare capacity for existing









36

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



development pressures in most areas. The regional scheme will provide security of

supply to the numerous towns and villages in the region.



The most likely source for the scheme is the Blackwater River, which has a recorded

low flow of 7.67 m3/s at Ballyduff. The river is a designated salmonid river under the

EC (Quality of Salmonid WatersRegulations) 1988, SI No.293 of 1988. The proposed

abstraction would have a minimal impact on the river flow. It is envisaged that an

intake and treatment plant would be located a short distance upstream of Lismore on

the Blackwater River from where treated water would be pumped to a reservoir on a

nearby hillside, located at an elevation as is necessary to supply a wide area by gravity.

Preliminary cost estimates for the above proposals of € 65M are based on a run of the

river abstraction, treatment plant, regional storage reservoir and key strategic trunk

mains.





4.4.1/5 Kilmacthomas Water Supply



The Kilmacthomas Water Supply Scheme serves the town of Kilmacthomas and the

hinterland to the south. The scheme has two discrete service areas separated by a

closed valve in the centre of Kilmacthomas. The primary source for the north side of

town is springs collected in a tank at St. Declan‟s Community College. This source

feeds the school directly and pumps to Kilmacthomas Reservoir TWL 65.63 mO.D.

and capacity 118 m3. The Kilmacthomas reservoir dates back to 1924. Two nearby

spring sources can augment the reservoir during summer periods. To the south the

area is supplied from the Ballyogarty well directly into the supply network. The

Ballyogarty well has a test yield of 234 m3/d. The source has recorded elevated levels

of nitrates and is classified as high risk of pollution. There is a second small reservoir at

Currabaha East TWL 45.46 mO.D., capacity 68m3 which is fed from Ballyogarty.

Augmentation of supply from the neighbouring scheme of

Kill/Bonmahon/Annestown is required during peak summer demand by opening a

boundary valve.



The Kilmacthomas Water Supply is currently included in the Water Services

Investment Programme 2005-2007 to advance through Planning. The Scheme will

require additional or alternative sources and treatment. There is a substantial area of

land zoned for residential and industrial development in Kilmacthomas. Development

pressure is evident by 239 houses currently at planning stage. A review of existing and

future demands is as follows:









37

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Table 4.4.1/5 Kilmacthomas Water Supply Scheme – Existing and Future

Demand Estimates

Domestic Non UFW Total

m³/d Domestic m³/d m³/d

m³/d

2006 Existing Scheme 123 42 54 219

2009 123 42

Kilmacthomas 99 20

Total 2009 222 62 95 379

2014 123 42

Kilmacthomas 122 60

Total 2014 245 102 116 463

2034 123 42

Kilmacthomas 221 210

Total 2034 344 252 199 795



The existing scheme has difficulty in meeting current peak demands in the summer

time and augmentation is required from the adjacent Kill/Bunmahon scheme. With

substantial existing development pressure in Kilmacthomas the upgrade of the water

supply scheme is now a priority. Additional source capacity is required to

accommodate future demand assessment. All feasible source options will be examined

in the Preliminary Report including groundwater and linking to the adjacent East

Waterford Water Supply. Provision of 795m3 storage capacity to provide 24 hrs

storage for security of supply and collection network upgrade to accommodate future

peak flows is also proposed. A preliminary cost of €1.9M based on the above

proposals is included.





4.4.1/6 Portlaw Water Supply

The Portlaw Water Supply Scheme consists of a spring source at Laherden which feeds

the reservoir TWL 74.7 mO.D. by gravity. A supplementary borehole at the reservoir

augments the spring source. From the reservoir the town of Portlaw and the

immediate surrounding areas are fed by gravity. There is a PRV controlling pressures

in the centre of town. There are substantial lengths of old mains and service

connections in poor condition in the town. Portlaw Water Supply Scheme is included

in the Water Services Investment Programme 2005-2007 to advance through Planning.

A Preliminary Report is currently being prepared and is expected to be finalised in

January 2007. Additional or alternative sources are being considered and trial well

drilling was completed in October 2006.



The spring source is collected in a buried concrete tank located in boggy ground to the

south of Portlaw. The source capacity is untested but inlet reservoir flows dipped to

288 m³/d in August 2005, from an average of 459m³/d. A safe yield somewhat less

than 458 m³/d is expected. The reservoir is a partially buried reinforced concrete

structure, capacity 427m³. The water treatment consists of chlorination, fluoridation

and pH correction. Water quality following treatment is adequate. An outbreak of

cryptosporidium in November 2006 demonstrates the risk status of the groundwater

source.









38

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



There are currently 467 domestic and 52 non domestic connections on the scheme

with an average demand of 458 m³/d of which 216 m³/d is UFW. There is substantial

residential and industrial zoned land in Portlaw. There are currently 216 houses at

various stages of planning and proposals for a large business park on 26 acres within

zoned lands in Portlaw, representing significant development pressure. The existing

and future demand estimates are as follows:



Table 4.4.1/6 Portlaw Water Supply Scheme Existing & Future Demand

Assessment

Domestic Non UFW Total

m³/d Domestic m³/d m³/d

m³/d





2006 – Existing Scheme 195 45 235 475

2009 – 195 45

Portlaw 90 60

Total 2009 285 105 260 650

2014 - 195 45

Portlaw 131 160

Total 2014 326 205 254 785

2034 – 195 45

Portlaw 313 550

Total 2034 508 595 472 1575



The predicted increase in non domestic demand reflects the large area of industrial

zoned land (98 acres) in Portlaw and the current proposals at planning stage for a

business park over 26 acres of zoned land.



The safe yield of the existing spring source is not sufficient to accommodate future

development in Portlaw. Additional or alternative water sources are required. The

option of local groundwater sources will be evaluated through trial drilling as part of

the Preliminary Report process. Alternative source options such as connection to the

EWWSS will also be considered. The existing reservoir will require augmenting to

provide 24 hours storage for security of supply for the design demand estimate of 1575

m³/d. The distribution network in Portlaw is in poor condition with difficult access to

pipes located at the rear of properties in the town. In many instances there are house

extensions located directly above the watermain. Substantial mains replacement in the

centre of town will be required. Preliminary cost estimate of €3.0M is included for the

above proposals.





4.4.1/7 Ballyduff, Kilmeaden Water Supply Scheme



The water supply scheme serves the zoned lands at Ballyduff (Lower) and Kilmeaden

and the intervening hinterland. There are two separate sources supplying two discrete

areas on the scheme separated by closed valve. To the East the area including the

eastern portion of Ballyduff is supplied from the Adamstown Treatment Plant on the

East Waterford Water Supply Scheme. The area to west including Kilmeaden is









39

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



supplied from the Kilmoyemoge Holy Well via the Hickey Reservoir TWL 171.39

mOD. The average flow from the Kilmoyemoge source meter over the last 12 months

was 314 m³/d.



The safe yield of the Kilmoyemoge well is estimated at 295 m³/d from observations

during dry summer months. Water quality is generally satisfactory. Treatment consists

of chlorination and fluoridation. The storage reservoir is a precast circular concrete

tank, volume 164 m³ dating from the mid 1970‟s. The reservoir is leaking at present

and remediation proposals are being considered. The distribution system requires

substantial maintenance due to failure of pipe collars on various sections



There are approximately 225 domestic and 35 non domestic connections on the

scheme. A water audit undertaken as part of the Water Conservation Scheme recorded

an average demand of 257 m³/d including 139 m³/d UFW. The scheme services the

zoned lands of Ballyduff Lower and Kilmeaden with substantial residential and

industrial zoned lands available for development.



Significant development is expected on the scheme in view of the proximity to

Waterford City and the Waterford City Bypass (currently under construction). There

are currently 60 houses at planning stage within available zoned lands. Future demand

estimates are as follows:



Table 4.4.1/7 Ballyduff/Kilmeaden Water Supply Scheme – Existing & Future

Demand Estimates

Domestic Non UFW Total

m³/d Domestic m³/d m³/d

2006 – m³/d

Existing Scheme 94 143 257

23

2009 94 23

Ballyduff Lower 2 0

Kilmeaden 23 18

Total 119 41 130 290

214 – 94 23

Ballyduff Lower 9 0

Kilmeaden 27 48

Total 2014 130 71 108 309

2034 – 94 23

Ballyduff Lower 44 0

Kilmeaden 41 170

Total 179 193 159 531



The capacity of the existing scheme is insufficient to cater for future demands in the

short to medium term and this will impact on larger development proposals in the

short term. The existing storage capacity at 164m³ does not offer 24 hour storage at

existing demand and is leaking. A new reservoir of 530 m³ to provide 24 hour storage

at design flow is recommended. The elevation of the reservoir should be in the region

of 140 mO.D., significantly less than the existing reservoir at 171.3 mO.D. An

additional or alternative source is required with connection of the scheme to the









40

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



EWWSS the most probable solution. Substantial main s replacement is required to

achieve target UFW levels and to ensure security of supply. A preliminary cost estimate

of € 1.20M is included for storage provision and connection to the EWWSS including

5.0 km rising/distribution main and booster pumping.





4.4.1/8 Kill/Bunmahon/Annestown Water Supply Scheme



The scheme is supplied by two separate sources each feed into separate areas. The

Ballyvadden stream source supplies Ballyvadden Reservoir TWL 57 mO.D. via slow

sand filters. Bunmahon Village is supplied by gravity from this reservoir with outlying

areas supplied via booster pump. The second source is taken from the Mahon River

and treated at Ballylaneen Water Treatment Plant. From Ballylaneen water is pumped

2km to two adjacent reservoirs at Ballyvadden Hill TWL 104.28 mO.D. The

Ballyvadden Hill reservoirs feed Ballylaneen, Kill and Annestown Reservoir TWL

63.44 mO.D. by gravity. Annestown village is supplied via Annestown Reservoir. The

Scheme is connected to the Kilmacthomas Water Supply Scheme at a closed valve

south of Ballylaneen which can facilitate emergency supply from Ballyvadden Hill

reservoir to the Kilmacthomas Water Supply Scheme.



The average supply from the River Mahon source via the Ballylaneen Water Treatment

Plant was 266 m³/d over the last 12 months. The treatment plant at Ballylaneen

includes coagulation, sedimentation, pH correction and filtration. It is currently at

capacity. The Ballyvadden stream source supplied an average of 97 m³/d over the last

12 months. Treatment consists of slow sand filtration. There are 3 filter beds with

combined area of 78m² suggesting a capacity based peak filter rate of 0.15m/hr with

one filter bed out of commission for maintenance of 187m³/day. Slow sand filtration

is insufficient to remove periodic colour from the water source. Storage on the scheme

consists of 4 reservoirs. The two reservoirs on Ballyvadden Hill have a combined

storage volume of 510 m³ (360 + 150) and TWL 104.28 mO.D. The low level

reservoir at Ballyvadden has a storage volume of 176 m³/d and TWL 57 mO.D.

Annestown reservoir has a storage volume of 182 m³ and a TWL of 66.05 mO.D.



There are currently 388 domestic and 67 non domestic connections on the

Kill/Bunmahon/Annestown Water Supply Scheme with an average demand of 363

m³/d of which 132 m³/d is UFW. The water supply scheme served the settlement

zones of Annestown, Ballylaneen, Bunmahon, and the intervening hinterland. There is

a substantial area of land zoned for residential development. It is not expected that

service demand will increase outside of zoned lands. Significant development pressure

on the scheme is evidenced by 122 houses currently at planning stage. There is also

expected to be a peak tourism demand associated with the coastal villages of

Bonmahon (Blue Flag) and Annestown. The current and future demand estimates are

as follows:









41

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Table 4.4.1/8 Kill/Bunmahon/Annestown Water Supply Scheme Existing &

Future Demand Estimate

Domestic Non Peak UFW Total

m³/d Domestic Tourism m³/d m³/d

m³/d m³/d

2006 - Existing 162 67 - 134 363

Scheme

2009 162 67

Annestown 16 2

Ballylaneen 4 0

Bunmahon 8 1

Kill 23 2

Total 2009 213 72 20 165 470

2014 162 67

Annestown 19 2

Ballylaneen 5 0

Bunmahon 14 2

Kill 29 3

Total 2014 229 74 30 157 490

2034 162 67

Annestown 33 4

Ballylaneen 11 2

Bunmahon 42 5

Kill 56 6

Total 2034 304 84 50 187 625



The capacity of the existing treatment plant at Ballylaneen is approximately 265m³/d.

The Ballyvadden Stream source has a minimum flow estimate of 340 m³/d which

would suggest that abstraction in excess of the available treatment capacity of 187m³/d

is not feasible. Current estimated available treated water capacity of 450 m³/d is not

sufficient to accommodate future demands in the short term.



Extending the supply from EWWSS to supply Kill/Bunmahon/ Annestown and the

additional schemes on route was included in Stage 3 proposals for the East Waterford

Regional Water Supply Scheme Preliminary Report. A preliminary cost estimate of €

1,850,000 is included for the above proposals.





4.4.1/9 Stradbally Sheskin Water Supply Scheme



The Scheme supplies the village of Stradbally and the hinterland to the south west as

far as Ballyvoyle. There is a single source taken from an impoundment on the Tay

River. Water is treated with alum dosing and pressure filtration and pumped to the

Stradbally Reservoir TWL 94.8 mO.D., capacity 113m3. Water gravitates to Stradbally

and is boosted to Sheskin.



The Tay River source has an estimated DWF of 0.26m³/s which suggests significant

spare capacity based on current average demand of 191 m³/d. The treatment plant

capacity is approximately 36 m³/hr or 720 m³/d based on 20 hrs operation. The









42

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



limiting factor is the 4” rising main from the treatment works to the reservoir at a

distance of 2km. Maximum flow via the 4” rising mains would be approximately 20

m³/hr or 480 m³/d based on 24 hr pumping.



There are currently 235 domestic and 40 non-domestic connections on the scheme

with an average demand over the last 12 months of 191 m³/d including 68 m³/d

UFW. The scheme serves the settlement zone of Stradbally with significant residential

development pressure evidenced by 155 houses currently at planning stage. Existing

and future demand estimates are as follows:



Table 4.4.1/9 Stradbally Skeskin Water Supply Scheme Existing and Future

Demand Estimates

Domestic Non- UFW Total

m³/d Domestic m³/d m³/d

m³/d



2006 Existing Scheme 98 25 68 191



2009 98 25

Stradbally 65 7

Total 2009 163 32 94 289



2014 98 25

Stradbally 75 10

Total 2014 173 35 93 301



2034 98 25

Stradbally 119 23

Total 2034 217 48 113 378





There is substantial source and treatment capacity available on the scheme. The rising

main from the treatment plant to the storage reservoir is in poor condition with

numerous leaks due to deterioration of the Class B Asbestos pipe and proves very

problematic to maintain as it is located beside the river. The storage capacity of 113m³

does not provide 24 hrs storage and increased capacity will be required. Access to the

reservoir is inadequate requiring crossing of fields. Preliminary cost estimate of €0.8M

includes for rising main replacement, additional storage provision and access roadway.





4.4.1/10 Rathgormuck/Carrick on Suir Environs Water Supply



There are eight small public water supply schemes located immediately to the south of

Carrick on Suir within County Waterford. Seven schemes are located at relatively high

elevation ranging from 120mO.D. to 170mO.D. with the exception of Clonae Power

ranging in elevation from 60 90m O.D. The schemes listed from west to east are

summarised as follows:









43

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Table 4.4.1/10Carrick on Suir Environs Scheme Summaries

Scheme Existing No. of Connection Future Source

Name Demand Demand

(incl. UFW) Estimate

2034

(m³/d) Domestic Non (m³/d) Type Capacity

domestic (m³/d)

Monahida 20 11 0 20 Borehole 141 (test)

Rathgormuck 42 18 12 75 Borehole 222 (test)

Feddens 15 10 0 15 Borehole 65 (est.)

Ballyknock 2 2 0 5 Borehole

Joanstown 34 10 5 34 Borehole 90 (est.)

Garravoone 16 9 2 34 Borehole 85 (est.)

Crehahagh 5.5 6 0 7.5 Borehole 15 (est.)

Clonae Power 44.5 42 7 105 Springs 50(est)

Totals 179 108 26 295.5



Storage is limited to 45m3 on the Garravoone WSS at TWL 149.7 mO.D. and 11.5 m3

on the Clonae power WSS at TWL 76mO.D. The groundwater source at Monahida is

adjacent to a septic tank and slurry spreading and the Rathgormuck supply is located in

the local Co-Op Yard. The Clonae Power spring source is categorised as high risk. It is

proposed to amalgamate the schemes for security of supply with connection to the

adjacent Carrick on Suir Water Supply if feasible or as an individual scheme with

common storage provision. The scheme is included in the Water Services Investment

Programme 2005 – 2007 with approval to advance through planning. Preliminary cost

estimate of € 2.35M is included to cover the above proposals.





4.4.1/11 Clonmel Environs Water Supply Scheme

The Croan, Derrinlaur, Glennagad, Kilgainey, Kilmacomma, Kilnamack, Knocklucas,

Lyranearla and Poulnagunoge Public Water Supply Schemes supply areas contiguous

to Clonmel. Water from Clonmel UDC supplies upwards of 42 connections in the

Croan, Kilgainey and Knocklucas Schemes. The remaining schemes in the area, serving

105 connections, are sourced from groundwater. The borehole for the Poulnagunoge

scheme is rated as highly vulnerable to pollution, indicating that its long-term viability

is questionable and provision should be made to replace it. Storage is limited to a 63m3

reservoir on the Kilmacomma WSS at TWL 65 mO.D. and a 10m3 storage tank on the

Glennagad WSS at TWL 216 mO.D. It is proposed to amalgamate these schemes to

provide security of supply.









44

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Table 4.4.1/11 Clonmel Environs Scheme Summaries

Scheme Name Existing No. of Future Source

Demand Connections Demand

(incl. Estimate

UFW)

(m³/d) Domestic (m³/d) Type Capacity

(m³/d)

Kilmacomma 44 59 44 Clonmel

UDC

Knocklucas 17 14 17 Clonmel

UDC

Glennagad 12 14 12 Borehole 200 (est)

Poulnagunoge 24 11 24 Borehole 110(test)

Lyranearla 30 16 30 Borehole

Croan 22 11 22 Clonmel

UDC

Kilgainey 20 23 20 Borehole 100 (est)

Derrinlaur 7 6 7 Borehole 105(test)

Totals 156 154 156



The groundwater based schemes serve a range of ground levels from 210 – 130 mOD

(in Glennagad) to 20 – 30 mOD (in Derrinlaur). Ground levels in the schemes

supplied from Clonmel UDC vary 15 and 65 mOD. From a rationalisation viewpoint,

the best option for supplying these schemes is from Clonmel Town Council or

Tipperary SR Schemes in the area, for both of which upgrade proposals have recently

been prepared.



Additional storage consisting of three 120m3 final water storage volumes of TWL‟s of

217, 160 and 90 mOD with 100 and 150 mm rising/distribution network would be

required to service a range of ground levels in the area. Booster sets and

interconnection pipework between schemes would be required to accommodate water

transfer from Clonmel UDC presuming adequate water is available. Preliminary cost

estimate of € 2.0 M is included for the above proposals.





4.4.1/12 Bundled Schemes Water Quality Improvement Proposals



In view of the large number of small public water supply sources associated with the

103 public water supply schemes in County Waterford and the relatively large scale of

the necessary water quality provisions countywide it is proposed to take a bundled

scheme approach. A list of the schemes requiring water quality provisions and the

proposed works are included in Appendix 4 and summarised below as follows:



UV Treatment:

A total of 30 schemes to be fitted with UV disinfection as a back-up to the existing

chlorination system, in order to ensure microbiological quality.



Estimate of capital cost per scheme € 6,000









45

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



pH Correction:

A total of 36 schemes require to be fitted with pH correction systems in order to

prevent corrosion problems due to aggressive water.



Estimate cost per scheme € 3,000



Chlorine Monitoring and boosting system:

A total of 22 schemes to be fitted with chlorine monitoring and booster dosing

systems to ensure adequate residuals and disinfection. Systems to be fitted include

chlorine monitor and chlorine dosing pumps and necessary electronics.



Estimate cost per scheme € 7,500



Turbidity:

A total of 10 schemes containing 30 separate reference points to be fitted with

turbidity monitors to reduce risk of cryptosporidium contamination of drinking water,

as recommended by the EPA – EC (Drinking Water) Regulations 2000, A Handbook

for Implementation for Sanitary Authorities.



Estimate cost per installation € 6,000



Filter to waste facility:

A total of 6 schemes containing 16 reference points to be fitted with filter to waste

facility, to minimize the risk of cryptosporidium breakthrough after backwashing, as

recommended by the EPA – EC (Drinking Water) Regulations 2000, A Handbook for

Implementation for Sanitary Authorities, 2004.



Estimate Cost per installation € 11,500



Testing and Office Facilities:

In order to provide suitable accommodation for plant operators to carry out essential

water testing and record keeping at the treatment plants as well as Health, Safety &

Welfare requirements, a total of 8 schemes require upgrading of laboratory/work

station units.



Estimate cost per scheme € 6,000



Alarms and Telemetry:

A total of 12 schemes to be fitted with alarms and telemetry links, in order to provide

real time water quality data to ensure rapid response to water problems at unmanned

water treatment plants.



Estimate cost per scheme € 7,500



Sludge collection facilities:

A total of 4 schemes to be provided with sludge tanks, to enable solids to be retained

before disposal of clear water to waste. This is necessary to comply with current

legislation governing disposal of such waste material.









46

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Total estimate cost € 20,000

Summary of Cost Estimates Quantity Rate Total

(€) (€)

UV Treatment: 30 6,000 180,000

pH Correction: 36 3,000 108,000

Chlorine Monitoring and boosting system: 22 7,500 165,000

Turbidity: 10 6,000 60,000

Filter to waste facility: 16 11,500 184,000

Testing and Office Facilities: 8 6,000 48,000

Alarms and Telemetry: 12 7,500 90,000

Sludge collection facilities 20,000

Total 855,000









47

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



4.4.2 Sewerage Schemes



4.4.2/1 Dungarvan Sewerage Scheme



Dungarvan Sewerage Scheme, currently at commissioning stage will provide secondary

treatment capacity for 25,000 p.e. with a discharge to sea outfall. The design of the

plant to the year 2022 was based on the following:



Table 4.4.2/1a Dungarvan Wastewater Treatment Plant Existing Design Loads

p.e. Flow (m³/d)



Existing Domestic 9833 1968

Future Domestic 5817 1161

Existing Non Domestic 6783 1413

Future Non Domestic 2567 378



Total 25,000 4,920



The latest population estimate for Dungarvan Town and the immediate vicinity served

by the collection system is 13,422 people based on the July 06 Geodirectory House

Count and an average occupancy rate of 3 person/house. In addition there are 396

houses currently at various stages of planning. Assuming all of these developments

proceed there is a potential short term population of 14,610 in the catchment area.



There has been significant commercial development in Dungarvan in recent years with

a large shopping mall development and numerous light industrial units. There are also

significant efforts to attract industry to the town following the closure of Waterford

Glass. In economic terms it is accepted that on average 34% of the population can be

anticipated to be available to the labour force. The anticipated increase in population

of Dungarvan & its environs will require the creation of substantial additional jobs

within the town. The industrial component of this will be catered for with the

expansion of the local enterprise parks and the redevelopment of the Waterford

Crystal site. The Town Development Plan will facilitate the generation of employment

opportunities by ensuring that sufficient and appropriate land is zoned and available

for development. On this basis an assumption that the non-domestic loading for

Dungarvan should increase to reflect the increase in scale of the residential sector. The

revised 2009, 2014 and 2034 load projection for Dungarvan is as follows:



Table 4.4.2/1b Dungarvan Wastewater Treatment Plant Future Load Estimates

2006 2009. 2014 2022 2034

p.e. p.e. p.e p.e. p.e.



Domestic 13,422 14,610 15,494 16,909 19,031

Commercial 2,550 2,874 3,060 3,357 3,803

Industrial 4,233 4,410 4,705 5,183 5,419

Headroom 2,021 2,189 2,326 2,545 2,825



Total 22,226 24,083 25,585 27,994 31,078









48

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Headroom is included at 10% of load to reflect uncertainties in future load estimation

particularly in relation to industrial loading with the possibility of a single development

having a significant impact on load estimates. Additional Treatment Capacity of 10,000

p.e. is proposed to accommodate current development trends and to reflect the

likelihood of significant additional future loading as investment is attracted to the

county town. The existing treatment plant now at commissioning stage cost

€11,276,200 or €451 per p.e. based on tender prices in 2003. It is expected that unit

costs per p.e. to provide additional capacity would be greater than those on the original

contract due to the various site and design constraints over and above working on a

green field site. The cost to provide additional treatment capacity is estimated at €600

p.e.



Cost Estimate

Quantity Rate Capital

(€) Cost (€)

Provision of additional treatment capacity 10,000 600 6.00m

Non Contract Costs at 15% 0.90m

Total Cost Estimate (Incl VAT @ 13%) 6.90m





4.4.2/2 Ballinroad Sewerage Scheme



Ballinroad is a satellite settlement to Dungarvan which has experience concentrated

residential development in recent years. The current population at Ballinroad is

estimated at 1,302 based on housing counts and an assumed occupancy rate of 3

persons/house. There are 228 houses in Ballinroad currently at various stages of

planning. Assuming all these developments proceed in the short term the potential

population in Ballinroad is 1986.



Proposals were considered to divert the waste flow from Ballinroad to the Dungarvan

Plant as the Ballinroad Treatment Plant (cap 750 p.e.) is currently overloaded.

However, the consequences of development pressures in Dungarvan which limit

available capacity in the Dungarvan Wastewater Treatment Plant make this option

strategically impracticable. For the purpose of strategic needs assessment we have

assumed the treatment capacity at Ballinroad will be augmented or replaced. The

Ballinroad Treatment plant is on a relatively compact site discharging to estuarine

waters at the mouth of the Glendine River. The future population at Ballinroad is

expected to rise to 2,500 over the next 25 years in view of the zoned land available and

recent development trends. A preliminary cost estimate of € 1.50M is proposed based

on a 2,500 p.e. treatment plant requirement.





4.4.2/3 Tramore Sewerage Scheme – Wastewater Treatment Plant Design

Loading Review



The Tramore Wastewater Treatment Plant currently at construction stage will provide

secondary treatment for a population equivalence of 20,000 during summer months

with a reduced design loading off season of less then 14,000 pe. Effluent discharge is

via a 2km long sea outfall.









49

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





Table 4.4.2/3a Tramore Wastewater Treatment Plant Existing Design Loads

p.e. Flow

Existing Domestic 8,621 1,940

Future Domestic 1,429 454

Non Domestic 2,667 462

Tourism 7,283 1,644



Total 20,000 4,500



The latest population estimate for Tramore within the settlement zone area based on

the July 2006 Geodirectory House Count and an occupancy rate of 3 persons/house is

14,421 which reflect significant residential development in recent years. This is

expected to continue with 460 houses currently at various stages of planning. There are

also two major shopping complexes and a new school at planning stage in Tramore. In

addition available zoned land in the settlement zone includes 105 acres residential and

6 acres tourism. The existing and future load estimates for Tramore are as follows:



Table 4.4.2/3b Tramore Wastewater Treatment Plant Future Load Estimates

2006 2009 2014 2034

p.e. p.e. p.e. p.e.

Domestic 14,421 15,801 16,143 17,513

Non Domestic incl. Tourism

Peak Load 8,500 8,700 9,050 10,500

Headroom at 10% 2,300 2,450 2,520 2,800





Total 25,221 26,950 27,713 30,813



Additional treatment plant capacity of 10,000 p.e. is required to accommodate current

development trends. The assumed unit cost per p.e. of additional treatment capacity is

predicted to be greater than the unit contract costs for the existing treatment plant at €

421/pe (incl. VAT) due to the site and design constraints involved. The cost to

provide additional treatment capacity is estimated at €600 p.e.



Cost Estimates Quantities Rate Capital

Cost

€ €

Provision of additional treatment capacity 10,000 600 6.00m

Non Contract Costs at 25% 0.90m

Total Capital Cost 6.90m





4.4.2/4 Tramore Sewerage Scheme – Collection System, Stage 2



The existing collection system in the old part of town is a combined system draining to

the Promenade pumphouse. There is also pumped flow to the Promenade

pumphouse from a sub catchment via the Cove pumphouse. More recent

developments are serviced by foul and storm systems, the former discharging to the









50

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



existing old town combined system with the latter discharging to existing watercourses

or the sea, as appropriate. Works are currently underway to redirect the pumped

output from the Promenade pumphouse to the site of the new wastewater treatment

plant at Riverstown, which is currently under construction. Storm water overflows

discharge to the sea to provide relief to the sewers where appropriate.



Tramore Sewerage Scheme – Collection System, Stage 2 is included in the WSIP 2005-

2007 to advance through planning. A Preliminary Report is currently being prepared to

assess the capacity, condition and levels of infiltration on the existing network. The

report will identify areas of unsatisfactory hydraulic performance under future flows

and make recommendations on resolving deficiencies and undercapacities in the

network. Existing overflows discharging to the marine environment require urgent

investigation and remedial measures to ensure compliance with the quality of Bathing

Waters and/or Urban Wastewater treatment Regulations as appropriate. The report

will assess existing and future storm flows with a view to minimizing pumping costs

and overflows with an optimum solution to reduce storm overflows to an acceptable

level. A preliminary capital cost for provision of the required collection network

improvements is € 10.2M





4.4.2/5 Waterford Grouped Towns & Villages Sewerage Scheme



The Waterford Grouped Towns & Villages Sewerage Scheme which consists of seven

towns, namely, Ardmore, Ballyduff/Kilmeaden, Cappoquin, Dunmore East,

Kilmacthomas, Stradbally and Tallow is included in the Water Services Investment

Programme 2005-2007 with a start date in 2007. In view of the increased level of

residential developments in recent years it is considered prudent at this stage to review

the design domestic load included in the Design Review Report dated Nov. 2004 for

the above scheme.



Table 4.4.2/5 Waterford Grouped Towns and Villages Sewerage Scheme –

Future Domestic Design Load Review

Design Review Future Domestic Load Estimates

Report 2005

Domestic 2006 2009 2016 2034

Demand p.e. p.e. p.e. p.e. p.e.

Ardmore 1284 891 1392 1553 2197

Cappoquin 1873 1059 1638 1773 2315

Dunmore East 4544 3078 4536 4953 6623

Kilmacthomas 1702 1098 1815 1953 2503

Ballyduff/Kilmeaden 1363

Stradbally 1017 795 1260 1318 1550

Tallow 2060 1182 1686 1894 2727



As can be seen above the domestic design load allocation will be realised or exceeded

in the towns of Ardmore, Dunmore East, Kilmacthomas and Stradbally on full

development of existing planning applications which is the basis of the 2009 p.e.

projection. If we assume the design of non-domestic load allocation remains

unchanged the following design plant loading revisions are required.









51

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





Current Design Additional Domestic Revised Design

Load P.E. Load P.E. Load P.E.

Ardmore 3,777 1,223 5,000

Dunmore East 8,314 1,686 10,000

Kilmacthomas 1,902 798 2,700

Stradbally 1,185 515 1,700



For preliminary cost estimates the additional cost of upsizing treatment plant capacities

is estimated at €750/pe. The additional cost estimates for the Grouped Towns &

Villages Sewerage Scheme are as follows:



Quantity Rate Capital Cost

€ €

Ardmore 1,223 p.e. 750 917,250

Dunmore East 1,686 p.e. 750 1,264,500

Kilmacthomas 1,902 p.e. 750 1,426,500

Stradbally 515 p.e. 750 386,250

Total 4,000,000





4.4.2/6 Lismore Sewerage Scheme



The existing Lismore Sewerage Scheme consists of a combined collection network

discharging to an extended aeration treatment plant with discharge to the River

Blackwater. The capacity of the treatment plant is nominally 1600 p.e.; however the

secondary settlement tank can only accommodate 1300 p.e. at 6 DWF. The hydraulic

load on the plant is problematic due to a lack of storm water drainage in Lismore. The

current population of Lismore based on July 06 Geodirectory and an occupancy rate

estimate of 3 persons/house is estimated at 1635. There are an additional 240 houses

at various stages of planning and a further 45 acres of residential zoned lands available

for development within the settlement zones of Lismore. The estimate future load for

Lismore is as follows:



Table 4.4.2/6 Lismore Sewerage Scheme – Future Demand Estimate

2006 2009 2014 2034

p.e p.e. p.e. p.e.



Domestic 1635 2355 2502 3091

Non Domestic 700 750 800 1000

Headroom of 10% 234 310 330 409



Total

2569 3415 3632 4500



The existing extended aeration plant is overloaded and requires additional capacity to

provide 4500 p.e. to cater for future development loads. The existing plant is located

in an old quarry site which affords no room for conventional expansion. An

alternative site to provide treatment in parallel or an alternative treatment plant to

replace existing facilities is required.







52

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





It is essential for the efficient operation of the existing and proposed treatment plants

to minimise the surface water contribution to the combined network. A storm water

collection system is required to facilitate transfer of surface water connection from the

existing combine system and for future development. For preliminary costing

purposes a length of 3.5km of storm water sewer is proposed which includes storm

water drainage for all main roads in Lismore Town. In addition significant combined

network upgrade is also required to accommodate future flows and minimise

infiltration. Cost estimate for the above proposals are as follows:



Quantity Rate Capital Cost

€ €

Provision of 3,000 p.e. additional

treatment capacity 3,000 p.e. 600 1,800,000

Storm water collection network 3,500m 325 1,137,500

Upgrade existing combined network 3,500m 325 1,137,500

Transfer of existing surface water

connections 250,000

Non Contract Costs at 15% 650,000

Total 4,975,000





4.4.2/7 Portlaw Sewerage Scheme



The Portlaw Sewerage Scheme consists of a combined gravity collection system with a

1750 p.e. estimated aeration treatment plant discharging to the Clodiagh River. There

is also a small combined collection system on the south side of the River Clodiagh

feeding a septic tank prior to discharge to the river. The current population estimate in

Portlaw based on the July 06 Geodirectory and an occupancy rate estimate of 3

persons/house is 1638. There are currently 216 houses at various stages of planning in

Portlaw with an additional 82 acres of residential zoned land available for development

within the settlement zone. There is no major industry and limited commercial load

on the scheme; however commercial loading is expected to increase in view of the

recent development of serviced industrial site on the industrial zoned lands in Portlaw

and in line with population increase. The future load estimate for Portlaw Sewerage

Scheme is as follows:



Table 4.4.2/7 Portlaw Sewerage Scheme – Future Design Load Estimates

2006 2009 2014 2034

p.e. p.e. p.e. p.e.

Domestic 1,638 2,286 2,553 3,623

Non Domestic 200 300 468 1,000

Headroom at 10% 184 259 302 462



Total

2,022 2,845 3,323 5,085



The existing plant is currently overloaded and there is limited room available on the

site for plant expansion. Additional treatment capacity of 3,500 p.e. is required.









53

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Proposals include a pumping station and river crossing to connect the collection

system on the south side of the River Clodiagh to the proposed treatment plant. In

order for the proposed plant to operate satisfactorily, surface water and infiltration to

the existing combined network must be minimized. Provision of a storm water

collection system and upgrade to the combined system will be required. For

preliminary cost estimation a length of 2500m of storm sewer and a similar length of

combined sewer upgrade is assumed. Cost estimates for the above proposals are as

follows:



Quantity Rate Capital Cost

€ €

Provision of additional

2750 pe treatment capacity 3,500 p.e. 600 2,100,000

Pumping station and 500m of

rising main 250,000

Combined collection network

upgrade 2,500 325 812,500

Storm Water Collection

network 2,500 325 812,500

Non Contract Costs at 15% 600,000

Total 4,575,000





4.4.2/8 Sludge Management Plan – East County Satellite Centre



A Sludge Management Strategy for County Waterford has been prepared in accordance

with the guidance document „Sludge Management Plans: A Guide to Their Preparation And

Implementation (DoELG 1998). The strategy proposes a sludge treatment Hub centre at

Dungarvan with two satellite sites in the east and west of the county to supply the Hub

centre. The Hub Centre is being progressed as part of the Dungarvan Sewerage

Scheme based on a thermal drying process which produces a relatively small quantity

of material in comparison with alternative treatment options and a granulated or

pelletised form of final product, which is the preferred form of biosolids for

agricultural application. The Dungarvan Sewerage Scheme is included in the WSIP

2005-2007 and is currently at commissioning phase.



A sludge satellite centre for the west of the county is being progressed as part of the

Waterford Grouped Towns & Villages Sewerage Scheme which is included in the

WSIP 2005-2007. The location of the satellite centre is at Cappoquin. The Cappoquin

Satellite Centre will be required to store sludges emanating from septic tanks (Primary

Sludge), and sludges from Secondary Wastewater Treatment Plants (Secondary Sludge)

separately requiring two storage tanks. The sludge at the Cappoquin Sludge Satellite

Site will need to be dewatered to a level of 15 – 20% dry solids, as this is the range

which will be acceptable at the Sludge Hub Centre.



A parallel sludge satellite centre is required for the east on the county requiring sludge

storage and dewatering facilities. Based on cost estimates prepared for the Cappoquin

Sludge Satellite Centre a preliminary cost estimate of €3.0M is included









54

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





4.4.2/9 Bunmahon Sewerage Scheme



The existing Bunmahon Sewerage Scheme consists of a combined collection system

discharging to a 56.25 m³ septic tank and sea outfall regulated by the tide. There are

two additional septic tanks serving Osbourne Terrace (capacity 18.4m³) and

immediately east of Knockmahon (capacity 17.75m³). The current population within

the settlement zone of Bunmahon is 306, based on house counts and an assumed

population density of 3 person/house. There are also 19 houses at various stages of

planning in the area. The existing septic tanks are at capacity. There are 13 acres of

residential zoned land within the settlement zone available for development.

Continued residential development is expected in addition to tourist influx in summer

months. The expected future loading on the scheme is as follows:



Table 4.4.2/9 – Bunmahon Sewerage scheme Future Load Estimate

2006 2009 2014 2034

Domestic 306 363 405 575

Non Domestic/Tourism 70 70 130 380

Headroom 38 43 54 95



Total 414 476 589 1050





The proposals include secondary treatment with capacity of 1050 p.e. pumping stations

to pick up two smaller septic tank outfall and connecting pipework. It will also be

necessary to divert storm water from the combined collection system where practical

to a separate storm sewer to minimise hydraulic load on the plant. The Bunmahon

Sewerage Scheme is included in the Water Services Investment Programme 2005- 2007

with approval to advance through planning. For preliminary costing we have assumed

1,500 m foul sewer and 1,500 m storm sewer requirement.



Quantity Rate Capital Cost

€ €

1050 p.e. package treatment plant 1,050 p.e. 600 630,000

Combined collection system upgrade 1,500 264 396,000

Storm sewer collection system 1,500 264 396,000

Pumping Stations 2 200,000

Transfer of connections 30,000

Non Contract Costs at 15% 248,000

Total 1,900,000





4.4.2/10 Kill Sewerage Scheme



The existing Kill Sewerage Scheme consists of a combined collection system serving

the village and gravitating to a package treatment plant (150p.e.) to the west of town.

with discharge to Ballymurrin Stream. The assimilative capacity of the receiving water

is small. The current population estimate of Kill is 204 based on the July ‟06

Geodirectory and an occupancy rate estimate of 3 persons/house. There are an









55

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



additional 55 houses at various stages of planning. With a further 18 acres of

residential zoned land available for development within the settlement zone. The

existing sewerage scheme is overloaded. Future loading estimates are as follows:



Table 4.4.2/10 Kill Sewerage Scheme – Future Load Estimates

2006 2009 2014 2034

p.e. p.e. p.e. p.e.

Domestic 204 369 407 561

Non-Domestic 50 60 65 80

Headroom at 10% 25 43 47 64



Total

279 472 519 705





Provision of a 750 p.e. treatment plant is required. Separate storm sewer collection

system and upgrade of the existing combined system to minimise surface water and

infiltration in the combined system. For preliminary cost estimates a length of 1500m

of storm sewer and combined sewer upgrades proposed. Cost estimates for the above

proposals are as follows:



Quantity Rate Capital Cost

(€) (€)

Provision of 750 p.e. treatment 750 p.e. 600 450,000

Storm sewer and combined sewer

Upgrade. 1500 m 264 396,000

Non Contract Costs at 15% 127,000

Total 973,000





4.4.2/11 Dunhill Sewerage Scheme



The existing Dunhill Sewerage Scheme consists of a combined sewerage collection

system discharge to a septic tank capacity 23.9m³ with a discharge to a small stream.

The current population in Dunhill is 222 based on recent house count and an

occupancy rate estimate of 3 person/house. There are an additional 35 houses at

various stages of planning and a further 12 acres of land zoned for residential

development within the settlement zone. The existing sewerage scheme is overloaded

and requires upgrading. The existing and future load estimates on the scheme are as

follows:



Table 4.4.2/11 – Dunhill Sewerage Scheme – Existing & Future Load Estimates

2006 2009 2014 2034

p.e. p.e. p.e. p.e.

Domestic 222 327 353 458

Non Domestic 50 50 70 100

Headroom 27 38 42 56









56

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



Total 299 415 465 614



A 650 p.e. secondary treatment plant is required with possible upgrade of the

combined sewer collection network with transfer of surface water collections to new

storm sewer collection network where possible. For preliminary costing purposes 400

m of combined sewer upgrade and 600 m of storm sewer have been included.



Quantity Rate Capital Cost

(€) (€)

650 p.e. secondary treatment

Plant 650 p.e. 600 390,000

Combined sewer upgrade 400 264 105,600

Storm sewer collection network 600 264 150,400

Non Contract costs at 15% 97,000

Total 743,000





4.4.2/12 Ballymacarbry Sewerage Scheme



The existing Ballymacarbry Sewerage Scheme includes combined collection scheme

with independent storm discharge from developments and road drainage directly to

the River Nire. The treatment plant consists of an RBC with capacity of 250 p.e. and

discharge to the River Nire. The current population estimate for Ballymacarbry based

on the July ‟06 Geodirectory house count and an occupancy rate estimate of 3

persons/house is 144 with an additional 16 houses currently at various stages of

planning. It should be noted that a large development consisting of 73 houses was

recently withdrawn. There is 38 acres of residential zoned land available in

Ballymacarbry. Current non-domestic load is limited to two pubs. There is an existing

industrial facility located in Ballymacarbry, however this has its own private treatment

system discharging to the Nire River under licence. The existing and future load

estimate in Ballymacarbry is as follows:



Table 4.4.2/12 Ballymacarbry Sewerage Scheme – Future loading Estimates

2006 2009 2014 2034

p.e. p.e. p.e. p.e.

Domestic 144 192 233 398

Non Domestic 40 53 65 110

Headroom of 10% 18 25 30 51

Total 202 270 328 559



An increase in treatment capacity to 600 p.e. is required to facilitate current

development trends. Based on package plant cost estimates and 15% for non contract

costs estimate for these works is €400,000.









57

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



4.4.2/13 Crooke Sewerage Scheme



The existing Crooke Sewerage Scheme consists of a combined collection network

gravitating to a septic tank capacity approximately 90 m³ with discharge to the River

Suir Estuary. There is an additional treatment facility consisting of a filter media

serving a private development. The current population estimate of Crooke is 456

persons based on the July ‟06 Geodirectory and an occupancy rate of 3 persons/house.

There are 48 houses currently at planning stage and an additional 32 acres of residential

zoned land within the settlement zone. The topography of the settlement zone limits

the area of zoned land that can gravitate to the septic tank site however it is considered

prudent to include for all the development land for treatment provision with the

possibility of including pumping at a future stage. The future load estimate for Crooke

is as follows:





Table 4.4.2/13 – Crooke Sewerage Scheme – Future Design Load Estimate



2006 2009 2014 2034

p.e. p.e. p.e. p.e.

Domestic 456 600 669 944

Non Domestic 30 40 45 75

Headroom of 10% 49 64 73 102



Total 535 704 787 1121





Provision of 1100 p.e. plant is required to accommodate future development. For

preliminary cost estimates a length of 2,000m of sewer is also included for expected

combined network upgrade and storm water collection network to minimise surface

water and infiltration on the combined network. Cost estimates are as follows:



Quantity Rate Capital Cost

(€) (€)

Provision of 1100 p.e. treatment plant 1100 p.e. 600 660,000

Sewer Upgrade 2,000m 264 528,000

Non Contract Costs at 15% 178,000

Total 1,366,000





4.3.2/14 Clashmore Sewerage Scheme – Collection System



A new 700 p.e. wastewater treatment plant providing secondary treatment is at

construction stage at Clashmore discharging to the Greagagh River. It is essential for

the efficient operation of the treatment pant to minimise storm water flow and

infiltration on the collection system.



The existing combined collection system at Clashmore follows the path of the

Greagagh River for much of its length and includes a river crossing. There is

significant infiltration with recorded flows of 19 times dry weather flow. Proposals for









58

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



upgrade of the collection system are included in the Water Services Investment

Programme 2005-2007 with approval to advance through Planning.



A detailed manhole survey and CCTV survey are required to identify the exact layout

and condition of the network. The capacity of the collection network to accommodate

future design flows should be assessed by means of hydraulic model. It is proposed to

provide a separate storm water collection system and divert as much surface water

from the combined system as practicable. Significant pipe repair or replacement is also

expected following detailed network assessment. For preliminary costing we have

estimated 1.25 km of new storm sewer and 1.50 km of repair or replacement of

existing sewer.



Cost Estimate Quantity Rate Capital Cost

(€) (€)

Combined collection system upgrade 1,500m 264 396,000

Storm sewer collection system 1,250m 264 330,000

Transfer connection s from storm sewer 50,000

Non Contract cost at 15% 116,000

Total Cost Estimate 892,000





4.4.2/15 Clonea Power Sewerage Scheme



The existing Clonea Power Sewerage Scheme consists of a combined sewer collection

system with a package treatment plant discharging to the River Clodiagh. The existing

population in Clonea Power based on the July ‟06 Geodirectory and an occupancy rate

estimate of 3 persons/house is 135. There are currently 79 houses at various stages of

planning within the settlement zone which would more than double the existing

population. There is also an additional 15 acres of residential zoned land available for

development. The existing septic tank will be overloaded on completion of the current

planned developments. The future load for the Clonea Power Sewerage Scheme is

estimated as follows:



Table 4.4.2/15 Clonea Power Sewerage Scheme – Future Design Load

Estimates

2006 2009 2014 2034

p.e. p.e. p.e. p.e.



Domestic 135 372 388 453

Non Domestic 50 75 80 100

Headroom at 10% 19 45 48 55

Total 204 492 516 608





Provision of a 600 p.e. package plant is required to accommodate development trends.

Minimising surface water and infiltration on the combined network is essential for the

efficient operation of the plant.









59

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



For the purpose of preliminary cost estimation it is assumed that some collection

network repair or upgrade will be required. Cost estimates for the above proposals are

as follows:



Quantity Rate Capital Cost

(€) (€)

Provision of 600 p.e. treatment capacity 600 600 360,000

Collect network upgrade 100,000

Non Contract Costs at 15% 69,000

Total 529,000





4.4.2/16 Aglish Sewerage Scheme – Collection Network



The existing Aglish Sewerage Scheme consists of a combined collection network

serving the village gravitating to a pumping station near the Church to the north side

of town. A rising main from the pump stations discharge to a vented manhole on the

south side of town from where the remainder of the scheme gravitates to the

treatment plant site, with discharge to the River Geoish. The treatment plant with a

capacity of 800 p.e. is currently at construction stage and is included in the Water

Services Investment Programme 2005-2007. It is essential for the efficient operation

of the treatment plant to minimise storm water flow and infiltration to the collection

system. A detailed manhole and CCTV survey are required to assess the condition of

the network and identify all connections. It is expected that significant upgrade and

diversion of surface water to the stream which traverses the village will be required.

The existing pumping station also requires upgrade including replacing the existing

building which is located directly over a large ope in the pump sump making access

unsafe. For preliminary cost estimates a length of 1,750m of storm sewer and 1,250 of

combined sewer upgrade is proposed. The cost estimate of the above proposals is as

follows:



Quantity Rate Capital Cost

(€) (€)

Storm sewer 1,750m 264 462,000

Combined sewer upgrade 1,250m 264 330,000

Pumping station upgrade 30,000

Non Contract Cost at 15% 123,000

Total 945,000





4.4.2/17 Villierstown Sewerage Scheme – Collection Network



The existing Villierstown Sewerage Scheme consists of a combined collection network

serving the village gravitating to the treatment plant site, with discharge to the

Blackwater River. The treatment plant with a capacity of 700 p.e. is currently at

construction stage and is included in the Water Services Investment Programme 2005-

2007. It is essential for the efficient operation of the treatment plant to minimise

storm water flow and infiltration to the collection system. A detailed manhole and

CCTV survey are required to assess the condition of the network and identify all









60

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



connections. It is expected that significant upgrade and diversion of surface water to

local watercourses as appropriate will be required. For preliminary cost estimates a

length of 1,500m of storm sewer and 1,250 of combined sewer upgrade is proposed.

The cost estimate of the above proposals is as follows:





Quantity Rate Capital Cost

(€) (€)

Storm sewer 1,500m 264 396,000

Combined sewer upgrade 1,250m 264 330,000

Non Contract Cost at 15% 109,000

Total 835,000





4.4.2/18 Lemybrien Sewerage Scheme



The existing Lemybrien Sewerage Scheme consists of a combined sewerage collection

network gravitating to a septic tank capacity 21m³. The septic tank discharges to the

River Tay via a 4,000m2 constructed wetland. The current population of Leamybrien is

186 based on July ‟06 Geodirectory House County and an occupancy rate of 3

persons/house. There are currently 26 houses at various stages of planning and an

additional 24 acres of zoned land available for development with the settlement zone.

The septic tank is currently overloaded. The future loading estimate for the Lemybrien

Sewerage Scheme is as follows:



Table 4.4.2/18 Lemybrien Sewerage Scheme – Future Design Load Estimates

2006 2009 2014 2034

p.e. p.e. p.e. p.e.

Domestic 186 264 290 393

Non Domestic 40 50 50 60

Headroom at 10% 23 31 34 45



Total 249 345 374 498





Provision of a 500 p.e. package plant to replace the existing septic tank is required with

discharge to the constructed wetland. The wetland capacity to provide tertiary

treatment is adequate. Storm water overflow from the proposed treatment plant can

be routed through the constructed wetland prior to discharge to the River Tay. The

cost estimate for the above proposals is as follows:



Quantity Rate Capital Cost

(€) (€)

Provision of 500 p.e. treatment capacity 500 p.e. 600 300,000

Non Contract Costs @ 15% 45,000

Total 345,000





4.4.2/19 Waterford City Environs Sewerage Scheme









61

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





There is a substantial area of institutional, industrial and special commercial zoned land

identified in the County Development Plan 2005-2011on the environs of Waterford

City. This area already contains the Waterford Institute of Technology, Waterford

Business and Technology Park and proposals for a large retail warehouse development.

The industrial zoned land including the current development within the Business and

Technology Park is 73.9 acres. The current development pumps wastewater to the city

collection network. A further 60 acres of special commercial related zoned land is

available. There is an existing development proposal at planning stage for a 15,939 sq.

m retail warehouse located within this zoned land. In view of the development

potential of the area adjacent to the city and the college campus the provision of

wastewater treatment capacity to cater for full development of the zoned land is

proposed. The total area of commercial and industrial zoned land is 134 acres.

Assuming full development at light industry loading rate of 100 p.e. /acre. A

preliminary cost estimate of € 9.00M is proposed for the provision of a collection

system, a 13,400 p.e secondary treatment plant and discharge to the Suir River Estuary.





4.4.2/20 Annestown Sewerage Schemes



Annestown is a picturesque village located on the coast with scenic views and a

popular summer beach destination for visitors. Development in the village in recent

years has been of low density and small scale in nature. The current population of the

village is estimated at 72 persons based on house counts. The Waterford County

Development Plan 2005-2007 identifies a development strategy for Annestown to

develop the adjoining lands to give some depth to strengthen the village settlement and

promote some needed commercial (retail) development for the permanent population.

There is a current planning application for 38 houses with an additional 8.6 acres of

land zoned for residential development. A future design population estimate of 300

p.e. is included for cost estimation.



The existing wastewater collection system in Annestown consists of a box culvert

originally discharging spring water to the Annestown stream. In the intervening years

this box culvert was utilised to connect foul sewer connections from a number of

houses and a septic tank was installed to intercept the box culvert prior to discharge to

the Annestown stream. A 300 p.e. package treatment plant and foul collection network

is proposed. The cost estimate for the above proposals is as follows:



Quantity Rate Capital Cost

(€) (€)

Provision of 300 p.e. treatment capacity 300 p.e. 600 180,000

Foul Collection System 300,000

Transfer connection s from storm sewer 30,000

Non Contract Costs @ 15% 77,000

Total 587,000









62

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





4.4.2/21 Rathgormack Sewerage Schemes



The village of Rathgormack is located 11kms southwest of Carrick-on-Suir. There is

no public sewerage system at present. The current population of Rathgormack is 66

based on July ‟06 Geodirectory House County and an occupancy rate of 3

persons/house. There are currently 39 houses at various stages of planning and an

additional 31 acres of zoned land available for development with the settlement zone.

Proposals include for a 350 p.e. treatment plant and foul collection system with

discharge to adjacent stream of the Clodiagh River. The treatment plant should be

designed with future duplication in mind in view of the relatively large area of zoned

land available. A preliminary cost estimate of € 750,000 is proposed for the provision

of a collection system, 350p.e secondary treatment plant and discharge to adjacent

stream





4.4.2/22 Bundled Small Sewerage Schemes



There are 14 locations which have been allocated residential zoned lands in the

Waterford County Development Plan for which there are no public wastewater

services in place or the services are limited to small public septic tanks serving small

council housing estates. A summary of the existing populations and the available zoned

lands is as follows:



Table 4.4.2/18 Bundled Small Sewerage Schemes

Area Name Existing Zoned Land Future

Population Available Population

Estimate (Acres) Estimate to 2034

Kilrossanty 24 15.04 100

Knockanore 18 38.19 210

Ballymacaw 72 19.00 168

Ballynameelagh 9 8.44 52

Ballysaggart 45 16.06 126

Butlerstown 18 59.75 319

Faha 9 6.05 40

Fenor 27 18.44 120

Fews 9 4.90 34

Fourmilewater 51 8.25 93

Kilbrien 15 7.64 54

Mellery 18 20.49 121

Modeligo 9 5.23 35

Newtown 12 8.24 54





It is proposed to progress procurement of package treatment plants for the above 14

settlement zones with future population ranging in size from 319 to 34 persons as a

bundle. Preliminary cost estimates for, site acquisition package treatment plants and

associated collection pipework is € 3.00M









63

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





5.0 REQUIREMENTS FOR INVESTMENT 2007 – 2014



Circular Letter L2/06 from the DoEHLG calls on Local Authorities to examine from

a strategic perspective the main requirements for water services investment over the

period 2007 – 2014.



Having regard to the objectives set out in the County and Local Area Development

Plans for Waterford, and in the light of continued growth in the housing and

commercial/industrial sectors, the main requirements in this area relate to the long-

term provision of adequate water and wastewater throughout the County. The existing

infrastructure deficit for both water and wastewater services is seen as a major

constraint on development. It is essential that the recommendations for

improvements to water supplies particularly in the west of the county proceed to

planning at an early stage. In addition, the provision of sewerage infrastructure and

treatment for the towns not addressed pre 2007 is essential if proposed development

areas are to be fully utilised.



The environmental and statutory justification of including schemes for the period 2007

to 2014 is undertaken in Appendix 1, using the same criteria detailed in the preceding

section of this report.



The full list of investment priority requirements covering 2007 to 2009 is shown in

Table A and longer term strategic investment 2010 to 2014 is shown on Table B

overleaf.









64

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________





6.0 PUBLIC CONSULTATION



This document is available for public consultation and comment for a one month

period. Following public consultation, all comments received will be considered and a

composite report will be prepared. This Assessment of Needs Report will be presented

to the Waterford County Council Transport and Infrastructure Strategic Policy

Committee (SPC) and the outcome from the SPC will be placed on the agenda of

Waterford County Council‟s monthly meeting and will then be forwarded to the

Department of Environment, Heritage and Local Government.



Formal comments and submissions should be addressed, before the closing date

advertised in the public notice, published in the local newspaper, to:



John O‟Flynn, Director of Services & County Engineer

Waterford County Council

Civic Offices

Dungarvan

Co. Waterford.



Water Services Investment Programme



The Department of the Environment, Heritage and Local Government is funding a

Water Services Investment Programme evaluated in the sum of €167,587,000 over the

period 2005 – 2007 in the Waterford County Council area. This programme is detailed

in Appendix 3. For the period 2007 – 2014 a number of additional investment

programmes are considered in this Assessment of Needs. These are set out in detail in

Table A & B below.



The following explanatory note highlights the various phases, which investment

schemes undergo from conception to completion.





Phasing of Schemes



Any Scheme going through a series of life cycle stages, between the concept stage and

the completion stage. The full list of life cycle stages applying to a generic project

consists of the following stages:-



 Concept

 Feasibility

 Outline Design

 Detailed Design

 Statutory and Legal

 Procurement

 Construction

 Completion/Facility/Management









65

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



The Department of the Environment, Heritage and Local Government has identified a

number of life cycle stage milestones at which Local Authorities must make formal

submissions to the Department and receive formal approvals. The generic stages at

which formal submissions and approvals are necessary are the:-



 Approval to enter planning phase

 Preliminary report stage (which establishes scheme feasibility)

 The preparation of contract documentation and detailed design

 The contract advertisement to procure construction services, where applicable.

 The approval to tenders, which allows construction to commence

 The final account stage.

 The operation phase.



For projects less than € 635,000 full management responsibility has been devolved to

the local authority on foot of Department Circular L1/06 and L7/06

which substantially revises the above approvals requirements and should offer a

reduction in the life cycle of some projects.



Many of the schemes under consideration are only at the concept/feasibility stage in

their individual life cycle. Accordingly, it should be noted that future cost estimates for

projects which may not reach construction phase until several years from now must be

viewed with some degree of caution, as the estimation of future scheme construction

costs can only be undertaken after detailed evaluation through the life cycle stages

listed above.









66

Waterford County Council Water Services Investment Programme Assessment of Needs 2007-2009

______________________________________________________________________________________



7.0 RECOMMENDATION OF ASSESSMENT OF NEEDS



The list of new schemes identified has been assessed in accordance with the

justification criteria, outlined in Appendix 1 under the Heading of High or Medium.

As a result, a single list has been identified and this is as set out in Table A overleaf.

Table B lists a number of schemes, which following an examination from a strategic

perspective, are included for longer-term water services investment. Table A also

includes indications, subject to the caveat in this report, on cost estimation. Many of

the schemes go through a generic life cycle, which can stretch to several years.

Accordingly, the entire list should be progressed with investment for studies, which are

generally low cost, being matched over the investment timeframe with construction

costs, which can be significant.



Note: Water conservation proposals, which have been approved under the National

Water Conservation Programme, 2003, in accordance with Department Circular

L9/03, and have, therefore, been excluded from the list of new schemes identified in

the Assessment of Needs and included in Table A, on the basis that they have been

separately funded under an additional programme.





It is recommended that following SPC approval and public consultation, an assessment of all comments

received will be made. The document will be revised as appropriate, placed on the agenda of Waterford

County Council’s monthly meeting and will then be forwarded to the Department of the Environment,

Heritage and Local Government.









67


Related docs
Other docs by HC111124191726
Work Zone Traffic Control
Views: 1  |  Downloads: 0
Ch. 10 � Word Identification
Views: 0  |  Downloads: 0
Implementing SB 1440 - SCIAC
Views: 0  |  Downloads: 0
logic & combinations
Views: 1  |  Downloads: 0
Chapter 32 �Reptiles and Birds�
Views: 7  |  Downloads: 0
Department of Recreation & Leisure Studies
Views: 1  |  Downloads: 0
University of California at Berkeley
Views: 0  |  Downloads: 0
HOOVER Happenings
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!