Embed
Email

leak_case_studies

Document Sample

Shared by: liwenting
Categories
Tags
Stats
views:
0
posted:
11/24/2011
language:
English
pages:
18
International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 1 of 18

INDUSTRIAL PROCESS PLANTS





CASE STUDIES



1 Study of leakage in heat exchanger at a refinery in Pakistan



PINSTECH Team conducted a Radiotracer Test at an oil refinery in Pakistan.

Radiotracer Br-82 in the form of Di- Bromo-Benzen with an activity of 130 mili Curie was used. A

brief feasibility of experimental set up was carried out and necessary arrangement was discussed

with plant engineers. Experimental set- up was completed and background radiation levels were

recorded before tracer injection. Special arrangements were made to inject radiotracer in the system.

Following monitoring stations were set up to monitor the passage of radiotracer in the heat

exchanger loop. The relative positions of various detectors are shown in figure-1.



Detector-1: At the Tube Inlet --- Just before the tube inlet pipe enters the exchanger

Detector-2: At the tube outlet --- Away from the Exchanger

Detector-3: At the Shell Inlet --- Away from the Exchanger

Detector-4: At the Shell Outlet --- Just after the shell outlet pipe goes away from the Exchanger

Detector-5: At first Platform (near Shell Top) --- against the Shell wall



All the rate meters and computer were time synchronized. Data recording was started at

14:23 hours. The detector-4 placed at Shell outlet to monitor leakage (if any) was connected to

computer for data acquisition. The data from other detectors was recorded manually. The data of

detector-4 was also recorded manually to avoid data loss in case of any problem with the computer.

Data of detector-4 was recorded every 5 seconds while for other detectors, data was recorded for

every 10 seconds.



Tracer Injection: Valves V-1 and V-3 of the Injection Port (see figure-1) were closed.

The Flange at the top of valve V-2 was removed and the valve V-2 was opened. The oil level in the

-1 -3

horizontal pipe between valve V and V was maintained such that 3/4 of pipe diameter was

filled with oil. Specially designed device to crush the silica glass ampoule was inserted vertically in

the pipe through valve V-2. Two glass ampoules containing Radiotracer Br-82 (in the form of Di-

Bromo-Benzen powder) were inserted in the crushing device. Ampoules were crushed and tracer

was mixed in oil in the pipe. The ampoule-crushing device was rinsed (inside the pipe) with

inactive oil before it was taken out and stored safely. The valve V-2 was closed and Valves V-3 and

V-1 were opened. The Radiotracer was injected into the system by starting the pump.

The injection was made at 14:32 hours in the Tube inlet pipe through Injection Port as

described above. The data was recorded from 14:23 to 16:00 hours i.e., for 1 hour & 37 minutes.

Data was analyzed and plotted as shown in figurer-2, 3, 4 & 5.

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 2 of 18

INDUSTRIAL PROCESS PLANTS









Detector−5









Detector- 2



OIL INPUT Detector- 3



TRACER INPUT

Detector- 4





V2

PUMP Detector-1



V1



Figure-1: Schematics of Experimental Set-up showing Tracer Injection

Port and position of various detectors.

________________________________________________________________________________



Discussion and Results



The data obtained from detector-1,2,4 & 5 is plotted in figure-2. As the Radiotracer did not

appear at detector-3, its data is not plotted. The data from detector-4 with 5-second time base is

plotted in figure-3. The data from detector-1 and detector-4 is plotted in figure-4. The zoom view of

figure-4 near the peak area is shown in figure-5. The timings of tracer-peak arrival and peak

duration are also given in figure-2 and figure-5.



The data from detector-1 (monitoring tracer injection in tube inlet) and detector-4

(monitoring leakage, if any, in shell outlet) is very important and is to be analyzed carefully. Tracer

r

injection was made away f om detector-1 at 14:32 hours. The tracer plume of injection reached

detector-1 at 14:33:50 hours and the tracer plume passed away from detector-1 at 14:34:50 within a

duration of 60 seconds. The maxima of injection peak was recorded at 14:34:00 hours (please see

peak-B, figure-4 & 5). A tracer peak was also recorded by detector-4 placed at shell outlet (leak

detector). The tracer peak arrived at detector-4 at 14:33:05 hours and passed away at 14:34:05 hours

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 3 of 18

INDUSTRIAL PROCESS PLANTS





within 60-second duration. The maxima of the peak was recorded at 14:33:15 hours (please see

peak-A, figure-4 & 5).

The detector-1 and detector-4 recorded the peak for the same duration i.e., for 60 seconds

and the peak maxima reached within 10 seconds of the arrival of tracer peaks on both detectors.

However, detector- 4 recorded the tracer peak 45 seconds earlier than detector-1. That means

detector-4 recorded tracer peak before the tracer entered the exchanger. This indicates that the peak

recorded by detector-4 at 14:33:05 hours is not related to any leakage in the exchanger but this peak

is due the fact that detector-4 has seen activity of injection plume while tracer passed through the

tube inlet pipe in the near vicinity (see figure-1). The detector-5 placed against the shell wall, at the

platform near the shell top (see figure-1) recorded tracer peak maxima at 14:37:10 hours while the

detector-2 placed against tube outlet (see figure-1) recorded the peak maxima at 15:08:10 hours.

The data acquisition was continued for 1 hour and 37 minutes after the tracer injection, but detector-

4 did not record any leakage. The absence of any tracer at detector-3 placed at shell inlet (see

figure-1) shows that tracer is diluted and adsorbed somewhere in series of reactors and did not

appear afterwards at the she ll inlet.



RESULT: The Tracer Test reveals that there is NO LEAKAGE in the

Exchanger.









Radiation Safety Aspects

All necessary radiation protection aspects were taken into account during all stages of the

experiment (radioisotope production, transportation, injection, etc.). Nobody except PINSTECH

personnel was allowed to stay within 10 meters diameter around the injection port during tracer

injection till the area was checked at the end of experiment. The injection port and the area around

were checked and no radiation contamination was found. However, there was still little activity

inside the pipe at the injection port and that too was safe at 1 meter distance. The process engineer

at site, his staff and Inspection Engineer were briefed about the necessary precautions in this regard.

It may be noted that continuous oil flow was taking place at the injection port leading to dilution of

activity besides radioactive decay process. All other points in the experimental loop were checked

and found safe. Next day, PINSTECH team checked injection port again and radiation level was

found within safe limits. No radioactivity was recorded by Detector-3 placed at the shell inlet. That

means that there is no question of any radioactivity in the refined product.

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 4 of 18

INDUSTRIAL PROCESS PLANTS









LeakTestin103-E-6(NRL)

14000

D-4(ShellOutlet)

Counts (per 5 second)









ActivityseenbyDetectorfrom

12000

Injection Plume from Tube Inlet pipe



10000 Sensitivity Test of Detector





8000



6000



4000



2000



0

14:24:00 Detectors - with 15:21:36 15:36:00 15:50:24 16:04:48

Response of 14:38:24 14:52:48 415:07:12 5 second counting ti

-2000

i e

Tm

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 5 of 18

INDUSTRIAL PROCESS PLANTS









LEAK TEST IN 103-E-6 (NRL)

600000

(Tube inlet)

(Shell outlet)

500000

Peak-B (Tube Inlet)

COUNTS (per 10 second)









( at 14:34:00 )



400000

Injection Time: 14:32



300000 PEAK POSITION TIMINGS

Detector at Peak Duration Peak max. at

Tube Inlet 14:33:50 to 14:34:50 14:34:00

200000 Shell Outlet 14:33:05 to 14:34:05 14:33:15

Peak-A (Shell Outlet)

( at 14:33:15 )

100000





0

14:24:00 14:38:24 14:52:48 15:07:12 15:21:36 15:36:00 15:50:24 16:04:48 16:19:12



TIME

Figure- 4: Response of Detector-1 & Detector- 4

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 6 of 18

INDUSTRIAL PROCESS PLANTS









LEAK TEST IN 103-E-6 (NRL)

30000

Peak-A (Shell Outlet) Peak-B (Tube Inlet)

( at 14:33:15 ) ( at 14:34:00 ) (Tube inlet)

(Shell outlet)

25000

COUNTS (per 10 second)









Injection Time: 14:32:00 Hours

20000





PEAK POSITION TIMINGS

15000

Detector at Peak Duration Peak max. at

Tube Inlet 14:33:50 to 14:34:50 14:34:00

Shell Outlet 14:33:05 to 14:34:05 14:33:15

10000







5000







0

14:24:00 14:31:12 14:38:24 14:45:36 14:52:48 15:00:00 15:07:12



TIME

Figure- 5: Response of Detector-1 & Detector- 4 ( Zoom view near peak area )

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 7 of 18

INDUSTRIAL PROCESS PLANTS









2 Inspection report on-stream radiotracer leak test of the Heat Exchanger tower of the

petrochemical Plant, Thailand



DESCRI The Heat Exchanger tower as a tube and shell heat exchanger is expected leaks from

PTI tube side into shell side as indicate by contaminants found from laboratory analysis.

To identify the problem, radiotracer technique has been applied by injection of

gamma emitting radioactive tracer into the tube side inlet and monitor gamma

radiation at the tube outlet and shell outlet to find the residence time of process

stream flow in the vessel and the leakage, if any.



OPERAT The equipment setting as showed in figure 1. Radiotracer Dibromobenzene-82 of

ION half- life 35 hours in liquid form is injected into the process line going to the vessel at

tube inlet. Collimated detectors installed as the following:



- Detector 1 about 5 meter down stream of the injection point

- Detector 2 at tube inlet

- Detector 3 at tube outlet

- Detector 4 at shell outlet (for leak detection)

The detectors are connected to data logging system at 0.05 seconds interval. Two

injections are performed with approximately 15 mCi Br-82 each at 15 bars into the

process stream of 8 bars. Transmitted gamma ray intensities at each position is

recorded and processed by Excel as gamma intensity VS time graph for

evaluation/interpretation. Detector 4 in located at the shell outlet and about 10 meters

away in the first and second injection respectively.

RESULT

Arrival times after injection (seconds)

S

First injection Second injection

Range Center Peak area Range Center

D1 7.4-35.4 8.8 D1 5.8-24 10

D2 13-34 21.6 23182 D2 13-34 23

D3 34-72 42 D3 31-63 42

D4 11-26 and 28-55 16.8 and 41 1735 D4 6.4-18 16

Ratio of sum peaks D4/D2 = 1735/23182 = 7.5 %

Comment:

- The first peak of D4 at the shell outlet is the interference from the nearby inlet

pipe as it arrives before the peak of D2 at tube inlet. The second peak is the leak.

The ratio of peak area D4/D2 is approximate leak e.g. 7.5%. The figure will be

less if the data is corrected with background subtraction. As detector 4 is situated

further away (10 meters from shell outlet) in injection 2, no leak peak is observed

because tracer is too diluted by the process stream.

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 8 of 18

INDUSTRIAL PROCESS PLANTS

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 9 of 18

INDUSTRIAL PROCESS PLANTS

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 10 of 18

INDUSTRIAL PROCESS PLANTS

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 11 of 18

INDUSTRIAL PROCESS PLANTS

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 12 of 18

INDUSTRIAL PROCESS PLANTS

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 13 of 18

INDUSTRIAL PROCESS PLANTS

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 14 of 18

INDUSTRIAL PROCESS PLANTS







3 Onstream Radiotracer technique leak test of the Hydrocraker unit combined feed

Exchager of The Petroleum Refinery, Thailand







PURPOSES The combined feed heat exchangers unit is operated at high temperature

(200-300°C) and at high pressure(100-200bar). It has been expected small

leakage of about 5% from reactor feed at shell side into reactor effluent at

tube side. The main purpose of this study is to identify/pin-point the

p r o b l e m .

DESCRIPTIO The on- stream radiotracer technique is based on injection of gamma

N emitting radioisotope into the process to observe the process

parameters/behavior. The technique is applicable for flow rate, RTD and

l e a k a g e .

OPERATION J a n u a r y 3 1 - F e b r u a r y 1 , 2 0 0 2

- Organic Bromine-82 radioactive tracer (half- life 35 hrs) is prepared by

neutron activation of inactive Di-bromobenzene power in the Nuclear

Research Reactor for 2-4 hours at neutron flux 1012 neutrons per square

c e n t i m e t e r p e r s e c o n d .

- After dissolution in gasoline the stock solution of 30 ml 120 mCi is

stored in a bottle inside the lead container for transportation at

maximum allowance dose rate of 200mR/Hr

- Injection unit comprises nitrogen/diesel oil chamber, tracer vessel and

line connector is installed at low pressure (3bar) P-9501A/B reactor

feed pump. Tracer solution each of 20 mCi Br-82 is injected into the

p r o c e s s l i n e a t 1 0 - 1 5 b a r .

- Collimated scintillation detectors installed at the following:-

Flow/Injection Test (to optimize the injection procedure)

D - 1 a t E- 9 5 0 1 A S h e l l s i d e r e a c t o r f e e d i n l e t

D - 2 a t E- 9 5 0 1 D S h e l l s i d e r e a c t o r f e e d i n l e t

D-3 reactor feed pipe at a few meters after P-9501A/B injection point.

D - 4 a t E- 9 5 0 3 A T u b e s i d e r e a c t o r f e e d i n l e t



Combined Leak Test (to identify which series leaks E-9501D-F or E-

9 5 0 1 A - C )

D- 1 at E- 9 5 0 1 A S h e l l s i d e r e a c t o r f e e d i n l e t .

D - 2 a t E- 9 5 0 1 D S h e l l s i d e r e a c t o r f e e d i n l e t .

D- 3 a t E- 9 5 0 1 A T u b e s i d e r e a c t o r e f f l u e n t o u t l e t .

D- 4 a t E- 9 5 0 3 D T u b e s i d e r e a c t o r e f f l u e n t o u t l e t .

- Gamma intensity is logged by PM4 program at 0.05-0.5 seconds

interval. Data is processed by Excels.

F e b r u a r y , 0 5 , 2 0 0 2

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 15 of 18

INDUSTRIAL PROCESS PLANTS





The combined leak test is repeated with 50 mCi Bromine- 82 tracer

i n j e c t i o n .



RESULTS/ I n j e c t i o n T e s t

COMMENTS - Graph 1 injection test at 15 bar represents detector responses at E -

9503A Tube side reactor feed inlet and at reactor feed pipe after P-

9501A/B injection point at 16 seconds and 79 seconds respectively.

Injection parameters could be optimized however, the gamma intensity

of 10 mCi Br-82 tracer solution at both positions found very low. No

responses at shell side reactor feed inlets of E-9501A and E-9501D at

100 meters from injection point as due to very high dilution effect

f r o m t h e p r o c e s s f l u i d f l o w s .

C o m b i n e d l e a k T e s t

- Graph 2 the combined leak test using 25 mCi Br-82 represents detector

responses at shell side reactor feed inlets of E-9501A and E -9501D

both at 126 seconds. The gamma intensity still found too low to allow

o b s e r v a t i o n o f l e a k a g e .

- Graph 3 the combined leak test using 55 mCi Br- 82 represents

detector responses at shell side reactor feed inlet of E -9501A and E-

9501D both at145 seconds with peak height of 700 counts. The

responses of the side reactor effluent out lets both at 190 seconds with

peak- height of 27 and 501 counts for A and D respectively. The

estimated leakage observed at 3% for A and D series respectively.

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 16 of 18

INDUSTRIAL PROCESS PLANTS

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 17 of 18

INDUSTRIAL PROCESS PLANTS

International Atomic Energy Agency

Rev. No. 0

PROCEDURE OF RADIOTRACER Date 5 December 2003

TECHNIQUES FOR LEAK TEST IN Page 18 of 18

INDUSTRIAL PROCESS PLANTS



Related docs
Other docs by liwenting
第04章 类的重用
Views: 89  |  Downloads: 0
摘要
Views: 81  |  Downloads: 0
摘要
Views: 85  |  Downloads: 0
摘要_2_
Views: 68  |  Downloads: 0
國泰醫院2012年紙本期刊到刊總表
Views: 134  |  Downloads: 0
”Lyme_disease”_-_the_European_history
Views: 66  |  Downloads: 0
تعریف و تاریخچهPRP
Views: 77  |  Downloads: 0
_C6C28D15-9903-407A-8FEE-77A0422212B0_
Views: 113  |  Downloads: 0
__________
Views: 96  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!