Local Transport Plan Programme

2008- 2009









Approved LTP

Priority Area Scheme Revised LTP value Comments

value



Darwen to Blackburn (A666) £130,500.00 £5,000.00 LTP allocation reduced pending Pennine Reach consultation

Bastwell AQMA - UTC traffic lights upgrade and lining -

Wilpshire to Blackburn (A666) £90,000.00 £94,000.00

resurfacing linked in 2009/10

Witton AQMA + corridor works (inbound bus lane) - linking with

Feniscowles to Blackburn (A674) £100,000.00 £238,000.00

safety and resurfacing scheme

Beehive roundabout reconfigured and guide roundabout partially

Corridors South East corridor (A6177) £120,000.00 £188,000.00

signalised

completion of Eanam/BCW bus lane and Intack AQMA. UTC

Hyndburn Corridor £150,000.00 £150,000.00

upgrade and bus stop modification

Whitebirk Gateway project retention £120,000.00 £220,000.00 ERDF Whitebirk Gateway scheme completion

Blackburn rail station platform 4 canopy £150,000.00 £0.00 contribution to Network Rail - deferred to 2009/10

Quality bus shelter allocation £30,000.00 £30,000.00 Borough Quality Bus standard shelters

UTC capital upgrades £40,000.00 £40,000.00 UTC strategy £32k and capital works £8k.





Freckleton street link road £75,000.00 £75,000.00 07/08 fees up to planning permission + preliminary works

Cycle parking £10,000.00 £5,000.00 location TBC - reduced to £5k.

Hubs Victoria Street £15,000.00 £15,000.00 Retention for ERDF scheme

Cycle routes £130,000.00 £130,000.00 Delivery of cycle strategy elements

Town Centre transport (Cardwell Place bus priority) £135,000.00 £95,000.00 Alma Street / BCW junction contribution







Preston Old Road, Blackburn (Witton Park) £26,000.00 £25,000.00 Central hatching, build outs, pedestrian refuge islands. (Linked to

Maintenance scheme)

Audley Range, Blackburn £25,000.00 £25,000.00 Improved pedestrian crossing facilities

Traffic calming measures in the form of a junction table and

St James Road/Oak Street, Blackburn £10,000.00 £10,000.00 improvement of the existing sight lines through the introduction of

waiting restrictions.

East Park Road, Blackburn £10,000.00 £10,000.00 Interactive Signs to influence traffic speed

Rivington Road, Belmont £18,000.00 £18,000.00 Improve the consipicuity of the various bends allong this route.



Yew Tree Drive, Blackburn. £15,000.00 £15,000.00 Two interactive signs with possible red road marking material.

Beardwood, Blackburn (The Pastures) £8,000.00 £8,000.00 Central hatching highlighted with red road marking material

Livesey Branch Road, Feniscowles, Blackburn £12,000.00 £12,000.00 Two interactive signs with possible red road marking material.

Extended traffic signal poles on main road approach. Anti skid

Neighbourhoods Yew Tree Drive/Lammack Road, Blackburn £12,000.00 £12,000.00 material (50m) - Part of scheme to be incorporated as a special

maintenance scheme.

A666 Bolton Road, Ewood Park £17,000.00 £17,000.00 Anti skid in advance of traffic lights and pelican crossing

Whalley Old Road, Blackburn £18,000.00 £18,000.00 Refuge island with central hatching

Central hatching between Fern Farm Entrance and traffic signals

A666 Bolton Road (2), Ewood Park £18,000.00 £18,000.00

with Kidder Street

New Bank Road, Blackburn £0.00 £3,000.00 2 additional road humps

Rural Allocation £0.00 £4,000.00 Interactive signs

A666, Bolton Road with Stones Bank Road £10,000.00 £9,000.00 Introduction of a right turning lane (Linked to Maintence Scheme)

Whole junction to be finished with anti skid material introduction of

Whalley New Road/Whalley Old Road, Blackburn £5,000.00 £4,000.00

new white lining and red road marking material

Bennington Street, Blackburn £3,000.00 £3,000.00 Two junction tables, 4 flat top road humps.

Improve road safety outside the Secondary School in the form of

North Road, Blackburn £3,000.00 £3,000.00

traffic calming measures.

Monitoring and evaluation of Traffic Accident Data £10,000.00 £6,000.00 Better information to inform future LTP schemes





Rail Cherry Tree rail station + Darwen CCTV public address £20,000.00 £20,000.00 Infrastructure + business case progression Darwen station

and Clitheroe - Manchester



Marketing and town centre signage £12,500.00 £12,500.00 Visitor Centre information + signage

Rights of way improvement plan £25,000.00 £25,000.00 RoWIP

LTP programme and project management £50,000.00 £50,000.00

Other

East lancs rapid transit £150,000.00 £160,500.00 contribution from LCC of £100k to Major scheme business case

LTP Monitoring £20,000.00 £20,000.00 Traffic counter equipment plus cordon surveys

Smarter choices initiatives £40,000.00 £40,000.00 NoWCARD contribution plus smarter choices





Total Integrated Transport Element £1,833,000.00 £1,833,000.00

£1,833,000 confirmed settlement



Priority Area- Approved LTP

Scheme Revised LTP value Comments

Maintenance value



A666 Bolton Road between Hall Street and B&Q entrance £10,000.00 £10,000.00

Lengths of existing flagged footway only

Accident black spot. To include drainage improvements on Green

A666 Bolton Road junction Green Arms Road £85,000.00 £85,000.00 Arms Road at its junction with Bolton Road. Link with traffic safety

scheme

A674 Preston Old Road from Markham Road to St Link with traffic safety scheme. To include f/way between Cartmel

£125,000.00 £125,000.00

Principal Roads Francis Road Rd and Markham Rd.

A666 Whalley New Road from Cemetery Entrance to

£127,000.00 £127,000.00

Pearl Street and from No.574 to No.700 Linkage with culvert strengthening scheme

A6119 Whitebirk Drive from the Borough Boundary to To be resurfaced using the Repave insitu Surface Course

£114,000.00 £114,000.00

Philips Road westbound. Recycling process

Retention monies held on Contract 701 completed in the 07/08

Miscellaneous – release of retention 06/07 £7,000.00 £7,000.00

financial year.





C614 Broadhead Road from entrance to “Higher Giles” to Rural route serving the West Peninne Moors. To include drainage

£108,000.00 £108,000.00

the entrance to “Bank Bottom” improvement works. Links two previous schemes.

Buncer Lane, Blackburn – right hand side footway

£54,000.00 £54,000.00

between Preston Old Rd and Mavis Rd High usage footway serving Witton Park and Witton High School

£25,000.00 £25,000.00 Completion of scheme

B6233 Limbrick from Barbara Castle Way to Altom Street

Non Principal Roads

C616 Marsh House Lane, Darwen from Priory Drive to Follow on to 07/08 scheme and completes the resurfacing of

£65,000.00 £65,000.00

Sudell Road Marsh House

Mill Lane, Blackburm between Mincing Lane and Darwen

£16,000.00 £16,000.00

Street. Blackburn Town Centre Street in poor condition.

C617 Bog Height Road from Heys Lane to 200 metres

£100,000.00 £100,000.00

east of Meadow Head Lane To include drainage improvement works. Split into two phases





Philips Road Bridge £90,000.00 £90,000.00 Completion of scheme commenced in 2007-08 (3t carriageway 0t









Bridge and

Structures

Maintenance

Local Transport Plan Programme

2008- 2009









Completion of scheme commenced in 2007-08 (18t restriction,

£150,000.00 £150,000.00

Moorgate St Canal Bridge bridge in dilapidated condition))

Bridge widening (plus approx £82k from Section 106 agreements

£140,000.00 £140,000.00

Greenbank Terrace Bridge Improvements, Lower Darwen (match funding))

Argyle St Bridge (with Cavendish St Bridge) Carry out 2 adjacent strengthening schemes in one contract to

£200,000.00 £200,000.00

Strengthening, Darwen deliver best value

Boulevard strengthening phase 1 £49,000.00 £49,000.00 Blackburn Boulevard strengthening / bollards

Essential Bridge Maintenance £25,000.00 £25,000.00 Allowance for essential structural bridge repairs

Bridge and

Structures £50,000.00 £50,000.00

Retaining Wall Strengthening Allowance for essential retaining wall strengthening/reconstruction

Maintenance

Management of sub-standard bridges, bridge On going assessment programme & management of sub-

£30,000.00 £30,000.00

assessments & general strengthening standard bridges etc

Including Snape St, Goose House, Barton St and Clinton St

£16,000.00 £16,000.00

Network Rail Bridge Assessments/Feasibility bridges

Street lighting £70,000.00 £70,000.00 Replacement of concrete columns

£515k PRN funding allocated 2008-09 for completion of scheme

£645,000.00 £645,000.00

Whalley New Road East Culvert Phase 2 started in 2007-08

£115k PRN funding allocated 2008-09 (to carry out with East

£115,000.00 £115,000.00

Whalley New Road West Culvert Culvert work to deliver best value)



Total Maintenance Element £2,416,000.00 £2,416,000.00

£1,786,000 settlement letter

Total LTP Allocation £4,249,000.00 £4,249,000.00


Related docs
Other docs by HC111124085258
nbs
Views: 4  |  Downloads: 0
Chlorine Dilution Tool
Views: 2  |  Downloads: 0
Model
Views: 3  |  Downloads: 0
Rick Wagoner
Views: 1  |  Downloads: 0
INTRODUCTION TO MARKETING
Views: 2  |  Downloads: 0
CURRICULUM VITAE
Views: 3  |  Downloads: 0
p032h
Views: 1  |  Downloads: 0
ICC Mar48 T3
Views: 8  |  Downloads: 0
Contents
Views: 2  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!