Embed
Email

CTA Main Street Viaduct Weekend Replacement_20060118

Document Sample

Shared by: liwenting
Categories
Tags
Stats
views:
0
posted:
11/23/2011
language:
English
pages:
2
CTA Main Street Viaduct Weekend Replacement



By James S. Szczupaj, SE, PE, Project Manager, Edwards and Kelcey



The Chicago Transit Authority (CTA) was confronted with a challenge for the



replacement of their viaduct over Main Street in Evanston, Illinois. The CTA needed to maintain



service during normal business hours for the thousands of customers on the Purple Line of its



mass transit rail system. To meet the challenge, the CTA employed rapid construction techniques



and permitted construction near their tracks during non-rush hour periods, including nights and



weekends, and during one very busy weekend shutdown in November 2005.



The Main Street Viaduct on this electrified third rail line carries two tracks, one each for



northbound and southbound traffic. The original 66 foot long viaduct consisted of four spans of



reinforced concrete deck slabs supported by three reinforced concrete piers and two unreinforced



concrete, gravity type abutments. Built nearly one hundred years ago in 1909 by the Chicago,



Milwaukee and St. Paul Railway, the viaduct had deteriorated significantly enough due the



effects of freeze thaw damage and needed complete replacement.



Because the limited time periods during which construction could take place and the



restricted use of typical planning and construction techniques for the bridge replacement, a



method was developed to construct a new, longer and wider, one hundred foot, two track, steel



through girder span adjacent to the existing bridge and roll it into place. The longer and wider



span allowed for the new substructure to be constructed behind the footings of existing



abutments. This enabled the installation of the four foot diameter drilled shaft piers on which the



abutments were founded to take place outside the clearance envelope of the transit cars during



non-rush periods in advance of the weekend shutdown. The steel superstructure was erected next



to the viaduct in approximately four weeks.



For a 54 hour window of time beginning in the evening of Friday, November 11, 2005, the



Chicago Transit Authority shut down service on its Purple Line to complete the replacement of



the viaduct. After service was halted and the tracks removed, the demolition of the existing

concrete viaduct began, and it was completely removed by early Saturday morning. Work



progressed continuously, and by Saturday night, the new 40 ton precast concrete abutment seats



were set onto the preconstructed drilled shafts. Early Sunday morning, remote-controlled, self-



propelled modular transporters lifted the new 210 ton span, rotated it more than 90 degrees to its



final alignment, and rolled it approximately 100 feet to its final position. Moving the bridge took



just 31 minutes, and the entire roll in, from the initial lift to final adjustments of the bearings, was



completed in four hours. The CTA tracks were reconstructed and service was restored to the



Purple Line in time for Monday morning’s rush hour period as planned.



The replacement of the Main St. Viaduct on the Purple Line was under contract with the Chicago



Transit Authority. Edwards and Kelcey was the Designer of Record for the project, and Kiewit



Western was the General Contractor.



Related docs
Other docs by liwenting
第04章 类的重用
Views: 89  |  Downloads: 0
摘要
Views: 81  |  Downloads: 0
摘要
Views: 85  |  Downloads: 0
摘要_2_
Views: 68  |  Downloads: 0
國泰醫院2012年紙本期刊到刊總表
Views: 134  |  Downloads: 0
”Lyme_disease”_-_the_European_history
Views: 66  |  Downloads: 0
تعریف و تاریخچهPRP
Views: 77  |  Downloads: 0
_C6C28D15-9903-407A-8FEE-77A0422212B0_
Views: 113  |  Downloads: 0
__________
Views: 96  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!