ABARE's list of major electricity generation projects
Note: Projects that are under construction or committed are shown in the blue shaded areas. Less advanced projects are
shown in the yellow shaded areas.
Electricity Generation - non-renewable
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Brown coal
Arckaringa Phase 1 Altona 200 km N of New project, na 560MW na 800 O
Energy/CNOOC Coober Pedy, SA feasibility study under
way
Arckaringa Phase 2 Altona 200 km N of Expansion, feasibility na 560MW na 800 O
Energy/CNOOC Coober Pedy, SA study under way
Dual Gas HRL Development Morwell, Latrobe New project, EIS 2013 600MW $750m 350 C
Demonstration Project Valley, Vic under way 35 O
FuturGas project Strike Oil Kingston, SA New project, 2016 40MW na
prefeasibility study
under way
For further information contact: Robert New (02 6272 2159)
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Black coal
Eraring Eraring Energy 40 km SW of Expansion, 2011 240MW $245m 350-450 C
Newcastle, NSW committed
Bluewaters stage 3 Griffin Energy 5 km NE of Expansion, EIS under 2013 208MW na
Collie, WA way
Bluewaters stage 4 Griffin Energy 5 km NE of Expansion, EIS under 2015 208MW na
Collie, WA way
Coolimba Aviva Corporation 20 km S of New project, EIS 2013 400MW $1b 600 C
Eneabba, WA completed 100 O
Galilee Power Project Waratah Coal 300 km W of New project, na 400MW $1.25b 1000 C
Rockhampton, prefeasibility study 60 O
Qld under way
Muja Power Station Verve Energy/ 200 km SE of Refurbishment, govt 2012 240MW $100m 200 C
refurbishment Inalco Energy Perth, WA approval received
Wandoan Power Xstrata/GE Surat Basin, Qld New project, 2015-16 400MW na
Project Energy/Stanwell prefeasibility study
Corporation under way
ZeroGen ZeroGen Pty Ltd to be determined, New project, 2015 400MW $3b
Qld prefeasibility study
completed
For further information contact: Robert New (02 6272 2159)
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Coal seam gas
Blackwater Power Bow Energy 15 km NE of New project, under 2011 30MW $35m 200 C
Project Blackwater, Qld construction 2 O
Braemar 3 ERM Power 40 km SW of Expansion, govt 2013 520MW na
Dalby, Qld approval received
Darling Downs Power Origin Energy 250 km W of Expansion, govt 2012 500 MW na
Station 2 Brisbane, Qld approval under way
Mungi Generation Molopo 150 km SW of New project, na 30MW (60MW na
project Rockhampton, feasibility study under ultimately)
Qld way
Narrabri 1 East Coast Power Narrabri, NSW New project, 2012 30MW $150m (incl.
planning approval stages 1 and 2)
under way
Narrabri 2 East Coast Power Narrabri, NSW New project, 2013 180MW $150m (inc 100 C
planning approval l.stages 1 and 12 O
under way 2)
Richmond Valley Power Metgasco East Casino, New project, govt na 30MW $40m 50 C
station and Casino Gas NSW approval received 10 O
project
Spring Gully stage 1 Origin Energy 80 km N of New project, govt na 500MW na 200 C
Roma, Qld approval under way 15 O
Spring Gully stage 2 Origin Energy 80 km N of Expansion, govt na 500MW na 200 C
Roma, Qld approval under way 15 O
Wilga Park B (stages 1 Eastern Star Gas Narrabri, NSW Expansion, planning na 30MW $42m 30 C
to 3) approval received 5 O
For further information contact: Farah Beaini (02 6272 2102)
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Gas
Channel Island Power Power and Water Channel Island, Expansion, under 2011 90MW $120m
Station Corporation NT construction
Kwinana Power Station Verve Energy Kwinana, WA Refurbishment, under late 2011 200MW $263m
rebuild construction
Mortlake Stage 1 Origin Energy 12 km W of New project, under 2011 550MW $710m 250 C
Mortlake, Vic construction 10 O
Owen Springs Power and Water Alice Springs, NT New project, under 2010 33MW $100m
Corporation construction
Bamarang stage 1 Delta Electricity 7 km SW of New project, govt na 250-300MW na 100 C
Nowra, NSW approval received 18 O
Bamarang stage 2 Delta Electricity 7 km SW of Expansion, govt na 100-150MW $130m 200-300 C
Nowra, NSW approval received 18 O
Centauri 1 Eneabba Gas 8 km E of New project, govt 2013 168MW na
Dongara, WA approval received
Dalton Power Station AGL 70 km W of New project, govt 2015-16 250-780MW $250-800m (up 250 C
Goulburn, NSW approval under way (1500MW ultimately) to $1.5b 6 O
ultimately)
Hanging Rock stage 1 Loran Energy 20 km SW of New project, govt na 300MW $360m 150 C
Products Moss Vale, NSW approval under way 15 O
Hanging Rock stage 2 Loran Energy 20 km SW of Expansion, govt na 300MW $240m 150 C
Products Moss Vale, NSW approval under way 15 O
Leafs Gully AGL 65 km SW of New project, govt 2011 360MW $200m 200 C
Sydney, NSW approval received 5 O
Marulan Gas Turbine EnergyAustralia 40 km NE of New project, govt na 350MW $280m 150 C
Facility Goulburn, NSW approval received 12 O
Marulan Gas Turbine Delta Electricity 40 km NE of New project, govt 2013-14 250-350MW $280m 150 C
Facility stage 1 Goulburn, NSW approval received 12 O
Marulan Gas Turbine Delta Electricity 40 km NE of Expansion, govt 2013-14 100-150MW $235m 200 C
Facility stage 2 Goulburn, NSW approval received 8 O
Mortlake stage 2 Origin Energy 12 km W of Expansion, EIS na 450MW na 20 O
Mortlake, Vic completed
Munmorah Delta Electricity Munmorah, NSW Expansion, govt 2013-14 100MW $795m 150 C
rehabilitation approval received
NQ Peaker AGL Townsville, Qld New project, 2011 360MW $252-324m
prefeasibility study
under way
Port Kembla Bluescope Steel Port Kembla, New project, EIS 2012 220MW $750m 300 C
Steelworks Co- NSW under way 30 O
generation plant
SEQ1 AGL Ipswich, Qld New project, 2011 360MW $252-324m
prefeasibility study
under way
SEQ2 AGL Kogan, Qld New project, 2012 1150MW $805-1035m
prefeasibility study
under way
Shaw River stage 1 Santos 30 km N of Port New project, EIS 2012 500MW $880m (incl. 600 C
Fairy, Vic completed 105 km 85 O
pipeline from
Pt Campbell)
Shaw River stages 2 & Santos 30 km N of Port Expansion, EIS under na 2x500MW na 30 O
3 Fairy, Vic way
Swanbank F CS Energy Ipswich, Qld Expansion, feasibility na 400MW na 400 C
study under way
Tallawara stage 2 TRUenergy 13 km S of Expansion, EIS under 2015 300-450MW $500m 200-400 C
Tallawarra Wollongong, way 3-20 O
NSW
Tarrone AGL 300 km SW of New project, govt 2012 840MW na
Melbourne, Vic approval under way
Torrens Island Power AGL Torrens Island, Expansion, EIS under na 700MW $800m
Station (TIPS) SA way
Valley Power Station Snowy Hydro Latrobe Valley, Expansion, govt na 50-100MW $80-100m 50 C
Augmentation project Vic approval received, on
hold
Weddell stage 3 Power and Water 40 km SE of Expansion, feasibility late 2011 40MW $50m
Corporation Darwin, NT study under way
Wellington ERM Power 4 km N of New project, govt 2012 640MW $900m 400 C
Wellington, NSW approval received 10 O
Yallourn Power Station TRUenergy Latrobe Valley, New project, govt 2015 1000MW
Vic approval under way
For further information contact: Farah Beaini (02 6272 2102)
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Oil
Buronga Peaking International 3 km NE of New project, govt na 150MW $110m 120 C
Power Plant Power Mildura, NSW approval received 4 O
For further information contact: Robert New (02 6272 2159)
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
To be determined
Bayswater B Macquarie Muswellbrook, New project, concept 2014-16 2000MW na
Generation NSW approved
Mt Piper expansion Delta Electricity 17 km NW of Expansion, govt 2015-16 2000MW $2.5-5.0b 950 C
Lithgow, NSW approval under way 50 O
For further information contact: Robert New (02 6272 2159)
Electricity Generation - renewable
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Wind
Collgar Wind Farm UBS IIT/REST 25 km SE of New project, under 2012 206MW $750m 150 C
Merredin, WA construction 25 O
Crookwell 2 Union Fenosa 14 km SE of New project, under 2012 92MW $238m 55 C
Wind Australia Crookwell, NSW construction 12 O
Gunning Acciona Energy 50 km W of New project, under 2011 47MW $147m 100 C
Goulburn, NSW construction 7 O
Hallett 4 (North Brown Energy 12 km SE of Expansion, under 2011 132MW $341m 120 C
Hill) Infrastructure Jamestown, SA construction 10 O
Investments
Hallett 5 (The Bluff) AGL 12 km SE of Expansion, under 2011 52MW $135-145m
Jamestown, SA construction
Macarthur Wind Farm AGL/ Meridian 230 km W of New project, under 2013 420MW $1b 400 C
Energy Melbourne, Vic construction 30 O
Oaklands Wind Farm AGL/ Windlab 5 km S of New project, under 2011 67MW $200m 200 C
Systems Glenthompson, construction
Vic
Woodlawn Wind Farm Infigen Energy 40 km S of New project, under 2011 48MW $102m 80 C
Goulburn, NSW construction 5 O
Allendale Acciona Energy 20 km S of Mt New project, govt na 70MW $210m 50 C
Gambier, SA approval under way 11 O
Ararat Wind Farm RES 7 km N of Ararat, New project, govt na 225MW $350m 40 C
Vic approval under way
Arriga Transfield Services 50 km SW of New project, na 130MW na
Cairns, Qld prefeasibility study
under way
Badgingarra Wind Griffin Energy/ 200 km N of New project, 2012 130MW na
Farm Stanwell Perth, WA feasibility study under
Corporation way
Bald Hills Wind Farm Mitsui 170 km SE of New project, govt 2012 104MW na
Melbourne, Vic approval received
Barn Hill AGL Barn Hill, SA New project, govt na 130MW $300m 50 C
approval received 6-10 O
Baynton Transfield Services 80 km N of New project, 2013-14 130MW na
Melbourne, Vic feasibility study under
way
Ben Lomond Wind AGL 62 km N of New project, govt na 150MW $300m 2 O
Farm Armidale, NSW approval under way
Ben More Transfield Services 150 km NW of New project, 2014 90MW na
Melbourne, Vic feasibility study under
way
Berrybank Wind Farm Union Fenosa 60 km E of New project, govt 2012 178-248MW $484m 240 C
Wind Australia Mortlake, Vic approval received 20 O
Boco Rock Wind Farm Wind Prospect 10 km SW of New project, govt 2013 270MW $750m 100 C
Nimmitabel, NSW approval received 15 O
Bodangora Infigen Energy 25 km SE of New project, na 45MW na
Dubbo, NSW feasibility study under
way
Carmody's Hill Wind Pacific Hydro 18 km N of Mt New project, govt na 140MW $350m
Farm Misery, SA approval under way
Carols Ridge Wind Epuron Yass region, New project, na 75MW $100m
Farm NSW feasibility study under
way
Cattle Hill Wind Farm NP Power 5 km E of Lake New project, EIS 2011 150-210MW na
Echo, Tas under way
Cherry Tree Infigen Energy 10 km N of New project, na 35MW na
Shepparton, Vic planning approval
under way
Collector Transfield Services 50 km NE of New project, 2013 150MW na
Canberra, NSW feasibility study under
way
Conroy's Gap Wind Origin Energy 17 km W of Yass, New project, govt na 30MW na 50 C
Farm NSW approval received 5 O
Cooper's Gap Wind AGL/ Windlab 65 km S of Dalby, New project, govt 2011 300MW $1.2b 200 C
Farm Systems Qld approval under way 10-15 O
Crookwell 3 Union Fenosa 15 km SE of New project, EIS 2012 54-102MW $90-120m 40 C
Wind Australia Crookwell, NSW under way 6 O
Crowlands Wind Farm Pacific Hydro 30 km NE of New project, govt na 172MW $360m 100-160 C
Ararat, Vic approval received 18 O
Crows Nest Wind Farm AGL 43 km N of New project, govt na 150MW $405-435m
Toowoomba, Qld approval received
Darlington Wind Farm Union Fenosa 5 km E of New project, 2013 250-320MW $720m
Wind Australia Mortlake, Vic feasibility study under
way
Drysdale Wind Farm Wind Farm 3 km N of New project, govt 2011 26MW $60-100m 100 C
Developments Purnim, Vic approval received
Flyers Creek Wind Infigen Energy 20 km S of New project, na 120MW $160-200m 50 C
Farm Orange, NSW planning approval 3 O
under way
Glen Innes Wind Farm Infigen Energy Waterloo Range, New project, govt na 54MW $150m 40 C
NSW approval received 4 O
Gullen Range Wind Epuron 25 km NW of New project, govt na 248MW $250m
Farm Goulburn, NSW approval received
Hallett 3 (Mt Bryan) AGL Hallett, SA Expansion, feasibility 2011 80MW $216-232m
study under way
Hawkesdale Wind Union Fenosa 35 km N of Point New project, govt 2012 62MW $150m 26 C
Farm Wind Australia Fairy, Vic approval received 8 O
High Road Transfield Services 70 km SW of New project, 2012 50MW na
Cairns, Qld feasibility study under
way
Keyneton Pacific Hydro 10 km SE of New project, na 120MW na
Angaston, SA prefeasibility study
under way
Kongorong Transfield Services 30 km SW of Mt New project, na 120MW na
Gambier, SA prefeasibility study
under way
Kulpara Transfield Services 100 km NW of New project, na 80MW na
Adelaide, SA prefeasibility study
under way
Kyoto Energy Park Pamada 10 km W of New project, govt na 113MW $190m 183 C
Scone, NSW approval received 12 O
Lal Lal Wind Farm West Wind Energy 25 km SE of New project, govt 2012 150MW $350m 50 C
Ballarat, Vic approval received 12-15 O
Lexton Wind Farm Origin Energy 44 km NW of New project, govt 2011 38MW $110m
Ballarat, Vic approval received
Lincoln Gap Wind NP Power/ Infigen near Port New project, govt 2011 177MW $275m
Farm Energy Augusta, SA approval under way
Milyeannup Wind Verve Energy 20 km E of New project, govt 2011 55MW $160m
Farm Augusta, WA approval under way
Moorabool Wind West Wind Energy 25 km SE of New project, govt 2014 220-360MW $600m 100 C
Project Ballarat, Vic approval under way 30 O
Mortlake Wind Farm Acciona Energy 5 km S of New project, govt na 144MW $432m 100 C
Mortlake, Vic approval under way 21 O
Morton's Lane NewEn Australia 100 km N of New project, govt na 30MW $60m
Warrnambool, approval received
Vic
Mount Gellibrand Acciona Energy 15 km NE of New project, govt na 232MW $696m
Wind Farm Colac, Vic approval received, on
hold
Mount Hill Transfield Services 80 km NE of Port New project, na 80MW na
Lincoln, SA prefeasibility study
under way
Mount Mercer Wind Meridian Energy 30 km S of New project, govt 2011 131MW $320-360m 120-200 C
Farm Ballarat, Vic approval under way 10-12 O
Mumbida Verve Energy 40 km S of New project, 2012 90MW $250m
Geraldton, WA feasibility study under
way
Musselroe Roaring 40s Cape Portland, New project, govt 2012 168MW $386m 50-100 C
Tas approval received
Myponga TrustPower 50 km S of New project, govt na 40MW na 30 C
Adelaide, SA approval received 12 O
Naroghid Wind Farm Wind Farm 10 km N of New project, govt 2011 42MW $60-100m 100 C
Developments Cobden, Vic approval received
Nilgen Wind Farm Pacific Hydro 9 km E of New project, govt na 132.5MW $280m 400 C
Lancelin, SA approval under way 15 O
Orford Future Energy 28 km NW of New project, na 100MW na
Port Fairy, Vic feasibility study under
way
Paling Yards Union Fenosa 84 km N of New project, 2013 100-180MW $312m 55 C
Wind Australia Goulburn, NSW feasibility study under 8-10 O
way
Portland stage 4 Pacific Hydro Cape Nelson New project, govt na 54MW na
North and Cape approval under way
Sir William Grant,
Vic
Robertstown Wind Roaring 40s 123 km N of New project, 2014 75MW $173m
Farm Adelaide, SA planning approval
under way
Ryan Corner Wind Union Fenosa 10 km NW of New project, govt 2012 136MW $327m 60 C
Farm Wind Australia Port Fairy, Vic approval received 15 O
Sapphire Wind Farm Wind Prospect Inverrel, NSW New project, govt 2013 356-485MW $925-1250m 100 C
approval under way 8 O
Sidonia Hills Wind Roaring 40s 10 km NE of New project, 2014 80MW $184m
Farm Kyneton, Vic planning approval
under way
Silverton Wind Farm Silverton Wind 25 km NW of New project, govt na 1000MW $2.2b 700 C
Farm Broken Hill, approval received 120 O
Developments NSW
Snowtown stage 2 TrustPower 5 km W of Expansion, govt 2011 212MW na
Snowtown, SA approval received
Stockyard Hill Wind Origin Energy 35 km W of New project, na 484MW $1.4b
Farm Ballarat, Vic planning approval
under way
Stony Gap Wind Farm Roaring 40s 120 km N or New project, 2013 123MW $283m
Adelaide, SA planning approval
under way
Taralga RES 3 km E of New project, govt 2012 110-165MW na
Taralga, NSW approval received
Tarrone Union Fenosa 25 km N of Port New project, 2013 30-40MW $90m 30 C
Wind Australia Fairy, Vic feasibility study under 5 O
way
The Sisters Wind Farm Wind Farm 12 km S of New project, 2013 24MW $63m 24 C
Developments Mortlake, Vic planning approval 2 O
under way
Tuki Wind Farm Origin Energy 37 km N of New project, na 38MW na
Ballarat, Vic prefeasibility study
under way
Tungketta Hill Wind Ausker Energies 25 km S of New project, govt na 55MW $110m 30-40 C
Farm (Elliston) Stage 1 Elliston, SA approval received 5-6 O
Tungketta Hill Wind Ausker Energies 25 km S of Expansion, govt na 100-120MW $200-240m 100 C
Farm (Elliston) Stage 2 Elliston, SA approval received 10-12 O
Tungketta Hill Wind Ausker Energies 25 km S of Expansion, govt na 145-185MW $290-370m 100 C
Farm (Elliston) Stage 3 Elliston, SA approval received 10-12 O
Vincent North Pacific Hydro Yorke Peninsula, New project, govt na 30MW $100m
SA approval under way
Walkaway 2 Infigen Energy 20 km SE of New project, na 94MW na
Geraldton, WA planning approval
received
Walkaway 3 Infigen Energy 20 km SE of New project, na 300MW na
Geraldton, WA planning approval
received
Waubra North Acciona Energy 45 km NW of New project, on hold na 75MW na
Ballarat, Vic
White Rock Wind Eureka Funds 100 km NE of New project, EIS 2015-16 440MW $1.2b
Farm Management Launceston, Tas under way
Woakwine Infigen Energy 10 km E of Robe, New project, na 450MW na
SA planning approval
under way
Woolsthorpe Wind Wind Farm 2 km W of New project, govt 2011 40MW $60-100m 100 C
Farm Developments Woolsthorpe, Vic approval received
Woorndoo (Salt Creek) NewEn Australia 100 km SW of New project, govt na 30MW $60m
Ballarat, Vic approval received
Worlds End AGL Burra, SA New project, na 180MW $486-522m
feasibility study under
way
Yaloak South Wind Pacific Hydro 35 km SE of New project, govt na na $100m 160 C
Farm Ballarat, Vic approval under way 4 O
Yaloak Wind Farm Pacific Hydro 35 km E of New project, na 30MW na
Ballarat, Vic planning approval
under way
Yass Valley Wind Farm Origin Energy 20 km W of Yass, New project, govt na 222-420MW $800m 100 C
NSW approval under way 10 O
For further information contact: Robert New (02 6272 2159)
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Hydro
Tumut 3 upgrade Snowy Hydro Talbingo, NSW Expansion, under 2011 50MW $28m
construction
Upper Tumut Snowy Hydro Cabramurra, Expansion, 2014 40MW $20m 35 C
expansion NSW committed
Burdekin Hydro Power Stanwell 100 km SW of New project, na 37MW na
Station Corporation Charters Towers, feasibility study under
Qld way
For further information contact: Robert New (02 6272 2159)
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Ocean
Banks Strait Tidal Tenax Energy Pty Banks Strait, TAS New project, govt 2015 302MW na 40 C
Energy Facility Ltd approval under way 10 O
Clarence Strait Tidal Tenax Energy Pty Clarence Strait, New project, govt 2013 450MW na 15 C
Energy Project Ltd NT approval under way 5 O
Derby Tidal Power Tidal Energy 14 km N of New project, govt na 40MW na
Project Australia Derby, WA approval under way
Port Phillip Heads Tenax Energy Pty Port Phillip New project, govt 2014 34MW na 25 C
Tidal Energy Project Ltd Heads, Vic approval under way 5 O
For further information contact: Robert New (02 6272 2159)
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Biomass
Bell Bay Power Plant Gunns 48 km N of New project, on hold na 180MW na
Launceston, Tas
North Qld Bio-Energy Nth. Qld. Bio- 4 km S of New project, govt 2013 80-85 MW $400m
Plant Energy Ingham, Qld approval under way
Corporation Ltd
For further information contact: Robert New (02 6272 2159)
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Solar
ACT Solar Power Plant ACT Government to be determined, New project, 2012 22MW $141m
ACT prefeasibility study
completed
Bungendore Infigen Suntech 10 km N of New project, govt na 30-50MW $150m 50 C
Photovoltaic Solar Australia Bundendore, approval under way 5 O
Farm NSW
Kogan Creek Solar CS Energy near Chinchilla, Expansion, feasibility 2012 44MW $98.8m 120 C
Boost Project Qld study under way
Mallee Solar Park TRUenergy near Mildura, Vic New project, 2015 180MW na 200 C
feasibility study under 20 O
way
Manildra Photovoltaic Infigen Suntech 5 km NW of New project, govt na 30-50MW $150m 50 C
Solar Farm Australia Manildra, NSW approval under way 5 O
Moree Photovoltaic Infigen Suntech 5 km SE of New project, govt na 30-100MW $180m 50 C
Solar Farm Australia Moree, NSW approval under way 5 O
Moree Solar Station BP Solar near Moree, NSW New project, govt na 150MW $600m 700 C
approval under way 15 O
Nyngan Photovoltaic Infigen Suntech 2 km S of New project, govt na 30-100MW $300m 50 C
Solar Farm Australia Nyngan, NSW approval under way 5 O
Whyalla Solar Oasis Wizard Power 2 km N of New project, 2012 80MW $355m 200 C
Whyalla, SA feasibility study under
way
For further information contact: Robert New (02 6272 2159)
Expected Capital Employmen
Project Company a Location Status b Startup New Capacity Expend. c td
Geothermal
Geelong Geothermal Greenearth Energy Geelong, Vic New project, 2015 140MW $104m (for
Power Project prefeasibility study 12MW
under way demonstration
stage)
Koroit Hot Rock 15 km NE of Port New project, 2013-14 50MW na
Fairy, Vic prefeasibility study
under way
Moomba stage 2 Geodynamics Moomba, SA Expansion, feasibility 2013 25MW na
study under way
Paralana Petratherm/Beach Moomba, SA New project, na 30MW $200m
Petroleum/TRU feasibility study under
energy way
For further information contact: Robert New (02 6272 2159)
a Principal operating companies. b Type of project and stage of development – categories of the former include: 'new project' and 'expansion'; categories of the latter
include: 'feasibility study under way', 'feasibility study completed', 'committed' and 'under construction'. c Total capital expenditure as reported by the company in
current dollars. Includes cost of development, plant and equipment. d Reported employment. Where possible, project employment has been shown at both the
construction phase (shown as 'C' against the employment numbers below) and in the operational phase (shown as 'O'). na Not available.