OFFICE OF THE CHIEF ENGINEER(NEZ) CPWD, SHILLONG - 03

(A) CPO WORKS COSTING RS. 10 LAKHS AND ABOVE (WORKS UNDER CONSTRUCTION)



NORTH EASTERN ZONE - P-11 to 14 Nov-07

Sl. Name of Work (i/c Sub-heads). Location State Client Zone A/A & E/S Tender A/A & E/S Date of Stipula-ted Head of Budget Expdr. Expdr. Upto date Upto Target Remarks / Self-explanatory note about the

No. amount details of date start (as date of Account Allotment upto last upto total date date of project as a whole as sanctioned

(In lakhs) Sub per Comple- (in lakhs) year (in reporting expdr. (in physi- physical

Heads agmt.) tion (As lakhs)=x month in lakhs) cal Pro- comple-

per agree- current =x+y gress tion

ment) year (in (%)

lakhs)=y



1 2 3 4 5 6 7 7a 8 9 10 11 12 13 14 15 16 17 18

1 C/o SMB, Cook house, Dining Hall, Diphu Assam AR NEZ 317.00 12-Feb-02 1-Feb-03 21-Sep-04 4055- 75.00 123.05 0.00 123.05 100% 31-Aug-07 Completed. Handing over notes being sent

Recreation Centre & JCOs RB(P)

accommodation at ARTC & S at Diphu.

(a) SMB, Cook House & Dining Hall).

(b) Recreation Centre & JCO's Diphu Assam AR NEZ 317.00 12-Feb-02 1-May-03 18-Aug-04 100% 31-Aug-07 Completed. Handing over notes being sent

accomodation

Electrical work Diphu Assam AR NEZ 317.00 12-Feb-02 326.54 0.00 326.54 95% 30-Dec-07 Elect. service connection work in progress in

SMB, JCO, Cook House. Wiring completed,

fittings to be installed.

2 C/o single living acomm for 16 NCO & Kohima Nagaland AR NEZ 240.00 12-Feb-02 1-Jun-03 21-Jun-04 4055 150.00 82.81 36.65 119.46 40% 31-Mar-08 Work rescinded. Tenders for balance work in

160 ORs of 29th AR, Kohima, RB(P) progress.Site for 4th barrack not yet cleared by

Nagaland. AR. Roof can not be cast near MT garrage

due to HT line crossing above the building. AR

requested to take necessary action in both

cases.

Electrical work Kohima Nagaland AR NEZ 240.00 12-Feb-02 2.02 0.00 2.02 20% 31-Dec-07 Conduit laid where site is available

3 C/o 24 / T-II & 8 / T-III qtrs for 16 NCO & Kohima Nagaland AR NEZ 230.00 12-Feb-02 Work nearing completion.

60 ORs of 29th AR at Kohima,

Nagaland.

(a) C/o 8 Nos. T-III qtrs. Kohima Nagaland AR NEZ 230.00 12-Feb-02 1-Aug-02 21-Jun-03 48.20 0.00 48.20 100% 26-Oct-06 Work completed.

Electrical work Kohima Nagaland AR NEZ 230.00 12-Feb-02 95% 30-Dec-07 Finishing work in progress

(b) C/o 24 Nos. T-II qtrs Kohima Nagaland AR NEZ 230.00 12-Feb-02 1-Jun-03 19-Sep-04 125.41 0.03 125.44 97% 31-Jan-08 Work in progress.

Electrical work Kohima Nagaland AR NEZ 230.00 12-Feb-02 80% 31-Dec-07 In progress with bldg. work

(c) Development works Kohima Nagaland AR NEZ 230.00 12-Feb-02 19.94 0.00 19.94 100% 26-Apr-06 Work completed.

Electrical work Kohima Nagaland AR NEZ 230.00 12-Feb-02 7.53 0.00 7.53 90% 30-Dec-07 Finishing work in progress

4 C/o Single Men Barrack for 12 NCOs & Ghaspani Nagaland AR NEZ 434.00 26-Nov-02

120 ORs, quarters and 8 single JCOs &

4 single Officers for 27 AR at Ghaspani,

Nagaland

(i) 12 Nos. T-II Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 1-Nov-03 31-Nov-04 46.02 1.81 47.83 100% 30-Oct-07 Work completed. Final bill pending.

Electrical work Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 0.26 0.00 0.26 70% 31-Dec-07 Dropping of Conduit in progress

(ii) 8 Nos. T-III Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 1-Apr-03 21-Feb-04 22.19 6.37 28.56 82% 28-Feb-08 Original work rescinded & balance work in

progress. Show cause Notice issued due to

slow progress.

Electrical work Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 0.60 0.00 0.60 40% 28-Feb-08 Conduit dropping completed in 4 nos. Balance

is in progress.

(iii) 2 Nos. T-IV Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 1-Apr-03 31-Oct-03 23.74 0.03 23.77 100% 26-Oct-06 Work completed.

Electrical work Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 4.62 0.00 4.62 100% 27-Jun-07 Work completed.

(iv) 1 No. T-V Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 1-May-04 21-Feb-05 10.42 6.20 16.62 50% 28-Feb-08 Original work rescinded & balance work in

progress.

Electrical work Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 31-Dec-07 Conduit in progress

(v) 8 Single JCOs & 4 SOs accomm. Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 1-Nov-03 31-Nov-04 63.21 12.44 75.65 100% 27-Jun-07 Work completed.

Electrical work Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 100% 30-Nov-07 Wiring is in progress

(vi) SM Barrack. Ghaspani Nagaland AR NEZ 434.00 26-Nov-02 1-Mar-04 31-May-05 121.36 0.00 121.36 100% 26-Jul-06 Work completed & handed over.

Electrical work Ghaspani Nagaland AR NEZ 434.00 21.66 0.00 21.66 100% 7-Jun-07 Completed

(vii) Development works. Ghaspani Nagaland AR NEZ 434.00 1-Nov-02 Nov.03 31-Nov-04 22.67 5.30 27.97 90% 28-Feb-08 Work being carried out as per reqnt. of site.









(A) CPOPage1

Sl. Name of Work (i/c Sub-heads). Location State Client Zone A/A & E/S Tender A/A & E/S Date of Stipula-ted Head of Budget Expdr. Expdr. Upto date Upto Target Remarks / Self-explanatory note about the

No. amount details of date start (as date of Account Allotment upto last upto total date date of project as a whole as sanctioned

(In lakhs) Sub per Comple- (in lakhs) year (in reporting expdr. (in physi- physical

Heads agmt.) tion (As lakhs)=x month in lakhs) cal Pro- comple-

per agree- current =x+y gress tion

ment) year (in (%)

lakhs)=y



1 2 3 4 5 6 7 7a 8 9 10 11 12 13 14 15 16 17 18

5 Single men barrack with toilet for 8 NCOs Mantripukhri Manipur AR NEZ 188.00 12-Feb-02 RB(NP) 10.00 1-T/V completed. Work stopped for 6 months

& 80 ORS, 4 single JCOs accommn., 4 due to poor law & order. Work cancelled as

SOs accommn. & 1 T-V qtr. for AR at informed by AR on 01.09.2006 during meeting

Mantripukhri with CE(NEZ)

(a) C/o S.M. barrack (D/S) with toilets. Mantripukhri Manipur AR NEZ 188.00 10-Feb-02 1-Oct-02 31-Dec-03 61.48 10.92 72.40 75% 31-Dec-07 Work in progress.

(b) C/o 4 Single JCO's accommodation & Mantripukhri Manipur AR NEZ 188.00 10-Feb-02 1-Nov-02 30-Nov-03 27.51 0.23 27.74 58% 31-Mar-08 Work in progress.

4 SOs accommodation.



(c) Electrical work Mantripukhri Manipur AR NEZ 188.00 10-Feb-02 6.24 1.29 7.53 70% 31-Dec-07 Conduit laid as per availability of workfront

6 C/o 2 nos. 120 MB for 88 Bn, BSF Alamganj-I Assam BSF NEZ 423.66 16-Nov-05 1-Dec-06 30-Jun-08 28.30 96.85 125.15 37% 30-Jun-08 FFL slab cast in both barracks. BW in GF

Panbari, Alamganj-I. complete . Roof slab cast in one block.

Electrical work Alamganj-I Assam BSF NEZ 423.66 0.58 0.58 2% 30-Jun-08 Conduiting in progress, tenders for balance

work under scrutiny in circle office.

7 C/o 143 /T-II, 35 /T-III & 1 /T-V Qtrs. for Alamganj-I Assam BSF NEZ 1280.22 25-Nov-05

88 Bn, BSF Panbari, Alamganj-I.

(a) 143 T-II Alamganj-I Assam BSF NEZ 1280.22 6-Dec-06 31-Dec-08 32.38 64.53 96.91 21% 30-Sep-09 8 blocks 1st floor slab cast. 7 blocks

completed upto lintel level. Brick work in GF

completed in 4 blocks.

Electrical work Alamganj-I Assam BSF NEZ 1280.22 0% 31-Dec-08 Call of tender In process

(b) 35 T-III & 1 T-V. Alamganj-I Assam BSF NEZ 1280.22 ######## 16-Jul-08 0.40 1.81 2.21 2% 16-Jul-08 Completed upto lintel level in 2 blocks.

Foundation excavation completed in 2 blocks.



Electrical work Alamganj-I Assam BSF NEZ 1280.22 0% 30-Jul-08 TS for balance work excluding provision kept in

tender by civil wing is done, tenders to be

invited. Conduit laying shall be started soon as

per availabilty of work front

(c) 2 lakhs ltres capacity UG sump & Alamganj-I Assam BSF NEZ 1280.22 100% 30-Sep-07 Work completed. Handing over notes being

pump house. sent.

Electrical work Alamganj-I Assam BSF NEZ 1280.22 DE under preparation

8 C/o Various Non-Resdl. bldgs. for 88 Bn. Alamganj-I Assam BSF NEZ 181.10 6-Jan-06 0.30 0.46 0.76 Work to start at ground.

BSF, Panbari, Alamganj I.

(a) SOs Mess with 4 suites and cook Alamganj-I Assam BSF NEZ 181.10 7-May-07 30-Nov-07 Tender accepted. Site handed over and lay out

house given.

Electrical work Alamganj-I Assam BSF NEZ 181.10 0.00 DE under preparation

(b) 6 nos. Trades Men Shop, shopping Alamganj-I Assam BSF NEZ 181.10 9.13 9.13 15% 31-Mar-08 RCC & brick work completed.

Centre, Bank and Post Office.

Electrical work Alamganj-I Assam BSF NEZ 181.10 0.00 DE under preparation

9 C/o Admn. Block, 10 bedded hospital, 4 Alamganj-II Assam BSF NEZ 220.84 21-Jun-02 217.82 0.54 218.36 Admn. Block and Gos' mess handed over.

suites for SOs mess, 7 suites for GOs

mess for BSF at Alamganj-II

(i) Admn. block(S/S) Alamganj-II Assam BSF NEZ 220.84 15-Feb-04 31-Jan-05 93.93 0.00 93.93 100% Work completed and handed over.

(ii) GO's Mess 7 suites (S/S) Alamganj-II Assam BSF NEZ 220.84 65.53 0.00 65.53 100% 30-Sep-06 Work completed and handed over.

(iii) 10 bedded hospital & SO's Mess with Alamganj-II Assam BSF NEZ 220.84 1-Apr-03 30-May-04 65% 15-Sep-08 Tenders under scrutiny. Notice under Clause -

4 suites (S/S) 3 issued to the lowest tenderer in other works,

which are being watched. If other works are

rescinded, this tender will also be cancelled

and the agency will be debarred. Formal case

will be sent for cancellation of registration of

the agency.

Electrical work Alamganj-II Assam BSF NEZ 220.84 10% 30-Sep-08 Conduit laid in slab, progressing as per

availability of work front









(A) CPOPage2

Sl. Name of Work (i/c Sub-heads). Location State Client Zone A/A & E/S Tender A/A & E/S Date of Stipula-ted Head of Budget Expdr. Expdr. Upto date Upto Target Remarks / Self-explanatory note about the

No. amount details of date start (as date of Account Allotment upto last upto total date date of project as a whole as sanctioned

(In lakhs) Sub per Comple- (in lakhs) year (in reporting expdr. (in physi- physical

Heads agmt.) tion (As lakhs)=x month in lakhs) cal Pro- comple-

per agree- current =x+y gress tion

ment) year (in (%)

lakhs)=y



1 2 3 4 5 6 7 7a 8 9 10 11 12 13 14 15 16 17 18

10 C/o 2 nos. 120 MB for 68 Bn, BSF Alamganj-II Assam BSF NEZ 423.66 7-Oct-05 31.33 142.92 174.25 50% 30-Jun-08 RCC work completed. Brick work 50%

Panbari, Alamganj-II. completed. Steel windows 50% fixed.

Plastering 10% done.

Electrical work Alamganj-II Assam BSF NEZ 423.66 Conduiting in progress, tenders for balance

work under scrutiny in circle office.

11 C/o 48 /T-II (F/S), 6 /T-III (D/S), 2 /T-IV Alamganj-II Assam BSF NEZ 481.50 6-Feb-06 14.66 30-Jun-08

(S/S) Qtrs. at 68 Bn HQ, Alamganj II.

(a) 48 T-II Alamganj-II Assam BSF NEZ 481.50 6-Dec-06 31-Mar-08 9.34 21.33 30.67 25% 30-Dec-08 3rd floor slab cast in 3 blocks. Grade beam

cast in 3 blocks.

Electrical work Alamganj-II Assam BSF NEZ 481.50 0% 30-Jun-08 Call of tenders is in process

(b) 6 T-III & 2 T-IV. Alamganj-II Assam BSF NEZ 481.50 Foundation excavation in progress.

Electrical work Alamganj-II Assam BSF NEZ 481.50 28.89 0.00 0.00 0.00 0% 30-Jun-08 Call of tenders is in process

(c) 1.5 lakh ltrs.capacity UG sump & Alamganj-II Assam BSF NEZ 481.50 25% 31-Mar-08 Bottom slab cast. Side wall half height

pump house no.2 near barrack. completed.

12 C/o 44-T/II Qtrs.,for BN. HQ, BSF at Tura-I Meghalaya BSF NEZ 263.77 18-Jun-03 1-Jul-04 30-Nov-05 4055 322.47 0.00 322.47 100% 31-Jul-07 Board of officers of BSF inspected. They gave

Tura-I. some suggestions which are being

implemented.

Electrical work Tura-I Meghalaya BSF NEZ 263.77 30-Oct-07 Wiring completed. Fittings to be erected at the

time of handing over

13 C/o Generator Room & P/F of 125 KVA Dobasipara, Meghalaya BSF NEZ 16.02 1-Feb-05 Handed over

DG Set at Bn. HQ 161 Bn. BSF Tura-I

Dobasipara.

Electrical work Dobasipara, Meghalaya BSF NEZ 16.02 30-Dec-07 Work is in final stage. Testing to be done.

Tura-I

14 C/o 120 MB with Cook House & dining Tura-II Meghalaya BSF NEZ 214.61 12-Aug-05 1-Sep-06 31-Jan-08 40.20 0.00 40.20 17% 30-Sep-08 Major development was involved. The building

hall for Jawans at 182 Bn, BSF at Tura II is in different terraces. Foundation and grade

(Praharinagar). beam completed.

Electrical work Tura-II Meghalaya BSF NEZ 214.61 1% 30-Sep-08 Conduiting in progress with civil work.

15 C/o 120 MB with Cook House & dining Tura-III Meghalaya BSF NEZ 231.38 13-Oct-05 16-Sep-06 15-Jan-08 21.35 21.35 2% 15-Dec-08 Foundation footings cast.

hall for Jawans at 56 Bn, BSF at

Dhanakgiri, Tura III.

Electrical work Tura-III Meghalaya BSF NEZ 231.38 0.00 0.00 0.00 0% 15-Dec-08 Call of tenders is in process

16 C/o Resdl. Qtrs. for BSF (SH: 24/T-I, 8/T- Tura-III Meghalaya BSF NEZ 270.72 1-May-00 4055 131.83 15-Dec-08

II, 8/T-III, 4/T-IV, 1/T-V) at Dhanakgiri

Tura III.

(a) T-I 24 Nos. & T-II 8 Nos.(Balance Tura-III Meghalaya BSF NEZ 270.72 1-Jul-02 15-Feb-04 23.94 0.37 24.31 32% 15-Dec-08 Shuttering for GD floor slab for T-I Qtrs. in

Work) progress. Shuttering for 1st floor slab for T-II

qtrs in progress.

Electrical work Tura-III Meghalaya BSF NEZ 270.72 2% 30-Dec-08 Conduit laid in sites where available,

progressing with civil work, tenders for balance

work recalled.

(b) T-IV 4 & T-V 1 No. Tura-III Meghalaya BSF NEZ 270.72 1-Dec-01 15-Dec-02 46.32 0.00 46.32 100% 31-Jul-07 T-V handed over, Handing over notes of T-IV

under preparation. Board of officers deputed.



Electrical work Tura-III Meghalaya BSF NEZ 270.72 T-V handed over, work compl in Type-IV

except fixings to be installed at the time of

handing over.









(A) CPOPage3

Sl. Name of Work (i/c Sub-heads). Location State Client Zone A/A & E/S Tender A/A & E/S Date of Stipula-ted Head of Budget Expdr. Expdr. Upto date Upto Target Remarks / Self-explanatory note about the

No. amount details of date start (as date of Account Allotment upto last upto total date date of project as a whole as sanctioned

(In lakhs) Sub per Comple- (in lakhs) year (in reporting expdr. (in physi- physical

Heads agmt.) tion (As lakhs)=x month in lakhs) cal Pro- comple-

per agree- current =x+y gress tion

ment) year (in (%)

lakhs)=y



1 2 3 4 5 6 7 7a 8 9 10 11 12 13 14 15 16 17 18

17 C/o Admn. Block for Bn. HQ. BSF at Tura-III Meghalaya BSF NEZ 98.28 1-Aug-02 4-Jul-04 15-Jul-05 4055 54.51 13.06 61.20 100% 7-Sep-07 Work completed except final coat which will be

Dhanakgiri, Tura III. done after electrical work is over. Handing over

note under preparation

Electrical work Tura-III Meghalaya BSF NEZ 98.28 0.00 90% 30-Dec-07 Wiring completed, fittings to be erected at the

time of handing over, elect service connection

work to be started.

(i) C/o Approach road, breast/ Retaining Tura-III Meghalaya BSF NEZ 98.28 100% 30-Nov-07 Completed

Wall, culvert etc.

Electrical work Tura-III Meghalaya BSF NEZ 98.28 90% 30-Sep-08 Wiring completed, fittings to be erected at the

time of handing over, elect service connection

work to be started.

18 C/o 64/ T-II (D/S), 6 / T-III (D/S) 2/ T-IV Tura-III Meghalaya BSF NEZ 421.61 21-May-04 4055 252.78 46.03 298.81 75% 31-Mar-08 Trusses to erected in 13 blocks. Shuttering for

(S/S) qtrs. for BSF at Dhanakgiri, Tura- GD floor slab in progress. Brick work and

III plastering in progress.

Electrical work Tura-III Meghalaya BSF NEZ 421.61 5-Apr-05 20% 30-Mar-08 Conduiting in progress.

19 C/o 64-T/I Qtrs. & c/o Retaining wall and Shillong Meghalaya BSF NEZ 396.26 27-May-03 30-Jun-03 30-Sep-04 4055

making terrace for Bn HQ BSF at

Umpling, Shillong

(i) 64 Nos. T-I Shillong Meghalaya BSF NEZ 396.26 1-Nov-05 15-Mar-07 196.50 135.83 332.33 97% 30-Dec-07 Inspection of work at 75% stage done by BSF.

Work nearing completion.

Electrical work Shillong Meghalaya BSF NEZ 396.26 60% 30-Dec-07 Conduiting in progress

(ii) C/o Retaining Wall and making Shillong Meghalaya BSF NEZ 396.26 1-Feb-04 31-Jul-04 79.81 0.00 79.81 100% 31-Mar-07 Work completed.

terrace.

20 C/o 30 Nos. T-II for 137 Bn. HQ at Shillong Meghalaya BSF NEZ 234.70 25-Nov-03 1-Aug-04 31-Oct-05 4055 118.27 50.46 168.73 98% 30-Dec-07 Inspection of work at 75% stage done by BSF.

Mawpat, Meghalaya. (i) Civil work Work nearing completion.

(ii) Electrical work Shillong Meghalaya BSF NEZ 234.70 80% 30-Dec-07 Wiring completed, installation of fitting is

progress.

21 C/o 8/T-III Qtrs. with internal w/s and s/i Patgaon, Assam BSF NEZ 69.27 20-Jan-06 1-Jun-06 31-May-07 2.30 36.28 38.58 70% 31-Mar-08 Work in progress.

i/c development work for BSF, Patgoan, Guwahati

Guwahati.

Electrical work Patgaon, Assam BSF NEZ 69.27 6-Jan-06 10% 31-Mar-08 Conduiting is in progress with building work.

Guwahati

22 C/o Boundary Wall & Security Fencing Patgaon, Assam BSF NEZ 89.97 27-Jul-00 4055-

for BSF at Patgoan. Guwahati OB(NP)





(a) Original scope of work(Part-A) Patgaon, Assam BSF NEZ 89.97 9.03 0.00 9.03 100% Land was under dispute between BSF and

Guwahati state Govt.of Assam. And work was closed on

26-3-2004.

(b) Left out portion(Part-B) Patgaon, Assam BSF NEZ 89.97 16-Feb-07 31-Aug-07 60.00 43.21 61.80 105.01 100% Work completed.

Guwahati

23 C/o Admn. Block for BSF at Masimpur, Masimpur Assam BSF NEZ 220.48 15-Aug-05 ######## 25-May-07 4055 115.00 56.58 37.66 94.24

Silchar. (i) Admn. Block OB(NP)

60% 31-Dec-07 Structural work completed.

(ii) Bulk services Masimpur Assam BSF NEZ 220.48 1-Aug-05 Terrace cutting work completed, retaining wall

in progress.

(iii) Electrical work Masimpur Assam BSF NEZ 220.48 5.01 5.01 60% 31-Mar-08 Laying of conduit in progress

24 C/o Balance one no. suite with mess Masimpur Assam BSF NEZ 50.24 6-Jul-06 4055 0.11 4.00 4.11 22% 31-Dec-07 Foundation completed. Column F 2 level cast.

portion in existing Officers' mess of BSF OB(NP) RPE for Rs.64.80 lakhs sent to BSF on

Campus, Masimpur. 1.11.07. Sanction awaited.









(A) CPOPage4

Sl. Name of Work (i/c Sub-heads). Location State Client Zone A/A & E/S Tender A/A & E/S Date of Stipula-ted Head of Budget Expdr. Expdr. Upto date Upto Target Remarks / Self-explanatory note about the

No. amount details of date start (as date of Account Allotment upto last upto total date date of project as a whole as sanctioned

(In lakhs) Sub per Comple- (in lakhs) year (in reporting expdr. (in physi- physical

Heads agmt.) tion (As lakhs)=x month in lakhs) cal Pro- comple-

per agree- current =x+y gress tion

ment) year (in (%)

lakhs)=y



1 2 3 4 5 6 7 7a 8 9 10 11 12 13 14 15 16 17 18

26 C/o Remaining portion of boundary wall, Masimpur Assam BSF NEZ 107.00 1-Jan-07 1-Jan-07 12-Aug-07 4055 11.41 29.94 41.35 60% 31-Dec-07 Work in progress.

double decker sentry post and guard OB(NP)

room cum walking platform at BSF

Campus, Masimpur.

25 Augmentation of water supply scheme Dholchera Assam BSF NEZ 79.23 1-Dec-06 13-Dec-06 1-Jun-07 0.00 0.38 0.38 5% 31-Mar-08 Work started.

for BSF at Dholchera.

(a) Pumps. Dholchera Assam BSF NEZ 79.23 1-Dec-06 Tenders yet to be invited.

26 C/o 42 nos. resdl. accomm. for BSF at Lunglei Mizoram BSF NEZ 470.54 22-Jan-02 4055 35.00 284.76 12.51 297.27 Original sanction was for 20 T-I qtrs. Reqnt. of

Lunglei (Mizoram) T/I-4 Nos.T/II-32 RB(P) T- I & II was reviewed & awarded only after

Nos. T/III-4 Nos. & T-IV-2 Nos. Qrts. final decision of BSF. 4/T-III & 2/T-IV

completed & occupied since 7/04. 4/T-I

completed in Sep.06

(i) 16 nos.T-II (D/S)-(part-1) Lunglei Mizoram BSF NEZ 470.54 2-Jan-02 1-Aug-03 31-Oct-04 100% Work completed.

(ii) 16 nos.T-II (D/S)-(pt.2) Lunglei Mizoram BSF NEZ 470.54 2-Jan-02 20% 31-Mar-08 Work in progress. F-2 slab by 12/07.

(iii) Development works & Retaining wall Lunglei Mizoram BSF NEZ 470.54 2-Jan-02 1-Apr-03 31-Aug-03 100% Work completed.



(iv) Electrical work Lunglei Mizoram BSF NEZ 470.54 28.23 11.97 0.00 11.97 50% 31-Mar-08 Completed in part-1. Part-2 tender awarded,

conduiting in progress (10%)

27 C/o Internal roads, drains, retaining wall, Lunglei Mizoram BSF NEZ 141.74 16-Nov-05 4055 14.49 25.23 39.72

re-carpeting of existing room & pavement OB(NP)

in BSF campus at Lunglei.

(i) Internal roads & drains Lunglei Mizoram BSF NEZ 141.74 1-Mar-06 1-Dec-06 32% 1-May-08 Work in progress.

(ii) Retaining wall Lunglei Mizoram BSF NEZ 141.74 1-Mar-06 1-Dec-06 90% 1-Mar-08 Work in progress.

28 C/o 2 nos. 120 men barrack at 131 Bn Nalkata Tripura BSF NEZ 678.17 6-Apr-06 20-Nov-06 31-May-08 92.90 93.74 186.64 40% 31-May-08 F-2 level slab cast. Initial delay due to forest

HQ, Nalkata. clearance.

Electrical work Nalkata Tripura BSF NEZ 678.17 6-Apr-06 10% 30-May-08 Conduiting in progress

29 C/o 24 nos.suites with SO's mess at HQ Salbagan, Tripura BSF NEZ 226.76 6-Jan-06 1-Sep-06 27-Nov-07 60.61 57.77 118.38 75% 31-Dec-07 Structural work completed.

Tripura FTR, Salbagan. Agartala

Electrical work Salbagan, Tripura BSF NEZ 226.76 0.00 40% 31-Dec-07 conduiting is in progress

Agartala

30 C/o Boundary wall 3110 mtr. (appx) i/c Salbagan, Tripura BSF NEZ 231.50 3-Jul-07 27-Oct-07 28-Oct-08 28-Oct-08 Work awarded.

guard room, 10 sentry posts & 4 steel Agartala

gates at BSF Campus, Salbagan.

31 C/o Extension of lounge of Officers' Salbagan, Tripura BSF NEZ 89.85 29-May-07 9-Oct-07 10-Jun-08 10-Jun-08 Work awarded.

Institute at Ftr. BSF, Salbagan. Agartala

32 C/o Amenity/ Community Centre at Bn Salbagan, Tripura BSF NEZ 252.78 25-Jun-07 27-Oct-07 28-Oct-08 0.00 1.64 1.64 28-Oct-08 Work awarded.

HQ Tripura Ftr. BSF at Salbagan, Agartala

Tripura

33 C/o 2 nos. 120 men barrack at Teliamura Tripura BSF NEZ 562.28 13-Jan-05 19-Apr-06 31-Oct-07 76.87 168.14 245.01 79% 31-Dec-07 Finishing in progress.

Teliamura.

34 Electrical work I/c SITC of 250 KVA Teliamura Tripura BSF NEZ 562.28 0.00 80% 31-Dec-07 Laying of conduit in progress, Tender for SITC

substation of 250 KVA transformer is awarded.

35 C/o Road 501 mtr. from Gate no.1 to MT Teliamura Tripura BSF NEZ 39.37 6-Jul-06 12-Mar-07 23-Jul-07 0.00 3.79 3.79 15% 31-Dec-07 Work in progress.

Section at T/III & T/IV qtrs for BSF Bn.

HQ. at Teliamura.

36 C/o Balance B / wall with 18 sentry posts Teliamura Tripura BSF NEZ 189.69 20-Feb-07 17-Aug-07 16-Feb-08 17-Feb-08 Work awarded.

for BSF Campus, Teliamura.

37 C/o Boundary wall around BSF Campus, Teliamura Tripura BSF NEZ 190.56 Work awarded.

Teliamura.









(A) CPOPage5

Sl. Name of Work (i/c Sub-heads). Location State Client Zone A/A & E/S Tender A/A & E/S Date of Stipula-ted Head of Budget Expdr. Expdr. Upto date Upto Target Remarks / Self-explanatory note about the

No. amount details of date start (as date of Account Allotment upto last upto total date date of project as a whole as sanctioned

(In lakhs) Sub per Comple- (in lakhs) year (in reporting expdr. (in physi- physical

Heads agmt.) tion (As lakhs)=x month in lakhs) cal Pro- comple-

per agree- current =x+y gress tion

ment) year (in (%)

lakhs)=y



1 2 3 4 5 6 7 7a 8 9 10 11 12 13 14 15 16 17 18

38 C/o 2 nos 120 men Jawans living barrack Fatikchera Tripura BSF NEZ 526.36 6-Mar-06 15-Oct-06 15-Apr-08 143.87 58.96 202.83

with cook house cum dining hall & lav.

block at Fatikchera. (i) Building work.

82% 15-Apr-08 Work in progress.

(ii) Devnt. work i/c tube well Fatikchera Tripura BSF NEZ 526.36 6-Mar-06 ######## 22-Aug-07 Work awarded recently.

(iii) Electrical work Fatikchera Tripura BSF NEZ 526.36 6-Mar-06 40% 30-Apr-08 Conduiting is in progress, Sale of tenders for

SITC 250 KVA transformer is in process

39 C/o 159 /T-II(T/S), 34 /T-III(T/S), 1 /T- Fatikchera Tripura BSF NEZ 1552.41 6-Jul-06 10-Jan-00 Sanction split up into four packages due to

IV(S/S) & 1 /T-V(S/S) qrtrs. at 135 Bn, poor response in earlier two calls. RPE for Rs.

BSF, Fatikchera. 1909.81 lakhs sent to BSF vide letter dtd.

5.2.07. Sanction awaited.

(i) 54/T-II (Pt.I) Fatikchera Tripura BSF NEZ 1552.41 6-Jul-06 11-Mar-07 10-Mar-08 1.97 214.29 216.26 60% 10-Mar-08 85% slab cast. B/W alongwith fixing of door

frame and windows plastering are running.

(ii) 54/T-II(Pt.II) Fatikchera Tripura BSF NEZ 1552.41 6-Jul-06 11-Mar-07 10-Mar-08 0 61.85 61.85 60% 10-Mar-08 89% slab cast. B/W alongwith fixing of door

frame and windows plastering are running.

(iii) 51/T-II, 1 /T-IV & 1 /T-V Fatikchera Tripura BSF NEZ 1552.41 6-Jul-06 11-Mar-07 10-Mar-08 62% 10-Mar-08 85% slab cast. B/W alongwith fixing of door

frame and windows plastering are running.

(iv) 34 /T-III(T/S) Fatikchera Tripura BSF NEZ 1552.41 6-Jul-06 8-Mar-07 3-Jul-08 0 66.15 66.15 65% 3-Jul-08 89% roof casting is over and B/W going on

besides fixing of doors & windows. Plastering

in progress.

(v) Devnt. works i/c road, culvert, S/W Fatikchera Tripura BSF NEZ 1552.41 6-Jul-06 1-May-07 22-Nov-07 31-Mar-08 Work started. Culverts completed.

drains and septic tanks.

(vi) C/o Retaining Wall, UG sump, Fatikchera Tripura BSF NEZ 1552.41 6-Jul-06 1-May-07 22-Nov-07 31-Mar-08 Work awarded.

external w/s line & pump house.

(vii) Iron removal filtration plant. Fatikchera Tripura BSF NEZ 1552.41 6-Jul-06 Completed.

Electrical work Fatikchera Tripura BSF NEZ 1552.41 6-Jul-06 30% 30-Apr-08 Conduiting in progress

40 C/o Amenity & Community Centre at Bagafa Tripura BSF NEZ 86.15 1-Sep-05 1-Apr-06 15-Feb-07 26.26 42.39 68.65

Bagafa. (i) Building work. 76% 31-Dec-07 Work is in progress.

(ii) Development of site. Bagafa Tripura BSF NEZ 86.15 1-Sep-05 12-Mar-07 13-Jun-07 Work awarded.

(iii) Electrical work Bagafa Tripura BSF NEZ 86.15 1-Sep-05 40% 31-Dec-07 Laying of conduit in progress

41 C/o 2 nos. 120 men Jawans living Bagafa Tripura BSF NEZ 556.47 6-Apr-06 6-Oct-06 27-Mar-08 72.46 46.50 118.96 35% 30-Apr-08 Delay in finalaisation of site by BSF officials

barrack with cook house cum dining hall

& lav. block at Bagafa.

Electrical work Bagafa Tripura BSF NEZ 556.47 6-Apr-06 10% 31-May-08 Conduiting in progress

42 C/o 1 No.120 men barrack at Panisagar. Panisagar Tripura BSF NEZ 272.02 19-Oct-05 5-Jun-06 4-Sep-07 74.26 70.26 144.52 65% 31-Mar-08 Structure completed. Work is in progress.





43 Electrical work I/c SITC of 250 KVA Panisagar Tripura BSF NEZ 272.02 19-Oct-05 50% 31-Dec-07 Conduiting in progress, Tender for SITC of 250

substation KVA transformer is awarded

44 C/o Community & Amenity Centre with Masimpur Assam BSF NEZ 211.21 27-Feb-07 Tender accepted. Structural drawings under

Family Welfare Centre at BSF Campus, preparation.

Masimpur, Silchar, Assam.

45 C/o 16 Nos. Qtrs.(Ty-V-6 & Ty-III-10) for Guwahati Assam CRPF NEZ 183.77 27-Oct-00 RB(P)

CRPF at GC Guwahati.

(i) 10/ T-III Guwahati Assam CRPF NEZ 183.77 27-Oct-00 Nov-01 Nov-02 34.08 34.08 100% 1-Sep-05 Work completed and handed over.

(ii) 6/ T-V Guwahati Assam CRPF NEZ 183.77 27-Oct-00 Work was kept in abeyance by client &

recently re-allotted to CPWD. Layout plan

showing the location & prel. Drgs. sent to

CRPF HQ. Approval is awaited.

Electrical work Guwahati Assam CRPF NEZ 183.77 Work awarded

46 2 Lakhs Litres capacity OHT for GC, Guwahati Assam CRPF NEZ 38.73 1-Jul-04 18-Sep-07 17-Jun-08 3% 17-Jun-08 Foundation cast.

CRPF, Guwahati.









(A) CPOPage6

Sl. Name of Work (i/c Sub-heads). Location State Client Zone A/A & E/S Tender A/A & E/S Date of Stipula-ted Head of Budget Expdr. Expdr. Upto date Upto Target Remarks / Self-explanatory note about the

No. amount details of date start (as date of Account Allotment upto last upto total date date of project as a whole as sanctioned

(In lakhs) Sub per Comple- (in lakhs) year (in reporting expdr. (in physi- physical

Heads agmt.) tion (As lakhs)=x month in lakhs) cal Pro- comple-

per agree- current =x+y gress tion

ment) year (in (%)

lakhs)=y



1 2 3 4 5 6 7 7a 8 9 10 11 12 13 14 15 16 17 18

47 C/o 284 Nos Family qtrs for GC, CRPF, Khatkhati Assam CRPF NEZ 1873.00 1-Nov-01 1-Nov-03 31-May-05 4055 75.00 1739.98 11.46 1751.44 100% 30-Jun-07 All Civil works completed. Delay due to local

Khatkhati (Assam). RB(NP) disturbance & flood in Assam.

Electrical work Khatkhati Assam CRPF NEZ 1873.00 1-Nov-01 76.04 0.29 76.33 90% 31-Dec-07 105 nos. qtrs. completed and handed over.

Balance wiring completed except erection of

fittings

48 C/O 33 KV line for feeding power to GC Khatkhati Assam CRPF NEZ 63.56 18-Aug-05 62.30 0.00 62.30 31-Mar-08 Work is to be carried by ASEB, Payment made

CRPF, Khatkheti. to ASEB

49 C/o Retaining wall with s/ w drain around Dayapur, Assam CRPF NEZ 38.85 26-Apr-05 17-Dec-06 16-May-07 OB(NP) 10.00 14.76 0.10 14.86 56% 31-Mar-08 Work in progress.

the parade ground in front of barrack Silchar

no.2 & laying/levelling the parade ground

at GC, CRPF, Dayapur, Silchar.



50 Erection of plinth & floor, toilets, toe wall Kashipur, Assam CRPF NEZ 25.41 25-Apr-07 19-Jul-07 18-Nov-07 31-Mar-08 Work awarded. Site not yet finalised.

etc. for C/o 9 nos. P/F huts(16' x 32') for Silchar

CRPF at Kashipur, Silchar.

51 C/o 27 roomed SOs dormitories for Langjing Manipur CRPF NEZ 239.81 8-Aug-03 2-Jun-04 1-Oct-05 53.96 7.89 61.85 40% 31-Dec-07 F-4 level slab casting in progress. Plaster in

CRPF at Langjing, Imphal. GF & FF in progress

Electrical work Langjing Manipur CRPF NEZ 239.81 1-Aug-03 1.62 0.10 1.72 35% 31-Dec-07 Conduiting in progress.

52 C/o 90 men barrack for CRPF at Usha Agartala, Tripura CRPF NEZ 219.42 6-Mar-06 4-Aug-06 31-Aug-07 OB(NP) 282.00 107.88 128.47 236.35 100% 31-Oct-07 Work completed. Final bill under preparation.

Bazar, Agartala Usha Bazar

Electrical work Agartala, Tripura CRPF NEZ 219.42 6-Mar-06 3.45 3.45 95% 31-Dec-07 Erection of fitting in progress

Usha Bazar

53 C/o Admn. Block for IGP/DIGP, Usha Agartala, Tripura CRPF NEZ 299.36 6-Mar-06 3-Jan-07 2-Jan-08 57.91 17.57 75.48 46% 2-Jan-08 Shuttering for floor 2 level in front block and 4

Bazar, Agartala Usha Bazar level in rear block is in progress.

Electrical work Agartala, Tripura CRPF NEZ 299.36 6-Mar-06 30% 31-Mar-08 Conduiting in progress

Usha Bazar

54 Pvdg. Flood light from gate no. 1 to 2 Guwahati Assam CRPF NEZ 13.91 6-Mar-06 19-Jun-06 0.00 0.00 0.00 50% 31-Jan-08 Poles delivered at site

along boundary wall at GC CRPF,

Guwahati.

55 Spl. Repair / rewiring of 147 nos. spl. Guwahati Assam CRPF NEZ 24.73 6-Mar-06 7-Apr-07 8-Oct-07 0.48 0.00 0.48 75% 31-Dec-07 Wiring completed, fittings to be installed

Type- I qtrs., Guwahati, Assam

56 Spl. Repair / rewiring of 107 nos. spl. Guwahati Assam CRPF NEZ 17.66 6-Mar-06 7-Apr-07 8-Oct-07 90% 31-Dec-07 Erection of fittings in progress

Type- I qtrs., Guwahati, Assam

57 C/o Office cum barrack for CISF at Doom Assam CISF NEZ 88.09 73.22 26-Nov-06 18-Jul-07 18-Jul-08 CSSA 0.20 0.18 0.38 30-Sep-08 Work awarded.

National Tech. Research Organisation, Dooma

Doom Dooma, Assam.

58 C/o Office bldg. & 6-T/II(D/S), 12- Itanagar, Aru. Pradesh ISPW NEZ 244.40 18-Apr-06

T/III(D/S) Qtrs. for ISPW Stn. at Itanagar, Naharlagun

Aru.Pradesh.

(a) 6-T/II(D/S) Itanagar, Aru. Pradesh ISPW NEZ 244.40 18-Apr-06 15-Jun-07 14-Jun-08 0.05 0.05 20% 14-Jun-08 Foundation & plinth beam cast. Column above

Naharlagun plinth in progress.

(b) 12-T/III(D/S) Itanagar, Aru. Pradesh ISPW NEZ 244.40 18-Apr-06 15-Sep-07 14-Dec-08 6% 14-Dec-08 RCC work in foundation completed in one

Naharlagun block & in progress in other blocks.

(c) Office bldg. Itanagar, Aru. Pradesh ISPW NEZ 244.40 18-Apr-06 Construction cannot start as Site is disputed.

Naharlagun

Electrical work ISPW NEZ 244.40 18-Apr-06 0.00 DE under preparation, tender to be invited.

59 C/o Combine TX/RX office building for Guwahati Assam ISPW NEZ 39.60 1-Sep-05 22-Jun-06 21-Mar-07 4055 OB 10.00 31-Dec-07 Brick work completed. Plastering work in

(Auth) 13.96 0.13 14.09 80%

ISPW at Guwahati (Assam) progress. Door windows frame fixed.

Electrical work Guwahati Assam ISPW NEZ 39.60 12-Sep-05 40% 31-Dec-07 Work awarded and in progress along with

building work.









(A) CPOPage7

Sl. Name of Work (i/c Sub-heads). Location State Client Zone A/A & E/S Tender A/A & E/S Date of Stipula-ted Head of Budget Expdr. Expdr. Upto date Upto Target Remarks / Self-explanatory note about the

No. amount details of date start (as date of Account Allotment upto last upto total date date of project as a whole as sanctioned

(In lakhs) Sub per Comple- (in lakhs) year (in reporting expdr. (in physi- physical

Heads agmt.) tion (As lakhs)=x month in lakhs) cal Pro- comple-

per agree- current =x+y gress tion

ment) year (in (%)

lakhs)=y



1 2 3 4 5 6 7 7a 8 9 10 11 12 13 14 15 16 17 18

60 C/o Office building for ISPW station at Kohima Nagaland ISPW NEZ 43.31 1-Nov-05 1-Apr-06 31-Dec-06 4055- 0.20 4.25 4.45 17% 31-Mar-08 Work in progress.

Kohima, Nagaland ISPW

Electrical work Kohima Nagaland ISPW NEZ 43.31 1-Nov-05 0% Work awarded, work front for electrical work is

not ready

61 C/o resdl.qtrs.(T/III-12,T/II-6) at Kohima, Kohima Nagaland ISPW NEZ 142.41 1-Nov-05 4055- 85.00

Nagaland ISPW

(i) T/III-12 Kohima Nagaland ISPW NEZ 142.41 1-Nov-05 1-Feb-06 31-May-07 26.60 10.61 37.21 38% 31-Mar-08 Work in progress.

(ii) T/II-6 Kohima Nagaland ISPW NEZ 142.41 1-Nov-05 1-Feb-06 26-Nov-06 25.54 16.93 42.47 96% 31-Dec-07 Work in progress.

Electrical work Kohima Nagaland ISPW NEZ 142.41 1-Nov-05 30% 31-Jan-08 Conduit laying In progress

62 Development of site & bulk services for Kohima Nagaland ISPW NEZ 94.78 1-Nov-05 1-Apr-06 31-Jan-07 OB(NP) 34.23 20.77 55.00 79% 28-Feb-08 Work in progress.

ISPW at Kohima, Nagaland

Electrical work Kohima Nagaland ISPW NEZ 94.78 1-Nov-05 30% 31-Jan-08 Conduiting in progress, PQ for 200 KVA

transformer is done, tender sale in progress

63 C/o Security fencing wall i/c approach Kohima Nagaland ISPW NEZ 19.59 30-Sep-04 5-May-05 5-Nov-05 4055 15.00 9.14 0.11 9.25 78% 28-Feb-08 Work in slow progress due to cutting and

road, R/wall for ISPW station at Kohima, dumping of earth around the campus. Initially

Nagaland. delayed due to non-existence of approach

road.

64 C/o ISPW station bldg. at Khatla, New Khatla, Mizoram ISPW NEZ 429.75 11-Apr-07 RB(NP) Tender accepted.

Complex and 6-T/II & 12-T/III staff qtrs. Luangmual,

Aizawl

at Luangmual, Aizawl.

(i) 6-T/II & 12-T/III staff qtrs. at Luangmual, Mizoram ISPW NEZ 429.75 1-Sep-07 1-Aug-08 31-Aug-08 Work awarded.

Luangmual, Aizawl Aizawl

(ii) Station bldg., Retaining & boundary Khatla, Mizoram ISPW NEZ 429.75 1-Jul-07 28-Feb-08 28-Feb-08 Work awarded.

wall at Khatla. Aizawl

65 Recarpeting of existing bituminous road Itanagar Aru. Pradesh ITBP NEZ 24.27 5-Nov-05 6-Apr-06 26-Sep-06 4055- 25.00 3.14 0.00 3.14 39% 31-Dec-07 Part recarpeting work done. Work rescinded

of ITBP at Itanagar. OB(NP) due to slow progress.

66 Re-carpetting of internal roads at BHQ Kimin Aru. Pradesh ITBP NEZ 31.68 16-Nov-06 7-Mar-07 27-Jul-07 4055- 5.89 0.00 5.89 60% 31-Dec-07 Premix carpeting and WBM in progress. Slow

10 Bn. ITBP at Kimin, Ar. Pradesh. OB(NP) progress due to rains.

67 C/o Security and retaining wall in ITBP, Itanagar Aru. Pradesh ITBP NEZ 371.79 16-Nov-06 7-Jun-07 28-Jun-08 4055- 257.50 0.00 238.12 238.12 80% 28-Jun-08 Work in progress

SHQ (NE-1) campus at Khating Hills, OB(NP)

Itanagar, Ar. Pradesh.

68 Supply, installation & testing of 1 no. 125 Itanagar Aru. Pradesh ITBP NEZ 25.20 22-Aug-06 11-Jul-07 10-Jan-08 31-Jan-08 Work awarded. Inspection of DG set at

KVA DG sets & provision of street lights manufacture premises has been conducted.

at ITBP campus at Itanagar, Aru.

Pradesh. 0

69 Providing electricity to Surwasamba Surwasamba Aru. Pradesh ITBP NEZ 39.41 39.41 8-Jan-07 4055-OB(NP)

0.00 0.00 0.00 0.00 0% 31-Mar-08 Payment to be released to Dept. of Power,

outpost of 2nd ITBP Bn. at Indo-China Arunachal Pradesh.

Border.

70 C/o 4 nos. Senior Officers' suites at Umsaw Meghalaya NEPA NEZ 23.84 Mar.05 1-Jul-06 31-May-07 4552 0.00 11.46 0.00 11.46 95% 31-Dec-07 Finishing works are in progress. Work nearing

NEPA, Umsaw, Meghalaya. completion.

Electrical work Umsaw Meghalaya NEPA 23.84 10% 30-Dec-07 Conduiting in progress

71 C/o Open Firing Range at NEPA, Umsaw Meghalaya NEPA NEZ 51.29 27-Jun-06 1-Nov-06 27-Aug-07 4552 0.00 13.54 0.00 13.54 65% 30-Dec-07 Work in progress. Excavation of earth &

Umsaw. Retaining wall in progress.

72 C/o Indoor firing range at NEPA, Umsaw Umsaw Meghalaya NEPA NEZ 74.15 27-Jun-06 5-Apl-07 31-Jan-08 4552 0.00 0.00 0.00 10% 31-Jan-08 Foundation work is in progress. Retaining wall

behind building is in progress.

73 Extension of officers mess with 20 beds Umsaw Meghalaya NEPA NEZ 40.95 1-Jun-04 7-Jun-07 31-Mar-08 4552 0.00 0.00 0.00 5% 31-Mar-08 Foundation work is in progress.

in 10 rooms at NEPA, Umsaw,

Meghalaya









(A) CPOPage8

Sl. Name of Work (i/c Sub-heads). Location State Client Zone A/A & E/S Tender A/A & E/S Date of Stipula-ted Head of Budget Expdr. Expdr. Upto date Upto Target Remarks / Self-explanatory note about the

No. amount details of date start (as date of Account Allotment upto last upto total date date of project as a whole as sanctioned

(In lakhs) Sub per Comple- (in lakhs) year (in reporting expdr. (in physi- physical

Heads agmt.) tion (As lakhs)=x month in lakhs) cal Pro- comple-

per agree- current =x+y gress tion

ment) year (in (%)

lakhs)=y



1 2 3 4 5 6 7 7a 8 9 10 11 12 13 14 15 16 17 18

74 C/o Garage, guard armour & generator Khejurbagan, Tripura SB NEZ 40.95 12-Mar-07 30-Sep-07 Work started.

room for SB at Khejurbagan, Agartala. Agartala



Electrical work Khejurbagan, Tripura SB NEZ 40.95 0.00 0.00 0.00 0% 31-Oct-08 Work front for electriocal work is not ready.

Agartala

75 C/o Office cum resdl. Qrs.(3/T-I, 10/T-II, Dibrugargh Assam SB NEZ 308.73 258.69 26-Mar-07 29-Aug-07 30-Aug-08 CSSA 30-Aug-08 Work awarded.

8/T-III, 2/T-IV & 1/T-V) for SB,

Dibrugarh.

76 C/o Office bldg & 10 resdl. Qtrs for the Tura Meghalaya SIB NEZ 68.45 1-May-01 1-Jan-03 17-Feb-04 4059 50.00 57.26 3.52 60.78 97% 30-Dec-07 Civil work completed. Electrical work in

office of DCIO, SIB, Dakopgiri, Tura. progress. Handing over notes under

preparation

Electrical work Tura Meghalaya SIB NEZ 68.45 0.00 60% 30-Dec-07 Office bldg. completed but not occupied by

client. Work in progress in quarters.

77 C/o Office building & 3 nos resdl. Qtrs. Williamna-gar Meghalaya SIB NEZ 33.58 22-Oct-03 1-Mar-05 31-Aug.05 4059 15.00 20.10 12.61 32.71 99% 30-Dec-07 Civil work completed. Electrical work in

for SIB at Williamnagar, Garo Hills. progress. Handing over notes under

preparation

Electrical work Williamna-gar Meghalaya SIB NEZ 33.58 0.00 60% 30-Dec-07 Work in progress with building work



78 C/o Office Bldg. & Resdl. Qrts. for SIB at Hengrabari, Assam SIB NEZ 496.20 23-Jul-04 4-Aug-04 30-Jun-07 4059- 377.98 68.23 446.21 100% 30-Nov-07 Work completed.

Hengrabari, Guwahati. Guwahati C.O. on

P.W.

(i) Office Building i/c internal w/s and s/i. Hengrabari, Assam SIB NEZ 496.20 Civil -136 30-Nov-04 27-Mar-06 70.00 131.48 11.08 144.17 100% 31-Mar-07 Work completed

Guwahati Elect - Nil (Authn)

Electrical work Hengrabari, Assam SIB NEZ 496.20 4-Jul-04 100% 31-Aug-07 Work completed

Guwahati

(II) Resdl. Qtrs. 6/T- I , 12/T- II, 6/T-III, Hengrabari, Assam SIB 496.20 Civil - 19-Feb-05 18-Aug-06 233.20 21.10 254.30 100% 31-May-07 Work completed.

6/T-IV and 2/T-V i/c int. w/s & s/i. Guwahati 289.09

Elect-Nil

Electrical work Hengrabari, Assam SIB NEZ 496.20 4-Jul-04 100% 31-Aug-07 Completed

Guwahati

(iii) Development work & Bulk Services Hengrabari, Assam SIB 496.20 Civil - 4-Aug-07 24-Oct-07 13.30 34.44 47.74 100% Nov-07 Work completed.

Road work Guwahati 44.65

Elect-Nil

(iv) U.G. Sump Hengrabari, Assam SIB NEZ 496.20 4-Jul-04 UG completed. Tender for pumps awarded.

Guwahati

(v) Sub-Station, SITC 63 KVA DG Set, Hengrabari, Assam SIB NEZ 496.20 4-Jul-04 100% 31-Aug-07 Work completed.

SITC of transformer and service Guwahati

connection & Deep tube well

79 C/o 10 Jawans Barrack & 4 Single room Dimapur Nagaland SIB NEZ 25.63 1-May-06 20-Jan-07 8.00 8.57 8.32 16.89 97% 31-Jan-08 Work in progress.

Accommodation for SIB at Circular road,

Dimapur, Nagaland.

Electrical work Dimapur Nagaland SIB NEZ 25.63 1-May-06 DE under preparation

80 C/O Boundary Wall cum security fencing Debendra- Assam SSB NEZ 437.77 15-Dec-06 15-Jul-07 15-Oct-08 4059 55.00 0.00 113.42 113.42 25% 31-Oct-08 RCC columns, grade beams , masonry and

around the SSB campus, nagar, fabrication of MS grills in progress

Debendranagar, Assam.

81 C/o Perimeter road along boundary of Salonibari, Assam SSB NEZ 180.84 28-Aug-06 15-Jul-07 15-Jul-08 4055 55.00 0.00 0.00 0.00 10% 31-Jul-08 Site waterlogged. Agency has started

SSB Training Centre at Salonibari, Tezpur collecting road metal.

Tezpur









(A) CPOPage9

(B) CPO WORKS COSTING RS. 10 LAKHS AND ABOVE (WORKS SANCTIONED BUT NOT STARTED)

NORTH EASTERN ZONE - P-11 to 14 Nov-07

Target Target Target Target

Sl.No









Date of A/A & E/S date for date for Target date for date for

sending Amount A/A & E/S detail structural date for call of start of

Name of work Location State Client Zone P.E. (in lakhs) date drgs. drgs. D.E. tenders work Reasons for delay and action proposed.

17 Sinking of Deep Tube well & C/o water Itanagar Aru. Pradesh ITBP NEZ 30-Oct-06 23.75 11-Jan-07 15-Nov-07 Tenders of tubewell under scrutiny and work of water

storage tank of 10,000 Gallons capacity storage tank awarded

at SHQ(NE-I), ITBP campus at Itanagar.

18 C/o SOs mess and dining hall in ITBP Itanagar Aru. Pradesh ITBP NEZ 28-May-07 270.54 21-Sep-07 Press Notice issued. Tenders to be received on

campus at Itanagar 23.11.07

19 Installation of 2 nos. 125 KVA DG sets at Kimin Aru. Pradesh ITBP NEZ 8-Jun-06 37.80 21-Sep-07 DE/NIT under preparation.

10th Bn. ITBP campus at Kimin,

Arunachal Pradesh.

20 Supply, installation & testing of 2 nos. Lohitpur Aru. Pradesh ITBP NEZ 6-Jun-06 27.30 21-Aug-06 15-Nov-07 PQ approved.

125 KVA DG sets for family qtrs. at Bn.

HQ ITBP campus at Lohitpur, Ar.

Pradesh.

21 Supply, installation & testing of 2 nos. Lohitpur Aru. Pradesh ITBP NEZ 4-Jul-07 24.05 13-Aug-07 DE/NIT under preparation.

62.5 KVA DG sets for ORs living

accomm./ main office area at Bn. HQ

Lohitpur, Arunachal Pradesh.

22 Providing electricity to Surwasamba Surwasamba Aru. Pradesh ITBP NEZ 6-Nov-06 39.41 8-Jan-07 DE under preparation, payment to Dept of Power AP

outpost of 2nd ITBP Bn. at Indo-China is pending due to non-receipt of budget allotment.

Border. Budget was allotted to SE(E) in May'07.









(B) cpoPage 10

(C) CPO WORKS FOR WHICH PE SENT BUT NOT SANCTIONED - WORKS COSTING RS. 10 LAKHS AND ABOVE

NORTH EASTERN ZONE - P-11 to 14 Nov-07

Sl.No







Name of work Location State Client Zone Date of PE Date of Detailed Remarks on the present status of PE.

requisi- Amount submis-

tion (in lakhs) sion of

P.E.

52 C/o GOs mess & T-VI Qrts. in ITBP campus at Itanagar Aru. ITBP NEZ 23-Feb-07 215.26 8-Aug-07 Modified PE sent. A/A & E/S awaited.

Itanagar Pradesh

53 C/o 120 Men Barrack at SHQ(NE-I), ITBP, Itanagar Aru. ITBP NEZ 25-Sep-06 576.53 28-May-07 A/A & E/S awaited.

Itanagar Pradesh

54 C/o M.T. Garage for 20 vans with workshop & store Itanagar Aru. ITBP NEZ 26-Dec-06 367.96 28-May-07 A/A & E/S awaited.

at SHQ with inspection pit / washing pit in ITBP Pradesh

campus at Itanagar

55 C/o Officers' mess at SHQ(NE-I), ITBP, Itanagar Itanagar Aru. ITBP NEZ 21-May-07 PE sent.

Pradesh

56 C/o Jawans' barrack i/c kitchen, toilets & bathrooms Itanagar Aru. ITBP NEZ 21-May-07 PE sent.

at SHQ(NE-I), ITBP, Itanagar Pradesh

57 Re-carpeting of existing bituminous internal roads at Along Ar. Pradesh ITBP NEZ 21-May-07 45.30 10-Oct-07 A/A & E/S awaited.

BHQ, 20th Bn, ITBP, Along, Ar. Pradesh.









(C) CPOPage 11

(D) CPO WORKS COSTING RS. 10 LAKHS AND ABOVE (WORKS FOR WHICH REQUISITION RECEIVED BUT PE IS YET TO BE SENT)

NORTH EASTERN ZONE - P-11 to 14 Nov-07

Sl.No









Name of work Location State Client Zone Date of Target Tartet Target Target Reasons for delay and action proposed.

requisi- date for date for date for date for

tion LOP prelim. appro- submissi

Drg. val of on of P.E.

prelim.

Drg.

37 C/o Training hall & T/IV Qtrs. in ITBP campus at Itanagar Ar. Pradesh ITBP NEZ 6-Oct-06 Prel. Drgs. based on detailed requrement received from ITBP

Itanagar in Oct.06 sent to client on 12.12.06 for approval. Approval

awaited. Client suggested change of site vide letter

dt.19/2/07. Revised drgs. sent to Client in 6/07 for approval.

Client approval awaited.

38 C/o 24/T-II(D/S), 8/T-III(D/S) & 2/T-IV(S/S) in ITBP Along Ar. Pradesh ITBP NEZ 1-Mar-06 Draft PE sent in 7/07 by SE,ACC-I to SE(P). Final PE under

campus at Along, Ar. Pradesh. process and shall be sent shortly. Drgs. sent to ITBP for

approval. SSP awaited. LOP to be prepared. Tenders for soil

investigation & SSP called.

39 C/o Training shed at BHQ, 20th Bn, ITBP, Along, Along Ar. Pradesh ITBP NEZ 21-May-07 SSP to be received from EE by October end.

Ar. Pradesh.

40 C/o 120 men barrack for jawans at BHQ, 20th Bn, Along Ar. Pradesh ITBP NEZ 21-May-07 SSP to be received from EE by October end.

ITBP, Along, Ar. Pradesh.

41 C/o Overhead water storage tank and bore wells i/c Kimin Ar. Pradesh ITBP NEZ 21-May-07 SSP to be received from EE by October end.

laying of pipe lines for providing water supply to

BHQ, ITBP at Kimin, Ar. Pradesh.

42 C/o 12-T/II, 4-T/IV, 1-T/V Resdl. Qtrs. For 9th Bn. Lohitpur Ar. Pradesh ITBP NEZ 1-Jun-06 Draft PE for Rs. 173.39 lacs received from SE, ACC-II under

ITBP at Lohitpur. scrutiny. LOP not finalised. SSP awaited.

43 WBM & recarpeting of road at BHQ, ITBP at Lohitpur Ar. Pradesh ITBP NEZ 21-May-07 Requisition received recently.

Lohitpur and Air Maint. Dett., Mohanbari.

44 C/o Training shed at 9th Bn. ITBP at Lohitpur. Lohitpur Ar. Pradesh ITBP NEZ 21-May-07 SSP awaited.

45 C/o MT garage for heavy vehicles for 9th Bn. ITBP Lohitpur Ar. Pradesh ITBP SSP awaited.

at Lohitpur.

46 C/o Supply, installation & testing of 2 nos. 125 KVA Kimin Ar. Pradesh ITBP NEZ 21-May-07 Requisition received recently.

DG sets at Kimin, Ar. Pradesh.

47 C/o Zonal Hqtrs. for ITBP at Shillong. Shillong Meghalaya ITBP NEZ 6-Jun-06 Site has been selected by client. Suitability Certificate is to

issued after inspection of site.

(E) CPO WORKS COSTING RS. 10 LAKHS AND ABOVE (works recently completed.)

NORTH EASTERN ZONE - P-11 to 14 Nov-07

Sl. Name of Work (i/c Sub-heads). Location Client Zone A/A & A/A & E/S Date of Stipulated Head of Budget Expdr. Expdr. Upto date Upto Target Remarks (Present stage of

No. E/S date start (as Dt. of A/c allot ment/ upto last upto total date date of work i/c reason of delay, if

amount per agmt.) Completio likely year (in repor- expdr. (in physica physical

any & action.

n (As per expre. lacs)=x ting lacs) =x+y l Pro-

(In lacs) comple-

agreement during month gress

tion

) current in (%)

year (in current

lacs) year (in

lacs)=y

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 C/o 24 Nos. T-II qtrs. i/c W/S & S/I for Diphu Assam AR NEZ 146.60 1-Jul-01 1-Mar-02 1-Jul-03 4055 142.04 142.04 100% 31-Jan-05 Handed over

16 Assam Rifles, Diphu RB(P)

2 C/o 24 Nos. T-II Qtrs. Married Diphu Assam AR NEZ 149.32 1-Jul-01 1-Mar-02 1-Jul-03 137.25 137.25 100% 30-Apr-05 Handed over

accommodation i/c w/s & S/I for 16

Assam Rifles Training Centre, Diphu.

3 C/o 24 Nos. T-I and 6 Nos. T-II Qtrs for Lokhra Assam AR NEZ 127.47 1-Aug-00 1-Feb-01 1-Jun-02 144.57 144.57 100% 31-Oct-04 Handed over

31 Assam Rifles at Lokhra

4 Resdl. & Non-Resdl. Bldg. For Assam Charduar Assam AR NEZ 4066.00 1-Aug-99 4055 178.00 3236.41 0.00 3236.41 100% 30-Jun-07 Entire project completed.

Rifles, Charduar. RB(NP)

5 C/o Rsdl quarters (12/T-III & 36 /T-II) Jorhat Assam AR NEZ 337.00 Nov-01 8-Jul-02 11-6-03 4055 0.00 273.12 0.00 273.12 100% Comp. Civil Work Completed.

for Assam Rifles at Jorhat. (RB) (Budget)

6 C/o 18 T-II & 6 T-III Qtrs for 2 MGAR at Silchar Assam AR NEZ 145.56 1-Nov-01 RB(NP) 60.00 133.47 3.79 0.00 Work completed.

Silchar

7 C/o 20/Ty-II, 6/Ty-III for AR T.C. and Sukhovi Nagaland AR NEZ 140.82 1-Nov-00 1-Jun-01 1-Oct-02 RB(P) 113.00 86.51 86.51 100% 30-Nov-04 Work completed.

School at Sukhovi, Nagaland

8 C/o Resdl. Qtrs. and SMB for 8 NCO & Agartala Tripura AR NEZ 365.00 1-Jan-02 RB(NP) 42.00 31-Dec-04 Work completed.

80 ORs for T. range & 26 AR. Agartala.



9 C/o 12/T-I, 18 /T-II , 4/T-III, 1/ T-V & Agartala Tripura AR NEZ 385.00 1-Jan-02 RB(NP) 96.04 0.00 96.04 Work completed.

S.M. Barrack (D/S) NCOs & 80 ORs for

HQ T-Tange and 26 Assam Rifles at

Agartala.

10 C/o Resdl. qtrs. for AR at Khatla, Khatla Mizoram AR NEZ 279.00 29-Oct-02 4055 245.97 -0.15 245.82 30-Oct-06 Work completed including

Mizoram. (SH: 24/T-II, 4/T-III, 1/T-IV ) RB(P) Electrical work.

11 C/o 1 /T-V & 4 /T-III qtrs. for AR at Khatla Mizoram AR NEZ 69.84 1-Aug-02 1-Feb-04 1-Feb-05 47.60 64.75 0.00 64.75 100% 31-Mar-07 T/III qtrs. being handed over

Khatla, Mizoram and T/V in Mar.07.

12 C/o T-II-20 Nos. (D/S) for BSF at SHQ, Shillong Meghalaya BSF NEZ 131.19 24-May-02 1-Jun-03 1-Sep-04 4055 94.68 43.78 138.46 100% 30-Oct-06 Work completed. Likely to be

Mawpat, Shillong. handed over in Nov '2006

13 C/o Internal road, culverts, Drains, Tura-I Meghalaya BSF NEZ 39.51 1-Apr-02 1-Mar-03 1-Dec-03 4055 63.50 0.00 63.50 100% Work completed & handed

Retaining walls for BSF at Dobasipara, over. RPE sent.

Tura-I

14 C/o 4 Sos suites with Mess at 199 Bn. Tura-III Meghalaya BSF NEZ 46.18 30-Sep-03 5-Jan-05 5-Jul-05 4055 16.38 5.79 22.17 100% 31-Dec-06 Work completed.

Dhanakgiri, Tura-III. OB(NP)

15 C/o 24/ T-II qtrs. (D/S) for 112 Bn. BSF Alamganj-I Assam BSF NEZ 149.30 12-Aug-02 1-Aug-03 1-Jul-04 89.69 0.10 89.79 100% 30-Sep-06 Work completed.

at Alamganj-I

16 C/o 14 nos. SOs suites with mess at Masimpur Assam BSF NEZ 63.19 15-May-03 1-Feb-04 1-Nov-04 OB(NP) 65.00 52.41 0.00 52.41 100% 31-Mar-07 Work completed.

Masimpur

17 C/o Resdl. Qtrs. T-I/34 Nos.(F/S) I/c Patgaon, Assam BSF NEZ 165.24 03-Sep-01 8-Dec-01 6-Jul-03 4055 25.00 119.83 9.65 129.48 100% Work completed

Development of site at Patgoan, Guwahati RB (P) (Budget)

Guwahati.

18 7 suites for Officer's Mess i) Suites & Pallel Manipur BSF NEZ 110.05 10-Mar-97 1-Feb-99 1-Mar-00 OB(NP) 50.00 75.32 75.32 100% 30-Jun-05 Work completed

(ii) Kitchen & Dining Halls, Pallel. (Consld.)

19 C/o 120 men barrack for SHQ. BSF, Koirengi Manipur BSF NEZ 223.75 9-Aug-01 1-Sep-02 1-Sep-03 OB(NP) 40.00 189.62 0.00 189.62 100% 31-Jan-07 Work completed

Koirengi

20 C/o. 2 nos. 168 men barracks with cook Churachand- Manipur BSF NEZ 309.05 1-Mar-97 15-Jan-99 31-May-00 264.94 0.00 264.94 100% 31-Jul-07 Kitchen/ Dining and Barrack 1

house and dining hall for BSF at pur completed in 5/04 & occupied.

Churachandpur, Manipur. Defects to be attended.



21 C/o Quarter guard for BSF at Lunglei Lunglei Mizoram BSF NEZ 93.99 25-Nov-02 1-Dec-03 1-Dec-04 20.00 33.25 0.00 33.25 100% 30-Nov-06 Main work completed & handed

over.

22 C/o 10 Bedded hospital with MI room at Lunglei Mizoram BSF NEZ 55.00 27-Feb-04 1-Sep-04 1-Jun-05 37.37 0.00 37.37 100% 30-Nov-06 Work completed.

Bn. Hq. 86 Bn. for BSF at Lunglei,

Mizoram.

23 C/o 4 GOs suites for at BSF transit Dimapur Nagaland BSF NEZ 36.28 1-Jan-02 1-Oct-02 1-Jul-03 OB(NP) 26.00 31.98 31.98 100% 31-Jul-05 KCD - Work completed in July,'

camp at Dimapur. (Consld.) 05 and handed over.



24 C/o 1/ 120 Men Barrack for BSF at BN Ambassa Tripura BSF NEZ 291.18 1-Feb-00 1-Oct-01 1-Feb-03 4055 150.53 150.53 100% 30-Nov-04 Work completed and handed

HQ Ambassa under SHQ, BSF, Tripura RB(NP) over.

(North)

25 C/o Resdl. qtrs. for BSF at BN HQ Ambassa Tripura BSF NEZ 342.81 1-May-00 4055 28-Feb-05 Work completed.

Ambassa , Tripura (North) RB(P)

26 C/o Quarter guard for 68 Bn. HQ at Ambassa Tripura BSF NEZ 79.43 11-Oct-02 1-Jun-03 1-Jun-04 OB(NP) 60.85 1.81 62.66 100% 30-Apr-05 TCD - Work completed.

Ambassa

27 C/o Admn. Block for BSF at Ambassa Ambassa Tripura BSF NEZ 116.19 18-Jun-03 1-Jun-04 1-Jun-05 97.74 0.00 97.74 100% 30-Apr-06 Work completed.



28 C/o 10 bedded hospital with MI rooms Ambassa Tripura BSF NEZ 104.49 21-Feb-02 1-Oct-02 1-Oct-03 4055 84.29 20.35 104.64 100% 30-Sep-05 TCD - Work completed. Final

and 4 suites with mess for SOs at Bn. OB(NP) bill under process.

HQ, 126 Bn, Ambassa

29 C/o 16 T-II quarters for BSF at Bagafa Bagafa Tripura BSF NEZ 132.78 25-Nov-02 15-Mar-01 15-Mar-03 76.77 18.34 95.11 100% Comp. Work completed.



30 C/o Primary School at Bagafa. Bagafa Tripura BSF NEZ 70.29 25-Jul-05 6-Mar-06 27-Jan-07 28.5 20.67 49.17 100% 15-Sep-07 Work completed.

31 C/o 36/T-II & 2/T-IV Qtrs at Fatikchera. Fatikchera Tripura BSF NEZ 309.58 17-Mar-04 1-Nov-04 15-Nov-05 95.11 184.81 279.92 100% Comp. Work completed.



32 C/o Amenity & Community Centre at Fatikchera Tripura BSF NEZ 82.49 23-Nov-05 1-Apr-06 15-Feb-07 30.88 4.79 35.67 100% 31-Jul-07 Work completed.

Fatikcherra.

33 C/o Non-Residential Building at BN HQ Fatikchera Tripura BSF NEZ 306.05 7-Oct-05 21-Apr-06 20-Jul-07 119.97 58.51 178.48 100% Main work completed on

Fatikcherra. (SH: 1 no.120 men 18.7.07 and handed over. Allied

barrack) work in progress.

34 C/o Internal Road for BSF at Nalkata Nalkata Tripura BSF NEZ 43.34 24-Jun-03 15-Jun-04 1-Jun-05 32.52 63.11 95.63 100% 31-Jan-06 Final bill under process.

35 C/o Resdl. Qtrs. (T/ I-24, T/ II-16, T/III-4, Nalkata Tripura BSF NEZ 346.54 1-May-00 Work completed.

T/IV-2, & T/ V-1 No.) for BSF at Nalkata



36 C/o Quarter guard for BSF at Nalkata Nalkata Tripura BSF NEZ 70.72 18-Jun-03 15-Dec-03 10-Dec-04 51.84 0.00 51.84 100% 31-Jul-06 Completed & handed over.

Final bill under preparation.

37 C/o. 10 bedded hospital for Sos at Bn. Nalkata Tripura BSF NEZ 101.53 11-Mar-02 15-Sep-02 10-Sep-03 OB(NP) 185.00 89.43 89.43

100% 30-Jul-06 Handing over note submitted

HQ (126 Bn. BSF) Nalkata

38 C/o 48 Nos. (D/S) T-I Resdl. qtrs. for Salbagan Tripura BSF NEZ 269.58 1-Jan-03 15-Nov-03 15-May-05 4055 226.03 226.03 100% 31-May-05 Work completed.

BSF at Salbagan RB(P)

39 C/o 50 Bedded Hospital at FTR Hospital Salbagan Tripura BSF NEZ 436.79 1-Jan-97 10-Mar-01 11-Mar-03 OB 425.00 621.33 0.00 621.33 100% 30-Jan-06 Civil work completed.

BSF TCM.at Salbagan (NP) Consd.

40 C/o family welfare centre at Salbagan Salbagan Tripura BSF NEZ 42.77 1-Jan-03 12-Jun-03 15-Apr-04 OB(NP) 42.77 6.60 49.37 100% 31-May-05 Work completed.



41 C/o 3 balance suites in GOs mess at Panisagar Tripura BSF NEZ 21.28 1-Oct-02 1-Mar-03 15-Sep-03 4055 6.38 6.38 100% 28-Feb-05 Work completed.

193 Bn. at Panisagar OB(NP)

42 C/o 24/T-II qtrs for BSF, Panisagar. Panisagar Tripura BSF NEZ 174.14 7-Nov-03 1-Oct-04 15-Feb-06 4055 30.36 97.33 127.69 100% 30-Jan-06 Work completed.

RB(P)

43 C/o Balance Road for BSF at Panisagar Tripura BSF NEZ 79.01 3-Jun-03 15-Jul-04 15-Jul-05 36.55 0.00 36.55 100% 30-Mar-06 Work completed.

Panisagar

44 C/o 12 Nos.Ty-III & 1 No. Ty-V Qtrs. For Panisagar Tripura BSF NEZ 130.68 2-May-05 5-Sep-05 6-Dec-06 RB (P) 150.00 201.11 0.00 201.11 100% 31-May-07 Work completed.

BSF at Panisagar.

45 C/o Resdl. Quarters for Sector HQ, Teliamura Tripura BSF NEZ 209.32 1-Jan-03 4055 30-Sep-05 Work completed.

Teliamura, Tripura

46 Bulk Water Supply scheme for BSF at Maharani- Tripura BSF NEZ 55.32 1-Mar-99 1-Mar-03 1-Aug-03 34.30 0.00 34.30 100% 30-Jun-06 Work completed. Handing over

Maharanichera chera in process.

47 C/o Admn. Block for BSF at Nalkata Nalkata Tripura BSF NEZ 112.12 11-Jul-03 4-May-03 5-May-04 830.00 95.17 0.00 95.17 100% 30-Oct-06 Completed. Handing over note

on 31.1.07.

48 C/o I no.120 men barrack at Gokulnagar Tripura BSF NEZ 297.42 1-Nov-05 1-Apr-06 31-Jul-07 80.98 100.06 181.04 100% 31-Jul-07 Work completed.

Gokulnagar.

49 C/o 4 Addl. rooms for signal centre at Guwahati Assam CRPF NEZ 17.57 15-Apr-01 3-Feb-03 3-Aug-03 4055 5.89 5.89 100% 31-Dec-04 Work completed and handed

GC, CRPF, Guwahati over.

50 C/o 180 Men Barrack 1 No. at GC, Guwahati Assam CRPF NEZ 275.48 15-Oct-99 1-Dec-00 1-Dec-01 4055 100.00 194.25 10.80 205.05 100%

CRPF, Guwahati, Assam. OB(NP)



51 Replacement of 160 KVA DG set with Guwahati Assam CRPF NEZ 23.31 6-May-06 7-Feb-07 27-May-07 13.53 0.00 13.53 100% 7-Aug-07 Completed

200 KVA DG set at power house GC,

CRPF, Guwahati

52 C/o Base structure upto plinth of 21 nos. Bongaigoan Assam CRPF NEZ 30.90 10-Sep-04 OB(NP) 21.28 0.00 21.28 100% 31-Dec-05 Work completed and handed

PF huts at Bongaigoan. over

53 C/o Base structure upto plinth of 26 nos. Goalpara Assam CRPF NEZ 37.78 30-Sep-04 OB(NP) 6.16 15.12 21.28 100% 31-Mar-06 Work already completed.

PF huts at 36 Bn. CRPF, Goalpara.



54 C/o Family welfare Centre at Khatkhati. Khatkhati Assam CRPF NEZ 121.43 1-Sep-03 1-May-04 1-May-05 71.74 24.43 96.17 100% 30-Nov-05 Work completed.



55 C/o 72 Nos. various types of Family Khatkhati Assam CRPF NEZ 369.42 1-Feb-00 RB(NP) 383.74 0.00 408.44 31-Dec-05 Work completed.

Quarters at GC, CRPF, Khatkhati.

56 C/o retaining wall to ditch side along Khatkhati Assam CRPF NEZ 23.97 9-Dec-05 6-Jun-06 6-Dec-06 19.35 19.35 100% 31-Dec-06 Work completed.

road leading to gate no.3 at GC CRPF,

Khatkhati

57 Renovation of children's park of existing Khatkhati Assam CRPF NEZ 21.11 1-Jan-06 23.18 0.00 0.00 100% 30-Apr-07 Work completed.

old T/I,T/II & T/III Qtrs. at GC CRPF,

Khatkhati

58 Cutting of Skirting road and c/o New Khatkhati Assam CRPF NEZ 18.62 6-Mar-06 0.00 20.85 20.85 100% 31-Mar-07 Work completed.

road to minimise gradient near parade

ground Pump house at GC CRPF,

Khatkhati

59 Pvdg. UG Telephone cable at GC, Khatkhati Assam CRPF NEZ 17.31 3-Sep-03 7-Jan-07 7-Jul-07 18.03 0.00 18.03 100% Jun-07 Work completed.

CRPF, Khatkhati

60 C/o Officers' Mess with suites at GC , Khatkhati Assam CRPF NEZ 288.89 1-Oct-00 1-Oct-02 21-Apr-04 OB(NP) 150.00 44.07 21.25 65.32 100% 31-Jul-07 Bldg. & Elect. work completed

CRPF, Khatkhati except work for fountain

61 Boring of 1 No. deep tube well for GC, Khatkhati Assam CRPF NEZ 20.46 1-Mar-00 1-Nov-04 21-Feb-05 15.48 0.00 15.48 100% 27-Jun-07 Work completed.

CRPF, Khatkhati

62 C/o 24 nos. toilets at GC, CRPF, Dayapur Assam CRPF NEZ 12.05 100% 30-Sep-06 Work completed

Dayapur, Silchar.

63 Providing wire mesh shutters in 5 Imphal Manipur CRPF NEZ 22.96 15-Sep-02 1-Feb-03 1-Jul-03 OB(NP) 30.00 22.21 0.00 22.21 100% Work completed.

barracks, Hospital bldg. & Officers'

mess at G.C. CRPF, Imphal.

64 C/o recreation room for CRPF at Imphal Manipur CRPF NEZ 16.83 1-Nov-01 1-Feb-03 1-Oct-03 4055 8.29 8.29 100% 30-Nov-04 Work completed.

Langjing OB(NP)

65 C/o approach road for CRPF Chill Chill Chill Chil Manipur CRPF NEZ 52.14 May.01 1-Jul-02 1-Sep-03 4055 12.45 0.79 13.24 100% 31-May-05 MCDI -Work completed.

Camp (i) Pt. I & II. OB(NP)



66 Prov. Wire Mesh shutters in T-II, 136 T-I Langjing, Manipur CRPF NEZ 72.13 1-Jan-02 1-Feb-03 1-Sep-03 4055 15.00 70.36 0.00 70.36 100% 30-Mar-06 MCD - Work completed &

(old) 184, T-I (New)/152 & T-I 'A'/48 at Imphal RB(NP) (Consd.) handed over.

CRPF, Langjing, Imphal

67 C/o 10 Officers' suites at G.C. CRPF, Imphal Manipur CRPF NEZ 97.63 1-Aug-00 1-Dec-01 1-Dec-02 OB(NP) 100.00 106.63 0.00 106.63 100% 30-Mar-06 Work completed.

Imphal. (Consd.)

68 C/o Generator room, operation & store Agartala, Tripura CRPF NEZ 27.05 1-Feb-04 OB(NP) 33.45 100% 31-Oct-05 Work completed. Final bill

room and filtration plant for CRPF at Usha Bazar under process.

Usha Bazar, Agartala.

69 C/o PF huts at GC, CRPF at Teliamura. Teliamura Tripura CRPF NEZ 16.74 4-Mar-05 5-Jun-05 5-Sep-05 OB(NP) 50.00 11.65 11.65 100% 30-Jan-06 TCD - Work completed.

(Consd.)

70 C/o Generator room, OPTR room, Agartala Tripura CRPF NEZ 27.90 1-Jan-05 5-Apr-05 OB(NP) 200.00 20.97 0.00 20.97 100% Comp. Final bill for main work passed.

Guard room at CRPF, Agartala.

71 Providing and installation of 250 KVA Salbagan Tripura CRPF NEZ 14.28 6-Jun-06 1-Sep-06 27-Mar-07 100% 31-Jul-07 Transformer installed.

transformer at GC, CRPF Campus,

Salbagan.

72 C/o Primary School at GC, CRPF, Khatkhati Assam CRPF NEZ 59.87 25-Aug-03 1-May-04 31-May-05 44.33 11.99 56.32 100% 30-Sep-07 Work completed.

Khatkhati (Assam).

73 C/o retaining wall near T-II Qtrs. of Umsaw Meghalaya NEPA NEZ 27.49 1-Oct-03 1-Oct-04 1-May-05 4552 26.12 0.39 26.51 100% 31-Mar-05 MGCD - Work completed.

NEPA at Umsaw, Meghalaya.

74 C/o 40 bedded Head constable mess at Umsaw Meghalaya NEPA NEZ 51.37 1-Sep-02 1-May-03 1-May-04 4552 45.79 4.39 50.18 100% 30-Sep-06 Bldg. inaugurated on 19.12.06

NEPA at Umsaw, Meghalaya. by Secy. (NEC) and is being

used by the client. Handing

over of the bldg. yet to be done.

Handing over note given to

client. Client is being pursued

for taking over of the bldg.



75 Carpeting of internal road of NEPA at Umsaw Meghalaya NEPA NEZ 16.58 1-Mar-05 1-May-06 1-Oct-06 4552 6.50 0.00 6.50 100% 31-Mar-07 Work completed.

Umsaw, Meghalaya

76 C/o Security Boundary Wall for ISPW Shillong Meghalaya ISPW NEZ 29.03 1-Jul-04 1-Jan-05 1-Jul-05 4056 12.77 14.23 27.00 100% 31-Jan-06 MGCD - Work completed.

at Motinagar, Shillong. OB(NP)



77 C/o 22 Nos qtrs. at ISPW Station at Basista, Assam ISPW NEZ 178.00 1-Feb-01 23-May-02 1-Sep-03 4055(R 182.77 0.00 182.77 100% Building handed over to client.

Basista, Guwahati. Guwahati B)

78 C/o Boundary wall with M.S. Security Itanagar Aru. ISPW NEZ 27.30 1-Dec-05 1-Jul-06 31-Dec-06 4055- 25.00 24.52 0.00 24.52 100% 15-Jul-07 Completed

Grill around the land of ISPW, Itanagar Pradesh. OB(NP)



79 C/o Approach road to ISPW land near Kohima Nagaland ISPW NEZ 31.37 1-Jan-06 1-Mar-06 1-Sep-06 4055- 30.00 0.17 26.18 26.35 100% Comp. Work completed.

new Sectt. Complex at Kohima, ISPW (Consdd.)

Nagaland

80 C/o Boundary wall around various Qtrs. Mokokchung Nagaland SIB NEZ 19.13 1-Aug-05 19.13 0.07 0.00 0.07 100% 30-Apr-06 Work completed.

& Office bldg. of SIB at Mokokchung,

Nagaland.

81 C/o Boundary wall around the land at Lakhimpur Assam SIB NEZ 12.36 27-Jun-05 Work completed & handed

Village Japisajia, Lakhimpur under SIB, over.

Guwahati.

82 C/o Firing Range at SSB, TC, Salonibari, Assam SSB NEZ 47.87 1-Nov-03 1-Jan-05 1-Jul-05 4055- 76.82 0.00 76.82 100% 30-Apr-06 Work completed.

Salonibari. Tezpur OB(NP)



83 C/O B/ wall, 10 nos. Watch Towers and Tezpur Assam SSB NEZ 279.00 1-Jul-03 4055 OB(NP) 0.00 262.48 262.48 28-Feb-07 Work completed

Guard room around the complex of SSB

T C, Salonibari, Tezpur


Related docs
Other docs by HC11112223113
CRE21
Views: 169  |  Downloads: 0
Supreme Court of the State of Washington
Views: 3  |  Downloads: 0
4 ?????????????
Views: 0  |  Downloads: 0
??????? ?? ????????? ? ...
Views: 0  |  Downloads: 0
Wrangler ProRodeo Tour Release
Views: 3  |  Downloads: 0
Assessment of Mental Capacity
Views: 5  |  Downloads: 0
UNIVERSIDAD NACIONAL DEL COMAHUE
Views: 12  |  Downloads: 0
REKENINGKUNDE
Views: 21  |  Downloads: 0
QUEUE-GENERATION INTERCONNECT
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!