Embed
Email

city-services

Document Sample

Shared by: changcheng2
Categories
Tags
Stats
views:
0
posted:
11/22/2011
language:
English
pages:
15
Reports Page 52 2 June 2009









MATTERS SUBMITTED BY THE DIRECTOR - CITY SERVICES



CIT.27 PEARL BEACH ROCK POOL CLIFF FACE STABILISATION (IR 4553172)

Directorate: City Services

Business Unit: Open Space and Leisure Services







BACKGROUND



This item was considered at the Strategy/Policy Workshop held on 18 March 2008 and the Council

Meeting of the 6 May 2008 (Attachment A) due to the risk considerations and funding required to

undertake the stabilisation of the cliff face.



On the 6 May 2008, Council resolved to;



A Option 2 for stabilisation works be adopted as the preferred option.



B Works commence immediately with the funding of $180,000 to be sourced through a

Council's budget review.



Since Council resolved the item above, concerns have been raised by the local residents (via Pearl

Beach Progress Association) and The National Trust of Australia (NSW) (the cliff face is registered

by the Trust as part of the tidal baths) in relation to the preferred treatment by Council. Based on

the letter from The National Trust dated 11 September 2008 (Attachment B) the Trust appears to

favour a mesh covered and reshaped rock face as per Option 3.



The report that follows outlines the preferred option for all parties concerned.









REPORT



The details of Option 3 (Combination of Mesh, shotcrete and rockbolts) are;



This method comprises a mixture of wire mesh, rock bolts, shotcrete and other works as

described below:



• Preparing the face of the cliff removing loose blocks, soil, trees and vegetation.

• Draping and pinning double dip galvanised 4mm mesh loosely to the rock face.

• Installing rock bolts to the rock face.

• 50m2 of shotcrete sprayed where appropriate to prevent further erosion or

detachment of blocks.



Estimated Cost: $140,000



It is important to note that although Option 3 is $40,000 cheaper than Option 2 to complete, there

will be an ongoing maintenance cost which will need to be covered by Council. This would be

funded by Open Space & Leisure Services as required.

Reports Page 53 2 June 2009







A revised design has been undertaken and reviewed by Council Officers. This design has

subsequently been forwarded to the Pearl Beach Progress Association and The National Trust of

Australia (NSW).



Letters have been received from both organisations confirming their support for the revised design.





Attachments: A SF.16 Pearl Beach Rock Pool - First Report (6 May 2008)

B Recommendations from The National Trust of Australia (NSW)

C Design for Pearl Beach Rock Pool cliff face stabilisation - Option 3



Tabled Items: Nil



FINANCIAL IMPACT STATEMENT



The estimated cost of the design option 3 is $140,000. This is a reduction of $40,000 from the

previous design and will be funded through the Budget Review Process as per previous Council

Resolution.



The necessity for ongoing maintenance will be funded through the recurrent budget of Open Space

& Leisure Services as required.







RECOMMENDATION



A Proceed with Option 3 as being the preferred plan by the local residents and The National

Trust of Australia (NSW) at an estimated cost of $140,000.



B As per resolution 6 May 2008 (IR 4553172) the works be funded through a budget review.

Reports Page 54 2 June 2009



ATTACHMENT A



TITLE COUNCIL REPORT PEARL BEACH ROCK POOL - CLIFF FACE

STABILISATION (IR 4553172)

Directorate: City Services

Business Unit: Open Space and Leisure Services





BACKGROUND



This item was considered at the Strategy/Policy Workshop held on 18 March 2008 due to the risk

considerations and funding required to undertake the stabilisation of the cliff face.



The Pearl Beach rock pool was constructed in 1929 by excavating the natural rock shelf located at

the southern end of the beach. The pool received an upgrade in the late 1950's, mid 1980's and

the latest inspection (2007) has deemed the pool in need of another substantial upgrade (at a cost

of $202,000).



The pool has high importance to the local community primarily used as a venue for recreational

swimming. The Umina Blue Swimmers Club has swum at the pool since 1969 with a current

membership of 50 swimmers. The pool has also been classified by the National Trust.



The cliff face located on the south-eastern side of the rock pool has suffered some substantial rock

fall in recent years. As a result of this, Council contracted an external risk management report from

Logov, Risk Management Services.



The report identified that the cliff face appeared unstable over a distance of approximately 50

metres and recommended a number of actions to be undertaken.



Logov recommended that Council undertake engineering investigations into the stability of the rock

face and rectification works necessary to make the area safe.





The following Councillors were present for this item:



Councillor Maher, Holstein, Scott, Macfadyen, Brooks, Hale, and Drake.







REPORT



Council Officers engaged engineers Pells, Sullivan, Meynink Engineering Consultants (PSM) to

investigate the rock face adjacent to Pearl Beach Pool.



The report deemed that rock falls of rocks of up to 1 metre in size is considered to be moderate to

high in risk, with the risk of falls of larger rock sizes to be low.



Options for Consideration



The Engineers report has recommended three appropriate engineering solutions to prevent further

rock fall.

Reports Page 55 2 June 2009







Option 1 Protective Wall

Construct a structural wall approximately 8 metres in height and 50 lineal metres in length at the

base of the cliff and backfilled with gravel. The wall geometry would be such to cover the entire

length of the pool and 10 meters each side.



Possible constructions types include,

• Reinforced concrete

• Steel columns with timber wall lagging

• Copper log wall



Estimated cost on Option 1 is $220,000 - $270,000.



Option 2 Shotcrete and Rock Bolts

Apply a shotcrete membrane over the entire rock slope.



A rock bolt reinforced concrete membrane would remove the risk of rock fall. This option may be

considered unsightly, however colouring the concrete may reduce this impact. Trees at the crest of

the cliff would have to be removed.



Estimated cost on Option 2 is $180,000 and will require minimal ongoing maintenance.





Option 3 Combination of Mesh, shotcrete and Rockbolts

This method comprises a mixture of wire mesh, rock bolts, shotcrete and other works as described

below;

• preparing the face of the cliff removing loose blocks, soil, trees and vegetation,

• draping and pinning double dip galvanised 4mm mesh loosely to the rock face,

• installing rock bolts to the rock face,

• 50m2 of shotcrete sprayed where appropriate to prevent further erosion or detachment of

blocks.



This method would capture any blocks of rock (up to 250mm) that may be detach from the rock

face, however blocks would have to be removed periodically from the base of the wall.



Estimated cost on Option 3 is $140,000 and will require ongoing maintenance.



In determining the best option for consideration, Option 2 was deemed suitable as;

• The pool has high aesthetic significance due to it sitting on a rock shelf at the base of a cliff.

• Reactive measures that catch falling rocks as identified in option 1 are typically hefty in

design and expense.

• Preventative measures to prevent rock fall as identified in options 2 & 3 are more practical.

• All options would require some form of ongoing maintenance while options 2 & 3 involving

regular inspections to be undertaken by an engineer.

• The galvanised mesh attached to the cliff face as identified on option 3 will corrode

within 10 - 30 years, and therefore would require considerable ongoing maintenance.

• Whilst Option 3 is the least expensive initial cost, the likelihood of further expense to Council

in the long term is higher through ongoing maintenance. As the galvanised mesh is

exposed, it is more susceptible to the elements, and may require repairs and replacement.



It is recommended that Option 2 be pursued as the preferred works. Once Council has approved

the preferred option, PSM can provide technical drawings and specifications required for the next

phase of the project.

Reports Page 56 2 June 2009







Option 2 Cost Estimate

Shotcrete and rock bolts



ITEM QUANTITY COST ESTIMATE

Prepare face (remove loose 50 lm (about 500m2 ) $35,000

blocks, soil, trees and

vegetation).

Install rockbolts over 50 lm of Nominally 100 x 2.1m rock $75,000

rock face. bolts

Spray shotcrete Nominally 500m2 $60,000

Detailed design & Allow $10,000

documentation

TOTAL ESTIMATE $180,000





Attachments: NIL.



Tabled Items: NIL



FINANCIAL IMPACT STATEMENT



The cost of the preferred option is an estimated $180,000 to shotcrete and rockbolt the cliff face.



No funding is currently available through the current Capital Works budget for these works. Based

on the urgency of the works, consideration should be given to obtaining funding through the budget

review process.



Should the project be unsuccessful in the budget review process, the project should be given

further consideration through a future Capital Works budget.





RECOMMENDATION



A Option 2 for stabilisation works be adopted as the preferred option.



B Works commence immediately with the funding of $180,000 to be sourced through a

Council's budget review.

Reports Page 57 2 June 2009







ATTACHMENT B

Reports Page 58 2 June 2009

Reports Page 59 2 June 2009



ATTACHMENT C

Reports Page 60 2 June 2009

Reports Page 61 2 June 2009

Reports Page 62 2 June 2009

Reports Page 63 2 June 2009

Reports Page 64 2 June 2009

Reports Page 65 2 June 2009

Reports Page 66 2 June 2009



Related docs
Other docs by changcheng2
preview-islamic_jurisprudence
Views: 0  |  Downloads: 0
Registration Form
Views: 0  |  Downloads: 0
9495_21rpt
Views: 0  |  Downloads: 0
AgNews-Willard.docx
Views: 2  |  Downloads: 0
Screening RIA
Views: 0  |  Downloads: 0
AcuteRespiraroryIllness
Views: 0  |  Downloads: 0
actoctober11enrolmentform
Views: 0  |  Downloads: 0
Colon Cleansing Diet Before Colonoscopy
Views: 0  |  Downloads: 0
BC_Gold_Division
Views: 0  |  Downloads: 0
Tavola 7 - Unioncamere Lombardia
Views: 1  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!