Embed
Email

to Download

Document Sample

Shared by: huanglianjiang1
Categories
Tags
Stats
views:
11
posted:
11/22/2011
language:
English
pages:
12
EXECUTIVE SUMMARY



1.0 BACKGROUND



As a part of the National Gas Grid, GAIL had got the Detail Feasibility Report (DFR) prepared for

Kochi-Kanjirkkod-Bangalore-Mangalore pipelines. The DFR These report was prepared during

2002 and were covering only the main trunk lines, based on the demand-supply situation at that

time. Now GAIL had received the Authorization from MoP&NG in July 2007 to lay Kochi-

Kanjirkkod-Bangalore-Mangalore Pipeline (KKBMPL) for a capacity of 16 MMSCMD (12.0

MMSCMD for GAIL and its Associates and 4.0 MMSCMD for common carrier) on common carrier

basis. DFR was prepared long back and since then market dynamics has considerably changed

thereby GAIL has decided to update DFR in house in line with the authorization received in 2007.



M/s Petronet LNG Limited (PLL) is constructing the LNG regasification terminal at Vyapeen,

Kochi for 2.5MMTPA capacity and as per the information received from PLL it is expected to be

completed by 2011-12. Regasified LNG (R-LNG) from M/s PLL at Vyapeen has been considered

as source for KKBMPL. Pipeline network considered for DFR preparation is shown in Sketch -

1.0.



Kochi → Alwaye → Kanjirkkod → Palghat/Pallakad → Coimbatore → Trippur → Bangalore →

Kanjirkod → Kasargod → Mangalore



PLL is constructing the regasification facility for 2.5 MMTPA (9.0 MMSCMD) and in near future it

will be upgraded to 5.0 MMTPA, therefore it is proposed that pipeline should also be executed in

phases. Synchronizing with the commissioning/Availability of R-LNG from PLL terminal.



Demand: Phase wise Demand of KKBMPL is given below:



(As provided by Mktg. Group)



Phase-I (2010-11)



Sr. Consumer Location Volume

No. (MMSCMD)

1 NEST, SEZ Kochi. 300 MW plant Vyapin Kochi 1.2

2 GTN Textiles. Alwaye, Ernakulam. Always 0.048

3 Premier Tyres Limited:Kalamassery,Kochi. Kalamassery 0.014



4 REL, Udyogruandal Kochi. Udyogmandal 0.9

5 FACT Udyogmandal (FACT-I) Udyogmandal 1

6 Sudchemie, Udyogmandal Udyogmandal 0.006

7 Travancore Cochin Chemicals, Udyogmandal 0.012

Udyogmandal

8 Cochin Minerals & Rutiles, Binanipuram Binaniparam 0.012

9 Binani Zinc Limited: Binanipuram, Kochi Binanipuram 0.1

10 Kerala Chemicals & Proteins Ltd: Kakkanad 0.022

Kakkanad, Kochi.

11 FACT Ambalamedu(FACT-II) Ambalamedu 1.21

12 BPCL, Refinery, Ambalamedu, Kochi Ambalamedu 1.6

13 Hindustan Organics Limited, Ambalamedu 0.11

Ambalamedu

14 Philips Carbon, Ambalamedu Ambalamedu 0.026

15 MILMA Ernakulam Ambalamedu 0.0096

Total 6.2696



Phase-II (2011-12)



No. Consumer Location Volume

(MMSCMD)

1. Apollo Tyres Limited: Perambra, Thrissur. Thrissur 0.042



2. Arya Vaidya Sala, Kottakal. Kottakal 0.014

3. KSEB Diesel Plant, Nallalam, Kozhikode Kozhikode 0.78

4. Western India Plywoods, Kannur Kannur 0.04

5. Kannur Power Projects Limited Kannur 2.25

6. Kasargod Power Corporation: Kasarpod Kasargod 0.5

7. MCF, Mangalore Mangalore 0.9

8. Indsil Electrosmelts limited:Pallakkad. Pallakkad 0.24

9. Precot Mills Limited: Walayar, Pallakkad Pallakkad 0.05

10. Steel Industries in Palakkad Pallakkad 0.02

Total 4.836



Phase-III (2012-13)



Sr. Consumer Location Volume

No. (MMSCMD)



1. Sri Kannapan Mills Ltd Coimbatore 0.0825

2 Flow Link Systems (P) Ltd Coimbatore 0.0275

3 CPC Pvt Ltd Coimbatore 0.0165

4 Kovai Auto Products Coimbatore 0.001

5 K.G.Denim Ltd Coimbatore 0385

6 Van Tex Ltd Coimbatore 0.0053

7. Texmo Precision Castings Coimbatore 0.005

8.

Texmo Industries(Pump Division) Coimbatore 0.02

9

Texmo Industries(Motor Division) Coimbatore 0.01

10

Super Spinning Mills Ltd Coimbatore 0.022

11.

Premier Mills P Ltd Coimbatore 0.1686

12 L.G Balakrishnan & Bros Ltd Coimbatore 0.0127

13. S A Textile Pvt Ltd Tirupur 0.0165

14. Gomuki Spinning Mills Pvt Ltd Tirupur 0.0165

15. Agni Steels Pvt Ltd Erode 0.01

16. Pavai Alloys and Steels Pvt Ltd Tiruchengode 0.075

17 Ran India Steels P Ltd Tiruchengode 0.01

18. Jansons Industries Ltd Tiruchengode 0.075

19. Micro-Tech CNG Pvt Ltd. Hosur 0.01

20. NGA Steels Pvt Ltd Salem 0.1

21. Sri Krishna Alloys Salem 0.015

Total 0.8731



Grand Total: 12 MMSCMD



Pipeline Design Throughput: 16 MMSCMD - (As per Authorization from MoP&NG)



Note: 12 MMSCMD for GAIL and its associates, 4.0 MMSCMD for common carrier as per

the authorization received from MoP& NG



1.1 PROJECT PROPOSAL



Based on the demand provided by the Marketing Department and authorization received from

MoP&NG, updation of the DFR has been carried in house by Project Development Pipeline (PD-

PL) group. Pipeline route as shown in sketch 1.0 is considered for updation of DFR.









The flow rate of re-gasified gas (R-LNG) considered is 16.0 MMSCMD starting from Kochi

Despatch Terminal. Distribution of gas in various segments of the pipeline network shall be as

follows:



Kochi - Alwaye - 16.0 MMSCMD

Alwaye FACT-1 / BSES/FACT-11 - 6.0 MMSCMD

Alwaye — Kanjirkkod - 10.0 MMSCMD

Kanjirkkod -- Mangalore - 6.0 MMSCMD

Kanjirkkod — Bangalore - 4.0 MMSCMD

Distribution of gas shall preferably be without the aid of compression facilities anywhere. Pipeline

segment shall be designed as per following design conditions:



Normal Inlet Pressure (i.e. custody transfer of regasified LNG : 87 kg/cm2g



By PLL to GAIL at Kochi Despatch Terminal)



Normal Inlet Temperature : 0O C



Pipeline Design Pressure : 92.0 kg/cm2g



Pipeline Design Temperature : -28oC to 65o C



Number of stream days / year : 365



Arrival Pressure at Receipt Terminals: Mangalore - 45 kg/cm2g, Banglore-45 kg/cm2 g



Pipeline length : As per Pipeline section details



Mainline and Spur line details are provided in the pipeline section details below:



Summary of Pipeline Length



Pipeline Size Length (Km)

24 862

12 38

8 214



Main Pipeline



Description: Kochi-Alwaye-Thrissur-Kanjirkkod-Palakkad-Bangalore Ch 0.0 Km at Kochi

Dispatch terminal near PLL



Pipeline Section Length (Km.) Pipe Size (Inch) Execution

Kochi Alwaye (TOP for FACT) 27 24 Phase-I

Alwaye Thrissur 18 Phase-II

Thrissur Kanjirkkod 62

Kanjirkkod Palghat/Pallakkad 50

Palghat/Pallakkad Coimbatore 53 Phase-III

Coimbatore Trippur 57

Trippur Erode/Trichengede 18

Erode/Trichengede Salem 77

Salem Bangalore 178



Mangalore Spurline



Description: Kanjirkkod-Mangalore Pipeline

Ch 0.0 Km at Ch 107 in Kanjirkkod- Palghat section of KKBMPL Mainline



Pipeline Section Length (Km.) Pipe Size (Inch) Execution

Kanjirkkod Kottakal 30 24 Phase-II

Kottakal Kozhikode 55 Phase-II

Kozhikode Kannur 100 Phase-II

Kannur Kasargod 27 24 Phase-II

Kasargod Mangalore 110 Phase-II

Total 322



FACT Spurline



Description Alwaye - FACT Pipeline



Ch 0.0 Km at Ch 27 in Kochi-Alwaye Section of KKBMPL Mainline



Pipeline Section Length (Km.) Pipe Size (Inch) Execution

Alwaye (FACT TOP) TOP of FACT-I 10 12 Phase-I

TOP of FACT-I FACT-II 18 12 Phase-I



Other Spur Pipeline and Consumer connections



Pipeline Section Length Pipe Execution

(Km.) Size

(Inch)

Kochi Teminal to NEST SEZ 5 8 Phase-I

FACT-1 TOP to REL 4 8

REL to FACT-I 1 8

FACT- I TOP to GTN textile 3 8

Grid for Consumers in Udyogmandal, ,Binanipuram,Kakkanad, 20 8

Alwaye

FACT-II to BPCL refinery Ambalamedu 4 8

BPCL refinery Ambalamedu to HOL & other consumers 4 8

Appolo tyres Thrissur 14 8 Phase-II

Aryavaidsala , Kottakal 8

KSEB Power Plant, Kozhikode 7 8



Western plywood, Kannur 20 8

Kannur Power Projects Limited 4 8

Power plant, Kasargod 4 8

MCF, Mangalore 2 8 Phase-II

Indosil, Pallakkad 18 8

Precot and others ,Pallakkad 5 8

TOP to Coimbatore Despatch Terminal 10 12 Phase-III

Grid for Consumers in Coimbatore 40 8

Grid for Consumers in Trippur 10 8

TOP to Erode Despatch Terminal Agni Steel 2 8

Grid for Consumers in Trichengede 15 8

Grid for Consumers in Salem 30 8



Summary of Pipeline - Phase- I



Pipeline Size Length (Km)

24 27

12 28

8 41



Summary of Pipeline - Phase-II



Pipeline Length(Km)

Size

24 452

8 76



Summary of Pipeline- Phase-III



Pipeline Length(Km)

Size

24 383

12 10

8 97



1.2 Pipeline Route, Environment Impact Assessment and Risk Analysis Study Detailed

Route Survey, Soil Resistivity Survey, Soil Investigation Studies and topographical surveys of

proposed pipeline route and terminals were carried out in the past , now in view of the changes in

consumer bases, fresh survey will be carried out. This DFR therefore is based on desk top study

of available maps and reconnaissance survey of critical accessible locations along the proposed

pipeline route.



Similarly. Environment Impact Assessment and Risk Analysis Studies of the proposed pipeline

are yet to be established. Thus. environment management plan and disaster management plan

are yet to be finalized and established. However, design. construction and operation of the

proposed pipeline network is being conceived and planned in a manner that impact on base

values of air quality, water quality, noise quality, soil quality, laud use, ecology, Flora / Fauna and

Socio economic aspects is minimal and temporary in nature.



1.3 OPTIMISATION STUDY



Following three alternatives have been considered for determination of optimum pipeline size and

configuration.



Alternative - 1



Pipeline Size : Kochi to Kanjirkkod (Trichur) - 22" O.D. (107 km long)



Kanjirkkod to Mangalore - 22" O.D. (322 km long)



Kanjirkkod to Bangalore - 22" O.D. (440 km long)

Compression facilities: NIL



Alternative-2



Pipeline Size: Kochi to Kanjirkkod (Trichur) 24" O.D. (107 km long)



Kanjirkkod to Mangalore 24" O.D. (322 km long)



Kanjirkkod to Bangalore - 24" O.D. (440 km long)



Compression facilities: NIL



Alternative-3



Pipeline Size : Kochi to Kanjirkkod (Trichur) -- 26" O.D. (107 km long)



Kanjirkkod to Mangalore 26" O.D. (322 km long)



Kanjirkkod to Bangalore 26" O.D. (440 km long)



Compression facilities: NIL



Summary of results of the optimization study are tabulated below:



Alternative Pipe Size Pressure at Pressure at

(Inch) Manglore Manglore (Kg/cm2)

(Kg/cm2)

1 22 43 48

2 24 62 64

3 26 70 72



TABLE



ALTERNATIVE COST IN Rs. LAKHS

Direct Capital cost without

common facilities (Rs.

Lakhs)

2 170055

3 190611



**Minimum pressure requirement of 45 Kg/cm2 is not achieved by pipe size selected in

alternative-1; therefore Costing has been carried out for Alternative-2 &3 only.



NOTE: 1. Cost of the common facilities in the above three alternatives has been excluded.



2. Capital cost estimates mentioned above are not to be considered for investment purposes.



From above Table, it can be observed that Alternative - 2 has the least Capex.



Therefore Alternative -2 is selected for preparation of this DFR.

Total Project cost including all the facilities is Rs. 2817.40 Crores including a Foreign Exchange

(FE) component of Rs. 18.59 Crores.



1.4 PROJECT FACILITIES



Facilities proposed for the pipeline system at various terminals and along the cross country

portions of the pipelines are as follows:



1.4.1 Pipeline



Details. of pipeline. segments such as pipeline size, material, length and location etc. of the

pipeline configuration considered in the DFR is indicated in Annexure-III (Ch. Process Design

basis)



The proposed pipeline shall have following features:



 External surface of the Buried portion of the pipeline shall be coated with 3 layer PE ,

internal coating shall be done by Epoxy. Supplemented by Impressed current type

cathodic protection system.

 Only mainline(24") shall be internally coated

 Continuous concrete weight coating shall be provided for anti-buoyancy. wherever

required.

 For monitoring the health of the pipeline, the pipeline and its associated fittings including

scraper traps, shall be designed to allow passage of online inspection (OLI) tools like

intelligent pigs.



1.4.2 Pipeline Associated Facilities



Sectionalizing Valve Stations (SV), Intermediated Pigging Stations (IPS), Tap-off stations (TOP),

Consumer Receipt Terminals (CRT), Cathodic Protection Stations (CP) and repeater stations

(RS) provided along the pipeline route are as follows:



Pipeline TOTAL NUMBER

Segment SV IPS TOP CRT CP RS

Kochi -

16 3 7 32 19 19

Bangalore

Kanjirkkod

11 1 4 17 10 10

Mangalore



SV: Sectionalizing Valve



IPS: Intermediate Pigging Station



TOP: tap off point



CRT Consumer receipt terminal



CP Cathodic protection



RS Remote Station

NOTE: Stations at FACT -I/II, Kanjirkkod. Kasargod, Mangalore, Coimbatore, Trippur, and Salem

shall be manned and shall also serve as maintenance basis.



Quantities of SVs, IPS, TOP, CRT, CP, RS are tentative only, they have been considered on the

basis of desk top study. Actual quantity shall be worked out during detail engineering based on

the detail route survey.



1.4.3 Facilities envisaged at other terminals are as follows:



1 .4.3.1 Kochi Dispatch Terminal



 Gas chromatograph and Analyser for H2S, moisture content

 Gas Filters

 Scraper Launcher for 24" O.D. pipeline section from Kochi to Kanjirkkod

 Flow meters for Kochi-Kanjirkkod sections of the pipeline.

 Control room building cum administrative building

 All utilities like instrument air, plant air, nitrogen, service water and drinking water, Fire

water Network etc. shall be drawn from R-LNG plant of PLL.

 DG Set

 Pipeline of NEST SEZ from Kochi dispatch terminal is non piggable (Line length is 5 Km

only).



1.4.3.2 Kanjirkkod Dispatch Terminal



 Gas chromatograph and .Analyser for H2S, moisture content

 Scraper Launcher for 24" O.D. pipeline section from Kanjirkkod to Mangalore

 Scraper Launcher/Receiver for 24" O.D. pipeline section from Kanjirkkod to Bangalore.

Pipeline section has been considered bidirectional.

 Flow meters for Kanjirkkod - Bangalore sections of the pipeline.

 Flow meters for Kanjirkkod- Mangalore sections of the pipeline.

 Control room building cum administrative building

 DG Set.



1.4.3.3 Receipt Terminals



a) FACT-II



 Scraper Receiver for 12.75" O.D. pipeline section from Alwaye to FACT-II.

 Cartridge type gas filters

 Flow meters

 Control room-cum -office



b) MCF (Mangalore)



 Scraper receiver

 Cartridge type gas filters

 Flow meters

 Control room-cum-administrative building

 DG set



c) Bidadi (Bangalore)

 Scraper launcher/ receiver *

 Cartridge type gas filters

 Flow meters

 Control room-cum-administrative building

 DG set



* Assumed that in future GAIL may flow the gas from Bangalore to Kanjirkkod therefore

Kanjirkkod Bangalore section of the pipeline is considered Bidirectional)



c) Receipt terminal for consumer clusters in Palakkad, Coimbatore,Trippur, Erode, Salem -

Facilities as above



1.4.3.4 Intermediate Pigging Station-cum-tap off's and maintenance base



a) Kanjirkkod, Kasargod, Coimbatore and Salem etc.



 Scraper launcher and receiver

 Cartridge type gas filters

 Flow meters

 Control room-cum-office

 DG Set



1 .4.3.5 Intermediate Pigging Station



 Scraper launcher and receiver

 Cartridge type gas filters

 Flow meters

 Control room



1.4.3.6 Consumer Terminals:



 Cartridge type gas filters

 Flow Meters

 Letdown system (PRS) -if required

 Field mounted flow computers for Consumer upto 0.8 MMSCMD

 Metering Data for all the consumers 0.8 MMSCMD

 Data for consumers > = 0.8 MMSCMD shall be collected thru SCADA

 Power supply for metering will be fulfilled through solar system however for other

applications power shall be taken from consumer on chargeable basis.



1.4.4 POWER SUPPLY AT TERMINALS



1.4.4.1 Kochi Dispatch Terminal



415V, 3 Phase supply from R-LNG plant of Petronet Ltd is considered available. 1 No. DG set of

125 KVA capacity shall also be provided to cater to Auxiliary/Emergency load.



1.4.4.2 Receipt Terminals



1.4.4.2.1 Bangalore (Bidadi) and MCF (Mangalore)

Two feeders of 11 kv/415 V supply from KSEB grid is considered available to meet the power

demand of the terminal. In addition a DG set of 125 KVA capacity to cater to Auxiliary /

Emergency load of the terminal shall also be provided.



1.4.4.2.2 Intermediate Pigging Stations at Kanjirkkod, Kannur and Salem



11 kv / 415 V power supply from the grid of State Electricity Boards of the states in 'which these

stations are located is considered to be available. In additional a DG set of 30-45 KVA capacity

shall be provided to cater to Auxiliary / emergency load of the terminal.



1.4.4.3 Other Stations



At all other stations, electricity load demand shall be met by Grid with solar system/CCVT /TEG



1.4.5 SCADA & TELECOMMUNICATION SYSTEM



The complete system shall be monitored and controlled by Supervisory Control and Data

Acquisition (SCADA) system for which Master Control Stations (MCS) will be provided at Kochi

and Kanjirkkod (Trichur). The inter-master stations communication shall be through high speed

data channels provided by OFC based communication system. A satellite communication system

(SCPC) connecting Kochi, Kayamkulam, Bangalore, Mangalore, and GAIL Noida is proposed for

back up and connectivity for essential voice and data traffic. To facilitate the operations personnel

at the manned stations for being able to view the entire pipeline date, remote work stations shall

be extended from the SMCS's to all manned Stations.



APPS system for leak detection envisaged shall be provided with following modules:



a) Predicitive00.



Module



b) Inventory analysis



c) Survival time analysis



d) Pipeline Transportation Efficiency Scrapers tracking module



e) Contingency Analysis



f) Operator learning.



1.4.6 CAPITAL COSTS



The total capital cost for the project is estimated at Rs. 2817.40 Crores including a Foreign

Exchange (FE) component of Rs. 18.59 Crores. The cost estimates have been prepared based

on desk top study.



1.4.7 PROJECT SCHEDULE



The proposed project facilities up to mechanical completion (including pre-project activities) are

expected to be completed in 36 months from the zero date i.e. the date of go-ahead clearance by

GAIL. It is assumed that the detail route survey and environment clearance shall be made

available prior to award of work. Pipeline is proposed to be executed in three phases.



Phase I (2010-11) - Kochi to Alwaye and spurline to FACT-I/FACT-II and Other Consumers in

Alwaye



Phase II (2011-12) - Alwaye to Kanjirkkod- Pallakkad,



Kanjirkkod to Mangalore and



Spurlines to consumer in Kottakal, Kannur, Kozhikode, Kasargod and Mangalore



Phase III (2012-13) -Pallakkad to Bangalore and



Spurlines to Consumer in Trippur, Coimbatore, Erode and Salem



Related docs
Other docs by huanglianjiang...
Property Loss Damage Claim Form
Views: 0  |  Downloads: 0
Hurt Hawks
Views: 0  |  Downloads: 0
MEIJI UNIVERSITY_ TOKYO
Views: 4  |  Downloads: 0
Noam Gill GBAS System
Views: 0  |  Downloads: 0
GCD
Views: 0  |  Downloads: 0
FREE COMMUNITY SECTOR JOB ADVERTISING TRIAL
Views: 1  |  Downloads: 0
Constraints
Views: 0  |  Downloads: 0
Monroe Co Benton twp AR 2009
Views: 0  |  Downloads: 0
By registering with docstoc.com you agree to our
privacy policy

You are almost ready to download!

You are almost ready to download!